*UPDATE LAPORAN KONDISI UNIT*

*PLTU UP PAITON 2 x 400 MW*


Kamis, 30 Mei 2019, Pukul 06.00 WIB

*INFORMASI EP*:
*Batubara*
- Saldo Awal : *167.487,006* MT
- Penerimaan : *10.204,162* MT
- Pemakaian Unit #1 : *5.162* MT
- Pemakaian Unit #2 : *5.241* MT
- Saldo Akhir : *167.487,006* MT *(17.63 Hop)*

*HSD*
- Saldo Awal : *2.845.188* Liter
- Penerimaan HSD : *-* Liter
- Pemakaian Unit #1 : *-* Liter
- Pemakaian Unit #2 : *-* Liter
- Pemakaian Alat Berat 28 Mei 2019 : *2.662* Liter
- Saldo Akhir : *2.842.526* Liter

*BONGKAR* :
- *(138)* TB Bomas Makmur / BG Pulau Tiga 3457
Cargo : *10.203* MT
Shipper : KPC
_Proses Sandar_

*ANTRI* :
_kosong_

*TONGKANG OTW* :
- *(139)* TB Voyager 9 / BG Azamara 25
Cargo : *9.773* MT
Shipper : PLN BB
ETA 29.05.2019
- *(140)* TB Leopard 02 / BG Polaris 02
Cargo : ...
Shipper : OBP
ETA 31.05.2019
- *(141)* TB KSA 60 / BG RMN 3201
Cargo : *9.153* MT
Shipper : KPC
ETA 01.06.2019
- *(142)* TB Anna 1 / BG RMN 3301
Cargo : *9.993* MT
Shipper : KPC
ETA 03.06.2019
- *(143)* TB Bomas Karya / BG Pulau Tiga 330-23
Cargo : *10.065* MT
Shipper : KPC
ETA 06.06.2019
- *(144)* TB Bomas Explorer / BG Pulau Tiga 338
Cargo : *9.608* MT
Shipper : KPC
ETA 06.06.2019

*TIM BAHAN BAKAR UP PAITON*