LEBAR
V = P x L ………………….. ( m2 )
Ukuran
LOKAS Lebar VOLUME
NO Lebar Panjang
( STA ) Rata-rata
(m¹) (m¹) (m¹) (m²)
1 2 2 3 4 5
1 0 + 000 6.00
7.00 50.00 350.00
2 0 + 050 8.00
8.00 50.00 400.00
3 0 + 100 8.00
8.00 50.00 400.00
4 0 + 150 8.00
7.50 34.70 260.25
5 0 + 184.7 7.00
5.22 1.80 0
6 0 + 186.5 3.43
5.72 13.50 77.15
7 0 + 200 8.00
6.70 3.00 0
8 0 + 203 5.39
6.40 47.00 300.57
9 0 + 250 7.40
7.70 50.00 385.00
10 0 + 300 8.00
7.35 50.00 367.50
11 0 + 350 6.70
6.75 50.00 337.50
12 0 + 400 6.80
6.80 50.00 340.00
13 0 + 450 6.80
6.80 50.00 340.00
14 0 + 500 6.80
6.40 50.00 320.00
15 0 + 550 6.00
6.50 50.00 325.00
16 0 + 600 7.00
7.00 50.00 350.00
17 0 + 650 7.00
7.25 50.00 362.50
18 0 + 700 7.50
7.75 50.00 387.50
19 0 + 750 8.00
7.75 50.00 387.50
20 0 + 800 7.50
7.75 50.00 387.50
21 0 + 850 8.00
8.00 50.00 400.00
22 0 + 900 8.00
7.25 50.00 362.50
23 0 + 950 6.50
6.35 50.00 317.50
24 1 + 000 6.20
7.10 50.00 355.00
25 1 + 050 8.00
8.00 50.00 400.00
26 1 + 100 8.00
7.00 50.00 350.00
27 1 + 150 6.00
6.75 50.00 337.50
28 1 + 200 7.50
7.00 50.00 350.00
29 1 + 250 6.50
6.75 50.00 337.50
30 1 + 300 7.00
7.00 4.00 28.00
31 1 + 304 7.00
JUMLAH PADA LEMBARAN INI 1304.00 9,316
IDARUDIN CH
....................... TAKDIR MANSYAH, ST DIREKTU
NIP. .................................... DIREKTUR
DATA KUANTITAS TERLAKSANA
SI 3. PEKERJAAN TANAH
Rumus Perhitungan
V = P x L ………………….. ( m2 )
KETERANGAN
DUIKER
DUIKER
Di buat Oleh :
Kontraktor Pelaksana
CV. DUTA KONSTRUKSI
IDARUDIN CHANDRA
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
DIVISI 2. DRAINASE DAN SALURAN AIR
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEMBANGUNAN JALAN PENGHUBUNG SKPA MALIGANO – SKPB BATUKARA KAWASAN
PEKERJAAN : MUTIARA KEC. MALIGANO
LOKASI : KABUPATEN MUNA
KONTRAKTOR PELAKSANA : CV. DUTA KONSTRUKSI
SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
TAHUN ANGGARAN : 2019
ITEM PEMBAYARAN : 2.1.(1) Galian untuk Saluran Air
SATUAN : M³
Gambar Sketsa Dan Perhitungan
B1 V= P x L ……………………………………………
Dimana :
V= Volume Galian ……………………………
P= Panjang Galian …………………………
H
DIMENSI LUAS
LOKASI POSISI PANJANG
NO ( STA )
B1 B2 H Segmen Rata-rata
(L/R) (m¹) (m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 5 6 7 8 9
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
10
G
a
8.38 l
i
8.20 a
13.25 n
23.45 Duiker Sta 0+186,5 S
18.47 Duiker Sta 0+203
a
l
13.01 u
1.50 r
a
- n
6.36 G
aS
8.25 li
9.67 is
ai
9.75 nK
9.60 i
Sr
12.50 ai
15.50 l
u
21.38 r
8.25 a
n
-
S
n
- S
i
- s
- i
K
- i
G
15.60 ar
33.13 li
i
40.88 a
40.31 n
11.49 S
5.88 a
l
17.08 u
9.40 r
a
- n
-
- S
- i
s
361.26 i
438.47 K
799.73 i
r
i
Di buat Oleh :
Kontraktor Pelaksana
CV. DUTA KONSTRUKSI
IDARUDIN CHANDRA
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
DIVISI 2. DRAINASE DAN SALURAN AIR
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEMBANGUNAN JALAN PENGHUBUNG SKPA MALIGANO – SKPB BATUKARA KAWASAN
PEKERJAAN : MUTIARA KEC. MALIGANO
LOKASI : KABUPATEN MUNA
KONTRAKTOR PELAKSANA : CV. DUTA KONSTRUKSI
SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
TAHUN ANGGARAN : 2019
ITEM PEMBAYARAN : 2.1.(1) Galian untuk Saluran Air
SATUAN : M³
Gambar Sketsa Dan Perhitungan
B1 V= P x L ……………………………………………
Dimana :
V= Volume Galian ……………………………
P= Panjang Galian …………………………
H
DIMENSI LUAS
LOKASI POSISI PANJANG
NO ( STA )
B1 B2 H Segmen Rata-rata
(L/R) (m¹) (m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 5 6 7 8 9
1 0 + 000 L - - - -
- -
2 0 + 050 L - - - -
- -
3 0 + 100 L - - - -
- -
4 0 + 150 L - - - -
- -
5 0 + 200 L - - - -
- -
6 0 + 203 L 1.06 0.57 0.40 0.33
0.30 47.00
7 0 + 250 L 1.00 0.60 0.35 0.28
0.23 50.00
8 0 + 300 L 0.62 0.55 0.30 0.18
0.19 50.00
9 0 + 350 L 0.80 0.60 0.30 0.21
0.22 50.00
10 0 + 400 L 0.84 0.53 0.35 0.24
0.22 50.00
11 0 + 450 L 0.76 0.53 0.30 0.19
0.20 50.00
12 0 + 500 L 0.80 0.60 0.30 0.21
0.28 50.00
13 0 + 550 L 1.20 0.80 0.35 0.35
0.54 50.00
14 0 + 600 L 2.00 1.20 0.45 0.72
0.62 50.00
15 0 + 650 L 1.50 1.10 0.40 0.52
0.70 50.00
16 0 + 700 L 2.20 1.30 0.50 0.88
0.72 50.00
17 0 + 750 L 1.70 1.10 0.40 0.56
0.59 20.00
18 0 + 770 L 1.90 1.20 0.40 0.62
0.61 30.00
19 0 + 800 L 1.80 1.20 0.40 0.60
0.55 50.00
20 0 + 850 L 1.70 1.20 0.35 0.51
0.37 50.00
21 0 + 900 L 1.20 1.10 0.20 0.23
- -
22 0 + 915 L - - - -
- -
23 0 + 929 L 1.50 0.80 0.30 0.35
0.45 21.00
24 0 + 950 L 1.60 1.20 0.40 0.56
0.43 50.00
25 1 + 000 L 1.00 1.00 0.30 0.30
- -
26 1 + 050 L - - - -
- -
27 1 + 080 L 1.40 1.20 0.3 0.39
0.56 20.00
28 1 + 100 L 1.70 1.20 0.50 0.73
0.61 22.00
29 1 + 122 L 1.60 0.90 0.40 0.50
- -
30 1 + 150 L 1.2 0.7 0.2 0.19
0.65 50.00
31 1 + 200 L 2.30 1.40 0.60 1.11
0.82 50.00
32 1 + 250 L 1.40 1.20 0.40 0.52
0.44 50.00
33 1 + 300 L 1.40 1.00 0.30 0.36
0.36 4.00
34 1 + 304 L 1.40 1.00 0.30 0.36
JUMLAH PADA LEMBARAN INI 964
TOTAL S/D LEMBARAN INI 964
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
10
-
-
-
- Duiker Sta 0+186,5
- Duiker Sta 0+203
14.24
11.39
9.64 G
11.24 a
l
10.83 i
10.09 a
n
14.00
26.75 S
a
31.00 l
34.88 u
r
35.88 a
11.80 n
18.30 S
S
27.69 i
s
18.44 i
- K
a
- n
9.50 a
G
n
21.50 a
- l
i
- a
11.15 n
13.48 S
- a
l
32.50 u
40.75 r
a
22.00 n
1.44
S
438.47 i
s
438.47 i
K
a Di buat Oleh :
n
Kontraktor Pelaksana
CV.a DUTA KONSTRUKSI
n
IDARUDIN CHANDRA
DIREKTUR
BACK UP DATA QUANTITY
DIVISI 1. UMUM
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEMBANGUNAN JALAN PENGHUBUNG SKPA MALIGANO – SKPB BATUKARA KAWASA
:
PEKERJAAN KEC. MALIGANO
LOKASI : KABUPATEN MUNA
Di buat Oleh :
Kontraktor Pelaksana
CV. DUTA KONSTRUKSI
IDARUDIN CHANDRA
DIREKTUR
IDARUDIN CHANDRA
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
DIVISI 3. PEKERJAAN TANAH
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEMBANGUNAN JALAN PENGHUBUNG SKPA MALIGANO – SKPB BATUKARA KAWASAN
PEKERJAAN : MUTIARA KEC. MALIGANO
LOKASI : KABUPATEN MUNA
KONTRAKTOR PELAKSANA : CV. DUTA KONSTRUKSI
SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
TAHUN ANGGARAN : 2019
ITEM PEMBAYARAN : 3.1.(1a) Galian Biasa (Cuttingan)
SATUAN : M³
Gambar Sketsa Dan Perhitungan
B
CUTTINGAN 1
H
V = P x L ……………………………………………
Dimana :
B1
B V = Volume Galian ……………………………
P = Panjang Galian …………………………
CUTTINGAN 2 Luas Rata-rata Galian …………………
H
Luas = ( B1 + B2 ) /2* H …………………………
B1
DIMENSI LUAS
LOKASI POSISI PANJANG
NO ( STA )
B B1 H Segmen Rata-rata
(L/R) (m¹) (m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 5 6 7 8 9
1 0 + 000 L/R - - - -
- -
2 0 + 013 L/R 7.80 8.00 0.50 3.95
7.21 17.00
3 0 + 030 L/R 8.50 8.95 1.20 10.47
9.95 20.00
4 0 + 050 L/R 7.60 8.10 1.20 9.42
5.88 22.00
5 0 + 072 L/R 7.77 7.77 0.30 2.33
- -
6 0 + 100 L/R - - - -
- -
7 0 + 150 L/R - - - -
- -
8 0 + 200 L/R - - - -
- -
9 0 + 250 L/R - - - -
- -
10 0 + 300 L/R - - - -
- -
11 0 + 350 L/R - - - -
- -
12 0 + 400 L/R - - - -
- -
13 0 + 450 L/R - - - -
- -
14 0 + 500 L/R - - - -
- -
15 0 + 550 L/R - - - -
- -
16 0 + 600 L/R - - - -
- -
17 0 + 650 L/R - - - -
- -
18 0 + 700 L/R - - - -
- -
- -
19 0 + 750 L/R - - - -
- -
20 0 + 800 L/R - - - -
- -
21 0 + 850 L/R - - - -
- -
22 0 + 900 L/R - - - -
- -
23 0 + 950 L/R - - - -
- -
24 0 + 965 L/R 10.50 10.00 0.65 6.66
6.13 26.00
25 0 + 991 L/R 8.70 8.50 0.65 5.59
- -
26 1 + 000 L/R - - - -
- -
27 1 + 050 L/R - - - -
- -
28 1 + 080 L/R 11.50 11.00 0.30 3.38
13.63 20.00
29 1 + 100 L/R 13.00 11.50 1.95 23.89
26.03 15.00
30 1 + 115 L/R 13.00 11.50 2.30 28.18
19.49 7.00
31 1 + 122 L/R 11.20 10.40 1.00 10.80
- -
32 1 + 150 L/R - - - -
- -
33 1 + 200 L/R - - - -
- -
34 1 + 304 L/R - - - -
JUMLAH PADA LEMBARAN INI 127
TOTAL S/D LEMBARAN INI 127
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
10
-
122.57
198.90 Cuttingan
129.26
-
- Duiker Sta 0+186,5
- Duiker Sta 0+203
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Cuttingan
159.28
-
-
-
272.63
390.47 Cuttingan
136.41
-
-
-
1,409.52
1,409.52
Di buat Oleh :
Kontraktor Pelaksana
CV. DUTA KONSTRUKSI
IDARUDIN CHANDRA
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
DIVISI 3. PEKERJAAN TANAH
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEMBANGUNAN JALAN PENGHUBUNG SKPA MALIGANO – SKPB BATUKARA KAWASAN
PEKERJAAN : MUTIARA KEC. MALIGANO
LOKASI : KABUPATEN MUNA
KONTRAKTOR PELAKSANA : CV. DUTA KONSTRUKSI
SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
TAHUN ANGGARAN : 2019
ITEM PEMBAYARAN : 3.1.(1a) Galian Biasa (Cuttingan)
SATUAN : M³
Gambar Sketsa Dan Perhitungan
CUTTIGAN
KANAN
T
V = P x L ……………………………………………
Dimana :
V = Volume Galian ……………………………
A
T
Luas = (1/2 x a x t) …………………………….
A A
DIMENSI LUAS
LOKASI POSISI PANJANG
NO ( STA )
1/2 a t Segmen Rata-rata
(L/R) (m¹) (m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 5 6 7 8 9
1 0 + 000 L - - - -
- -
2 0 + 050 L - - - -
- -
3 0 + 100 L - - - -
- -
4 0 + 150 L - - - -
- -
5 0 + 200 L - - - -
- -
6 0 + 250 L - - - -
- -
7 0 + 300 L - - - -
- -
8 0 + 350 L - - - -
- -
9 0 + 400 L - - - -
- -
10 0 + 450 L - - - -
- -
11 0 + 500 L - - - -
- -
15 0 + 550 L 1/2 2.50 0.39 0.49
0.49 50.00
16 0 + 600 L 1/2 2.50 0.40 0.50
0.50 64.00
17 0 + 664 L 1/2 2.50 0.40 0.50
- -
18 0 + 675 L - - - -
- -
19 0 + 688 L 1/2 2.50 0.80 1.00
1.33 12.00
20 0 + 700 L 1/2 3.00 1.10 1.65
1.35 20.00
21 0 + 720 L 1/2 3.00 0.70 1.05
2.45 30.00
2.45 30.00
22 0 + 750 L 1/2 3.20 2.40 3.84
2.09 6.00
23 0 + 756 L 1/2 2.00 0.33 0.33
1.29 14.00
24 0 + 770 L 1/2 3.00 1.50 2.25
2.63 30.00
25 0 + 800 L 1/2 3.00 2.00 3.00
5.50 20.00
26 0 + 820 L 1/2 4.00 4.00 8.00
7.50 30.00
27 0 + 850 L 1/2 4.00 3.50 7.00
5.38 50.00
28 0 + 900 L 1/2 3.00 2.50 3.75
- -
29 0 + 950 L - - - -
- -
30 1 + 000 L - - - -
- -
31 1 + 050 L - - - -
- -
32 1 + 100 L
- -
32 1 + 150 L
- -
32 1 + 200 L 1/2 2.50 1.00 1.25
0.81 11.50
32 1 + 211.5 L 1/2 2.50 0.30 0.38
- -
32 1 + 220 L
- -
32 1 + 233 L 1/2 1.00 0.30 0.15
1.04 17.00
32 1 + 250 L 1/2 3.50 1.10 1.93
5.13 50.00
32 1 + 300 L 1/2 4.50 3.70 8.33
8.33 4.00
32 1 + 304 L 1/2 4.50 3.70 8.33
JUMLAH PADA LEMBARAN INI 409
LEMBARAN LALU 127
TOTAL S/D LEMBARAN INI 535.50
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
10
-
-
-
- Duiker Sta 0+186,5
- Duiker Sta 0+203
-
-
-
-
- C
- u
t
24.69 t
i
32.00 n
g
- a
n
-
15.90
27.00
73.35
73.35
12.51 Cu
18.06 tti
ng
78.75 an
110.00
225.00
268.75
-
-
-
-
C
- u
t
- t
9.34 i
n
- g
a
- n
17.64 Cu
256.25 ttin
gan
33.30
1,202.54
1,409.52
2,612.06
Di buat Oleh :
Kontraktor Pelaksana
CV. DUTA KONSTRUKSI
IDARUDIN CHANDRA
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
DIVISI 3. PEKERJAAN TANAH
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEMBANGUNAN JALAN PENGHUBUNG SKPA MALIGANO – SKPB BATUKARA KAWASAN
PEKERJAAN : MUTIARA KEC. MALIGANO
LOKASI : KABUPATEN MUNA
KONTRAKTOR PELAKSANA : CV. DUTA KONSTRUKSI
SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
TAHUN ANGGARAN : 2019
ITEM PEMBAYARAN : 3.1.(1a) Galian Biasa (Cuttingan)
SATUAN : M³
Gambar Sketsa Dan Perhitungan
CUTTIGAN KIRI
T
V = P x L ……………………………………………
Dimana :
A
V = Volume Galian ……………………………
CUTTIGAN KIRI P = Panjang Galian …………………………
Luas Rata-rata Galian …………………
T
T
Luas = (1/2 x a x t) …………………………….
A A
DIMENSI LUAS
LOKASI POSISI PANJANG
NO ( STA )
1/2 a t Segmen Rata-rata
(L/R) (m¹) (m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 5 6 7 8 9
1 0 + 000 R - - - -
- -
2 0 + 050 R - - - -
- -
3 0 + 100 R - - - -
- -
4 0 + 150 R - - - -
- -
5 0 + 200 R - - - -
- -
6 0 + 250 R - - - -
- -
7 0 + 300 R - - - -
- -
8 0 + 350 R - - - -
- -
9 0 + 400 R - - - -
- -
10 0 + 450 R - - - -
- -
11 0 + 500 R - - - -
- -
12 0 + 550 R - - - -
- -
15 0 + 550 R - - - -
- -
16 0 + 600 R - - - -
- -
17 0 + 664 R 1/2 2.50 0.95 1.19
1.75 16.00
18 0 + 680 R 1/2 2.50 1.85 2.31
1.84 20.00
19 0 + 700 R 1/2 2.50 1.10 1.38
0.84 20.00
20 0 + 720 R 1/2 1.00 0.60 0.30
- -
- -
21 0 + 720 R - - - -
- -
22 0 + 750 R - - - -
-
23 0 + 756 R - - - -
- -
24 0 + 770 R - - - -
- -
25 0 + 800 R - - - -
- -
26 0 + 820 R - - - -
- -
27 0 + 850 R - - - -
- -
28 0 + 900 R - - - -
- -
29 0 + 915 R 1/2 1.50 0.85 0.64
3.82 14.00
30 0 + 929 R 1/2 3.50 4.00 7.00
4.18 11.00
31 0 + 940 R 1/2 2.00 1.35 1.35
- -
32 1 + 000 R
- -
32 1 + 010 R 1/2 1.00 0.30 0.15
1.76 13.00
32 1 + 023 R 1/2 2.50 2.70 3.38
1.99 27.00
32 1 + 050 R 1/2 1.50 0.80 0.60
3.00 11.00
32 1 + 061 R 1/2 3.00 3.60 5.40
4.08 9.00
32 1 + 070 R 1/2 2.50 2.20 2.75
- -
32 1 + 250 R - - - -
- -
32 1 + 300 R - - - -
- -
32 1 + 304 R - - - -
JUMLAH PADA LEMBARAN INI 141
LEMBARAN LALU 536
TOTAL S/D LEMBARAN INI 676.50
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
10
-
-
-
- Duiker Sta 0+186,5
- Duiker Sta 0+203
-
-
-
-
-
- C
- u
t
- t
i
- n
g
28.00 a
n
36.88
16.75
-
-
-
- Cu
- tti
ng
- an
-
-
-
-
53.46
45.93
-
C
- u
t
22.91 t
53.66 i
n
33.00 g
a
36.68 n
- Cu
- ttin
gan
-
327.26
2,612.06
2,939.32
Di buat Oleh :
Kontraktor Pelaksana
CV. DUTA KONSTRUKSI
IDARUDIN CHANDRA
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
DIVISI 3. PEKERJAAN TANAH
SATKER : TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PEMBANGUNAN JALAN PENGHUBUNG SKPA MALIGANO – SKPB BATUKARA KAWASAN TRANSMIGRAS
LOKASI : KABUPATEN MUNA
KONTRAKTOR PELAKSANA : CV. DUTA KONSTRUKSI
SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
TAHUN ANGGARAN : 2019
ITEM PEMBAYARAN : 3.4.(1) Pembersihan dan Pengupasan Lahan
SATUAN : M²
Gambar Sketsa Rumus Perhitungan
LEBAR
V = P x L ………………….. ( m2 )
Ukuran
LOKAS Lebar VOLUME
NO Lebar Panjang
( STA ) Rata-rata
(m¹) (m¹) (m¹) (m²)
1 2 2 3 4 5
1 0 + 000 -
- - -
2 0 + 050 -
- - -
3 0 + 100 -
- - -
4 0 + 150 -
- - -
5 0 + 184.7 -
- - -
6 0 + 186.5 -
- - -
7 0 + 200 -
- - -
8 0 + 203 -
- - -
9 0 + 250 -
- - -
10 0 + 300 -
- - -
11 0 + 350 -
- - -
12 0 + 400 -
- - -
13 0 + 450 -
- - -
14 0 + 500 3.50
3.50 50.00 175.00
15 0 + 550 3.50
3.50 50.00 175.00
16 0 + 600 3.50
3.50 50.00 175.00
17 0 + 650 3.50
3.50 50.00 175.00
18 0 + 700 3.50
3.50 50.00 175.00
19 0 + 750 3.50
3.50 50.00 175.00
20 0 + 800 3.50
3.50 50.00 175.00
21 0 + 850 3.50
3.50 50.00 175.00
22 0 + 900 3.50
3.50 50.00 175.00
23 0 + 950 3.50
3.50 50.00 175.00
24 1 + 000 3.50
3.50 50.00 175.00
25 1 + 050 3.50
3.50 50.00 175.00
26 1 + 100 3.50
- - -
27 1 + 150 -
- - -
28 1 + 200 -
- - -
29 1 + 250 -
- - -
30 1 + 300 -
- - -
31 1 + 304 -
JUMLAH PADA LEMBARAN INI 600.00 2,100
IDARUDIN CH
....................... TAKDIR MANSYAH, ST DIREKTU
NIP. .................................... DIREKTUR
DATA KUANTITAS TERLAKSANA
SI 3. PEKERJAAN TANAH
Rumus Perhitungan
V = P x L ………………….. ( m2 )
KETERANGAN
DUIKER
DUIKER
Di buat Oleh :
Kontraktor Pelaksana
CV. DUTA KONSTRUKSI
IDARUDIN CHANDRA
DIREKTUR
BACK UP DATA KUANTITAS
DIVISI 3. PEKERJAAN TANAH
SATKER : TRANSMIGRASI DAN TENAGA KERJA
PROGRAM : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PEMBANGUNAN JALAN PENGHUBUNG SKPA MALIGANO – SKPB BATUKARA KAWASAN TRANSMIG
KONTRAKTOR PELAKSANA : KABUPATEN MUNA
SUPERVISI : CV. DUTA KONSTRUKSI
TAHUN ANGGARAN : CV. BUILDING ENGGINEERING CONSULTANT
ITEM PEMBAYARAN : 2019
SATUAN : 3.2.(2) Sub Base dengan Material Tanah Pilihan
RUAS : M³
IDARUDIN CHA
....................... TAKDIR MANSYAH, ST DIREKTUR
NIP. .................................... DIREKTUR
ACK UP DATA KUANTITAS
VISI 3. PEKERJAAN TANAH
Rumus Perhitungan
KETERANGAN
DUIKER
DUIKER
Di buat Oleh :
Kontraktor Pelaksana
CV. DUTA KONSTRUKSI
Di buat Oleh :
Kontraktor Pelaksana
CV. DUTA KONSTRUKSI
IDARUDIN CHANDRA
DIREKTUR
REKAPITULASI BACK UP DATA
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PPEMBANGUNAN / PENINGKATAN JALAN NON STATUS
: PEMBANGUNAN JALAN PENGHUBUNG SKPA MALIGANO – SKPB BATUKARA KAWASAN
PEKERJAAN TRANSMIGRASI MUTIARA KEC. MALIGANO
LOKASI : KABUPATEN MUNA
KONTRAKTOR : CV. DUTA KONSTRUKSI
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
TAHUN ANGGARAN : 2019
1. DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 1.00
IDARUDIN CHAN
....................... TAKDIR MANSYAH, ST DIREKTUR
NIP. .................................... DIREKTUR
B BATUKARA KAWASAN
KET.
Tetap
+
+
+
Tetap
Di buat Oleh :
Kontraktor Pelaksana
CV. DUTA KONSTRUKSI
IDARUDIN CHANDRA
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
DIVISI 2. DRAINASE DAN SALURAN AIR
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSM
PEKERJAAN : WAKORUMBA SELATAN
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR PELAKSANA : CV. MONDOLALO
TAHUN ANGGARAN : 2019
ITEM PEMBAYARAN : 2.1.(1) Galian untuk Saluran Air
SATUAN : M³
Gambar Sketsa Dan Perhitungan
B1
V= P x L ……………………………………………
Dimana :
V= Volume Galian ……………………………
H
DIMENSI LUAS
LOKASI POSISI PANJANG
NO ( STA )
B1 B2 H Segmen Rata-rata
(L/R) (m¹) (m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 5 6 7 8 9
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
10
8.38
8.20
13.25
23.45 Duiker Sta 0+186,5
13.01
1.50
-
6.36
8.25
9.67
9.75
9.60
12.50
15.50
21.38
8.25
-
-
-
-
-
15.60
33.13
40.88
40.31
11.49
5.88
17.08
9.40
-
-
-
-
361.26
438.47
799.73
BACK UP DATA KUANTITAS TERLAKSANA
DIVISI 2. DRAINASE DAN SALURAN AIR
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSM
PEKERJAAN : WAKORUMBA SELATAN
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR PELAKSANA : CV. MONDOLALO
TAHUN ANGGARAN : 2019
ITEM PEMBAYARAN : 2.1.(1) Galian untuk Saluran Air
SATUAN : M³
Gambar Sketsa Dan Perhitungan
B1 V= P x L ……………………………………………
Dimana :
V= Volume Galian ……………………………
P= Panjang Galian …………………………
H
DIMENSI LUAS
LOKASI POSISI PANJANG
NO ( STA )
B1 B2 H Segmen Rata-rata
(L/R) (m¹) (m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 5 6 7 8 9
1 0 + 000 L - - - -
- -
2 0 + 050 L - - - -
- -
3 0 + 100 L - - - -
- -
4 0 + 150 L - - - -
- -
5 0 + 200 L - - - -
- -
6 0 + 203 L - - - -
0.00 47.00
7 0 + 250 L - - - -
0.00 50.00
8 0 + 300 L - - - -
0.00 50.00
9 0 + 350 L - - - -
0.00 50.00
10 0 + 400 L - - - -
0.00 50.00
11 0 + 450 L - - - -
0.00 50.00
12 0 + 500 L -
0.21 27.50
12 0 + 527.5 L 1.30 0.80 0.40 0.42
0.66 22.50
13 0 + 550 L 2.00 1.00 0.60 0.90
0.83 50.00
14 0 + 600 L 1.50 1.00 0.60 0.75
0.61 50.00
15 0 + 650 L 1.80 1.30 0.30 0.47
0.74 50.00
16 0 + 700 L 1.90 1.00 0.70 1.02
0.77 42.00
16 0 + 742 L 2.10 0.95 0.35 0.53
1.17 8.00
17 0 + 750 L 2.60 1.00 1.00 1.80
1.31 23.00
18 0 + 773 L 1.70 1.00 0.60 0.81
0.78 27.00
19 0 + 800 L 1.50 1.00 0.60 0.75
0.56 50.00
20 0 + 850 L 1.50 0.90 0.30 0.36
0.60 50.00
21 0 + 900 L 2.00 0.80 0.60 0.84
0.65 21.00
22 0 + 921 L 1.50 0.80 0.40 0.46
0.46 5.00
23 0 + 926 L 1.30 1.00 0.40 0.46
0.44 10.00
24 0 + 936 L 1.50 0.60 0.40 0.42
0.51 14.00
25 0 + 950 L 1.60 0.80 0.50 0.60
0.30 50.00
26 1 + 000 L 1.50 0.90 0.60 0.00
0.36 14.00
27 1 + 014 L 1.50 0.90 0.60 0.72
0.49 10.00
28 1 + 024 L 1.50 1.00 0.20 0.25
0.45 26.00
29 1 + 050 L 1.80 1.40 0.40 0.64
0.66 -880.00
30 0 + 170 L 1.60 1.10 0.50 0.68
0.52 20.00
31 0 + 190 L 1.00 0.80 0.40 0.36
0.32 910.00
32 1 + 100 L 1.30 0.60 0.30 0.29
0.46 25.00
33 1 + 125 L 1.50 1.00 0.50 0.63
0.44 7.00
34 1 + 132 L 1.60 1.00 0.20 0.26
0.34 18.00
35 1 + 150 L 1.60 1.20 0.30 0.42
0.38 26.00
36 1 + 176 L 1.30 0.90 0.30 0.33
0.33 24.00
37 1 + 200 L 1.30 0.90 0.30 0.33
0.25 9.00
38 1 + 209 L 0.90 0.80 0.20 0.17
0.18 18.00
39 1 + 227 L 1.10 0.80 0.20 0.19
0.31 23.00
40 1 + 250 L 1.20 0.90 0.40 0.42
0.21 -1250.00
41 L 0.00
0.00 0.00
42 L 0.00
0.00 0.00
43 L 0.00
0.00 0.00
44 L 0.00
0.00 0.00
45 L 0.00
0.00 0.00
46 L 0.00
0.00 0.00
47 L 0.00
0.00 0.00
48 L 0.00
0.00 0.00
49 L 0.00
0.00 0.00
50 L 0.00
0.00 0.00
51 L 0.00
0.00 0.00
52 L 0.00
0.00 0.00
53 L 0.00
0.00 0.00
54 L 0.00
0.00 0.00
55 L 0.00
0.00 0.00
56 L 0.00
0.00 0.00
57 L 0.00
0.00 0.00
58 L 0.00
0.00 0.00
59 L 0.00
0.00 0.00
60 L 0.00
0.00 0.00
61 L 0.00
0.00 0.00
62 L 0.00
0.00 0.00
63 L 0.00
0.00 0.00
64 L 0.00
0.00 0.00
65 L 0.00
0.00 0.00
66 L 0.00
0.00 0.00
67 L 0.00
0.00 0.00
68 L 0.00
0.00 0.00
69 L 0.00
0.00 0.00
70 L 0.00
0.00 0.00
71 L 0.00
0.00 0.00
72 L 0.00
0.00 0.00
73 L 0.00
0.00 0.00
74 L 0.00
0.00 0.00
75 L 0.00
0.00 0.00
76 L 0.00
0.00 0.00
77 L 0.00
0.00 0.00
78 L 0.00
0.00 0.00
79 L 0.00
0.00 0.00
80 L 0.00
0.00 0.00
33 L 0.00
0.00 0.00
34 L 0.00
JUMLAH PADA LEMBARAN INI (203)
TOTAL S/D LEMBARAN INI (203)
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
10
-
-
-
- Duiker Sta 0+186,5
- Duiker Sta 0+203
0.00
0.00
0.00 G
0.00 a
l
0.00 i
0.00 a
n
5.78
14.85 S
a
41.25 l
30.38 u
r
37.00 a
32.52 n
9.34 S
30.02 i
s
i
s
21.06 i
27.75 K
a
30.00 n
13.65 a
n
2.30
4.40
G
7.14 a
15.00 l
i
5.04 a
4.85 n
11.57 S
-578.60 a
l
10.35 u
293.48 r
a
11.38 n
3.10
S
6.12 i
9.75 s
i
7.92 K
2.25 a
n
3.24 a
7.02 n
-262.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(142.62)
(142.62)
Di buat Oleh :
Kontraktor Pelaksana
CV. DUTA KONSTRUKSI
IDARUDIN CHANDRA
DIREKTUR
PEMERINTAH KABUPATEN MUNA
DINAS TRANSMIGRASI DAN TENAGA KERJA
TAHUN ANGGARAN 2019
JL. Macan No. 48 Tlp. ( 0403 ) 21429 Kode Pos 93615
KEGIATAN :
PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN :
PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA
KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN
NOMOR KONTRAK :
06/KTRK/DTTK/VII/2019
NILAI KONTRAK :
Rp. 2.037.747.000,-
LOKASI :
KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONSULTAN SUPERVISI :
CV. BUILDING ENGGINEERING CONSULTANT
KONTRAKTOR PELAKSANA :
CV. MONDOLALO
TAHUN ANGGARAN 2019
PEMERINTAH KABUPATEN MUNA
DINAS TRANSMIGRASI DAN TENAGA KERJA
TAHUN ANGGARAN 2019
JL. Macan No. 48 Tlp. ( 0403 ) 21429 Kode Pos 93615
PEKERJAAN :
PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA
KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN
NOMOR KONTRAK :
06/KTRK/DTTK/VII/2019
NILAI KONTRAK :
Rp. 2.037.747.000,-
LOKASI :
KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONSULTAN SUPERVISI :
CV. BUILDING ENGGINEERING CONSULTANT
KONTRAKTOR PELAKSANA :
CV. MONDOLALO
TAHUN ANGGARAN 2019
PEMERINTAH KABUPATEN MUNA
DINAS TRANSMIGRASI DAN TENAGA KE
PEKERJAAN PEMBANGUNAN BRONJONG PENAHA
TAHUN ANGGARAN 2019
JL. Macan No. 48 Tlp. ( 0403 ) 21429 Kode Pos 93615 Raha
Pada hari ini Sabtu tanggal Dua Puluh Bulan April Tahun Dua Ribu Sembilan Belas kami ya
ASWIN, SP
1. Nama :
Jabatan :
Pejabat Pembuat Komitmen (PPK) Program PKP2T Dinas Transn
Alamat : Raha
Bahwa Kemajuan pekerjaan yang telah dilaksanakan oleh PIHAK KETIGA sampai den
Sebesar 51,66% (Lima Puluh Satu Koma Enam Puluh Enam Persen) dari volume kontrak.
lan April Tahun Dua Ribu Sembilan Belas kami yang bertanda tangan dibawah ini :
dilaksanakan oleh PIHAK KETIGA sampai dengan Tanggal 20 April 2019 adalah
Enam Puluh Enam Persen) dari volume kontrak.
KEGIATAN :
PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN :
PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA
KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN
NOMOR KONTRAK :
06/KTRK/DTTK/VII/2019
NILAI KONTRAK :
Rp. 2.037.747.000,-
LOKASI :
KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONSULTAN SUPERVISI :
CV. BUILDING ENGGINEERING CONSULTANT
KONTRAKTOR PELAKSANA :
CV. MONDOLALO
TAHUN ANGGARAN 2019
PEMERINTAH KABUPATEN MUNA
DINAS TRANSMIGRASI DAN TENAGA KERJA
TAHUN ANGGARAN 2019
JL. Macan No. 48 Tlp. ( 0403 ) 21429 Kode Pos 93615
KEGIATAN :
PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN :
PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA
KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN
NOMOR KONTRAK :
06/KTRK/DTTK/VII/2019
NILAI KONTRAK :
Rp. 2.037.747.000,-
LOKASI :
KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONSULTAN SUPERVISI :
CV. BUILDING ENGGINEERING CONSULTANT
KONTRAKTOR PELAKSANA :
CV. MONDOLALO
TAHUN ANGGARAN 2019
PEMERINTAH KABUPATEN MUNA
DINAS TRANSMIGRASI DAN TENAGA KERJA
TAHUN ANGGARAN 2019
JL. Macan No. 48 Tlp. ( 0403 ) 21429 Kode Pos 93615
KEGIATAN :
PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN :
PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA
KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN
NOMOR KONTRAK :
06/KTRK/DTTK/VII/2019
NILAI KONTRAK :
Rp. 2.037.747.000,-
LOKASI :
KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONSULTAN SUPERVISI :
CV. BUILDING ENGGINEERING CONSULTANT
KONTRAKTOR PELAKSANA :
CV. MONDOLALO
TAHUN ANGGARAN 2019
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
- -
BOBOT REALSASI 0 -
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIO
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
PERIODE MINGGU KE- I (18 JULI 2019 S/D 25 JULI 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
19)
- - - - - -
-
- - - - - -
-
- - - - - -
- - - - - -
- - - - - -
-
-
REKA
PERIO
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
PERIODE MINGGU KE- I (18 JULI 2019 S/D 25 JULI 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
19)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
PERIODE
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
PERIODE MINGGU KE- II (26 JULI 2019 S/D 02 AGUSTUS 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
2019)
- - - - - -
-
- - - - - -
-
- - - - - -
- - - - - -
- - - - - -
-
-
REKA
PERIODE
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
PERIODE MINGGU KE- II (26 JULI 2019 S/D 02 AGUSTUS 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
0.00
R 0.00
0.00
0.00
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
- -
BOBOT REALSASI 0 - -
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIODE M
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
ERIODE MINGGU KE- III (03 AGUSTUS 2019 S/D 10 AGUSTUS 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
US 2019)
- - - - - -
-
- - - - - -
-
- - - - - -
- - - - - -
- - - - - -
-
-
REKA
PERIODE M
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
ERIODE MINGGU KE- III (03 AGUSTUS 2019 S/D 10 AGUSTUS 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
0.00
R 0.00
0.00
0.00
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
US 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
- - - -
- - -
BOBOT REALSASI 0 - - -
PERIODE MINGGU KE- III (03 AGUSTUS 2019 S/D 10 AGUSTUS 2019)
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIODE M
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
ERIODE MINGGU KE- IV (11 AGUSTUS 2019 S/D 18 AGUSTUS 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
US 2019)
- - - - - -
-
- - - - - -
-
- - - - - -
- - - - - -
- - - - - -
-
-
REKA
PERIODE M
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
ERIODE MINGGU KE- IV (11 AGUSTUS 2019 S/D 18 AGUSTUS 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
0.00
R 0.00
0.00
0.00
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
US 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
- - - -
- - -
BOBOT REALSASI 0 - - -
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
-
-7.03
5
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIOD
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
PERIODE BULAN KE- I (18 JULI 2019 S/D 18 AGUSTUS 2019)
LAPORAN BULAN
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI BULAN LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
2019)
- - - - - -
-
- - - - - -
-
- - - - - -
- - - - - -
- - - - - -
-
-
REKA
PERIOD
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
PERIODE BULAN KE- I (18 JULI 2019 S/D 18 AGUSTUS 2019)
LAPORAN BULAN
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
0.00
R 0.00
0.00
0.00
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. BULAN INI
(%)
BULAN INI ( % )
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
RINCIAN SERTIFIKAT BULANAN
MUTUAL CHECK (MC-01)
PERIODE BULAN KE- I (12 SEPTEMBER 2018 S/D 09 OKTOBER 20
KONTRAK AWAL
NO URAIAN PEKERJAAN HARGA NILAI HARGA
SATUAN VOLUME
SATUAN (Rp)
I. UMUM
1 Sarana Prasarana dan Personil Ls 1.00 300,000.00 300,000.00
2 Administrasi Ls 1.00 2,100,000.00 2,100,000.00
3 Pengukuran (Uitzet/Steaking Out) Ls 1.00 1,200,000.00 1,200,000.00
4 Ass Buill Drawing Ls 1.00 2,000,000.00 2,000,000.00
JUMLAH HARGA I 5,600,000.00
II. PEKERJAAN DRAINASE
1 Pek. Galian Parit / Drainase M³ 59.62 81,075.00 4,833,950.94
2 Pek. Pasangan Batu Gunung 1 : 4 M³ 31.96 867,405.90 27,721,598.64
3 Pek. Pelesteran 1 : 3 M³ 163.07 74,659.27 12,174,836.04
4 Pek. Acian Semen Air M² 163.07 43,336.60 7,066,986.04
JUMLAH HARGA II 51,797,371.65
III. PEKERJAAN TALUD
1 Pek. Galian Talud M³ 7.07 81,075.00 573,038.10
2 Pek. Pasangan Batu Kosong M³ 2.48 407,210.40 1,009,881.79
3 Pek. Pasanagan Batu Gunung 1 : 5 M³ 8.46 867,405.90 7,338,253.91
4 Pek. Plesteran Siar Adukan 1 : 2 M² 22.00 69,955.28 1,539,016.20
JUMLAH HARGA III 10,460,190.01
REALISASI FISIK
A REAL COST 67,857,561.66
B PPN 10 % 6,785,756.17
C JUMLAH TOTAL 74,643,317.83
F PENGURANGAN
~ Sertifikat Sampai dengan Bulan Lalu
~ Retensi 5%
~ Pengembalian Uang Muka 20%
~ Lain-Lain
JUMLAH PENGURANGAN
G JUMLAH PEMBAYARAN SERTIFIKAT BULANAN (C-F)
TERBILANG :
TUJUH PULUH JUTA SEMBILAN RATUS DELAPAN RIBU RUPIAH
Menegetahui/Menyetujui
KPA/PPK
Dinas Pekerjaan Umum Dan Pentaan Ruang
Kab. Muna
MUSTAJAB, ST
NIP. 19740730 200901 1 004
AN
D 09 OKTOBER 2018)
N TANAH LONGSOR
67,857,561.66
100.00
6,785,756.17
74,643,317.83
74,640,000.00
-
3,732,000.00
14,928,663.57
-
18,660,663.57
55,979,336.43
DIBULATKAN 55,979,000.00
-
100.00
100.00
Dibuat Oleh :
i Kontraktor Pelaksana
SULTANT CV. DARMA ABADI
GAMSIR
DIREKTUR
ujui
ntaan Ruang
1 004
RINCIAN SERTIFIKAT BULANAN
MUTUAL CHECK (MC-01)
PERIODE BULAN KE- I (12 SEPTEMBER 2018 S/D 09 OKTOBER 201
VOLUME VOLUME
NO URAIAN PEKERJAAN SATUAN
KONTRAK REALISASI
I. UMUM
1 Sarana Prasarana dan Personil Ls 1.00 1.00
2 Administrasi Ls 1.00 1.00
3 Pengukuran (Uitzet/Steaking Out) Ls 1.00 1.00
4 Ass Buill Drawing Ls 1.00 1.00
JUMLAH HARGA I
II. PEKERJAAN DRAINASE
1 Pek. Galian Parit / Drainase M³ 59.62 59.62
2 Pek. Pasangan Batu Gunung 1 : 4 M³ 31.96 31.96
3 Pek. Pelesteran 1 : 3 M³ 163.07 163.07
4 Pek. Acian Semen Air M² 163.07 163.07
JUMLAH HARGA II
III. PEKERJAAN TALUD
1 Pek. Galian Talud M³ 7.07 7.07
2 Pek. Pasangan Batu Kosong M³ 2.48 2.48
3 Pek. Pasanagan Batu Gunung 1 : 5 M³ 8.46 8.46
4 Pek. Plesteran Siar Adukan 1 : 2 M² 22.00 22.00
JUMLAH HARGA III
TOTAL NILAI ITEM SAAT INI SEBELUM PPN
PPN 10%
TOTAL NILAI ITEM SETELAH PPN 10%
DIBULATKAN
PRESENTASE FISIK SAMPAI DENGAN SAAT INI
Menegetahui/Menyetujui
KPA/PPK
Dinas Pekerjaan Umum Dan Pentaan Ruang
Kab. Muna
MUSTAJAB, ST
NIP. 19740730 200901 1 004
RINCIAN SERTIFIKAT BULANAN
MUTUAL CHECK (MC-01)
E- I (12 SEPTEMBER 2018 S/D 09 OKTOBER 2018)
HARGA SATUAN
NILAI (Rp)
(Rp)
300,000.00 300,000.00
2,100,000.00 2,100,000.00
1,200,000.00 1,200,000.00
2,000,000.00 2,000,000.00
UMLAH HARGA I 5,600,000.00
81,075.00 4,833,950.94
867,405.90 27,721,598.64
74,659.27 12,174,836.04
43,336.60 7,066,986.04
UMLAH HARGA II 51,797,371.65
81,075.00 573,038.10
407,210.40 1,009,881.79
867,405.90 7,338,253.91
69,955.28 1,539,016.20
UMLAH HARGA III 10,460,190.01
TEM SAAT INI SEBELUM PPN 67,857,561.66
PPN 10% 6,785,756.17
AI ITEM SETELAH PPN 10% 74,643,317.83
DIBULATKAN 74,640,000.00
ISIK SAMPAI DENGAN SAAT INI 100.00
HARYADI, ST GAMSIR
Diperiksa Oleh : Dibuat Oleh :
Konsultan Supervisi Kontraktor Pelaksana
CV. MAESTRO STUDIOCONSULTANT CV. DARMA ABADI
HARYADI, ST GAMSIR
DIREKTUR DIREKTUR
Menegetahui/Menyetujui
KPA/PPK
Dinas Pekerjaan Umum Dan Pentaan Ruang
Kab. Muna
MUSTAJAB, ST
NIP. 19740730 200901 1 004
BACK UP DATA KUANTITAS TERLAKSANA
DIMENSI LUAS
LOKASI PANJANG VOLUME
NO B1 B2 H Segmen Rata-rata
( STA )
(m¹) (m¹) (m¹) (m²) (m²) (m¹) (m³)
1 2 3 4 5 6 7 8 9
A. LOKASI I
1 0 + 000 0.30 0.55 0.75 0.32
0.32 10.00 3.23
2 0 + 010 0.30 0.53 0.79 0.33
0.35 10.00 3.48
3 0 + 020 0.35 0.55 0.82 0.37
0.38 8.00 3.02
4 0 + 028 0.35 0.55 0.86 0.39
0.39 12.00 4.70
5 0 + 040 0.35 0.55 0.88 0.40
B. LOKASI II
1 0 + 000 0.35 0.35 0.75 0.26
0.29 10.00 2.94
2 0 + 010 0.35 0.4 0.87 0.33
0.32 10.00 3.21
3 0 + 020 0.35 0.4 0.84 0.32
0.31 10.00 3.08
4 0 + 030 0.35 0.35 0.86 0.30
0.30 10.00 3.05
DIMENSI LUAS
LOKASI PANJANG VOLUME
NO B1 B2 H Segmen Rata-rata
( STA )
(m¹) (m¹) (m¹) (m²) (m²) (m¹) (m³)
1 2 3 4 5 6 7 8 9
0.30 10.00 3.05
5 0 + 040 0.35 0.35 0.88 0.31
0.33 9.40 3.06
0 + 049.4 0.35 0.35 0.98 0.34
DIMENSI LUAS
LOKASI PANJANG VOLUME
NO B1 B2 H Segmen Rata-rata
( STA )
(m¹) (m¹) (m¹) (m²) (m²) (m¹) (m³)
1 2 3 4 5 6 7 8 9
C. TAMHAN PADA LOKASI I
1. 0 + 000 0.35 0.4 0.8 0.30
0.31 10.00 3.10
2 0 + 010 0.35 0.45 0.8 0.32
0.31 10.00 3.14
3 0 + 020 0.35 0.42 0.8 0.31
0.31 10.00 3.12
4 0 + 030 0.35 0.44 0.8 0.32
0.32 10.00 3.20
5 0 + 040 0.35 0.46 0.8 0.32
0.33 10.00 3.26
6 0 + 050 0.35 0.47 0.8 0.33
0.32 13.00 4.21
7 0 + 063 0.35 0.45 0.8 0.32
( m³ )
( m³ )
( m' )
( m² )
( m² )
KETERANGAN
KETERANGAN
KETERANGAN
Dibuat Oleh :
Kontraktor Pelaksana
CV. RAF SAN JAYA
HAMDI
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
DIMENSI LUAS
LOKASI PANJANG
NO B1 B2 H Segmen Rata-rata
( STA )
(m¹) (m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 5 6 7 8
A. LOKASI I
1 0 + 000 0.30 0.05 0.15 0.03
0.03 10.00
2 0 + 010 0.30 0.05 0.15 0.03
0.03 10.00
3 0 + 020 0.30 0.05 0.15 0.03
0.03 8.00
4 0 + 028 0.30 0.05 0.15 0.03
0.03 12.00
5 0 + 040 0.30 0.05 0.15 0.03
B. LOKASI II
1 0 + 000
0.00 10.00
2 0 + 010
0.00 10.00
3 0 + 020
0.00 10.00
4 0 + 030
0.00 10.00
5 0 + 040
0.00 9.40
6 0 + 049.4
TOTAL 175.42
TOTAL 175.42
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
9
0.26
0.26
0.21
0.32
0.14
0.00
0.00
0.24
0.39
0.17
0.26
0.26
0.26
0.26
0.22
0.00
0.00
0.00
0.00
0.00
3.26
3.26
Selisih
0.14
Dibuat Oleh :
Kontraktor Pelaksana
CV. RAF SAN JAYA
HAMDI
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
B2
L = Luas Rata-rata Galian …………………..
Luas = ( B1 + B2 ) /2* H …………………………….
DIMENSI LUAS
LOKASI PANJANG
NO B1 B2 H Segmen Rata-rata
( STA )
(m¹) (m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 5 6 7 8
A. LOKASI I
1 0 + 000 1.14 0.30 0.20 0.14
0.15 10.00
2 0 + 010 1.14 0.30 0.23 0.17
0.21 10.00
3 0 + 020 1.10 0.30 0.36 0.25
0.27 8.00
4 0 + 028 1.00 0.30 0.45 0.29
0.37 12.00
5 0 + 040 1.00 0.30 0.70 0.46
B. LOKASI II
1 0 + 000
0.00 10.00
2 0 + 010
0.00 10.00
3 0 + 020
0.00 10.00
4 0 + 030
0.00 10.00
DIMENSI LUAS
LOKASI PANJANG
NO B1 B2 H Segmen Rata-rata
( STA )
(m¹) (m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 5 6 7 8
0.00 10.00
5 0 + 040
0.00 9.40
6 0 + 049.4
DIMENSI LUAS
LOKASI PANJANG
NO B1 B2 H Segmen Rata-rata
( STA )
(m¹) (m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 5 6 7 8
C. TAMHAN PADA LOKASI I
1. 0 + 000 1 0.3 0.5 0.33
0.33 10.00
2 0 + 010 1 0.3 0.5 0.33
0.33 10.00
3 0 + 020 1 0.3 0.5 0.33
0.33 10.00
4 0 + 030 1 0.3 0.5 0.33
0.33 10.00
5 0 + 040 1 0.3 0.5 0.33
0.33 10.00
6 0 + 050 1 0.3 0.5 0.33
0.33 13.00
7 0 + 063 1 0.3 0.5 0.33
TOTAL 238.42
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
9
1.55
2.09
2.18
4.49
2.46
0.00
0.00
4.69
7.06
3.32
5.88
4.49
3.53
3.71
3.72
0.00
0.00
0.00
0.00
VOLUME
KETERANGAN
(m³)
9
0.00
0.00
VOLUME
KETERANGAN
(m³)
9
3.25
3.25
3.25 PEKERJAAN
TAMBAHAN
3.25 VOLUME
3.25
4.23
69.64
Selisih
0.34
Dibuat Oleh :
Kontraktor Pelaksana
CV. RAF SAN JAYA
HAMDI
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
Dimana :
V = Volume Galian ……………………………..
P = Panjang Galian ………………………………
Muka Tanah L = Luas Rata-rata Galian …………………..
Luas = ( L* T ) …………………………….
Urugan Pasir
T
DIMENSI LUAS
LOKASI PANJANG
NO L T Segmen Rata-rata
( STA )
(m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 6 7 8
A. LOKASI I
1 0 + 000 0.60 0.05 0.03
0.03 10.00
2 0 + 010 0.59 0.05 0.03
0.03 10.00
3 0 + 020 0.72 0.05 0.04
0.04 8.00
4 0 + 028 0.76 0.05 0.04
0.04 12.00
5 0 + 040 0.78 0.05 0.04
B. LOKASI II
1 0 + 000 0.65 0.05 0.03
0.04 10.00
2 0 + 010 0.77 0.05 0.04
0.04 10.00
3 0 + 020 0.84 0.05 0.04
0.04 10.00
4 0 + 030 0.86 0.05 0.04
0.04 10.00
DIMENSI LUAS
LOKASI PANJANG
NO L T Segmen Rata-rata
( STA )
(m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 6 7 8
0.04 10.00
5 0 + 040 0.88 0.05 0.04
0.05 9.40
6 0 + 049.4 0.98 0.05 0.05
DIMENSI LUAS
LOKASI PANJANG
NO L T Segmen Rata-rata
( STA )
(m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 6 7 8
C. TAMHAN PADA LOKASI I
1. 0 + 000 0.8 0.05 0.04
0.04 10.00
2 0 + 010 0.8 0.05 0.04
0.04 10.00
3 0 + 020 0.8 0.05 0.04
0.04 10.00
4 0 + 030 0.8 0.05 0.04
0.04 10.00
5 0 + 040 0.8 0.05 0.04
0.04 10.00
6 0 + 050 0.8 0.05 0.04
0.04 13.00
7 0 + 063 0.8 0.05 0.04
TOTAL 238.42
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
9
0.30
0.33
0.30
0.46
0.28
0.00
0.00
0.45
0.61
0.22
0.34
0.35
0.37
0.38
0.32
0.36
0.40
0.43
0.44
VOLUME
KETERANGAN
(m³)
9
0.44
0.44
VOLUME
KETERANGAN
(m³)
9
0.40
0.40
0.40
0.40
0.40
0.52
9.27
Selisih
3.12
Dibuat Oleh :
Kontraktor Pelaksana
CV. RAF SAN JAYA
HAMDI
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
Dimensi B
Pasangan Batu Gunung
L = Luas Rata-rata Galian …………………..
Luas = ( B1 + B2 ) /2* H …………………………….
Dimensi A
B2
DIMENSI LUAS
LOKASI PANJANG VOLUME
NO B1 B2 H Segmen Rata-rata
( STA )
(m¹) (m¹) (m¹) (m²) (m²) (m¹) (m³)
1 2 3 4 5 6 7 8 9
A. LOKASI I
1 0 + 000 0.32 0.40 0.46 0.17
0.14 10.00 1.41
2 0 + 010 0.30 0.40 0.33 0.12
0.23 10.00 2.28
3 0 + 020 0.31 0.50 0.84 0.34
0.31 8.00 2.48
4 0 + 028 0.32 0.50 0.68 0.28
0.24 12.00 2.89
5 0 + 040 0.33 0.50 0.49 0.20
B. LOKASI II
1 0 + 000 0.3 0.45 0.71 0.27
0.36 10.00 3.61
2 0 + 010 0.31 0.55 1.06 0.46
0.54 10.00 5.40
3 0 + 020 0.31 0.65 1.3 0.62
0.64 10.00 6.39
4 0 + 030 0.34 0.65 1.32 0.65
0.66 10.00 6.56
Pasangan Batu Gunung
Dimensi B
Dimensi A
B2
DIMENSI LUAS
LOKASI PANJANG VOLUME
NO B1 B2 H Segmen Rata-rata
( STA )
(m¹) (m¹) (m¹) (m²) (m²) (m¹) (m³)
1 2 3 4 5 6 7 8 9
0.66 10.00 6.56
5 0 + 040 0.26 0.68 1.4 0.66
0.69 9.40 6.50
6 0 + 049.4 0.32 0.68 1.45 0.73
Pasangan Batu Gunung
Dimensi B
Dimensi A
B2
DIMENSI LUAS
LOKASI PANJANG VOLUME
NO B1 B2 H Segmen Rata-rata
( STA )
(m¹) (m¹) (m¹) (m²) (m²) (m¹) (m³)
1 2 3 4 5 6 7 8 9
C. TAMHAN PADA LOKASI I
1. 0 + 000 0.3 0.6 0.8 0.36
0.36 10.00 3.60
2 0 + 010 0.3 0.6 0.8 0.36
0.36 10.00 3.60
3 0 + 020 0.3 0.6 0.8 0.36
0.36 10.00 3.60
4 0 + 030 0.3 0.6 0.8 0.36
0.36 10.00 3.60
5 0 + 040 0.3 0.6 0.8 0.36
0.36 10.00 3.60
6 0 + 050 0.3 0.6 0.8 0.36
0.36 13.00 4.68
7 0 + 063 0.3 0.6 0.8 0.36
( m³ )
( m³ )
( m' )
( m² )
( m² )
KETERANGAN
KETERANGAN
KETERANGAN
PEKERJAAN
TAMBAHAN
VOLUME
Dibuat Oleh :
Kontraktor Pelaksana
CV. RAF SAN JAYA
HAMDI
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
Pengukuran (Uitzet/Steaking
3. Terlaksana 1.00
Out)
PERHITUNGAN VOLUME
Ls
Ls
Ls
Ls
Luas = ( L* T )…………………………….
DIMENSI LUAS
LOKASI PANJANG
NO L T Segmen Rata-rata
( STA )
(m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 6=(3*4) 7 8
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
9=(7*8)
4.88
4.88
4.88
4.88
4.88
4.88
4.88
4.88
4.19
4.88
4.88
4.88
4.88
4.88
4.88
4.88
4.29
4.88
4.88
4.88
4.88
4.88
4.88
4.88
4.29
4.88
4.88
4.88
4.88
4.88
4.88
VOLUME
KETERANGAN
(m³)
9=(7*8)
4.88
4.88
4.88
4.88
4.88
2.34
175.99
Selisih
13.85
Dibuat Oleh :
Kontraktor Pelaksana
PT. MALVINA BAZAR UTAM
ADAM
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
DIMENSI LUAS
LOKASI PANJANG
NO L T Segmen Rata-rata
( STA )
(m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 6=(3*4) 7 8
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
9=(7*8)
5.25
5.25
5.25
5.25
5.25
5.25
5.25
5.25
4.52
5.25
5.25
5.25
5.25
5.25
5.25
5.25
4.62
5.25
5.25
5.25
5.25
5.25
5.25
5.25
4.62
5.25
5.25
5.25
5.25
5.25
5.25
VOLUME
KETERANGAN
(m³)
9=(7*8)
5.25
5.25
5.25
5.25
5.25
2.52
189.53
Selisih
0.37
Dibuat Oleh :
Kontraktor Pelaksana
PT. MALVINA BAZAR UTAM
ADAM
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
L = L Rata-rata …………………..
V = P x L …………………………
DIMENSI A
LOKASI PANJANG VOLUME
NO Lebar Lebar Rata-rata
( STA )
(m¹) (m¹) (m¹) ( m² )
1 2 3 4 5 6
1 0 + 000 0.60
0.60 25.00 15.00
2 0 + 025 0.60
0.60 25.00 15.00
3 0 + 050 0.60
0.60 25.00 15.00
4 0 + 075 0.60
0.60 25.00 15.00
5 0 + 100 0.60
0.60 25.00 15.00
6 0 + 125 0.60
0.60 25.00 15.00
7 0 + 150 0.60
0.60 25.00 15.00
8 0 + 175 0.60
0.60 25.00 15.00
9 0 + 200 0.60
0.60 0.00
10 0 + 203.5 0.60
0.60 21.50 12.90
11 0 + 225 0.60
0.60 25.00 15.00
12 0 + 250 0.60
0.60 25.00 15.00
13 0 + 275 0.60
0.60 25.00 15.00
14 0 + 300 0.60
0.60 25.00 15.00
15 0 + 325 0.60
0.60 25.00 15.00
16 0 + 350 0.60
0.60 25.00 15.00
17 0 + 375 0.60
0.60 25.00 15.00
18 0 + 400 0.60
0.60 0.00
19 0 + 403 0.60
0.60 22.00 13.20
20 0 + 425 0.60
0.60 25.00 15.00
21 0 + 450 0.60
0.60 25.00 15.00
22 0 + 475 0.60
0.60 25.00 15.00
23 0 + 500 0.60
0.60 25.00 15.00
24 0 + 525 0.60
0.60 25.00 15.00
25 0 + 550 0.60
0.60 25.00 15.00
26 0 + 575 0.60
0.60 25.00 15.00
27 0 + 600 0.60
0.60 0.00
28 0 + 603 0.60
0.60 22.00 13.20
29 0 + 625 0.60
0.60 25.00 15.00
30 0 + 650 0.60
0.60 25.00 15.00
31 0 + 675 0.60
0.60 25.00 15.00
32 0 + 700 0.60
0.60 25.00 15.00
33 0 + 725 0.60
0.60 25.00 15.00
34 0 + 750 0.60
0.60 25.00 15.00
35 0 + 775 0.60
0.60 25.00 15.00
36 0 + 800 0.60
0.60 25.00 15.00
37 0 + 825 0.60
DIMENSI A
LOKASI PANJANG VOLUME
NO Lebar Lebar Rata-rata
( STA )
(m¹) (m¹) (m¹) ( m² )
1 2 3 4 5 6
0.60 25.00 15.00
38 0 + 850 0.60
0.60 25.00 15.00
39 0 + 875 0.60
0.60 25.00 15.00
39 0 + 900 0.60
0.60 12.00 7.20
40 0 + 912 0.60
TOTAL 902.50 541.50
( m² )
( m² )
( m' )
( m' )
( m² )
KETERANGAN
KETERANGAN
Dibuat Oleh :
Kontraktor Pelaksana
CV. RAF SAN JAYA
HAMDI
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
DIMENSI LUAS
LOKASI PANJANG
NO L T Segmen Rata-rata
( STA )
(m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 6=(3*4) 7 8
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
9=(7*8)
5.25
5.25
5.25
5.25
5.25
5.25
5.25
5.25
4.52
5.25
5.25
5.25
5.25
5.25
5.25
5.25
4.62
5.25
5.25
5.25
5.25
5.25
5.25
5.25
4.62
5.25
5.25
5.25
5.25
5.25
5.25
VOLUME
KETERANGAN
(m³)
9=(7*8)
5.25
5.25
5.25
5.25
5.25
2.52
189.53
Selisih
0.37
Dibuat Oleh :
Kontraktor Pelaksana
PT. MALVINA BAZAR UTAM
ADAM
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
DIMENSI A LUAS
LOKASI PANJANG
NO L T Segmen Rata-rata
( STA )
(m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 6 7 8
A. LOKASI I
1 0 + 000 0.60 0.35 0.21
0.18 10.00
2 0 + 010 0.59 0.25 0.15
0.20 10.00
3 0 + 020 0.72 0.35 0.25
0.24 8.00
4 0 + 028 0.76 0.30 0.23
0.29 12.00
5 0 + 040 0.78 0.45 0.35
0.00
6 0 + 040 1.03 0.30 0.31
0.39 5.50
7 0 + 045.5 1.03 0.45 0.46
0.00
8 0 + 045.5 0.00 0.00 0.00
0.00 1.10
9 0 + 046.6 0.00 0.00 0.00
0.00
10 0 + 000 0.00 0.00 0.00
0.00 0.92
11 0 + 000.9 0.00 0.00 0.00
0.00
12 0 + 000 1.05 0.35 0.37
0.49 9.00
13 0 + 009 0.95 0.65 0.62
0.43 14.70
14 0 + 023.7 0.70 0.35 0.25
B. LOKASI II
1 0 + 000 0.65 0.4 0.26
0.26 10.00
2 0 + 010 0.77 0.35 0.27
0.30 10.00
3 0 + 020 0.84 0.4 0.34
0.34 10.00
4 0 + 030 0.86 0.4 0.34
0.33 10.00
DIMENSI A LUAS
LOKASI PANJANG
NO L T Segmen Rata-rata
( STA )
(m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 6 7 8
0.33 10.00
5 0 + 040 0.88 0.35 0.31
0.35 9.40
6 0 + 049.4 0.98 0.4 0.39
DIMENSI A LUAS
LOKASI PANJANG
NO L T Segmen Rata-rata
( STA )
(m¹) (m¹) (m²) (m²) (m¹)
1 2 3 4 6 7 8
C. TAMHAN PADA LOKASI I
TOTAL 238.42
Berlanjut Kelembaran Lerikutnya
P x L ……………………………………………… ( m³ )
VOLUME
KETERANGAN
(m³)
9
1.79
2.00
1.92
3.47
2.12
0.00
0.00
4.43
6.34
1.73
2.70
2.98
3.50
3.56
2.94
2.65
3.03
3.40
3.26
VOLUME
KETERANGAN
(m³)
9
3.26
3.29
VOLUME
KETERANGAN
(m³)
9
2.40
2.40
2.40 PEKERJAAN
TAMBAHAN
2.40 VOLUME
2.40
3.12
70.22
lanjut Kelembaran Lerikutnya
Dibuat Oleh :
Kontraktor Pelaksana
CV. RAF SAN JAYA
HAMDI
DIREKTUR
BACK UP DATA KUANTITAS TERLAKSANA
V = P x L …………………
DIMENSI A
LOKASI PANJANG VOLUME
NO Lebar Lebar Rata-rata
( STA )
(m¹) (m¹) (m¹) ( m² )
1 2 3 4 5 6
A. LOKASI I
1 0 + 000 0.46
0.40 10.00 3.95
2 0 + 010 0.33
0.59 10.00 5.85
3 0 + 020 0.84
0.76 8.00 6.08
4 0 + 028 0.68
0.59 12.00 7.02
5 0 + 040 0.49
6 0 + 040 0.83
0.66 5.50 3.60
7 0 + 045.5 0.48
8 0 + 045.5 0.70
0.43 1.10 0.47
9 0 + 046.6 0.15
10 0 + 000 0.10
0.53 0.92 0.48
11 0 + 000.9 0.95
12 0 + 000 1.50
1.50 9.00 13.50
13 0 + 009 1.50
0.95 14.70 13.89
14 0 + 023.7 0.39
15 0 + 023.7 0.48
0.48 6.30 2.99
16 0 + 030 0.47
0.57 10.00 5.65
17 0 + 040 0.66
0.60 10.00 6.00
18 0 + 050 0.54
0.63 10.00 6.25
19 0 + 060 0.71
0.71 10.00 7.05
20 0 + 070 0.70
0.74 8.50 6.29
21 0 + 078.5 0.78
B. LOKASI II
1 0 + 000 0.71
0.89 10.00 8.85
2 0 + 010 1.06
1.18 10.00 11.80
DIMENSI A
LOKASI PANJANG VOLUME
NO Lebar Lebar Rata-rata
( STA )
(m¹) (m¹) (m¹) ( m² )
1 2 3 4 5 6
1.18 10.00 11.80
3 0 + 020 1.3
1.31 10.00 13.10
4 0 + 030 1.32
1.36 10.00 13.60
5 0 + 040 1.4
1.43 9.40 13.40
6 0 + 049.4 1.45
DIMENSI A
LOKASI PANJANG VOLUME
NO Lebar Lebar Rata-rata
( STA )
(m¹) (m¹) (m¹) ( m² )
1 2 3 4 5 6
C. TAMBAHAN DI LOKASI I
1. 0 + 000 0.8
0.80 10.00 8.00
2 0 + 010 0.8
0.80 10.00 8.00
3 0 + 020 0.8
0.80 10.00 8.00
4 0 + 030 0.8
0.80 10.00 8.00
5 0 + 040 0.8
0.80 10.00 8.00
6 0 + 050 0.8
0.80 13.00 10.40
7 0 + 063 0.8
TOTAL 238.42 200.22
( m² )
( m² )
( m' )
( m' )
( m² )
KETERANGAN
KETERANGAN
KETERANGAN
Dibuat Oleh :
Kontraktor Pelaksana
CV. RAF SAN JAYA
HAMDI
DIREKTUR
REKAPITULASI
BACK UP DATA KUANTITAS TERLAKSANA
I. UMUM
1 Sarana Prasarana dan Personil Ls 1.00 1.00 - 300,000.00
2 Administrasi Ls 1.00 1.00 - 2,100,000.00
3 Pengukuran (Uitzet/Steaking Out) Ls 1.00 1.00 - 1,200,000.00
4 Ass Buill Drawing Ls 1.00 1.00 - 2,000,000.00
JUMLAH HARGA I
II. PEKERJAAN DRAINASE
1 Pek. Galian Parit / Drainase M³ 59.62 59.62 - 81,075.00
2 Pek. Pasangan Batu Gunung 1 : 4 M³ 31.96 31.96 - 867,405.90
3 Pek. Pelesteran 1 : 3 M³ 163.07 163.07 - 74,659.27
4 Pek. Acian Semen Air M² 163.07 163.07 - 43,336.60
JUMLAH HARGA II
III. PEKERJAAN TALUD
1 Pek. Galian Talud M³ 7.07 7.07 - 81,075.00
2 Pek. Pasangan Batu Kosong M³ 2.48 2.48 - 407,210.40
3 Pek. Pasanagan Batu Gunung 1 : 5 M³ 8.46 8.46 - 867,405.90
4 Pek. Plesteran Siar Adukan 1 : 2 M² 22.00 22.00 - 69,955.28
JUMLAH HARGA III
A. REAL COST (JUMLAH HARGA I S/D III)
B. PPN 10% ( A x 10%)
C. TOTAL COST (A + B)
D. DIBULATKAN
Menegetahui / Disetujui:
Pejabat Pelaksana Teknis Kegiatan (PPTK)
Dinas Pekerjaan Umum Dan Pentaan Ruang
Kab. Muna
300,000.00 300,000.00
2,100,000.00 2,100,000.00
1,200,000.00 1,200,000.00
2,000,000.00 2,000,000.00
5,600,000.00
4,833,950.94 4,833,950.94
27,721,598.64 27,721,598.64
12,174,836.04 12,174,836.04
7,066,986.04 7,066,986.04
51,797,371.65
573,038.10 573,038.10
1,009,881.79 1,009,881.79
7,338,253.91 7,338,253.91
1,539,016.20 1,539,016.20
10,460,190.01 10,460,190.01
67,857,561.66 67,857,561.66
6,785,756.17 6,785,756.17
74,643,317.83 74,643,317.83
74,640,000.00 74,640,000.00
HARYADI, ST GAMSIR
DIREKTUR DIREKTUR
Diperiksa Oleh : Dibuat Oleh :
Konsultan Supervisi Kontraktor Pelaksana
MAESTRO STUDIOCONSULTANT CV. DARMA ABADI
HARYADI, ST GAMSIR
DIREKTUR DIREKTUR
RINCIAN SERTIFIKAT BULANAN
MUTUAL CHECK (MC-01)
PERIODE BULAN KE- I (18 JULI 2019 S/D 18 AGUSTUS 201
KONTRAK AWAL
NO URAIAN PEKERJAAN
SATUAN VOLUME HARGA SATUAN NILAI HARGA (Rp)
1. DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 208,540,000.00 208,540,000.00
Jumlah Harga Pekerjaan DIVISI 1 208,540,000.00
2. DIVISI 2. DRAINASE DAN SALURAN AIR
2.1.(1) Galian untuk Saluran Air M³ 2,730.00 9,411.86 25,694,377.80
Jumlah Harga Pekerjaan DIVISI 2 25,694,377.80
3. DIVISI 3. PEKERJAAN TANAH
3.1.(1a) Galian Berbutir (Cuttingan) M³ 3,000.40 192,802.36 578,484,200.94
3.2.(2) Sub Base dengan Material Tanah Pilihan M³ 5,400.00 184,491.09 996,251,880.60
3.3.(1) Penyiapan Badan Jalan M² 24,000.00 1,813.64 43,527,305.28
JUMLAH HARGA III 1,618,263,386.82
REALISASI FISIK
A REAL COST ( 1 + 2 + 3 ) 1,852,497,764.62
B PPN 10 % 185,249,776.46
C JUMLAH TOTAL ( A + B ) 2,037,747,541.09
F PENGURANGAN
~ Sertifikat Sampai dengan Bulan Lalu
~ Retensi 5%
~ Pengembalian Uang Muka 20%
~ Lain-Lain
JUMLAH PENGURANGAN
G JUMLAH PEMBAYARAN SERTIFIKAT BULANAN (C-F)
TERBILANG :
-
-
Menegetahui/Menyetujui
KPA/PPK
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
IKHSAN, S.Kom. MM
NIP. 19811230 200801 1 005
AN SERTIFIKAT BULANAN
UTUAL CHECK (MC-01)
- I (18 JULI 2019 S/D 18 AGUSTUS 2019)
- - -
-
- - -
-
- - -
- - -
- - -
-
-
-
-
-
-
-
-
-
-
-
-
DIBULATKAN -
-
-
-
Menegetahui/Menyetujui
KPA/PPK
TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
IKHSAN, S.Kom. MM
NIP. 19811230 200801 1 005
PERIODE M
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
ERIODE MINGGU KE- V (19 AGUSTUS 2019 S/D 26 AGUSTUS 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
US 2019)
- - - - - -
-
- - - - - -
-
- - - - - -
- - - - - -
- - - - - -
-
-
REKA
PERIODE M
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
ERIODE MINGGU KE- V (19 AGUSTUS 2019 S/D 26 AGUSTUS 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
0.00
R 0.00
0.00
0.00
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
US 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
- - - -
- - -
BOBOT REALSASI 0 - - -
- -
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
- -
- -
-7.03 -7.23
5
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIODE MIN
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
RIODE MINGGU KE- VI (27 AGUSTUS 2019 S/D 03 SEPTEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
BER 2019)
- - - - - -
-
- - - - - -
-
- - - - - -
- - - - - -
- - - - - -
-
-
REKA
PERIODE MIN
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
RIODE MINGGU KE- VI (27 AGUSTUS 2019 S/D 03 SEPTEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
0.00
R 0.00
0.00
0.00
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
BER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
- - - -
- - -
BOBOT REALSASI 0 - - -
- - -
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
- - -
- - -
-7.03 -7.23 -7.42
5
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIODE MING
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
IODE MINGGU KE- VII (04 SEPTEMBER 2019 S/D 11 SEPTEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
MBER 2019)
- - - - - -
-
- - - - - -
- - - - - -
- - - - - -
-
2.81
REKA
PERIODE MING
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
IODE MINGGU KE- VII (04 SEPTEMBER 2019 S/D 11 SEPTEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
0.00
R 0.00
0.00
0.00
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
MBER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
2.81 2.81
0.00 0.00
0.00 0.00
2.81 2.81
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
2.81 - - -
- - -
BOBOT REALSASI 0 - - -
PERIODE MINGGU KE- VII (04 SEPTEMBER 2019 S/D 11 SEPTEMBER 2019)
- - - 2.81
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
- - - 2.81
- - - 2.81
-7.03 -7.23 -7.42 -4.81
5
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIODE MING
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
ODE MINGGU KE- VIII (12 SEPTEMBER 2019 S/D 18 SEPTEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
MBER 2019)
- - - - - -
-
11.21
REKA
PERIODE MING
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
ODE MINGGU KE- VIII (12 SEPTEMBER 2019 S/D 18 SEPTEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
2.81
R 0.00
0.00
2.81
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
MBER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
6.75 3.94
0.00 0.00
4.45 4.45
11.21 8.39
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
6.75 - - -
- - -
4.45
BOBOT REALSASI 0 - - -
PERIODE MINGGU KE- VIII (12 SEPTEMBER 2019 S/D 18 SEPTEMBER 2019)
- - - 2.81 3.94
4.45
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
- - - 2.81 8.39
- - - 2.81 11.21
-7.03 -7.23 -7.42 -4.81 1.78
5
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIODE BU
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
ERIODE BULAN KE- II (19 AGUSTUS 2019 S/D 19 SEPTEMBER 2019)
LAPORAN BULAN
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI BULAN LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
BER 2019)
- - - - - -
-
11.21
REKA
PERIODE BU
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
ERIODE BULAN KE- II (19 AGUSTUS 2019 S/D 19 SEPTEMBER 2019)
LAPORAN BULAN
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
0.00
R 0.00
0.00
0.00
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
BER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. BULAN INI
(%)
BULAN INI ( % )
6.75 6.75
0.00 0.00
4.45 4.45
11.21 11.21
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
RINCIAN SERTIFIKAT BULANAN
MUTUAL CHECK (MC-02)
PERIODE BULAN KE- II (19 AGUSTUS 2019 S/D 19 SEPTEMBE
KONTRAK AWAL
NO URAIAN PEKERJAAN
SATUAN VOLUME HARGA SATUAN NILAI HARGA (Rp)
1. DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 208,540,000.00 208,540,000.00
Jumlah Harga Pekerjaan DIVISI 1 208,540,000.00
2. DIVISI 2. DRAINASE DAN SALURAN AIR
2.1.(1) Galian untuk Saluran Air M³ 2,730.00 9,411.86 25,694,377.80
Jumlah Harga Pekerjaan DIVISI 2 25,694,377.80
3. DIVISI 3. PEKERJAAN TANAH
3.1.(1a) Galian Berbutir (Cuttingan) M³ 3,000.40 192,802.36 578,484,200.94
3.2.(2) Sub Base dengan Material Tanah Pilihan M³ 5,400.00 184,491.09 996,251,880.60
3.3.(1) Penyiapan Badan Jalan M² 24,000.00 1,813.64 43,527,305.28
JUMLAH HARGA III 1,618,263,386.82
REALISASI FISIK
A REAL COST ( 1 + 2 + 3 ) 1,852,497,764.62
B PPN 10 % 185,249,776.46
C JUMLAH TOTAL ( A + B ) 2,037,747,541.09
F PENGURANGAN
~ Sertifikat Sampai dengan Bulan Lalu
~ Retensi 5%
~ Pengembalian Uang Muka 20%
~ Lain-Lain
JUMLAH PENGURANGAN
G JUMLAH PEMBAYARAN SERTIFIKAT BULANAN (C-F)
TERBILANG :
DUA RATUS DUA PULUH DELAPAN JUTA TIGA RATUS ENAM PULUH RIBU RUPIAH
DUA RATUS DUA PULUH DELAPAN JUTA TIGA RATUS ENAM PULUH RIBU RUPIAH
Menegetahui/Menyetujui
KPA/PPK
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
IKHSAN, S.Kom. MM
NIP. 19811230 200801 1 005
AN SERTIFIKAT BULANAN
UTUAL CHECK (MC-02)
19 AGUSTUS 2019 S/D 19 SEPTEMBER 2019)
- - -
-
207,600,295.70
11.21
20,760,029.57
228,360,325.27
228,360,000.00
-
-
-
-
-
228,360,000.00
DIBULATKAN 228,360,000.00
-
11.21
11.21
Menegetahui/Menyetujui
KPA/PPK
TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
IKHSAN, S.Kom. MM
NIP. 19811230 200801 1 005
PERIODE MING
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
IODE MINGGU KE- IX (19 SEPTEMBER 2019 S/D 26 SEPTEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
MBER 2019)
16.34
REKA
PERIODE MING
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
IODE MINGGU KE- IX (19 SEPTEMBER 2019 S/D 26 SEPTEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 0.00
4.45
11.21
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
MBER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
6.75 0.00
0.10 0.10
9.49 5.04
16.34 5.13
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
6.75 - - -
0.10 - -
9.49
BOBOT REALSASI 0 - - -
- - - 2.81 3.94 -
4.45 5.04
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIODE MIN
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
RIODE MINGGU KE- X (27 SEPTEMBER 2019 S/D 04 OKTOBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
BER 2019)
21.63
REKA
PERIODE MIN
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
RIODE MINGGU KE- X (27 SEPTEMBER 2019 S/D 04 OKTOBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 0.10
9.49
16.34
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
BER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
6.75 0.00
0.31 0.21
14.57 5.08
21.63 5.29
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
6.75 - - -
0.31 - -
14.57
BOBOT REALSASI 0 - - -
- - - 2.81 3.94 - -
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIODE MI
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
ERIODE MINGGU KE- XI (05 0KTOBERR 2019 S/D 11 OKTOBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
BER 2019)
27.34
REKA
PERIODE MI
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
ERIODE MINGGU KE- XI (05 0KTOBERR 2019 S/D 11 OKTOBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 0.31
14.57
21.63
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
BER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
6.75 0.00
0.93 0.62
19.66 5.08
27.34 5.71
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
6.75 - - -
0.93 - -
19.66
BOBOT REALSASI 0 - - -
- - - 2.81 3.94 - - -
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIODE MIN
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
ERIODE MINGGU KE- XII (06 0KTOBERR 2019 S/D 12 OKTOBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
BER 2019)
37.82
REKA
PERIODE MIN
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
ERIODE MINGGU KE- XII (06 0KTOBERR 2019 S/D 12 OKTOBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 0.93
19.66
27.34
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
BER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
6.75 0.00
1.21 0.28
29.86 10.20
37.82 10.48
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
6.75 - - -
1.21 - -
29.86
BOBOT REALSASI 0 - - -
PERIODE MINGGU KE- XII (06 0KTOBERR 2019 S/D 12 OKTOBER 2019)
- - - 2.81 3.94 - - - -
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIODE BU
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
ERIODE BULAN KE- III (19 SEPTEMBER 2019 S/D 18OKTOBER 2019)
LAPORAN BULAN
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI BULAN LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
BER 2019)
37.82
REKA
PERIODE BU
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
ERIODE BULAN KE- III (19 SEPTEMBER 2019 S/D 18OKTOBER 2019)
LAPORAN BULAN
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 0.00
4.45
11.21
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
BER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. BULAN INI
(%)
BULAN INI ( % )
6.75 0.00
1.21 1.21
29.86 25.40
37.82 26.61
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
RINCIAN SERTIFIKAT BULANAN
MUTUAL CHECK (MC-03)
PERIODE BULAN KE- III (19 SEPTEMBER 2019 S/D 18OKTOBE
KONTRAK AWAL
NO URAIAN PEKERJAAN
SATUAN VOLUME HARGA SATUAN NILAI HARGA (Rp)
1. DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 208,540,000.00 208,540,000.00
Jumlah Harga Pekerjaan DIVISI 1 208,540,000.00
2. DIVISI 2. DRAINASE DAN SALURAN AIR
2.1.(1) Galian untuk Saluran Air M³ 2,730.00 9,411.86 25,694,377.80
Jumlah Harga Pekerjaan DIVISI 2 25,694,377.80
3. DIVISI 3. PEKERJAAN TANAH
3.1.(1a) Galian Berbutir (Cuttingan) M³ 3,000.40 192,802.36 578,484,200.94
3.2.(2) Sub Base dengan Material Tanah Pilihan M³ 5,400.00 184,491.09 996,251,880.60
3.3.(1) Penyiapan Badan Jalan M² 24,000.00 1,813.64 43,527,305.28
JUMLAH HARGA III 1,618,263,386.82
REALISASI FISIK
A REAL COST ( 1 + 2 + 3 ) 1,852,497,764.62
B PPN 10 % 185,249,776.46
C JUMLAH TOTAL ( A + B ) 2,037,747,541.09
F PENGURANGAN
~ Sertifikat Sampai dengan Bulan Lalu
~ Retensi 5%
~ Pengembalian Uang Muka 20%
~ Lain-Lain
JUMLAH PENGURANGAN
G JUMLAH PEMBAYARAN SERTIFIKAT BULANAN (C-F)
TERBILANG :
TUJUH RATUS TUJUH PULUH JUTA ENAM RATUS LIMA RIBU RUPIAH
TUJUH RATUS TUJUH PULUH JUTA ENAM RATUS LIMA RIBU RUPIAH
Menegetahui/Menyetujui
KPA/PPK
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
IKHSAN, S.Kom. MM
NIP. 19811230 200801 1 005
AN SERTIFIKAT BULANAN
UTUAL CHECK (MC-03)
19 SEPTEMBER 2019 S/D 18OKTOBER 2019)
700,550,314.45
37.82
70,055,031.44
770,605,345.89
770,605,000.00
-
-
-
-
-
770,605,000.00
DIBULATKAN 770,605,000.00
-
37.82
37.82
Menegetahui/Menyetujui
KPA/PPK
TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
IKHSAN, S.Kom. MM
NIP. 19811230 200801 1 005
PERIODE MIN
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
RIODE MINGGU KE- XIII (19 0KTOBERR 2019 S/D 26 OKTOBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
BER 2019)
56.88
REKA
PERIODE MIN
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
RIODE MINGGU KE- XIII (19 0KTOBERR 2019 S/D 26 OKTOBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 1.21
29.86
37.82
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
BER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
6.75 0.00
1.31 0.10
48.82 18.97
56.88 19.07
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
6.75 - - -
1.31 - -
48.82
BOBOT REALSASI 0 - - -
PERIODE MINGGU KE- XIII (19 0KTOBERR 2019 S/D 26 OKTOBER 2019)
- - - 2.81 3.94 - - - - -
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIODE MIN
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
RIODE MINGGU KE- XIV (27 0KTOBER 2019 S/D 03 NOVEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
BER 2019)
77.68
REKA
PERIODE MIN
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
RIODE MINGGU KE- XIV (27 0KTOBER 2019 S/D 03 NOVEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 1.31
48.82
56.88
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
BER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
6.75 0.00
1.31 0.00
69.61 20.79
77.68 20.79
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
KURVA " S " PRO
SATKER : DINAS TRANSMIGRASI DAN TENAGA KERJA
KEGIATAN : PEMBANGUNAN / PENINGKATAN JALAN NON STATUS
PEKERJAAN : PERKERASAN JALAN KAWASAN TRANSMIGRASI EX-UPT LABUNIA KAWASAN TRANSMIG
LOKASI : KECAMATAN WAKORUMBA SELATAN KAB. MUNA
KONTRAKTOR : CV. MONDOLALO
KONSULTAN SUPERVISI : CV. BUILDING ENGGINEERING CONSULTANT
Bobot Bobot
BULAN KE - 1
No. Uraian Rencana. Realisasi.
(%) (%) M1 M2 M3
6.75 - - -
1.31 - -
69.61
BOBOT REALSASI 0 - - -
PERIODE MINGGU KE- XIV (27 0KTOBERR 2019 S/D 03 NOVEMBER 2019)
- - - 2.81 3.94 - - - - - -
1.81 0.20 0.20 0.20 1.81 10.92 10.92 10.92 12.53 10.92 10.92 10.92 12.53
7.03 7.23 7.42 7.62 9.43 20.35 31.27 42.19 54.7 65.6 76.6 87.5 100.0
Dibuat Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
Direktur
Ket.
100 %
50%
0%
6
PERIODE MING
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
RIODE MINGGU KE- XV (04 NOVEMBER 2019 S/D 11 NOVEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
MBER 2019)
86.78
REKA
PERIODE MING
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
RIODE MINGGU KE- XV (04 NOVEMBER 2019 S/D 11 NOVEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 1.31
69.61
77.68
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
MBER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
6.75 0.00
1.31 0.00
78.71 9.10
86.78 9.10
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
PERIODE MING
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
IODE MINGGU KE- XVI (12 NOVEMBER 2019 S/D 13 NOVEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
MBER 2019)
86.78
REKA
PERIODE MING
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
IODE MINGGU KE- XVI (12 NOVEMBER 2019 S/D 13 NOVEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 1.31
78.71
86.78
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
MBER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
6.75 0.00
1.31 0.00
78.71 0.00
86.78 0.00
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
PERIODE BU
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
ERIODE BULAN KE- IV (19 OKTOBER 2019 S/D 13 NOVEMBER 2019)
LAPORAN BULAN
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI BULAN LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
BER 2019)
86.78
REKA
PERIODE BU
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
ERIODE BULAN KE- IV (19 OKTOBER 2019 S/D 13 NOVEMBER 2019)
LAPORAN BULAN
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 1.21
29.86
37.82
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
BER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. BULAN INI
(%)
BULAN INI ( % )
6.75 0.00
1.31 0.10
78.71 48.86
86.78 48.96
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
RINCIAN SERTIFIKAT BULANAN
MUTUAL CHECK (MC-04)
PERIODE BULAN KE- IV (19 OKTOBER 2019 S/D 13 NOVEMBE
KONTRAK AWAL
NO URAIAN PEKERJAAN
SATUAN VOLUME HARGA SATUAN NILAI HARGA (Rp)
1. DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 208,540,000.00 208,540,000.00
Jumlah Harga Pekerjaan DIVISI 1 208,540,000.00
2. DIVISI 2. DRAINASE DAN SALURAN AIR
2.1.(1) Galian untuk Saluran Air M³ 2,730.00 9,411.86 25,694,377.80
Jumlah Harga Pekerjaan DIVISI 2 25,694,377.80
3. DIVISI 3. PEKERJAAN TANAH
3.1.(1a) Galian Berbutir (Cuttingan) M³ 3,000.40 192,802.36 578,484,200.94
3.2.(2) Sub Base dengan Material Tanah Pilihan M³ 5,400.00 184,491.09 996,251,880.60
3.3.(1) Penyiapan Badan Jalan M² 24,000.00 1,813.64 43,527,305.28
JUMLAH HARGA III 1,618,263,386.82
REALISASI FISIK
A REAL COST ( 1 + 2 + 3 ) 1,852,497,764.62
B PPN 10 % 185,249,776.46
C JUMLAH TOTAL ( A + B ) 2,037,747,541.09
F PENGURANGAN
~ Sertifikat Sampai dengan Bulan Lalu
~ Retensi 5%
~ Pengembalian Uang Muka 20%
~ Lain-Lain
JUMLAH PENGURANGAN
G JUMLAH PEMBAYARAN SERTIFIKAT BULANAN (C-F)
TERBILANG :
SATU MILIYAR TUJUH RATUS ENAM PULUH DELAPAN JUTA TIGA RATUS TUJUH RIBU R
SATU MILIYAR TUJUH RATUS ENAM PULUH DELAPAN JUTA TIGA RATUS TUJUH RIBU R
Menegetahui/Menyetujui
KPA/PPK
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
IKHSAN, S.Kom. MM
NIP. 19811230 200801 1 005
AN SERTIFIKAT BULANAN
UTUAL CHECK (MC-04)
(19 OKTOBER 2019 S/D 13 NOVEMBER 2019)
1,607,552,692.02
86.78
160,755,269.20
1,768,307,961.22
1,768,307,000.00
-
-
-
-
-
1,768,307,000.00
DIBULATKAN 1,768,307,000.00
-
86.78
86.78
Menegetahui/Menyetujui
KPA/PPK
TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
IKHSAN, S.Kom. MM
NIP. 19811230 200801 1 005
PERIODE MING
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
ODE MINGGU KE- XVII (14 NOVEMBER 2019 S/D 21 NOVEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL ADENDUM
MASA PELAKSANAAN
NO. ADENDUM
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
MBER 2019)
91.15
REKA
PERIODE MING
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
ODE MINGGU KE- XVII (14 NOVEMBER 2019 S/D 21 NOVEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 1.31
78.71
86.78
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
MBER 2019)
O. KONTRAK : 06/ADD-I/KTRK/DTTK/XI/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
6.75 0.00
1.31 0.00
83.09 4.37
91.15 4.37
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
PERIODE MING
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
ODE MINGGU KE- XVIII (22 NOVEMBER 2019 S/D 29 NOVEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL ADENDUM
MASA PELAKSANAAN
NO. ADENDUM
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
MBER 2019)
95.50
REKA
PERIODE MING
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
ODE MINGGU KE- XVIII (22 NOVEMBER 2019 S/D 29 NOVEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 1.31
83.09
91.15
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
MBER 2019)
O. KONTRAK : 06/ADD-I/KTRK/DTTK/XI/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
6.75 0.00
1.39 0.08
87.36 4.27
95.50 4.35
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
PERIODE MING
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
IODE MINGGU KE- XIX (30 NOVEMBER 2019 S/D 07 DESEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL ADENDUM
MASA PELAKSANAAN
NO. ADENDUM
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI MINGGU LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
MBER 2019)
100.00
REKA
PERIODE MING
1. DIVISI 1. UMUM
JUMLAH TOTAL
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
IODE MINGGU KE- XIX (30 NOVEMBER 2019 S/D 07 DESEMBER 2019)
LAPORAN MINGGU
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 1.39
87.36
95.50
AN
MBER 2019)
O. KONTRAK : 06/ADD-I/KTRK/DTTK/XI/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. MINGGU INI
(%)
MINGGU INI ( % )
11.26 4.50
1.39 0.00
87.36 0.00
100.00 4.50
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
PERIODE BU
K
NO. MATA
URAIAN PEKERJAAN PERKIRAAN
PEMBAYARAN SATUAN
KUANTITAS
C TOTAL COST (A + B)
D DIBULATKAN
LAPORAN KEMAJUAN PEKERJAAN
RIODE BULAN KE- V (14 NOVEMBER 2019 S/D 03 DESEMBER 2019)
LAPORAN BULAN
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
KONTRAK
HARGA SATUANAWAL PR
JUMLAH HARGA
BOBOT REALISASI BULAN LALU
(%)
(Rp) VOLUME KEMAJUAN BOBOT
(Rp)
(5) (6) (7) (8) (9) (10)
1,852,497,764.62
185,249,776.46
100.00
2,037,747,541.09
###
BER 2019)
100.00
REKA
PERIODE BU
1. DIVISI 1. UMUM
JUMLAH TOTAL
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
RIODE BULAN KE- V (14 NOVEMBER 2019 S/D 03 DESEMBER 2019)
LAPORAN BULAN
PERIODE
X-UPT LABUNIA KAWASAN TRANSMIGRASI MUTIARA KEC. WAKORUMBA SELATAN TANGGAL KONTRTAK
MASA PELAKSANAAN
NO. KONTRAK
NILAI KONTRAK
6.75
R 1.31
78.71
86.78
Di Periksa Oleh :
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
Konsultan Supervisi
CV. BUILDING ENGGINEERING CONSULTANT
TAKDIR MANSYAH, ST
DIREKTUR
AN
BER 2019)
O. KONTRAK : 06/KTRK/DTTK/VII/2019
KEMAJUAN PEKERJAAN
KEMAJUAN PEKERJAAN S/D. BULAN INI
(%)
BULAN INI ( % )
11.26 4.50
1.39 0.08
87.36 8.64
100.00 13.22
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
RINCIAN SERTIFIKAT BULANAN
MUTUAL CHECK (MC-05)
PERIODE BULAN KE- V (14 NOVEMBER 2019 S/D 03 DESEMBE
KONTRAK AWAL
NO URAIAN PEKERJAAN
SATUAN VOLUME HARGA SATUAN NILAI HARGA (Rp)
1. DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 208,540,000.00 208,540,000.00
Jumlah Harga Pekerjaan DIVISI 1 208,540,000.00
2. DIVISI 2. DRAINASE DAN SALURAN AIR
2.1.(1) Galian untuk Saluran Air M³ 2,730.00 9,411.86 25,694,377.80
Jumlah Harga Pekerjaan DIVISI 2 25,694,377.80
3. DIVISI 3. PEKERJAAN TANAH
3.1.(1a) Galian Berbutir (Cuttingan) M³ 3,000.40 192,802.36 578,484,200.94
3.2.(2) Sub Base dengan Material Tanah Pilihan M³ 5,400.00 184,491.09 996,251,880.60
3.3.(1) Penyiapan Badan Jalan M² 24,000.00 1,813.64 43,527,305.28
JUMLAH HARGA III 1,618,263,386.82
REALISASI FISIK
A REAL COST ( 1 + 2 + 3 ) 1,852,497,764.62
B PPN 10 % 185,249,776.46
C JUMLAH TOTAL ( A + B ) 2,037,747,541.09
F PENGURANGAN
~ Sertifikat Sampai dengan Bulan Lalu
~ Retensi 5%
~ Pengembalian Uang Muka 20%
~ Lain-Lain
JUMLAH PENGURANGAN
G JUMLAH PEMBAYARAN SERTIFIKAT BULANAN (C-F)
TERBILANG :
DUA MILIYAR TIGA PULUH TUJUH JUTA TUJUH RATUS EMPAT PULUH TUJUH RUPIAH
DUA MILIYAR TIGA PULUH TUJUH JUTA TUJUH RATUS EMPAT PULUH TUJUH RUPIAH
Di Setujui Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK)
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
SYAHRUN RAEBA, SE
NIP. 19641231 199203 1 153
Menegetahui/Menyetujui
KPA/PPK
DINAS TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
IKHSAN, S.Kom. MM
NIP. 19811230 200801 1 005
AN SERTIFIKAT BULANAN
UTUAL CHECK (MC-05)
14 NOVEMBER 2019 S/D 03 DESEMBER 2019)
1,852,497,764.62
100.00
185,249,776.46
2,037,747,541.09
2,037,747,000.00
-
-
-
-
-
2,037,747,000.00
DIBULATKAN 2,037,747,000.00
-
100.00
100.00
Di buat Oleh :
Kontraktor Pelaksana
CV. MONDOLALO
MUHAMMAD BURHANUDDIN
DIREKTUR
Menegetahui/Menyetujui
KPA/PPK
TRANSMIGRASI DAN TENAGA KERJA
KABUPATEN MUNA
IKHSAN, S.Kom. MM
NIP. 19811230 200801 1 005
PEMERINTAH KABUPATEN MUNA
DINAS TRANSMIGRASI DAN TENAGA KE
TAHUN ANGGARAN 2019
JL. Macan No. 48 Tlp. ( 0403 ) 21429 Kode Pos 93615 Raha
Pada hari ini Selasa tanggal Tiga Bulan Desember Tahun Dua Ribu Sembilan Belas kami ya
IKHSAN, S.Kom. MM
1. Nama :
Jabatan : Pejabat Pembuat Komitmen (PPK) Kegiatan Pembangunan / Pen
Transnaker Kabupaten Muna
Alamat : Raha Kab. Muna
Bahwa Kemajuan pekerjaan yang telah dilaksanakan oleh PIHAK KETIGA sampai de
adalah Sebesar 100 % (Seratus Persen) dari volume kontrak.
esember Tahun Dua Ribu Sembilan Belas kami yang bertanda tangan dibawah ini :
PROGRAM :
PENYIAPAN KAWASAN DAN PEMBANGUNAN PERMUKIMAN
TRANSMIGRASI PERMUKIMAN TRANSMIGRASI (PKP2T)
PEKERJAAN :
PEMBANGUNAN BRONJONG PENAHAN TEBING
NOMOR KONTRAK :
11/KTRK/PKP2T/III/2019
NILAI KONTRAK :
Rp. 1.002.877.735,-
LOKASI :
UPT LANGKORONI I KEC. MALIGANO KAB. MUNA
KONTRAKTOR PELAKSANA :
CV. ALGROUP MANDIRI
PROGRAM :
ASAN DAN PEMBANGUNAN PERMUKIMAN
I PERMUKIMAN TRANSMIGRASI (PKP2T)
PEKERJAAN :
UNAN BRONJONG PENAHAN TEBING
NOMOR KONTRAK :
11/KTRK/PKP2T/III/2019
NILAI KONTRAK :
Rp. 1.002.877.735,-
LOKASI :
RONI I KEC. MALIGANO KAB. MUNA
KONTRAKTOR PELAKSANA :
V. ALGROUP MANDIRI