1 Type P1 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 5.90 m' Rp 126,000 Rp 743,400
BL132 Frame Aluminium Coklat Uk. 4 x 7.5 Fin. Powder Coating 7.60 m' Rp 82,845 Rp 629,622
KU2 Kaca polos tb. 5 mm 2.04 m² Rp 112,376 Rp 229,248
BT252 Handle Pintu Stainless 2.00 Buah Rp 112,665 Rp 225,330
PP11 Kunci tanam (808) 2.00 bj Rp 12,600 Rp 25,200
PP5 Engsel pintu 6.00 bh Rp 31,500 Rp 189,000
PP15 Door closer 2.00 bh Rp 94,500 Rp 189,000
KU5 Sealant isi min 340 gr 4.16 tube Rp 73,500 Rp 305,973
UP Upah Pemasangan 1.00 Ls Rp 253,677 Rp 253,677
Sub Jumlah Rp 2,790,450
Jumlah Total Rp 2,790,450
2 Type P2 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 5.10 m' Rp 126,000 Rp 642,600
BL132 Frame Aluminium Coklat Uk. 4 x 7.5 Fin. Powder Coating 6.00 m' Rp 82,845 Rp 497,070
KU2 Kaca polos tb. 5 mm 0.43 m² Rp 112,376 Rp 48,547
BT252 Handle Pintu Stainless 1.00 Buah Rp 112,665 Rp 112,665
PP11 Kunci tanam (808) 1.00 bj Rp 12,600 Rp 12,600
BL122 Pintu Swing Ganda BRC / PMG Uk. 1.2 x 3m 1.00 Unit Rp 986,816 Rp 986,816
BT255 Stiker Sandblast Polos Putih Es 0.43 m2 Rp 95,000 Rp 41,040
KU5 Sealant isi min 340 gr 1.90 tube Rp 73,500 Rp 139,683
UP Upah Pemasangan 1.00 Ls Rp 248,102 Rp 248,102
Sub Jumlah Rp 2,729,123
Jumlah Total Rp 2,729,123
3 Type P3 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 5.00 m' Rp 126,000 Rp 630,000
BL132 Frame Aluminium Coklat Uk. 4 x 7.5 Fin. Powder Coating 5.80 m' Rp 82,845 Rp 480,501
KU2 Kaca polos tb. 5 mm 0.17 m² Rp 112,376 Rp 19,104
BT255 Stiker Sandblast Polos Putih Es 0.17 m2 Rp 95,000 Rp 16,150
KU5 Sealant isi min 340 gr 0.95 tube Rp 73,500 Rp 69,842
BT252 Handle Pintu Stainless 1.00 Buah Rp 112,665 Rp 112,665
PP13 Kunci tanam kamar mandi 1.00 bh Rp 36,750 Rp 36,750
PP5 Engsel pintu 3.00 bh Rp 31,500 Rp 94,500
BT12 Kisi Aluminium 2.50 m Rp 82,845 Rp 207,113
UP Upah Pemasangan 1.00 Ls Rp 166,662 Rp 166,662
Sub Jumlah Rp 1,833,287
Jumlah Total Rp 1,833,287
4 Type P4 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 6.60 m' Rp 126,000 Rp 831,600
BL132 Frame Aluminium Coklat Uk. 4 x 7.5 Fin. Powder Coating 5.80 m' Rp 82,845 Rp 480,501
KU2 Kaca polos tb. 5 mm 0.38 m² Rp 112,376 Rp 42,703
BT255 Stiker Sandblast Polos Putih Es 0.17 m2 Rp 95,000 Rp 16,150
KU5 Sealant isi min 340 gr 1.86 tube Rp 73,500 Rp 136,357
BT252 Handle Pintu Stainless 1.00 Buah Rp 112,665 Rp 112,665
PP13 Kunci tanam kamar mandi 1.00 bh Rp 36,750 Rp 36,750
PP5 Engsel pintu 3.00 bh Rp 31,500 Rp 94,500
ANALISA KUSEN
BT12 Kisi Aluminium 2.50 m Rp 82,845 Rp 207,113
UP Upah Pemasangan 1.00 Ls Rp 195,834 Rp 195,834
Sub Jumlah Rp 2,154,173
Jumlah Total Rp 2,154,173
5 Type P5 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 5.90 m' Rp 126,000 Rp 743,400
BL132 Frame Aluminium Coklat Uk. 4 x 7.5 Fin. Powder Coating 7.60 m' Rp 82,845 Rp 629,622
KU2 Kaca polos tb. 5 mm 2.04 m² Rp 112,376 Rp 229,248
BT252 Handle Pintu Stainless 2.00 Buah Rp 112,665 Rp 225,330
PP11 Kunci tanam (808) 2.00 bj Rp 12,600 Rp 25,200
PP5 Engsel pintu 6.00 bh Rp 31,500 Rp 189,000
PP15 Door closer 2.00 bh Rp 94,500 Rp 189,000
KU5 Sealant isi min 340 gr 4.16 tube Rp 73,500 Rp 305,973
UP Upah Pemasangan 1.00 Ls Rp 253,677 Rp 253,677
Sub Jumlah Rp 2,790,450
Jumlah Total Rp 2,790,450
6 Type P6 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 6.80 m' Rp 126,000 Rp 856,800
BL132 Frame Aluminium Coklat Uk. 4 x 7.5 Fin. Powder Coating 9.40 m' Rp 82,845 Rp 778,743
KU2 Kaca polos tb. 5 mm 1.63 m² Rp 112,376 Rp 182,611
PP5 Engsel pintu 18.00 bh Rp 31,500 Rp 567,000
KU5 Sealant isi min 340 gr 8.14 tube Rp 73,500 Rp 598,643
BT12 Kisi Aluminium 16.50 m Rp 82,845 Rp 1,366,943
UP Upah Pemasangan 1.00 Ls Rp 298,380 Rp 298,380
Sub Jumlah Rp 4,649,119
Jumlah Total Rp 4,649,119
7 Type J1 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 8.94 m' Rp 126,000 Rp 1,126,440
BL132 Frame Aluminium Coklat Uk. 4 x 7.5 Fin. Powder Coating 6.88 m' Rp 82,845 Rp 569,974
KU2 Kaca polos tb. 5 mm 1.44 m² Rp 112,376 Rp 162,361
PP3 Engsel jendela 2.00 bh Rp 15,750 Rp 31,500
PP17 Kunci selot 2.00 bh Rp 73,500 Rp 147,000
PP18 Hak angin 4.00 bj Rp 10,500 Rp 42,000
KU5 Sealant isi min 340 gr 4.63 tube Rp 73,500 Rp 340,561
UP Upah Pemasangan 1.00 Ls Rp 241,984 Rp 241,984
Sub Jumlah Rp 2,661,819
Jumlah Total Rp 2,661,819
8 Type J2 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 24.39 m' Rp 126,000 Rp 3,073,140
BL132 Frame Aluminium Coklat Uk. 4 x 7.5 Fin. Powder Coating 20.72 m' Rp 82,845 Rp 1,716,548
KU2 Kaca polos tb. 5 mm 4.72 m² Rp 112,376 Rp 529,876
PP3 Engsel jendela 6.00 bh Rp 15,750 Rp 94,500
PP17 Kunci selot 6.00 bh Rp 73,500 Rp 441,000
PP18 Hak angin 12.00 bj Rp 10,500 Rp 126,000
KU5 Sealant isi min 340 gr 14.52 tube Rp 73,500 Rp 1,066,914
UP Upah Pemasangan 1.00 Ls Rp 704,798 Rp 704,798
ANALISA KUSEN
Sub Jumlah Rp 7,752,777
Jumlah Total Rp 7,752,777
9 Type J3 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 9.21 m' Rp 126,000 Rp 1,160,460
BL132 Frame Aluminium Coklat Uk. 4 x 7.5 Fin. Powder Coating 7.20 m' Rp 82,845 Rp 596,484
KU2 Kaca polos tb. 5 mm 1.52 m² Rp 112,376 Rp 170,812
PP3 Engsel jendela 2.00 bh Rp 15,750 Rp 31,500
PP17 Kunci selot 2.00 bh Rp 73,500 Rp 147,000
PP18 Hak angin 4.00 bj Rp 10,500 Rp 42,000
KU5 Sealant isi min 340 gr 4.83 tube Rp 73,500 Rp 355,195
UP Upah Pemasangan 1.00 Ls Rp 250,345 Rp 250,345
Sub Jumlah Rp 2,753,796
Jumlah Total Rp 2,753,796
10 Type J4 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 4.60 m' Rp 126,000 Rp 579,600
KU2 Kaca polos tb. 5 mm 0.48 m² Rp 112,376 Rp 53,379
KU5 Sealant isi min 340 gr 1.95 tube Rp 73,500 Rp 143,009
UP Upah Pemasangan 1.00 Ls Rp 77,599 Rp 77,599
Sub Jumlah Rp 853,587
Jumlah Total Rp 853,587
11 Type J5 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 22.75 m' Rp 126,000 Rp 2,866,500
BL132 Frame Aluminium Coklat Uk. 4 x 7.5 Fin. Powder Coating 20.64 m' Rp 82,845 Rp 1,709,921
KU2 Kaca polos tb. 5 mm 2.40 m² Rp 112,376 Rp 269,703
PP3 Engsel jendela 6.00 bh Rp 15,750 Rp 94,500
PP17 Kunci selot 6.00 bh Rp 73,500 Rp 441,000
PP18 Hak angin 12.00 bj Rp 10,500 Rp 126,000
KU5 Sealant isi min 340 gr 8.52 tube Rp 73,500 Rp 626,579
UP Upah Pemasangan 1.00 Ls Rp 613,420 Rp 613,420
Sub Jumlah Rp 6,747,623
Jumlah Total Rp 6,747,623
12 Type J6 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 22.96 m' Rp 126,000 Rp 2,892,960
KU2 Kaca polos tb. 5 mm 5.54 m² Rp 112,376 Rp 623,014
KU5 Sealant isi min 340 gr 8.86 tube Rp 73,500 Rp 651,190
BT12 Kisi Aluminium 45.05 m Rp 82,845 Rp 3,732,167
UP Upah Pemasangan 1.00 Ls Rp 789,933 Rp 789,933
Sub Jumlah Rp 8,689,264
Jumlah Total Rp 8,689,264
13 Type J7 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 9.37 m' Rp 126,000 Rp 1,180,620
KU2 Kaca polos tb. 5 mm 1.21 m² Rp 112,376 Rp 135,638
KU5 Sealant isi min 340 gr 5.13 tube Rp 73,500 Rp 377,145
UP Upah Pemasangan 1.00 Ls Rp 169,340 Rp 169,340
Sub Jumlah Rp 1,862,743
ANALISA KUSEN
Jumlah Total Rp 1,862,743
14 Type J8 Unit
BL131 Kusen Aluminium Coklat Uk. 4 x 7.5 Profil 4" Fin. Powder Coatiing 22.90 m' Rp 126,000 Rp 2,885,400
KU2 Kaca polos tb. 5 mm 2.04 m² Rp 112,376 Rp 229,248
KU5 Sealant isi min 340 gr 7.24 tube Rp 73,500 Rp 532,127
BT12 Kisi Aluminium 82.65 m Rp 82,845 Rp 6,847,139
UP Upah Pemasangan 1.00 Ls Rp 1,049,391 Rp 1,049,391
Sub Jumlah Rp 11,543,305
Jumlah Total Rp 11,543,305
18 Type CW Unit
KU12 Kaca stopsol tebal 8mm 1.10 m2 Rp 506,048 Rp 556,652
KU5 Sealant isi min 340 gr 4.43 tube Rp 73,500 Rp 325,928
Aluminium Mullion 2mm 1.14 Btg Rp 350,000 Rp 397,833
Aluminium Transoms 0.58 Btg Rp 198,000 Rp 115,500
Skrup 1.19 kg Rp 13,601 Rp 16,233
omega 0.84 Btg Rp 136,500 Rp 114,039
Karet 9.80 m' Rp 4,500 Rp 44,100
backrod 9.80 m' Rp 3,750 Rp 36,750
spigot 9.80 m' Rp 7,500 Rp 73,500
UP Upah Pemasangan 1.00 Ls Rp 168,054 Rp 168,054
Sub Jumlah Rp 1,848,589
Jumlah Total Rp 1,848,589
ANALISA HARGA PEKERJAAN TAMBAHAN
KODE URAIAN SATUAN KOEFISIEN HARSAT JUMLAH
0 1 2 3 4 5=3x4
A TENAGA
L.01 Pekerja OH 0.76 Rp 71,000.00 Rp 53,960.00
L.02.4 Tukang besi/besi beton OH 0.76 Rp 88,000.00 Rp 66,880.00
L.03 Kepala tukang OH 0.08 Rp 99,000.00 Rp 7,524.00
L.04 Mandor OH 0.04 Rp 94,000.00 Rp 3,572.00
B BAHAN
BB72 Reng 0.43 m' 3.33 Rp 8,749.65 Rp 29,165.50
C PERALATAN
Peralatan Ls 1.00 Rp 2,916.55 Rp 2,916.55
A TENAGA
L.01 Pekerja OH 0.20 Rp 71,000.00 Rp 14,200.00
L.02.2 Tukang batu/tembok OH 0.10 Rp 88,000.00 Rp 8,800.00
L.02.5 Tukang cat/pelitur OH 0.06 Rp 88,000.00 Rp 5,544.00
L.03 Kepala tukang OH 0.01 Rp 99,000.00 Rp 990.00
L.04 Mandor OH 0.01 Rp 94,000.00 Rp 940.00
B BAHAN
Pre Treatment/Cleaning m2 1.00 Rp 4,725.00 Rp 4,725.00
LD33 Waterproofing Kg 1.00 Rp 47,250.00 Rp 47,250.00
BPS20 Semen PC (Portland Cement) / Semen Gresik (50 Kg) kg 11.50 Rp 1,312.50 Rp 15,093.75
BPS15 Pasir pasang m³ 0.04 Rp 157,500.00 Rp 6,300.00
C PERALATAN
P27 Kuas bh 0.25 Rp 21,000.00 Rp 5,250.00
Jumlah Rp 373,137.81
Overhead & Profit (Contoh 15 %) 0.15 Rp 55,970.67
Harga Satuan Pekerjaan Rp 429,108.48
Jumlah Rp 415,747.81
Overhead & Profit (Contoh 15 %) 0.15 Rp 62,362.17
Harga Satuan Pekerjaan Rp 478,109.98
Jumlah Rp 165,880.00
Overhead & Profit (Contoh 15 %) 0.15 Rp 24,882.00
Harga Satuan Pekerjaan Rp 190,762.00
Jumlah Rp 719,000.00
Overhead & Profit (Contoh 15 %) 0.15 Rp 107,850.00
Harga Satuan Pekerjaan Rp 826,850.00
Jumlah Rp 3,222,725.00
Overhead & Profit (Contoh 15 %) 0.15 Rp 483,408.75
Harga Satuan Pekerjaan Rp 3,706,133.75
Jumlah Rp 193,326.00
Overhead & Profit (Contoh 15 %) 0.15 Rp 28,998.90
Harga Satuan Pekerjaan Rp 222,324.90
HARGA DASAR BAHAN BANGUNAN KABUPATEN JEMBER TAHUN ANGGARAN 2019
Di Setujui Surabaya,
PONDOK PESANTREN PT. ANSILA CIPTA KONSULTAN
NURUL WAJID
Gode Mas, ST
Direktur
RENCANA ANGGARAN BIAYA ( RAB )
A PEKERJAAN BONGKARAN
1 Bongkaran Atap 73.05 m2 Rp 296,179.63 Rp 21,634,701.35
2 Bongkaran Beton Kolom 1.50 m3 Rp 1,160,715.70 Rp 1,741,073.55
3 Bongkaran Dinding 130.50 m2 Rp 580,357.85 Rp 75,736,699.43
Rp 99,112,474.32
B PEKERJAAN PERSIAPAN
1 Pemasangan Bowplank 18.00 m' Rp 125,064.86 Rp 2,251,167.49
Rp 2,251,167.49
C PEKERJAAN PONDASI
1 Galian Pondasi 70.00 m3 Rp 63,940.00 Rp 4,475,800.00
2 Pondasi Setempat (Siklop) 2.95 m3 Rp 2,262,473.42 Rp 6,674,296.58
3 Pekerjaan Anstamping 12.00 m3 Rp 431,101.10 Rp 5,173,213.18
4 Pekerjaan Batu Kali 44.00 m3 Rp 742,204.10 Rp 32,656,980.30
5 Pekerjaan Sloof 2.34 m3 Rp 1,683,116.80 Rp 3,938,493.31
6 Urugan Kembali Galian Tanah 28.70 m3 Rp 46,230.00 Rp 1,326,801.00
Rp 54,245,584.37
D PEKERJAAN KOLOM DAN DINDING
1 Pekerjaan Kolom 2.66 m3 Rp 1,713,634.78 Rp 4,565,123.04
2 Pekerjaan Dinding 190.50 m2 Rp 108,572.22 Rp 20,683,007.67
3 Plester Dinding 381.00 m2 Rp 58,907.03 Rp 22,443,576.53
4 Acian Dinding 381.00 m2 Rp 33,574.97 Rp 12,792,063.09
Rp 60,483,770.33
E PEKERJAAN BALOK DAN PLAT
1 Pekerjaan Balok 4.68 m3 Rp 1,687,940.51 Rp 7,899,561.60
2 Pekerjaan Plat 12.60 m3 Rp 2,054,637.68 Rp 25,888,434.72
Rp 33,787,996.32
F PEKERJAAN LANTAI
2 Pemasangan Keramik 73.29 m2 Rp 157,518.38 Rp 11,545,230.54
Rp 11,545,230.54
G PEKERJAAN KUSEN
1 Pemasangan Kusen Pintu 12.50 m2 Rp 375,549.52 Rp 4,694,369.00
2 Pemasangan Daun Pintu 12.50 m2 Rp 739,070.50 Rp 9,238,381.25
3 Pemasangan Kusen Jendela 11.60 m2 Rp 1,698,835.04 Rp 19,706,486.45
4 Pemasangan Engsel Pintu 10.00 bh Rp 54,445.60 Rp 544,456.00
5 Pemasangan Kunci Pintu 5.00 bh Rp 105,949.50 Rp 529,747.50
6 Pemasangan Engsel Jendela 20.00 bh Rp 21,239.35 Rp 424,787.00
7 Pemasangan Spring Knip Jendela 10.00 bh Rp 29,241.05 Rp 292,410.50
Rp 35,430,637.70
H PEKERJAAN INSTALASI LISTRIK
1 Pekerjaan Pemasang Lampu 8.00 ttk Rp 232,787.31 Rp 1,862,298.50
2 Pemasangan meteran 1.00 bh Rp 178,298.88 Rp 178,298.88
3 Pemasangan Stop Kontak 10.00 bh Rp 110,256.25 Rp 1,102,562.50
Rp 3,143,159.88
RENCANA ANGGARAN BIAYA ( RAB )
A PEKERJAAN BONGKARAN
1 Bongkaran Atap 140.00 m2 Rp 296,179.63 Rp
2 Bongkaran Keramik Lt 1 96.00 m2 Rp 252,797.03 Rp
3 Bongkaran Keramik Lt 2 96.00 m2 Rp 252,797.03 Rp
4 Bongkaran Kusen Pintu 12.50 m2 Rp 375,549.52 Rp
5 Bongkaran Kusen Jendela 11.60 m2 Rp 375,549.52 Rp
Rp
B PEKERJAAN ATAP
1 Pekerjaan Kerangka Atap 140.00 m2 Rp 232,417.59 Rp
2 Penutup Atap 140.00 m2 Rp 163,494.35 Rp
3 Bumbungan Atap 12.00 m1 Rp 118,545.45 Rp
Rp
C PEKERJAAN KUSEN
1 Pekerjaan Kusen Pintu 12.00 m2 Rp 2,790,449.64 Rp
2 Pekerjaan Kusen Jendela 1 12.96 m2 Rp 2,661,819.48 Rp
3 Pekerjaan Kusen jendela 2 6.00 m2 Rp 853,586.55 Rp
Rp
D PEKERJAAN LANTAI
1 Pemasangan Keramik Lantai 1 uk 40x40 96.00 m2 Rp 252,797.03 Rp
2 Pemasangan Keramik Lantai 2 uk 40x40 96.00 m2 Rp 252,797.03 Rp
Rp
E PEKERJAAN CAT DINDING
1 Pengecatan Dinding Lt1 272.57 m2 Rp 27,964.55 Rp
2 Pengecatan Dinding Lt2 284.00 m3 Rp 27,964.55 Rp
Rp
E PEKERJAAN PLAFOND
1 Pemasangan Plafond Lantai 1 72.00 m2 Rp 47,857.25 Rp
2 Pemasangan Plafond Lantai 2 72.00 m2 Rp 47,857.25 Rp
Rp
N BIAYA ( RAB )
JUMLAH HARGA
140
41,465,147.50
24,268,514.40 96
24,268,514.40
4,694,369.00
4,356,374.43
99,052,919.73
32,538,462.25
22,889,209.00
1,422,545.40
56,850,216.65
300,000,018.11
33,485,395.69
34,497,180.48
5,121,519.27
73,104,095.44
24,268,514.40
24,268,514.40
48,537,028.80
7,622,381.29
7,941,932.20
15,564,313.49 48
32
3,445,722.00 160
3,445,722.00 135.04
6,891,444.00 270.08
142.00
284
REKAPITULASI RENCANA ANGGARAN BIAYA ( RAB )
Di Setujui Surabaya,
MADRASAH IBTIDAIYAH CV. GADING JAYA CONSULTAN
DARUSSALAM
Herwinda Istisansu
Direktur
ANALISA HARGA SATUAN DAN UPAH
Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2 PB : 3 Kr dan 40% batu belah
No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A TENAGA
Pekerja L.01 OH 3.400 71000
Tukang batu/tembok L.02.2 OH 0.850 88000
Kepala tukang L.03 OH 0.085 99000
Mandor L.04 OH 0.170 94000
JUMLAH TENAGA KERJA
B BAHAN
Batu pecah / belah 15/20 BPS2 m³ 0.480 194,250.00
Semen PC (Portland Cement) / Semen Gresik (50 Kg)BPS20 Kg 194.000 1,312.50
Pasir cor / beton BPS14 m³ 0.312 157,500.00
Batu kerikil beton / koral beton BPS11 m³ 0.468 220500
Besi beton polos BL2 Kg 126.000 8662.5
Kawat ikat beton BL49 Kg 1.800 19,499.55
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15 %) 15% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 atap jurai rangka atap baja canai dingin profil C75
No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.760 71,000.00
Tukang besi/besi beton L.02.4 OH 0.760 88,000.00
Kepala tukang L.03 OH 0.076 99,000.00
Mandor L.04 OH 0.038 94,000.00
JUMLAH TENAGA KERJA
B BAHAN
Baja ringan canai dingin C75 BT140 kg 4.050 15,750.00
JUMLAH HARGA BAHAN
C PERALATAN
Peralatan % 10% x Rangka
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 atap jurai rangka atap baja canai dingin profil C75
No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.760 71000
Tukang besi/besi beton L.02.4 OH 0.760 88000
Kepala tukang L.03 OH 0.076 99000
Mandor L.04 OH 0.038 94000
JUMLAH TENAGA KERJA
B BAHAN
Baja ringan canai dingin C75 BT140 kg 4.050 15750
JUMLAH HARGA BAHAN
C PERALATAN
Peralatan % 10% x Rangka
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP
No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.300 71000
Tukang batu/tembok L.02.2 OH 0.100 88000
Kepala tukang L.03 OH 0.010 99000
Mandor L.04 OH 0.015 94000
JUMLAH TENAGA KERJA
B BAHAN
Batu bata merah BPS1 buah 70.000 525
Semen PC (Portland Cement) / Semen Gresik (50 Kg)BPS20 Kg 14.370 1312.5
Pasir pasang BPS15 m³ 0.040 157500
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 acian
No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.200 71000
Tukang batu/tembok L.02.2 OH 0.100 88000
Kepala tukang L.03 OH 0.010 99000
Mandor L.04 OH 0.010 94000
JUMLAH TENAGA KERJA
B BAHAN
Semen PC ( 40 kg ) BPS22 Kg 3.250 1312.5
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm & 6 mm
No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.100 71000
Tukang kayu L.02.3 OH 0.100 88000
Kepala tukang L.03 OH 0.010 99000
Mandor L.04 OH 0.005 94000
JUMLAH TENAGA KERJA
B BAHAN
Triplek tebal 4 mm (0.90 x 2.00) BB46 Lembar 0.375 63420
Paku triplek BP3 kg 0.030 15750
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II
No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A TENAGA
Pekerja L.01 OH 1.000 71000
Tukang kayu L.02.3 OH 3.000 88000
Kepala tukang L.03 OH 0.300 99000
Mandor L.04 OH 0.050 94000
JUMLAH TENAGA KERJA
B BAHAN
Kayu kelas I (Papan) BK4 m³ 0.064 17207583.75
Lem kayu P21 Kg 0.500 13125
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm)
No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.700 71000
Tukang kayu L.02.3 OH 2.100 88000
Kepala tukang L.03 OH 0.210 99000
Mandor L.04 OH 0.035 94000
JUMLAH TENAGA KERJA
B BAHAN
Kayu kelas II (Papan) BK6 m³ 0.025 9298800
Paku biasa 2"- 5" BP4 kg 0.030 15750
Lem kayu P21 kg 0.500 13125
Plywood tebal 4 mm (1.22 x 2.44) BB44 Lembar 1.000 144585
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) Interior
No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A TENAGA
Pekerja L.01 OH 0.020 71000
Tukang cat/pelitur L.02.5 OH 0.063 88000
Kepala tukang L.03 OH 0.006 99000
Mandor L.04 OH 0.003 94000
JUMLAH TENAGA KERJA
B BAHAN
Plamur tembok P18 Kg 0.100 10500
Cat dasar BT85 Kg 0.100 31500
Cat tembok (premium) Mowilex P31 Kg 0.260 105000
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
DANA HIBAH
Rp 946,714.00
Rp 62,604.00
Rp 1,009,318.00
Rp -
Rp -
Rp 1,009,318.00
Rp 151,397.70
Rp 1,160,715.70
Rp 53,250.00
Rp 2,350.00
Rp 55,600.00
Rp -
Rp -
Rp 55,600.00
Rp 8,340.00
Rp 63,940.00
Rp 35,500.00
Rp 4,700.00
Rp 40,200.00
Rp -
Rp -
Rp 40,200.00
Rp 6,030.00
Rp 46,230.00
Rp 17,750.00
Rp 2,350.00
Rp 20,100.00
Rp 142,254.00
Rp 142,254.00
Rp -
Rp 162,354.00
Rp 24,353.10
Rp 186,707.10
Rp 106,500.00
Rp 66,000.00
Rp 7,425.00
Rp 7,050.00
Rp 186,975.00
Rp 233,100.00
Rp 80,062.50
Rp 67,767.37
Rp 77,490.00
Rp 458,419.87
Rp -
Rp 645,394.87
Rp 96,809.23
Rp 742,204.10
Rp 55,380.00
Rp 34,320.00
Rp 3,861.00
Rp 3,666.00
Rp 97,227.00
Rp 233,100.00
Rp 44,543.52
Rp 277,643.52
Rp -
Rp 374,870.52
Rp 56,230.58
Rp 431,101.10
Rp 241,400.00
Rp 74,800.00
Rp 8,415.00
Rp 15,980.00
Rp 340,595.00
Rp 93,240.00
Rp 254,625.00
Rp 49,140.00
Rp 103,194.00
Rp 1,091,475.00
Rp 35,099.19
Rp 1,626,773.19
Rp -
Rp 1,967,368.19
Rp 295,105.23
Rp 2,262,473.42
Rp 117,150.00
Rp 24,200.00
Rp 2,772.00
Rp 7,802.00
Rp 151,924.00
Rp 542,062.50
Rp 76,610.46
Rp 166,768.10
Rp 101,587.50
Rp 887,028.56
Rp -
Rp 1,038,952.56
Rp 155,842.88
Rp 1,194,795.44
Rp 4,970.00
Rp 6,160.00
Rp 693.00
Rp 376.00
Rp 12,199.00
Rp 115,762.50
Rp 2,924.93
Rp 118,687.43
Rp -
Rp 130,886.43
Rp 19,632.96
Rp 150,519.40
Rp 36,920.00
Rp 22,880.00
Rp 2,574.00
Rp 2,444.00
Rp 64,818.00
Rp 220,995.34
Rp 4,725.00
Rp 3,202.50
Rp 228,922.84
Rp -
Rp 293,740.84
Rp 44,061.13
Rp 337,801.96
Rp 46,860.00
Rp 29,040.00
Rp 3,267.00
Rp 3,102.00
Rp 82,269.00
Rp 196,440.30
Rp 6,300.00
Rp 6,405.00
Rp 115,421.12
Rp 105,252.00
Rp 46,200.00
Rp 476,018.42
Rp 238,009.21
Rp -
Rp 320,278.21
Rp 48,041.73
Rp 368,319.94
Rp 46,860.00
Rp 29,040.00
Rp 3,267.00
Rp 3,102.00
Rp 82,269.00
Rp 196,440.30
Rp 6,300.00
Rp 6,405.00
Rp 138,505.34
Rp 105,252.00
Rp 46,200.00
Rp 499,102.64
Rp 249,551.32
Rp -
Rp 331,820.32
Rp 49,773.05
Rp 381,593.37
Rp 46,860.00
Rp 29,040.00
Rp 3,267.00
Rp 3,102.00
Rp 82,269.00
Rp 196,440.30
Rp 6,300.00
Rp 6,405.00
Rp 115,421.12
Rp 105,252.00
Rp 138,600.00
Rp 568,418.42
Rp -
Rp 650,687.42
Rp 97,603.11
Rp 748,290.53
Rp 53,960.00
Rp 66,880.00
Rp 7,524.00
Rp 3,572.00
Rp 131,936.00
Rp 63,787.50
Rp 63,787.50
Rp 6,378.75
Rp 6,378.75
Rp 202,102.25
Rp 30,315.34
Rp 232,417.59
Rp 53,960.00
Rp 66,880.00
Rp 7,524.00
Rp 3,572.00
Rp 131,936.00
Rp 63,787.50
Rp 63,787.50
Rp 6,378.75
Rp 6,378.75
Rp 202,102.25
Rp 30,315.34
Rp 232,417.59
Rp 21,300.00
Rp 8,800.00
Rp 990.00
Rp 1,410.00
Rp 32,500.00
Rp 36,750.00
Rp 18,860.63
Rp 6,300.00
Rp 61,910.63
Rp -
Rp 94,410.63
Rp 14,161.59
Rp 108,572.22
Rp 21,300.00
Rp 13,200.00
Rp 1,485.00
Rp 1,410.00
Rp 37,395.00
Rp 10,206.00
Rp 3,622.50
Rp 13,828.50
Rp -
Rp 51,223.50
Rp 7,683.53
Rp 58,907.03
Rp 14,200.00
Rp 8,800.00
Rp 990.00
Rp 940.00
Rp 24,930.00
Rp 4,265.63
Rp 4,265.63
Rp -
Rp 29,195.63
Rp 4,379.34
Rp 33,574.97
Rp 49,700.00
Rp 30,800.00
Rp 3,465.00
Rp 3,290.00
Rp 87,255.00
Rp 22,680.00
Rp 13,125.00
Rp 7,087.50
Rp 6,825.00
Rp 49,717.50
Rp 136,972.50
Rp 20,545.88
Rp 157,518.38
Rp 18,460.00
Rp 11,440.00
Rp 1,287.00
Rp 1,222.00
Rp 32,409.00
Rp 146,727.00
Rp 13,125.00
Rp 20,475.00
Rp 7,087.50
Rp 187,414.50
Rp -
Rp 219,823.50
Rp 32,973.53
Rp 252,797.03
Rp 2,130.00
Rp 6,160.00
Rp 693.00
Rp 376.00
Rp 9,359.00
Rp 20,212.50
Rp 157.50
Rp 20,370.00
Rp -
Rp 29,729.00
Rp 4,459.35
Rp 34,188.35
Rp 7,100.00
Rp 8,800.00
Rp 990.00
Rp 470.00
Rp 17,360.00
Rp 23,782.50
Rp 472.50
Rp 24,255.00
Rp -
Rp 41,615.00
Rp 6,242.25
Rp 47,857.25
Rp 10,650.00
Rp 6,600.00
Rp 792.00
Rp 752.00
Rp 18,794.00
Rp 123,375.00
Rp 123,375.00
Rp -
Rp 142,169.00
Rp 21,325.35
Rp 163,494.35
Rp 28,400.00
Rp 17,600.00
Rp 1,980.00
Rp 188.00
Rp 48,168.00
Rp 39,375.00
Rp 10,500.00
Rp 5,040.00
Rp 54,915.00
Rp -
Rp 103,083.00
Rp 15,462.45
Rp 118,545.45
Rp 24,850.00
Rp 92,400.00
Rp 10,395.00
Rp 1,692.00
Rp 129,337.00
Rp 196,440.30
Rp 787.50
Rp 197,227.80
Rp -
Rp 326,564.80
Rp 48,984.72
Rp 375,549.52
Rp 71,000.00
Rp 264,000.00
Rp 29,700.00
Rp 4,700.00
Rp 369,400.00
Rp 1,101,285.36
Rp 6,562.50
Rp 1,107,847.86
Rp -
Rp 1,477,247.86
Rp 221,587.18
Rp 1,698,835.04
Rp 49,700.00
Rp 184,800.00
Rp 20,790.00
Rp 3,290.00
Rp 258,580.00
Rp 232,470.00
Rp 472.50
Rp 6,562.50
Rp 144,585.00
Rp 384,090.00
Rp -
Rp 642,670.00
Rp 96,400.50
Rp 739,070.50
Rp 7,100.00
Rp 8,800.00
Rp 990.00
Rp 470.00
Rp 17,360.00
Rp 66,150.00
Rp 170,100.00
Rp 3,937.50
Rp 240,187.50
Rp 257,547.50
Rp 38,632.13
Rp 296,179.63
Rp 7,100.00
Rp 17,600.00
Rp 1,980.00
Rp 470.00
Rp 27,150.00
Rp 102,286.80
Rp 1,575.00
Rp 103,861.80
Rp 131,011.80
Rp 19,651.77
Rp 150,663.57
Rp 1,065.00
Rp 13,200.00
Rp 1,485.00
Rp 94.00
Rp 15,844.00
Rp 31,500.00
Rp 31,500.00
Rp 47,344.00
Rp 7,101.60
Rp 54,445.60
Rp 10,650.00
Rp 282.00
Rp 10,932.00
Rp 1,050.00
Rp 1,050.00
Rp 11,982.00
Rp 1,797.30
Rp 13,779.30
Rp 1,988.00
Rp 3,696.00
Rp 396.00
Rp 282.00
Rp 6,362.00
Rp 3,780.00
Rp 14,175.00
Rp 17,955.00
Rp 24,317.00
Rp 3,647.55
Rp 27,964.55
Rp 1,420.00
Rp 5,544.00
Rp 594.00
Rp 282.00
Rp 7,840.00
Rp 1,050.00
Rp 3,150.00
Rp 27,300.00
Rp 31,500.00
Rp 39,340.00
Rp 5,901.00
Rp 45,241.00
Rp 88,000.00
Rp 88,000.00
Rp 7,875.00
Rp 2,415.00
Rp 1,050.00
Rp 6,825.00
Rp 48,877.50
Rp 67,042.50
Rp -
Rp 155,042.50
Rp 23,256.38
Rp 178,298.88
Pembongkaran 1 m3 beton bertulang PPE13
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 13.334 71,000.00 Rp 946,714.00
Mandor L.04 OH 0.666 94,000.00 Rp 62,604.00
JUMLAH TENAGA KERJA Rp 1,009,318.00
B BAHAN
JUMLAH HARGA BAHAN Rp -
C PERALATAN
JUMLAH HARGA ALAT Rp -
PPE13 D Jumlah (A+B+C) Rp 1,009,318.00
E Overhead & Profit (Contoh 15 %) 15% x D (maksimum) Rp 151,397.70
F Harga Satuan Pekerjaan (D+E) Rp 1,160,715.70
Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2 PB : 3 Kr dan 40% batu belah PPO10
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 3.400 71,000.00 Rp 241,400.00
Tukang batu/tembok L.02.2 OH 0.850 88,000.00 Rp 74,800.00
Kepala tukang L.03 OH 0.085 99,000.00 Rp 8,415.00
Mandor L.04 OH 0.170 94,000.00 Rp 15,980.00
JUMLAH TENAGA KERJA Rp 340,595.00
B BAHAN
Batu pecah / belah 15/20 BPS2 m³ 0.480 194,250.00 Rp 93,240.00
Semen PC (Portland Cement) / Semen Gresik (50 Kg) BPS20 Kg 194.000 1,312.50 Rp 254,625.00
Pasir cor / beton BPS14 m³ 0.312 157,500.00 Rp 49,140.00
Batu kerikil beton / koral beton BPS11 m³ 0.468 220,500.00 Rp 103,194.00
Besi beton polos BL2 Kg 126.000 8,662.50 Rp 1,091,475.00