CODE AKTIVITAS PENDAHUL LANJUTAN NORMAL CEPAT

U WAKTU $ WAKTU $
A PROSPEKSI A B,C 2 1500 1 2000
B EKSPLORASI B D,E 5 3000 3 6000
C PERENCANAA C F 2 2600 1 4000
N TAMBANG
D KONTRUKSI D G 2 2300 1 4000
E EKSPLOITASI E H 10 6000 5 9000
F PENGOLAHAN F H 10 3000 5 5000
G PEMASARAN G H 5 1300 2 2500
H REKLAMASI H 4 7600 3 10200

Degan biaya tak langsung: Tahun 1 – Tahun 10 = $1000

Tahun 11 – Tahun Berikutnya = $500

A. JARINGAN KERJA
B. JALUR KRITIS
C. WAKTU PENYELESAIAIN DAN TOTAL BIAYA NORMAL
D. WAKTU DAN BIAYA OPTIMAL
E. GANT CHART

D G

B
E H
A

C F
COD AKTIVITAS PENDAHULU LANJUTA NORMAL CEPAT A B C
E N WAKTU $ WAKT $
U
A PROSPEKSI A B,C 2 1500 1 2000 1 500 500
B EKSPLORASI B D,E 5 3000 3 6000 2 3000 1500
C PERENCANAAN C F 2 2600 1 4000 1 1400 1400
TAMBANG
D KONTRUKSI D G 2 2300 1 4000 1 1700 1700
E EKSPLOITASI E H 10 6000 5 9000 5 3000 600
F PENGOLAHAN F H 10 3000 5 5000 5 2000 400
G PEMASARAN G H 5 1300 2 2500 3 1200 500
H REKLAMASI H 4 7600 3 10200 1 2600 2600

Penyelesaian pada Kertas HVS