REKAPITULASI TOTAL ANGGARAN BIAYA :

PEKERJAAN PEMBANGUNAN GEDUNG PERKULIAHAN DI KAMPUS UPI DI DAERAH


(UPI KAMPUS PURWAKARTA TAHAP II)

LOKASI : JL. VETERAN NO. 8 PURWAKARTA - JAWA BARAT

I. PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG --------------------------------------------------------------------- Rp. 265,965,000.00

II. PEKERJAAN STRUKTUR --------------------------------------------------------------------- Rp. 4,345,688,139.58


II.1 PEKERJAAN STRUKTUR ELV. +0.000 s/d +4.200 ------------------------------ Rp. 10,509,775.38
II.2 PEKERJAAN STRUKTUR ELV. +4.200 s/d +8.400 ------------------------------ Rp. 10,509,775.38
II.3 PEKERJAAN STRUKTUR ELV. +8.400 s/d +12.600 ------------------------------ Rp. 2,130,218,225.13
II.4 PEKERJAAN STRUKTUR ELV. +12.600 s/d +16.800 ------------------------------ Rp. 1,534,330,903.22
II.5 PEKERJAAN STRUKTUR ELV. +16.800 s/d +18.500 ------------------------------ Rp. 117,473,967.08
II.6 PEKERJAAN STRUKTUR ATAP ------------------------------ Rp. 542,645,493.38

III. PEKERJAAN ARSITEKTUR --------------------------------------------------------------------- Rp. 5,586,570,219.30


III.1 PEKERJAAN ARSITEKTUR LANTAI 1 ------------------------------ Rp. 1,183,750,791.19
III.2 PEKERJAAN ARSITEKTUR LANTAI 2 ------------------------------ Rp. 1,167,869,439.36
III.3 PEKERJAAN ARSITEKTUR LANTAI 3 ------------------------------ Rp. 1,109,473,978.78
III.4 PEKERJAAN ARSITEKTUR LANTAI 4 ------------------------------ Rp. 1,108,429,941.25
III.6 PEKERJAAN ARSITEKTUR LANTAI ROOFTOP ------------------------------ Rp. 1,017,046,068.72

IV. PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING --------------------------------------------------------------------- Rp. 5,165,287,326.27


IV.1 PEKERJAAN PLUMBING ------------------------------ Rp. 538,615,282.60
IV.2 PEKERJAAN PEMADAMAN KEBAKARAN ------------------------------ Rp. 945,035,093.36
IV.3 PEKERJAAN AIR CONDITIONING ------------------------------ Rp. 1,563,024,650.46
IV.4 PEKERJAAN ELEVATOR ------------------------------ Rp. 1,452,220,000.00
IV.5 PEKERJAAN ELEKTRIKAL ------------------------------ Rp. 666,392,299.86
IV.5.1 BIAYA PENYAMBUNGAN LISTRIK -------------- Rp. 7,000,000.00
IV.5.2 PEKERJAAN PANEL UTAMA DAN TRAFO -------------- Rp. 14,532,293.64
IV.5.3 PEKERJAAN PANEL DISTRIBUSI -------------- Rp. 109,107,322.50
IV.5.4 PEKERJAAN KABEL FEEDER -------------- Rp. 8,544,909.45
IV.5.5 PEKERJAAN RAK KABEL -------------- Rp. 145,186,058.60
IV.5.6 PEKERJAAN PENERANGAN DAN STOP KONTAK D -------------- Rp. 43,043,090.20
IV.5.7 PEKERJAAN TITIK INSTALASI -------------- Rp. 206,466,535.00
IV.5.8 PEKERJAAN PENANGKAL PETIR -------------- Rp. 1,068,669.64
IV.5.9 PEKERJAAN INSTALASI DATA dan BRACKET PROJ -------------- Rp. 32,837.20
IV.5.10 PEKERJAAN FIRE ALARM -------------- Rp. 112,686,357.14
IV.5.11 PEKERJAAN CCTV -------------- Rp. 18,724,226.49

V. PEK. FACADE --------------------------------------------------------------------- Rp. 1,370,912,025.06


VI. PEK. LANDSCAPE --------------------------------------------------------------------- Rp. 293,566,008.75
VII. PEK. TRAFO --------------------------------------------------------------------- Rp. 14,532,293.64

lantai 1
JUMLAH BIAYA KONSTRUKSI . ………………… Rp. 17,042,521,012.60
PPn 10% . ………………… Rp. 1,704,252,101.26
TOTAL BIAYA . ………………… Rp. 18,746,773,113.85
DIBULATKAN . ………………… Rp. 18,746,773,000.00
###
TERBILANG : Dua Puluh Milyar Seratus Tujuh Puluh delapan Juta Enam Ribu Rupiah
###
###
###
PT.BARINDO PRIMA AGUNG

BARLIANTO,SE
Direktur
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME
Rp. Rp.

CATATAN :
Sebelum mengisi harga, kontraktor wajib membaca Dokumen Tender dan Catatan Harga dengan
seksama agar sudah mengetahui kondisi yang di minta.

I. PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG


1 K3 lot 1.00 24,515,000.00 24,515,000.00

Kontraktor wajib mengadakan kotak P3K , alat pemadam kebakaran portable, Asuransi Tenaga
Kerja, Alat Perlindungan Tenaga Kerja guna untuk pencegahan kebakaran. Sesuai dengan
anjuran atau saran dari perusahaan asuransi dan instansi yang berwenang.

2 Pengadaan Listrik Kerja Bln 5.00 15,400,000.00 77,000,000.00

Pengadaan Penerangan sementara/buatan yang dipergunakan oleh kontraktor untuk penerangan


dalam bekerja termasuk pemindahan & perijinan materan PLN (bila digunakan) disediakan oleh
kontraktor. Kabel-kabel peralatan serta lampu & perapihan kembali pada waktu pekerjaan
selesai atas beban kontraktor dan termasuk pengadaan air

3 Mobilisasi atau transportasi peralatan dan bahan + Lift Barang lot 1.00 164,450,000.00 164,450,000.00

Disesuaikan dengan kebutuhan kontraktor, sudah termasuk untuk semua peralatan utama dan
peralatan bantu.

JUMLAH PEKERJAAN PERSIAPAN & PENUNJANG Rp. 265,965,000.00


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME
Rp. Rp.
1 2 3 4 5 6 (5X6)

II.A PEKERJAAN STRUKTUR ELV. +0.000 s/e +4.200


1 Pek. Pas. Balok Separator Lift
- Pek. IWF 200.100.5,5.8 Baja Profil, Merk : eN kg 332.28 20,097.00 6,677,831.16
- Pek. Plat penghubung T.10mm Baja Profil, Merk : eN kg 18.84 20,097.00 378,627.48
- Pek. Vote IWF 200.100.5.8 Baja Profil, Merk : eN kg 38.34 20,097.00 770,518.98
- Baut HTB 4 D19 Baut HTB 4e19 bh 96.00 7,500.00 720,000.00
- Pek. Pengecatan besi Anti Karat Cat zinchromat, setara Meiji m2 80.16 24,486.00 1,962,797.76

JUMLAH PEKERJAAN STRUKTUR ELV. +0.000 s/e +4.200 Rp. 10,509,775.38

II.A PEKERJAAN STRUKTUR ELV. +4.200 s/e +8.400


1 Pek. Pas. Balok Separator Lift
- Pek. IWF 200.100.5,5.8 Baja Profil, Merk : eN kg 332.28 20,097.00 6,677,831.16
- Pek. Plat penghubung T.10mm Baja Profil, Merk : eN kg 18.84 20,097.00 378,627.48
- Pek. Vote IWF 200.100.5.8 Baja Profil, Merk : eN kg 38.34 20,097.00 770,518.98
- Baut HTB 4 D19 Baut HTB 4e19 bh 96.00 7,500.00 720,000.00
- Pek. Pengecatan besi Anti Karat Cat zinchromat, setara Meiji m2 80.16 24,486.00 1,962,797.76

JUMLAH PEKERJAAN STRUKTUR ELV. +4.200 s/e +8.400 Rp. 10,509,775.38

II.A PEKERJAAN STRUKTUR ELV. +8.400 s/d +12.600


1 Pek. Pas. Kolom K1 600x600
- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 29.64 1,011,037.50 29,967,151.50
- Besi tulangan 16 D22 Mutu baja BJTP 40 (ulir) kg 6,270.47 12,734.15 79,849,105.55
- Besi Ø12 - 100 & 150 Mutu baja BJTP 24 (polos) kg 1,576.89 12,734.15 20,080,353.79
- Bekisting m2 197.57 195,453.50 38,615,748.00

2 Pek. Pas. Kolom K2 500x500


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 10.29 1,011,037.50 10,403,575.88
- Besi tulangan 12 D19 Mutu baja BJTP 40 (ulir) kg 1,709.97 12,734.15 21,775,014.48
- Besi Ø12 - 100 & 150 Mutu baja BJTP 24 (polos) kg 653.67 12,734.15 8,323,931.83
- Bekisting m2 82.32 195,453.50 16,089,732.12

3 Pek. Pas. Kolom K4 350x350


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 2.52 1,011,037.50 2,547,814.50
- Besi tulangan 14 D16 Mutu baja BJTP 40 (ulir) kg 688.86 12,734.15 8,772,046.57
- Besi Ø10 - 100 Mutu baja BJTP 24 (polos) kg 177.10 12,734.15 2,255,217.97
- Bekisting m2 28.81 195,453.50 5,631,015.34

4 Pek. Pas. Kolom K5 300x300


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 2.81 1,011,037.50 2,841,015.38
- Besi tulangan 12 D13 Mutu baja BJTP 40 (ulir) kg 506.08 12,734.15 6,444,498.63
- Besi Ø10 - 100 Mutu baja BJTP 24 (polos) kg 229.58 12,734.15 2,923,506.16
- Bekisting m2 37.44 195,453.50 7,317,779.04

5 Pek. Pas. Balok B2 300x650


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.25 1,011,037.50 1,263,796.88
- Besi tulangan 8 D19 Mutu baja BJTP 40 (ulir) kg 130.42 12,734.15 1,660,787.84
- Besi tulangan 6 D19 Mutu baja BJTP 40 (ulir) kg 97.81 12,734.15 1,245,527.21
- Besi Ø10 - 100 Mutu baja BJTP 24 (polos) kg 78.74 12,734.15 1,002,686.97
- Besi tulangan 2 D13 Mutu baja BJTP 40 (ulir) kg 19.77 12,734.15 251,754.15
- Bekisting m2 10.24 251,278.50 2,573,091.84

6 Pek. Pas. Balok B3 300x650


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 76.83 1,011,037.50 77,678,011.13
- Besi tulangan 12 D22 Mutu baja BJTP 40 (ulir) kg 7,236.53 12,734.15 92,151,058.50
- Besi tulangan 8 D22 Mutu baja BJTP 40 (ulir) kg 4,824.35 12,734.15 61,433,996.55
- Besi Ø12 - 100 & 150 Mutu baja BJTP 24 (polos) kg 3,803.98 12,734.15 48,440,451.92
- Besi Tulangan 2 D16 Mutu baja BJTP 40 (ulir) kg 839.35 12,734.15 10,688,408.80
- Bekisting m2 630.40 251,278.50 158,405,966.40

7 Pek. Pas. Balok B4 300x550


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 7.92 1,011,037.50 8,007,417.00
- Besi tulangan 8 D22 Mutu baja BJTP 40 (ulir) kg 454.01 12,734.15 5,781,431.44
- Besi tulangan 7 D22 Mutu baja BJTP 40 (ulir) kg 340.51 12,734.15 4,336,105.42
- Besi Tulangan 2 D16 Mutu baja BJTP 40 (ulir) kg 157.29 12,734.15 2,002,954.45
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 414.91 12,734.15 5,283,526.18
- Bekisting m2 67.20 251,278.50 16,885,915.20

8 Pek. Pas. Balok B4' 300x550


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 8.40 1,011,037.50 8,492,715.00
- Besi tulangan 8 D22 Mutu baja BJTP 40 (ulir) kg 444.62 12,734.15 5,661,857.77
- Besi tulangan 7 D22 Mutu baja BJTP 40 (ulir) kg 444.62 12,734.15 5,661,857.77
- Besi tulangan 3 Ø10 Mutu baja BJTP 24 (polos) kg 62.64 12,734.15 797,667.16
- Besi tulangan 5 Ø10 Mutu baja BJTP 24 (polos) kg 104.41 12,734.15 1,329,572.60
- Besi Tulangan 2 D16 Mutu baja BJTP 40 (ulir) kg 108.55 12,734.15 1,382,291.98
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 623.61 12,734.15 7,941,143.28
- Bekisting m2 107.20 251,278.50 26,937,055.20

9 Pek. Pas. Balok B5 250x500


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 20.38 1,011,037.50 20,604,944.25
- Besi tulangan 8 D16 Mutu baja BJTP 40 (ulir) kg 1,204.47 12,734.15 15,337,901.65
- Besi tulangan 5 D16 Mutu baja BJTP 40 (ulir) kg 752.79 12,734.15 9,586,140.78
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 1,258.78 12,734.15 16,029,493.34
- Besi Tulangan 2 D13 Mutu baja BJTP 40 (ulir) kg 184.03 12,734.15 2,343,465.62
- Bekisting m2 203.75 251,278.50 51,197,994.38
10 Pek. Pas. Balok B5' 250x500
- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 2.37 1,011,037.50 2,396,158.88
- Besi tulangan 8 D16 Mutu baja BJTP 40 (ulir) kg 99.41 12,734.15 1,265,901.85
- Besi tulangan 5 D16 Mutu baja BJTP 40 (ulir) kg 62.13 12,734.15 791,172.74
- Besi tulangan 2 Ø10 Mutu baja BJTP 24 (polos) kg 16.59 12,734.15 211,259.55
- Besi tulangan 4 Ø10 Mutu baja BJTP 24 (polos) kg 33.18 12,734.15 422,519.10
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 214.03 12,734.15 2,725,490.12
- Besi Tulangan 2 D13 Mutu baja BJTP 40 (ulir) kg 28.59 12,734.15 364,069.35
- Bekisting m2 34.27 251,278.50 8,611,314.20

11 Pek. Pas. Balok B8 200x400


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.96 1,011,037.50 970,596.00
- Besi tulangan 6 D16 Mutu baja BJTP 40 (ulir) kg 107.78 12,734.15 1,372,486.69
- Besi tulangan 5 D16 Mutu baja BJTP 40 (ulir) kg 89.81 12,734.15 1,143,654.01
- Besi Ø10 - 150 Mutu baja BJTP 24 (polos) kg 63.14 12,734.15 804,034.23
- Bekisting m2 12.00 251,278.50 3,015,342.00

12 Pek. Pas. Balok B6 200x300


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.27 1,011,037.50 1,284,017.63
- Besi tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 104.58 12,734.15 1,331,737.41
- Besi tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 87.15 12,734.15 1,109,781.17
- Besi Ø8 - 100 & 150 Mutu baja BJTP 24 (polos) kg 72.72 12,734.15 926,027.39
- Bekisting m2 16.96 251,278.50 4,261,683.36

13 Pek. Pas. Balok B7 150x300


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 3.12 1,011,037.50 3,154,437.00
- Besi tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 466.25 12,734.15 5,937,297.44
- Besi tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 388.55 12,734.15 4,947,853.98
- Besi Ø8 - 100 & 150 Mutu baja BJTP 24 (polos) kg 226.75 12,734.15 2,887,468.51
- Bekisting m2 52.03 251,278.50 13,074,020.36

14 Pek. Pas. Balok B7' 150x300


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 8.33 1,011,037.50 8,421,942.38
- Besi tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 463.94 12,734.15 5,907,881.55
- Besi tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 386.62 12,734.15 4,923,277.07
- Besi tulangan 2 Ø10 Mutu baja BJTP 24 (polos) kg 170.15 12,734.15 2,166,715.62
- Besi Ø8 - 100 & 150 Mutu baja BJTP 24 (polos) kg 607.15 12,734.15 7,731,539.17
- Bekisting m2 160.13 251,278.50 40,237,226.21

15 Balok Overstek Plafond


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 3.36 1,011,037.50 3,397,086.00
- Besi tulangan 4 Ø10 Mutu baja BJTP 24 (polos) kg 149.88 12,734.15 1,908,594.40
- Besi Ø10 - 150 Mutu baja BJTP 24 (polos) kg 325.52 12,734.15 4,145,220.51
- Bekisting m2 72.80 251,278.50 18,293,074.80

16 Pek. Pas. Struktur Tangga As e kiri


a Pek. Pas. Balok tangga 15x30
- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.07 1,011,037.50 70,772.63
- Besi Tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 9.72 12,734.15 123,775.94
- Besi Tulangan 4 D13 Mutu baja BJTP 40 (ulir) kg 6.48 12,734.15 82,517.29
- Besi Ø8 - 100 & 150 Mutu baja BJTP 24 (polos) kg 5.08 12,734.15 64,689.48
- Bekisting m2 1.20 251,278.50 301,534.20

b Pek. Pas Tangga s/d elv + 9,625


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.53 1,011,037.50 535,849.88
- Besi Tulangan D16-150 Mutu baja BJTP 40 (ulir) kg 36.22 12,734.15 461,230.91
- Besi Tulangan D13-150 Mutu baja BJTP 24 (polos) kg 23.91 12,734.15 304,473.53
- Besi Tulangan Ø10 -150 Mutu baja BJTP 24 (polos) kg 14.16 12,734.15 180,315.56
- Bekisting m2 6.68 227,628.50 1,520,558.38

c Pek. Pas. Kolom bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.05 1,011,037.50 50,551.88
- Besi tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 11.54 12,734.15 146,952.09
- Besi Ø8 - 150 Mutu baja BJTP 24 (polos) kg 3.99 12,734.15 50,809.26
- Bekisting m2 0.95 195,453.50 185,680.83

d Pek. Pas. Balok bordes Elv. + 9,625


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.12 1,011,037.50 121,324.50
- Besi Tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 22.05 12,734.15 280,788.01
- Besi Tulangan Ø8-150 Mutu baja BJTP 24 (polos) kg 6.77 12,734.15 86,210.20
- Bekisting m2 2.03 251,278.50 510,095.36

e Pek. Pas. Plat bordes Elv. + 9,625


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.22 1,011,037.50 222,428.25
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 36.25 12,734.15 461,612.94
- Besi Tulangan D16 - 150 Mutu baja BJTP 40 (ulir) kg 92.71 12,734.15 1,180,583.05
- Bekisting m2 3.65 233,953.50 853,930.28

f Pek. Pas Tangga s/d elv + 11,550


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.10 1,011,037.50 1,112,141.25
- Besi Tulangan D16-150 Mutu baja BJTP 40 (ulir) kg 71.46 12,734.15 909,982.36
- Besi Tulangan D13-150 Mutu baja BJTP 24 (polos) kg 47.19 12,734.15 600,924.54
- Besi Tulangan Ø10 -150 Mutu baja BJTP 24 (polos) kg 27.94 12,734.15 355,792.15
- Bekisting m2 14.76 227,628.50 3,359,796.66

g Pek. Pas. Balok bordes Elv. + 11,550


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.10 1,011,037.50 101,103.75
- Besi Tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 22.05 12,734.15 280,788.01
- Besi Tulangan Ø8-150 Mutu baja BJTP 24 (polos) kg 5.96 12,734.15 75,895.53
- Bekisting m2 1.76 251,278.50 442,250.16

h Pek. Pas. Plat bordes Elv. + 11,550


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.22 1,011,037.50 222,428.25
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 36.25 12,734.15 461,612.94
- Besi Tulangan D16 - 150 Mutu baja BJTP 40 (ulir) kg 92.71 12,734.15 1,180,583.05
- Bekisting m2 1.82 233,953.50 425,795.37

i Pek. Pas Tangga s/d elv + 12,600


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.59 1,011,037.50 596,512.13
- Besi Tulangan D16-150 Mutu baja BJTP 40 (ulir) kg 37.92 12,734.15 482,878.97
- Besi Tulangan D13-150 Mutu baja BJTP 24 (polos) kg 25.04 12,734.15 318,863.12
- Besi Tulangan Ø10 -150 Mutu baja BJTP 24 (polos) kg 14.83 12,734.15 188,847.44
- Bekisting m2 7.38 227,628.50 1,679,898.33

17 Pek. Pas. Struktur Tangga As e kanan


a Pek. Pas. Balok tangga 15x30
- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.07 1,011,037.50 70,772.63
- Besi Tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 9.72 12,734.15 123,775.94
- Besi Tulangan 4 D13 Mutu baja BJTP 40 (ulir) kg 6.48 12,734.15 82,517.29
- Besi Ø8 - 100 & 150 Mutu baja BJTP 24 (polos) kg 5.08 12,734.15 64,689.48
- Bekisting m2 1.20 251,278.50 301,534.20

b Pek. Pas Tangga s/d elv + 9,625


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.53 1,011,037.50 535,849.88
- Besi Tulangan D16-150 Mutu baja BJTP 40 (ulir) kg 36.22 12,734.15 461,230.91
- Besi Tulangan D13-150 Mutu baja BJTP 40 (ulir) kg 23.91 12,734.15 304,473.53
- Besi Tulangan Ø10 -150 Mutu baja BJTP 24 (polos) kg 14.16 12,734.15 180,315.56
- Bekisting m2 6.68 227,628.50 1,520,558.38

c Pek. Pas. Kolom bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.05 1,011,037.50 50,551.88
- Besi tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 11.54 12,734.15 146,952.09
- Besi Ø8 - 150 Mutu baja BJTP 24 (polos) kg 3.99 12,734.15 50,809.26
- Bekisting m2 0.95 195,453.50 185,680.83

e Pek. Pas. Balok bordes Elv. + 9,625


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.12 1,011,037.50 121,324.50
- Besi Tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 22.05 12,734.15 280,788.01
- Besi Tulangan Ø8-150 Mutu baja BJTP 24 (polos) kg 6.77 12,734.15 86,210.20
- Bekisting m2 2.03 251,278.50 510,095.36

e Pek. Pas. Plat bordes Elv. + 9,625


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.22 1,011,037.50 222,428.25
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 36.25 12,734.15 461,612.94
- Besi Tulangan D16 - 150 Mutu baja BJTP 40 (ulir) kg 92.71 12,734.15 1,180,583.05
- Bekisting m2 3.65 233,953.50 853,930.28

f Pek. Pas Tangga s/d elv + 11,550


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.10 1,011,037.50 1,112,141.25
- Besi Tulangan D16-150 Mutu baja BJTP 40 (ulir) kg 71.46 12,734.15 909,982.36
- Besi Tulangan D13-150 Mutu baja BJTP 40 (ulir) kg 47.19 12,734.15 600,924.54
- Besi Tulangan Ø10 -150 Mutu baja BJTP 24 (polos) kg 27.94 12,734.15 355,792.15
- Bekisting m2 14.76 227,628.50 3,359,796.66

g Pek. Pas. Balok bordes Elv. + 11,550


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.10 1,011,037.50 101,103.75
- Besi Tulangan 5 D13 Mutu baja BJTP 24 (polos) kg 22.05 12,734.15 280,788.01
- Besi Tulangan Ø8-150 Mutu baja BJTP 40 (ulir) kg 5.96 12,734.15 75,895.53
- Bekisting m2 1.76 251,278.50 442,250.16

h Pek. Pas. Plat bordes Elv. + 11,550


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.22 1,011,037.50 222,428.25
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 36.25 12,734.15 461,612.94
- Besi Tulangan D16 - 150 Mutu baja BJTP 40 (ulir) kg 92.71 12,734.15 1,180,583.05
- Bekisting m2 1.82 233,953.50 425,795.37

i Pek. Pas Tangga s/d elv + 12,600


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.59 1,011,037.50 596,512.13
- Besi Tulangan D16-150 Mutu baja BJTP 40 (ulir) kg 37.92 12,734.15 482,878.97
- Besi Tulangan D13-150 Mutu baja BJTP 24 (polos) kg 25.04 12,734.15 318,863.12
- Besi Tulangan Ø10 -150 Mutu baja BJTP 24 (polos) kg 14.83 12,734.15 188,847.44
- Bekisting m2 7.38 227,628.50 1,679,898.33

18 Pek. Pas. Struktur Tangga Kebakaran


a Pek. Pas Tangga s/d elv + 10,500
- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 3.79 1,011,037.50 3,831,832.13
- Besi Tulangan D16-150 Mutu baja BJTP 40 (ulir) kg 60.36 12,734.15 768,633.29
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 23.60 12,734.15 300,525.94
- Besi Tulangan Ø8 -150 Mutu baja BJTP 24 (polos) kg 15.11 12,734.15 192,413.01
- Bekisting m2 12.64 227,628.50 2,877,224.24

b Pek. Pas. Balok bordes Elv. + 10,500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.18 1,011,037.50 181,986.75
- Besi Tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 33.21 12,734.15 422,901.12
- Besi Tulangan Ø8-150 Mutu baja BJTP 24 (polos) kg 10.14 12,734.15 129,124.28
- Bekisting m2 3.12 251,278.50 783,988.92

c Pek. Pas. Plat bordes Elv. + 10,500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.43 1,011,037.50 434,746.13
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 56.79 12,734.15 723,172.38
- Besi Tulangan D16 - 150 Mutu baja BJTP 40 (ulir) kg 145.25 12,734.15 1,849,635.29
- Bekisting m2 2.88 233,953.50 673,786.08

d Pek. Pas Tangga s/d elv + 12,600


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 3.79 1,011,037.50 3,831,832.13
- Besi Tulangan D16-150 Mutu baja BJTP 40 (ulir) kg 60.36 12,734.15 768,633.29
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 23.60 12,734.15 300,525.94
- Besi Tulangan Ø8 -150 Mutu baja BJTP 24 (polos) kg 15.11 12,734.15 192,413.01
- Bekisting m2 12.64 227,628.50 2,877,224.24

19 Pek. Pas. Dinding Beton t.150mm (Tangga Kebakaran)


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 11.09 1,011,037.50 11,212,405.88
- Besi tulangan Ø12 - 150 Mutu baja BJTP 24 (polos) kg 1,010.14 12,734.15 12,863,274.28
- Standed Bar bh 72.00 -
- Waterproofing integral Waterproofing formeex WP system, Merk : Hitchins, Pentens, Sika kg 38.81 22,137.50 859,156.38
- Waterproofing coating Waterproofing Formeex Uniflex Cementitious Membrance m2 55.44 36,850.00 2,042,964.00
Merk : Sika, Fosroc
- Water stop Waterstop Lebar 150 mm m1 17.60 107,398.50 1,890,213.60
- Bekisting batako m2 73.92 76,613.90 5,663,299.49
- Bekisting multipleks m2 73.92 288,018.50 21,290,327.52

20 Pekerjaan dinding beton Lift As-D2 T.25cm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 8.19 1,011,037.50 8,280,397.13
- Waterproofing integral mix Waterproofing formeex WP system, Merk : Hitchins, Pentens, Sika kg 28.67 22,137.50 634,682.13
- Besi D13 -100 Mutu baja BJTP 40 (ulir) kg 794.28 12,734.15 10,114,480.66
- Besi Ø12 - 150 Mutu baja BJTP 24 (polos) kg 458.76 12,734.15 5,841,918.65
- Besi Ø12 - 150 Mutu baja BJTP 24 (polos) kg 489.42 12,734.15 6,232,347.69
- Bekisting m2 65.52 288,018.50 18,870,972.12

21 Pekerjaan dinding beton Lift As-D5 T.25cm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 8.19 1,011,037.50 8,280,397.13
- Waterproofing integral mix Waterproofing formeex WP system, Merk : Hitchins, Pentens, Sika kg 28.67 22,137.50 634,682.13
- Besi D13 -100 Mutu baja BJTP 40 (ulir) kg 794.28 12,734.15 10,114,480.66
- Besi Ø12 - 150 Mutu baja BJTP 24 (polos) kg 458.76 12,734.15 5,841,918.65
- Besi Ø12 - 150 Mutu baja BJTP 24 (polos) kg 489.42 12,734.15 6,232,347.69
- Bekisting m2 65.52 288,018.50 18,870,972.12

22 Pek. Pelat Lantai 4 T=12mm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 122.00 1,011,037.50 123,346,575.00
- Wiremesh M8 (2 lapis) kg 11,081.47 40,122.50 444,616,280.08
- Bekisting m2 1,016.65 233,953.50 237,848,825.78
- Standed Bar bh 1,017.00 -

23 Pek. Pas. Balok Separator Lift


- Pek. IWF 200.100.5,5.8 Baja Profil, Merk : DN kg 332.28 20,097.00 6,677,831.16
- Pek. Plat penghubung T.10mm Baja Profil, Merk : DN kg 18.84 20,097.00 378,627.48
- Pek. Vote IWF 200.100.5.8 Baja Profil, Merk : DN kg 38.34 20,097.00 770,518.98
- Baut HTB 4 D19 Baut HTB 4D19 bh 96.00 1,500.00 144,000.00
- Pek. Pengecatan besi Anti Karat Cat zinchromat, setara Meiji m2 80.16 24,486.00 1,962,797.76

JUMLAH PEKERJAAN STRUKTUR ELV. +8.400 s/e +12.600 Rp. 2,130,218,225.13

II.D PEKERJAAN STRUKTUR ELV. +12.600 s/e +16.800


1 Pek. Pas. Kolom K1 400x400
- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 13.56 1,011,037.50 13,709,668.50
- Besi tulangan 8 D19 Mutu baja BJTP 40 (ulir) kg 2,279.97 12,734.15 29,033,479.98
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 721.07 12,734.15 9,182,213.54
- Bekisting m2 135.55 195,453.50 26,493,721.93

2 Pek. Pas. Kolom K2 400x400


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 6.59 1,011,037.50 6,662,737.13
- Besi tulangan 8 D19 Mutu baja BJTP 40 (ulir) kg 1,139.98 12,734.15 14,516,676.32
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 360.54 12,734.15 4,591,170.44
- Bekisting m2 65.86 195,453.50 12,872,567.51

3 Pek. Pas. Kolom K4 350x350


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.86 1,011,037.50 869,492.25
- Besi tulangan 10 D16 Mutu baja BJTP 40 (ulir) kg 164.01 12,734.15 2,088,527.94
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 60.72 12,734.15 773,217.59
- Bekisting m2 9.88 195,453.50 1,931,080.58

4 Pek. Pas. Kolom K5 300x300


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 2.81 1,011,037.50 2,841,015.38
- Besi tulangan 12 D13 Mutu baja BJTP 40 (ulir) kg 506.08 12,734.15 6,444,498.63
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 200.89 12,734.15 2,558,163.39
- Bekisting m2 37.44 195,453.50 7,317,779.04

5 Pek. Pas. Balok B3 300x650


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 5.07 1,011,037.50 5,125,960.13
- Besi tulangan 12 D22 Mutu baja BJTP 40 (ulir) kg 804.99 12,734.15 10,250,863.41
- Besi tulangan 8 D22 Mutu baja BJTP 40 (ulir) kg 536.66 12,734.15 6,833,908.94
- Besi Ø12 - 100 & 150 Mutu baja BJTP 24 (polos) kg 386.65 12,734.15 4,923,659.10
- Besi Tulangan 2 D16 Mutu baja BJTP 40 (ulir) kg 105.84 12,734.15 1,347,782.44
- Bekisting m2 41.60 251,278.50 10,453,185.60

6 Pek. Pas. Balok B3' 300x650


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 18.24 1,011,037.50 18,441,324.00
- Besi tulangan 12 D22 Mutu baja BJTP 40 (ulir) kg 1,416.41 12,734.15 18,036,777.40
- Besi tulangan 8 D22 Mutu baja BJTP 40 (ulir) kg 944.27 12,734.15 12,024,475.82
- Besi tulangan 2 Ø10 Mutu baja BJTP 24 (polos) kg 85.01 12,734.15 1,082,530.09
- Besi tulangan 4 Ø10 Mutu baja BJTP 24 (polos) kg 166.69 12,734.15 2,122,655.46
- Besi Ø12 - 100 & 150 Mutu baja BJTP 24 (polos) kg 1,889.16 12,734.15 24,056,846.81
- Besi Tulangan 2 D16 Mutu baja BJTP 40 (ulir) kg 222.63 12,734.15 2,835,003.81
- Bekisting m2 220.80 251,278.50 55,482,292.80

6 Pek. Pas. Balok B4 300x550


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 2.64 1,011,037.50 2,669,139.00
- Besi tulangan 8 D22 Mutu baja BJTP 40 (ulir) kg 304.85 12,734.15 3,882,005.63
- Besi tulangan 7 D22 Mutu baja BJTP 40 (ulir) kg 266.75 12,734.15 3,396,834.51
- Besi Tulangan 2 D16 Mutu baja BJTP 40 (ulir) kg 62.58 12,734.15 796,903.11
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 202.30 12,734.15 2,576,118.55
- Bekisting m2 22.40 251,278.50 5,628,638.40

7 Pek. Pas. Balok B4' 300x550


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 41.20 1,011,037.50 41,654,745.00
- Besi tulangan 8 D22 Mutu baja BJTP 40 (ulir) kg 2,017.66 12,734.15 25,693,185.09
- Besi tulangan 7 D22 Mutu baja BJTP 40 (ulir) kg 1,765.45 12,734.15 22,481,505.12
- Besi tulangan 2 Ø10 Mutu baja BJTP 24 (polos) kg 200.35 12,734.15 2,551,286.95
- Besi tulangan 5 Ø10 Mutu baja BJTP 24 (polos) kg 500.88 12,734.15 6,378,281.05
- Besi Tulangan 2 D16 Mutu baja BJTP 40 (ulir) kg 515.82 12,734.15 6,568,529.25
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 3,204.16 12,734.15 40,802,254.06
- Bekisting m2 536.00 251,278.50 134,685,276.00

8 Pek. Pas. Balok B5 250x500


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 8.18 1,011,037.50 8,270,286.75
- Besi tulangan 8 D16 Mutu baja BJTP 40 (ulir) kg 387.72 12,734.15 4,937,284.64
- Besi tulangan 5 D16 Mutu baja BJTP 40 (ulir) kg 242.33 12,734.15 3,085,866.57
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 521.09 12,734.15 6,635,638.22
- Besi Tulangan 2 D13 kg 665.76 12,734.15 8,477,887.70
- Bekisting m2 81.75 251,278.50 20,542,017.38

9 Pek. Pas. Balok B5' 250x500


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 4.56 1,011,037.50 4,610,331.00
- Besi tulangan 8 D16 Mutu baja BJTP 40 (ulir) kg 214.99 12,734.15 2,737,714.91
- Besi tulangan 5 D16 Mutu baja BJTP 40 (ulir) kg 134.37 12,734.15 1,711,087.74
- Besi tulangan 2 Ø10 Mutu baja BJTP 24 (polos) kg 33.50 12,734.15 426,594.03
- Besi tulangan 4 Ø10 Mutu baja BJTP 24 (polos) kg 66.99 12,734.15 853,060.71
- Besi Tulangan 2 D13 Mutu baja BJTP 40 (ulir) kg 60.01 12,734.15 764,176.34
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 404.49 12,734.15 5,150,836.33
- Bekisting m2 64.60 251,278.50 16,232,591.10

10 Pek. Pas. Balok B8 200x400


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 7.52 1,011,037.50 7,603,002.00
- Besi tulangan 6 D16 Mutu baja BJTP 40 (ulir) kg 835.94 12,734.15 10,644,985.35
- Besi tulangan 5 D16 Mutu baja BJTP 40 (ulir) kg 696.62 12,734.15 8,870,863.57
- Besi Ø10 - 150 Mutu baja BJTP 24 (polos) kg 473.52 12,734.15 6,029,874.71
- Bekisting m2 94.00 251,278.50 23,620,179.00

11 Pek. Pas. Balok B6 200x300


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 1.40 1,011,037.50 1,415,452.50
- Besi tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 111.60 12,734.15 1,421,131.14
- Besi tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 93.00 12,734.15 1,184,275.95
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 124.23 12,734.15 1,581,963.45
- Bekisting m2 18.72 251,278.50 4,703,933.52

Pek. Pas. Balok B7' 150x300


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 15.40 1,011,037.50 15,569,977.50
- Besi tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 563.03 12,734.15 7,169,708.47
- Besi tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 469.19 12,734.15 5,974,735.84
- Besi tulangan 3 Ø10 Mutu baja BJTP 24 (polos) kg 317.15 12,734.15 4,038,635.67
- Besi tulangan 2 Ø10 Mutu baja BJTP 24 (polos) kg 323.68 12,734.15 4,121,789.67
- Besi Ø8 - 100 & 150 Mutu baja BJTP 24 (polos) kg 1,114.99 12,734.15 14,198,449.91
- Bekisting m2 291.74 251,278.50 73,307,989.59

19 Pek. Balok Dudukan Rooftank B9 20x20


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 0.22 1,011,037.50 222,428.25
- Besi tulangan 6 D16 Mutu baja BJTP 40 (ulir) kg 70.69 12,734.15 900,177.06
- Besi Ø10 - 100 &150 Mutu baja BJTP 24 (polos) kg 23.29 12,734.15 296,578.35
- Bekisting m2 3.36 251,278.50 844,295.76

12 Balok Overstek Plafond


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 3.36 1,011,037.50 3,397,086.00
- Besi tulangan 4 Ø10 Mutu baja BJTP 24 (polos) kg 149.88 12,734.15 1,908,594.40
- Besi Ø10 - 150 Mutu baja BJTP 24 (polos) kg 323.83 12,734.15 4,123,699.79
- Bekisting m2 31.20 251,278.50 7,839,889.20

13 Pek. Pas Struktur Tangga Rooftop Kiri


a Pek. Pas. Balok tangga 15x30
- Cor beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 0.07 1,011,037.50 70,772.63
- Besi Tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 9.72 12,734.15 123,775.94
- Besi Tulangan 4 D13 Mutu baja BJTP 24 (polos) kg 6.48 12,734.15 82,517.29
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 4.06 12,734.15 51,700.65
- Bekisting m2 1.20 227,628.50 273,154.20

a Pek. Pas Tangga s/d elv + 14,700


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 7.90 1,011,037.50 7,987,196.25
- Besi Tulangan D16-150 Mutu baja BJTP 40 (ulir) kg 68.41 12,734.15 871,143.20
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 26.75 12,734.15 340,638.51
- Besi Tulangan Ø8 -150 Mutu baja BJTP 24 (polos) kg 17.12 12,734.15 218,008.65
- Bekisting m2 13.84 251,278.50 3,477,694.44

b Pek. Pas. Balok bordes Elv. + 14,700


- Cor beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 0.12 1,011,037.50 121,324.50
- Besi Tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 22.05 12,734.15 280,788.01
- Besi Tulangan Ø8-150 Mutu baja BJTP 24 (polos) kg 6.77 12,734.15 86,210.20
- Bekisting m2 2.03 233,953.50 474,925.61

c Pek. Pas. Plat bordes Elv. + 14,700


- Cor beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 0.26 1,011,037.50 262,869.75
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 36.06 12,734.15 459,193.45
- Besi Tulangan D16 - 150 Mutu baja BJTP 40 (ulir) kg 92.23 12,734.15 1,174,470.65
- Bekisting m2 1.72 227,628.50 391,521.02

d Pek. Pas Tangga s/d elv + 16,800


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 12.23 1,011,037.50 12,364,988.63
- Besi Tulangan D16-150 Mutu baja BJTP 40 (ulir) kg 71.63 12,734.15 912,147.16
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 28.01 12,734.15 356,683.54
- Besi Tulangan Ø8 -150 Mutu baja BJTP 24 (polos) kg 17.93 12,734.15 228,323.31
- Bekisting m2 14.53 251,278.50 3,651,076.61

14 Pek. Pas Struktur Tangga Rooftop kanan


a Pek. Pas. Balok tangga 15x30
- Cor beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 0.07 1,011,037.50 70,772.63
- Besi Tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 9.72 12,734.15 123,775.94
- Besi Tulangan 4 D13 Mutu baja BJTP 24 (polos) kg 6.48 12,734.15 82,517.29
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 4.06 12,734.15 51,700.65
- Bekisting m2 1.20 251,278.50 301,534.20

a Pek. Pas Tangga s/d elv + 14,700


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 7.90 1,011,037.50 7,987,196.25
- Besi Tulangan D16-150 Mutu baja BJTP 40 (ulir) kg 68.41 12,734.15 871,143.20
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 26.75 12,734.15 340,638.51
- Besi Tulangan Ø8 -150 Mutu baja BJTP 24 (polos) kg 17.12 12,734.15 218,008.65
- Bekisting m2 13.84 251,278.50 3,477,694.44

b Pek. Pas. Balok bordes Elv. + 14,700


- Cor beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 0.12 1,011,037.50 121,324.50
- Besi Tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 22.05 12,734.15 280,788.01
- Besi Tulangan Ø8-150 Mutu baja BJTP 24 (polos) kg 6.77 12,734.15 86,210.20
- Bekisting m2 2.03 251,278.50 510,095.36

c Pek. Pas. Plat bordes Elv. + 14,700


- Cor beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 0.26 1,011,037.50 262,869.75
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 36.06 12,734.15 459,193.45
- Besi Tulangan D16 - 150 Mutu baja BJTP 40 (ulir) kg 92.23 12,734.15 1,174,470.65
- Bekisting m2 1.72 251,278.50 432,199.02

e Pek. Pas Tangga s/d elv + 16,800


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 12.23 1,011,037.50 12,364,988.63
- Besi Tulangan D16-150 Mutu baja BJTP 40 (ulir) kg 71.63 12,734.15 912,147.16
- Besi Tulangan Ø10-150 Mutu baja BJTP 24 (polos) kg 28.01 12,734.15 356,683.54
- Besi Tulangan Ø8 -150 Mutu baja BJTP 24 (polos) kg 17.93 12,734.15 228,323.31
- Bekisting m2 14.53 251,278.50 3,651,076.61

14 Pek. dinding beton Lift Kiri T.25cm


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 8.19 1,011,037.50 8,280,397.13
- Waterproofing integral mix Waterproofing formeex WP system, Merk : Hitchins, Pentens, Sika kg 28.67 22,137.50 634,682.13
- Besi D13 -100 Mutu baja BJTP 24 (polos) kg 794.28 12,734.15 10,114,480.66
- Besi Ø12 - 150 Mutu baja BJTP 24 (polos) kg 458.76 12,734.15 5,841,918.65
- Besi Ø12 - 150 kg 489.42 12,734.15 6,232,347.69
- Bekisting m2 65.52 288,018.50 18,870,972.12

15 Pek. dinding beton Lift Kanan T.25cm


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 8.19 1,011,037.50 8,280,397.13
- Waterproofing integral mix Waterproofing formeex WP system, Merk : Hitchins, Pentens, Sika kg 28.67 22,137.50 634,682.13
- Besi D13 -100 Mutu baja BJTP 24 (polos) kg 794.28 12,734.15 10,114,480.66

- Besi Ø12 - 150 Mutu baja BJTP 24 (polos) kg 458.76 12,734.15 5,841,918.65
- Besi Ø12 - 150 Mutu baja BJTP 24 (polos) kg 489.42 12,734.15 6,232,347.69
- Bekisting m2 65.52 288,018.50 18,870,972.12

16 Pek. Pelat Atap Beton T=12 cm


- Cor beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 63.51 1,011,037.50 64,210,991.63
- Waterproofing Integral Waterproofing formeex WP system, Merk : Sika, Fosroc kg 222.30 22,137.50 4,921,166.25
- Wiremesh M8 (2 layer) kg 5,769.17 40,122.50 231,473,523.33
- Bekisting m2 529.29 233,953.50 123,829,248.02
- Standed Bar bh 530.00 -

17 Pek. Pelat Lantai Rooftank T=15 cm


- Cor beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 3.65 1,011,037.50 3,690,286.88
- Waterproofing Integral Waterproofing formeex WP system, Merk : Sika, Fosroc kg 12.76 22,137.50 282,474.50
- Wiremesh M8 (2 layer) kg 264.87 40,122.50 10,627,246.58
- Bekisting m2 24.30 233,953.50 5,685,070.05
- Standed Bar bh 25.00 -

18 Pek. Pas. Balok Separator Lift


- Pek. IWF 200.100.5,5.8 Baja Profil, Merk : DN kg 332.28 20,097.00 6,677,831.16
- Pek. Plat penghubung T.10mm Baja Profil, Merk : DN kg 18.84 20,097.00 378,627.48
- Pek. Vote IWF 200.100.5.8 Baja Profil, Merk : DN kg 38.34 20,097.00 770,518.98
- Baut HTB 4 D19 Baut HTB 4D19 bh 96.00 12,000.00 1,152,000.00
- Pek. Pengecatan besi Anti Karat Cat zinchromat, setara Meiji m2 80.16 24,486.00 1,962,797.76

JUMLAH PEKERJAAN STRUKTUR ELV. +12.600 s/e +16.800 Rp. 1,534,330,903.22

II.E PEKERJAAN STRUKTUR ELV. +16.800 s/d +19.300


1 Pek. Pas. Kolom K2 400x400
- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 2.41 1,011,037.50 2,436,600.38
- Besi tulangan 8 D19 Mutu baja BJTP 40 (ulir) kg 512.96 12,734.15 6,532,109.58
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 139.56 12,734.15 1,777,177.97
- Bekisting m2 24.06 195,453.50 4,702,611.21

2 Pek. Pas. Kolom K5 300x300


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 1.35 1,011,037.50 1,364,900.63
- Besi tulangan 12 D13 Mutu baja BJTP 40 (ulir) kg 332.63 12,734.15 4,235,760.31
- Besi Ø10 - 100 Mutu baja BJTP 24 (polos) kg 120.53 12,734.15 1,534,847.10
- Bekisting m2 18.05 195,453.50 3,527,935.68

3 Pek. Pas. Balok B5 250x500


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 4.30 1,011,037.50 4,347,461.25
- Besi tulangan 8 D16 Mutu baja BJTP 40 (ulir) kg 153.56 12,734.15 1,955,456.07
- Besi tulangan 5 D16 Mutu baja BJTP 40 (ulir) kg 95.97 12,734.15 1,222,096.38
- Besi Ø10 - 100 Mutu baja BJTP 24 (polos) kg 261.91 12,734.15 3,335,201.23
- Bekisting m2 43.00 251,278.50 10,804,975.50

4 Pek. Pas. Balok B7' 150x300


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 2.13 12,734.15 27,123.74
- Besi tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 155.84 12,734.15 1,984,489.94
- Besi tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 103.89 12,734.15 1,322,950.84
- Besi tulangan 3 Ø10 Mutu baja BJTP 24 (polos) kg 90.91 12,734.15 1,157,661.58
- Besi tulangan 2 Ø10 Mutu baja BJTP 24 (polos) kg 60.44 12,734.15 769,652.03
- Besi Ø8 - 100 & 150 Mutu baja BJTP 24 (polos) kg 134.36 12,734.15 1,710,960.39
- Bekisting m2 35.57 251,278.50 8,937,976.25

4 Pek. Pas. Balok B10 200x400


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 3.46 1,011,037.50 3,498,189.75
- Besi tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 142.69 12,734.15 1,817,035.86
- Besi tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 118.91 12,734.15 1,514,217.78
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 260.43 12,734.15 3,316,354.68
- Bekisting m2 43.30 251,278.50 10,880,359.05

5 Pek. Pelat Beton Atap Lift T=12mm


- Cor beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 8.84 1,011,037.50 8,937,571.50
- Waterproofing Integral Waterproofing formeex WP system, Merk : Sika, Fosroc kg 30.93 22,137.50 684,712.88
- Wiremesh M8 (2 layer) kg 147.28 40,122.50 5,909,241.80
- Bekisting m2 73.64 233,953.50 17,228,335.74
- Standed Bar bh 74.00 -

JUMLAH PEKERJAAN STRUKTUR ELV. +16.800 s/e +17.300 Rp. 117,473,967.08

II.F PEKERJAAN STRUKTUR ATAP


1 Pek. Pas. Kolom pedestal 300x300
- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 2.97 1,011,037.50 3,002,781.38
- Besi tulangan 8 D19 Mutu baja BJTP 40 (ulir) kg 1,792.26 12,734.15 22,822,907.68
- Besi Ø10 - 100 & 150 Mutu baja BJTP 24 (polos) kg 284.11 12,734.15 3,617,899.36
- Bekisting m2 39.60 195,453.50 7,739,958.60

2 Pek. Pas. Balok penghubung pedestal 150x250


- Cor Beton Cor beton Reaey mix K-350, fc' : 31,20 Mpa m3 8.85 1,011,037.50 8,947,681.88
- Besi tulangan 6 D13 Mutu baja BJTP 40 (ulir) kg 1,020.65 12,734.15 12,997,110.20
- Besi tulangan 5 D13 Mutu baja BJTP 40 (ulir) kg 680.43 12,734.15 8,664,697.68
- Besi Ø8 - 100 & 150 Mutu baja BJTP 24 (polos) kg 615.37 12,734.15 7,836,213.89
- Bekisting m2 153.40 251,278.50 38,546,121.90

3 Pek.Struktur kuda-kuda baja KD1


- Base Plat T.10mm Baja Profil, Merk : DN kg 254.34 20,097.00 5,111,470.98
- Angkur baut 4D22 Baut HTB 4D22 bh 144.00 12,000.00 1,728,000.00
- Chemical untuk Angkur ex. Hilti titik 144.00 1,000.00 144,000.00
- Kolom IWF 200.100.5.8 Baja Profil, Merk : DN kg 571.27 20,097.00 11,480,813.19
- Plat penghubung T.10 mm kolom dengan balok Baja Profil, Merk : DN kg 84.78 20,097.00 1,703,823.66
- Vote IWF 200.100.5.8 Baja Profil, Merk : DN kg 287.55 20,097.00 5,778,892.35
- Baut HTB 6D19 Baut HTB 3D19 bh 216.00 12,000.00 2,592,000.00
- Kuda-kuda IWF 200.100.5.8 Baja Profil, Merk : DN kg 4,608.47 20,097.00 92,616,421.59
- Plat penghubung T.2x10mm kuda-kuda Baja Profil, Merk : DN kg 145.54 20,097.00 2,924,917.38
- Vote IWF 200.100.5.8 Baja Profil, Merk : DN kg 95.85 20,097.00 1,926,297.45
- Baut HTB 8 D19 Baut HTB 3D19 bh 144.00 12,000.00 1,728,000.00
- Pengecatan Anti Karat Cat zinchromat, setara Meiji m2 192.17 25,000.00 4,804,250.00
4 Pek.Struktur kuda-kuda baja KD2
- Base Plat T.10mm Baja Profil, Merk : DN kg 28.26 20,097.00 567,941.22
- Angkur baut 4D22 Baut HTB 4D22 bh 16.00 15,000.00 240,000.00
- Chemical untuk Angkur ex. Hilti titik 16.00 1,000.00 16,000.00
- Kolom IWF 200.100.5.8 Baja Profil, Merk : DN kg 80.51 20,097.00 1,618,009.47
- Plat penghubung T.10 mm kolom dengan balok Baja Profil, Merk : DN kg 9.42 20,097.00 189,313.74
- Vote IWF 200.100.5.8 Baja Profil, Merk : DN kg 63.90 20,097.00 1,284,198.30
- Baut HTB 6D19 Baut HTB 3D19 bh 24.00 15,000.00 360,000.00
- Kuda-kuda IWF 200.100.5.8 Baja Profil, Merk : DN kg 488.88 20,097.00 9,825,021.36
- Plat penghubung T.10mm kuda-kuda Baja Profil, Merk : DN kg 16.17 20,097.00 324,968.49
- Vote IWF 200.100.5.8 Baja Profil, Merk : DN kg 10.65 20,097.00 214,033.05
- Baut HTB 8 D19 Baut HTB 3D19 bh 32.00 12,000.00 384,000.00
- Pengecatan Anti Karat Cat zinchromat, setara Meiji m2 25.87 25,000.00 646,750.00

5 Pek.Struktur jurai baja J1


- Base Plat T.10mm Baja Profil, Merk : DN kg 56.52 20,097.00 1,135,882.44
- Angkur baut 4D22 Baut HTB 4D22 bh 32.00 22,500.00 720,000.00
- Chemical untuk Angkur ex. Hilti titik 32.00 1,000.00 32,000.00
- Kolom IWF 200.100.5.8 Baja Profil, Merk : DN kg 161.03 20,097.00 3,236,219.91
- Plat penghubung T.10 mm kolom dengan balok Baja Profil, Merk : DN kg 18.84 20,097.00 378,627.48
- Vote IWF 200.100.5.8 Baja Profil, Merk : DN kg 63.90 20,097.00 1,284,198.30
- Baut HTB 6D19 Baut HTB 3D19 bh 24.00 12,500.00 300,000.00
- Kuda-kuda IWF 200.100.5.8 Baja Profil, Merk : DN kg 1,431.36 20,097.00 28,766,041.92
- Plat penghubung T.2x10mm kuda-kuda Baja Profil, Merk : DN kg 32.34 20,097.00 649,936.98
- Vote IWF 200.100.5.8 Baja Profil, Merk : DN kg 21.30 20,097.00 428,066.10
- Baut HTB 8 D19 Baut HTB 3D19 bh 32.00 15,000.00 480,000.00
- Pengecatan Anti Karat Cat zinchromat, setara Meiji m2 71.87 25,000.00 1,796,750.00

6 Pek. Struktur rangka atap


- Lipped channel 150.65.20.2,3 Baja Profil, Merk : DN kg 6,108.74 20,097.00 122,767,347.78
- Besi siku L 50.50.5 Baja Profil, Merk : DN kg 98.28 20,097.00 1,975,133.16
- Baut HTB Ø12 bh 420.00 1,500.00 630,000.00
- Hollow galvanish 30x60 Hollow galvanish 30x60 tebal 1,1mm m1 1,080.51 12,500.00 13,506,375.00
- Reng zincalume m1 2,886.45 10,500.00 30,307,725.00
- Trekstang Ø10 Mutu baja BJTP 24 (polos) kg 172.90 12,734.15 2,201,734.54
- Ikatan angin Ø12 Mutu baja BJTP 24 (polos) kg 900.04 12,734.15 11,461,244.37
- Water mur Watermur bh 64.00 53,000.00 3,392,000.00
- Pengecatan anti karat Cat zinchromat, setara Meiji m2 602.36 25,000.00 15,059,000.00

7 Pek.Struktur kuda-kuda baja atap void


- Base Plat T.10mm Baja Profil, Merk : DN kg 127.17 20,097.00 2,555,735.49
- Angkur baut 4D22 Baut HTB 4D22 bh 72.00 15,000.00 1,080,000.00
- Chemical untuk Angkur ex. Hilti titik 72.00 1,000.00 72,000.00
- Hollow galvanish 100/50 Metal square hollow 50/100, tebal 2,0mm m1 25.02 25,000.00 625,500.00
- Plat penghubung T.10 mm kolom dengan balok Baja Profil, Merk : DN kg 42.39 20,097.00 851,911.83
- Baut HTB 3D19 Baut HTB 3D19 bh 54.00 15,000.00 810,000.00
- Kuda-kuda Hollow galvanish 100/50 Metal square hollow 50/100, tebal 2,0mm m1 122.40 25,000.00 3,060,000.00
- Plat penghubung T.2x6mm kuda-kuda Baja Profil, Merk : DN kg 34.83 20,097.00 699,978.51
- Baut HTB 12 D16 bh 108.00 12,500.00 1,350,000.00
- Voute Hollow Galvanish 100/50 Metal square hollow 50/100, tebal 2,0mm m1 18.72 25,000.00 468,000.00
- Pengecatan Anti Karat Cat zinchromat, setara Meiji m2 2.16 25,000.00 54,000.00

8 Pek. Rangka atap void


- Hollow galvanish 100/50 Hollow galvanish 50/100, tebal 2,0mm m1 268.50 97,405.00 26,153,242.50
- Pengecatan anti karat Cat zinchromat, setara Meiji m2 80.55 24,486.00 1,972,347.30

JUMLAH PEKERJAAN STRUKTUR ATAP Rp. 542,645,493.38


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME
Rp. Rp.
1 2 3 4 5 6 (5X6)

III. PEKERJAAN ARSITEKTUR


III.A LANTAI 1
III.A.1 PEK. PAS. DINDING
1 Pek. Dinding bata ringan Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m2 875.71 104,335.00 91,367,202.85
2 Pek. Dinding Partisi U Runner 92.25, Gypsumboard T.12mm, Merk : A-Plus m2 145.33 77,848.68 11,313,748.75
3 Pek. Kursi Bata Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m2 8.64 104,335.00 901,454.40

2 Pek. Kolom praktis 100x150


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 5.86 837,138.50 4,905,631.61
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 1,250.79 12,734.15 15,927,747.48
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 647.48 12,734.15 8,245,107.44
- Bekisting m2 106.02 189,953.50 20,138,870.07

3 Pek. Balok Praktis 100x200


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 4.09 837,138.50 3,423,896.47
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 707.58 12,734.15 9,010,429.86
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 313.30 12,734.15 3,989,609.20
- Bekisting m2 81.90 248,253.50 20,331,961.65

4 Pek. Kolom praktis Penggantung Balok Praktis 100x150


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 0.07 837,138.50 58,599.70
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 32.96 12,734.15 419,717.58
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 9.28 12,734.15 118,172.91
- Bekisting m2 1.44 189,953.50 273,533.04

5 Pek. Plesteran Dinding, Balok, Kolom dan Kusen MU Plester (50kg) m2 2,229.79 43,476.13 96,942,628.76
6 Pek. Acian Dinding, Balok, Kolom dan Kusen MU Acian (40kg) m2 2,229.79 30,229.38 67,405,158.08

III.A.2 PEK. PAS. PELAPISAN DINDING


1 Pek. Plat beton meja Wastafel
- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 0.12 837,138.50 100,456.62
- Besi Ø 8 - 150 (2 lapis) Mutu baja BJTP 24 (polos) kg 17.64 12,734.15 224,639.32
- Bekisting m2 1.16 233,953.50 271,386.06

2 Pek. Balok Beton Meja Wastafel


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 0.17 837,138.50 142,313.55
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 31.62 12,734.15 402,653.82
- Besi Ø 10 - 150 Mutu baja BJTP 24 (polos) kg 19.03 12,734.15 242,330.87
- Bekisting m2 2.31 251,278.50 580,453.34

3 Pek. Pelapis Meja Wastafel Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 1.16 173,387.50 201,129.50
4 Pek. List Meja Wastafel List Granit 100x600 m1 8.88 17,338.75 153,968.10

5 Pek. Pelapisan Dinding KM/Toilet Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 122.59 167,722.50 20,561,101.28
6 Pek. Waterproofing dinding dan Lantai KM/ toilet Waterproofing Formdex Uniflex Cementitious Membrance, m2 71.20 36,850.00 2,623,720.00
Merk : Sika, Fosroc

7 Pek. Plint t.10cm Homogeneous Tile 600x600 Merk : Garuda Multipipe White m1 318.18 30,457.90 9,691,094.62

8 Pek. Pas. Backdrop Entrance Metal square hollow 30/60, tebal 1,1mm + Cat Anti Karat unit 1.00 11,023,037.92 11,023,037.92
Multiplek 9mm, HPL 0.8mm ex Taco, Lem Kayu & HPL
GRC Cladding
Logo UPI : Stainless Steel, Cutting, Pengecatan Duco
Huruf : Stainless Steel, Cutting, Pengecatan Duco
"UNIVERSITAS PENDIDIKAN INDONESIA KAMPUS PURWAKARTA"
10 Pek. Pelapisan Dinding Hall Entrance Homogeneous Tile 600x600 Merk : Vicenca GYK 6607 m2 57.80 222,884.75 12,882,738.55
Pas. Batu Alam Adesit untuk kolom selasar tinggi 160
11 Batu Adesit 300x600 finish coating transparan m2 33.28 233,557.50 7,772,793.60
cm
III.A.3 PEK. PAS. KUSEN, DAUN PINTU DAN JENDELA
1 Pek. Pintu P1 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 2,669,105.65 10,676,422.59
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO

2 Pek. Pintu P2 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 2.00 2,448,308.43 4,896,616.86
Sudah termasuk metal close untuk engsel
Metal square hollow 20/20, tebal 0,9mm + Cat Anti Karat
Metal square hollow 40/40, tebal 1,1mm + Cat Anti Karat
Plat Besi + Cat Anti Karat
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO

3 Pek. Pintu P5 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 6.00 3,437,897.10 20,627,382.60
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Kaca Polos 6mm, Merk : Asahimas
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

4 Pek. Pintu P6 detail by Vendor (standar SNI) Ex. Spectrum unit 4.00 1,732,500.00 6,930,000.00
5 Pek. Pintu P7 detail by Vendor (standar SNI) Ex. Spectrum unit 1.00 1,732,500.00 1,732,500.00

6 Pek. Pintu P10 Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo unit 1.00 4,100,799.76 4,100,799.76
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo
Rel dan Roda, Sealant
Handel Tanam Oval Dekkson Oval Flush Pull Plate Dekson PP 012 Dekson
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO

7 Pek. Pintu Jendela PJ1 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 1.00 8,052,522.50 8,052,522.50
Sudah termasuk metal close untuk engsel
Rangka daun Pintu Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 6mm, Merk : Asahimas
Kaca Tempered 12mm, Merk : Asahimas
Handle Stainless Steel Dekkson PH-DKS-DL-1868 Dekson 120cm
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

8 Pek. Pintu Jendela PJ2' Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 8.00 6,360,710.34 50,885,682.71
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Kaca Polos 6mm, Merk : Asahimas
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO

9 Pek. Pintu Jendela PJ3 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 7,795,801.05 31,183,204.19
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Kaca Polos 6mm, Merk : Asahimas
Papan Kayu
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO

10 Pek. Jendela J1' Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 1,973,565.00 7,894,260.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 6mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

11 Pek. Jendela J3' Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 2.00 1,914,467.50 3,828,935.00
Kaca Polos 5mm, Merk : Asahimas

12 Pek. Jendela J6' Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 4,976,950.00 19,907,800.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 6mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

13 Pek. Jendela J7' Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 2.00 6,230,840.00 12,461,680.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 5mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

14 Pek. Jendela J8' Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 12.00 8,711,230.00 104,534,760.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 6mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

15 Pek. Jendela J10 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 2.00 4,174,816.56 8,349,633.11
Kaca Polos 6mm, Merk : Asahimas
Double Multiplek 18mm + HPL 0.8mm ex Taco

16 Pek. Bouvenlight B1 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 296,540.75 1,186,163.00
Kaca Polos 6mm, Merk : Asahimas

III.A.4 PEK. PAS. PLAFOND


1 Pek. Rangka gypsum wet area Metal square hollow 40/20, tebal 1,1mm m2 35.19 57,193.13 2,012,626.07
Metal square hollow 40/40, tebal 1,1mm
2 Pek. Rangka Plafond Gypsum Metal square hollow 40/20, tebal 1,1mm m2 537.40 57,193.13 30,735,585.38
3 Pek. Rangka gypsum Selasar Metal square hollow 40/20, tebal 1,1mm m2 263.55 57,193.13 15,073,248.09
Metal square hollow 40/40, tebal 1,1mm

4 Pek. Plafond gypsum wet area Gypsumboard T.9mm, Merk : A-Plus m2 35.19 56,185.25 1,977,158.95
5 Pek. Plafond Gypsum Gypsumboard T.9mm, Merk : A-Plus m2 537.40 56,185.25 30,193,953.35
6 Pek. Plafond Gypsum Selasar Gypsumboard T.9mm, Merk : A-Plus m2 263.55 56,185.25 14,807,622.64

7 Pek. List Plafond gypsum wet area List plafond profil aluminium U, 1cm m1 48.23 18,179.15 876,780.40
8 Pek. List Plafond Plafond Gypsum List plafond profil aluminium U, 2cm m1 294.30 18,729.15 5,511,988.85
9 Pek. List Plafond Plafond Gypsum Selasar List plafond profil aluminium U, 2cm m1 188.25 18,729.15 3,525,762.49

III.A.5 PEK. PAS. PELAPISAN LANTAI


1 Pek. Plesteran (untuk leveling) MU Plester (50kg) m2 34.42 43,476.13 1,496,448.22
2 Pek. Lantai Homogenous Tile 600X600 Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 909.65 173,387.50 157,721,939.38
3 Pek. Pelapisan lantai kamar mandi 600x600 Homogeneous Tile 600x600 Merk : Vicenca GYK 6607 m2 34.42 222,884.75 7,671,693.10
4 Pek. Guiding Block tipe line Tactile Tipe line Aluminium bh 652.00 8,696.88 5,670,362.50
5 Pek. Guiding Block tipe dot Tactile tipe dot Aluminium bh 576.00 7,115.63 4,098,600.00
6 Pek. Pelapisan Lantai Tangga Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 28.40 316,332.50 8,983,843.00
Pembuatan alur stepnoshing
7 Pek. Pelapisan Dinding Trap Tangga Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 10.82 316,332.50 3,422,717.65
8 Pek. Pelapisan Lantai Tangga Darurat Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 14.40 316,332.50 4,555,188.00
Pembuatan alur stepnoshing
9 Pek. Pelapisan Dinding Trap Tangga Darurat Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 5.46 316,332.50 1,727,175.45

III.A.6 PEK. PAS. FINISHING DAN PENGECATAN


1 Pek. Pengecatan dinding Fin. Cat Eksterior Cat dasar Jotun Jotashield Primer 7 m2 752.54 22,955.35 17,274,819.09
Cat tembok eksterior, setara Jotun Jotashield Antifade
2 Pek. Pengecatan dinding Fin. Cat Interior Cat dasar Jotun Base Coat Sealer m2 2,411.74 22,955.35 55,362,335.81
Cat tembok interior, setara Jotun Majestic True Beauty SHEEN
3 Pek. Pengecatan plafond Cat plafond, Merk : Vinilex m2 572.59 19,130.10 10,953,703.96
4 Pek. Pelapisan Dinding Granit Tangga Homogeneous Tile 600x600 Merk : Habitat Arabella m2 61.53 219,697.50 13,517,987.18
5 Pek. Pelapisan Dinding Granit Entrance Homogeneous Tile 600x600 Merk : Vicenca GYK 6607 m2 21.25 248,572.50 5,282,165.63
6 Pek. Pelapisan Dinding Kolom Selasar Homogeneous Tile 600x600 Merk : Habitat Arabella m2 64.26 219,697.50 14,117,761.35
7 Pek. Pelapisan Kursi Beton Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 29.52 173,387.50 5,118,399.00

III.A.7 PEK. PAS. PLUMBING FIXTURES


1 Pek. Closet duduk Closet Duduk tipe CW660NJ/SW660J, Merk : Toto unit 9.00 2,000,680.00 18,006,120.00
2 Pek. Wasthafel Washtafel tipe LW813CJ, Kran washtafel Tipe TX109LD, Merk : Toto unit 4.00 1,472,845.00 5,891,380.00
3 Pek. Floor drain Floordrain tipe TX1C, Merk : Toto bh 9.00 50,248.00 452,232.00
4 Pek. Jet Washer Jet Washer tipe THX20NB, Merk : Toto unit 9.00 139,645.00 1,256,805.00
5 Pek. Divider Urinoir Divider Urinoir tipe A100, Merk : Toto unit 5.00 1,056,220.00 5,281,100.00
6 Pek. Urinoir Urinoir tipe U57, Merk : Toto unit 5.00 278,520.00 1,392,600.00
7 Pek. Partisi dan Pintu dinding toilet + Accessories tinggi 210 cm, cubical PVC, tipe Compact - Phenolic 12mm, Ex. Wimas unit 8.00 47,190.00 377,520.00
Frame Stainless Steel, Engsel, Kunci, Handle, dan Accs, Ex. Wimas
8 Pek. Kaca Cermin Merk : Asahimas m2 3.56 95,205.00 338,929.80
9 Pek. Handraill Handrail tipe T113B6, setara Toto unit 2.00 132,770.00 265,540.00

III.A.8 PEK. PAS. TANGGA


1 Pek. Railling Tangga Darurat Kayu Solid 20x80 + Pengecatan Kayu m1 14.79 350,662.66 5,186,300.71
Metal square hollow 40/40, tebal 1,1mm + Cat Anti Karat
Metal square hollow 40/60, tebal 1,0mm + Cat Anti Karat
Plat Besi t.8mm, Besi Nako 8mm
2 Pek. Railling Tangga Kayu Solid 20x80 + Pengecatan Kayu m1 26.60 177,321.39 4,716,748.87
Metal square hollow 40/40, tebal 1,1mm + Cat Anti Karat

JUMLAH PEKERJAAN ARSITEKTUR LANTAI 1 Rp. 1,183,750,791.19

III.B LANTAI 2
III.B.1 PEK. PAS. DINDING
1 Pek. Dinding bata ringan Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m2 1,154.68 104,335.00 120,473,537.80
2 Pek. Dinding partisi U Runner 92.25, Gypsumboard T.12mm, Merk :Jayaboard, Knauf m2 235.99 77,848.68 18,371,510.12

3 Pek. Kolom praktis 100x150


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 8.25 837,138.50 6,906,392.63
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 1,761.87 12,734.15 22,435,916.86
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 912.04 12,734.15 11,614,054.17
- Bekisting m2 149.34 189,953.50 28,367,655.69

4 Pek. Balok Praktis 100x200


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 3.32 837,138.50 2,779,299.82
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 592.06 12,734.15 7,539,380.85
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 255.20 12,734.15 3,249,755.08
- Bekisting m2 66.44 248,253.50 16,493,962.54

5 Pek. Kolom praktis Penggantung Balok Praktis 100x150


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 0.08 837,138.50 66,971.08
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 37.08 12,734.15 472,182.28
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 10.44 12,734.15 132,944.53
- Bekisting m2 1.62 189,953.50 307,724.67

6 Pek. Plesteran Dinding, Balok, Kolom dan Kusen MU Plester (50kg) m2 2,934.73 43,476.13 127,590,688.32
7 Pek. Acian Dinding, Balok, Kolom dan Kusen MU Acian (40kg) m2 2,934.73 30,229.38 88,715,053.69

III.B.2 PEK. PAS. PELAPISAN DINDING


1 Pek. Plat beton meja Wastafel
- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 0.12 837,138.50 100,456.62
- Besi Ø 8 - 150 (2 lapis) Mutu baja BJTP 24 (polos) kg 17.64 12,734.15 224,639.32
- Bekisting m2 1.16 233,953.50 271,386.06

2 Pek. Balok Beton Meja Wastafel


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 0.17 837,138.50 142,313.55
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 31.62 12,734.15 402,653.82
- Besi Ø 10 - 150 Mutu baja BJTP 24 (polos) kg 19.03 12,734.15 242,330.87
- Bekisting m2 2.31 251,278.50 580,453.34

3 Pek. Pelapis Meja Wastafel Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 1.16 173,387.50 201,129.50
4 Pek. List Meja Wastafel List Granit 100x600 m1 8.88 17,338.75 153,968.10

5 Pek. Pelapisan Dinding keramik KM/Toilet Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 114.98 167,722.50 19,284,733.05
6 Pek. Waterproofing dinding dan Lantai KM/ toilet Waterproofing Formdex Uniflex Cementitious Membrance, m2 66.53 36,850.00 2,451,630.50
Merk : Sika, Fosroc

7 Pek. Plint t.10cm Homogeneous Tile 600x600 Merk : Garuda Multipipe White m1 530.48 30,457.90 16,157,306.79
Pek. Pelapisan Dinding Entrance Lift Homogeneous Tile 600x600 Merk : Habitat Arabella m2 60.00 219,697.50 13,181,850.00
III.B.3 PEK. PAS. KUSEN, DAUN PINTU DAN JENDELA
1 Pek. Pintu P1 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 8.00 2,669,105.65 21,352,845.19
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO

2 Pek. Pintu P5 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 5.00 3,437,897.10 17,189,485.50
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Kaca Polos 6mm, Merk : Asahimas
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

3 Pek. Pintu P6 detail by Vendor (standar SNI) Ex. Spectrum unit 4.00 1,732,500.00 6,930,000.00
4 Pek. Pintu P7 detail by Vendor (standar SNI) Ex. Spectrum unit 1.00 1,732,500.00 1,732,500.00

5 Pek. Pintu Jendela PJ2 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 11.00 6,237,834.84 68,616,183.23
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Kaca Polos 6mm, Merk : Asahimas
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO

6 Pek. Jendela J1 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 1.00 2,103,365.00 2,103,365.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 6mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

7 Pek. Jendela J3 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 2.00 2,037,805.00 4,075,610.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 5mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

8 Pek. Jendela J4 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 5.00 4,261,675.00 21,308,375.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 5mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

9 Pek. Jendela J6 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 4,974,200.00 19,896,800.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 5mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

10 Pek. Jendela J7 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 6,023,050.00 24,092,200.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 5mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

11 Pek. Jendela J8 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 8,711,230.00 34,844,920.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 5mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

12 Pek. Jendela J9 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 2.00 5,113,790.00 10,227,580.00
Kaca Polos 5mm, Merk : Asahimas

13 Pek. Bouvenlight B1 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 296,540.75 1,186,163.00
Kaca Polos 6mm, Merk : Asahimas

III.B.4 PEK. PAS. PLAFOND


1 Pek. Rangka gypsum wet area Metal square hollow 40/20, tebal 1,1mm m2 35.19 57,193.13 2,012,626.07
Metal square hollow 40/40, tebal 1,1mm
2 Pek. Rangka Plafond Gypsum Metal square hollow 40/40, tebal 1,1mm m2 599.20 57,193.13 34,270,120.50
3 Pek. Rangka gypsum Selasar Metal square hollow 40/20, tebal 1,1mm m2 202.62 57,193.13 11,588,470.99
Metal square hollow 40/40, tebal 1,1mm

4 Pek. Plafond gypsum wet area Gypsumboard T.9mm, Merk : A-Plus m2 35.19 56,185.25 1,977,158.95
5 Pek. Plafond Gypsum Gypsumboard T.9mm, Merk : A-Plus m2 599.20 56,185.25 33,666,201.80
6 Pek. Plafond Gypsum Selasar Gypsumboard T.9mm, Merk : A-Plus m2 202.62 56,185.25 11,384,255.36

7 Pek. List Plafond gypsum wet area List plafond profil aluminium U, 1cm m1 48.23 18,179.15 876,780.40
8 Pek. List Plafond Plafond Gypsum List plafond profil aluminium U, 2cm m1 332.41 18,729.15 6,225,756.75
9 Pek. List Plafond Plafond Gypsum Selasar List plafond profil aluminium U, 2cm m1 156.80 18,729.15 2,936,730.72

III.B.5 PEK. PAS. PELAPISAN LANTAI


1 Pek. Plesteran (untuk leveling) MU Plester (50kg) m2 28.40 43,476.13 1,234,721.95
2 Pek. Lantai Homogenous Tile 600X600 Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 807.08 173,387.50 139,937,583.50
3 Pek. Pelapisan lantai kamar mandi 600x600 Homogeneous Tile 600x600 Merk : Vicenca GYK 6607 m2 32.04 222,884.75 7,141,227.39
4 Pek. Pelapisan Lantai Tangga Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 28.40 316,332.50 8,983,843.00
Pembuatan alur stepnoshing
5 Pek. Pelapisan Dinding Trap Tangga Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 10.82 316,332.50 3,422,717.65
6 Pek. Pelapisan Lantai Tangga Darurat Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 14.40 316,332.50 4,555,188.00
Pembuatan alur stepnoshing
7 Pek. Pelapisan Dinding Trap Tangga Darurat Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 5.46 316,332.50 1,727,175.45

III.B.6 PEK. PAS. FINISHING DAN PENGECATAN


1 Pek. Pengecatan dinding Fin. Cat Eksterior Cat dasar Jotun Jotashield Primer 7 m2 759.68 22,955.35 17,438,720.29
Cat tembok eksterior, setara Jotun Jotashield Antifade
2 Pek. Pengecatan dinding Fin. Cat Interior Cat dasar Jotun Base Coat Sealer m2 3,034.55 22,955.35 69,659,157.34
Cat tembok interior, setara Jotun Majestic True Beauty SHEEN
3 Pek. Pengecatan plafond Cat plafond, Merk : Vinilex m2 634.39 19,130.10 12,135,944.14
4 Pek. Pelapisan Dinding Granit Tangga Homogeneous Tile 600x600 Merk : Habitat Arabella m2 61.53 219,697.50 13,517,987.18

III.B.7 PEK. PAS. PLUMBING FIXTURES


1 Pek. Closet duduk Closet Duduk tipe CW660NJ/SW660J, Merk : Toto unit 8.00 2,000,680.00 16,005,440.00
2 Pek. Wasthafel Washtafel tipe LW813CJ, Kran washtafel Tipe TX109LD, Merk : Toto unit 4.00 1,472,845.00 5,891,380.00
3 Pek. Floor drain Floordrain tipe TX1C, Merk : Toto bh 8.00 50,248.00 401,984.00
4 Pek. Jet Washer Jet Washer tipe THX20NB, Merk : Toto unit 8.00 139,645.00 1,117,160.00
5 Pek. Divider Urinoir Divider Urinoir tipe A100, Merk : Toto unit 5.00 1,056,220.00 5,281,100.00
6 Pek. Urinoir Urinoir tipe U57, Merk : Toto unit 5.00 278,520.00 1,392,600.00
7 Pek. Partisi dan Pintu dinding toilet + Accessories tinggi 210 cm, cubical PVC, tipe Compact - Phenolic 12mm, Ex. Wimas unit 8.00 47,190.00 377,520.00
Frame Stainless Steel, Engsel, Kunci, Handle, dan Accs, Ex. Wimas
8 Pek. Kaca Cermin Merk : Asahimas m2 3.56 95,205.00 338,929.80

III.B.8 PEK. PAS. TANGGA


1 Pek. Railling Tangga Darurat Kayu Solid 20x80 + Pengecatan Kayu m1 14.79 350,662.66 5,186,300.71
Metal square hollow 40/40, tebal 1,1mm + Cat Anti Karat
Metal square hollow 40/60, tebal 1,0mm + Cat Anti Karat
Plat Besi t.8mm, Besi Nako 8mm
2 Pek. Railling Tangga Kayu Solid 20x80 + Pengecatan Kayu m1 26.60 177,321.39 4,716,748.87
Metal square hollow 40/40, tebal 1,1mm + Cat Anti Karat

JUMLAH PEKERJAAN ARSITEKTUR LANTAI 2 Rp. 1,167,869,439.36

III.C LANTAI 3
III.C.1 PEK. PAS. DINDING
1 Pek. Dinding bata ringan Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m2 1,111.20 104,335.00 115,937,052.00
2 Pek. Dinding Parapet Balkon Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m2 172.90 104,335.00 18,039,521.50

3 Pek. Kolom praktis 100x150


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 8.76 837,138.50 7,333,333.26
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 1,926.94 12,734.15 24,537,943.00
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 972.63 12,734.15 12,385,616.31
- Bekisting m2 183.54 189,953.50 34,864,065.39

4 Pek. Balok Praktis 100x200


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 4.25 837,138.50 3,557,838.63
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 709.34 12,734.15 9,032,841.96
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 323.30 12,734.15 4,116,950.70
- Bekisting m2 84.94 248,253.50 21,086,652.29

5 Pek. Kolom praktis Penggantung Balok Praktis 100x150


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 0.05 837,138.50 41,856.93
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 20.60 12,734.15 262,323.49
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 5.80 12,734.15 73,858.07
- Bekisting m2 0.90 189,953.50 170,958.15

6 Pek. Plesteran Dinding, Balok, Kolom dan Kusen MU Plester (50kg) m2 2,681.94 43,476.13 116,600,358.68
7 Pek. Acian Dinding, Balok, Kolom dan Kusen MU Acian (40kg) m2 2,681.94 30,229.38 81,073,369.99

III.C.2 PEK. PAS. PELAPISAN DINDING


1 Pek. Plat beton meja Wastafel
- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 0.12 837,138.50 100,456.62
- Besi Ø 8 - 150 (2 lapis) Mutu baja BJTP 24 (polos) kg 17.64 12,734.15 224,639.32
- Bekisting m2 1.16 233,953.50 271,386.06

2 Pek. Balok Beton Meja Wastafel


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 0.17 837,138.50 142,313.55
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 31.62 12,734.15 402,653.82
- Besi Ø 10 - 150 Mutu baja BJTP 24 (polos) kg 19.03 12,734.15 242,330.87
- Bekisting m2 2.31 251,278.50 580,453.34

3 Pek. Pelapis Meja Wastafel Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 1.16 173,387.50 201,129.50
4 Pek. List Meja Wastafel List Granit 100x600 m1 8.88 17,338.75 153,968.10

5 Pek. Pelapisan Dinding keramik KM/Toilet Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 114.98 167,722.50 19,284,733.05
6 Pek. Waterproofing dinding dan Lantai KM/ toilet Waterproofing Formdex Uniflex Cementitious Membrance, m2 66.53 36,850.00 2,451,630.50
Merk : Sika, Fosroc

7 Pek. Plint t.10cm Homogeneous Tile 600x600 Merk : Garuda Multipipe White m1 625.58 30,457.90 19,053,853.08

III.C.3 PEK. PAS. KUSEN, DAUN PINTU DAN JENDELA


1 Pek. Pintu P2' Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 2,310,811.92 9,243,247.67
Sudah termasuk metal close untuk engsel
Metal square hollow 20/20, tebal 0,9mm + Cat Anti Karat
Metal square hollow 40/40, tebal 1,1mm + Cat Anti Karat
Plat Besi + Cat Anti Karat
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO

2 Pek. Pintu P4 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 2.00 5,252,592.34 10,505,184.68
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Kaca Polos 6mm, Merk : Asahimas
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

3 Pek. Pintu P5 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 3.00 3,437,897.10 10,313,691.30
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Kaca Polos 6mm, Merk : Asahimas
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"
4 Pek. Pintu P6 detail by Vendor (standar SNI) Ex. Spectrum unit 4.00 1,732,500.00 6,930,000.00
5 Pek. Pintu P7 detail by Vendor (standar SNI) Ex. Spectrum unit 1.00 1,732,500.00 1,732,500.00

6 Pek. Pintu P9 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 2.00 6,231,529.70 12,463,059.40
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Kaca Polos 6mm, Merk : Asahimas
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

7 Pek. Pintu Jendela PJ2 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 6,237,834.84 24,951,339.36
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Kaca Polos 6mm, Merk : Asahimas
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO

8 Pek. Jendela J2 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 2,957,350.00 11,829,400.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 6mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

9 Pek. Jendela J3 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 12.00 2,037,805.00 24,453,660.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 5mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

10 Pek. Jendela J4 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 4,261,675.00 17,046,700.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 5mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

11 Pek. Jendela J5 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 4,508,900.00 18,035,600.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 6mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

12 Pek. Jendela J6 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 5.00 4,974,200.00 24,871,000.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 5mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

13 Pek. Bouvenlight B1 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 296,540.75 1,186,163.00
Kaca Polos 6mm, Merk : Asahimas

III.C.4 PEK. PAS. PLAFOND


1 Pek. Rangka gypsum wet area Metal square hollow 40/20, tebal 1,1mm m2 100.59 57,193.13 5,753,056.44
Metal square hollow 40/40, tebal 1,1mm
2 Pek. Rangka Plafond Gypsum Metal square hollow 40/40, tebal 1,1mm m2 600.50 57,193.13 34,344,471.56
3 Pek. Rangka gypsum Selasar Metal square hollow 40/20, tebal 1,1mm m2 205.00 57,193.13 11,724,590.63
Metal square hollow 40/40, tebal 1,1mm
4 Pek. Rangka Drop Ceilling Metal square hollow 40/20, tebal 1,1mm m2 86.46 57,193.13 4,944,917.59
Metal square hollow 40/40, tebal 1,1mm

5 Pek. Plafond gypsum wet area Gypsumboard T.9mm, Merk : A-Plus m2 100.59 56,185.25 5,651,674.30
6 Pek. Plafond Gypsum Gypsumboard T.9mm, Merk : A-Plus m2 600.50 56,185.25 33,739,242.63
7 Pek. Plafond Gypsum Selasar Gypsumboard T.9mm, Merk : A-Plus m2 205.00 56,185.25 11,517,976.25
8 Pek. Pas. Drop Ceilling Gypsumboard T.9mm, Merk : A-Plus m2 86.46 56,185.25 4,857,776.72

9 Pek. List Plafond gypsum wet area List plafond profil aluminium U, 1cm m1 208.63 18,179.15 3,792,716.06
10 Pek. List Plafond Plafond Gypsum List plafond profil aluminium U, 2cm m1 270.15 18,729.15 5,059,679.87
11 Pek. List Plafond Plafond Gypsum Selasar List plafond profil aluminium U, 2cm m1 161.70 18,729.15 3,028,503.56

III.C.5 PEK. PAS. PELAPISAN LANTAI


1 Pek. Plesteran (untuk leveling) MU Plester (50kg) m2 32.04 43,476.13 1,392,975.05
2 Pek. Lantai Homogenous Tile 600X600 Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 811.44 173,387.50 140,693,553.00
3 Pek. Pelapisan lantai kamar mandi 600x600 Homogeneous Tile 600x600 Merk : Vicenca GYK 6607 m2 32.04 222,884.75 7,141,227.39
4 Pek. Guiding Block tipe line Tactile Tipe line Aluminium bh 1,112.00 8,696.88 9,670,925.00
5 Pek. Guiding Block tipe dot Tactile tipe dot Aluminium bh 864.00 7,115.63 6,147,900.00
6 Pek. Pelapisan Lantai Tangga Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 28.40 316,332.50 8,983,843.00
Pembuatan alur stepnoshing
7 Pek. Pelapisan Dinding Trap Tangga Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 10.82 316,332.50 3,422,717.65
8 Pek. Pelapisan Lantai Tangga Darurat Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 14.40 316,332.50 4,555,188.00
Pembuatan alur stepnoshing
9 Pek. Pelapisan Dinding Trap Tangga Darurat Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 5.46 316,332.50 1,727,175.45

III.C.6 PEK. PAS. FINISHING DAN PENGECATAN


1 Pek. Pengecatan dinding Fin. Cat Eksterior Cat dasar Jotun Jotashield Primer 7 m2 1,105.48 22,955.35 25,376,680.32
Cat tembok eksterior, setara Jotun Jotashield Antifade
2 Pek. Pengecatan dinding Fin. Cat Interior Cat dasar Jotun Base Coat Sealer m2 2,058.18 22,955.35 47,246,242.26
Cat tembok interior, setara Jotun Majestic True Beauty SHEEN
3 Pek. Pengecatan plafond Cat plafond, Merk : Vinilex m2 992.55 19,130.10 18,987,580.76
4 Pek. Pelapisan Dinding Granit Tangga Homogeneous Tile 600x600 Merk : Habitat Arabella m2 14.65 219,697.50 3,218,568.38

III.C.7 PEK. PAS. PLUMBING FIXTURES


1 Pek. Closet duduk Closet Duduk tipe CW660NJ/SW660J, Merk : Toto unit 8.00 2,000,680.00 16,005,440.00
2 Pek. Wasthafel Washtafel tipe LW813CJ, Kran washtafel Tipe TX109LD, Merk : Toto unit 4.00 1,472,845.00 5,891,380.00
3 Pek. Floor drain Floordrain tipe TX1C, Merk : Toto bh 8.00 50,248.00 401,984.00
4 Pek. Jet Washer Jet Washer tipe THX20NB, Merk : Toto unit 8.00 139,645.00 1,117,160.00
5 Pek. Divider Urinoir Divider Urinoir tipe A100, Merk : Toto unit 5.00 1,056,220.00 5,281,100.00
6 Pek. Urinoir Urinoir tipe U57, Merk : Toto unit 5.00 278,520.00 1,392,600.00
7 Pek. Partisi dan Pintu dinding toilet + Accessories tinggi 210 cm, cubical PVC, tipe Compact - Phenolic 12mm, Ex. Wimas unit 8.00 47,190.00 377,520.00
Frame Stainless Steel, Engsel, Kunci, Handle, dan Accs, Ex. Wimas
8 Pek. Kaca Cermin Merk : Asahimas m2 3.56 95,205.00 338,929.80

III.C.8 PEK. PAS. TANGGA


1 Pek. Railling Tangga Darurat Kayu Solid 20x80 + Pengecatan Kayu m1 14.79 350,662.66 5,186,300.71
Metal square hollow 40/40, tebal 1,1mm + Cat Anti Karat
Metal square hollow 40/60, tebal 1,0mm + Cat Anti Karat
Plat Besi t.8mm, Besi Nako 8mm
2 Pek. Railling Tangga Kayu Solid 20x80 + Pengecatan Kayu m1 26.60 177,321.39 4,716,748.87
Metal square hollow 40/40, tebal 1,1mm + Cat Anti Karat

JUMLAH PEKERJAAN ARSITEKTUR LANTAI 3 Rp. 1,109,473,978.78

III.D LANTAI 4
III.D.1 PEK. PAS. DINDING
1 Pek. Dinding bata ringan Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m2 1,179.16 104,335.00 123,027,658.60
2 Pek. Dinding Parapet Balkon Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m2 170.62 104,335.00 17,801,637.70

3 Pek. Kolom praktis 100x150


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 9.46 837,138.50 7,919,330.21
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 2,074.88 12,734.15 26,421,833.15
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 1,049.22 12,734.15 13,360,924.86
- Bekisting m2 196.08 189,953.50 37,246,082.28

4 Pek. Balok Praktis 100x200


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 4.35 837,138.50 3,641,552.48
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 729.74 12,734.15 9,292,618.62
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 330.92 12,734.15 4,213,984.92
- Bekisting m2 86.90 248,253.50 21,573,229.15

5 Pek. Kolom praktis Penggantung Balok Praktis 100x150


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 0.06 837,138.50 50,228.31
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 28.84 12,734.15 367,252.89
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 8.12 12,734.15 103,401.30
- Bekisting m2 1.26 189,953.50 239,341.41

6 Pek. Plesteran Dinding, Balok, Kolom dan Kusen MU Plester (50kg) m2 2,726.06 43,476.13 118,518,525.32
7 Pek. Acian Dinding, Balok, Kolom dan Kusen MU Acian (40kg) m2 2,726.06 30,229.38 82,407,090.01

III.D.2 PEK. PAS. PELAPISAN DINDING


1 Pek. Plat beton meja Wastafel
- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 0.12 837,138.50 100,456.62
- Besi Ø 8 - 150 (2 lapis) Mutu baja BJTP 24 (polos) kg 17.64 12,734.15 224,639.32
- Bekisting m2 1.16 233,953.50 271,386.06

2 Pek. Balok Beton Meja Wastafel


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 0.17 837,138.50 142,313.55
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 31.62 12,734.15 402,653.82
- Besi Ø 10 - 150 Mutu baja BJTP 24 (polos) kg 19.03 12,734.15 242,330.87
- Bekisting m2 2.31 251,278.50 580,453.34

3 Pek. Pelapis Meja Wastafel Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 1.16 173,387.50 201,129.50
4 Pek. List Meja Wastafel List Granit 100x600 m1 8.88 17,338.75 153,968.10

5 Pek. Pelapisan Dinding keramik KM/Toilet Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 114.98 167,722.50 19,284,733.05
6 Pek. Waterproofing dinding dan Lantai KM/ toilet Waterproofing Formdex Uniflex Cementitious Membrance, m2 66.53 36,850.00 2,451,630.50
Merk : Sika, Fosroc

7 Pek. Plint t.10cm Homogeneous Tile 600x600 Merk : Garuda Multipipe White m1 628.73 30,457.90 19,149,795.47

III.D.3 PEK. PAS. KUSEN, DAUN PINTU DAN JENDELA


1 Pek. Pintu P2' Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 8.00 2,310,811.92 18,486,495.35
Sudah termasuk metal close untuk engsel
Metal square hollow 20/20, tebal 0,9mm + Cat Anti Karat
Metal square hollow 40/40, tebal 1,1mm + Cat Anti Karat
Plat Besi + Cat Anti Karat
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO
2 Pek. Pintu P4 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 5.00 5,252,592.34 26,262,961.69
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Kaca Polos 6mm, Merk : Asahimas
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

3 Pek. Pintu P5 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 3.00 3,437,897.10 10,313,691.30
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Kaca Polos 6mm, Merk : Asahimas
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

4 Pek. Pintu P6 detail by Vendor (standar SNI) Ex. Spectrum unit 4.00 1,732,500.00 6,930,000.00
5 Pek. Pintu P7 detail by Vendor (standar SNI) Ex. Spectrum unit 1.00 1,732,500.00 1,732,500.00

6 Pek. Pintu Jendela PJ2 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 6,237,834.84 24,951,339.36
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo
Kaca Polos 6mm, Merk : Asahimas
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO

7 Pek. Jendela J2 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 2,957,350.00 11,829,400.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 6mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

8 Pek. Jendela J3 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 10.00 2,037,805.00 20,378,050.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 5mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

9 Pek. Jendela J4 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 4,261,675.00 17,046,700.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 5mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

10 Pek. Jendela J5 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 4,508,900.00 18,035,600.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 6mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

11 Pek. Jendela J6 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 4,974,200.00 19,896,800.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 5mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

12 Pek. Jendela J8 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 1.00 8,711,230.00 8,711,230.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo
Kaca Polos 6mm, Merk : Asahimas
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16"

13 Pek. Bouvenlight B1 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo unit 4.00 296,540.75 1,186,163.00
Kaca Polos 6mm, Merk : Asahimas

III.D.4 PEK. PAS. PLAFOND


1 Pek. Rangka gypsum wet area Metal square hollow 40/20, tebal 1,1mm m2 100.59 57,193.13 5,753,056.44
Metal square hollow 40/40, tebal 1,1mm
2 Pek. Rangka Plafond Gypsum Metal square hollow 40/40, tebal 1,1mm m2 603.62 57,193.13 34,522,914.11
3 Pek. Rangka gypsum Selasar Metal square hollow 40/20, tebal 1,1mm m2 210.60 57,193.13 12,044,872.13
Metal square hollow 40/40, tebal 1,1mm

4 Pek. Plafond gypsum wet area Gypsumboard T.9mm, Merk : A-Plus m2 100.59 56,185.25 5,651,674.30
5 Pek. Plafond Gypsum Gypsumboard T.9mm, Merk : A-Plus m2 603.62 56,185.25 33,914,540.61
6 Pek. Plafond Gypsum Selasar Gypsumboard T.9mm, Merk : A-Plus m2 210.60 56,185.25 11,832,613.65

7 Pek. List Plafond gypsum wet area List plafond profil aluminium U, 1cm m1 208.63 18,179.15 3,792,716.06
8 Pek. List Plafond Plafond Gypsum List plafond profil aluminium U, 2cm m1 302.80 18,729.15 5,671,186.62
9 Pek. List Plafond Plafond Gypsum Selasar List plafond profil aluminium U, 2cm m1 169.10 18,729.15 3,167,099.27

III.D.5 PEK. PAS. PELAPISAN LANTAI


1 Pek. Plesteran (untuk leveling) MU Plester (50kg) m2 28.40 43,476.13 1,234,721.95
2 Pek. Lantai Homogenous Tile 600X600 Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 818.60 173,387.50 141,935,007.50
3 Pek. Pelapisan lantai kamar mandi 600x00 Homogeneous Tile 600x600 Merk : Vicenca GYK 6607 m2 32.04 222,884.75 7,141,227.39
4 Pek. Pelapisan Lantai Tangga Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 28.40 316,332.50 8,983,843.00
Pembuatan alur stepnoshing
5 Pek. Pelapisan Dinding Trap Tangga Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 10.82 316,332.50 3,422,717.65
6 Pek. Pelapisan Lantai Tangga Darurat Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 14.40 316,332.50 4,555,188.00
Pembuatan alur stepnoshing
7 Pek. Pelapisan Dinding Trap Tangga Darurat Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : N m2 5.46 316,332.50 1,727,175.45

III.D.6 PEK. PAS. FINISHING DAN PENGECATAN


1 Pek. Pengecatan dinding Fin. Cat Eksterior Cat dasar Jotun Jotashield Primer 7 m2 1,105.48 22,955.35 25,376,680.32
Cat tembok eksterior, setara Jotun Jotashield Antifade
2 Pek. Pengecatan dinding Fin. Cat Interior Cat dasar Jotun Base Coat Sealer m2 1,966.96 22,955.35 45,152,255.24
Cat tembok interior, setara Jotun Majestic True Beauty SHEEN
3 Pek. Pengecatan plafond Cat plafond, Merk : Vinilex m2 704.21 19,130.10 13,471,607.72
4 Pek. Pelapisan Dinding Granit Tangga Homogeneous Tile 600x600 Merk : Habitat Arabella m2 14.65 219,697.50 3,218,568.38

III.D.7 PEK. PAS. PLUMBING FIXTURES


1 Pek. Closet duduk Closet Duduk tipe CW660NJ/SW660J, Merk : Toto unit 8.00 2,000,680.00 16,005,440.00
2 Pek. Wasthafel Washtafel tipe LW813CJ, Kran washtafel Tipe TX109LD, Merk : Toto unit 4.00 1,472,845.00 5,891,380.00
3 Pek. Floor drain Floordrain tipe TX1C, Merk : Toto bh 8.00 50,248.00 401,984.00
4 Pek. Jet Washer Jet Washer tipe THX20NB, Merk : Toto unit 8.00 139,645.00 1,117,160.00
5 Pek. Divider Urinoir Divider Urinoir tipe A100, Merk : Toto unit 5.00 1,056,220.00 5,281,100.00
6 Pek. Urinoir Urinoir tipe U57, Merk : Toto unit 5.00 278,520.00 1,392,600.00
7 Pek. Partisi dan Pintu dinding toilet + Accessories tinggi 210 cm, cubical PVC, tipe Compact - Phenolic 12mm, Ex. Wimas unit 8.00 47,190.00 377,520.00
Frame Stainless Steel, Engsel, Kunci, Handle, dan Accs, Ex. Wimas
8 Pek. Kaca Cermin Merk : Asahimas m2 3.56 95,205.00 338,929.80

III.D.8 PEK. PAS. TANGGA


1 Pek. Railling Tangga Darurat Kayu Solid 20x80 Fin. melamic m1 14.79 350,662.66 5,186,300.71
Metal square hollow 40/40, tebal 1,1mm + Cat Anti Karat
Plat Besi t.8mm, Besi Nako 8mm
2 Pek. Railling Tangga Kayu Solid 20x80 + Pengecatan Kayu m1 26.60 177,321.39 4,716,748.87
Metal square hollow 40/40, tebal 1,1mm + Cat Anti Karat

JUMLAH PEKERJAAN ARSITEKTUR LANTAI 4 Rp. 1,108,429,941.25

III.E LANTAI ROOFTOP


III.E.1 PEK. PAS. DINDING
1 Pek. Dinding bata ringan Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m2 295.10 104,335.00 30,789,258.50
2 Pek. Dinding Parapet Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m2 101.64 104,335.00 10,604,609.40

3 Pek. Kolom praktis 100x150


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 2.19 837,138.50 1,833,333.32
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 559.98 12,734.15 7,130,869.32
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 248.70 12,734.15 3,166,983.11
- Bekisting m2 63.90 189,953.50 12,138,028.65

4 Pek. Balok Praktis 100x200


- Cor Beton Cor beton Ready mix K-175 fc' : 14,50 Mpa m3 3.52 837,138.50 2,946,727.52
- Besi 4Ø 10 Mutu baja BJTP 24 (polos) kg 471.22 12,734.15 6,000,586.16
- Besi Ø 8 - 150 Mutu baja BJTP 24 (polos) kg 256.73 12,734.15 3,269,238.33
- Bekisting m2 70.36 248,253.50 17,467,116.26

5 Pek. Plesteran Dinding, Balok, Kolom dan Kusen MU Plester (50kg) m2 1,113.73 43,476.13 48,420,664.70
6 Pek. Acian Dinding, Balok, Kolom dan Kusen MU Acian (40kg) m2 1,113.73 30,229.38 33,667,361.82

III.E.2 PEK. PAS. PELAPISAN DINDING


1 Pek. Plint t.10cm Homogeneous Tile 600x600 Merk : Garuda Multipipe White m1 22.00 30,457.90 670,073.80

III.E.3 PEK. PAS. KUSEN, DAUN PINTU DAN JENDELA


1 Pek. Pintu P11 CNP 150.50.20.3,2 unit 5.00 15,423,579.90 77,117,899.48
Rangka Besi Siku
Plat Baja 1.8mm
Pengecatan Duco
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO

III.E.4 PEK. PAS. PELAPISAN LANTAI


1 Pek. Plesteran (untuk leveling) MU Plester (50kg) m2 6.40 43,476.13 278,247.20
2 Pek. Lantai Homogenous Tile 600X600 Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 6.40 173,387.50 1,109,680.00

III.E.5 PEK. PAS. FINISHING DAN PENGECATAN


1 Pek. Pengecatan dinding Fin. Cat Eksterior Cat dasar Jotun Jotashield Primer 7 m2 1,070.64 22,955.35 24,576,915.92
Cat tembok eksterior, setara Jotun Jotashield Antifade
2 Pek. Pengecatan dinding Fin. Cat Interior Cat dasar Jotun Base Coat Sealer m2 840.00 22,955.35 19,282,494.00
Cat tembok interior, setara Jotun Majestic True Beauty SHEEN

III.F PEK. PAS. RANGKA DAN PENUTUP ATAP


1 Pek. Plesteran Dak, Balon dan R. Praktek MU Plester (50kg) m2 813.72 43,476.13 35,377,392.44
2 Pek. Acian Dak, Balon dan R. Praktek MU Acian (40kg) m2 813.72 30,229.38 24,598,247.03
3 Pek. Waterproofing Dak, Balkon dan R. Praktek Waterproofing DUO Composite membrane, ex. De Boer m2 813.72 296,796.30 241,509,082.22

4 Pek. Atap Genteng Type Pelat Datar Merk : Kanmuri m2 1,242.72 156,739.00 194,782,690.08
5 Pek. Aluminium Foil m2 1,242.72 2,500.00 3,106,800.00
6 Pek. Pas. Nok Atap m1 119.32 126,000.00 15,034,320.00
7 Pek. Pas. Ridge Tree / Menara Nok bh 619.00 75,000.00 46,425,000.00

8 Pek. Rangka gypsum Metal square hollow 40/20, tebal 1,1mm m2 874.00 56,000.00 48,944,000.00
Metal square hollow 40/40, tebal 1,1mm
9 Pek. Plafond gypsum Gypsumboard AquaLine 600x600 T.9mm, setara Gyproc m2 874.00 56,185.25 49,105,908.50
10 Pek. Pengecatan Plafond Cat plafond, Merk : Vinilex m2 874.00 19,130.10 16,719,707.40

11 Pek. Atap Transparan flexible polycarbonate 2mm ultraviolet m2 82.00 30,596.61 2,508,922.33

12 Pek. Listplank Kalsiplank 8mm, uk. 0,2x3m m1 212.60 61,050.00 12,979,230.00


13 Pek. Talang Vertikal air hujan Ø4" Pipa PVC 4" m1 420.00 54,790.31 23,011,931.25
14 Pek. Pengecatan Talang Vertikal Cat besi m2 98.91 25,000.00 2,472,750.00

JUMLAH PEKERJAAN ARSITEKTUR LANTAI ROOFTOOP Rp. 1,017,046,068.72


TOTAL PEKERJAAN ARSITEKTUR Rp. 5,586,570,219.30
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME
Rp. Rp.
1 2 3 4 5 6 (5 X 6)

IV.1 PEKERJAAN PLUMBING


IV.1.1 Pekerjaan Instalasi Air Bersih
1 Peralatan Utama
1 Ground Reservoir & Ruang Pompa kap. 158 M3 unit Bak GR - By Struktur
- Floating valve dia. 40 Standard SNI, Merk : Socla, Yuta, setara bh 2.00 435,655.00 871,310.00
- Water Level Control (WLC) bh 1.00 8,343,830.00 8,343,830.00
- Pipa GIP dia. 150 mm, penghubung Suction pit ke GWT Standard SNI, Kelas medium, merk : PPI, Bakri m' 1.70 86,325.45 146,753.26
- Butterfly Valve dia. 150 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 2.00 8,280,690.00 16,561,380.00

2 Pembuatan Sumur Dalam (kedalaman 90 meter) Unit 1.00 66,577,500.00 66,577,500.00


lengkap pompa, pemipaan dengan accessories, serta pemipaan dari deepwell menuju
ke GWT Row Water ruang pompa.

3 Biaya sambungan PDAM , lengkap meteran air diameter 1 1/2 " Unit 1.00 9,699,415.00 9,699,415.00
4 Pipa dari Meter Air PDAM ke GWT, PVC dia 40 mm Standard SNI, merk : Rucika, Wavin m' 30.00 32,596.34 977,890.18

5 Pompa Filter Air bersih (PF.1 & PF.2) Jenis centrifugal end suction pump, kapasitas : 100 lpm, head 35 m Unit 2.00 25,095,400.00 50,190,800.00
- Aksesoris : Standard SNI, merk : Ebara, Grundfos, Torishima
- Fleksible joint dia. 40 mm Standard SNI, merk : Tozen, AFA Flex bh 4.00 964,405.36 3,857,621.43
- Check valve dia. 40 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 2.00 3,879,405.36 7,758,810.71
- Gate valve dia. 40 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 4.00 3,329,405.36 13,317,621.43
- Y strainer dia. 40 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 2.00 304,405.36 608,810.71

- Panel control dan pengkabelan Standard SNI set 1.00 0.00

6 Pompa Sumpit (pompa submersible) Submersible Pump, kapasitas : 60 lpm, head 10 m unit 1.00 19,490,625.00 19,490,625.00
- Aksesoris : Standard SNI, merk : Ebara, Grundfos, Torishima
- Fleksible joint dia. 32 mm Standard SNI, merk : Tozen, AFA Flex bh 1.00 744,405.36 744,405.36
- Check Valve dia. 32 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 1.00 3,329,405.36 3,329,405.36
- Gate valve dia. 32 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 1.00 2,779,405.36 2,779,405.36

7 Instalasi pemipaan di ruang pompa dan atau ke bangunan


- Pemipaan dari Pompa Filter ke GWT
- Pipa GIP dia. 40 mm (Suction pompa sampe header discharge pompa) Standard SNI, Kelas medium, merk : PPI, Bakri m' 4.00 45,576.34 182,305.36
- Pipa PVC dia. 40 mm (dari header discharge pompa sampai GWT) Standard SNI, merk : Rucika, Wavin m' 12.00 32,596.34 391,156.07

- Accesories
- Gate Valve dia. 25 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 2.00 11,566,643.00 23,133,286.00
- Gate Valve dia. 40 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 3.00 3,054,405.36 9,163,216.07

- Pemipaan air bersih dari Pompa ke bangunan


- Pipa GIP dia. 50 mm (Suction pompa sampe header discharge pompa) Standard SNI, Kelas medium, merk : PPI, Bakri m' 4.00 75,654.46 302,617.86
- Pipa PVC dia. 50 mm (dari header discharge pompa sampai ke shaft bangunan) Standard SNI, merk : Rucika, Wavin m' 87.00 37,913.66 3,298,488.48

- Pemipaan dari pompa sumpit menuju ke drainase bangunan


- Pipa PVC dia. 32 mm Standard SNI, merk : Rucika, Wavin m' 15.00 26,821.34 402,320.09

2 Instalasi pemipaan
Pemipaan air bersih menggunakan PVC kelas AW
lengkap fitting dan alat bantunya.

1 Lantai 1
a. Pemipaan toilet
- dia. 15 mm Standard SNI, merk : Rucika, Wavin m' 86.00 14,068.21 1,209,866.43
- dia. 20 mm m' 5.00 15,752.59 78,762.95
- dia. 25 mm m' 4.00 25,377.59 101,510.36
- dia. 32 mm m' 10.00 26,821.34 268,213.39
- dia. 40 mm m' 3.00 32,596.34 97,789.02
b. Valve-valve
- Gate valve dia. 20 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 1.00 11,566,643.00 11,566,643.00
- Gate valve dia. 32 mm bh 1.00 2,779,405.36 2,779,405.36
- Gate valve dia. 40 mm bh 2.00 3,054,405.36 6,108,810.71

2 Lantai 2
a. Pemipaan toilet
- dia. 15 mm Standard SNI, merk : Rucika, Wavin m' 83.00 14,068.21 1,167,661.79
- dia. 20 mm m' 5.00 15,752.59 78,762.95
- dia. 25 mm m' 4.00 25,377.59 101,510.36
- dia. 32 mm m' 10.00 26,821.34 268,213.39
- dia. 40 mm m' 3.00 32,596.34 97,789.02
b. Valve-valve
- Gate valve dia. 32 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 1.00 2,779,405.36 2,779,405.36
- Gate valve dia. 40 mm bh 2.00 3,054,405.36 6,108,810.71

3 Lantai 3
a. Pemipaan toilet
- dia. 15 mm Standard SNI, merk : Rucika, Wavin m' 83.00 14,068.21 1,167,661.79
- dia. 20 mm m' 5.00 15,752.59 78,762.95
- dia. 25 mm m' 4.00 25,377.59 101,510.36
- dia. 32 mm m' 10.00 26,821.34 268,213.39
- dia. 40 mm m' 3.00 32,596.34 97,789.02
b. Valve-valve
- Gate valve dia. 32 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 1.00 2,779,405.36 2,779,405.36
- Gate valve dia. 40 mm bh 2.00 3,054,405.36 6,108,810.71

4 Lantai 4
a. Pemipaan toilet
- dia. 15 mm Standard SNI, merk : Rucika, Wavin m' 83.00 14,068.21 1,167,661.79
- dia. 20 mm m' 5.00 15,752.59 78,762.95
- dia. 25 mm m' 4.00 25,377.59 101,510.36
- dia. 32 mm m' 10.00 26,821.34 268,213.39
- dia. 40 mm m' 3.00 32,596.34 97,789.02
b. Valve-valve
- Gate valve dia. 32 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 1.00 2,779,405.36 2,779,405.36
- Gate valve dia. 40 mm bh 2.00 3,054,405.36 6,108,810.71

5 Lantai Atap
a. Tangki Air
- Rooftank kap. 6000 liter + dudukan (Baja IWF dan Plat Bordes) unit 1.00 84,851,250.00 84,851,250.00
- Accessories:
Level water control set 1.00 8,343,830.00 8,343,830.00
Floating valve dia. 50 mm bh 1.00 441,705.00 441,705.00
Gate valve dia. 50 mm bh 1.00 3,329,405.36 3,329,405.36
Gate valve dia. 80 mm bh 2.00 5,521,868.00 11,043,736.00
Header dia. 100 mm (panjang 1,5 meter) bh 1.00 451,818.45 451,818.45

b. Packaged Booster pumps kapasitas 165 lpm , head 10 meter (1 operasi, 1 standby) unit 1.00 25,721,575.00 25,721,575.00
- Accessories
Flexible Connection dia. 50 mm Standard SNI, merk : Tozen, AFA Flex bh 2.00 964,405.36 1,928,810.71
Gate Valve dia. 50 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 2.00 3,329,405.36 6,658,810.71
Y - Strainer dia. 50 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 2.00 304,405.36 608,810.71
c. Pipa supply dan pengisian rooftank lantai atap
- pipa dia. 50 mm Standard SNI, merk : Rucika, Wavin m' 43.00 37,913.66 1,630,287.41
- pipa dia. 65 mm m' 17.00 43,688.66 742,707.23
- pipa dia. 80 mm m' 2.50 58,126.16 145,315.40
- Gate valve dia. 50 mm Standard SNI, Kelas 10 K, merk : Kitz, Toyo bh 1.00 3,329,405.36 3,329,405.36
- Gate valve dia. 65 mm bh 2.00 3,871,868.00 7,743,736.00

6 Pipa Riser di Shaft


- Pipa dia. 50 mm Standard SNI, merk : Rucika, Wavin m' 12.00 37,913.66 454,963.93
- Pipa dia. 40 mm m' 8.00 32,596.34 260,770.71

IV.1.2 Pekerjaan Air Kotor


1 Instalasi Pemipaan Standard SNI, merk : Rucika, Wavin
Pipa Air Kotor PVC kelas 10 kg/cm2 termasuk fitting & alat bantunya
1. Pemipaan lantai 1
Pipa air kotor & air bekas
- PVC dia. 100 mm m' 24.20 65,344.91 1,581,347
- PVC dia. 80 mm m' 9.00 58,126.16 523,135
- PVC dia. 65 mm m' 7.80 43,688.66 340,772
- PVC dia. 50 mm m' 19.00 37,913.66 720,360
- Clean Out (CO) dia. 100 mm bh 1.00 301,242.86 301,243
- Clean Out (CO) dia. 65 mm bh 3.00 218,742.86 656,229
- Floor Drain toilet dia. 65mm bh 10.00 57,867.86 578,679
- Floor Drain Balkon dia. 50 mm bh 16.00 49,617.86 793,886

Pipa Vent
- PVC dia 65 mm m' 1.20 43,688.66 52,426
- PVC dia 50 mm m' 5.50 37,913.66 208,525
- PVC dia 40 mm m' 4.80 32,596.34 156,462
- PVC dia 32 mm m' 32.90 26,821.34 882,422
- PVC dia 25 mm m' 29.60 25,377.59 751,177

2. Pemipaan lantai 2
Pipa air kotor & air bekas Standard SNI, merk : Rucika, Wavin
- PVC dia. 100 mm termasuk fitting & alat bantunya m' 25.00 65,344.91 1,633,623
- PVC dia. 80 mm m' 9.00 58,126.16 523,135
- PVC dia. 65 mm m' 3.00 43,688.66 131,066
- PVC dia. 50 mm m' 2.00 37,913.66 75,827
- Clean Out (CO) dia. 100 mm bh 2.00 301,242.86 602,485.71
- Clean Out (CO) dia. 65 mm bh 2.00 218,742.86 437,485.71
- Floor Drain toilet dia. 65mm bh 10.00 57,867.86 578,679
- Floor Drain Balkon dia. 50 mm bh 16.00 49,617.86 793,886

Pipa Vent
- PVC dia 65 mm m' 1.20 43,688.66 52,426
- PVC dia 50 mm m' 5.50 37,913.66 208,525
- PVC dia 40 mm m' 4.80 32,596.34 156,462
- PVC dia 32 mm m' 32.90 26,821.34 882,422
- PVC dia 25 mm m' 29.60 25,377.59 751,177

3. Pemipaan lantai 3
Pipa air kotor & air bekas Standard SNI, merk : Rucika, Wavin
- PVC dia. 100 mm termasuk fitting & alat bantunya m' 25.00 65,344.91 1,633,623
- PVC dia. 80 mm m' 9.00 58,126.16 523,135
- PVC dia. 65 mm m' 3.00 43,688.66 131,066
- PVC dia. 50 mm m' 2.00 37,913.66 75,827
- Clean Out (CO) dia. 100 mm bh 2.00 301,242.86 602,486
- Clean Out (CO) dia. 65 mm bh 2.00 218,742.86 437,486
- Floor Drain toilet dia. 65mm bh 10.00 57,867.86 578,679
- Floor Drain Balkon dia. 50 mm bh 16.00 49,617.86 793,886

Pipa Vent
- PVC dia 65 mm m' 1.20 43,688.66 52,426
- PVC dia 50 mm m' 5.50 37,913.66 208,525
- PVC dia 40 mm m' 4.80 32,596.34 156,462
- PVC dia 32 mm m' 32.90 26,821.34 882,422
- PVC dia 25 mm m' 29.60 25,377.59 751,177

4. Pemipaan lantai 4
Pipa air kotor & air bekas Standard SNI, merk : Rucika, Wavin
- PVC dia. 100 mm termasuk fitting & alat bantunya m' 25.00 65,344.91 1,633,623
- PVC dia. 80 mm m' 9.00 58,126.16 523,135
- PVC dia. 65 mm m' 3.00 43,688.66 131,066
- PVC dia. 50 mm m' 2.00 37,913.66 75,827
- Clean Out (CO) dia. 100 mm bh 2.00 301,242.86 602,486
- Clean Out (CO) dia. 65 mm bh 2.00 218,742.86 437,486
- Floor Drain toilet dia. 65mm bh 10.00 57,867.86 578,679
- Floor Drain Balkon dia. 50 mm bh 16.00 49,617.86 793,886
-
Pipa Vent
- PVC dia 65 mm m' 1.20 43,688.66 52,426
- PVC dia 50 mm m' 5.50 37,913.66 208,525
- PVC dia 40 mm m' 4.80 32,596.34 156,462
- PVC dia 32 mm m' 32.90 26,821.34 882,422
- PVC dia 25 mm m' 29.60 25,377.59 751,177

5 Pemipaan Area Site


- PVC dia. 100 mm Standard SNI, merk : Rucika, Wavin m' 29.00 65,344.91 1,895,002
- PVC dia. 150 mm termasuk fitting & alat bantunya m' 3.00 90,610.54 271,832

2 Pekerjaan Talang air hujan


a. Pipa PVC dia. 50 mm Standard SNI, merk : Rucika, Wavin m' 98.00 37,913.66 3,715,538.75
b. Pipa PVC dia. 80 mm termasuk fitting & alat bantunya m' 318.00 58,126.16 18,484,119.11
c. Pipa PVC dia. 100 mm m' 173.00 65,344.91 11,304,669.55
d. Pipa PVC dia. 150 mm m' 75.00 90,610.54 6,795,790.18
e. Pipa PVC dia. 200 mm m' 13.00 105,048.04 1,365,624.46

f. Roof drain bh 50.00 57,867.86 2,893,392.86


g. Sumur resapan bh 5.00 2,005,535.71 10,027,678.57

PEKERJAAN AIR KOTOR Rp. 538,615,282.60

IV.2 PEKERJAAN PEMADAMAN KEBAKARAN


1 Peralatan Utama
1 Diesel Fire Pump + Controller Standard NFPA 20, Merk : Fairbanks Nijhuis, Amstrong
Kapasitas : 1892 lpm (500 GPM), Head : 105 m Unit 1.00 72,127,000.00 72,127,000.00

2 Electric Fire Pump + Controller Standard NFPA 20, Merk : Fairbanks Nijhuis, Amstrong
Kapasitas : 1892 lpm (500 GPM), Head : 105 m Unit 1.00 19,746,375.00 19,746,375.00

3 Jockey Pump + Controller Standard NFPA 20, Merk : Fairbanks Nijhuis, Amstrong
Kapasitas : 30 lpm, Head : 112 m Unit 1.00 19,417,553.57 19,417,553.57
4 Horn / Buzzer bh 1.00 93,244.64 93,244.64

5 Flexible Connection : Standard SNI, merk : Tozen, AFA Flex


- Diameter 100 mm bh 4.00 1,671,868.00 6,687,472.00
- Diameter 25 mm bh 2.00 1,061,643.00 2,123,286.00

6 Check Valve : Standard SNI, Kelas 16 K, merk : Kitz, Toyo


- Diameter 100 mm bh 2.00 4,982,744.64 9,965,489.29
- Diameter 25 mm bh 1.00 2,766,643.00 2,766,643.00

7 Gate Valve : Standard SNI, Kelas 16 K, merk : Kitz, Toyo


- Diameter 150 mm bh 1.00 13,782,744.64 13,782,744.64
- Diameter 100 mm bh 4.00 15,982,744.64 63,930,978.57
- Diameter 65 mm bh 2.00 19,266,643.00 38,533,286.00

8 Safety Relief Valve : Standard SNI, Kelas 20 K, merk : Claval


- Diameter 100 mm bh 1.00 582,744.64 582,744.64

9 Alarm Check Valve Standard SNI, merk : Viking, Tyco


- Diameter 100 mm bh 1.00 2,782,744.64 2,782,744.64

10 Header BSP SCH.40 Diameter 200 mm Standard SNI, Merk : PPI, Bakrie, Spindo Ls 1.00 2,419,214.29 2,419,214.29

11 Pemipaan BSP Schedule.40 :


- Diameter 150 mm Standard SNI, Merk : PPI, Bakrie, Spindo m' 92.00 889,485.54 81,832,669.29
- Diameter 100 mm m' 8.00 853,391.79 6,827,134.29
- Diameter 65 mm m' 2.00 624,798.04 1,249,596.07
- Diameter 25 mm m' 3.00 535,079.29 1,605,237.86

12 Instalasi Daya Listrik Pompa


- Instalasi Electric Pump, FRC 4 x 1 x 50 mm2 + BCC 35 mm ttk 1.00 465,025.00 465,025.00
- Instalasi Jockey pump, FRC 4 x 1 x 6 mm2 + BCC 6 mm ttk 1.00 338,525.00 338,525.00

13 Instalasi Pillar Hydrant & Siammese Connection


- Instalasi ke Phillar Hydrant Standard SNI, Merk : Ozeki, Apron
- Pipa BSP Schedule 40, dia. 100 mm m' 60.00 853,391.79 51,203,507.14
- Phillar Hydrant Unit 2.00 4,130,225.00 8,260,450.00
- Gate valve diameter 100 mm bh 2.00 15,982,744.64 31,965,489.29

- Instalasi ke Siamese Connection Standard SNI, Merk : Ozeki, Apron


- Pipa BSP Schedule 40,dia. 100 mm m' 18.00 15,982,744.64 287,689,403.57
- Siamesse Connection Unit 1.00 1,531,475.00 1,531,475.00
- Check valve diameter 100 mm bh 1.00 4,982,744.64 4,982,744.64

2 Instalasi Hydrant
a Lantai 1
1 Instalasi Pipa Tegak
- Landing Valve dia. 65 mm bh 1.00 8,266,643.00 8,266,643.00
- Fire Hose Cabinet (FHC), 125 x 75 x 18 cm Standard SNI, Merk : Ozeki, Appron, Hozeki, Onfire bh 2.00 1,820,225.00 3,640,450.00
- Pipa BSP Schedule 40, dia. 40 mm Standard SNI, Merk : PPI, Bakrie, Spindo m' 4.50 571,173.04 2,570,278.66
- Pipa BSP Schedule 40, dia. 65 mm m' 37.00 624,798.04 23,117,527.32
- Indicating /Control Valve, diameter 40 mm Standard SNI, Kelas 16 K, merk : Kitz, Toyo bh 1.00 7,166,643.00 7,166,643.00
- Gate Valve dia. 40 mm Standard SNI, Kelas 16 K, merk : Kitz, Toyo bh 1.00 7,166,643.00 7,166,643.00
- Fire extinguisher kapasitas 5 kg Standard SNI, Merk : Ozeki, Appron, Hozeki, Onfire bh 2.00 551,540.00 1,103,080.00

b Lantai 2
1 Instalasi Pipa Tegak dan Indoor Hidran Box
- Landing Valve dia. 65 mm bh 1.00 8,266,643.00 8,266,643.00
- Fire Hose Cabinet (FHC), 125 x 75 x 18 cm Standard SNI, Merk : Ozeki, Appron, Hozeki, Onfire bh 2.00 1,820,225.00 3,640,450.00
- Pipa BSP Schedule 40, dia. 40 mm Standard SNI, Merk : PPI, Bakrie, Spindo m' 4.50 571,173.04 2,570,278.66
- Pipa BSP Schedule 40, dia. 65 mm m' 37.00 624,798.04 23,117,527.32
- Indicating /Control Valve, diameter 40 mm Standard SNI, Kelas 16 K, merk : Kitz, Toyo bh 1.00 7,166,643.00 7,166,643.00
- Gate Valve dia. 40 mm Standard SNI, Kelas 16 K, merk : Kitz, Toyo bh 1.00 7,166,643.00 7,166,643.00
- Fire extinguisher kapasitas 5 kg Standard SNI, Merk : Ozeki, Appron, Hozeki, Onfire bh 2.00 551,540.00 1,103,080.00

c Lantai 3
1 Instalasi Pipa Tegak dan Indoor Hidran Box
- Landing Valve dia. 65 mm bh 1.00 8,266,643.00 8,266,643.00
- Fire Hose Cabinet (FHC), 125 x 75 x 18 cm Standard SNI, Merk : Ozeki, Appron, Hozeki, Onfire bh 2.00 1,820,225.00 3,640,450.00
- Pipa BSP Schedule 40, dia. 40 mm Standard SNI, Merk : PPI, Bakrie, Spindo m' 4.50 571,173.04 2,570,278.66
- Pipa BSP Schedule 40, dia. 65 mm m' 37.00 624,798.04 23,117,527.32
- Indicating /Control Valve, diameter 40 mm Standard SNI, Kelas 16 K, merk : Kitz, Toyo bh 1.00 7,166,643.00 7,166,643.00
- Gate Valve dia. 40 mm Standard SNI, Kelas 16 K, merk : Kitz, Toyo bh 1.00 7,166,643.00 7,166,643.00
- Fire extinguisher kapasitas 5 kg Standard SNI, Merk : Ozeki, Appron, Hozeki, Onfire bh 2.00 551,540.00 1,103,080.00

d Lantai 4
1 Instalasi Pipa Tegak dan Indoor Hidran Box
- Landing Valve dia. 65 mm bh 1.00 8,266,643.00 8,266,643.00
- Fire Hose Cabinet (FHC), 125 x 75 x 18 cm Standard SNI, Merk : Ozeki, Appron, Hozeki, Onfire bh 2.00 1,820,225.00 3,640,450.00
- Pipa BSP Schedule 40, dia. 40 mm Standard SNI, Merk : PPI, Bakrie, Spindo m' 4.50 571,173.04 2,570,278.66
- Pipa BSP Schedule 40, dia. 65 mm m' 37.00 624,798.04 23,117,527.32
- Indicating /Control Valve, diameter 40 mm Standard SNI, Kelas 16 K, merk : Kitz, Toyo bh 1.00 7,166,643.00 7,166,643.00
- Gate Valve dia. 40 mm Standard SNI, Kelas 16 K, merk : Kitz, Toyo bh 1.00 7,166,643.00 7,166,643.00
- Fire extinguisher kapasitas 5 kg Standard SNI, Merk : Ozeki, Appron, Hozeki, Onfire bh 2.00 551,540.00 1,103,080.00

PEKERJAAN PEMADAMAN KEBAKARAN Rp. 945,035,093.36

IV.3 PEKERJAAN AIR CONDITIONING


1 Lantai 1
a. Sistem AC Split (Standard)
- OU+IU.1.1.1, kapasitas : 20000 Btuh, Cassete Double Flow Type Standard SNI, Merk : Daikin, LG, Panasonic Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.1.1.2, kapasitas : 20000 Btuh, Cassete Double Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.1.2.1, kapasitas : 21000 Btuh, Cassete Double Flow Type Unit 1.00 22,978,214.29 22,978,214.29
- OU+IU.1.2.2, kapasitas : 21000 Btuh, Cassete Double Flow Type Unit 1.00 22,978,214.29 22,978,214.29
- OU+IU.1.3.1, kapasitas : 21000 Btuh, Cassete Double Flow Type Unit 1.00 22,978,214.29 22,978,214.29
- OU+IU.1.3.2, kapasitas : 21000 Btuh, Cassete Double Flow Type Unit 1.00 22,978,214.29 22,978,214.29
- OU+IU.1.4.1, kapasitas : 20000 Btuh, Cassete Double Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.1.4.2, kapasitas : 20000 Btuh, Cassete Double Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.1.5.1, kapasitas : 32000 Btuh, Cassete Multi Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.1.5.2, kapasitas : 9000 Btuh, Wall Type Unit 1.00 4,976,714.29 4,976,714.29
- OU+IU.1.6.1, kapasitas : 32000 Btuh, Cassete Multi Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.1.6.2, kapasitas : 9000 Btuh, Wall Type Unit 1.00 4,976,714.29 4,976,714.29
- OU+IU.1.7.1, kapasitas : 32000 Btuh, Cassete Multi Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.1.7.2, kapasitas : 9000 Btuh, Wall Type Unit 1.00 4,976,714.29 4,976,714.29
- OU+IU.1.8.1, kapasitas : 32000 Btuh, Cassete Multi Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.1.8.2, kapasitas : 9000 Btuh, Wall Type Unit 1.00 4,976,714.29 4,976,714.29
- OU+IU.1.9, kapasitas : 4500 Btuh, Wall Type Unit 1.00 4,976,714.29 4,976,714.29

- Pemipaan Refrigeran Standard SNI, pipa tembaga berisolasi, Merk : Mouller, Denzi m' 435.80 107,898.81 47,022,301.55
Closed Cell Elastomeric Rubber insulation, Merk: Insuflex, Armaflex

- Pemipaan Drain PVC berisolasi Standard SNI, pipa PVC, Merk : Wavin, Pralon m' 105.00 31,757.00 3,334,485.00
Closed Cell Elastomeric Rubber insulation, Merk: Insuflex, Armaflex

2. Sistem Exhaust Fan


a. Unit Fan Standard SNI, Merk : Panasonic, Wood
- EF.1.1, kapasitas : 900 cfm/ESP. 0,6 in.wg Axial/Inline Fan Unit 1.00 1,522,950.00 1,522,950.00
- EF.1.2, kapasitas : 150 cfm, Wall Fan type Wall fan Unit 1.00 959,200.00 959,200.00

b. Saluran udara / Ducting Exhaust tanpa isolasi & Grille


- ducting ukuran 6"x6" Standard SNI, bjls tanpa isolasi m' 8.90 104,539.29 930,399.64
- ducting ukuran 8"x6" Merk : Lokform, Sarana m' 10.30 121,117.86 1,247,513.93
- ducting ukuran 8"x8" m' 3.00 135,967.86 407,903.57
- ducting ukuran 12"x10" m' 1.00 165,117.86 165,117.86
- ducting ukuran 16"x10" m' 1.70 193,717.86 329,320.36
- grille ukuran 8"x8" Standard SNI, Alumunium Anodized, bh 6.00 335,303.57 2,011,821.43
- grille ukuran 24"x14" Merk : Catura, Comport Air, Dinamis bh 1.00 527,803.57 527,803.57

3. Instalasi Listrik
Titik instalasi daya listrik Exhaust Fan titik 2.00 297,005.50 594,011.00
Titik instalasi daya listrik Unit AC titik 17.00 374,775.50 6,371,183.50

2 Lantai 2
a. Sistem AC Split (Standard)
- OU+IU.2.1.1, kapasitas : 20000 Btuh, Cassete Double Flow Type Standard SNI, Merk : Daikin, LG, Panasonic Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.2.1.2, kapasitas : 20000 Btuh, Cassete Double Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.2.2.1, kapasitas : 24000 Btuh, Cassete Double Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.2.2.2, kapasitas : 12000 Btuh, Wall Type Unit 1.00 6,351,714.29 6,351,714.29
- OU+IU.2.2.3, kapasitas : 13600 Btuh, Wall Type Unit 1.00 6,901,714.29 6,901,714.29
- OU+IU.2.3.1, kapasitas : 24000 Btuh, Cassete Double Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.2.3.2, kapasitas : 12000 Btuh, Wall Type Unit 1.00 6,351,714.29 6,351,714.29
- OU+IU.2.3.3, kapasitas : 10500 Btuh, Wall Type Unit 1.00 5,801,714.29 5,801,714.29
- OU+IU.2.4.1, kapasitas : 20000 Btuh, Cassete Double Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.2.4.2, kapasitas : 20000 Btuh, Cassete Doble Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.2.5.1, kapasitas : 24000 Btuh, Cassete Double Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.2.5.2, kapasitas : 7600 Btuh, Wall Type Unit 1.00 4,983,589.29 4,983,589.29
- OU+IU.2.5.3, kapasitas : 9000 Btuh, Wall Type Unit 1.00 4,976,714.29 4,976,714.29
- OU+IU.2.6, kapasitas : 15000 Btuh, Cassete Double Flow Type Unit 1.00 27,928,214.29 27,928,214.29
- OU+IU.2.7, kapasitas : 29000 Btuh, Cassete Double Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.2.8, kapasitas : 14500 Btuh, Cassete Double Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.2.9, kapasitas : 25600 Btuh, Cassete Double Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.2.10.1, kapasitas : 25600 Btuh, Cassete Double Flow Type Unit 1.00 25,178,214.29 25,178,214.29
- OU+IU.2.10.2, kapasitas : 12000 Btuh, Wall Type Unit 1.00 6,351,714.29 6,351,714.29
- OU+IU.2.10.3, kapasitas : 10500 Btuh, Wall Type Unit 1.00 5,801,714.29 5,801,714.29
- OU+IU.2.11.1, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.2.11.2, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29

- Pemipaan Refrigeran Standard SNI, pipa tembaga berisolasi, Merk : Mouller, Denzi m' 652.80 107,898.81 70,436,343.39
Closed Cell Elastomeric Rubber insulation, Merk: Insuflex, Armaflex

- Pemipaan Drain PVC berisolasi Standard SNI, pipa PVC, Merk : Wavin, Pralon m' 120.00 31,757.00 3,810,840.00
Closed Cell Elastomeric Rubber insulation, Merk: Insuflex, Armaflex

2. Sistem Exhaust Fan


a. Unit Fan Standard SNI, Merk : Panasonic, Wood
- EF.1.1, kapasitas : 850 cfm/ESP. 0,6 in.wg Axial/Inline Fan Unit 1.00 1,179,475.00 1,179,475.00

b. Saluran udara / Ducting Exhaust tanpa isolasi & Grille


- ducting ukuran 6"x6" Standard SNI, bjls tanpa isolasi m' 8.90 104,539.29 930,399.64
- ducting ukuran 8"x6" Merk : Lokform, Sarana m' 10.30 121,117.86 1,247,513.93
- ducting ukuran 8"x8" m' 3.00 135,967.86 407,903.57
- ducting ukuran 12"x10" m' 1.00 165,117.86 165,117.86
- ducting ukuran 16"x10" m' 1.70 193,717.86 329,320.36
- grille ukuran 8"x8" Standard SNI, Alumunium Anodized, bh 6.00 335,303.57 2,011,821.43
- grille ukuran 24"x14" Merk : Catura, Comport Air, Dinamis bh 1.00 527,803.57 527,803.57

3. Instalasi Listrik
Titik instalasi daya listrik Exhaust Fan titik 1.00 297,005.50 297,005.50
Titik instalasi daya listrik Unit AC titik 17.00 374,775.50 6,371,183.50

3 Lantai 3
a. Sistem AC Split (Standard)
- OU+IU.3.1.1, kapasitas : 22500 Btuh, Wall Type Standard SNI, Merk : Daikin, LG, Panasonic Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.3.1.2, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.3.2.1, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.3.2.2, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.3.2.3, kapasitas : 16000 Btuh, Wall Type Unit 2.00 7,646,964.29 15,293,928.57
- OU+IU.3.3.1, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.3.3.2, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.3.3.3, kapasitas : 16000 Btuh, Wall Type Unit 2.00 7,646,964.29 15,293,928.57
- OU+IU.3.4.1, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.3.4.2, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.3.5.1, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.3.5.2, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.3.6.1, kapasitas : 42000 Btuh, Wall Type Unit 1.00 51,055,714.29 51,055,714.29
- OU+IU.3.6.2, kapasitas : 42000 Btuh, Cassete Type Unit 1.00 51,055,714.29 51,055,714.29
- OU+IU.3.6.3, kapasitas : 42000 Btuh, Cassete Type Unit 1.00 51,055,714.29 51,055,714.29
- OU+IU.3.7.1, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.3.7.2, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29

- Pemipaan Refrigeran Standard SNI, pipa tembaga berisolasi, Merk : Mouller, Denzi m' 386.00 107,898.81 41,648,940.79
Closed Cell Elastomeric Rubber insulation, Merk: Insuflex, Armaflex

- Pemipaan Drain PVC berisolasi Standard SNI, pipa PVC, Merk : Wavin, Pralon m' 105.00 31,757.00 3,334,485.00
Closed Cell Elastomeric Rubber insulation, Merk: Insuflex, Armaflex

2. Sistem Exhaust Fan


a. Unit Fan Standard SNI, Merk : Panasonic, Wood
- EF.1.1, kapasitas : 850 cfm/ESP. 0,6 in.wg Axial/Inline Fan Unit 1.00 1,179,475.00 1,179,475.00

b. Saluran udara / Ducting Exhaust tanpa isolasi & Grille


- ducting ukuran 6"x6" Standard SNI, bjls tanpa isolasi m' 8.90 104,539.29 930,399.64
- ducting ukuran 8"x6" Merk : Lokform, Sarana m' 10.30 121,117.86 1,247,513.93
- ducting ukuran 8"x8" m' 3.00 135,967.86 407,903.57
- ducting ukuran 12"x10" m' 1.00 165,117.86 165,117.86
- ducting ukuran 16"x10" m' 1.70 193,717.86 329,320.36
- grille ukuran 8"x8" Standard SNI, Alumunium Anodized, bh 6.00 335,303.57 2,011,821.43
- grille ukuran 24"x14" Merk : Catura, Comport Air, Dinamis bh 1.00 527,803.57 527,803.57

3. Instalasi Listrik
Titik instalasi daya listrik Exhaust Fan titik 1.00 297,005.50 297,005.50
Titik instalasi daya listrik Unit AC titik 15.00 374,775.50 5,621,632.50

4 Lantai 4
a. Sistem AC Split (Standard)
- OU+IU.4.1.1, kapasitas : 22500 Btuh, Wall Type Standard SNI, Merk : Daikin, LG, Panasonic Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.4.1.2, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.4.2.1, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.4.2.2, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.4.2.3, kapasitas : 16000 Btuh, Wall Type Unit 2.00 7,646,964.29 15,293,928.57
- OU+IU.4.3.1, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.4.3.2, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.4.3.3, kapasitas : 16000 Btuh, Wall Type Unit 2.00 7,646,964.29 15,293,928.57
- OU+IU.4.4.1, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.4.4.2, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.4.5.1, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.4.5.2, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.4.6.1, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.4.6.2, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.4.6.2, kapasitas : 16000 Btuh, Wall Type Unit 2.00 7,646,964.29 15,293,928.57
- OU+IU.4.7.1, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.4.7.2, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.4.7.3, kapasitas : 16000 Btuh, Wall Type Unit 2.00 7,646,964.29 15,293,928.57
- OU+IU.4.8.1, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.4.8.2, kapasitas : 16000 Btuh, Wall Type Unit 1.00 7,646,964.29 7,646,964.29
- OU+IU.4.8.3, kapasitas : 16000 Btuh, Wall Type Unit 2.00 7,646,964.29 15,293,928.57
- OU+IU.4.9.1, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29
- OU+IU.4.9.2, kapasitas : 22500 Btuh, Wall Type Unit 1.00 11,950,714.29 11,950,714.29

- Pemipaan Refrigeran Standard SNI, pipa tembaga berisolasi, Merk : Mouller, Denzi m' 564.80 107,898.81 60,941,248.08
Closed Cell Elastomeric Rubber insulation, Merk: Insuflex, Armaflex
- Pemipaan Drain PVC berisolasi Standard SNI, pipa PVC, Merk : Wavin, Pralon m' 120.00 31,757.00 3,810,840.00
Closed Cell Elastomeric Rubber insulation, Merk: Insuflex, Armaflex

2. Sistem Exhaust Fan


a. Unit Fan Standard SNI, Merk : Panasonic, Wood
- EF.1.1, kapasitas : 850 cfm/ESP. 0,6 in.wg Axial/Inline Fan Unit 1.00 1,179,475.00 1,179,475.00

b. Saluran udara / Ducting Exhaust tanpa isolasi & Grille


- ducting ukuran 6"x6" Standard SNI, bjls tanpa isolasi m' 8.90 104,539.29 930,399.64
- ducting ukuran 8"x6" Merk : Lokform, Sarana m' 10.30 121,117.86 1,247,513.93
- ducting ukuran 8"x8" m' 3.00 135,967.86 407,903.57
- ducting ukuran 12"x10" m' 1.00 165,117.86 165,117.86
- ducting ukuran 16"x10" m' 1.70 193,717.86 329,320.36
- grille ukuran 8"x8" Standard SNI, Alumunium Anodized, bh 6.00 335,303.57 2,011,821.43
- grille ukuran 24"x14" Merk : Catura, Comport Air, Dinamis bh 1.00 527,803.57 527,803.57

3. Instalasi Listrik
Titik instalasi daya listrik Exhaust Fan titik 1.00 297,005.50 297,005.50
Titik instalasi daya listrik Unit AC titik 15.00 374,775.50 5,621,632.50

5 Lantai Atap (Ruang mesin Lift)


a. Sistem AC Split Standard
- OU+IU.MR.1.1, kapasitas : 7600 Btuh, Wall Type Unit 1.00 4,983,589.29 4,983,589.29
- OU+IU.MR.1.2, kapasitas : 7600 Btuh, Wall Type Unit 1.00 4,983,589.29 4,983,589.29
- OU+IU.MR.2.1, kapasitas : 7600 Btuh, Wall Type Unit 1.00 4,983,589.29 4,983,589.29
- OU+IU.MR.2.1, kapasitas : 7600 Btuh, Wall Type Unit 1.00 4,983,589.29 4,983,589.29

6 Pekerjaan Core Drille Untuk jalur pipa Drain AC bh 10.00 175,375.00 1,753,750.00

PEKERJAAN HVAC Rp. 1,563,024,650.46

IV.4 PEKERJAAN ELEVATOR


1. Lift No.1 & No.2 Standard SNI, Machine Room Type, Unit 2.00 726,110,000.00 1,452,220,000.00
- Jenis : Passangers Merk : Sigma, LG, Otis
- Kapasitas :1000 kg / 15 orang Termasuk Interior dan accessories
- Lintasan : 4 Lantai
- Kecepatan : 60 Mpm

2. Instalasi Daya Listrik titik 2.00 0.00


3. Upah pasang & perizinan Unit - 0.00

PEKERJAAN ELEVATOR Rp. 1,452,220,000.00

IV.5 PEKERJAAN ELEKTRIKAL


IV.5.1 BIAYA PENYAMBUNGAN LISTRIK
1. Biaya Penyambungan listrik TEGANGAN RENDAH Daya tersambung, TR (197 kVA) ls 1.00 3,500,000.00 3,500,000.00
2. Biaya SLO ls 1.00 3,500,000.00 3,500,000.00
3. Kabel TM dari Gardu PLN kr MVMDP, N2XSY 3 x 1c x 70 mm2 Include

PEKERJAAN BIAYA PENYAMBUNGAN LISTRIK Rp. 7,000,000.00

IV.5.3 PEKERJAAN PANEL DISTRIBUSI


Pengadaan dan Pemasangan Panel Distribusi Tegangan Rendah Panel Maker (Sier Panel)
1. Panel Lantai 1 Komponen (Ex, Schneider, ABB)
- SDP unit 1.00 15,217,235.00 15,217,235.00
- PP/ LP L1 unit 1.00 4,343,900.00 4,343,900.00
- PP - AB lengkap DOL unit 1.00 4,343,900.00 4,343,900.00
- PP - Depweel unit 1.00 7,181,900.00 7,181,900.00

2. Panel Lantai 2
- PP/ LP L2 unit 1.00 19,472,502.50 19,472,502.50

3. Panel Lantai 3
- PP/ LP L3 unit 1.00 21,109,302.50 21,109,302.50

4. Panel Lantai 4
- PP/ LP L4 unit 1.00 15,222,900.00 15,222,900.00

5. Panel Lantai Atap


- PP/LP Booster unit 1.00 8,345,727.50 8,345,727.50
- PP - Lift.1 unit 1.00 6,934,977.50 6,934,977.50
- PP - Lift.2 unit 1.00 6,934,977.50 6,934,977.50

PEKERJAAN PANEL DISTRIBUSI Rp. 109,107,322.50

IV.5.4 PEKERJAAN KABEL FEEDER termasuk skoen, klem dan aksesories lainnya
Pengadaan dan Pemasangan Kabel Feeder (Ex. Suppreme, Kabelmetal, Kabelindo)

1 Kabel Feeder di lantai 1


- Kabel dari SDP ke PP/LP L1 , NYY 4 x 50 mm2 + BCC 35 mm Pada pada kabel tray m' 10.00 85,712.00 857,120.00
- Kabel dari SDP ke PP AB , NYY 4 x 16 mm2 + BCC 10 mm Pada pada kabel tray m' 12.00 54,067.20 648,806.40
- Kabel dari SDP SDP ke PP - Deepwell, NYFGbY 4 x 10 mm2 + BCC 6 mm Pada pada kabel tray m' 10.00 21,053.45 210,534.50

2 Kabel Feeder di lantai 2


- Kabel dari SDP ke PP/LP L2 , NYY 4 x 70 mm2 + BCC 35 mm Pada pada kabel tray m' 10.00 69,927.00 699,270.00

3 Kabel Feeder di lantai 3


- Kabel dari SDP ke PP/LP L3 , NYY 4 x 50 mm2 + BCC 35 mm Pada pada kabel tray m' 15.00 85,712.00 1,285,680.00

4 Kabel Feeder di lantai 4


- Kabel dari SDP ke PP/LP L4 , NYY 4 x 70 mm2 + BCC 35 mm Pada pada kabel tray m' 20.00 69,927.00 1,398,540.00

5 Kabel Feeder di lantai Atap


- Kabel dari SDP ke PP - Lift.1, NYY 4 x 10 mm2 + BCC 6 mm Pada pada kabel tray m' 65.00 30,953.45 2,011,974.25
- Kabel dari SDP ke PP - Lift.2, NYY 4 x 10 mm2 + BCC 6 mm Pada pada kabel tray m' 30.00 30,953.45 928,603.50
- Kabel dari PP/LP- Audi ke PP - Booster, NYY 3 x 6 mm2 + BCC 6 mm Pada pada kabel tray m' 14.00 36,027.20 504,380.80

PEKERJAAN KABEL FEEDER Rp. 8,544,909.45

IV.5.5 PEKERJAAN RAK KABEL termasuk Tee, Cros, Elbow, Reducer) dan aksesories lainnya
Pengadaan dan Pemasangan Rak Kabel lengkap Sambungan dan dudukan (Ex. Tri Abadi, Tresstar)

1. Rak kabel di lantai 1


- Kabel Tray (30 cm) 300 x 100 m' 2.00 716,143.45 1,432,286.90
- Kabel Tray (20 cm) 200 x 100 m' 50.00 432,205.95 21,610,297.50
- Kabel Tray (15 cm) 150 x 100 m' 3.00 363,799.70 1,091,399.10
- Kabel Tray (10 cm) 100 x 100 m' 60.00 187,627.83 11,257,669.50

2. Rak kabel di lantai 2


- Kabel Tray (30 cm) 300 x 100 m' 2.00 716,143.45 1,432,286.90
- Kabel Tray (20 cm) 200 x 100 m' 50.00 432,205.95 21,610,297.50
- Kabel Tray (15 cm) 150 x 100 m' 3.00 363,799.70 1,091,399.10
- Kabel Tray (10 cm) 100 x 100 m' 60.00 187,627.83 11,257,669.50

3. Rak kabel di lantai 3


- Kabel Tray (30 cm) 300 x 100 m' 2.00 716,143.45 1,432,286.90
- Kabel Tray (20 cm) 200 x 100 m' 50.00 432,205.95 21,610,297.50
- Kabel Tray (15 cm) 150 x 100 m' 3.00 363,799.70 1,091,399.10
- Kabel Tray (10 cm) 100 x 100 m' 60.00 187,627.83 11,257,669.50

4. Rak kabel di lantai 4


- Kabel Tray (30 cm) 300 x 100 m' 2.00 716,143.45 1,432,286.90
- Kabel Tray (20 cm) 200 x 100 m' 50.00 432,205.95 21,610,297.50
- Kabel Tray (15 cm) 150 x 100 m' 3.00 363,799.70 1,091,399.10
- Kabel Tray (10 cm) 100 x 100 m' 60.00 187,627.83 11,257,669.50

5. Rak kabel di shaft


- Kabel Leader (100 cm) 1000 x 100 m' 28.00 129,265.95 3,619,446.60

PEKERJAAN RAK KABEL Rp. 145,186,058.60

IV.5.6 PEKERJAAN PENERANGAN DAN STOP KONTAK DAYA


Pengadaan dan pemasangan Armature lampu, saklar, stop kontak termasuk dudukan dan material bantu lainnya.
1. Penerangan Lantai 1 (Ex. Artolite, setara)
- Fixtures lampu
- TL LED 2 x 16 w Replektor M6 Terpasang Inbow bh 64.00 0.00
- TL LED 1 x 16 w Replektor M6 Terpasang Inbow bh 9.00 0.00
- TL LED 1 x 16 w single cover clear Acrilic Terpasang Inbow bh 14.00 160,418.50 2,245,859.00
- Downlight LED 18 w type Reccesed di Plafond bh 9.00 154,506.00 1,390,554.00
- Baret LED 18 w Terpasang Outbow (Out) di Plafond bh 10.00 121,506.00 1,215,060.00
- Saklar (Ex. Clipsal/ Schneider)
- Saklar tunggal Terpasang Inbow lengkap alat bantunya bh 11.00 90,587.20 996,459.20
- Saklar Ganda bh 12.00 101,587.20 1,219,046.40
- Saklar hotel bh 3.00 200,587.20 601,761.60
- Saklar grid (6 module) bh 1.00 255,587.20 255,587.20
- Stop kontak (Ex. Clipsal/ Schneider)
- Stop kontak 10 A / 1 Phase Terpasang Inbow lengkap di dinding bh 43.00 35,587.20 1,530,249.60
- Stop kontak 10 A / 1 Phase Terpasang di atas plafond bh 3.00 35,587.20 106,761.60
- Stop kontak (2 x 16 A) / 1 Phase Terpasang Inbow lengkap di dinding/ di meja bh 10.00 108,075.00 1,080,750.00

2. Penerangan Lantai 2 (Ex. Artolite, setara)


- Fixtures lampu
- TL LED 2 x 16 w Replektor M6 Terpasang Inbow bh 67.00 - 0.00
- TL LED 1 x 16 w Replektor M6 Terpasang Inbow (ressed) di Plafond bh 26.00 - 0.00
- TL LED 1 x 16 w single cover clear Acrilic Terpasang Inbow (ressed) di Plafond bh 14.00 160,418.50 2,245,859.00
- Spot Lamp LED 38 Watt / Water proof Terpasang di Canopy bh 2.00 339,729.50 679,459.00
- Baret LED 18 w Terpasang Outbow (Out) di Plafond bh 11.00 121,506.00 1,336,566.00
- Saklar
- Saklar tunggal Terpasang Inbow lengkap alat bantunya bh 7.00 90,587.20 634,110.40
- Saklar Ganda (Ex. Clipsal/ Schneider) bh 19.00 101,587.20 1,930,156.80
- Saklar hotel bh 9.00 200,587.20 1,805,284.80
- Stop kontak (Ex. Clipsal/ Schneider)
- Stop kontak 10 A / 1 Phase Terpasang Inbow lengkap di dinding bh 31.00 35,587.20 1,103,203.20
- Stop kontak 10 A / 1 Phase Terpasang di atas plafond bh 1.00 35,587.20 35,587.20
- Stop kontak (2 x 16 A) / 1 Phase Terpasang Inbow lengkap di dinding/ di meja bh 29.00 108,075.00 3,134,175.00

3. Penerangan Lantai 3 (Ex. Artolite, setara)


- Fixtures lampu
- TL LED 2 x 19 w Replektor M6, Terpasang Inbow bh 93.00 - 0.00
- TL LED 1 x 16 w single cover clear Acrilic Terpasang Inbow (ressed) di Plafond bh 14.00 160,418.50 2,245,859.00
- Baret LED 18 w Terpasang Outbow (Out) di Plafond bh 7.00 121,506.00 850,542.00
- Saklar
- Saklar tunggal Terpasang Inbow lengkap alat bantunya bh 3.00 90,587.20 271,761.60
- Saklar Ganda (Ex. Clipsal/ Schneider) bh 9.00 101,587.20 914,284.80
- Saklar hotel (Ex. Clipsal/ Schneider) bh 9.00 200,587.20 1,805,284.80
- Stop kontak (Ex. Clipsal/ Schneider)
- Stop kontak 10 A / 1 Phase Terpasang Inbow lengkap di dinding bh 14.00 35,587.20 498,220.80
- Stop kontak 10 A / 1 Phase Terpasang di atas plafond bh 6.00 35,587.20 213,523.20
- Stop kontak (2 x 16 A) / 1 Phase Terpasang Inbow lengkap di dinding/ di meja bh 20.00 108,075.00 2,161,500.00

4. Penerangan Lantai 4 (Ex. Artolite, setara)


- Fixtures lampu
- TL LED 2 x 19 w Replektor M6, Terpasang Inbow bh 96.00 - 0.00
- TL LED 1 x 16 w single cover clear Acrilic Terpasang Inbow (ressed) di Plafond bh 14.00 160,418.50 2,245,859.00
- Baret LED 18 w Terpasang Outbow (Out) di Plafond bh 7.00 121,506.00 850,542.00
- Saklar
- Saklar tunggal (Ex. Clipsal/ Schneider) bh 5.00 90,587.20 452,936.00
- Saklar Ganda (Ex. Clipsal/ Schneider) bh 9.00 101,587.20 914,284.80
- Saklar hotel (Ex. Clipsal/ Schneider) bh 7.00 200,587.20 1,404,110.40
- Stop kontak (Ex. Clipsal/ Schneider)
- Stop kontak 10 A / 1 Phase Terpasang Inbow lengkap di dinding bh 11.00 35,587.20 391,459.20
- Stop kontak 10 A / 1 Phase Terpasang di atas plafond bh 9.00 35,587.20 320,284.80
- Stop kontak (2 x 16 A) / 1 Phase Terpasang Inbow lengkap di dinding/ di meja bh 26.00 108,075.00 2,809,950.00

5. Penerangan Lantai Atap


- TL LED 1 x 16 w single cover clear Acrilic Terpasang Inbow (ressed) di Plafond bh 2.00 160,418.50 320,837.00
- Baret LED 18 w Terpasang Outbow (Out) di Plafond bh 2.00 121,506.00 243,012.00
- Saklar tunggal bh 2.00 90,587.20 181,174.40
- Saklar hotel bh 2.00 200,587.20 401,174.40

PEKERJAAN PENERANGAN DAN STOP KONTAK DAYA Rp. 43,043,090.20

IV.5.7 PEKERJAAN TITIK INSTALASI


1 Titik instalasi penerangan, cable gland, sealant & alat penunjang lainnya
NYM 3 x 2,5 mm2 Dalam konduit PVC Hight Impact ttk 461.00 269,582.50 124,277,532.50

2 Titik instalasi stop kontak daya, cable gland, sealant & alat penunjang lainnya
- Titik Instalasi stop kontak 10A pada dinding, NYM 3 x 2,5 mm2 Kabel Power (Ex. Suppreme) ttk 99.00 392,920.00 38,899,080.00
- Titik Instalasi stop kontak 2 x 16A pada dinding, NYM 3 x 2,5 mm2 Kabel Power (Ex. Suppreme) ttk 85.00 392,920.00 33,398,200.00
- Titik Instalasi stop kontak 10A di atas plafond, NYM 3 x 2,5 mm2 Kabel Power (Ex. Suppreme) ttk 19.00 392,920.00 7,465,480.00
- Titik Instalasi Exhaust Fan di atas plafond, NYM 3 x 2,5 mm2 Kabel Power (Ex. Suppreme) ttk 9.00 269,582.50 2,426,242.50

PEKERJAAN TITIK INSTALASI Rp. 206,466,535.00

IV.5.8 PEKERJAAN PENANGKAL PETIR


1. Batang Penangkal Petir (Splitzent) Konvensional Bh 16.00 0.00
2. Kabel BC 50 mm lengkap dudukan Kawat hantaran m' 155.00 6,894.64 1,068,669.64
3. Bak kontrol & Elektroda pentanahan ttk 4.00 0.00

PEKERJAAN PENANGKAL PETIR Rp. 1,068,669.64

IV.5.11 PEKERJAAN INSTALASI DATA dan BRACKET PROJECTOR


1 Sentral Utama Jaringan Data
- Rack Server 9U Wall Mounting Rack Server Lengkap AC Cord Terminal (Ex. Indorack ) unit 1.00 0.00
- Routerboard Utama 4 Port 10Gb-SFP+ Switch Layer III ( Ex. Mikrotik Routerboard CRS305-1S-4G-1N ) unit 1.00 0.00
- Routerboard Distribusi Tiap Lantai Router Distribusi ( Ex. Mirotik CCR1009-7G-1C-1S+ ) unit 1.00 0.00
- SFP Tranceiver RJ45 Modul Port SFP RJ45 ( Ekx Mikrobits SFP Tranceiver SFP -1GE-1S+) unit 2.00 0.00
- Switch 24 Port Gigabyte Switch Unmanaged ( Ex. HP 1420-24G 24-Port Gigabit Unmanaged Switch JG708B unit ) 1.00 0.00
- Acsess Point Gigabit Port, Up to 300Mbps 2.4Ghz, ( ex Aruba Instan on AP15) unit 2.00 0.00
- Fiber Optik Burried Double Jacket 12 Core 12 Core MM Outdoor Direct Buried, Double Jacket 50um/125 ( Ex. Netviel ) m 150.00 0.00
- OTB Rack Wall Mouting 12 core Optik Terminal Box Full Acsesoris Pigtail SC-SC Rack Wall Mounting (Ex. Netviel
unit) 2.00 0.00
- SFP Transceiver Module 10Gb Module SFP 10Gb Support Mikrotik ( Ex.Mikrobits SFP Transceiver SFP-10G-BD-SM-10KM
unit 2.00 0.00
- Pathcord SC-LC Duplex Kabel Pathcord SC-LC, 2m ,SM, Duplex (Ex. Netviel ) roll 2.00 0.00
- Instalasi Data dari Router Distribusi ke Switch Tiap Lantai Kabel UTP Cat 6+Conektor RJ45 ( Ex. Belden.AMP.Comscope) titik 3.00 0.00
2 Instalasi Data dan Projector Lantai 1
- Instalasi Data Kabel UTP Cat 6+Conektor RJ45 ( Ex. Belden.AMP.Comscope) titik 18.00 0.00
- Outlet Data ( RG 45 ) Cat 6 Outlet Terpasang Pada Dinding Sejajar dengan Stop Kontak ( Ex. Clipsal /Schneider
bh ) 18.00 0.00
- Instalasi Kabel HDMI Kabel HDMI Support Quality 4K pada Plafond ke Bracket Projector titik 2.00 0.00
- Outlet HDMI Outlet Terpasang Pada Dinding Sejajar dengan Data ( Ex. Clipsal/Schneider/howell
titik) 2.00 0.00
- Bracket Projector Plafond Terpasang Pada As Plafond warna Putih berputar 360 derajat unit 2.00 0.00
- Acsess Point Terpasang Pada Plafond + POE Injector 15.4 Watt ( Ex. Aruba Instan AP15)unit 2.00 0.00
3 Instalasi Data dan Projector Lantai 2
- Instalasi Data Kabel UTP Cat 6+Conektor RJ45 ( Ex. Belden.AMP.Comscope) titik 18.00 0.00
- Outlet Data ( RG 45 ) Cat 6 Outlet Terpasang Pada Dinding Sejajar dengan Stop Kontak ( Ex. Clipsal /Schneider
bh ) 18.00 0.00
- Instalasi Kabel HDMI Kabel HDMI Support Quality 4K pada Plafond ke Bracket Projector titik 2.00 0.00
Outlet
- HDMI Outlet Terpasang Pada Dinding Sejajar dengan Data ( Ex. Clipsal/Schneider/howell
bh ) 2.00 0.00
Bracket Projector
- Plafond Terpasang Pada As Plafond warna Putih berputar 360 derajat unit 2.00 0.00
Rack Server- 9U Wall Mounting Rack Server Lengkap AC Cord Terminal (Ex. Indorack ) unit 1.00 0.00
Switch 24- Port Gigabyte Switch Unmanaged ( Ex. HP 1420-24G 24-Port Gigabit Unmanaged Switch JG708B unit ) 1.00 0.00
Acsess
- Point Terpasang Pada Plafond + POE Injector 15.4 Watt ( Ex. Aruba Instan AP15)unit 2.00 0.00
4 Instalasi Data dan Projector Lantai 3
Instalasi
- Data Kabel UTP Cat 6+Conektor RJ45 ( Ex. Belden.AMP.Comscope) titik 9.00 0.00
Outlet Data- ( RG 45 ) Cat 6 Outlet Terpasang Pada Dinding Sejajar dengan Stop Kontak ( Ex. Clipsal /Schneider
bh ) 9.00 0.00
Instalasi
- Kabel HDMI Kabel HDMI Support Quality 4K pada Plafond ke Bracket Projector titik 6.00 0.00
Outlet
- HDMI Outlet Terpasang Pada Dinding Sejajar dengan Data ( Ex. Clipsal/Schneider/howell
bh ) 6.00 0.00
- Bracket Projector Plafond Terpasang Pada As Plafond warna Putih berputar 360 derajat unit 6.00 0.00
- Rack Server 9U Wall Mounting Rack Server Lengkap AC Cord Terminal (Ex. Indorack ) unit 1.00 0.00
- Switch 24 Port Gigabyte Switch Unmanaged ( Ex. HP 1420-24G 24-Port Gigabit Unmanaged Switch JG708B unit ) 1.00 0.00
Acsess
- Point Terpasang Pada Plafond + POE Injector 15.4 Watt ( Ex. Aruba Instan AP15)unit 2.00 0.00
5 Instalasi Data dan Projector Lantai 4
Instalasi
- Data Kabel UTP Cat 6+Conektor RJ45 ( Ex. Belden.AMP.Comscope) titik 11.00 0.00
Outlet Data- ( RG 45 ) Cat 6 Outlet Terpasang Pada Dinding Sejajar dengan Stop Kontak ( Ex. Clipsal /Schneider
bh ) 11.00 0.00
- Instalasi Kabel HDMI Kabel HDMI Support Quality 4K pada Plafond ke Bracket Projector titik 9.00 0.00
- Outlet HDMI Outlet Terpasang Pada Dinding Sejajar dengan Data ( Ex. Clipsal/Schneider/howell
bh ) 9.00 0.00
- Bracket Projector Plafond Terpasang Pada As Plafond warna Putih berputar 360 derajat unit 9.00 0.00
Rack Server- 9U Wall Mounting Rack Server Lengkap AC Cord Terminal (Ex. Indorack ) unit 1.00 0.00
Switch 24- Port Gigabyte Switch Unmanaged ( Ex. HP 1420-24G 24-Port Gigabit Unmanaged Switch JG708B unit ) 1.00 0.00
Acsess
- Point Terpasang Pada Plafond + POE Injector 15.4 Watt ( Ex. Aruba Instan AP15)unit 2.00 0.00

PEKERJAAN INSTALASI DATA DAN BRACKET PROJECTOR Rp. 0.00

IV.5.10 PEKERJAAN FIRE ALARM


1 Sentral Fire Alarm
- FACP - Full Addressible Adressible (Ex. Nohmi, Esser, setara) unit 1.00 4,765,750.00 4,765,750.00
- Kabel dari FACP ke Annunciator Panel, FRC 2 x 2,5 mm2 (Ex. Draca) m' 50.00 24,926.79 1,246,339.29
- Kabel koneksi / Interface dari FACP ke :
- Panel SDP, FRC 2 x 1 x 1,5 mm2 dalam konduit (Ex. Draca) m' 20.00 19,289.29 385,785.71
- Sound System, FRC 2 x 1 x 1,5 mm2 dalam konduit (Ex. Draca) m' 20.00 19,289.29 385,785.71
- Elevator (Lift), FRC 2 x 1 x 1,5 mm2 dalam konduit (Ex. Draca) m' 20.00 19,289.29 385,785.71
- Hydrant Pump, FRC 3 (2 x 1 x 1,5) mm2 dalam konduit (Ex. Draca) m' 20.00 19,289.29 385,785.71

2 Instalasi lantai 1
- Terminal Box Fire ( TBF - L1 ) Terminal (Ex. Nohmi, Esser, setara) unit 1.00 0.00
- Kabel tuvur dari FACP ke Terminal Box ( TBF L1 ), FRC 2 x 2,5 mm2 Kabel (Ex. Draca) m 6.00 24,926.79 149,560.71
- Smoke Detector Konvensinal (Ex. Nohmi, Esser, setara) bh 10.00 511,775.00 5,117,750.00
- Modul for Detector Adressible (Ex. Nohmi, Esser, setara) bh 1.00 3,041,775.00 3,041,775.00
- Manual Alarm + modul Adressible (Ex. Nohmi, Esser, setara) bh 1.00 401,775.00 401,775.00
- Bell Alarm + modul Adressible (Ex. Nohmi, Esser, setara) bh 1.00 841,775.00 841,775.00
- Visual Alarm + modul Adressible (Ex. Nohmi, Esser, setara) bh 1.00 209,275.00 209,275.00
- Exit Lamp lengkap battere (Artolite, Philips) bh 1.00 291,775.00 291,775.00
- Instalasi detector NYA 2 x 1,5 mm/ AWG 18, dalam konduit Kabel power (Ex. Suppreme) ttk 10.00 1,455,614.29 14,556,142.86
- Instalasi Manual, Bell, visual alarm, FRC 2 x 2,5 mm2 Kabel power (Ex. Draca) ttk 3.00 358,364.29 1,075,092.86
- Instalasi Flow Switch, FRC 2 x 2,5 mm2 Kabel power (Ex. Draca) ttk 1.00 358,364.29 358,364.29
- Instalasi Socket Telephone emergency Instalasi Jack Telephone ttk 1.00 173,564.29 173,564.29
- Instalasi Exit Lamp, FRC 2 x 2,5 mm2 Kabel power (Ex. Draca) ttk 1.00 358,364.29 358,364.29

3 Instalasi lantai 2
- Terminal Box Fire ( TBF - L2 ) Terminal (Ex. Nohmi, Esser, setara) unit 1.00 - 0.00
- Kabel tuvur dari FACP ke Terminal Box ( TBF L1 ), FRC 2 x 2,5 mm2 Kabel (Ex. Draca) m 10.00 24,926.79 249,267.86
- Smoke Detector Konvensinal (Ex. Nohmi, Esser, setara) bh 11.00 511,775.00 5,629,525.00
- Modul for Detector Adressible (Ex. Nohmi, Esser, setara) bh 1.00 3,041,775.00 3,041,775.00
- Manual Alarm + modul Adressible (Ex. Nohmi, Esser, setara) bh 1.00 401,775.00 401,775.00
- Bell Alarm + modul Adressible (Ex. Nohmi, Esser, setara) bh 1.00 841,775.00 841,775.00
- Visual Alarm Adressible (Ex. Nohmi, Esser, setara) bh 1.00 209,275.00 209,275.00
- Exit Lamp lengkap battere (Artolite, Philips) bh 1.00 291,775.00 291,775.00
- Instalasi detector NYA 2 x 1,5 mm/ AWG 18, dalam konduit Kabel power (Ex. Suppreme) ttk 11.00 1,455,614.29 16,011,757.14
- Instalasi Manual, Bell, visual alarm, FRC 2 x 2,5 mm2 Kabel power (Ex. Draca) ttk 3.00 358,364.29 1,075,092.86
- Instalasi Flow Switch, FRC 2 x 2,5 mm2 Kabel power (Ex. Draca) ttk 1.00 358,364.29 358,364.29
- Instalasi Socket Telephone emergency Instalasi Jack Telephone ttk 1.00 173,564.29 173,564.29
- Instalasi Exit Lamp, FRC 2 x 2,5 mm2 Kabel power (Ex. Draca) ttk 1.00 358,364.29 358,364.29

4 Instalasi lantai 3
- Terminal Box Fire ( TBF - L3 ) Terminal (Ex. Nohmi, Esser, setara) unit 1.00 - 0.00
- Kabel tuvur dari FACP ke Terminal Box ( TBF L1 ), FRC 2 x 2,5 mm2 Kabel (Ex. Draca) m 15.00 24,926.79 373,901.79
- Smoke Detector Konvensinal (Ex. Nohmi, Esser, setara) bh 9.00 511,775.00 4,605,975.00
- Modul for Detector Adressible (Ex. Nohmi, Esser, setara) bh 1.00 3,041,775.00 3,041,775.00
- Manual Alarm + modul Adressible (Ex. Nohmi, Esser, setara) bh 1.00 401,775.00 401,775.00
- Bell Alarm + modul Adressible (Ex. Nohmi, Esser, setara) bh 1.00 841,775.00 841,775.00
- Visual Alarm Adressible (Ex. Nohmi, Esser, setara) bh 1.00 209,275.00 209,275.00
- Exit Lamp lengkap battere (Artolite, Philips) bh 1.00 291,775.00 291,775.00
- Instalasi detector NYA 2 x 1,5 mm/ AWG 18, dalam konduit Kabel power (Ex. Suppreme) ttk 9.00 1,455,614.29 13,100,528.57
- Instalasi Manual, Bell, visual alarm, FRC 2 x 2,5 mm2 Kabel power (Ex. Draca) ttk 3.00 358,364.29 1,075,092.86
- Instalasi Flow Switch, FRC 2 x 2,5 mm2 Kabel power (Ex. Draca) ttk 1.00 358,364.29 358,364.29
- Instalasi Socket Telephone emergency Instalasi Jack Telephone ttk 1.00 173,564.29 173,564.29
- Instalasi Exit Lamp, FRC 2 x 2,5 mm2 Kabel power (Ex. Draca) ttk 1.00 358,364.29 358,364.29

5 Instalasi lantai 4 & Atap


- Terminal Box Fire ( TBF - L4 ) Terminal (Ex. Nohmi, Esser, setara) unit 1.00 - 0.00
- Kabel tuvur dari FACP ke Terminal Box ( TBF L1 ), FRC 2 x 2,5 mm2 Kabel (Ex. Draca) m 25.00 24,926.79 623,169.64
- Smoke Detector Konvensinal (Ex. Nohmi, Esser, setara) bh 9.00 511,775.00 4,605,975.00
- Modul for Detector Adressible (Ex. Nohmi, Esser, setara) bh 1.00 3,041,775.00 3,041,775.00
- Manual Alarm + modul Adressible (Ex. Nohmi, Esser, setara) bh 1.00 401,775.00 401,775.00
- Bell Alarm + modul Adressible (Ex. Nohmi, Esser, setara) bh 1.00 841,775.00 841,775.00
- Visual Alarm Adressible (Ex. Nohmi, Esser, setara) bh 1.00 209,275.00 209,275.00
- Exit Lamp lengkap battere (Artolite, Philips) bh 1.00 291,775.00 291,775.00
- Instalasi detector NYA 2 x 1,5 mm/ AWG 18, dalam konduit Kabel power (Ex. Suppreme) ttk 9.00 1,455,614.29 13,100,528.57
- Instalasi Manual, Bell, visual alarm, FRC 2 x 2,5 mm2 Kabel power (Ex. Draca) ttk 3.00 358,364.29 1,075,092.86
- Instalasi Flow Switch, FRC 2 x 2,5 mm2 Kabel power (Ex. Draca) ttk 1.00 358,364.29 358,364.29
- Instalasi Socket Telephone emergency Instalasi Jack Telephone ttk 1.00 173,564.29 173,564.29
- Instalasi Exit Lamp, FRC 2 x 2,5 mm2 Kabel power (Ex. Draca) ttk 1.00 358,364.29 358,364.29

PEKERJAAN FIRE ALARM Rp. 112,686,357.14

IV.5.11 PEKERJAAN CCTV


1 Pekerjaan Sistem CCTV
- NVR Manager NVR,HD 4TB, Resolusi Support 4K, 16 Ch, Port Gigabit Ethernet ( Ex. Honeywell, Panasonic
unit ) 1.00 178,475.00 178,475.00
- PC Computer , monitor 32 " set 1.00 7,158,087.20 7,158,087.20
- Monitor LED 42 " ( Ex. LG ) unit 1.00 3,139,950.00 3,139,950.00
- Core Switch-Distribution Switch bh - -
- Kabel RGB / HDMI m 40.00 15,000.00 600,000.00
-
2 Instalasi lantai 1 -
- Switching 8 Port POE 123 Watt, 8 Port 100Mb, Rakc Switch, ( Ex. Dlink, Allied Telesys ) bh 1.00 25,000.00 25,000.00
- Kabel feder dari Core switch ke ONU LT 1, FO 6 Core Kabel instalasi ( Ex. Belden ) m 22.00 15,000.00 330,000.00
- Dome Camera IP Camera Dome, 4MP, IP 67 ( Ex. Honeywell, Panasonic ) bh 4.00 175,000.00 700,000.00
- Instalasi CCTV, Cat-6 dalam konduit Kabel instalasi ( Ex. Belden ) ttk 4.00 277,514.29 1,110,057.14
-
3 Instalasi lantai 2 -
- Dome Camera Camera ( Ex. Boosch, setara ) bh 3.00 175,000.00 525,000.00
- Instalasi CCTV, Cat-6 dalam konduit Kabel instalasi ( Ex. Belden ) ttk 3.00 277,514.29 832,542.86
-
4 Instalasi lantai 3 -
- Dome Camera IP Camera Dome, 4MP, IP 67 ( Ex. Honeywell, Panasonic ) bh 3.00 175,000.00 525,000.00
- Instalasi CCTV, Cat-6 dalam konduit Kabel instalasi ( Ex. Belden ) ttk 3.00 277,514.29 832,542.86
-
5 Instalasi lantai 4 -
- Switching 16 Port POE 123 Watt, 8 Port 100Mb, Rakc Switch, ( Ex. Dlink, Allied Telesys ) bh 1.00 25,000.00 25,000.00
- Kabel feder dari Core switch ke ONU LT 2, FO 6 Core Kabel instalasi ( Ex. Belden ) m 32.00 15,000.00 480,000.00
- Dome Camera IP Camera Dome, 4MP, IP 67 ( Ex. Honeywell, Panasonic ) bh 3.00 175,000.00 525,000.00
- Instalasi CCTV, Cat-6 dalam konduit Kabel instalasi ( Ex. Belden ) ttk 3.00 277,514.29 832,542.86
-
6 Instalasi lantai Atap -
- Dome Camera IP Camera Dome, 4MP, IP 67 ( Ex. Honeywell, Panasonic ) bh 2.00 175,000.00 350,000.00
- Instalasi CCTV, Cat-6 dalam konduit Kabel instalasi ( Ex. Belden ) ttk 2.00 277,514.29 555,028.57

PEKERJAAN CCTV Rp. 18,724,226.49


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME
Rp. Rp.
1 2 3 4 5 6 (5X6)

VIII PEKERJAAN TRAFO


VIII.2 PEK. PAS. KUSEN, DAUN PINTU DAN JENDELA
1 Pek. Pintu PT Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : YKK unit 1.00 3,403,132.64 3,403,132.64
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm
Lever Handle Dekkson Solid LHSR DKS 058SSS
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS
Escutcheon Dekkson ESCN DKS 855SSS
Mortise Roller Dekkson MTS RL 8585 SSS SUS316
Cylinder Dekkson CYL DC DL70mm SN
Door Closer Dekkson DCL 300 HO

2 Pek. Bouvenlight BV Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : YKK unit 5.00 346,103.12 1,730,515.60
Metal square hollow 20/20, tebal 0,9mm + Cat Anti Karat

VIII.3 PEK. PAS. PLAFOND


1 Pek. Plafond Exposed MU Acian (40kg) m2 29.00 55,457.72 1,608,273.99

VIII.4 PEK. PAS. PELAPISAN LANTAI


1 Pek. Floor Hardener Floor hardener T.5mm, Merk : Fosroc, Delta, Sica m2 29.00 33,264.00 964,656.00

VIII.5 PEK. PAS. FINISHING DAN PENGECATAN


1 Pek. Pengecatan dinding Fin. Cat Eksterior Cat dasar Jotun Jotashield Primer 7 m2 137.14 22,955.35 3,148,096.70
Cat tembok eksterior, setara Jotun Jotashield Antifade
2 Pek. Pengecatan dinding Fin. Cat Interior Cat dasar Jotun Base Coat Sealer m2 136.04 22,955.35 3,122,845.81
Cat tembok interior, setara Jotun Majestic True Beauty SHEEN
3 Pek. Pengecatan plafond Cat plafond, setara Vinilex m2 29.00 19,130.10 554,772.90

JUMLAH PEKERJAAN TRAFO Rp. 14,532,293.64


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME
Rp. Rp.
1 2 3 4 5 6 (5X6)

VI PEKERJAAN FACADE
1 Pek. Secondary Skin 1 (1 unit) Rangka metal square Galvanized, 40x40, Plat Besi, Baut, GRC Cladding bh 36.00 1,602,731.30 57,698,326.92
- Base Plat 6mm Baja Profil, Merk : DN kg 6.59 20,097.00 132,519.62
- Angkur bh 28.00 1,500.00 42,000.00
- Hollow 40x40 Metal square hollow 40/40, tebal 2,3mm m1 51.00 69,157.55 3,527,035.05
- Hollow 50x100 Metal square hollow 50/100, tebal 2,0mm m1 82.04 97,405.00 7,991,106.20
- Fin Cat Anti Karat Epoxy Cat epoxy undercoat, Merk : Petalac m2 32.77 72,902.50 2,389,160.73

2 Pek. Logo UPI Stainless Steel, Cutting, Pengecatan Duco unit 1.00 24,948,000.00 24,948,000.00

3 Pek. Secondary Skin 2 (4 unit) Rangka metal square Galvanized, 40x40, Plat Besi, Baut, GRC Cladding bh 224.00 1,602,731.30 359,011,811.95
- Base Plat 6mm Baja Profil, Merk : DN kg 28.26 20,097.00 567,941.22
- Dynabolt bh 120.00 1,500.00 180,000.00
- Hollow 40x40 Metal square hollow 40/40, tebal 2,3mm m1 182.40 69,157.55 12,614,337.12
- Hollow 50x100 Metal square hollow 50/100, tebal 2,0mm m1 345.48 97,405.00 33,651,479.40
- Fin Cat Anti Karat Epoxy Cat epoxy undercoat, Merk : Petalac m2 132.83 72,902.50 9,683,493.27

4 Pek. Secondary Skin 3 (1 unit) Rangka metal square Galvanized, 40x40, Plat Besi, Baut, GRC Cladding bh 102.00 1,602,731.30 163,478,592.94
- Base Plat 6mm Baja Profil, Merk : DN kg 11.30 20,097.00 227,176.49
- Dynabolt bh 48.00 1,500.00 72,000.00
- Hollow 40x40 Metal square hollow 40/40, tebal 2,3mm m1 91.80 69,157.55 6,348,663.09
- Hollow 50x100 Metal square hollow 50/100, tebal 2,0mm m1 141.40 97,405.00 13,773,067.00
- Fin Cat Anti Karat Epoxy Cat epoxy undercoat, Merk : Petalac m2 57.11 72,902.50 4,163,315.97

5 Pek. Secondary Skin 4 (4 unit) Rangka metal square Galvanized, 40x40, Plat Besi, Baut, GRC Cladding bh 176.00 1,602,731.30 282,080,709.39
- Base Plat 6mm Baja Profil, Merk : DN kg 24.49 20,097.00 492,215.72
- Dynabolt bh 104.00 1,500.00 156,000.00
- Hollow 40x40 Metal square hollow 40/40, tebal 2,3mm m1 149.20 69,157.55 10,318,306.46
- Hollow 50x100 Metal square hollow 50/100, tebal 2,0mm m1 280.60 97,405.00 27,331,843.00
- Fin Cat Anti Karat Epoxy Cat epoxy undercoat, Merk : Petalac m2 108.05 72,902.50 7,877,260.93

6 Pek. Aluminium Composite Panel 1 Alumunium composite panel T.4mm, Anti UV,Merk : Maco m2 208.96 318,128.25 66,476,079.12
7 Pek. Aluminium Composite Panel 2 Alumunium composite panel T.4mm, Anti UV,Merk : Maco m2 186.90 318,128.25 59,458,169.93
8 Pek. Aluminium Composite Panel 3 Alumunium composite panel T.4mm, Anti UV,Merk : Maco m2 158.64 318,128.25 50,467,865.58
9 Pek. Aluminium Composite Panel 4 Alumunium composite panel T.4mm, Anti UV,Merk : Maco m2 80.90 318,128.25 25,736,575.43
10 Pek. Huruf Stainless Steel, Cutting, Pengecatan Duco unit 46.00 523,348.54 24,074,032.84

11 Pek. Rooster Rooster Terakota uk. 200x200 m2 189.84 239,827.50 45,528,852.60

12 Pek. Kanopi
- Pek. Lipped channel 150.65.20.3,2 Baja Profil, Merk : DN kg 546.71 20,097.00 10,987,230.87
- Pek. Pengecatan Duco Cat duco polyurethane clear matt MV-3, Merk : Petalac 2K m2 133.66 65,285.00 8,725,993.10
- Pek. Aluminium Composite Panel Alumunium composite panel T.4mm, Anti UV,Merk : Maco m2 110.01 318,128.25 34,997,288.78
- Pek. Kaca Tempered Laminated 10mm Kaca tempered laminated T.10mm, setara Asahimas m2 36.30 224,125.00 8,135,737.50
(5mm polos tempered+PVB clear+5mm polos biasa)

- Pek. Rangka Plafond Lambisering Kayu Metal square hollow 40/40, tebal 1,1mm m2 29.79 41,884.15 1,247,519.41
- Pek. Plafond Lambisering Kayu Kayu papan kamper samarinda oven m2 29.79 212,198.00 6,320,317.43

JUMLAH PEKERJAAN FACADE Rp. 1,370,912,025.06


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME
Rp. Rp.
1 2 3 4 5 6 (5X6)

VII PEKERJAAN LANDSCAPE


1 Pek. Rumput Rumput Gajah Mini m2 229.96 37,840.69 8,701,844.50

2 Pek. Paving Block


- Galian tanah m3 124.90 68,200.00 8,518,180.00
- Pemadatan tanah Pemadatan tanah CBR 4% m2 249.80 52,250.00 13,052,050.00
- Sub base course T.25 cm Sirtu T.25 cm m3 62.45 26,237.20 1,638,513.14
- Base course T.15 cm Amparan batu 5-7 T.15 cm m3 37.47 155,881.00 5,840,861.07
- Lapisan pengisi 2-3 T.5 cm Amparan batu 2-3 T.5 cm m3 12.49 153,461.00 1,916,727.89
- Paving block T.8 cm Paving block press mesin, Merk : Cisangkan m2 249.80 192,368.00 48,053,526.40

3 Pek. Aspal hotmix


- Galian tanah m3 200.26 68,200.00 13,657,732.00
- Pemadatan tanah Pemadatan tanah CBR 4% m2 400.52 52,250.00 20,927,170.00
- Sub base course T.25 cm Sirtu T.25 cm m3 100.13 26,237.20 2,627,130.84
- Base course T.15 cm Amparan batu 5-7 T.15 cm m3 60.08 155,881.00 9,365,330.48
- Lapisan pengisi 1-2 & 2-3 T.5 cm Amparan batu 1-2 & 2-3 T.5 cm m3 20.03 153,461.00 3,073,823.83
- Aspal hotmix T.5 cm Aspal hotmix T.5 cm m2 400.52 124,836.25 49,999,414.85

4 Pek. Ramp
- Pemadatan tanah Pemadatan tanah CBR 4% m2 134.40 52,250.00 7,022,400.00
- Rollag 1 bata Bata merah 1 bata m2 44.80 213,609.00 9,569,683.20
- Pasir urug T.10 cm Urugan pasir T.10 cm m3 13.44 194,150.00 2,609,376.00
- Lantai kerja T.5 cm Camp 1PC : 3PS : 5KR T.5 cm m3 6.72 703,807.50 4,729,586.40
- Cor beton T.12cm Cor beton Ready mix K-300 fc' : 26,40 Mpa m3 16.13 973,115.00 15,696,344.95
- Wiremesh M8 Wiremesh M8 kg 732.48 40,122.50 29,388,928.80

5 Pek. Trap tangga


- Pemadatan tanah Pemadatan tanah CBR 4% m2 2.88 52,250.00 150,480.00
- Rollag 1 bata Bata merah 1 bata m2 4.32 213,609.00 922,790.88
- Pasir urug T.10 cm Urugan pasir T.10 cm m3 0.29 194,150.00 56,303.50
- Lantai kerja T.5 cm Camp 1PC : 3PS : 5KR T.5 cm m3 0.14 703,807.50 98,533.05
- Pelapisan Batu Sikat m2 4.73 233,557.50 1,104,726.98

6 Pembuatan saluran air galian tanah biasa termasuk pki alat berat m3 288.75 68,200.00 19,692,750.00
- Galian tanah biasa tanah ex.galian diurug/ratakan kembali & dipadatkan m3 99.00 68,200.00 6,751,800.00
- Urugan tanah kembali U ditch precast, termasuk urugan pasir, m' 150.00 56,000.00 8,400,000.00
- Pasang U ditch uk.80x100x120 lantai kerja dan alat bantu

JUMLAH PEKERJAAN LANDSCAPE Rp. 293,566,008.75


ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN

K3
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
JUMLAH TENAGA KERJA
B. BAHAN
Kotak P3K paket 1.00 15,000.00 15,000.00
Fire Extinguisher bh 4.00 500,000.00 2,000,000.00
Asuransi Tenaga Kerja lot 1.00 12,500,000.00 12,500,000.00
Alat Perlindungan Tenaga Kerja lot 1.00 5,000,000.00 5,000,000.00
Jaring Pengaman ls 1.00 5,000,000.00 5,000,000.00
JUMLAH HARGA BAHAN 24,515,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 24,515,000.00


E. Overhead & Profit 10% 2,451,500.00
F. Harga Satuan Pekerjaan (D+E) 26,966,500.00

Pengadaan Tenaga Listrik


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
JUMLAH TENAGA KERJA
B. BAHAN
Listrik Kerja bln 1.00 5,000,000.00 5,000,000.00
Pengadaan air bln 6.00 1,500,000.00 9,000,000.00
JUMLAH HARGA BAHAN 14,000,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 14,000,000.00


E. Overhead & Profit 10% 1,400,000.00
F. Harga Satuan Pekerjaan (D+E) 15,400,000.00

Mobilisasi atau transportasi peralatan dan bahan + Lift Barang


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
JUMLAH TENAGA KERJA
B. BAHAN
Biaya sewa lift barang bulan 5.00 7,500,000.00 37,500,000.00
Biaya Sewa Mobile Crane bulan 3.00 25,000,000.00 75,000,000.00
Biaya mobilisasi, demobilisasi dan
Ls 1.00 25,000,000.00 25,000,000.00
Pembersihan sisa pekerjaan
Biaya operator Ls 1.00 12,000,000.00 12,000,000.00
JUMLAH HARGA BAHAN 149,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 149,500,000.00


E. Overhead & Profit 10% 14,950,000.00
F. Harga Satuan Pekerjaan (D+E) 164,450,000.00
ANALISA HARGA SATUAN PEKERJAAN STRUKTUR

A.2.3.1.1. Penggalian 1 m3 Tanah Biasa Sedalam 1m


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.70 85,000.00 59,500.00
Mandor L.04 OH 0.03 100,000.00 2,500.00
JUMLAH TENAGA KERJA 62,000.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 62,000.00


E. Overhead & Profit 10% 6,200.00
F. Harga Satuan Pekerjaan (D+E) 68,200.00

A.2.3.1.11. Pengurugan 1 m3 Dengan Pasir Urug


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.30 85,000.00 25,500.00
Mandor L.04 OH 0.01 100,000.00 1,000.00
JUMLAH TENAGA KERJA 26,500.00
B. BAHAN
Pasir Urug m3 1.20 125,000.00 150,000.00
JUMLAH HARGA BAHAN 150,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 176,500.00


E. Overhead & Profit 10% 17,650.00
F. Harga Satuan Pekerjaan (D+E) 194,150.00

A.4.1.1.4. Membuat 1 m3 Lantai Kerja Beton Mutu f'c = 7,4 Mpa Slump (3-6)cm, w/c = 0,87
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.20 85,000.00 102,000.00
Tukang Batu L.02 OH 0.20 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.02 95,000.00 1,900.00
Mandor L.04 OH 0.06 100,000.00 6,000.00
JUMLAH TENAGA KERJA 127,900.00
B. BAHAN
Semen Portland kg 230.00 1,100.00 253,000.00
Pasir Beton kg 893.00 250.00 223,250.00
Kerikil (Maks 30mm) kg 1,027.00 25.00 25,675.00
Air ltr 200.00 50.00 10,000.00
JUMLAH HARGA BAHAN 511,925.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 639,825.00


E. Overhead & Profit 10% 63,982.50
F. Harga Satuan Pekerjaan (D+E) 703,807.50

A.4.1.1.5. Membuat 1 m3 Beton Mutu f'c = 14,5 Mpa (K-175)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.65 85,000.00 140,250.00
Tukang Batu L.02 OH 0.28 90,000.00 24,750.00
Kepala Tukang L.03 OH 0.03 95,000.00 2,660.00
Mandor L.04 OH 0.08 100,000.00 8,300.00
JUMLAH TENAGA KERJA 175,960.00
B. BAHAN
Semen Portland kg 326.00 1,100.00 358,600.00
Pasir Beton kg 760.00 250.00 190,000.00
Kerikil (Maks 30mm) kg 1,029.00 25.00 25,725.00
Air ltr 215.00 50.00 10,750.00
JUMLAH HARGA BAHAN 585,075.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 761,035.00


E. Overhead & Profit 10% 76,103.50
F. Harga Satuan Pekerjaan (D+E) 837,138.50

A.4.1.1.10. Membuat 1 m3 Beton Mutu f'c = 26,40 Mpa (K-300)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.10 85,000.00 178,500.00
Tukang Batu L.02 OH 0.35 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.04 95,000.00 3,325.00
Mandor L.04 OH 0.11 100,000.00 10,500.00
JUMLAH TENAGA KERJA 223,825.00
B. BAHAN
Semen Portland kg 413.00 1,100.00 454,300.00
Pasir Beton kg 681.00 250.00 170,250.00
Kerikil (Maks 30mm) kg 1,021.00 25.00 25,525.00
Air ltr 215.00 50.00 10,750.00
JUMLAH HARGA BAHAN 660,825.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 884,650.00


E. Overhead & Profit 10% 88,465.00
F. Harga Satuan Pekerjaan (D+E) 973,115.00

A.4.1.1.12. Membuat 1 m3 Beton Mutu f'c = 31,20 Mpa (K-350)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.10 85,000.00 178,500.00
Tukang Batu L.02 OH 0.35 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.04 95,000.00 3,325.00
Mandor L.04 OH 0.11 100,000.00 10,500.00
JUMLAH TENAGA KERJA 223,825.00
B. BAHAN
Semen Portland kg 448.00 1,100.00 492,800.00
Pasir Beton kg 667.00 250.00 166,750.00
Kerikil (Maks 30mm) kg 1,000.00 25.00 25,000.00
Air ltr 215.00 50.00 10,750.00
JUMLAH HARGA BAHAN 695,300.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 919,125.00


E. Overhead & Profit 10% 91,912.50
F. Harga Satuan Pekerjaan (D+E) 1,011,037.50

A.4.1.1.17. Pembesian 1 kg dengan Besi Polos


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.01 85,000.00 595.00
Tukang besi L.02 OH 0.01 90,000.00 630.00
Kepala Tukang L.03 OH 0.00 95,000.00 66.50
Mandor L.04 OH 0.00 100,000.00 40.00
JUMLAH TENAGA KERJA 1,331.50
B. BAHAN
Besi Beton Polos kg 1.05 9,500.00 9,975.00
Kawat Beton kg 0.02 18,000.00 270.00
JUMLAH HARGA BAHAN 10,245.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 11,576.50


E. Overhead & Profit 10% 1,157.65
F. Harga Satuan Pekerjaan (D+E) 12,734.15

A.4.1.1.17. Pembesian 1 kg dengan Besi Ulir


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.01 85,000.00 595.00
Tukang besi L.02 OH 0.01 90,000.00 630.00
Kepala Tukang L.03 OH 0.00 95,000.00 66.50
Mandor L.04 OH 0.00 100,000.00 40.00
JUMLAH TENAGA KERJA 1,331.50
B. BAHAN
Besi Beton Ulir kg 1.05 9,500.00 9,975.00
Kawat Beton kg 0.02 18,000.00 270.00
JUMLAH HARGA BAHAN 10,245.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 11,576.50


E. Overhead & Profit 10% 1,157.65
F. Harga Satuan Pekerjaan (D+E) 12,734.15

A.4.1.1.19. Pemasangan 1 kg Jaring Kawat Baja (Wiremesh)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.00 85,000.00 212.50
Tukang besi L.02 OH 0.00 90,000.00 225.00
Kepala Tukang L.03 OH 0.00 95,000.00 237.50
Mandor L.04 OH 0.00 100,000.00 10.00
JUMLAH TENAGA KERJA 685.00
B. BAHAN
Jaring Kawat Baja Dilas kg 1.02 35,000.00 35,700.00
Kawat Beton kg 0.01 18,000.00 90.00
JUMLAH HARGA BAHAN 35,790.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 36,475.00


E. Overhead & Profit 10% 3,647.50
F. Harga Satuan Pekerjaan (D+E) 40,122.50

A.4.1.1.22. Pemasangan 1 m2 Bekisting Untuk Kolom


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 85,000.00 56,100.00
Tukang kayu L.02 OH 0.33 90,000.00 29,700.00
Kepala Tukang L.03 OH 0.03 95,000.00 3,135.00
Mandor L.04 OH 0.03 100,000.00 3,300.00
JUMLAH TENAGA KERJA 92,235.00
B. BAHAN
Kayu Kelas III m3 0.05 1,500,000.00 71,250.00
Paku 5-10cm kg 0.40 18,000.00 7,200.00
Minyak Bekisting ltr 0.20 10,000.00 2,000.00
JUMLAH HARGA BAHAN 80,450.00
C. PERALATAN
Sewa Pipa Support + Accesories bh 1.00 5,000.00 5,000.00
JUMLAH HARGA PERALATAN 5,000.00

D. Jumlah (A+B+C) 177,685.00


E. Overhead & Profit 10% 17,768.50
F. Harga Satuan Pekerjaan (D+E) 195,453.50

A.4.1.1.22. Pemasangan 1 m2 Bekisting Untuk Kolom 3 x pakai


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 85,000.00 56,100.00
Tukang kayu L.02 OH 0.33 90,000.00 29,700.00
Kepala Tukang L.03 OH 0.03 95,000.00 3,135.00
Mandor L.04 OH 0.03 100,000.00 3,300.00
JUMLAH TENAGA KERJA 92,235.00
B. BAHAN
Kayu Papan Albasiah m3 0.05 1,500,000.00 71,250.00
Paku 5-10cm kg 0.40 18,000.00 7,200.00
Minyak Bekisting ltr 0.20 10,000.00 2,000.00

JUMLAH HARGA BAHAN 80,450.00


C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 172,685.00


E. Overhead & Profit 10% 17,268.50
F. Harga Satuan Pekerjaan (D+E) 189,953.50

A.4.1.1.23. Pemasangan 1 m2 Bekisting Untuk Balok


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 85,000.00 56,100.00
Tukang kayu L.02 OH 0.33 90,000.00 29,700.00
Kepala Tukang L.03 OH 0.03 95,000.00 3,135.00
Mandor L.04 OH 0.03 100,000.00 3,300.00
JUMLAH TENAGA KERJA 92,235.00
B. BAHAN
Kayu Kelas III m3 0.06 1,500,000.00 87,000.00
Paku 5-10cm kg 0.40 18,000.00 7,200.00
Minyak Bekisting ltr 0.20 10,000.00 2,000.00
Plywood tebal 9mm lbr 0.35 110,000.00 38,500.00
JUMLAH HARGA BAHAN 134,700.00
C. PERALATAN
Sewa Perancah/Scafolding + Accessories lot 1.00 1,500.00 1,500.00
JUMLAH HARGA PERALATAN 1,500.00

D. Jumlah (A+B+C) 228,435.00


E. Overhead & Profit 10% 22,843.50
F. Harga Satuan Pekerjaan (D+E) 251,278.50

A.4.1.1.23. Pemasangan 1 m2 Bekisting Untuk Balok Praktis


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 85,000.00 56,100.00
Tukang kayu L.02 OH 0.33 90,000.00 29,700.00
Kepala Tukang L.03 OH 0.03 95,000.00 3,135.00
Mandor L.04 OH 0.03 100,000.00 3,300.00
JUMLAH TENAGA KERJA 92,235.00
B. BAHAN
Kayu Papan Albasiah m3 0.05 1,750,000.00 85,750.00
Paku 5-10cm kg 0.40 18,000.00 7,200.00
Minyak Bekisting ltr 0.20 10,000.00 2,000.00
Plywood tebal 9mm lbr 0.35 110,000.00 38,500.00
JUMLAH HARGA BAHAN 133,450.00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 225,685.00


E. Overhead & Profit 10% 22,568.50
F. Harga Satuan Pekerjaan (D+E) 248,253.50

A.4.1.1.24. Pemasangan 1 m2 Bekisting Untuk Lantai


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 85,000.00 56,100.00
Tukang kayu L.02 OH 0.33 90,000.00 29,700.00
Kepala Tukang L.03 OH 0.03 95,000.00 3,135.00
Mandor L.04 OH 0.03 100,000.00 3,300.00
JUMLAH TENAGA KERJA 92,235.00
B. BAHAN
Kayu Kelas III m3 0.05 1,500,000.00 71,250.00
Paku 5-10cm kg 0.40 18,000.00 7,200.00
Minyak Bekisting ltr 0.20 10,000.00 2,000.00
Plywood tebal 9mm lbr 0.35 110,000.00 38,500.00
JUMLAH HARGA BAHAN 118,950.00
C. PERALATAN
Sewa Perancah/Scafolding + Accessories lot 1.00 1,500.00 1,500.00
JUMLAH HARGA PERALATAN 1,500.00

D. Jumlah (A+B+C) 212,685.00


E. Overhead & Profit 10% 21,268.50
F. Harga Satuan Pekerjaan (D+E) 233,953.50

A.4.1.1.25. Pemasangan 1 m2 Bekisting Untuk Dinding


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 85,000.00 56,100.00
Tukang kayu L.02 OH 0.33 90,000.00 29,700.00
Kepala Tukang L.03 OH 0.03 95,000.00 3,135.00
Mandor L.04 OH 0.03 100,000.00 3,300.00
JUMLAH TENAGA KERJA 92,235.00
B. BAHAN
Kayu Kelas III m3 0.09 1,500,000.00 135,000.00
Paku 5-10cm kg 0.40 18,000.00 7,200.00
Minyak Bekisting ltr 0.20 10,000.00 2,000.00
Balok Kayu Kelas III m3 0.02 1,250,000.00 25,000.00
Penjaga Jarak Bekisting/Spacer bh 4.00 100.00 400.00
JUMLAH HARGA BAHAN 169,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 261,835.00


E. Overhead & Profit 10% 26,183.50
F. Harga Satuan Pekerjaan (D+E) 288,018.50

A.4.1.1.26. Pemasangan 1 m2 Bekisting Untuk Tangga


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 85,000.00 56,100.00
Tukang kayu L.02 OH 0.33 90,000.00 29,700.00
Kepala Tukang L.03 OH 0.03 95,000.00 3,135.00
Mandor L.04 OH 0.03 100,000.00 3,300.00
JUMLAH TENAGA KERJA 92,235.00
B. BAHAN
Kayu Kelas III m3 0.05 1,500,000.00 67,500.00
Paku 5-10cm kg 0.40 18,000.00 7,200.00
Minyak Bekisting ltr 0.15 10,000.00 1,500.00
Plywood tebal 9mm lbr 0.35 110,000.00 38,500.00
JUMLAH HARGA BAHAN 114,700.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 206,935.00


E. Overhead & Profit 10% 20,693.50
F. Harga Satuan Pekerjaan (D+E) 227,628.50

Pemasangan 1 m2 Bekisting Batako


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.32 85,000.00 27,353.00
Tukang kayu L.02 OH 0.18 90,000.00 16,245.00
Kepala Tukang L.03 OH 0.02 95,000.00 1,501.00
Mandor L.04 OH 0.01 100,000.00 830.00
JUMLAH TENAGA KERJA 45,929.00
B. BAHAN
Batako bh 13.00 1,500.00 19,500.00
Semen PC 50kg zak 0.04 50,000.00 2,074.00
Pasir pasang m3 0.01 185,000.00 2,146.00
JUMLAH HARGA BAHAN 23,720.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 69,649.00


E. Overhead & Profit 10% 6,964.90
F. Harga Satuan Pekerjaan (D+E) 76,613.90

Pengerjaan 1 kg Pekerjaan Baja Profil


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.06 85,000.00 5,100.00
Tukang Besi L.02 OH 0.06 90,000.00 5,400.00
Kepala Tukang L.03 OH 0.01 95,000.00 570.00
Mandor L.04 OH 0.00 100,000.00 300.00
JUMLAH TENAGA KERJA 11,370.00
B. BAHAN
Baja Profil, Merk : DN kg 1.15 6,000.00 6,900.00
JUMLAH HARGA BAHAN 6,900.00
C. PERALATAN

JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 18,270.00


E. Overhead & Profit 10% 1,827.00
F. Harga Satuan Pekerjaan (D+E) 20,097.00

A.4.1.1.14. Pemasangan 1 m1 PVC Waterstop Lebar 150mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.06 85,000.00 5,100.00
Tukang L.02 OH 0.03 90,000.00 2,700.00
Kepala Tukang L.03 OH 0.00 95,000.00 285.00
Mandor L.04 OH 0.00 100,000.00 300.00
JUMLAH TENAGA KERJA 8,385.00
B. BAHAN
Waterstop Lebar 150 mm m1 1.05 85,000.00 89,250.00
JUMLAH HARGA BAHAN 89,250.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 97,635.00


E. Overhead & Profit 10% 9,763.50
F. Harga Satuan Pekerjaan (D+E) 107,398.50

1 m1 Pek. Pas. Reng zincalume


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 1,010.63 1,010.63
JUMLAH TENAGA KERJA 1,010.63
B. BAHAN
Reng zincalume m1 1.05 5,833.33 6,125.00
JUMLAH HARGA BAHAN 6,125.00
C. PERALATAN
Material & alat Bantu ls 1.00 612.50 612.50
JUMLAH HARGA PERALATAN 612.50

D. Jumlah (A+B+C) 7,748.13


E. Overhead & Profit 10% 774.81
F. Harga Satuan Pekerjaan (D+E) 8,522.94

1 m1 Pek. Pas. Hollow 30x60


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 4,966.50 4,966.50
JUMLAH TENAGA KERJA 4,966.50
B. BAHAN
Metal square hollow 30/60, tebal 1,1mm m1 1.05 28,666.67 30,100.00
JUMLAH HARGA BAHAN 30,100.00
C. PERALATAN
Material & alat Bantu ls 1.00 3,010.00 3,010.00
JUMLAH HARGA PERALATAN 3,010.00

D. Jumlah (A+B+C) 38,076.50


E. Overhead & Profit 10% 3,807.65
F. Harga Satuan Pekerjaan (D+E) 41,884.15

1 m1 Pek. Pas. Hollow 40x40


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 5,717.25 5,717.25
JUMLAH TENAGA KERJA 5,717.25
B. BAHAN
Metal square hollow 40/40, tebal 1,1mm m1 1.05 33,000.00 34,650.00
JUMLAH HARGA BAHAN 34,650.00
C. PERALATAN
Material & alat Bantu ls 1.00 3,465.00 3,465.00
JUMLAH HARGA PERALATAN 3,465.00

D. Jumlah (A+B+C) 43,832.25


E. Overhead & Profit 10% 4,383.23
F. Harga Satuan Pekerjaan (D+E) 48,215.48

1 m1 Pek. Pas. Hollow 40x40


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 8,200.50 8,200.50
JUMLAH TENAGA KERJA 8,200.50
B. BAHAN
Metal square hollow 40/40, tebal 2,3mm m1 1.05 47,333.33 49,700.00
JUMLAH HARGA BAHAN 49,700.00
C. PERALATAN
Material & alat Bantu ls 1.00 4,970.00 4,970.00
JUMLAH HARGA PERALATAN 4,970.00

D. Jumlah (A+B+C) 62,870.50


E. Overhead & Profit 10% 6,287.05
F. Harga Satuan Pekerjaan (D+E) 69,157.55

1 m1 Pek. Pas. Hollow 50x100


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 11,550.00 11,550.00
JUMLAH TENAGA KERJA 11,550.00
B. BAHAN
Metal square hollow 50/100, tebal 2,0mm m1 1.05 66,666.67 70,000.00
JUMLAH HARGA BAHAN 70,000.00
C. PERALATAN
Material & alat Bantu ls 1.00 7,000.00 7,000.00
JUMLAH HARGA PERALATAN 7,000.00

D. Jumlah (A+B+C) 88,550.00


E. Overhead & Profit 10% 8,855.00
F. Harga Satuan Pekerjaan (D+E) 97,405.00
ANALISA HARGA SATUAN PEKERJAAN ARSITEKTUR

Pemasangan 1 m2 Dinding Bata Ringan Tebal 10cm Dengan Mortar Siap Pakai
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1000 85,000.00 8,500.00
Tukang Batu L.02 OH 0.2000 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.0100 95,000.00 950.00
Mandor L.04 OH 0.0100 100,000.00 1,000.00
JUMLAH TENAGA KERJA 28,450.00
B. BAHAN
Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m3 0.1100 550,000.00 60,500.00
Drymix Thinbed M-101 (40kg) zak 0.1000 45,000.00 4,500.00
Angkur dia. 8mm kg 0.2000 7,000.00 1,400.00
JUMLAH HARGA BAHAN 66,400.00

C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 94,850.00


E. Overhead & Profit 10% 9,485.00
F. Harga Satuan Pekerjaan (D+E) 104,335.00

A.4.4.1.4. Pemasangan 1 m2 Dinding Bata Merah (5x11x12)cm Tebal 1 Batu Campuran 1SP:5PP
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.6000 85,000.00 51,000.00
Tukang Batu L.02 OH 0.2000 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.0200 95,000.00 1,900.00
Mandor L.04 OH 0.0300 100,000.00 3,000.00
JUMLAH TENAGA KERJA 73,900.00
B. BAHAN
Bata Merah bh 77.0000 1,000.00 77,000.00
Semen Portland kg 22.2000 1,100.00 24,420.00
Pasir Pasang m3 0.1020 185,000.00 18,870.00
JUMLAH HARGA BAHAN 120,290.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 194,190.00


E. Overhead & Profit 10% 19,419.00
F. Harga Satuan Pekerjaan (D+E) 213,609.00

Pemasangan 1 m2 Partisi Gypsum T.12mm + rangka hollow


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1500 85,000.00 12,750.00
Tukang Batu L.02 OH 0.2000 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.0400 95,000.00 3,800.00
Mandor L.04 OH 0.0100 100,000.00 1,000.00
JUMLAH TENAGA KERJA 35,550.00
B. BAHAN
U Runner 92.25 m1 3.2500 350.00 1,137.50
Gypsumboard T.9mm, Merk : A-Plus lbr 0.6944 49,000.00 34,027.78
Sekrup kg 0.3750 150.00 56.25
JUMLAH HARGA BAHAN 35,221.53

C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 70,771.53


E. Overhead & Profit 10% 7,077.15
F. Harga Satuan Pekerjaan (D+E) 77,848.68

Pemasangan 1 m2 plesteran tebal 10mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1600 85,000.00 13,600.00
Tukang Batu L.02 OH 0.1500 90,000.00 13,500.00
Kepala Tukang L.03 OH 0.0150 95,000.00 1,425.00
Mandor L.04 OH 0.0150 100,000.00 1,500.00
JUMLAH TENAGA KERJA 30,025.00
B. BAHAN
MU Plester (50kg) kg 4.4700 2,125.00 9,498.75
JUMLAH HARGA BAHAN 9,498.75
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 39,523.75


E. Overhead & Profit 10% 3,952.38
F. Harga Satuan Pekerjaan (D+E) 43,476.13

A.4.4.2.27. Pemasangan 1 m2 acian


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1500 85,000.00 12,750.00
Tukang Batu L.02 OH 0.1000 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.0100 95,000.00 950.00
Mandor L.04 OH 0.0100 100,000.00 1,000.00
JUMLAH TENAGA KERJA 23,700.00
B. BAHAN
MU Acian (40kg) kg 2.7500 1,375.00 3,781.25
JUMLAH HARGA BAHAN 3,781.25
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 27,481.25


E. Overhead & Profit 10% 2,748.13
F. Harga Satuan Pekerjaan (D+E) 30,229.38

Pelapisan 1 m2 Dinding Batu Alam


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.7000 85,000.00 59,500.00
Tukang Batu L.02 OH 0.3500 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.0350 95,000.00 3,325.00
Mandor L.04 OH 0.0350 100,000.00 3,500.00
JUMLAH TENAGA KERJA 97,825.00
B. BAHAN
Batu Alam m2 1.0500 95,000.00 99,750.00
Drymix tile adhesive (40kg) zak 0.2000 55,000.00 11,000.00
Semen Warna kg 0.5000 7,500.00 3,750.00
JUMLAH HARGA BAHAN 114,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 212,325.00


E. Overhead & Profit 10% 21,232.50
F. Harga Satuan Pekerjaan (D+E) 233,557.50

A.4.5.1.7. Pemasangan 1 m2 Langit - langit gypsum board ukuran (120x240x9) mm, tebal 9mm
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1000 85,000.00 8,500.00
Tukang Kayu L.02 OH 0.0500 90,000.00 4,500.00
Kepala Tukang L.03 OH 0.0050 95,000.00 475.00
Mandor L.04 OH 0.0050 100,000.00 500.00
JUMLAH TENAGA KERJA 13,975.00
B. BAHAN
Gypsumboard T.9mm, Merk : A-Plus lbr 0.3640 49,000.00 17,836.00
Sekrup kg 0.1100 150.00 16.50
Compound kg 0.5500 35,000.00 19,250.00
JUMLAH HARGA BAHAN 37,102.50
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 51,077.50


E. Overhead & Profit 10% 5,107.75
F. Harga Satuan Pekerjaan (D+E) 56,185.25

A.4.5.1.7. Pemasangan 1 m2 Langit - langit gypsum board wet area ukuran (120x240x9) mm, tebal 9mm
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1000 85,000.00 8,500.00
Tukang Kayu L.02 OH 0.0500 90,000.00 4,500.00
Kepala Tukang L.03 OH 0.0050 95,000.00 475.00
Mandor L.04 OH 0.0050 100,000.00 500.00
JUMLAH TENAGA KERJA 13,975.00
B. BAHAN
Gypsumboard T.9mm, Merk : A-Plus lbr 0.3640 49,000.00 17,836.00
Sekrup kg 0.1100 150.00 16.50
Compound kg 0.5500 35,000.00 19,250.00
JUMLAH HARGA BAHAN 37,102.50
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 51,077.50


E. Overhead & Profit 10% 5,107.75
F. Harga Satuan Pekerjaan (D+E) 56,185.25

A.4.5.1.6. Pemasangan 1 m2 Langit - langit lambisering kayu, tebal 9mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.6000 85,000.00 51,000.00
Tukang Kayu L.02 OH 0.8000 90,000.00 72,000.00
Kepala Tukang L.03 OH 0.0900 95,000.00 8,550.00
Mandor L.04 OH 0.0400 100,000.00 4,000.00
JUMLAH TENAGA KERJA 135,550.00
B. BAHAN
Kayu papan kamper samarinda oven m3 0.0150 3,250,000.00 48,750.00
Paku Triplek kg 0.0100 22,000.00 220.00
JUMLAH HARGA BAHAN 48,970.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 184,520.00


E. Overhead & Profit 15% 27,678.00
F. Harga Satuan Pekerjaan (D+E) 212,198.00

A.4.5.1.10. Pemasangan 1 m2 rangka langit-langit


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1400 85,000.00 11,900.00
Tukang Kayu L.02 OH 0.1400 90,000.00 12,600.00
Kepala Tukang L.03 OH 0.0140 95,000.00 1,330.00
Mandor L.04 OH 0.0140 100,000.00 1,400.00
JUMLAH TENAGA KERJA 27,230.00
B. BAHAN
Metal square hollow 40/20, tebal 1,1mm m1 3.0000 18,666.67 56,000.00
Metal square hollow 40/40, tebal 1,1mm m1 1.0000 33,000.00 33,000.00
Acssesoris (Perkuatan,Las,dll) ls 1.0000 5,000.00 5,000.00
JUMLAH HARGA BAHAN 94,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 121,230.00


E. Overhead & Profit 10% 12,123.00
F. Harga Satuan Pekerjaan (D+E) 133,353.00

A.4.5.1.10. Pemasangan 1 m2 rangka langit-langit Lambisering


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1400 85,000.00 11,900.00
Tukang Kayu L.02 OH 0.1000 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.0140 95,000.00 1,330.00
Mandor L.04 OH 0.0140 100,000.00 1,400.00
JUMLAH TENAGA KERJA 23,630.00
B. BAHAN
Metal square hollow 40/40, tebal 1,1mm m1 4.0000 33,000.00 132,000.00
Acssesoris (Perkuatan,Las,dll) ls 1.0000 5,000.00 5,000.00
JUMLAH HARGA BAHAN 137,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 160,630.00


E. Overhead & Profit 10% 16,063.00
F. Harga Satuan Pekerjaan (D+E) 176,693.00

A.4.5.1.10. Pemasangan 1 m2 rangka langit-langit


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1400 85,000.00 11,900.00
Tukang Kayu L.02 OH 0.1000 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.0140 95,000.00 1,330.00
Mandor L.04 OH 0.0140 100,000.00 1,400.00
JUMLAH TENAGA KERJA 23,630.00
B. BAHAN
Metal furing acoustic Tee m1 3.3000 16,666.67 55,000.00
Metal furing acoustic wall angle m1 0.4000 15,833.33 6,333.33
Suspension rod dia 4mm btg 0.8000 4,000.00 3,200.00
Suspension clip bh 2.0000 11,500.00 23,000.00
Rumset bh 2.0000 1,500.00 3,000.00
JUMLAH HARGA BAHAN 90,533.33
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 114,163.33


E. Overhead & Profit 10% 11,416.33
F. Harga Satuan Pekerjaan (D+E) 125,579.67

A.4.5.1.9. Pemasangan 1 m1 List langit-langit


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0500 85,000.00 4,250.00
Tukang Kayu L.02 OH 0.0500 90,000.00 4,500.00
Kepala Tukang L.03 OH 0.0050 95,000.00 475.00
Mandor L.04 OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 9,525.00
B. BAHAN
List plafond profil aluminium U, 1cm m1 1.0000 7,000.00 7,000.00
Sekrup kg 0.0100 150.00 1.50
JUMLAH HARGA BAHAN 7,001.50
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 16,526.50


E. Overhead & Profit 10% 1,652.65
F. Harga Satuan Pekerjaan (D+E) 18,179.15

A.4.5.1.9. Pemasangan 1 m1 List langit-langit


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0500 85,000.00 4,250.00
Tukang Kayu L.02 OH 0.0500 90,000.00 4,500.00
Kepala Tukang L.03 OH 0.0050 95,000.00 475.00
Mandor L.04 OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 9,525.00
B. BAHAN
List plafond profil aluminium U, 2cm m1 1.0000 7,500.00 7,500.00
Sekrup kg 0.0100 150.00 1.50
JUMLAH HARGA BAHAN 7,501.50
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 17,026.50


E. Overhead & Profit 10% 1,702.65
F. Harga Satuan Pekerjaan (D+E) 18,729.15

Pemasangan 1 m2 Dinding Homogenous tile, uk. 600x600


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2400 85,000.00 20,400.00
Tukang Batu L.02 OH 0.3500 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.0350 95,000.00 3,325.00
Mandor L.04 OH 0.0350 100,000.00 3,500.00
JUMLAH TENAGA KERJA 58,725.00
B. BAHAN
Homogeneous Tile 600x600 Merk : Vicenca GYK 6607 m2 1.0500 150,000.00 157,500.00
Drymix TA water repellent (40kg) zak 0.1250 48,000.00 6,000.00
Semen Warna kg 0.5000 7,500.00 3,750.00
JUMLAH HARGA BAHAN 167,250.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 225,975.00


E. Overhead & Profit 10% 22,597.50
F. Harga Satuan Pekerjaan (D+E) 248,572.50

Pemasangan 1 m2 Dinding Homogeneous Tile 600x600


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2400 85,000.00 20,400.00
Tukang Batu L.02 OH 0.3500 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.0350 95,000.00 3,325.00
Mandor L.04 OH 0.0350 100,000.00 3,500.00
JUMLAH TENAGA KERJA 58,725.00
B. BAHAN
Homogeneous Tile 600x600 Merk : Habitat Arabella m2 1.0500 125,000.00 131,250.00
Drymix TA water repellent (40kg) zak 0.1250 48,000.00 6,000.00
Semen Warna kg 0.5000 7,500.00 3,750.00
JUMLAH HARGA BAHAN 141,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 199,725.00


E. Overhead & Profit 10% 19,972.50
F. Harga Satuan Pekerjaan (D+E) 219,697.50

Pemasangan 1 m2 Dinding Homogeneous Tile 600x600


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2400 85,000.00 20,400.00
Tukang Batu L.02 OH 0.3500 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.0350 95,000.00 3,325.00
Mandor L.04 OH 0.0350 100,000.00 3,500.00
JUMLAH TENAGA KERJA 58,725.00
B. BAHAN
Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 1.0500 80,000.00 84,000.00
Drymix TA water repellent (40kg) zak 0.1250 48,000.00 6,000.00
Semen Warna kg 0.5000 7,500.00 3,750.00
JUMLAH HARGA BAHAN 93,750.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 152,475.00


E. Overhead & Profit 10% 15,247.50
F. Harga Satuan Pekerjaan (D+E) 167,722.50

Pemasangan 1 m2 lantai Homogeneous Tile 600x600


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2400 85,000.00 20,400.00
Tukang Batu L.02 OH 0.3500 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.0120 95,000.00 1,140.00
Mandor L.04 OH 0.0120 100,000.00 1,200.00
JUMLAH TENAGA KERJA 54,240.00
B. BAHAN
Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 1.0000 80,000.00 80,000.00
Semen Portland kg 9.6000 1,100.00 10,560.00
Semen warna kg 0.6000 7,500.00 4,500.00
Pasir Pasang m3 0.0450 185,000.00 8,325.00
JUMLAH HARGA BAHAN 103,385.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 157,625.00


E. Overhead & Profit 10% 15,762.50
F. Harga Satuan Pekerjaan (D+E) 173,387.50

Pemasangan 1 m2 Lantai KM/WC Homogeneous Tile 600x600


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2500 85,000.00 21,250.00
Tukang Batu L.02 OH 0.1250 90,000.00 11,250.00
Kepala Tukang L.03 OH 0.0130 95,000.00 1,235.00
Mandor L.04 OH 0.0130 100,000.00 1,300.00
JUMLAH TENAGA KERJA 35,035.00
B. BAHAN
Homogeneous Tile 600x600 Merk : Vicenca GYK 6607 m2 1.0500 150,000.00 157,500.00
Drymix TA water repellent (40kg) zak 0.2000 48,000.00 9,600.00
Semen Warna kg 0.0650 7,500.00 487.50
JUMLAH HARGA BAHAN 167,587.50
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 202,622.50


E. Overhead & Profit 10% 20,262.25
F. Harga Satuan Pekerjaan (D+E) 222,884.75

A.4.4.3.44. Pemasangan 1 m2 lantai Karpet


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1700 85,000.00 14,450.00
Tukang Batu L.02 OH 0.1700 90,000.00 15,300.00
Kepala Tukang L.03 OH 0.0170 95,000.00 1,615.00
Mandor L.04 OH 0.0090 100,000.00 900.00
JUMLAH TENAGA KERJA 32,265.00
B. BAHAN
Karpet, Tuntex m2 1.0500 35,000.00 36,750.00
Lem Karpet kg 0.3500 35,000.00 12,250.00
JUMLAH HARGA BAHAN 49,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 81,265.00


E. Overhead & Profit 10% 8,126.50
F. Harga Satuan Pekerjaan (D+E) 89,391.50

A.4.4.3.61. Pemasangan 1 m2 Floor Hardener


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1200 85,000.00 10,200.00
Tukang Batu L.02 OH 0.1200 90,000.00 10,800.00
Kepala Tukang L.03 OH 0.0120 95,000.00 1,140.00
Mandor L.04 OH 0.0060 100,000.00 600.00
JUMLAH TENAGA KERJA 22,740.00
B. BAHAN
Floor hardener T.5mm, Merk : Fosroc, Delta, Sica kg 5.0000 1,500.00 7,500.00
JUMLAH HARGA BAHAN 7,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 30,240.00


E. Overhead & Profit 10% 3,024.00
F. Harga Satuan Pekerjaan (D+E) 33,264.00

Pemasangan 1 m2 Homogenous Tile 600x600 lantai tangga


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.7000 85,000.00 59,500.00
Tukang Batu L.02 OH 0.3500 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.0350 95,000.00 3,325.00
Mandor L.04 OH 0.0350 100,000.00 3,500.00
Pembuatan alur stepnoshing L.05 ls 1.0000 -
JUMLAH TENAGA KERJA 97,825.00
B. BAHAN
Homogeneous Tile 600x600 Cementum matt beige, Merk : Niro granit m2 1.0000 175,000.00 175,000.00
Drymix tile adhesive (40kg) zak 0.2000 55,000.00 11,000.00
Semen Warna kg 0.5000 7,500.00 3,750.00
JUMLAH HARGA BAHAN 189,750.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 287,575.00


E. Overhead & Profit 10% 28,757.50
F. Harga Satuan Pekerjaan (D+E) 316,332.50

Pemasangan 1 m2 Homogenous Tile 600x600 dinding trap tangga


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.7000 85,000.00 59,500.00
Tukang Batu L.02 OH 0.3500 90,000.00 31,500.00
Kepala Tukang L.03 OH 0.0350 95,000.00 3,325.00
Mandor L.04 OH 0.0350 100,000.00 3,500.00
Pemotongan L.04 ls 1.0000 -
JUMLAH TENAGA KERJA 97,825.00
B. BAHAN
Homogeneous Tile 600x600 Cementum matt beige, Merk : Niro granit m2 1.0000 175,000.00 175,000.00
Drymix tile adhesive (40kg) zak 0.2000 55,000.00 11,000.00
Semen Warna kg 0.5000 7,500.00 3,750.00
JUMLAH HARGA BAHAN 189,750.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 287,575.00


E. Overhead & Profit 10% 28,757.50
F. Harga Satuan Pekerjaan (D+E) 316,332.50

A.4.4.3.20. Pemasangan 1 m1 Plint Lantai


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0900 85,000.00 7,650.00
Tukang Batu L.02 OH 0.0900 90,000.00 8,100.00
Kepala Tukang L.03 OH 0.0090 95,000.00 855.00
Mandor L.04 OH 0.0050 100,000.00 500.00
JUMLAH TENAGA KERJA 17,105.00
B. BAHAN
Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 0.1050 80,000.00 8,400.00
Semen Portland kg 1.1400 1,100.00 1,254.00
Semen Warna kg 0.0500 7,500.00 375.00
Pasir Pasang m3 0.0030 185,000.00 555.00
JUMLAH HARGA BAHAN 10,584.00
C. PERALATAN

JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 27,689.00


E. Overhead & Profit 10% 2,768.90
F. Harga Satuan Pekerjaan (D+E) 30,457.90

Pengecatan 1 m2 tembok baru (1 lapis cat dasar, 2 lapis cat penutup) interior
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
pekerja L.01 OH 0.0200 85,000.00 1,700.00
tukang cat L.02 OH 0.0630 90,000.00 5,670.00
kepala tukang L.03 OH 0.0063 95,000.00 598.50
Mandor L.04 OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 8,268.50
B. BAHAN
Cat dasar Jotun Base Coat Sealer ltr 0.1000 35,000.00 3,500.00
Cat tembok interior, setara Jotun Majestic True Beauty SHEEN ltr 0.2600 35,000.00 9,100.00
JUMLAH HARGA BAHAN 12,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 20,868.50


E. Overhead & Profit 10% 2,086.85
F. Harga Satuan Pekerjaan (D+E) 22,955.35

1 m2 Pengecatan plafond
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
pekerja L.01 OH 0.0200 85,000.00 1,700.00
tukang cat L.02 OH 0.0630 90,000.00 5,670.00
kepala tukang L.03 OH 0.0063 95,000.00 598.50
Mandor L.04 OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 8,268.50
B. BAHAN
Cat plafond, Merk : Vinilex ltr 0.2500 35,000.00 8,750.00
Rol cat bh 0.0100 15,000.00 150.00
Steger werk lot 0.0250 8,900.00 222.50
JUMLAH HARGA BAHAN 9,122.50
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 17,391.00


E. Overhead & Profit 10% 1,739.10
F. Harga Satuan Pekerjaan (D+E) 19,130.10

Pengecatan 1 m2 tembok baru (1 lapis cat dasar, 2 lapis cat penutup) eksterior
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
pekerja L.01 OH 0.0200 85,000.00 1,700.00
tukang cat L.02 OH 0.0630 90,000.00 5,670.00
kepala tukang L.03 OH 0.0063 95,000.00 598.50
Mandor L.04 OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 8,268.50
B. BAHAN
Cat dasar Jotun Jotashield Primer 7 ltr 0.1000 35,000.00 3,500.00
Cat tembok eksterior, setara Jotun Jotashield Antifade ltr 0.2600 35,000.00 9,100.00
JUMLAH HARGA BAHAN 12,600.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 20,868.50


E. Overhead & Profit 10% 2,086.85
F. Harga Satuan Pekerjaan (D+E) 22,955.35

1 m2 Pengecatan kayu Polyurethane acrylic


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2600 85,000.00 22,100.00
Tukang cat L.02 OH 0.4000 90,000.00 36,000.00
Kepala Tukang L.03 OH 0.0400 95,000.00 3,800.00
Mandor L.04 OH 0.0200 100,000.00 2,000.00
JUMLAH TENAGA KERJA 63,900.00
B. BAHAN
(Untuk kayu solid dengan memakai dempul dan anti getah)
Wood filler + wood stain kg 0.2000 45,000.00 9,000.00
Meiji gum sealer kg 0.1000 25,000.00 2,500.00
Cat Petalac-2K Super Sanding sealer ltr 0.2500 45,000.00 11,250.00
Thinner Super Sanding Sealer ltr 0.1000 35,000.00 3,500.00
Cat Petalac-2K Clear Matt MV-3 ltr 0.2500 35,000.00 8,750.00
Thinner Slow Dry ltr 0.1000 45,000.00 4,500.00
Ampelas kayu lbr 0.1000 3,500.00 350.00
JUMLAH HARGA BAHAN 39,850.00
C. PERALATAN
Alat Bantu ls 0.0500 10,000.00 500.00
JUMLAH HARGA PERALATAN 500.00

D. Jumlah (A+B+C) 104,250.00


E. Overhead & Profit 10% 10,425.00
F. Harga Satuan Pekerjaan (D+E) 114,675.00

1 m2 Pengecatan Besi cat Duco


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1300 85,000.00 11,050.00
Tukang cat L.02 OH 0.2000 90,000.00 18,000.00
Kepala Tukang L.03 OH 0.0200 95,000.00 1,900.00
Mandor L.04 OH 0.0100 100,000.00 1,000.00
JUMLAH TENAGA KERJA 31,950.00
B. BAHAN
Cat duco polyurethane clear matt MV-3, Merk : Petalac 2K ltr 0.1670 50,000.00 8,350.00
Cat epoxy undercoat, Merk : Petalac ltr 0.2000 35,000.00 7,000.00
Cat polyster putty, Merk : Petalac ltr 0.1000 35,000.00 3,500.00
Thinner P.U. ltr 0.1000 19,000.00 1,900.00
Thinner slow dry ltr 0.1000 45,000.00 4,500.00
Ampelas besi lbr 0.4000 3,500.00 1,400.00
Kwas 3" bh 0.0500 15,000.00 750.00
JUMLAH HARGA BAHAN 27,400.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 59,350.00


E. Overhead & Profit 10% 5,935.00
F. Harga Satuan Pekerjaan (D+E) 65,285.00

1 m2 Pengecatan Zinchromate
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0200 85,000.00 1,700.00
Tukang cat L.02 OH 0.0630 90,000.00 5,670.00
Kepala Tukang L.03 OH 0.0100 95,000.00 950.00
Mandor L.04 OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 8,620.00
B. BAHAN
Cat zinchromat, setara Meiji kg 0.2200 35,000.00 7,700.00
Ampelas besi lbr 0.4400 3,500.00 1,540.00
Thinner ltr 0.1650 25,000.00 4,125.00
Kwas cat rata-rata bh 0.0550 5,000.00 275.00
JUMLAH HARGA BAHAN 13,640.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 22,260.00


E. Overhead & Profit 10% 2,226.00
F. Harga Satuan Pekerjaan (D+E) 24,486.00
1 m2 Pengecatan Anti Karat Epoxy
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2200 85,000.00 18,700.00
Tukang cat L.02 OH 0.3300 90,000.00 29,700.00
Kepala Tukang L.03 OH 0.0330 95,000.00 3,135.00
Mandor L.04 OH 0.0110 100,000.00 1,100.00
JUMLAH TENAGA KERJA 52,635.00
B. BAHAN
Cat epoxy undercoat, Merk : Petalac ltr 0.2200 35,000.00 7,700.00
Ampelas besi lbr 0.4400 3,500.00 1,540.00
Thinner ltr 0.1650 25,000.00 4,125.00
Kwas cat rata-rata bh 0.0550 5,000.00 275.00
JUMLAH HARGA BAHAN 13,640.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 66,275.00


E. Overhead & Profit 10% 6,627.50
F. Harga Satuan Pekerjaan (D+E) 72,902.50

1 kg Waterproofing formdex WP system


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Upah pasang ls 1.0000 2,625.00 2,625.00
JUMLAH TENAGA KERJA 2,625.00
B. BAHAN
Waterproofing formdex WP system, Merk : Sika, Fosroc kg 1.0000 17,500.00 17,500.00
JUMLAH HARGA BAHAN 17,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 20,125.00


E. Overhead & Profit 10% 2,012.50
F. Harga Satuan Pekerjaan (D+E) 22,137.50

1 m2 Waterproofing Formdex Uniflex Cementitious Membrance


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.0000 25,000.00 25,000.00
JUMLAH TENAGA KERJA 25,000.00
B. BAHAN
Waterproofing Formdex Uniflex Cementitious Membrance, m2 1.0000 8,500.00 8,500.00
Merk : Sika, Fosroc
- Coating membrance (3x)
JUMLAH HARGA BAHAN 8,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 33,500.00


E. Overhead & Profit 10% 3,350.00
F. Harga Satuan Pekerjaan (D+E) 36,850.00

1 m2 Waterproofing DUO Composite membrane, ex. De Boer


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Upah pasang ls 1.0000 25,000.00 25,000.00
JUMLAH TENAGA KERJA 25,000.00
B. BAHAN
Duo Composite Membrane roll 0.5000 350,000.00 175,000.00
C Profile pcs 4.0000 2,500.00 10,000.00
Fastener and Mechano Plate pcs 3.0000 7,500.00 22,500.00
Duo Kit Sealant tube 0.3333 75,000.00 25,000.00
Duo Primer pile 0.0185 125,000.00 2,314.81
JUMLAH HARGA BAHAN 234,814.81
C. PERALATAN
Material dan Alat Bantu ls 1.0000 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 269,814.81


E. Overhead & Profit 10% 26,981.48
F. Harga Satuan Pekerjaan (D+E) 296,796.30

1 m2 Rumput gajah mini


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Mandor L.04 OH 0.0013 100,000.00 125.00
Supir OH 0.0050 100,000.00 500.00
Tukang Gali OH 0.0050 90,000.00 450.00
Tukang Tanam OH 0.0050 90,000.00 450.00
Tukang Penyiraman OH 0.0050 90,000.00 450.00
Pekerja L.01 OH 0.0050 85,000.00 425.00
JUMLAH TENAGA KERJA 2,400.00
B. BAHAN
Bensin/Solar ltr 0.0250 8,500.00 212.50
Oli ltr 0.0020 6,500.00 13.00
Tanah Top Soil m3 0.0500 25,000.00 1,250.00
Pupuk Kandang (1 karung : 40 Kg) krg 0.0100 5,000.00 50.00
Furadan kg 0.0100 35,000.00 350.00
Atonik/Rotone btl 0.0020 25,000.00 50.00
Pupuk Kompos (5kg) kntg 0.0400 15,000.00 600.00
Rumput Gajah Mini m2 1.1000 25,000.00 27,500.00
JUMLAH HARGA BAHAN 30,025.50
C. PERALATAN
Mobil Operasional hari 0.0005 75,000.00 37.50
Mobil Tanki air 5000 lt hari 0.0020 125,000.00 250.00
Truk engkel hari 0.0005 75,000.00 37.50
Linggis/Blencong hari 0.0020 1,000.00 2.00
Cangkul hari 0.0020 1,000.00 2.00
pH Meter hari 0.0020 2,500.00 5.00
Karung Plastik buah 0.0050 100.00 0.50
Selang Penyiraman jam 0.0050 500.00 2.50
Biaya Lain-Lain ls 1.0000 1,638.13 1,638.13
JUMLAH HARGA PERALATAN 1,975.13

D. Jumlah (A+B+C) 34,400.63


E. Overhead & Profit 10% 3,440.06
F. Harga Satuan Pekerjaan (D+E) 37,840.69

A.2.3.1.10. Pemadatan Tanah 1 m3 tanah (Per 20cm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.5000 85,000.00 42,500.00
Mandor L.04 OH 0.0500 100,000.00 5,000.00
JUMLAH TENAGA KERJA 47,500.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 47,500.00


E. Overhead & Profit 10% 4,750.00
F. Harga Satuan Pekerjaan (D+E) 52,250.00

A.2.3.1.14. Pengurugan 1 m3 Sirtu Padat


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2500 85,000.00 21,250.00
Mandor L.04 OH 0.0250 100,000.00 2,500.00
JUMLAH TENAGA KERJA 23,750.00
B. BAHAN
Sirtu kg 1.2000 85.00 102.00
JUMLAH HARGA BAHAN 102.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 23,852.00


E. Overhead & Profit 10% 2,385.20
F. Harga Satuan Pekerjaan (D+E) 26,237.20

1 m3 Amparan 2/3
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3210 85,000.00 27,285.00
Tukang Batu L.02 OH 0.1800 90,000.00 16,200.00
Kepala Tukang L.03 OH 0.0150 95,000.00 1,425.00
Mandor L.04 OH 0.0080 100,000.00 800.00
JUMLAH TENAGA KERJA 45,710.00
B. BAHAN
Amparan batu pecah mesin 5-7 m3 1.1000 85,000.00 93,500.00
JUMLAH HARGA BAHAN 93,500.00
C. PERALATAN
Peralatan Utama dan alat bantu jam 0.0200 125,000.00 2,500.00
JUMLAH HARGA PERALATAN 2,500.00

D. Jumlah (A+B+C) 141,710.00


E. Overhead & Profit 10% 14,171.00
F. Harga Satuan Pekerjaan (D+E) 155,881.00

1 m3 Lapisan Pengisi 1/2


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3210 85,000.00 27,285.00
Tukang Batu L.02 OH 0.1800 90,000.00 16,200.00
Kepala Tukang L.03 OH 0.0150 95,000.00 1,425.00
Mandor L.04 OH 0.0080 100,000.00 800.00
JUMLAH TENAGA KERJA 45,710.00
B. BAHAN
Amparan batu pecah mesin 1-2 m3 1.1000 85,000.00 93,500.00
JUMLAH HARGA BAHAN 93,500.00
C. PERALATAN
Peralatan Utama dan alat bantu jam 0.0200 15,000.00 300.00
JUMLAH HARGA PERALATAN 300.00

D. Jumlah (A+B+C) 139,510.00


E. Overhead & Profit 10% 13,951.00
F. Harga Satuan Pekerjaan (D+E) 153,461.00

1 m2 Aspal Hotmix
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.0000 15,000.00 15,000.00
JUMLAH TENAGA KERJA 15,000.00
B. BAHAN
Aspal Hotmix kg 77.0000 1,200.00 92,400.00
Pasir Pasang m3 0.0275 185,000.00 5,087.50
JUMLAH HARGA BAHAN 97,487.50
C. PERALATAN
Material dan Alat Bantu ls 1.0000 1,000.00 1,000.00
JUMLAH HARGA PERALATAN 1,000.00

D. Jumlah (A+B+C) 113,487.50


E. Overhead & Profit 10% 11,348.75
F. Harga Satuan Pekerjaan (D+E) 124,836.25

A.4.4.3.65. Pemasangan 1 m2 Paving Block Natural tebal 8cm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.4000 85,000.00 34,000.00
Tukang Batu L.02 OH 0.4000 90,000.00 36,000.00
Kepala Tukang L.03 OH 0.0500 95,000.00 4,750.00
Mandor L.04 OH 0.0013 100,000.00 130.00
JUMLAH TENAGA KERJA 74,880.00
B. BAHAN
Paving Block 8cm Natural bh 25.0000 3,500.00 87,500.00
Pasir Beton m3 0.0500 250,000.00 12,500.00
JUMLAH HARGA BAHAN 100,000.00

C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 174,880.00


E. Overhead & Profit 10% 17,488.00
F. Harga Satuan Pekerjaan (D+E) 192,368.00

Pemasangan 1 m1 U-ditch
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.0000 25,000.00 25,000.00
JUMLAH TENAGA KERJA 25,000.00
B. BAHAN
U-ditch 300x400 bh 1.7000 110,000.00 187,000.00
JUMLAH HARGA BAHAN 187,000.00
C. PERALATAN
Material dan Alat Bantu ls 1.0000 15,000.00 15,000.00
JUMLAH HARGA PERALATAN 15,000.00

D. Jumlah (A+B+C) 227,000.00


E. Overhead & Profit 10% 22,700.00
F. Harga Satuan Pekerjaan (D+E) 249,700.00

Pemasangan 1 m1 Cover U-ditch


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.0000 25,000.00 25,000.00
JUMLAH TENAGA KERJA 25,000.00
B. BAHAN
Cover U-ditch 300 bh 1.7000 110,000.00 187,000.00
JUMLAH HARGA BAHAN 187,000.00
C. PERALATAN
Material dan Alat Bantu ls 1.0000 15,000.00 15,000.00
JUMLAH HARGA PERALATAN 15,000.00

D. Jumlah (A+B+C) 227,000.00


E. Overhead & Profit 10% 22,700.00
F. Harga Satuan Pekerjaan (D+E) 249,700.00

1 m2 Aluminium Composite Panel


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Upah Pasang ls 1.0000 25,000.00 25,000.00
JUMLAH TENAGA KERJA 25,000.00
B. BAHAN
Alumunium composite panel T.4mm, Anti UV,Merk : Maco m2 1.0500 125,000.00 131,250.00
Rangka metal square zincalume, 40x40 m2 1.0500 125,000.00 131,250.00
Sekrup kg 1.0500 150.00 157.50
Sealant untuk ACP m1 1.0500 1,000.00 1,050.00
JUMLAH HARGA BAHAN 263,707.50
C. PERALATAN
Peralatan dan material bantu ls 0.0500 10,000.00 500.00
JUMLAH HARGA PERALATAN 500.00

D. Jumlah (A+B+C) 289,207.50


E. Overhead & Profit 10% 28,920.75
F. Harga Satuan Pekerjaan (D+E) 318,128.25

A.4.4.1.22. Pemasangan 1 m2 Dinding Terawang (Rooster) 12x11x24 Campuran 1SP:3PP


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 85,000.00 25,500.00
Tukang Batu L.02 OH 0.1000 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.0100 95,000.00 950.00
Mandor L.04 OH 0.0150 100,000.00 1,500.00
JUMLAH TENAGA KERJA 36,950.00
B. BAHAN
Rooster Terakota uk. 200x200 bh 25.0000 6,500.00 162,500.00
Semen Portland kg 11.0000 1,100.00 12,100.00
Pasir Pasang m3 0.0350 185,000.00 6,475.00
JUMLAH HARGA BAHAN 181,075.00
C. PERALATAN
JUMLAH HARGA PERALATAN
D. Jumlah (A+B+C) 218,025.00
E. Overhead & Profit 10% 21,802.50
F. Harga Satuan Pekerjaan (D+E) 239,827.50

Pemasangan 1 m2 Kaca
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.0000 2,418.70 2,418.70
JUMLAH TENAGA KERJA 2,418.70
B. BAHAN
flexible polycarbonate 2mm ultraviolet lbr 0.3359 72,000.00 24,187.05
JUMLAH HARGA BAHAN 24,187.05
C. PERALATAN
Material dan Alat Bantu ls 1.0000 1,209.35 1,209.35
JUMLAH HARGA PERALATAN 1,209.35

D. Jumlah (A+B+C) 27,815.10


E. Overhead & Profit 10% 2,781.51
F. Harga Satuan Pekerjaan (D+E) 30,596.61

Pemasangan 1 m2 Kaca
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
NO URAIAN KODE SATUAN KOEFISIEN
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.0000 15,000.00 15,000.00
JUMLAH TENAGA KERJA 15,000.00
B. BAHAN
Kaca tempered laminated T.10mm, Merk : Asahimas m2 1.0500 175,000.00 183,750.00
(5mm polos tempered+PVB clear+5mm polos biasa)
JUMLAH HARGA BAHAN 183,750.00
C. PERALATAN
Material dan Alat Bantu ls 1.0000 5,000.00 5,000.00
JUMLAH HARGA PERALATAN 5,000.00

D. Jumlah (A+B+C) 203,750.00


E. Overhead & Profit 10% 20,375.00
F. Harga Satuan Pekerjaan (D+E) 224,125.00

Pemasangan 1 bh Secondary Skin


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.0000 25,000.00 25,000.00
JUMLAH TENAGA KERJA 25,000.00
B. BAHAN
Rangka metal square Galvanized, 40x40 m1 10.1640 135,000.00 1,372,140.00
Pengecatan Besi Anti Karat m2 1.6454 22,260.00 36,627.49
Plat Besi kg 0.4522 18,270.00 8,260.96
Baut bh 8.0000 -
GRC Cladding m2 0.7225 -
JUMLAH HARGA BAHAN 1,417,028.46
C. PERALATAN
Material dan Alat Bantu ls 1.0000 15,000.00 15,000.00
JUMLAH HARGA PERALATAN 15,000.00

D. Jumlah (A+B+C) 1,457,028.46


E. Overhead & Profit 10% 145,702.85
F. Harga Satuan Pekerjaan (D+E) 1,602,731.30

1 unit Closet Duduk


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0.0200 25,000.00 500.00
JUMLAH TENAGA KERJA 500.00
B. BAHAN
Closet Duduk tipe CW660NJ/SW660J, Merk : Toto unit 1.0100 1,800,000.00 1,818,000.00
JUMLAH HARGA BAHAN 1,818,000.00
C. PERALATAN
Material & alat Bantu ls 0.0200 15,000.00 300.00
JUMLAH HARGA PERALATAN 300.00

D. Jumlah (A+B+C) 1,818,800.00


E. Overhead & Profit 10% 181,880.00
F. Harga Satuan Pekerjaan (D+E) 2,000,680.00
1 unit Floor Drain
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0.0200 10,000.00 200.00
JUMLAH TENAGA KERJA 200.00
B. BAHAN
Floordrain tipe TX1C, Merk : Toto unit 1.0100 45,000.00 45,450.00
JUMLAH HARGA BAHAN 45,450.00
C. PERALATAN
Material & alat Bantu ls 0.0200 1,500.00 30.00
JUMLAH HARGA PERALATAN 30.00

D. Jumlah (A+B+C) 45,680.00


E. Overhead & Profit 10% 4,568.00
F. Harga Satuan Pekerjaan (D+E) 50,248.00

1 unit Jet Washer


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0.0200 25,000.00 500.00
JUMLAH TENAGA KERJA 500.00
B. BAHAN
Jet Washer tipe THX20NB, Merk : Toto unit 1.0100 125,000.00 126,250.00
JUMLAH HARGA BAHAN 126,250.00
C. PERALATAN
Material & alat Bantu ls 0.0200 10,000.00 200.00
JUMLAH HARGA PERALATAN 200.00

D. Jumlah (A+B+C) 126,950.00


E. Overhead & Profit 10% 12,695.00
F. Harga Satuan Pekerjaan (D+E) 139,645.00

1 unit Urinoir
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0.0200 25,000.00 500.00
JUMLAH TENAGA KERJA 500.00
B. BAHAN
Urinoir tipe U57, Merk : Toto unit 1.0100 250,000.00 252,500.00
JUMLAH HARGA BAHAN 252,500.00
C. PERALATAN
Material & alat Bantu ls 0.0200 10,000.00 200.00
JUMLAH HARGA PERALATAN 200.00

D. Jumlah (A+B+C) 253,200.00


E. Overhead & Profit 10% 25,320.00
F. Harga Satuan Pekerjaan (D+E) 278,520.00

1 unit Divider Urinoir


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0.0200 25,000.00 500.00
JUMLAH TENAGA KERJA 500.00
B. BAHAN
Divider Urinoir tipe A100, Merk : Toto unit 1.0100 950,000.00 959,500.00
JUMLAH HARGA BAHAN 959,500.00
C. PERALATAN
Material & alat Bantu ls 0.0200 10,000.00 200.00
JUMLAH HARGA PERALATAN 200.00

D. Jumlah (A+B+C) 960,200.00


E. Overhead & Profit 10% 96,020.00
F. Harga Satuan Pekerjaan (D+E) 1,056,220.00

1 unit Wastafel
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0.0200 25,000.00 500.00
JUMLAH TENAGA KERJA 500.00
B. BAHAN
Washtafel tipe LW813CJ, Merk : Toto unit 1.0100 1,250,000.00 1,262,500.00
Kran washtafel Tipe TX109LD, Merk : Toto unit 1.0100 75,000.00 75,750.00
JUMLAH HARGA BAHAN 1,338,250.00
C. PERALATAN
Material & alat Bantu ls 0.0200 10,000.00 200.00
JUMLAH HARGA PERALATAN 200.00

D. Jumlah (A+B+C) 1,338,950.00


E. Overhead & Profit 10% 133,895.00
F. Harga Satuan Pekerjaan (D+E) 1,472,845.00

1 m2 Kaca Cermin
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0.0200 25,000.00 500.00
JUMLAH TENAGA KERJA 500.00
B. BAHAN
Kaca Cermin dinding T.6mm, Merk : Asahimas m2 1.0100 85,000.00 85,850.00
JUMLAH HARGA BAHAN 85,850.00
C. PERALATAN
Material & alat Bantu ls 0.0200 10,000.00 200.00
JUMLAH HARGA PERALATAN 200.00

D. Jumlah (A+B+C) 86,550.00


E. Overhead & Profit 10% 8,655.00
F. Harga Satuan Pekerjaan (D+E) 95,205.00

1 unit Handrail
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
NO URAIAN KODE SATUAN KOEFISIEN
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0.0200 25,000.00 500.00
JUMLAH TENAGA KERJA 500.00
B. BAHAN
Handrail tipe T113B6, setara Toto unit 1.0000 120,000.00 120,000.00
JUMLAH HARGA BAHAN 120,000.00
C. PERALATAN
Material & alat Bantu ls 0.0200 10,000.00 200.00
JUMLAH HARGA PERALATAN 200.00

D. Jumlah (A+B+C) 120,700.00


E. Overhead & Profit 10% 12,070.00
F. Harga Satuan Pekerjaan (D+E) 132,770.00

1 unit Partisi dan pintu dinding toilet


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 1.0000 3,900.00 3,900.00
JUMLAH TENAGA KERJA 3,900.00
B. BAHAN
cubical PVC, tipe Compact - Phenolic 12mm, Ex. Wimas m1 1.3200 12,500.00 16,500.00
Accessories Pintu Toilet, Ex. Wimas set 1.0000 22,500.00 22,500.00
JUMLAH HARGA BAHAN 39,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 42,900.00


E. Overhead & Profit 10% 4,290.00
F. Harga Satuan Pekerjaan (D+E) 47,190.00

1 m1 Railling tangga
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0.1000 25,000.00 2,500.00
JUMLAH TENAGA KERJA 2,500.00
B. BAHAN
Kayu Solid 20x80 m3 0.0017 6,619,500.00 11,120.76
Metal square hollow 40/40, tebal 1,1mm m1 4.2000 33,000.00 138,600.00
Plat Besi t.8mm kg 1.2560 18,270.00 22,947.12
Besi Nako 8mm kg 2.0221 10,000.00 20,220.60
Pengecatan Kayu m2 0.2100 104,250.00 21,892.50
Pengecatan Besi m2 1.7018 59,350.00 101,003.25
JUMLAH HARGA BAHAN 315,784.23
C. PERALATAN
Material & alat Bantu ls 0.0500 10,000.00 500.00
JUMLAH HARGA PERALATAN 500.00

D. Jumlah (A+B+C) 318,784.23


E. Overhead & Profit 10% 31,878.42
F. Harga Satuan Pekerjaan (D+E) 350,662.66
1 m1 Railling tangga Darurat
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0.0200 25,000.00 500.00
JUMLAH TENAGA KERJA 500.00
B. BAHAN
Kayu Solid 20x80 m3 0.0017 6,619,500.00 11,120.76
Metal square hollow 40/40, tebal 1,1mm m1 3.0000 33,000.00 99,000.00
Pengecatan Kayu m2 0.2100 104,250.00 21,892.50
Pengecatan Besi m2 0.4800 59,350.00 28,488.00
JUMLAH HARGA BAHAN 160,501.26
C. PERALATAN
Material & alat Bantu ls 0.0200 10,000.00 200.00
JUMLAH HARGA PERALATAN 200.00

D. Jumlah (A+B+C) 161,201.26


E. Overhead & Profit 10% 16,120.13
F. Harga Satuan Pekerjaan (D+E) 177,321.39

A.4.5.2.30. Pemasangan 1 m2 Genteng Keramik


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2000 85,000.00 17,000.00
Tukang Kayu L.02 OH 0.1000 90,000.00 9,000.00
Kepala Tukang L.03 OH 0.0100 95,000.00 950.00
Mandor L.04 OH 0.0100 100,000.00 1,000.00
JUMLAH TENAGA KERJA 27,950.00
B. BAHAN
Genteng Keramik bh 12.0000 9,500.00 114,000.00
Paku Biasa 2" - 3" kg 0.0300 18,000.00 540.00
JUMLAH HARGA BAHAN 114,540.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 142,490.00


E. Overhead & Profit 10% 14,249.00
F. Harga Satuan Pekerjaan (D+E) 156,739.00

1 m1 Listplank
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0.5000 25,000.00 12,500.00
JUMLAH TENAGA KERJA 12,500.00
B. BAHAN
Kalsiplank 8mm, uk. 0,2x3m lbr 0.3333 43,000.00 14,333.33
Metal square hollow 30/60, tebal 1,1mm m1 1.0000 28,666.67 28,666.67
Sekrup bh 8.0000 -
JUMLAH HARGA BAHAN 43,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN
D. Jumlah (A+B+C) 55,500.00
E. Overhead & Profit 10% 5,550.00
F. Harga Satuan Pekerjaan (D+E) 61,050.00

1 m1 Nok Atap
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 0.1500 25,000.00 3,750.00
JUMLAH TENAGA KERJA 3,750.00
B. BAHAN
Nok Atap m1 1.0000 12,000.00 12,000.00
JUMLAH HARGA BAHAN 12,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 15,750.00


E. Overhead & Profit 10% 1,575.00
F. Harga Satuan Pekerjaan (D+E) 17,325.00

Pemasangan 1 bh Guiding Block tipe line


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.0000 1,581.25 1,581.25
JUMLAH TENAGA KERJA 1,581.25
B. BAHAN
Tactile tipe line Aluminium bh 1.0000 5,500.00 5,500.00
JUMLAH HARGA BAHAN 5,500.00
C. PERALATAN
Material dan Alat Bantu ls 1.0000 825.00 825.00
JUMLAH HARGA PERALATAN 825.00

D. Jumlah (A+B+C) 7,906.25


E. Overhead & Profit 10% 790.63
F. Harga Satuan Pekerjaan (D+E) 8,696.88

Pemasangan 1 bh Guiding Block tipe dot


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.0000 1,293.75 1,293.75
JUMLAH TENAGA KERJA 1,293.75
B. BAHAN
Tactile tipe dot Aluminium bh 1.0000 4,500.00 4,500.00
JUMLAH HARGA BAHAN 4,500.00
C. PERALATAN
Material dan Alat Bantu ls 1.0000 675.00 675.00
JUMLAH HARGA PERALATAN 675.00

D. Jumlah (A+B+C) 6,468.75


E. Overhead & Profit 10% 646.88
F. Harga Satuan Pekerjaan (D+E) 7,115.63

1 bh Logo UPI
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 1.0000 25,000.00 25,000.00
JUMLAH TENAGA KERJA 25,000.00
B. BAHAN
Stainless Steel cm2 84,100.0000 150.00 12,615,000.00
Cutting cm2 65,465.0000 150.00 9,819,750.00
Pengecatan Duco m2 8.4100 25,000.00 210,250.00
JUMLAH HARGA BAHAN 22,645,000.00
C. PERALATAN
Material dan Alat Bantu ls 1.0000 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 22,680,000.00


E. Overhead & Profit 10% 2,268,000.00
F. Harga Satuan Pekerjaan (D+E) 24,948,000.00

1 bh Logo UPI untuk backdrop


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 1.0000 25,000.00 25,000.00
JUMLAH TENAGA KERJA 25,000.00
B. BAHAN
Stainless Steel cm2 1,600.0000 150.00 240,000.00
Cutting cm2 1,117.0000 150.00 167,550.00
Pengecatan Duco m2 0.1600 59,350.00 9,496.00
JUMLAH HARGA BAHAN 417,046.00
C. PERALATAN
Material dan Alat Bantu ls 1.0000 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 452,046.00


E. Overhead & Profit 10% 45,204.60
F. Harga Satuan Pekerjaan (D+E) 497,250.60

1 bh Huruf UPI
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 1.0000 25,000.00 25,000.00
JUMLAH TENAGA KERJA 25,000.00
B. BAHAN
Stainless Steel cm2 1,184.0000 150.00 177,600.00
Cutting cm2 1,720.0000 150.00 258,000.00
Pengecatan Duco m2 0.2069 25,000.00 5,171.40
JUMLAH HARGA BAHAN 440,771.40
C. PERALATAN
Material dan Alat Bantu ls 1.0000 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 475,771.40


E. Overhead & Profit 10% 47,577.14
F. Harga Satuan Pekerjaan (D+E) 523,348.54

1 bh Huruf UPI untuk backdrop t.11 cm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 1.0000 1,712.64 1,712.64
JUMLAH TENAGA KERJA 1,712.64
B. BAHAN
Stainless Steel cm2 55.0000 150.00 8,250.00
Cutting cm2 57.0000 150.00 8,550.00
Pengecatan Duco m2 0.0055 59,350.00 326.43
JUMLAH HARGA BAHAN 17,126.43
C. PERALATAN
Material dan Alat Bantu ls 1.0000 856.32 856.32
JUMLAH HARGA PERALATAN 856.32

D. Jumlah (A+B+C) 19,695.39


E. Overhead & Profit 10% 1,969.54
F. Harga Satuan Pekerjaan (D+E) 21,664.93

1 bh Huruf UPI untuk backdrop t.15 cm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 1.0000 6,743.90 6,743.90
JUMLAH TENAGA KERJA 6,743.90
B. BAHAN
Stainless Steel cm2 154.0000 150.00 23,100.00
Cutting cm2 289.5000 150.00 43,425.00
Pengecatan Duco m2 0.0154 59,350.00 913.99
JUMLAH HARGA BAHAN 67,438.99
C. PERALATAN
Material dan Alat Bantu ls 1.0000 3,371.95 3,371.95
JUMLAH HARGA PERALATAN 3,371.95

D. Jumlah (A+B+C) 77,554.84


E. Overhead & Profit 10% 7,755.48
F. Harga Satuan Pekerjaan (D+E) 85,310.32

1 unit Backdrop
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos pasang ls 1.00 910,994.87 910,994.87
JUMLAH TENAGA KERJA 910,994.87
B. BAHAN
Metal square hollow 30/60, tebal 1,1mm m1 98.30 28,666.67 2,817,933.33
Multiplek 9mm lbr 13.00 110,000.00 1,430,000.00
HPL 0.8mm ex Taco lbr 13.00 160,000.00 2,080,000.00
Lem Kayu & HPL kg 3.50 25,000.00 87,500.00
Pengecatan Zinchromate m2 15.73 22,260.00 350,105.28
GRC Cladding m2 3.3750 15,000.00 50,625.00
Logo UPI unit 1.00 452,046.00 452,046.00
Huruf t.11cm bh 30.00 19,695.39 590,861.66
Huruf t.15cm bh 16.00 77,554.84 1,240,877.42
JUMLAH HARGA BAHAN 9,099,948.69
C. PERALATAN
Material & alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 10,020,943.56


E. Overhead & Profit 10% 1,002,094.36
F. Harga Satuan Pekerjaan (D+E) 11,023,037.92
ANALISA HARGA SATUAN PEKERJAAN KUSEN

A.4.6.1.1. Pembuatan dan Pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 7.00 85,000.00 595,000.00
Tukang Kayu L.02 OH 21.00 90,000.00 1,890,000.00
Kepala Tukang L.03 OH 2.10 95,000.00 199,500.00
Mandor L.04 OH 0.35 100,000.00 35,000.00
JUMLAH TENAGA KERJA 2,719,500.00
B. BAHAN
Balok Kayu Samarinda Oven m3 1.10 3,500,000.00 3,850,000.00
Paku 5-10cm kg 1.25 18,000.00 22,500.00
Lem Kayu kg 1.10 25,000.00 27,500.00
JUMLAH HARGA BAHAN 3,900,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 6,619,500.00


E. Overhead & Profit 10% 661,950.00
F. Harga Satuan Pekerjaan (D+E) 7,281,450.00

1 m2 Daun Pintu Double Multiplek T.18mm, + Megateak 3mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.30 85,000.00 25,500.00
Tukang kayu L.02 OH 1.50 90,000.00 135,000.00
Kepala tukang L.03 OH 0.20 95,000.00 19,000.00
Mandor L.04 OH 0.02 100,000.00 2,000.00
JUMLAH TENAGA KERJA 181,500.00
B. BAHAN
Kayu papan kamper samarinda oven m3 0.02 3,250,000.00 48,750.00
Multiplek 18mm lbr 0.69 220,000.00 152,777.78
Megateak 3mm lbr 1.00 65,000.00 65,000.00
Lem putih (Fox) kg 0.01 35,000.00 175.00
Paku triplek kg 0.20 22,000.00 4,400.00
Pengecatan polyurethane acrylic m2 2.00 104,250.00 208,500.00
JUMLAH HARGA BAHAN 479,602.78
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 661,102.78


E. Overhead & Profit 10% 66,110.28
F. Harga Satuan Pekerjaan (D+E) 727,213.06

1 unit Pintu tipe P1


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 5.20 95,000.00 494,000.00
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo m2 1.51 661,102.78 994,959.68
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 1.00 275,000.00 275,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 1.50 85,000.00 127,500.00
Escutcheon Dekkson ESCN DKS 855SSS unit 1.00 175,000.00 175,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 1.00 75,000.00 75,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 1.00 125,000.00 125,000.00
Door Closer Dekkson DCL 300 HO unit 1.00 75,000.00 75,000.00
JUMLAH HARGA BAHAN 2,341,459.68
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 2,426,459.68


E. Overhead & Profit 10% 242,645.97
F. Harga Satuan Pekerjaan (D+E) 2,669,105.65

1 unit Pintu tipe P2


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 6.90 95,000.00 655,500.00
Sudah termasuk metal close untuk engsel
Metal square hollow 20/20, tebal 0,9mm m1 27.50 6,666.67 183,333.33
Metal square hollow 40/40, tebal 1,1mm m1 6.80 33,000.00 224,400.00
Plat Besi kg 1.35 18,270.00 24,739.86
Pengecatan Duco m2 3.37 59,350.00 200,261.74
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 1.00 275,000.00 275,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 1.50 85,000.00 127,500.00
Escutcheon Dekkson ESCN DKS 855SSS unit 1.00 175,000.00 175,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 1.00 75,000.00 75,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 1.00 125,000.00 125,000.00
Door Closer Dekkson DCL 300 HO unit 1.00 75,000.00 75,000.00
JUMLAH HARGA BAHAN 2,140,734.93
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 2,225,734.93


E. Overhead & Profit 10% 222,573.49
F. Harga Satuan Pekerjaan (D+E) 2,448,308.43

1 unit Pintu tipe P2'


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 6.60 95,000.00 627,000.00
Sudah termasuk metal close untuk engsel
Metal square hollow 20/20, tebal 0,9mm m1 21.28 6,666.67 141,866.67
Metal square hollow 40/40, tebal 1,1mm m1 6.20 33,000.00 204,600.00
Plat Besi kg 1.35 18,270.00 24,739.86
Pengecatan Duco m2 2.78 59,350.00 165,031.58
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 1.00 275,000.00 275,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 1.50 85,000.00 127,500.00
Escutcheon Dekkson ESCN DKS 855SSS unit 1.00 175,000.00 175,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 1.00 75,000.00 75,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 1.00 125,000.00 125,000.00
Door Closer Dekkson DCL 300 HO unit 1.00 75,000.00 75,000.00
JUMLAH HARGA BAHAN 2,015,738.11
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 2,100,738.11


E. Overhead & Profit 10% 210,073.81
F. Harga Satuan Pekerjaan (D+E) 2,310,811.92

1 unit Pintu tipe P4


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 8.40 95,000.00 798,000.00
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo m2 2.86 661,102.78 1,890,753.94
Kaca Polos 6mm, Merk : Asahimas m2 0.90 85,000.00 76,330.00
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 2.00 275,000.00 550,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 3.00 85,000.00 255,000.00
Escutcheon Dekkson ESCN DKS 855SSS unit 2.00 175,000.00 350,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 2.00 75,000.00 150,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 2.00 125,000.00 250,000.00
Door Closer Dekkson DCL 300 HO unit 2.00 75,000.00 150,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
JUMLAH HARGA BAHAN 4,690,083.94
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 4,775,083.94


E. Overhead & Profit 10% 477,508.39
F. Harga Satuan Pekerjaan (D+E) 5,252,592.34

1 unit Pintu tipe P5


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 7.60 95,000.00 722,000.00
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo m2 1.98 661,102.78 1,308,983.50
Kaca Polos 6mm, Merk : Asahimas m2 0.55 85,000.00 46,877.50
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 1.00 275,000.00 275,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 1.50 85,000.00 127,500.00
Escutcheon Dekkson ESCN DKS 855SSS unit 1.00 175,000.00 175,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 1.00 75,000.00 75,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 1.00 125,000.00 125,000.00
Door Closer Dekkson DCL 300 HO unit 1.00 75,000.00 75,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 1.00 25,000.00 25,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 1.00 85,000.00 85,000.00
JUMLAH HARGA BAHAN 3,040,361.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 3,125,361.00


E. Overhead & Profit 10% 312,536.10
F. Harga Satuan Pekerjaan (D+E) 3,437,897.10

1 unit Pintu tipe P6


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
detail by Vendor (standar SNI) Ex. Spectrum ls 1.00 1,500,000.00 1,500,000.00
JUMLAH HARGA BAHAN 1,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 1,575,000.00


E. Overhead & Profit 10% 157,500.00
F. Harga Satuan Pekerjaan (D+E) 1,732,500.00

1 unit Pintu tipe P7


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
detail by Vendor (standar SNI) Ex. Spectrum ls 1.00 1,500,000.00 1,500,000.00
JUMLAH HARGA BAHAN 1,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 1,575,000.00


E. Overhead & Profit 10% 157,500.00
F. Harga Satuan Pekerjaan (D+E) 1,732,500.00

1 unit Pintu tipe P8


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 6.38 95,000.00 606,100.00
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo m2 1.98 661,102.78 1,308,983.50
Architrave Kayu m3 0.04 6,619,500.00 273,385.35
Finishing Kayu m2 2.11 104,250.00 220,071.75
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 4.30 275,000.00 1,182,500.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 3.00 85,000.00 255,000.00
Escutcheon Dekkson ESCN DKS 855SSS unit 2.00 175,000.00 350,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 2.00 75,000.00 150,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 2.00 125,000.00 250,000.00
Door Closer Dekkson DCL 300 HO unit 2.00 75,000.00 150,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
JUMLAH HARGA BAHAN 4,966,040.60
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 5,051,040.60


E. Overhead & Profit 10% 505,104.06
F. Harga Satuan Pekerjaan (D+E) 5,556,144.66

1 unit Pintu tipe P9


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 9.90 95,000.00 940,500.00
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo m2 3.96 661,102.78 2,617,967.00
Kaca Polos 6mm, Merk : Asahimas m2 1.14 85,000.00 96,560.00
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 2.00 275,000.00 550,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 3.00 85,000.00 255,000.00
Escutcheon Dekkson ESCN DKS 855SSS unit 2.00 175,000.00 350,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 2.00 75,000.00 150,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 2.00 125,000.00 250,000.00
Door Closer Dekkson DCL 300 HO unit 2.00 75,000.00 150,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
JUMLAH HARGA BAHAN 5,580,027.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 5,665,027.00


E. Overhead & Profit 10% 566,502.70
F. Harga Satuan Pekerjaan (D+E) 6,231,529.70

1 unit Pintu tipe P10


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 5.44 95,000.00 516,800.00
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo m2 3.17 661,102.78 2,097,599.78
Rel dan Roda set 1.00 125,000.00 125,000.00
Sealant m1 2.20 500.00 1,100.00
Handel Tanam Oval Dekkson Oval Flush Pull Plate Dekson PP 012 Dekson psg 1.00 325,000.00 325,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 1.50 85,000.00 127,500.00
Escutcheon Dekkson ESCN DKS 855SSS unit 1.00 175,000.00 175,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 1.00 75,000.00 75,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 1.00 125,000.00 125,000.00
Door Closer Dekkson DCL 300 HO unit 1.00 75,000.00 75,000.00
JUMLAH HARGA BAHAN 3,642,999.78
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 3,727,999.78


E. Overhead & Profit 10% 372,799.98
F. Harga Satuan Pekerjaan (D+E) 4,100,799.76

1 unit Pintu tipe P11


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
CNP 150.50.20.3,2 kg 29.07 20,097.00 584,179.60
Rangka Besi Siku kg 27.14 20,097.00 545,512.97
Plat Baja 1.8mm kg 572.27 20,097.00 11,500,809.71
Pengecatan Duco m2 7.64 59,350.00 453,434.00
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 1.00 275,000.00 275,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 1.50 85,000.00 127,500.00
Escutcheon Dekkson ESCN DKS 855SSS unit 1.00 175,000.00 175,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 1.00 75,000.00 75,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 1.00 125,000.00 125,000.00
Door Closer Dekkson DCL 300 HO unit 1.00 75,000.00 75,000.00
JUMLAH HARGA BAHAN 13,936,436.27
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 14,021,436.27


E. Overhead & Profit 10% 1,402,143.63
F. Harga Satuan Pekerjaan (D+E) 15,423,579.90

1 unit Pintu Jendela tipe PJ1


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 34.40 95,000.00 3,268,000.00
Sudah termasuk metal close untuk engsel
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 11.80 65,000.00 767,000.00
Kaca Polos 6mm, Merk : Asahimas m2 10.04 85,000.00 852,975.00
Kaca Tempered 12mm, Merk : Asahimas m2 6.02 125,000.00 752,500.00
Handle Stainless Steel Dekkson PH-DKS-DL-1868 Dekson 120cm psg 2.00 110,000.00 220,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 3.00 85,000.00 255,000.00
Escutcheon Dekkson ESCN DKS 855SSS unit 2.00 175,000.00 350,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 2.00 75,000.00 150,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 2.00 125,000.00 250,000.00
Door Closer Dekkson DCL 300 HO unit 2.00 75,000.00 150,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
JUMLAH HARGA BAHAN 7,235,475.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 7,320,475.00


E. Overhead & Profit 10% 732,047.50
F. Harga Satuan Pekerjaan (D+E) 8,052,522.50

1 unit Pintu Jendela tipe PJ2


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 14.50 95,000.00 1,377,500.00
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo m2 2.86 661,102.78 1,890,753.94
Kaca Polos 6mm, Merk : Asahimas m2 2.85 85,000.00 242,505.00
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 2.00 275,000.00 550,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 3.00 85,000.00 255,000.00
Escutcheon Dekkson ESCN DKS 855SSS unit 2.00 175,000.00 350,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 2.00 75,000.00 150,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 2.00 125,000.00 250,000.00
Door Closer Dekkson DCL 300 HO unit 2.00 75,000.00 150,000.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 4.00 65,000.00 260,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 1.00 25,000.00 25,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 1.00 85,000.00 85,000.00
JUMLAH HARGA BAHAN 5,585,758.94
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 5,670,758.94


E. Overhead & Profit 10% 567,075.89
F. Harga Satuan Pekerjaan (D+E) 6,237,834.84

1 unit Pintu Jendela tipe PJ2'


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 14.70 95,000.00 1,396,500.00
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo m2 2.86 661,102.78 1,890,753.94
Kaca Polos 6mm, Merk : Asahimas m2 3.03 85,000.00 257,210.00
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 2.00 275,000.00 550,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 3.00 85,000.00 255,000.00
Escutcheon Dekkson ESCN DKS 855SSS unit 2.00 175,000.00 350,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 2.00 75,000.00 150,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 2.00 125,000.00 250,000.00
Door Closer Dekkson DCL 300 HO unit 2.00 75,000.00 150,000.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 5.20 65,000.00 338,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 1.00 25,000.00 25,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 1.00 85,000.00 85,000.00
JUMLAH HARGA BAHAN 5,697,463.94
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 5,782,463.94


E. Overhead & Profit 10% 578,246.39
F. Harga Satuan Pekerjaan (D+E) 6,360,710.34

1 unit Pintu Jendela tipe PJ3


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 18.80 95,000.00 1,786,000.00
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo m2 2.86 661,102.78 1,890,753.94
Kaca Polos 6mm, Merk : Asahimas m2 3.11 85,000.00 264,180.00
Papan Kayu m2 1.05 661,102.78 694,157.92
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 2.00 275,000.00 550,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 3.00 85,000.00 255,000.00
Escutcheon Dekkson ESCN DKS 855SSS unit 2.00 175,000.00 350,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 2.00 75,000.00 150,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 2.00 125,000.00 250,000.00
Door Closer Dekkson DCL 300 HO unit 2.00 75,000.00 150,000.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 6.80 65,000.00 442,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
JUMLAH HARGA BAHAN 7,002,091.86
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 7,087,091.86


E. Overhead & Profit 10% 708,709.19
F. Harga Satuan Pekerjaan (D+E) 7,795,801.05

1 unit Pintu Jendela tipe PJ4


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 13.70 95,000.00 1,301,500.00
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo m2 2.86 661,102.78 1,890,753.94
Kaca Polos 6mm, Merk : Asahimas m2 2.39 85,000.00 203,405.00
Papan Kayu m2 1.05 661,102.78 694,157.92
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 2.00 275,000.00 550,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 3.00 85,000.00 255,000.00
Escutcheon Dekkson ESCN DKS 855SSS unit 2.00 175,000.00 350,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 2.00 75,000.00 150,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 2.00 125,000.00 250,000.00
Door Closer Dekkson DCL 300 HO unit 2.00 75,000.00 150,000.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 2.40 65,000.00 156,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 1.00 25,000.00 25,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 1.00 85,000.00 85,000.00
JUMLAH HARGA BAHAN 6,060,816.86
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 6,145,816.86


E. Overhead & Profit 10% 614,581.69
F. Harga Satuan Pekerjaan (D+E) 6,760,398.55

Jendela tipe J1
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 8.90 95,000.00 845,500.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 9.50 65,000.00 617,500.00
Kaca Polos 6mm, Merk : Asahimas m2 2.99 85,000.00 254,150.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 1.00 25,000.00 25,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 1.00 85,000.00 85,000.00
JUMLAH HARGA BAHAN 1,827,150.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 1,912,150.00


E. Overhead & Profit 10% 191,215.00
F. Harga Satuan Pekerjaan (D+E) 2,103,365.00

Jendela tipe J1'


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 10.60 95,000.00 1,007,000.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 5.20 65,000.00 338,000.00
Kaca Polos 6mm, Merk : Asahimas m2 2.99 85,000.00 254,150.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 1.00 25,000.00 25,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 1.00 85,000.00 85,000.00
JUMLAH HARGA BAHAN 1,709,150.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 1,794,150.00


E. Overhead & Profit 10% 179,415.00
F. Harga Satuan Pekerjaan (D+E) 1,973,565.00

Jendela tipe J2
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 15.50 95,000.00 1,472,500.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 8.00 65,000.00 520,000.00
Kaca Polos 6mm, Merk : Asahimas m2 4.60 85,000.00 391,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
JUMLAH HARGA BAHAN 2,603,500.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 2,688,500.00


E. Overhead & Profit 10% 268,850.00
F. Harga Satuan Pekerjaan (D+E) 2,957,350.00

Jendela tipe J3
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 9.00 95,000.00 855,000.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 8.00 65,000.00 520,000.00
Kaca Polos 6mm, Merk : Asahimas m2 2.03 85,000.00 172,550.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
JUMLAH HARGA BAHAN 1,767,550.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 1,852,550.00


E. Overhead & Profit 10% 185,255.00
F. Harga Satuan Pekerjaan (D+E) 2,037,805.00

Jendela tipe J3'


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 10.40 95,000.00 988,000.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 4.00 65,000.00 260,000.00
Kaca Polos 6mm, Merk : Asahimas m2 2.21 85,000.00 187,425.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
JUMLAH HARGA BAHAN 1,655,425.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 1,740,425.00


E. Overhead & Profit 10% 174,042.50
F. Harga Satuan Pekerjaan (D+E) 1,914,467.50

Jendela tipe J4
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 24.00 95,000.00 2,280,000.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 11.40 65,000.00 741,000.00
Kaca Polos 6mm, Merk : Asahimas m2 6.45 85,000.00 548,250.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
JUMLAH HARGA BAHAN 3,789,250.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 3,874,250.00


E. Overhead & Profit 10% 387,425.00
F. Harga Satuan Pekerjaan (D+E) 4,261,675.00

Jendela tipe J5
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 26.50 95,000.00 2,517,500.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 8.00 65,000.00 520,000.00
Kaca Polos 6mm, Merk : Asahimas m2 8.90 85,000.00 756,500.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
JUMLAH HARGA BAHAN 4,014,000.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 4,099,000.00


E. Overhead & Profit 10% 409,900.00
F. Harga Satuan Pekerjaan (D+E) 4,508,900.00

Jendela tipe J6
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 28.70 95,000.00 2,726,500.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 10.90 65,000.00 708,500.00
Kaca Polos 6mm, Merk : Asahimas m2 9.20 85,000.00 782,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
JUMLAH HARGA BAHAN 4,437,000.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 4,522,000.00


E. Overhead & Profit 10% 452,200.00
F. Harga Satuan Pekerjaan (D+E) 4,974,200.00

Jendela tipe J6'


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 29.70 95,000.00 2,821,500.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 8.30 65,000.00 539,500.00
Kaca Polos 6mm, Merk : Asahimas m2 10.10 85,000.00 858,500.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
JUMLAH HARGA BAHAN 4,439,500.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 4,524,500.00


E. Overhead & Profit 10% 452,450.00
F. Harga Satuan Pekerjaan (D+E) 4,976,950.00

Jendela tipe J7
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 28.10 95,000.00 2,669,500.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 16.00 65,000.00 1,040,000.00
Kaca Polos 6mm, Merk : Asahimas m2 14.60 85,000.00 1,241,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 4.00 25,000.00 100,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 4.00 85,000.00 340,000.00
JUMLAH HARGA BAHAN 5,390,500.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 5,475,500.00


E. Overhead & Profit 10% 547,550.00
F. Harga Satuan Pekerjaan (D+E) 6,023,050.00

Jendela tipe J7'


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 35.40 95,000.00 3,363,000.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 13.80 65,000.00 897,000.00
Kaca Polos 6mm, Merk : Asahimas m2 11.64 85,000.00 989,400.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 3.00 25,000.00 75,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 3.00 85,000.00 255,000.00
JUMLAH HARGA BAHAN 5,579,400.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 5,664,400.00


E. Overhead & Profit 10% 566,440.00
F. Harga Satuan Pekerjaan (D+E) 6,230,840.00

Jendela tipe J8
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 51.70 95,000.00 4,911,500.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 15.60 65,000.00 1,014,000.00
Kaca Polos 6mm, Merk : Asahimas m2 17.28 85,000.00 1,468,800.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 4.00 25,000.00 100,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 4.00 85,000.00 340,000.00
JUMLAH HARGA BAHAN 7,834,300.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 7,919,300.00


E. Overhead & Profit 10% 791,930.00
F. Harga Satuan Pekerjaan (D+E) 8,711,230.00
Jendela tipe J8'
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 51.70 95,000.00 4,911,500.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 15.60 65,000.00 1,014,000.00
Kaca Polos 6mm, Merk : Asahimas m2 17.28 85,000.00 1,468,800.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 4.00 25,000.00 100,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 4.00 85,000.00 340,000.00
JUMLAH HARGA BAHAN 7,834,300.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 7,919,300.00


E. Overhead & Profit 10% 791,930.00
F. Harga Satuan Pekerjaan (D+E) 8,711,230.00

Jendela tipe J9
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 24.90 95,000.00 2,365,500.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 16.80 65,000.00 1,092,000.00
Kaca Polos 6mm, Merk : Asahimas m2 7.84 85,000.00 666,400.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 4.00 25,000.00 100,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 4.00 85,000.00 340,000.00
JUMLAH HARGA BAHAN 4,563,900.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 4,648,900.00


E. Overhead & Profit 10% 464,890.00
F. Harga Satuan Pekerjaan (D+E) 5,113,790.00

Jendela tipe J10


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 17.05 95,000.00 1,619,750.00
Kaca Polos 6mm, Merk : Asahimas m2 3.71 85,000.00 315,010.00
Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 9.60 65,000.00 624,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 2.00 25,000.00 50,000.00
Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 2.00 85,000.00 170,000.00
Multiplek 18mm lbr 2.45 220,000.00 539,305.56
HPL 0.8mm ex Taco lbr 2.45 160,000.00 392,222.22
JUMLAH HARGA BAHAN 3,710,287.78
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 3,795,287.78


E. Overhead & Profit 10% 379,528.78
F. Harga Satuan Pekerjaan (D+E) 4,174,816.56

Jendela tipe J11


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 58,475.00 58,475.00
JUMLAH TENAGA KERJA 58,475.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 5.20 95,000.00 494,000.00
Kaca Polos 6mm, Merk : Asahimas m2 0.95 85,000.00 80,750.00
JUMLAH HARGA BAHAN 574,750.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 643,225.00


E. Overhead & Profit 10% 64,322.50
F. Harga Satuan Pekerjaan (D+E) 707,547.50

Bouvenlight tipe B1
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 24,507.50 24,507.50
JUMLAH TENAGA KERJA 24,507.50
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 2.30 95,000.00 218,500.00
Kaca Polos 6mm, Merk : Asahimas m2 0.20 85,000.00 16,575.00
JUMLAH HARGA BAHAN 235,075.00
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 269,582.50


E. Overhead & Profit 10% 26,958.25
F. Harga Satuan Pekerjaan (D+E) 296,540.75

1 unit Pintu tipe PT


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 75,000.00 75,000.00
JUMLAH TENAGA KERJA 75,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 5.30 95,000.00 503,500.00
Sudah termasuk metal close untuk engsel
Daun Pintu Solid lapis Megateak 3mm, Ex. Tobindo m2 2.50 661,102.78 1,652,756.94
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 1.00 275,000.00 275,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 1.50 85,000.00 127,500.00
Escutcheon Dekkson ESCN DKS 855SSS unit 1.00 175,000.00 175,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 1.00 75,000.00 75,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 1.00 125,000.00 125,000.00
Door Closer Dekkson DCL 300 HO unit 1.00 75,000.00 75,000.00
JUMLAH HARGA BAHAN 3,008,756.94
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 3,093,756.94


E. Overhead & Profit 10% 309,375.69
F. Harga Satuan Pekerjaan (D+E) 3,403,132.64

Bouvenlight tipe BV
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 15,000.00 15,000.00
JUMLAH TENAGA KERJA 15,000.00
B. BAHAN
Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 2.40 95,000.00 228,000.00
Metal square hollow 20/20, tebal 0,9mm m1 5.40 6,666.67 36,000.00
Pengecatan Duco m2 0.43 59,350.00 25,639.20
JUMLAH HARGA BAHAN 289,639.20
C. PERALATAN
Material dan Alat Bantu ls 1.00 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 314,639.20


E. Overhead & Profit 10% 31,463.92
F. Harga Satuan Pekerjaan (D+E) 346,103.12
ANALISA HARGA SATUAN PEKERJAAN MEP

1 m1 Pek. Pas. Pipa 4"


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Ongkos Pasang ls 1.00 6,496.88 6,496.88
JUMLAH TENAGA KERJA 6,496.88
B. BAHAN
PVC Dia. 4” m1 1.05 37,500.00 39,375.00
JUMLAH HARGA BAHAN 39,375.00
C. PERALATAN
Material & alat Bantu ls 1.00 3,937.50 3,937.50
JUMLAH HARGA PERALATAN 3,937.50

D. Jumlah (A+B+C) 49,809.38


E. Overhead & Profit 10% 4,980.94
F. Harga Satuan Pekerjaan (D+E) 54,790.31

Memasang 1 bh Floting Valve 10K 1" (25 mm) lengkap


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 85,000.00 21,250.00
Tukang L.02 OH 0.200 90,000.00 18,000.00
Kepala tukang L.03 OH 0.040 95,000.00 3,800.00
Mandor L.04 OH 0.030 100,000.00 3,000.00
JUMLAH TENAGA KERJA 46,050.00
B. BAHAN
Floating valve dia. 40 mm bh 1.000 350,000.00 350,000.00
JUMLAH HARGA BAHAN 350,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 396,050.00


E. Overhead & Profit 10% 39,605.00
F. Harga Satuan Pembantu Tukangan (D+E) 435,655.00

Memasang 1 bh Gate valve 10K 1 1/2" (40 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 26,732.14
B. BAHAN
Gate valve 10 K dia. 40 mm bh 1.000 2,750,000.00 2,750,000.00
JUMLAH HARGA BAHAN 2,750,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 2,776,732.14


E. Overhead & Profit 10% 277,673.21
F. Harga Satuan Pembantu Tukangan (D+E) 3,054,405.36

Memasang 1 set Water level control


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 85,000.00 42,500.00
Tukang L.02 OH 0.400 90,000.00 36,000.00
Kepala tukang L.03 OH 0.040 95,000.00 3,800.00
Mandor L.04 OH 0.030 100,000.00 3,000.00
JUMLAH TENAGA KERJA 85,300.00
B. BAHAN
Water Level Control ( WLC ) set 1.000 7,500,000.00 7,500,000.00
JUMLAH HARGA BAHAN 7,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 7,585,300.00


E. Overhead & Profit 10% 758,530.00
F. Harga Satuan Pembantu Tukangan (D+E) 8,343,830.00

Memasang 1 m' Pipa GSP Medium ø 6 "


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.093 85,000.00 7,892.86
Tukang L.02 OH 0.093 90,000.00 8,357.14
Kepala tukang L.03 OH 0.014 95,000.00 1,357.14
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 18,321.43
B. BAHAN
GIP Medium Dia. 6” m1 1.000 45,833.33 45,833.33
Fitting & Sambungan m' 1.000 11,458.33 11,458.33
JUMLAH HARGA BAHAN 57,291.67
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 2,864.58 2,864.58
JUMLAH HARGA PERALATAN 2,864.58

D. Jumlah (A+B+C) 78,477.68


E. Overhead & Profit 10% 7,847.77
F. Harga Satuan Pembantu Tukangan (D+E) 86,325.45

Memasang 1 bh Butterfly valve 10K 6" (150 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.020 95,000.00 1,900.00
Mandor L.04 OH 0.010 100,000.00 1,000.00
JUMLAH TENAGA KERJA 27,900.00
B. BAHAN
Butterfly valve 10 K dia. 150 mm bh 1.000 7,500,000.00 7,500,000.00
JUMLAH HARGA BAHAN 7,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 7,527,900.00


E. Overhead & Profit 10% 752,790.00
F. Harga Satuan Pembantu Tukangan (D+E) 8,280,690.00

1 titik Pembuatan Sumur Bor Dalam ( Deepwell )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A. Persiapan Lapangan
Mobilisasi & Demobilisasi Peralatan Kali 2.000 1,000,000.00 2,000,000.00
Pembuatan Spull bak / Bak sirkulasi Unit 1.000 10,500,000.00 10,500,000.00
Transfortasi Tenaga Kerja Ls 1.000 1,000,000.00 1,000,000.00
B. Jasa Kontruksi
Jasa Bor pilot hole dia 4" M' 60.000 350,000.00 21,000,000.00
Solar/olie/bensin/bahan las Ls 1.000 650,000.00 650,000.00
Buang Lumpur Bor Ls 1.000 1,000,000.00 1,000,000.00
Spolling ( Pemberesihan sumur ) Ls 1.000 1,000,000.00 1,000,000.00

C. Lain - Lain
MATERIAL
Pompa Deepwell submersible Groundfos 1.5 PK Unit 1.000 15,000,000.00 15,000,000.00
Pipa GIP Medium,dia. 1.1/4 " M' 75.000 85,000.00 6,375,000.00
Tutup Sumur Pcs 1.000 500,000.00 500,000.00
Pasir & semen ls 1.000 500,000.00 500,000.00

D. Accessories Pompa
Kelistrikan & kontrol ls 1.000 1,000,000.00 1,000,000.00

E. Perizinan

D. Jumlah (A+B+C) 60,525,000.00


E. Overhead & Profit 10% 6,052,500.00
F. Harga Satuan Pekerjaan (D+E) 66,577,500.00

Titik Biaya Sambungan Air bersih PDAM lengkap Meter Air + Gate valve 10K ( 32 mm)
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 85,000.00 21,250.00
Tukang L.02 OH 0.200 90,000.00 18,000.00
Kepala tukang L.03 OH 0.020 95,000.00 1,900.00
Mandor L.04 OH 0.015 100,000.00 1,500.00
JUMLAH TENAGA KERJA 42,650.00
B. BAHAN
Gate valve 150 PSI dia. dia. 32 mm bh 1.000 8,500,000.00 8,500,000.00
meter air bh 1.000 175,000.00 175,000.00
box meter bh 1.000 75,000.00 75,000.00
JUMLAH HARGA BAHAN 8,750,000.00
C. BIAYA SAMBUNGAN
sambungan aIir bersih, PDAM, diameter 40 mm ttk 1.000 25,000.00 25,000.00
JUMLAH BIAYA SAMBUNGAN 25,000.00

D. Jumlah (A+B+C) 8,817,650.00


E. Overhead & Profit 10% 881,765.00
F. Harga Satuan Pekerjaan (D+E) 9,699,415.00

Memasang 1 m' pipa PVC tipe AW ø1 1/2" (40 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 85,000.00 3,035.71
Tukang L.02 OH 0.036 90,000.00 3,214.29
Kepala tukang L.03 OH 0.003 95,000.00 271.43
Mandor L.04 OH 0.001 100,000.00 142.86
JUMLAH TENAGA KERJA 6,664.29
B. BAHAN
PVC Dia. 1 1/2” m1 1.000 17,500.00 17,500.00
Fitting & sambungan m' 1.000 4,375.00 4,375.00
JUMLAH HARGA BAHAN 21,875.00
C. PERALATAN
Fitting, sambungan, klem dll bh 1.000 1,093.75 1,093.75
JUMLAH HARGA PERALATAN 1,093.75

D. Jumlah (A+B+C) 29,633.04


E. Overhead & Profit 10% 2,963.30
F. Harga Satuan Pembantu Tukangan (D+E) 32,596.34

Memasang 1 Unit Pompa Filter Air Bersih ( PF )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 85,000.00 85,000.00
Tukang L.02 OH 1.000 90,000.00 90,000.00
Kepala tukang L.03 OH 0.200 95,000.00 19,000.00
Mandor L.04 OH 0.200 100,000.00 20,000.00
JUMLAH TENAGA KERJA 214,000.00
B. BAHAN
Pompa Transfer, kapasitas : 150 Lpm/ head 42 meter unit 1.000 22,500,000.00 22,500,000.00
JUMLAH HARGA BAHAN 22,500,000.00
C. PERALATAN
Alat bantu (5% x item 1) ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 22,814,000.00


E. Overhead & Profit 10% 2,281,400.00
F. Harga Satuan Pembantu Tukangan (D+E) 25,095,400.00

Memasang 1 bh flexible joint 10K 1 1/2 " (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 26,732.14
B. BAHAN
Flexible Joint 10 K 50 mm bh 1.000 850,000.00 850,000.00
JUMLAH HARGA BAHAN 850,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 876,732.14


E. Overhead & Profit 10% 87,673.21
F. Harga Satuan Pembantu Tukangan (D+E) 964,405.36

Memasang 1 bh Check valve 10K 1,5" (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 26,732.14
B. BAHAN
Check valve 10 K dia. 50 mm bh 1.000 3,500,000.00 3,500,000.00
JUMLAH HARGA BAHAN 3,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 3,526,732.14


E. Overhead & Profit 10% 352,673.21
F. Harga Satuan Pembantu Tukangan (D+E) 3,879,405.36

Memasang 1 bh Gate valve 10K 1 1/2" (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 26,732.14
B. BAHAN
Gate valve 10 K dia. 50 mm bh 1.000 3,000,000.00 3,000,000.00
JUMLAH HARGA BAHAN 3,000,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 3,026,732.14


E. Overhead & Profit 10% 302,673.21
F. Harga Satuan Pembantu Tukangan (D+E) 3,329,405.36

Memasang 1 bh strainer 10K 1 1/2" (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 26,732.14
B. BAHAN
Y - Strainer 10 K dia. 50 mm bh 1.000 250,000.00 250,000.00
JUMLAH HARGA BAHAN 250,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 276,732.14


E. Overhead & Profit 10% 27,673.21
F. Harga Satuan Pembantu Tukangan (D+E) 304,405.36

Memasang 1 ttk Instalasi daya listrik pompa transfer air bersih


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.214 85,000.00 18,214.29
Tukang L.02 OH 0.200 90,000.00 18,000.00
Kepala tukang L.03 OH 0.071 95,000.00 6,785.71
Mandor L.04 OH 0.057 100,000.00 5,714.29
JUMLAH TENAGA KERJA 48,714.29
B. BAHAN
NYY 3 x 4 MM2 m1 20.000 18,000.00 360,000.00
Pipa konduit PVC Hight Inpact m1 20.000 3,500.00 70,000.00
JUMLAH HARGA BAHAN 430,000.00
C. PERALATAN
Perlengkapan ( klem, dll ) bh 1.000 10,750.00 10,750.00
JUMLAH HARGA PERALATAN 10,750.00

D. Jumlah (A+B+C) 489,464.29


E. Overhead & Profit 10% 48,946.43
F. Harga Satuan Pembantu Tukangan (D+E) 538,410.71

Memasang 1 Unit Sand Filter kapasitas : 100 Lpm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.714 85,000.00 60,714.29
Tukang L.02 OH 0.714 90,000.00 64,285.71
Kepala tukang L.03 OH 0.286 95,000.00 27,142.86
Mandor L.04 OH 0.143 100,000.00 14,285.71
JUMLAH TENAGA KERJA 166,428.57
B. BAHAN
Sand Filter kapasitas : 100 Lpm unit 1.000 12,500,000.00 12,500,000.00
JUMLAH HARGA BAHAN 12,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 12,666,428.57


E. Overhead & Profit 10% 1,266,642.86
F. Harga Satuan Pembantu Tukangan (D+E) 13,933,071.43

Memasang 1 Unit Carbon Filter kapasitas : 100 Lpm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.714 85,000.00 60,714.29
Tukang L.02 OH 0.714 90,000.00 64,285.71
Kepala tukang L.03 OH 0.286 95,000.00 27,142.86
Mandor L.04 OH 0.143 100,000.00 14,285.71
JUMLAH TENAGA KERJA 166,428.57
B. BAHAN
Carbon Filter kapasitas : 100 Lpm unit 1.000 12,500,000.00 12,500,000.00
JUMLAH HARGA BAHAN 12,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 12,666,428.57


E. Overhead & Profit 10% 1,266,642.86
F. Harga Satuan Pembantu Tukangan (D+E) 13,933,071.43

Memasang 1 bh flexible joint 10K 2" (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 26,732.14
B. BAHAN
Flexible Joint 10 K 50 mm bh 1.000 850,000.00 850,000.00
JUMLAH HARGA BAHAN 850,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 876,732.14


E. Overhead & Profit 10% 87,673.21
F. Harga Satuan Pembantu Tukangan (D+E) 964,405.36

Memasang 1 bh Check valve 10K 2" (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 26,732.14
B. BAHAN
Check valve 10 K dia. 50 mm bh 1.000 3,500,000.00 3,500,000.00
JUMLAH HARGA BAHAN 3,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 3,526,732.14


E. Overhead & Profit 10% 352,673.21
F. Harga Satuan Pembantu Tukangan (D+E) 3,879,405.36

Memasang 1 bh Gate valve 10K 2" (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 26,732.14
B. BAHAN
Gate valve 10 K dia. 50 mm bh 1.000 3,000,000.00 3,000,000.00
JUMLAH HARGA BAHAN 3,000,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 3,026,732.14


E. Overhead & Profit 10% 302,673.21
F. Harga Satuan Pembantu Tukangan (D+E) 3,329,405.36

Memasang 1 bh strainer 10K 2" ( 50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 26,732.14
B. BAHAN
Y - Strainer 10 K dia. 50 mm bh 1.000 250,000.00 250,000.00
JUMLAH HARGA BAHAN 250,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 276,732.14


E. Overhead & Profit 10% 27,673.21
F. Harga Satuan Pembantu Tukangan (D+E) 304,405.36

1 unit Pompa Sumpit ( Submersible Pump )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 85,000.00 85,000.00
Tukang L.02 OH 1.000 90,000.00 90,000.00
Kepala tukang L.03 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.200 100,000.00 20,000.00
JUMLAH TENAGA KERJA 218,750.00
B. BAHAN
Pompa Sumpit, kap. 50 Lpm/ head: 10 meter unit 1.000 17,500,000.00 17,500,000.00
JUMLAH HARGA BAHAN 17,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 17,718,750.00


E. Overhead & Profit 10% 1,771,875.00
F. Harga Satuan Pekerjaan (D+E) 19,490,625.00

Memasang 1 bh flexible joint 10K 1 1/4 " (32 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 26,732.14
B. BAHAN
Flexible Joint 10 K dia. 32 mm bh 1.000 650,000.00 650,000.00
JUMLAH HARGA BAHAN 650,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 676,732.14


E. Overhead & Profit 10% 67,673.21
F. Harga Satuan Pembantu Tukangan (D+E) 744,405.36

Memasang 1 bh Check valve 10K 1,25" (32 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 26,732.14
B. BAHAN
Check valve 10 K dia. 32 mm bh 1.000 3,000,000.00 3,000,000.00
JUMLAH HARGA BAHAN 3,000,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 3,026,732.14


E. Overhead & Profit 10% 302,673.21
F. Harga Satuan Pembantu Tukangan (D+E) 3,329,405.36

Memasang 1 bh Gate valve 10K 1 1/4" (32 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 26,732.14
B. BAHAN
Gate valve 10 K dia. 32 mm bh 1.000 2,500,000.00 2,500,000.00
JUMLAH HARGA BAHAN 2,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 2,526,732.14


E. Overhead & Profit 10% 252,673.21
F. Harga Satuan Pembantu Tukangan (D+E) 2,779,405.36
Memasang 1 m' pipa GIP medium ø 1 1/2" (40 mm)
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.071 85,000.00 6,071.43
Tukang L.02 OH 0.071 90,000.00 6,428.57
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.006 100,000.00 571.43
JUMLAH TENAGA KERJA 14,089.29
B. BAHAN
GIP Medium Dia. 1 1/2” m1 1.000 20,833.33 20,833.33
Fitting & Sambungan m1 1.000 5,208.33 5,208.33
JUMLAH HARGA BAHAN 26,041.67
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 1,302.08 1,302.08
JUMLAH HARGA PERALATAN 1,302.08

D. Jumlah (A+B+C) 41,433.04


E. Overhead & Profit 10% 4,143.30
F. Harga Satuan Pembantu Tukangan (D+E) 45,576.34

Memasang 1 bh Gate valve 10K 1" (25 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 85,000.00 6,800.00
Tukang L.02 OH 0.080 90,000.00 7,200.00
Kepala tukang L.03 OH 0.010 95,000.00 950.00
Mandor L.04 OH 0.002 100,000.00 180.00
JUMLAH TENAGA KERJA 15,130.00
B. BAHAN
Gate valve 150 PSI dia. dia. 25 mm bh 1.000 10,500,000.00 10,500,000.00
JUMLAH HARGA BAHAN 10,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 10,515,130.00


E. Overhead & Profit 10% 1,051,513.00
F. Harga Satuan Pembantu Tukangan (D+E) 11,566,643.00

Memasang 1 m' pipa GIP medium ø 2" (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.071 85,000.00 6,071.43
Tukang L.02 OH 0.071 90,000.00 6,428.57
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.006 100,000.00 571.43
JUMLAH TENAGA KERJA 14,089.29
B. BAHAN
GIP Medium Dia. 2” m1 1.000 41,666.67 41,666.67
Fitting & Sambungan m' 1.000 10,416.67 10,416.67
JUMLAH HARGA BAHAN 52,083.33
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 2,604.17 2,604.17
JUMLAH HARGA PERALATAN 2,604.17

D. Jumlah (A+B+C) 68,776.79


E. Overhead & Profit 10% 6,877.68
F. Harga Satuan Pembantu Tukangan (D+E) 75,654.46

Memasang 1 m' pipa PVC tipe AW ø2" (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.057 85,000.00 4,857.14
Tukang L.02 OH 0.050 90,000.00 4,500.00
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 10,185.71
B. BAHAN
PVC Dia. 2” m1 1.000 18,500.00 18,500.00
Fitting & sambungan m' 1.000 4,625.00 4,625.00
JUMLAH HARGA BAHAN 23,125.00
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 1,156.25 1,156.25
JUMLAH HARGA PERALATAN 1,156.25

D. Jumlah (A+B+C) 34,466.96


E. Overhead & Profit 10% 3,446.70
F. Harga Satuan Pembantu Tukangan (D+E) 37,913.66

Memasang 1 m' pipa PVC tipe AW ø1 1/4" (32 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 85,000.00 3,035.71
Tukang L.02 OH 0.036 90,000.00 3,214.29
Kepala tukang L.03 OH 0.003 95,000.00 271.43
Mandor L.04 OH 0.001 100,000.00 142.86
JUMLAH TENAGA KERJA 6,664.29
B. BAHAN
PVC Dia. 1 1/4” m1 1.000 13,500.00 13,500.00
Fitting & sambungan m' 1.000 3,375.00 3,375.00
JUMLAH HARGA BAHAN 16,875.00
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 843.75 843.75
JUMLAH HARGA PERALATAN 843.75

D. Jumlah (A+B+C) 24,383.04


E. Overhead & Profit 10% 2,438.30
F. Harga Satuan Pembantu Tukangan (D+E) 26,821.34

Memasang 1 m' pipa PVC tipe AW ø 1/2" (15 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 85,000.00 3,035.71
Tukang L.02 OH 0.036 90,000.00 3,214.29
Kepala tukang L.03 OH 0.003 95,000.00 271.43
Mandor L.04 OH 0.001 100,000.00 142.86
JUMLAH TENAGA KERJA 6,664.29
B. BAHAN
PVC dia. 1/2” m1 1.000 4,666.67 4,666.67
Fitting & sambungan m1 1.000 1,166.67 1,166.67
JUMLAH HARGA BAHAN 5,833.33
C. PERALATAN
Perlengkapan ( hanger, Clamp, penunpu, dll ) bh 1.000 291.67 291.67
JUMLAH HARGA PERALATAN 291.67

D. Jumlah (A+B+C) 12,789.29


E. Overhead & Profit 10% 1,278.93
F. Harga Satuan Pembantu Tukangan (D+E) 14,068.21

Memasang 1 m' pipa PVC tipe AW ø 3/4" (20 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
NO URAIAN KODE SATUAN KOEFISIEN
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 85,000.00 3,035.71
Tukang L.02 OH 0.036 90,000.00 3,214.29
Kepala tukang L.03 OH 0.003 95,000.00 271.43
Mandor L.04 OH 0.001 100,000.00 142.86
JUMLAH TENAGA KERJA 6,664.29
B. BAHAN
PVC dia. 3/4” m1 1.000 5,833.33 5,833.33
Fitting & sambungan m' 1.000 1,458.33 1,458.33
JUMLAH HARGA BAHAN 7,291.67
C. PERALATAN
Perlengkapan ( hanger, Clamp, penunpu, dll ) bh 1.000 364.58 364.58
JUMLAH HARGA PERALATAN 364.58

D. Jumlah (A+B+C) 14,320.54


E. Overhead & Profit 10% 1,432.05
F. Harga Satuan Pembantu Tukangan (D+E) 15,752.59

Memasang 1 m' pipa PVC tipe AW ø 1" (25 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 85,000.00 3,035.71
Tukang L.02 OH 0.036 90,000.00 3,214.29
Kepala tukang L.03 OH 0.003 95,000.00 271.43
Mandor L.04 OH 0.001 100,000.00 142.86
JUMLAH TENAGA KERJA 6,664.29
B. BAHAN
PVC Dia. 1” m1 1.000 12,500.00 12,500.00
Fitting & sambungan m' 1.000 3,125.00 3,125.00
JUMLAH HARGA BAHAN 15,625.00
C. PERALATAN
Perlengkapan ( hanger, Clamp, penunpu, dll ) bh 1.000 781.25 781.25
JUMLAH HARGA PERALATAN 781.25

D. Jumlah (A+B+C) 23,070.54


E. Overhead & Profit 10% 2,307.05
F. Harga Satuan Pembantu Tukangan (D+E) 25,377.59

Memasang 1 bh Gate valve 10K 3/4" (20 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 85,000.00 6,800.00
Tukang L.02 OH 0.080 90,000.00 7,200.00
Kepala tukang L.03 OH 0.010 95,000.00 950.00
Mandor L.04 OH 0.002 100,000.00 180.00
JUMLAH TENAGA KERJA 15,130.00
B. BAHAN
Gate valve 150 PSI dia. dia. 25 mm bh 1.000 10,500,000.00 10,500,000.00
JUMLAH HARGA BAHAN 10,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 10,515,130.00


E. Overhead & Profit 10% 1,051,513.00
F. Harga Satuan Pembantu Tukangan (D+E) 11,566,643.00

Memasang 1 unit Rooftank kapasitas 6 m3


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 85,000.00 85,000.00
Tukang L.02 OH 1.000 90,000.00 90,000.00
Kepala tukang L.03 OH 0.500 95,000.00 47,500.00
Mandor L.04 OH 0.400 100,000.00 40,000.00
JUMLAH TENAGA KERJA 262,500.00
B. BAHAN
Roof Tank ( PRF ), kapasitas 6000 L unit 1.000 75,000,000.00 75,000,000.00
Dudukan tanki bh 1.000 -
JUMLAH HARGA BAHAN 75,000,000.00
C. PERALATAN
Perlengkapan ( alat bantu pemasangan ) ls 1.000 1,875,000.00 1,875,000.00
JUMLAH HARGA PERALATAN 1,875,000.00

D. Jumlah (A+B+C) 77,137,500.00


E. Overhead & Profit 10% 7,713,750.00
F. Harga Satuan Pembantu Tukangan (D+E) 84,851,250.00

Memasang 1 bh Floting valve 10K 2" (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 85,000.00 21,250.00
Tukang L.02 OH 0.250 90,000.00 22,500.00
Kepala tukang L.03 OH 0.040 95,000.00 3,800.00
Mandor L.04 OH 0.040 100,000.00 4,000.00
JUMLAH TENAGA KERJA 51,550.00
B. BAHAN
Floating valve dia. 40 mm bh 1.000 350,000.00 350,000.00
JUMLAH HARGA BAHAN 350,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 401,550.00


E. Overhead & Profit 10% 40,155.00
F. Harga Satuan Pembantu Tukangan (D+E) 441,705.00

Memasang 1 bh Gate valve 10K 3" (80 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.107 85,000.00 9,107.14
Tukang L.02 OH 0.107 90,000.00 9,642.86
Kepala tukang L.03 OH 0.010 95,000.00 950.00
Mandor L.04 OH 0.002 100,000.00 180.00
JUMLAH TENAGA KERJA 19,880.00
B. BAHAN
Gate valve 10 K dia. 80 mm bh 1.000 5,000,000.00 5,000,000.00
JUMLAH HARGA BAHAN 5,000,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 5,019,880.00


E. Overhead & Profit 10% 501,988.00
F. Harga Satuan Pembantu Tukangan (D+E) 5,521,868.00

1 m' Header GSP Medium 4 "


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.571 85,000.00 48,571.43
Tukang L.02 OH 0.571 90,000.00 51,428.57
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.107 100,000.00 10,714.29
JUMLAH TENAGA KERJA 124,285.71
B. BAHAN
GSP Medium Dia. 4” ( 100 mm ) m1 2.000 91,666.67 183,333.33
Sambungan cabang, dop m1 1.000 45,833.33 45,833.33
JUMLAH HARGA BAHAN 229,166.67
C. PERALATAN
Perlengkapan ( Dudukan/ penunpu, dll ) ls 1.000 57,291.67 57,291.67
JUMLAH HARGA PERALATAN 57,291.67

D. Jumlah (A+B+C) 410,744.05


E. Overhead & Profit 10% 41,074.40
F. Harga Satuan Pekerjaan (D+E) 451,818.45

Memasang 1 Unit Packaged Booster Pumps kapasitas 165 lpm, head 10 meter (1 pump operation in 2 pumps system/Single alternate)
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 85,000.00 127,500.00
Tukang L.02 OH 1.500 90,000.00 135,000.00
Kepala tukang L.03 OH 0.350 95,000.00 33,250.00
Mandor L.04 OH 0.250 100,000.00 25,000.00
JUMLAH TENAGA KERJA 320,750.00
B. BAHAN
Booster Pump Packaged, Kapasitas 165 lpm ; Head 10 meter unit 1.000 22,500,000.00 22,500,000.00
JUMLAH HARGA BAHAN 22,500,000.00
C. PERALATAN
Perlengkapan ( Dudukan pompa & penahan getaran ) bh 1.000 562,500.00 562,500.00
JUMLAH HARGA PERALATAN 562,500.00

D. Jumlah (A+B+C) 23,383,250.00


E. Overhead & Profit 10% 2,338,325.00
F. Harga Satuan Pembantu Tukangan (D+E) 25,721,575.00

Memasang 1 m' pipa PVC tipe AW ø2 1/2" (65 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.057 85,000.00 4,857.14
Tukang L.02 OH 0.050 90,000.00 4,500.00
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 10,185.71
B. BAHAN
PVC Dia. 2 1/2” m1 1.000 22,500.00 22,500.00
Fitting & sambungan m1 1.000 5,625.00 5,625.00
JUMLAH HARGA BAHAN 28,125.00
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 1,406.25 1,406.25
JUMLAH HARGA PERALATAN 1,406.25

D. Jumlah (A+B+C) 39,716.96


E. Overhead & Profit 10% 3,971.70
F. Harga Satuan Pembantu Tukangan (D+E) 43,688.66

Memasang 1 m' pipa PVC tipe AW ø3" (80 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.057 85,000.00 4,857.14
Tukang L.02 OH 0.050 90,000.00 4,500.00
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 10,185.71
B. BAHAN
PVC Dia. 3” m1 1.000 32,500.00 32,500.00
Fitting & sambungan m1 1.000 8,125.00 8,125.00
JUMLAH HARGA BAHAN 40,625.00
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 2,031.25 2,031.25
JUMLAH HARGA PERALATAN 2,031.25

D. Jumlah (A+B+C) 52,841.96


E. Overhead & Profit 10% 5,284.20
F. Harga Satuan Pembantu Tukangan (D+E) 58,126.16

Memasang 1 bh Gate valve 10K 2 1/2" (65 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.107 85,000.00 9,107.14
Tukang L.02 OH 0.107 90,000.00 9,642.86
Kepala tukang L.03 OH 0.010 95,000.00 950.00
Mandor L.04 OH 0.002 100,000.00 180.00
JUMLAH TENAGA KERJA 19,880.00
B. BAHAN
Gate valve 10 K dia. 65 mm bh 1.000 3,500,000.00 3,500,000.00
JUMLAH HARGA BAHAN 3,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 3,519,880.00


E. Overhead & Profit 10% 351,988.00
F. Harga Satuan Pembantu Tukangan (D+E) 3,871,868.00

Memasang 1 m' pipa PVC tipe AW ø4" (100 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.057 85,000.00 4,857.14
Tukang L.02 OH 0.050 90,000.00 4,500.00
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 10,185.71
B. BAHAN
PVC Dia. 4” m1 1.000 37,500.00 37,500.00
Fitting & sambungan m' 1.000 9,375.00 9,375.00
JUMLAH HARGA BAHAN 46,875.00
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 2,343.75 2,343.75
JUMLAH HARGA PERALATAN 2,343.75

D. Jumlah (A+B+C) 59,404.46


E. Overhead & Profit 10% 5,940.45
F. Harga Satuan Pembantu Tukangan (D+E) 65,344.91

Memasang 1 bh Clean out 4" (100 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.107 90,000.00 9,642.86
Kepala tukang L.03 OH 0.014 95,000.00 1,357.14
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 23,857.14
B. BAHAN
CO diameter 100 mm bh 1.000 250,000.00 250,000.00
JUMLAH HARGA BAHAN 250,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN
D. Jumlah (A+B+C) 273,857.14
E. Overhead & Profit 10% 27,385.71
F. Harga Satuan Pembantu Tukangan (D+E) 301,242.86

Memasang 1 bh Clean out 2,5" (65 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.107 90,000.00 9,642.86
Kepala tukang L.03 OH 0.014 95,000.00 1,357.14
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 23,857.14
B. BAHAN
CO diameter 65 mm bh 1.000 175,000.00 175,000.00
JUMLAH HARGA BAHAN 175,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 198,857.14


E. Overhead & Profit 10% 19,885.71
F. Harga Satuan Pembantu Tukangan (D+E) 218,742.86

Memasang 1 m' pipa PVC tipe AW ø6" (150 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.057 85,000.00 4,857.14
Tukang L.02 OH 0.050 90,000.00 4,500.00
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 10,185.71
B. BAHAN
PVC Dia. 6” m1 1.000 55,000.00 55,000.00
Fitting & sambungan m' 1.000 13,750.00 13,750.00
JUMLAH HARGA BAHAN 68,750.00
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) ls 1.000 3,437.50 3,437.50
JUMLAH HARGA PERALATAN 3,437.50

D. Jumlah (A+B+C) 82,373.21


E. Overhead & Profit 10% 8,237.32
F. Harga Satuan Pembantu Tukangan (D+E) 90,610.54

Memasang 1 m' pipa PVC tipe AW ø8" (200 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.057 85,000.00 4,857.14
Tukang L.02 OH 0.050 90,000.00 4,500.00
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 10,185.71
B. BAHAN
PVC Dia. 8” m1 1.000 65,000.00 65,000.00
Fitting & sambungan m' 1.000 16,250.00 16,250.00
JUMLAH HARGA BAHAN 81,250.00
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) ls 1.000 4,062.50 4,062.50
JUMLAH HARGA PERALATAN 4,062.50

D. Jumlah (A+B+C) 95,498.21


E. Overhead & Profit 10% 9,549.82
F. Harga Satuan Pembantu Tukangan (D+E) 105,048.04
Memasang 1 bh roof drain dia. 2,5"
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.107 85,000.00 9,107.14
Tukang L.02 OH 0.071 90,000.00 6,428.57
Kepala tukang L.03 OH 0.014 95,000.00 1,357.14
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 17,607.14
B. BAHAN
Roof Drain dia. 65 mm m1 1.000 35,000.00 35,000.00
JUMLAH HARGA BAHAN 35,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 52,607.14


E. Overhead & Profit 10% 5,260.71
F. Harga Satuan Pembantu Tukangan (D+E) 57,867.86

Memasang 1 bh roof drain dia. 2"


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.107 85,000.00 9,107.14
Tukang L.02 OH 0.071 90,000.00 6,428.57
Kepala tukang L.03 OH 0.014 95,000.00 1,357.14
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 17,607.14
B. BAHAN
Roof Drain dia. 50 mm m1 1.000 27,500.00 27,500.00
JUMLAH HARGA BAHAN 27,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 45,107.14


E. Overhead & Profit 10% 4,510.71
F. Harga Satuan Pembantu Tukangan (D+E) 49,617.86

Pemasangan 1 titik Core Drill untuk drain AC


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
ongkos pasang Ls 1.0000 150,000.00 150,000.00
JUMLAH TENAGA KERJA 150,000.00
B. BAHAN
Core Drill Machine ttk 1.0000 1,000.00 1,000.00
Mata Bor bh 1.0000 1,500.00 1,500.00
JUMLAH HARGA BAHAN 2,500.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 152,500.00


E. Overhead & Profit 15% 22,875.00
F. Harga Satuan Pekerjaan (D+E) 175,375.00

Memasang 1 unit sumur resapan


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.429 85,000.00 36,428.57
Tukang L.02 OH 0.286 90,000.00 25,714.29
Kepala tukang L.03 OH 0.071 95,000.00 6,785.71
Mandor L.04 OH 0.043 100,000.00 4,285.71
JUMLAH TENAGA KERJA 73,214.29
B. BAHAN
Sumur Resapan ( Buist beton + galian ) unit 1.000 1,750,000.00 1,750,000.00
JUMLAH HARGA BAHAN 1,750,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 1,823,214.29


E. Overhead & Profit 10% 182,321.43
F. Harga Satuan Pembantu Tukangan (D+E) 2,005,535.71

Memasang 1 bh pompa diesel (pemadam kebakaran) kap. 1890 lpm (500 gpm) ; Head 105 m
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 85,000.00 127,500.00
Tukang L.02 OH 1.500 90,000.00 135,000.00
Kepala tukang L.03 OH 1.000 95,000.00 95,000.00
Mandor L.04 OH 0.500 100,000.00 50,000.00
JUMLAH TENAGA KERJA 407,500.00
B. BAHAN
Diesel Fire Pump, kapasitas : 1890 lpm / 105 meter set 1.000 65,000,000.00 65,000,000.00
JUMLAH HARGA BAHAN 65,000,000.00
C. PERALATAN
Perlengkapan ( Dudukan pompa & penahan getaran ) bh 1.000 162,500.00 162,500.00
JUMLAH HARGA PERALATAN 162,500.00

D. Jumlah (A+B+C) 65,570,000.00


E. Overhead & Profit 10% 6,557,000.00
F. Harga Satuan Pembantu Tukangan (D+E) 72,127,000.00

Memasang 1 bh pompa elektrik (pemadam kebakaran) kap. 1890 lpm (500 gpm) ; Head 105 m
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 85,000.00 127,500.00
Tukang L.02 OH 1.500 90,000.00 135,000.00
Kepala tukang L.03 OH 1.000 95,000.00 95,000.00
Mandor L.04 OH 0.500 100,000.00 50,000.00
JUMLAH TENAGA KERJA 407,500.00
B. BAHAN
Electric Fire Pump, kapasitas : 500 Gpm / 105 meter set 1.000 17,500,000.00 17,500,000.00
JUMLAH HARGA BAHAN 17,500,000.00
C. PERALATAN
Perlengkapan ( Dudukan pompa & penahan getaran ) bh 1.000 43,750.00 43,750.00
JUMLAH HARGA PERALATAN 43,750.00

D. Jumlah (A+B+C) 17,951,250.00


E. Overhead & Profit 10% 1,795,125.00
F. Harga Satuan Pembantu Tukangan (D+E) 19,746,375.00

Memasang 1 bh jockey pump (pemadam kebakaran) kapasitas 37 lpm (10 gpm) ; Head 112 meter
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.571 85,000.00 48,571.43
Tukang L.02 OH 0.571 90,000.00 51,428.57
Kepala tukang L.03 OH 0.107 95,000.00 10,178.57
Mandor L.04 OH 0.071 100,000.00 7,142.86
JUMLAH TENAGA KERJA 117,321.43
B. BAHAN
Jockey Fire Pump, kapasitas : 30 Lpm / 112 meter bh 1.000 17,500,000.00 17,500,000.00
JUMLAH HARGA BAHAN 17,500,000.00
C. PERALATAN
Perlengkapan ( Dudukan pompa & penahan getaran ) bh 1.000 35,000.00 35,000.00
JUMLAH HARGA PERALATAN 35,000.00

D. Jumlah (A+B+C) 17,652,321.43


E. Overhead & Profit 10% 1,765,232.14
F. Harga Satuan Pembantu Tukangan (D+E) 19,417,553.57

1 bh Horn Buzzer
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.179 85,000.00 15,178.57
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 29,767.86
B. BAHAN
Horn / Buzzer bh 1.000 55,000.00 55,000.00
JUMLAH HARGA BAHAN 55,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 84,767.86


E. Overhead & Profit 10% 8,476.79
F. Harga Satuan Pekerjaan (D+E) 93,244.64

Memasang 1 bh Flexible Joint 16K dia. 4" (100 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.107 85,000.00 9,107.14
Tukang L.02 OH 0.107 90,000.00 9,642.86
Kepala tukang L.03 OH 0.010 95,000.00 950.00
Mandor L.04 OH 0.002 100,000.00 180.00
JUMLAH TENAGA KERJA 19,880.00
B. BAHAN
Flexible Joint kelas 16/20K dia. 100 mm bh 1.000 1,500,000.00 1,500,000.00
JUMLAH HARGA BAHAN 1,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 1,519,880.00


E. Overhead & Profit 10% 151,988.00
F. Harga Satuan Pembantu Tukangan (D+E) 1,671,868.00

Memasang 1 bh Flexible Joint 16K dia. 1" ( 25 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 85,000.00 6,800.00
Tukang L.02 OH 0.080 90,000.00 7,200.00
Kepala tukang L.03 OH 0.010 95,000.00 950.00
Mandor L.04 OH 0.002 100,000.00 180.00
JUMLAH TENAGA KERJA 15,130.00
B. BAHAN
Flexible Joint 16/20 K dia. dia. 25 mm bh 1.000 950,000.00 950,000.00
JUMLAH HARGA BAHAN 950,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN
D. Jumlah (A+B+C) 965,130.00
E. Overhead & Profit 10% 96,513.00
F. Harga Satuan Pembantu Tukangan (D+E) 1,061,643.00

Memasang 1 bh Check valve 16K dia. 4" (100 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.179 85,000.00 15,178.57
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 29,767.86
B. BAHAN
Check valve kelas 16/20K dia. 100 mm bh 1.000 4,500,000.00 4,500,000.00
JUMLAH HARGA BAHAN 4,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 4,529,767.86


E. Overhead & Profit 10% 452,976.79
F. Harga Satuan Pembantu Tukangan (D+E) 4,982,744.64

Memasang 1 bh Check valve 16K dia. 1" (25 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 85,000.00 6,800.00
Tukang L.02 OH 0.080 90,000.00 7,200.00
Kepala tukang L.03 OH 0.010 95,000.00 950.00
Mandor L.04 OH 0.002 100,000.00 180.00
JUMLAH TENAGA KERJA 15,130.00
B. BAHAN
Check valve 10 K dia. 25 mm bh 1.000 2,500,000.00 2,500,000.00
JUMLAH HARGA BAHAN 2,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 2,515,130.00


E. Overhead & Profit 10% 251,513.00
F. Harga Satuan Pembantu Tukangan (D+E) 2,766,643.00

Memasang 1 bh Gate valve 16K 6" (150 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 #N/A 0.179 85,000.00 15,178.57
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 29,767.86
B. BAHAN
Gate valve kelas 16/20K dia. 150 mm bh 1.000 12,500,000.00 12,500,000.00
JUMLAH HARGA BAHAN 12,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 12,529,767.86


E. Overhead & Profit 10% 1,252,976.79
F. Harga Satuan Pembantu Tukangan (D+E) 13,782,744.64

Memasang 1 bh Gate valve 16K 4" (100 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
NO URAIAN KODE SATUAN KOEFISIEN
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.179 85,000.00 15,178.57
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 29,767.86
B. BAHAN
Gate valve kelas 16/20K dia. 100 mm bh 1.000 14,500,000.00 14,500,000.00
JUMLAH HARGA BAHAN 14,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 14,529,767.86


E. Overhead & Profit 10% 1,452,976.79
F. Harga Satuan Pembantu Tukangan (D+E) 15,982,744.64

Memasang 1 bh Gate valve 16K dia. 2 1/2" (65 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 85,000.00 6,800.00
Tukang L.02 OH 0.080 90,000.00 7,200.00
Kepala tukang L.03 OH 0.010 95,000.00 950.00
Mandor L.04 OH 0.002 100,000.00 180.00
JUMLAH TENAGA KERJA 15,130.00
B. BAHAN
Gate valve kelas 16/20K dia. 65 mm bh 1.000 17,500,000.00 17,500,000.00
JUMLAH HARGA BAHAN 17,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 17,515,130.00


E. Overhead & Profit 10% 1,751,513.00
F. Harga Satuan Pembantu Tukangan (D+E) 19,266,643.00

Memasang 1 bh Safety Relief Valve dia. 100 mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.179 85,000.00 15,178.57
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 29,767.86
B. BAHAN
Safety Valve Dia. 100 mm bh 1.000 500,000.00 500,000.00
JUMLAH HARGA BAHAN 500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 529,767.86


E. Overhead & Profit 10% 52,976.79
F. Harga Satuan Pembantu Tukangan (D+E) 582,744.64

Memasang 1 bh Alarm Check Valve


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.179 85,000.00 15,178.57
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.011 95,000.00 1,017.86
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 29,767.86
B. BAHAN
Alarm Check Valve bh 1.000 2,500,000.00 2,500,000.00
JUMLAH HARGA BAHAN 2,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 2,529,767.86


E. Overhead & Profit 10% 252,976.79
F. Harga Satuan Pembantu Tukangan (D+E) 2,782,744.64

1 m' Pipa Header BSP sch. 40 ø 8"


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.429 95,000.00 40,714.29
Mandor L.04 OH 0.286 100,000.00 28,571.43
JUMLAH TENAGA KERJA 219,285.71
B. BAHAN
BSP SCH. Dia. 8” m1 2.500 600,000.00 1,500,000.00
Sambungan m1 1.000 150,000.00 150,000.00
JUMLAH HARGA BAHAN 1,650,000.00
C. PERALATAN
Perlengkapan ( dudukan/ penunpu, dll ) ls 1.000 330,000.00 330,000.00
JUMLAH HARGA PERALATAN 330,000.00

D. Jumlah (A+B+C) 2,199,285.71


E. Overhead & Profit 10% 219,928.57
F. Harga Satuan Pekerjaan (D+E) 2,419,214.29

Memasang 1 m' pipa BSP sch. 40 ø 6" (150 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.057 85,000.00 4,857.14
Tukang L.02 OH 0.050 90,000.00 4,500.00
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 10,185.71
B. BAHAN
BSP SCH. Dia. 6” m1 1.000 608,333.33 608,333.33
Fitting & Sambungan m' 1.000 152,083.33 152,083.33
JUMLAH HARGA BAHAN 760,416.67
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 38,020.83 38,020.83
JUMLAH HARGA PERALATAN 38,020.83

D. Jumlah (A+B+C) 808,623.21


E. Overhead & Profit 10% 80,862.32
F. Harga Satuan Pembantu Tukangan (D+E) 889,485.54

Memasang 1 m' pipa BSP sch. 40 ø 4" (100 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.057 85,000.00 4,857.14
Tukang L.02 OH 0.050 90,000.00 4,500.00
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 10,185.71
B. BAHAN
BSP SCH. Dia. 4” m1 1.000 583,333.33 583,333.33
Fitting & Sambungan m' 1.000 145,833.33 145,833.33
JUMLAH HARGA BAHAN 729,166.67
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 36,458.33 36,458.33
JUMLAH HARGA PERALATAN 36,458.33

D. Jumlah (A+B+C) 775,810.71


E. Overhead & Profit 10% 77,581.07
F. Harga Satuan Pembantu Tukangan (D+E) 853,391.79

Memasang 1 m' pipa BSP sch. 40 ø 2,5" (65mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.057 85,000.00 4,857.14
Tukang L.02 OH 0.050 90,000.00 4,500.00
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 10,185.71
B. BAHAN
BSP SCH. 40 Dia. 2 1/2” m1 1.000 425,000.00 425,000.00
Fitting & Sambungan m' 1.000 106,250.00 106,250.00
JUMLAH HARGA BAHAN 531,250.00
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 26,562.50 26,562.50
JUMLAH HARGA PERALATAN 26,562.50

D. Jumlah (A+B+C) 567,998.21


E. Overhead & Profit 10% 56,799.82
F. Harga Satuan Pembantu Tukangan (D+E) 624,798.04

1 Titik Instalasi Elecric Fire Pump ( FRC 4 x 1 x 50 mm2 ) + BCC 35 mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang L.02 OH 0.150 90,000.00 13,500.00
Kepala tukang L.03 OH 0.100 95,000.00 9,500.00
Mandor L.04 OH 0.075 100,000.00 7,500.00
JUMLAH TENAGA KERJA 43,250.00
B. BAHAN
FRC 4C X 50 MM2 m1 10.000 25,000.00 250,000.00
BCC 35 mm m1 10.000 8,000.00 80,000.00
JUMLAH HARGA BAHAN 330,000.00
C. PERALATAN
Perlengkapan Instalasi ( tee doos, klamp, soket, fhiser, lasdop, dll ) ls 1.000 49,500.00 49,500.00
JUMLAH HARGA PERALATAN 49,500.00

D. Jumlah (A+B+C) 422,750.00


E. Overhead & Profit 10% 42,275.00
F. Harga Satuan Pekerjaan (D+E) 465,025.00

1 Titik Instalasi Jockey Fire Pump ( FRC 4 x 1 x 6 mm2 ) + BCC 6 mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang L.02 OH 0.150 90,000.00 13,500.00
Kepala tukang L.03 OH 0.100 95,000.00 9,500.00
Mandor L.04 OH 0.075 100,000.00 7,500.00
JUMLAH TENAGA KERJA 43,250.00
B. BAHAN
FRC 4C X 6 MM2 m1 10.000 17,000.00 170,000.00
BCC 6 mm m1 10.000 6,000.00 60,000.00
JUMLAH HARGA BAHAN 230,000.00
C. PERALATAN
Perlengkapan Instalasi ( tee doos, klamp, soket, fhiser, lasdop, dll ) ls 1.000 34,500.00 34,500.00
JUMLAH HARGA PERALATAN 34,500.00

D. Jumlah (A+B+C) 307,750.00


E. Overhead & Profit 10% 30,775.00
F. Harga Satuan Pekerjaan (D+E) 338,525.00

Memasang 1 m' pipa BSP sch. 40 ø 1" (25 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.029 85,000.00 2,428.57
Tukang L.02 OH 0.021 90,000.00 1,928.57
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 5,185.71
B. BAHAN
BSP SCH.40 Dia. 1” m1 1.000 366,666.67 366,666.67
Fitting & Sambungan m' 1.000 91,666.67 91,666.67
JUMLAH HARGA BAHAN 458,333.33
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 22,916.67 22,916.67
JUMLAH HARGA PERALATAN 22,916.67

D. Jumlah (A+B+C) 486,435.71


E. Overhead & Profit 10% 48,643.57
F. Harga Satuan Pembantu Tukangan (D+E) 535,079.29

Memasang 1 bh Hydran pillar 2 ways


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 85,000.00 34,000.00
Tukang L.02 OH 0.400 90,000.00 36,000.00
Kepala tukang L.03 OH 0.050 95,000.00 4,750.00
Mandor L.04 OH 0.050 100,000.00 5,000.00
JUMLAH TENAGA KERJA 79,750.00
B. BAHAN
Hydrant Pillar One Way 3 '' x 2,5 '' (H-13 ) + lengkap Hose Cabinet unit 1.000 3,500,000.00 3,500,000.00
JUMLAH HARGA BAHAN 3,500,000.00
C. PERALATAN
Perlengkapan ( pondasi, dll ) bh 1.000 175,000.00 175,000.00
JUMLAH HARGA PERALATAN 175,000.00

D. Jumlah (A+B+C) 3,754,750.00


E. Overhead & Profit 10% 375,475.00
F. Harga Satuan Pembantu Tukangan (D+E) 4,130,225.00

Memasang 1 bh Siamesse connection


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 85,000.00 34,000.00
Tukang L.02 OH 0.400 90,000.00 36,000.00
Kepala tukang L.03 OH 0.050 95,000.00 4,750.00
Mandor L.04 OH 0.050 100,000.00 5,000.00
JUMLAH TENAGA KERJA 79,750.00
B. BAHAN
Siammesse Connection - Type S - 7 ( 4 '' x 2,5 " x 2,5 '' ) unit 1.000 1,250,000.00 1,250,000.00
JUMLAH HARGA BAHAN 1,250,000.00
C. PERALATAN
Perlengkapan ( pondasi, dll ) bh 1.000 62,500.00 62,500.00
JUMLAH HARGA PERALATAN 62,500.00

D. Jumlah (A+B+C) 1,392,250.00


E. Overhead & Profit 10% 139,225.00
F. Harga Satuan Pembantu Tukangan (D+E) 1,531,475.00

Memasang 1 bh Landing Valve 16K 2 1/2 " (65 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 85,000.00 6,800.00
Tukang L.02 OH 0.080 90,000.00 7,200.00
Kepala tukang L.03 OH 0.010 95,000.00 950.00
Mandor L.04 OH 0.002 100,000.00 180.00
JUMLAH TENAGA KERJA 15,130.00
B. BAHAN
Butterfly valve dia. 65 mm bh 1.000 7,500,000.00 7,500,000.00
JUMLAH HARGA BAHAN 7,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 7,515,130.00


E. Overhead & Profit 10% 751,513.00
F. Harga Satuan Pembantu Tukangan (D+E) 8,266,643.00

Memasang 1 bh Fire Hose Cabinet (FHC), 125 x 75 x 18 cm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 85,000.00 34,000.00
Tukang L.02 OH 0.400 90,000.00 36,000.00
Kepala tukang L.03 OH 0.050 95,000.00 4,750.00
Mandor L.04 OH 0.050 100,000.00 5,000.00
JUMLAH TENAGA KERJA 79,750.00
B. BAHAN
In - Door Type B ( Uk. 125 x 75 x 18 ) cm lengkap bh 1.000 1,500,000.00 1,500,000.00
JUMLAH HARGA BAHAN 1,500,000.00
C. PERALATAN
Perlengkapan ( pondasi, dll ) bh 1.000 75,000.00 75,000.00
JUMLAH HARGA PERALATAN 75,000.00

D. Jumlah (A+B+C) 1,654,750.00


E. Overhead & Profit 10% 165,475.00
F. Harga Satuan Pembantu Tukangan (D+E) 1,820,225.00

Memasang 1 m' pipa BSP sch. 40 ø 1 1/2" (40 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.029 85,000.00 2,428.57
Tukang L.02 OH 0.021 90,000.00 1,928.57
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 5,185.71
B. BAHAN
BSP SCH.40 Dia. 1 1/2” m1 1.000 391,666.67 391,666.67
Fitting & sambungan m' 1.000 97,916.67 97,916.67
JUMLAH HARGA BAHAN 489,583.33
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 24,479.17 24,479.17
JUMLAH HARGA PERALATAN 24,479.17

D. Jumlah (A+B+C) 519,248.21


E. Overhead & Profit 10% 51,924.82
F. Harga Satuan Pembantu Tukangan (D+E) 571,173.04

Memasang 1 bh head Sprinkler 68 derajat


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.107 85,000.00 9,107.14
Tukang L.02 OH 0.107 90,000.00 9,642.86
Kepala tukang L.03 OH 0.020 95,000.00 1,900.00
Mandor L.04 OH 0.010 100,000.00 1,000.00
JUMLAH TENAGA KERJA 21,650.00
B. BAHAN
head Sprinkler 68 derajat unit 1.000 125,000.00 125,000.00
JUMLAH HARGA BAHAN 125,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 146,650.00


E. Overhead & Profit 10% 14,665.00
F. Harga Satuan Pembantu Tukangan (D+E) 161,315.00

Memasang 1 bh Plat Orifice


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.107 85,000.00 9,107.14
Tukang L.02 OH 0.107 90,000.00 9,642.86
Kepala tukang L.03 OH 0.020 95,000.00 1,900.00
Mandor L.04 OH 0.010 100,000.00 1,000.00
JUMLAH TENAGA KERJA 21,650.00
B. BAHAN
Pelat Orifice dia 100 mm bh 1.000 750,000.00 750,000.00
JUMLAH HARGA BAHAN 750,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 771,650.00


E. Overhead & Profit 10% 77,165.00
F. Harga Satuan Pembantu Tukangan (D+E) 848,815.00

Memasang 1 bh Plat Orifice


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.107 85,000.00 9,107.14
Tukang L.02 OH 0.107 90,000.00 9,642.86
Kepala tukang L.03 OH 0.020 95,000.00 1,900.00
Mandor L.04 OH 0.010 100,000.00 1,000.00
JUMLAH TENAGA KERJA 21,650.00
B. BAHAN
Pelat Orifice dia. 50 mm bh 1.000 650,000.00 650,000.00
JUMLAH HARGA BAHAN 650,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 671,650.00


E. Overhead & Profit 10% 67,165.00
F. Harga Satuan Pembantu Tukangan (D+E) 738,815.00

Memasang 1 bh Gate valve 16K dia. 2" (50 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 85,000.00 6,800.00
Tukang L.02 OH 0.080 90,000.00 7,200.00
Kepala tukang L.03 OH 0.010 95,000.00 950.00
Mandor L.04 OH 0.002 100,000.00 180.00
JUMLAH TENAGA KERJA 15,130.00
B. BAHAN
Gate valve 16 K dia. 50 mm bh 1.000 7,500,000.00 7,500,000.00
JUMLAH HARGA BAHAN 7,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 7,515,130.00


E. Overhead & Profit 10% 751,513.00
F. Harga Satuan Pembantu Tukangan (D+E) 8,266,643.00

Memasang 1 bh Sight Glass dia. 25 mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang L.02 OH 0.200 90,000.00 18,000.00
Kepala tukang L.03 OH 0.020 95,000.00 1,900.00
Mandor L.04 OH 0.020 100,000.00 2,000.00
JUMLAH TENAGA KERJA 38,900.00
B. BAHAN
Sight Glass diameter 25 mm bh 1.000 75,000.00 75,000.00
JUMLAH HARGA BAHAN 75,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 113,900.00


E. Overhead & Profit 10% 11,390.00
F. Harga Satuan Pembantu Tukangan (D+E) 125,290.00

Memasang 1 bh Flow Switch


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang L.02 OH 0.200 90,000.00 18,000.00
Kepala tukang L.03 OH 0.020 95,000.00 1,900.00
Mandor L.04 OH 0.020 100,000.00 2,000.00
JUMLAH TENAGA KERJA 38,900.00
B. BAHAN
Flow Switch bh 1.000 250,000.00 250,000.00
JUMLAH HARGA BAHAN 250,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 288,900.00


E. Overhead & Profit 10% 28,890.00
F. Harga Satuan Pembantu Tukangan (D+E) 317,790.00

Memasang 1 bh Pressure Gauge


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang L.02 OH 0.200 90,000.00 18,000.00
Kepala tukang L.03 OH 0.020 95,000.00 1,900.00
Mandor L.04 OH 0.020 100,000.00 2,000.00
JUMLAH TENAGA KERJA 38,900.00
B. BAHAN
Pressure Gauge bh 1.000 2,500,000.00 2,500,000.00
JUMLAH HARGA BAHAN 2,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 2,538,900.00


E. Overhead & Profit 10% 253,890.00
F. Harga Satuan Pembantu Tukangan (D+E) 2,792,790.00

Memasang 1 bh Temper Switch


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang L.02 OH 0.200 90,000.00 18,000.00
Kepala tukang L.03 OH 0.020 95,000.00 1,900.00
Mandor L.04 OH 0.020 100,000.00 2,000.00
JUMLAH TENAGA KERJA 38,900.00
B. BAHAN
temper Switch bh 1.000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 63,900.00


E. Overhead & Profit 10% 6,390.00
F. Harga Satuan Pembantu Tukangan (D+E) 70,290.00

Memasang 1 bh Gate valve 16K dia. 1 1/2" (40 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 85,000.00 6,800.00
Tukang L.02 OH 0.080 90,000.00 7,200.00
Kepala tukang L.03 OH 0.010 95,000.00 950.00
Mandor L.04 OH 0.002 100,000.00 180.00
JUMLAH TENAGA KERJA 15,130.00
B. BAHAN
Gate valve 16 K dia. 40 mm bh 1.000 6,500,000.00 6,500,000.00
JUMLAH HARGA BAHAN 6,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 6,515,130.00


E. Overhead & Profit 10% 651,513.00
F. Harga Satuan Pembantu Tukangan (D+E) 7,166,643.00

Memasang 1 bh Fire Extinguisher (Dry Chemical) 5 kG


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.020 95,000.00 1,900.00
Mandor L.04 OH 0.020 100,000.00 2,000.00
JUMLAH TENAGA KERJA 28,900.00
B. BAHAN
Fire Extinguisher type Dry Chemical kap. 5 kg unit 1.000 450,000.00 450,000.00
JUMLAH HARGA BAHAN 450,000.00
C. PERALATAN
Perlengkapan ( Bracket ) bh 1.000 22,500.00 22,500.00
JUMLAH HARGA PERALATAN 22,500.00

D. Jumlah (A+B+C) 501,400.00


E. Overhead & Profit 10% 50,140.00
F. Harga Satuan Pembantu Tukangan (D+E) 551,540.00

Memasang 1 bh Gate valve 16K dia. 1" (25 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 85,000.00 6,800.00
Tukang L.02 OH 0.080 90,000.00 7,200.00
Kepala tukang L.03 OH 0.010 95,000.00 950.00
Mandor L.04 OH 0.002 100,000.00 180.00
JUMLAH TENAGA KERJA 15,130.00
B. BAHAN
Gate valve 150 PSI dia. dia. 25 mm bh 1.000 10,500,000.00 10,500,000.00
JUMLAH HARGA BAHAN 10,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 10,515,130.00


E. Overhead & Profit 10% 1,051,513.00
F. Harga Satuan Pembantu Tukangan (D+E) 11,566,643.00

Memasang 1 m' pipa BSP sch. 40 ø 3" (80 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.029 85,000.00 2,428.57
Tukang L.02 OH 0.021 90,000.00 1,928.57
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 5,185.71
B. BAHAN
BSP SCH. 40 Dia. 3” m1 1.000 458,333.33 458,333.33
Fitting & sambungan m1 1.000 114,583.33 114,583.33
JUMLAH HARGA BAHAN 572,916.67
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 28,645.83 28,645.83
JUMLAH HARGA PERALATAN 28,645.83

D. Jumlah (A+B+C) 606,748.21


E. Overhead & Profit 10% 60,674.82
F. Harga Satuan Pembantu Tukangan (D+E) 667,423.04

Memasang 1 m' pipa BSP sch. 40 ø 2"


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.029 85,000.00 2,428.57
Tukang L.02 OH 0.021 90,000.00 1,928.57
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 5,185.71
B. BAHAN
BSP SCH.40 Dia. 2” m1 1.000 416,666.67 416,666.67
Fitting & Sambungan m' 1.000 104,166.67 104,166.67
JUMLAH HARGA BAHAN 520,833.33
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 26,041.67 26,041.67
JUMLAH HARGA PERALATAN 26,041.67

D. Jumlah (A+B+C) 552,060.71


E. Overhead & Profit 10% 55,206.07
F. Harga Satuan Pembantu Tukangan (D+E) 607,266.79

Memasang 1 m' pipa BSP sch. 40 ø 1 1/4" (32 mm)


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.029 85,000.00 2,428.57
Tukang L.02 OH 0.021 90,000.00 1,928.57
Kepala tukang L.03 OH 0.006 95,000.00 542.86
Mandor L.04 OH 0.003 100,000.00 285.71
JUMLAH TENAGA KERJA 5,185.71
B. BAHAN
BSP SCH.40 Dia. 1 1/4” m1 1.000 383,333.33 383,333.33
Fitting & sambungan m' 1.000 95,833.33 95,833.33
JUMLAH HARGA BAHAN 479,166.67
C. PERALATAN
Perlengkapan ( hanger, Clamp, dll ) bh 1.000 23,958.33 23,958.33
JUMLAH HARGA PERALATAN 23,958.33

D. Jumlah (A+B+C) 508,310.71


E. Overhead & Profit 10% 50,831.07
F. Harga Satuan Pembantu Tukangan (D+E) 559,141.79

Memasang 1 Unit OU + IU, Kapasitas : 7600 Btuh/h - Wall Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.107 100,000.00 10,714.29
JUMLAH TENAGA KERJA 174,285.71
B. BAHAN
OU + IU, Kapasitas : 7600 Btuh/h - Wall Type unit 1.000 4,250,000.00 4,250,000.00
JUMLAH HARGA BAHAN 4,250,000.00
C. PERALATAN
Perlengkapan ( perkuatan ) bh 1.000 106,250.00 106,250.00
JUMLAH HARGA PERALATAN 106,250.00

D. Jumlah (A+B+C) 4,530,535.71


E. Overhead & Profit 10% 453,053.57
F. Harga Satuan Pembantu Tukangan (D+E) 4,983,589.29

Memasang 1 Unit OU + IU, Kapasitas : 42000 Btuh/h - Cassete Type (multy flow)
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 42000 Btuh/h - Cassete Type (multy flow) unit 1.000 45,000,000.00 45,000,000.00
JUMLAH HARGA BAHAN 45,000,000.00
C. PERALATAN
Perlengkapan ( Dudukan & Perkuatan ) bh 1.000 1,125,000.00 1,125,000.00
JUMLAH HARGA PERALATAN 1,125,000.00

D. Jumlah (A+B+C) 46,414,285.71


E. Overhead & Profit 10% 4,641,428.57
F. Harga Satuan Pembantu Tukangan (D+E) 51,055,714.29

Memasang 1 Unit OU + IU, Kapasitas : 45000 Btuh/h - Cassete Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 45000 Btuh/h - Cassete Type unit 1.000 42,500,000.00 42,500,000.00
JUMLAH HARGA BAHAN 42,500,000.00
C. PERALATAN
Perlengkapan ( Dudukan & Perkuatan ) bh 1.000 1,062,500.00 1,062,500.00
JUMLAH HARGA PERALATAN 1,062,500.00

D. Jumlah (A+B+C) 43,851,785.71


E. Overhead & Profit 10% 4,385,178.57
F. Harga Satuan Pembantu Tukangan (D+E) 48,236,964.29

Memasang 1 Unit OU + IU, Kapasitas : 18000 Btuh/h - Wall Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 18000 Btuh/h - Wall Type Unit 1.000 6,500,000.00 6,500,000.00
JUMLAH HARGA BAHAN 6,500,000.00
C. PERALATAN
Perlengkapan ( Dudukan & Perkuatan ) bh 1.000 162,500.00 162,500.00
JUMLAH HARGA PERALATAN 162,500.00

D. Jumlah (A+B+C) 6,951,785.71


E. Overhead & Profit 10% 695,178.57
F. Harga Satuan Pembantu Tukangan (D+E) 7,646,964.29

Memasang 1 bh Exhaust Fan 850 Cfm ESP. 0,6 inwg - Axial Inline Fan
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang L.02 OH 0.200 90,000.00 18,000.00
Kepala tukang L.03 OH 0.350 95,000.00 33,250.00
Mandor L.04 OH 0.350 100,000.00 35,000.00
JUMLAH TENAGA KERJA 103,250.00
B. BAHAN
Exhaust Fan, kap.850 Cfm - Axial/Inline fan unit 1.000 950,000.00 950,000.00
JUMLAH HARGA BAHAN 950,000.00
C. PERALATAN
Perlengkapan ( dudukan ) bh 1.000 19,000.00 19,000.00
JUMLAH HARGA PERALATAN 19,000.00

D. Jumlah (A+B+C) 1,072,250.00


E. Overhead & Profit 10% 107,225.00
F. Harga Satuan Pembantu Tukangan (D+E) 1,179,475.00

Memasang 1 Unit OU + IU, Kapasitas : 22500 Btuh/h - Cassete Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 22500 Btuh/h - Cassete Type unit 1.000 22,500,000.00 22,500,000.00
JUMLAH HARGA BAHAN 22,500,000.00
C. PERALATAN
Perlengkapan ( Dudukan & Perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 22,889,285.71


E. Overhead & Profit 10% 2,288,928.57
F. Harga Satuan Pembantu Tukangan (D+E) 25,178,214.29

Memasang 1 Unit OU + IU, Kapasitas : 22500 Btuh/h - Wall Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 22500 Btuh/h - Wall Type Unit 1.000 10,500,000.00 10,500,000.00
JUMLAH HARGA BAHAN 10,500,000.00
C. PERALATAN
Perlengkapan ( Dudukan & Perkuatan ) bh 1.000 75,000.00 75,000.00
JUMLAH HARGA PERALATAN 75,000.00

D. Jumlah (A+B+C) 10,864,285.71


E. Overhead & Profit 10% 1,086,428.57
F. Harga Satuan Pembantu Tukangan (D+E) 11,950,714.29

Memasang 1 Unit OU + IU, Kapasitas : 25600 Btuh/h - Cassete Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 25600 Btuh/h - Cassete Type unit 1.000 22,500,000.00 22,500,000.00
JUMLAH HARGA BAHAN 22,500,000.00
C. PERALATAN
Perlengkapan ( Dudukan & Perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 22,889,285.71


E. Overhead & Profit 10% 2,288,928.57
F. Harga Satuan Pembantu Tukangan (D+E) 25,178,214.29

Memasang 1 Unit OU + IU, Kapasitas : 14500 Btuh/h - Cassete Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 14500 Btuh/h - Cassete Type unit 1.000 22,500,000.00 22,500,000.00
JUMLAH HARGA BAHAN 22,500,000.00
C. PERALATAN
Perlengkapan ( Dudukan & Perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 22,889,285.71


E. Overhead & Profit 10% 2,288,928.57
F. Harga Satuan Pembantu Tukangan (D+E) 25,178,214.29

Memasang 1 Unit OU + IU, Kapasitas : 15000 Btuh/h - Cassete Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 15000 Btuh/h - Cassete Type unit 1.000 25,000,000.00 25,000,000.00
JUMLAH HARGA BAHAN 25,000,000.00
C. PERALATAN
Perlengkapan ( Dudukan & Perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 25,389,285.71


E. Overhead & Profit 10% 2,538,928.57
F. Harga Satuan Pembantu Tukangan (D+E) 27,928,214.29

Memasang 1 Unit OU + IU, Kapasitas : 29000 Btuh/h - Cassete Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 29000 Btuh/h - Cassete Type unit 1.000 22,500,000.00 22,500,000.00
JUMLAH HARGA BAHAN 22,500,000.00
C. PERALATAN
Perlengkapan ( Dudukan & Perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 22,889,285.71


E. Overhead & Profit 10% 2,288,928.57
F. Harga Satuan Pembantu Tukangan (D+E) 25,178,214.29

Memasang 1 Unit OU + IU, Kapasitas : 7600 Btuh/h - Wall Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.107 100,000.00 10,714.29
JUMLAH TENAGA KERJA 174,285.71
B. BAHAN
OU + IU, Kapasitas : 7600 Btuh/h - Wall Type unit 1.000 4,250,000.00 4,250,000.00
JUMLAH HARGA BAHAN 4,250,000.00
C. PERALATAN
Perlengkapan ( perkuatan ) bh 1.000 106,250.00 106,250.00
JUMLAH HARGA PERALATAN 106,250.00
D. Jumlah (A+B+C) 4,530,535.71
E. Overhead & Profit 10% 453,053.57
F. Harga Satuan Pembantu Tukangan (D+E) 4,983,589.29

Memasang 1 Unit OU + IU, Kapasitas : 10500 Btuh/h - Wall Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.107 100,000.00 10,714.29
JUMLAH TENAGA KERJA 174,285.71
B. BAHAN
OU + IU, Kapasitas : 10500 Btuh/h - Wall Type unit 1.000 5,000,000.00 5,000,000.00
JUMLAH HARGA BAHAN 5,000,000.00
C. PERALATAN
Perlengkapan ( perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 5,274,285.71


E. Overhead & Profit 10% 527,428.57
F. Harga Satuan Pembantu Tukangan (D+E) 5,801,714.29

Memasang 1 Unit OU + IU, Kapasitas : 12000 Btuh/h - Wall Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.107 100,000.00 10,714.29
JUMLAH TENAGA KERJA 174,285.71
B. BAHAN
OU + IU, Kapasitas : 12000 Btuh/h - Wall Type unit 1.000 5,500,000.00 5,500,000.00
JUMLAH HARGA BAHAN 5,500,000.00
C. PERALATAN
Perlengkapan ( perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 5,774,285.71


E. Overhead & Profit 10% 577,428.57
F. Harga Satuan Pembantu Tukangan (D+E) 6,351,714.29

Memasang 1 Unit OU + IU, Kapasitas : 13600 Btuh/h - Wall Type


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.107 100,000.00 10,714.29
JUMLAH TENAGA KERJA 174,285.71
B. BAHAN
OU + IU, Kapasitas : 13600 Btuh/h - Wall Type unit 1.000 6,000,000.00 6,000,000.00
JUMLAH HARGA BAHAN 6,000,000.00
C. PERALATAN
Perlengkapan ( perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 6,274,285.71


E. Overhead & Profit 10% 627,428.57
F. Harga Satuan Pembantu Tukangan (D+E) 6,901,714.29
Memasang 1 Unit OU + IU, Kapasitas : 24000 Btuh/h - Cassete Type
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 24000 Btuh/h - Cassete Type unit 1.000 22,500,000.00 22,500,000.00
JUMLAH HARGA BAHAN 22,500,000.00
C. PERALATAN
Perlengkapan ( Dudukan & Perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 22,889,285.71


E. Overhead & Profit 10% 2,288,928.57
F. Harga Satuan Pembantu Tukangan (D+E) 25,178,214.29

Memasang 1 ttk Pengkabelan power AC


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 85,000.00 8,500.00
Tukang L.02 OH 0.100 90,000.00 9,000.00
Kepala tukang L.03 OH 0.075 95,000.00 7,125.00
Mandor L.04 OH 0.050 100,000.00 5,000.00
JUMLAH TENAGA KERJA 29,625.00
B. BAHAN
Kabel NYM 3 X 4 mm2 m1 14.000 22,000.00 308,000.00
JUMLAH HARGA BAHAN 308,000.00
C. PERALATAN
Perlengkapan Instalasi ( klamp, soket, fhiser, lasdop, dll ) ls 1.000 3,080.00 3,080.00
JUMLAH HARGA PERALATAN 3,080.00

D. Jumlah (A+B+C) 340,705.00


E. Overhead & Profit 10% 34,070.50
F. Harga Satuan Pembantu Tukangan (D+E) 374,775.50

Memasang titik instalasi DAYA U/ EXHAUST FAN


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 85,000.00 8,500.00
Tukang L.02 OH 0.100 90,000.00 9,000.00
Kepala tukang L.03 OH 0.075 95,000.00 7,125.00
Mandor L.04 OH 0.050 100,000.00 5,000.00
JUMLAH TENAGA KERJA 29,625.00
B. BAHAN
NYM 3 x 2,5 MM2 m1 14.000 17,000.00 238,000.00
JUMLAH HARGA BAHAN 238,000.00
C. PERALATAN
Perlengkapan Instalasi ( klamp, soket, fhiser, lasdop, dll ) ls 1.000 2,380.00 2,380.00
JUMLAH HARGA PERALATAN 2,380.00

D. Jumlah (A+B+C) 270,005.00


E. Overhead & Profit 10% 27,000.50
F. Harga Satuan Pembantu Tukangan (D+E) 297,005.50

Memasang 1 bh Exhaust Fan 900 Cfm ESP. 0,6 inwg - Axial Inline Fan
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
NO URAIAN KODE SATUAN KOEFISIEN
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang L.02 OH 0.200 90,000.00 18,000.00
Kepala tukang L.03 OH 0.350 95,000.00 33,250.00
Mandor L.04 OH 0.350 100,000.00 35,000.00
JUMLAH TENAGA KERJA 103,250.00
B. BAHAN
Exhaust Fan kapasitas 900 CFM / 0,6 InWg/ Axial-Inline Fan unit 1.000 1,250,000.00 1,250,000.00
JUMLAH HARGA BAHAN 1,250,000.00
C. PERALATAN
Perlengkapan ( dudukan ) bh 1.000 31,250.00 31,250.00
JUMLAH HARGA PERALATAN 31,250.00

D. Jumlah (A+B+C) 1,384,500.00


E. Overhead & Profit 10% 138,450.00
F. Harga Satuan Pembantu Tukangan (D+E) 1,522,950.00

Memasang 1 bh Exhaust Fan, kap. 150 Cfm - Wall Fan


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang L.02 OH 0.200 90,000.00 18,000.00
Kepala tukang L.03 OH 0.350 95,000.00 33,250.00
Mandor L.04 OH 0.350 100,000.00 35,000.00
JUMLAH TENAGA KERJA 103,250.00
B. BAHAN
Exhaust Fan, kap.150 Cfm - Wall Fan unit 1.000 750,000.00 750,000.00
JUMLAH HARGA BAHAN 750,000.00
C. PERALATAN
Perlengkapan ( dudukan ) bh 1.000 18,750.00 18,750.00
JUMLAH HARGA PERALATAN 18,750.00

D. Jumlah (A+B+C) 872,000.00


E. Overhead & Profit 10% 87,200.00
F. Harga Satuan Pembantu Tukangan (D+E) 959,200.00

Memasang 1 M Ducting Exhaust ( 6 " x 6 " ), BJLS 60, tanpa isolasi


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.286 85,000.00 24,285.71
Tukang L.02 OH 0.286 90,000.00 25,714.29
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.107 100,000.00 10,714.29
JUMLAH TENAGA KERJA 74,285.71
B. BAHAN
BJLS 60 ( 6 " x 6 " ) m1 0.800 25,000.00 20,000.00
JUMLAH HARGA BAHAN 20,000.00
C. PERALATAN
Perlengkapan ( penggantung ) ls 0.500 1,500.00 750.00
JUMLAH HARGA PERALATAN 750.00

D. Jumlah (A+B+C) 95,035.71


E. Overhead & Profit 10% 9,503.57
F. Harga Satuan Pembantu Tukangan (D+E) 104,539.29

Memasang 1 M Ducting Exhaust ( 8" x 6" ), BJLS 60, tanpa isolasi


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.286 85,000.00 24,285.71
Tukang L.02 OH 0.286 90,000.00 25,714.29
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.143 100,000.00 14,285.71
JUMLAH TENAGA KERJA 77,857.14
B. BAHAN
BJLS 60 (8" x 6" ) m1 0.900 35,000.00 31,500.00
JUMLAH HARGA BAHAN 31,500.00
C. PERALATAN
Perlengkapan ( penggantung ) ls 0.500 1,500.00 750.00
JUMLAH HARGA PERALATAN 750.00

D. Jumlah (A+B+C) 110,107.14


E. Overhead & Profit 10% 11,010.71
F. Harga Satuan Pembantu Tukangan (D+E) 121,117.86

Memasang 1 M Ducting Exhaust ( 8" x 8" ), BJLS 60, tanpa isolasi


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.286 85,000.00 24,285.71
Tukang L.02 OH 0.286 90,000.00 25,714.29
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.143 100,000.00 14,285.71
JUMLAH TENAGA KERJA 77,857.14
B. BAHAN
BJLS 60 ( 8" x 8" ) m1 1.000 45,000.00 45,000.00
JUMLAH HARGA BAHAN 45,000.00
C. PERALATAN
Perlengkapan ( penggantung ) ls 0.500 1,500.00 750.00
JUMLAH HARGA PERALATAN 750.00

D. Jumlah (A+B+C) 123,607.14


E. Overhead & Profit 10% 12,360.71
F. Harga Satuan Pembantu Tukangan (D+E) 135,967.86

Memasang 1 M Ducting Exhaust ( 12" x 10" ), BJLS 60, tanpa isolasi


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.286 85,000.00 24,285.71
Tukang L.02 OH 0.286 90,000.00 25,714.29
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.143 100,000.00 14,285.71
JUMLAH TENAGA KERJA 77,857.14
B. BAHAN
BJLS 60 ( 12 " x 10 " ) m1 1.300 55,000.00 71,500.00
JUMLAH HARGA BAHAN 71,500.00
C. PERALATAN
Perlengkapan ( penggantung ) ls 0.500 1,500.00 750.00
JUMLAH HARGA PERALATAN 750.00

D. Jumlah (A+B+C) 150,107.14


E. Overhead & Profit 10% 15,010.71
F. Harga Satuan Pembantu Tukangan (D+E) 165,117.86

Memasang 1 M Ducting Exhaust ( 16" x 10" ), BJLS 60, tanpa isolasi


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.286 85,000.00 24,285.71
Tukang L.02 OH 0.286 90,000.00 25,714.29
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.143 100,000.00 14,285.71
JUMLAH TENAGA KERJA 77,857.14
B. BAHAN
BJLS 60 ( 16 " x 10 " ) m1 1.500 65,000.00 97,500.00
JUMLAH HARGA BAHAN 97,500.00
C. PERALATAN
Perlengkapan ( penggantung ) ls 0.500 1,500.00 750.00
JUMLAH HARGA PERALATAN 750.00

D. Jumlah (A+B+C) 176,107.14


E. Overhead & Profit 10% 17,610.71
F. Harga Satuan Pembantu Tukangan (D+E) 193,717.86

Memasang Exhaust Air Grille uk. 8" x 8 "


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.036 95,000.00 3,392.86
Mandor L.04 OH 0.014 100,000.00 1,428.57
JUMLAH TENAGA KERJA 29,821.43
B. BAHAN
Exhaust Air Grille uk. 8" x8" bh 1.000 275,000.00 275,000.00
JUMLAH HARGA BAHAN 275,000.00
C. PERALATAN

JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 304,821.43


E. Overhead & Profit 10% 30,482.14
F. Harga Satuan Pembantu Tukangan (D+E) 335,303.57

Memasang Exhaust Air Grille uk. 22" x 14"


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.143 85,000.00 12,142.86
Tukang L.02 OH 0.143 90,000.00 12,857.14
Kepala tukang L.03 OH 0.036 95,000.00 3,392.86
Mandor L.04 OH 0.014 100,000.00 1,428.57
JUMLAH TENAGA KERJA 29,821.43
B. BAHAN
Exhaust Air Grille uk. 22" x 14 " bh 1.000 450,000.00 450,000.00
JUMLAH HARGA BAHAN 450,000.00
C. PERALATAN

JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 479,821.43


E. Overhead & Profit 10% 47,982.14
F. Harga Satuan Pembantu Tukangan (D+E) 527,803.57

Memasang Pipa drain, PVC dia. 20 mm + Isolasi+ Isolasi


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 85,000.00 4,590.00
Tukang L.02 OH 0.090 90,000.00 8,100.00
Kepala tukang L.03 OH 0.009 95,000.00 855.00
Mandor L.04 OH 0.027 100,000.00 2,700.00
JUMLAH TENAGA KERJA 16,245.00
B. BAHAN
Pipa drain, PVC dia. 20 mm + Isolasi m1 1.000 12,500.00 12,500.00
JUMLAH HARGA BAHAN 12,500.00

C. PERALATAN
Perlengkapan ( clamp, penggantung ) m' 1.000 125.00 125.00
JUMLAH HARGA PERALATAN 125.00

D. Jumlah (A+B+C) 28,870.00


E. Overhead & Profit 10% 2,887.00
F. Harga Satuan Pembantu Tukangan (D+E) 31,757.00

Memasang 1 meter Pipa Refrigerant, Ø 9,5 mm + Ø 19,5 mm + Isolasi EPDM


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 85,000.00 4,590.00
Tukang L.02 OH 0.090 90,000.00 8,100.00
Kepala tukang L.03 OH 0.009 95,000.00 855.00
Mandor L.04 OH 0.027 100,000.00 2,700.00
JUMLAH TENAGA KERJA 16,245.00
B. BAHAN
Pipa Refrigerant, Ø 9,5 mm + Ø 19,5 mm + Isolasi EPDM m1 1.000 81,034.48 81,034.48
JUMLAH HARGA BAHAN 81,034.48
C. PERALATAN
Perlengkapan ( clamp, penggantung ) m' 1.000 810.34 810.34
JUMLAH HARGA PERALATAN 810.34

D. Jumlah (A+B+C) 98,089.83


E. Overhead & Profit 10% 9,808.98
F. Harga Satuan Pembantu Tukangan (D+E) 107,898.81

Memasang 1 Unit AC Single Split Wall Mounted (inverter) kapasitas 4500 Btuh
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.107 100,000.00 10,714.29
JUMLAH TENAGA KERJA 174,285.71
B. BAHAN
OU + IU, Kapasitas : 4500 Btuh/h - Wall Type unit 1.000 4,250,000.00 4,250,000.00
JUMLAH HARGA BAHAN 4,250,000.00
C. PERALATAN
Perlengkapan ( perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 4,524,285.71


E. Overhead & Profit 10% 452,428.57
F. Harga Satuan Pembantu Tukangan (D+E) 4,976,714.29

Memasang 1 Unit AC Single Split Wall Mounted (inverter) kapasitas 9000 Btuh
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.143 95,000.00 13,571.43
Mandor L.04 OH 0.107 100,000.00 10,714.29
JUMLAH TENAGA KERJA 174,285.71
B. BAHAN
OU + IU, Kapasitas : 9000 Btuh/h - Wall Type unit 1.000 4,250,000.00 4,250,000.00
JUMLAH HARGA BAHAN 4,250,000.00
C. PERALATAN
Perlengkapan ( dudukan & perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 4,524,285.71


E. Overhead & Profit 10% 452,428.57
F. Harga Satuan Pembantu Tukangan (D+E) 4,976,714.29

Memasang 1 Unit AC Single Split Compact Cassete Type (Inverter) kapasitas 32000 Btuh
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 32000 Btuh/h - Cassete Type unit 1.000 22,500,000.00 22,500,000.00
JUMLAH HARGA BAHAN 22,500,000.00
C. PERALATAN
Perlengkapan ( Dudukan & Perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 22,889,285.71


E. Overhead & Profit 10% 2,288,928.57
F. Harga Satuan Pembantu Tukangan (D+E) 25,178,214.29

Memasang 1 Unit AC Single Split Cassete Double Flow / 2 Flow Side Type (Inverter) kapasitas 20000 Btuh
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 20000 Btuh/h - Cassete Type unit 1.000 22,500,000.00 22,500,000.00
JUMLAH HARGA BAHAN 22,500,000.00
C. PERALATAN
Perlengkapan ( dudukan & Perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 22,889,285.71


E. Overhead & Profit 10% 2,288,928.57
F. Harga Satuan Pembantu Tukangan (D+E) 25,178,214.29

Memasang 1 Unit AC Single Split Cassete Double Flow / 2 Flow Side Type (Inverter) kapasitas 21000 Btuh
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.857 85,000.00 72,857.14
Tukang L.02 OH 0.857 90,000.00 77,142.86
Kepala tukang L.03 OH 0.714 95,000.00 67,857.14
Mandor L.04 OH 0.714 100,000.00 71,428.57
JUMLAH TENAGA KERJA 289,285.71
B. BAHAN
OU + IU, Kapasitas : 21000 Btuh/h - Cassete Type unit 1.000 20,500,000.00 20,500,000.00
JUMLAH HARGA BAHAN 20,500,000.00
C. PERALATAN
Perlengkapan ( dudukan & Perkuatan ) bh 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 20,889,285.71


E. Overhead & Profit 10% 2,088,928.57
F. Harga Satuan Pembantu Tukangan (D+E) 22,978,214.29

1 Unit Lift ( 15 Passanggers /60 Mpm / 5 Lantai )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
JUMLAH TENAGA KERJA
B. BAHAN
Lift Pasanggers (type ACRA-PA15(1150)-CO60-4/4 ) unit 1.000 625,000,000.00 625,000,000.00
ARD unit 1.000 25,000,000.00 25,000,000.00
Ongkos pasang, perijinan dan interior unit 1.000 10,000,000.00 10,000,000.00

JUMLAH HARGA BAHAN


C. PERALATAN
Perlengkapan Instalasi unit 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 660,100,000.00


E. Overhead & Profit 10% 66,010,000.00
F. Harga Satuan Pekerjaan (D+E) 726,110,000.00

1 unit Panel MVMDP


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.000 85,000.00 170,000.00
Tukang L.02 OH 2.000 90,000.00 180,000.00
Kepala tukang L.03 OH 1.000 95,000.00 95,000.00
Mandor L.04 OH 1.000 100,000.00 100,000.00
JUMLAH TENAGA KERJA 545,000.00
B. BAHAN
Cubicle Incoming unit 1.000 36,000,000.00 36,000,000.00
Cubiclr Areester unit 1.000 10,500,000.00 10,500,000.00
Cubicle Outgoing unit 1.000 52,000,000.00 52,000,000.00
JUMLAH HARGA BAHAN 98,500,000.00
C. PERALATAN
Perlengkapan ( kabel skun, VDE, dll ) ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 99,145,000.00


E. Overhead & Profit 10% 9,914,500.00
F. Harga Satuan Pekerjaan (D+E) 109,059,500.00

1 unit Trafo kapasitas : 500 kVA


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 85,000.00 85,000.00
Tukang L.02 OH 1.000 90,000.00 90,000.00
Kepala tukang L.03 OH 0.750 95,000.00 71,250.00
Mandor L.04 OH 0.500 100,000.00 50,000.00
JUMLAH TENAGA KERJA 296,250.00
B. BAHAN
Trafo, kap. 500 kVA unit 1.000 7,500,000.00 7,500,000.00
JUMLAH HARGA BAHAN 7,500,000.00
C. PERALATAN
Perlengkapan ( kabel skun, VDE, dll ) ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 7,896,250.00


E. Overhead & Profit 10% 789,625.00
F. Harga Satuan Pekerjaan (D+E) 8,685,875.00

1 unit Capasitor Bank 120 kVAR


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 85,000.00 85,000.00
Tukang L.02 OH 1.000 90,000.00 90,000.00
Kepala tukang L.03 OH 0.750 95,000.00 71,250.00
Mandor L.04 OH 0.500 100,000.00 50,000.00
JUMLAH TENAGA KERJA 296,250.00
B. BAHAN
Capasitor Bank 120 kVAR unit 1.000 7,500,000.00 7,500,000.00
JUMLAH HARGA BAHAN 7,500,000.00
C. PERALATAN
Perlengkapan ( kabel skun, VDE, dll ) ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 7,896,250.00


E. Overhead & Profit 10% 789,625.00
F. Harga Satuan Pekerjaan (D+E) 8,685,875.00

1 unit Panel LVMDP


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.000 85,000.00 170,000.00
Tukang L.02 OH 2.000 90,000.00 180,000.00
Kepala tukang L.03 OH 1.000 95,000.00 95,000.00
Mandor L.04 OH 1.000 100,000.00 100,000.00
JUMLAH TENAGA KERJA 545,000.00
B. BAHAN
MCCB, 800 A / 4p/35 KA bh 2.000 850,000.00 1,700,000.00
MCCB, 350 - 630 A / 3p/25 KA bh 1.000 950,000.00 950,000.00
MCCB, 175 - 250 A / 32 KA bh 1.000 1,050,000.00 1,050,000.00
MCCB, 80 - 160 A / 22 KA bh 1.000 950,000.00 950,000.00
Motorized for MCCB' bh 1.000 4,000,000.00 4,000,000.00
Interlock bh 1.000 750,000.00 750,000.00
Arresster + MCB 25A/3p-w/25kA set 1.000 175,000.00 175,000.00
Digital power Meter bh 1.000 1,000,000.00 1,000,000.00
Pilot Lamp bh 2.000 125,000.00 250,000.00
Puse Carrier 4 A bh 2.000 500.00 1,000.00
CT 800/5A CT 70 bh 1.000 650,000.00 650,000.00
Box Panel ( 120 x 100 x 30 ) cm bh 2.000 3,750,000.00 7,500,000.00
Wiring bh 1.000 6,641,600.00 6,641,600.00
JUMLAH HARGA BAHAN 25,617,600.00
C. PERALATAN
Perlengkapan ( kabel skun, VDE, dll ) ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 26,262,600.00


E. Overhead & Profit 10% 2,626,260.00
F. Harga Satuan Pekerjaan (D+E) 28,888,860.00

1 unit Panel PP-Hydrant


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.450 85,000.00 38,250.00
Tukang L.02 OH 0.450 90,000.00 40,500.00
Kepala tukang L.03 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.250 100,000.00 25,000.00
JUMLAH TENAGA KERJA 127,500.00
B. BAHAN
MCCB, 125 - 160 A / 36 KA bh 1.000 1,800,000.00 1,800,000.00
MCCB, 80 - 160 A / 22 KA bh 1.000 950,000.00 950,000.00
MCB, 16 A / 3 PH/10KA bh 2.000 450,000.00 900,000.00
Pilot Lamp bh 3.000 125,000.00 375,000.00
Puse Carrier 4 A bh 3.000 500.00 1,500.00
Box Panel bh 1.000 3,500,000.00 3,500,000.00
Wiring bh 1.000 2,634,275.00 2,634,275.00
JUMLAH HARGA BAHAN 10,160,775.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 10,388,275.00


E. Overhead & Profit 10% 1,038,827.50
F. Harga Satuan Pekerjaan (D+E) 11,427,102.50

1 M' Kabel Power N2XSY 3 x 1c x 70 mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.166 85,000.00 14,110.00
Tukang L.02 OH 0.166 90,000.00 14,940.00
Kepala tukang L.03 OH 0.033 95,000.00 3,135.00
Mandor L.04 OH 0.017 100,000.00 1,660.00
JUMLAH TENAGA KERJA 33,845.00
B. BAHAN
N2XSY,1c X 70 mm2 m1 3.000 3,900.00 11,700.00
JUMLAH HARGA BAHAN 11,700.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 292.50 292.50
JUMLAH HARGA PERALATAN 292.50

D. Jumlah (A+B+C) 45,837.50


E. Overhead & Profit 10% 4,583.75
F. Harga Satuan Pekerjaan (D+E) 50,421.25

1 M' Kabel Power NYY 4 ( 1 c x 240 mm2 )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.166 85,000.00 14,110.00
Tukang L.02 OH 0.166 90,000.00 14,940.00
Kepala tukang L.03 OH 0.033 95,000.00 3,135.00
Mandor L.04 OH 0.017 100,000.00 1,660.00
JUMLAH TENAGA KERJA 33,845.00
B. BAHAN
NYY 1 x240 MM2 m1 4.000 19,000.00 76,000.00
JUMLAH HARGA BAHAN 76,000.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 1,900.00 1,900.00
JUMLAH HARGA PERALATAN 1,900.00

D. Jumlah (A+B+C) 111,745.00


E. Overhead & Profit 10% 11,174.50
F. Harga Satuan Pekerjaan (D+E) 122,919.50

1 M ' Kabel Power NYY 4 x 70 mm2


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.166 85,000.00 14,110.00
Tukang L.02 OH 0.166 90,000.00 14,940.00
Kepala tukang L.03 OH 0.033 95,000.00 3,135.00
Mandor L.04 OH 0.017 100,000.00 1,660.00
JUMLAH TENAGA KERJA 33,845.00
B. BAHAN
NYY 4 x 70 MM2 m1 1.000 21,000.00 21,000.00
JUMLAH HARGA BAHAN 21,000.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 525.00 525.00
JUMLAH HARGA PERALATAN 525.00

D. Jumlah (A+B+C) 55,370.00


E. Overhead & Profit 10% 5,537.00
F. Harga Satuan Pekerjaan (D+E) 60,907.00

1 unit Panel SDP


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 85,000.00 85,000.00
Tukang L.02 OH 1.000 90,000.00 90,000.00
Kepala tukang L.03 OH 0.750 95,000.00 71,250.00
Mandor L.04 OH 0.500 100,000.00 50,000.00
JUMLAH TENAGA KERJA 296,250.00
B. BAHAN
MCCB, 350 - 630 A / 3p/25 KA bh 1.000 950,000.00 950,000.00
MCCB, 80 - 160 A / 22 KA bh 2.000 950,000.00 1,900,000.00
MCCB, 80 - 125 A / 22 KA bh 1.000 850,000.00 850,000.00
MCCB, 80 - 100 A / 22 KA bh 2.000 650,000.00 1,300,000.00
MCCB, 30 - 63 A / 22 KA bh 1.000 450,000.00 450,000.00
MCB, 32 A / 3 PH/ 16 kA bh 3.000 350,000.00 1,050,000.00
MCB, 20 A / 3 PH/16 KA bh 1.000 65,000.00 65,000.00
Arresster + MCB 25A/3p-w/25kA set - 175,000.00 -
Digital power Meter bh 1.000 1,000,000.00 1,000,000.00
Pilot Lamp bh 2.000 125,000.00 250,000.00
Puse Carrier 4 A bh 2.000 500.00 1,000.00
CT 800/5A CT 70 bh 1.000 650,000.00 650,000.00
Box Panel ( 120 x 100 x 30 ) cm bh 1.000 3,750,000.00 3,750,000.00
Wiring bh 1.000 1,221,600.00 1,221,600.00
JUMLAH HARGA BAHAN 13,437,600.00
C. PERALATAN
Perlengkapan ( kabel skun, VDE, dll ) ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 13,833,850.00


E. Overhead & Profit 10% 1,383,385.00
F. Harga Satuan Pekerjaan (D+E) 15,217,235.00

1 unit Panel PP - AB
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.450 85,000.00 38,250.00
Tukang L.02 OH 0.450 90,000.00 40,500.00
Kepala tukang L.03 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.250 100,000.00 25,000.00
JUMLAH TENAGA KERJA 127,500.00
B. BAHAN
MCB, 32 A / 3 PH/ 16 kA bh 1.000 350,000.00 350,000.00
MCB, 20 A / 3 PH/10 KA bh 2.000 210,000.00 420,000.00
MCB, 10 A / 1 PH/10 KA bh 5.000 125,000.00 625,000.00
DOL 10 A bh 3.000 650,000.00 1,950,000.00
Pilot Lamp bh 3.000 125,000.00 375,000.00
Puse Carrier 4 A bh 3.000 500.00 1,500.00
Box Panel bh 1.000 -
Wiring bh 1.000 -
JUMLAH HARGA BAHAN 3,721,500.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 3,949,000.00


E. Overhead & Profit 10% 394,900.00
F. Harga Satuan Pekerjaan (D+E) 4,343,900.00
1 unit Panel PP - DW
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.450 85,000.00 38,250.00
Tukang L.02 OH 0.450 90,000.00 40,500.00
Kepala tukang L.03 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.250 100,000.00 25,000.00
JUMLAH TENAGA KERJA 127,500.00
B. BAHAN
MCB, 25 A / 3 PH/10 KA bh 1.000 75,000.00 75,000.00
MCB, 16 A / 3 PH/10KA bh 3.000 450,000.00 1,350,000.00
Pilot Lamp bh 3.000 125,000.00 375,000.00
Puse Carrier 4 A bh 3.000 500.00 1,500.00
Box Panel bh 1.000 3,500,000.00 3,500,000.00
Wiring bh 1.000 1,000,000.00 1,000,000.00
JUMLAH HARGA BAHAN 6,301,500.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 6,529,000.00


E. Overhead & Profit 10% 652,900.00
F. Harga Satuan Pekerjaan (D+E) 7,181,900.00

1 unit Panel PP/LP- L2


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.450 85,000.00 38,250.00
Tukang L.02 OH 0.450 90,000.00 40,500.00
Kepala tukang L.03 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.250 100,000.00 25,000.00
JUMLAH TENAGA KERJA 127,500.00
B. BAHAN
MCCB, 80 - 125 A / 22 KA bh 1.000 850,000.00 850,000.00
MCCB, 30 - 63 A / 22 KA bh 1.000 450,000.00 450,000.00
MCCB, 30 - 50 A / 3p/22 KA bh 1.000 425,000.00 425,000.00
MCB, 16 A / 3 PH/10KA bh 3.000 450,000.00 1,350,000.00
MCB, 10 A / 3 PH/10KA bh 1.000 225,000.00 225,000.00
MCB, 20 A / 1 PH/10 KA bh 4.000 90,000.00 360,000.00
MCB, 16 A / 1 PH/10 KA bh 3.000 450,000.00 1,350,000.00
MCB, 10 A / 1 PH/10 KA bh 18.000 125,000.00 2,250,000.00
MCB, 6 A / 1 PH/10 KA bh 8.000 90,000.00 720,000.00
MCB, 6 A / 1 PH/6 KA bh 13.000 65,000.00 845,000.00
MCB, 4 A / 1 PH/6 KA bh 1.000 75,000.00 75,000.00
Stop Kontak 10 A/16A/1Phase bh 2.000 25,000.00 50,000.00
Pilot Lamp bh 3.000 125,000.00 375,000.00
Puse Carrier 4 A bh 3.000 500.00 1,500.00
Box Panel ( 800x600x300 ) bh 1.000 5,500,000.00 5,500,000.00
Wiring bh 1.000 2,648,275.00 2,648,275.00
JUMLAH HARGA BAHAN 17,474,775.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 17,702,275.00


E. Overhead & Profit 10% 1,770,227.50
F. Harga Satuan Pekerjaan (D+E) 19,472,502.50

1 unit Panel PP/LP- L3


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
NO URAIAN KODE SATUAN KOEFISIEN
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.450 85,000.00 38,250.00
Tukang L.02 OH 0.450 90,000.00 40,500.00
Kepala tukang L.03 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.250 100,000.00 25,000.00
JUMLAH TENAGA KERJA 127,500.00
B. BAHAN
MCCB, 80 - 100 A / 22 KA bh 1.000 650,000.00 650,000.00
MCCB, 30 - 63 A / 22 KA bh 1.000 450,000.00 450,000.00
MCB, 16 A / 3 PH/10KA bh 9.000 450,000.00 4,050,000.00
MCB, 10 A / 3 PH/10KA bh 18.000 225,000.00 4,050,000.00
MCB, 6 A / 1 PH/6 KA bh 13.000 65,000.00 845,000.00
MCB, 4 A / 1 PH/6 KA bh 1.000 75,000.00 75,000.00
Stop Kontak 10 A/16A/1Phase bh 2.000 25,000.00 50,000.00
Pilot Lamp bh 3.000 125,000.00 375,000.00
Puse Carrier 4 A bh 3.000 500.00 1,500.00
Box Panel bh 1.000 3,500,000.00 3,500,000.00
Wiring bh 1.000 4,916,275.00 4,916,275.00
JUMLAH HARGA BAHAN 18,962,775.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 19,190,275.00


E. Overhead & Profit 10% 1,919,027.50
F. Harga Satuan Pekerjaan (D+E) 21,109,302.50

1 unit Panel PP/ LP-L4


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.450 85,000.00 38,250.00
Tukang L.02 OH 0.450 90,000.00 40,500.00
Kepala tukang L.03 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.250 100,000.00 25,000.00
JUMLAH TENAGA KERJA 127,500.00
B. BAHAN
MCCB, 80 - 125 A / 22 KA bh 1.000 850,000.00 850,000.00
MCCB, 40 - 80 A / 22 KA bh 1.000 550,000.00 550,000.00
MCB, 32 A / 3 PH/ 16 kA bh 1.000 350,000.00 350,000.00
MCB, 16 A / 3 PH/10KA bh 9.000 450,000.00 4,050,000.00
MCB, 20 A / 1 PH/10 KA bh 1.000 90,000.00 90,000.00
MCB, 10 A / 1 PH/10 KA bh 15.000 125,000.00 1,875,000.00
MCB, 6 A / 1 PH/6 KA bh 13.000 65,000.00 845,000.00
MCB, 4 A / 1 PH/6 KA bh 1.000 75,000.00 75,000.00
Stop Kontak 10 A/16A/1Phase bh 2.000 25,000.00 50,000.00
Pilot Lamp bh 3.000 125,000.00 375,000.00
Puse Carrier 4 A bh 3.000 500.00 1,500.00
Box PAnel ( 800x600x300 ) bh 1.000 3,500,000.00 3,500,000.00
Wiring bh 1.000 1,000,000.00 1,000,000.00
JUMLAH HARGA BAHAN 13,611,500.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 13,839,000.00


E. Overhead & Profit 10% 1,383,900.00
F. Harga Satuan Pekerjaan (D+E) 15,222,900.00

1 unit Panel PP/ LP-L5


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.450 85,000.00 38,250.00
Tukang L.02 OH 0.450 90,000.00 40,500.00
Kepala tukang L.03 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.250 100,000.00 25,000.00
JUMLAH TENAGA KERJA 127,500.00
B. BAHAN
MCCB, 80 - 100 A / 22 KA bh 1.000 650,000.00 650,000.00
MCCB, 30 - 50 A / 3p/22 KA bh 1.000 425,000.00 425,000.00
MCB, 32 A / 3 PH/ 16 kA bh 1.000 350,000.00 350,000.00
MCB, 16 A / 3 PH/10KA bh 5.000 450,000.00 2,250,000.00
MCB, 10 A / 3 PH/10KA bh 1.000 225,000.00 225,000.00
MCB, 20 A / 1 PH/10 KA bh 1.000 90,000.00 90,000.00
MCB, 10 A / 1 PH/10 KA bh 12.000 125,000.00 1,500,000.00
MCB, 6 A / 1 PH/10 KA bh 6.000 90,000.00 540,000.00
MCB, 6 A / 1 PH/6 KA bh 13.000 65,000.00 845,000.00
MCB, 4 A / 1 PH/6 KA bh 1.000 75,000.00 75,000.00
Stop Kontak 10 A/16A/1Phase bh 2.000 25,000.00 50,000.00
Pilot Lamp bh 3.000 125,000.00 375,000.00
Puse Carrier 4 A bh 3.000 500.00 1,500.00
Box Panel ( 800x600x300 ) bh 1.000 3,500,000.00 3,500,000.00
Wiring bh 1.000 1,000,000.00 1,000,000.00
JUMLAH HARGA BAHAN 11,876,500.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 12,104,000.00


E. Overhead & Profit 10% 1,210,400.00
F. Harga Satuan Pekerjaan (D+E) 13,314,400.00

1 unit Panel PP/ LP-Audi


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.450 85,000.00 38,250.00
Tukang L.02 OH 0.450 90,000.00 40,500.00
Kepala tukang L.03 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.250 100,000.00 25,000.00
JUMLAH TENAGA KERJA 127,500.00
B. BAHAN
MCCB, 30 - 50 A / 3p/22 KA bh 1.000 425,000.00 425,000.00
MCB, 20 A / 3 PH/16 KA bh 1.000 65,000.00 65,000.00
MCB, 32 A / 3 PH/ 16 kA bh 1.000 350,000.00 350,000.00
MCB, 16 A / 3 PH/10KA bh 1.000 450,000.00 450,000.00
MCB, 16 A / 1 PH/10 KA bh 8.000 450,000.00 3,600,000.00
MCB, 10 A / 1 PH/10 KA bh 7.000 125,000.00 875,000.00
MCB, 6 A / 1 PH/10 KA bh 5.000 90,000.00 450,000.00
Pilot Lamp bh 3.000 125,000.00 375,000.00
Puse Carrier 4 A bh 3.000 500.00 1,500.00
Box Panel ( 600x400x250 ) bh 1.000 4,500,000.00 4,500,000.00
Wiring bh 1.000 3,710,525.00 3,710,525.00
JUMLAH HARGA BAHAN 14,802,025.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 15,029,525.00


E. Overhead & Profit 10% 1,502,952.50
F. Harga Satuan Pekerjaan (D+E) 16,532,477.50

1 unit Panel PP-Booster


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.450 85,000.00 38,250.00
Tukang L.02 OH 0.450 90,000.00 40,500.00
Kepala tukang L.03 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.250 100,000.00 25,000.00
JUMLAH TENAGA KERJA 127,500.00
B. BAHAN
MCB, 16 A / 1 PH/10 KA bh 1.000 450,000.00 450,000.00
MCB, 10 A / 1 PH/10 KA bh 3.000 125,000.00 375,000.00
Pilot Lamp bh 3.000 125,000.00 375,000.00
Puse Carrier 4 A bh 3.000 500.00 1,500.00
Box Panel ( 400x300x200 ) bh 1.000 4,250,000.00 4,250,000.00
Wiring bh 1.000 1,908,025.00 1,908,025.00
JUMLAH HARGA BAHAN 7,359,525.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 7,587,025.00


E. Overhead & Profit 10% 758,702.50
F. Harga Satuan Pekerjaan (D+E) 8,345,727.50

1 unit Panel PP-Lift


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.450 85,000.00 38,250.00
Tukang L.02 OH 0.450 90,000.00 40,500.00
Kepala tukang L.03 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.250 100,000.00 25,000.00
JUMLAH TENAGA KERJA 127,500.00
B. BAHAN
MCB, 20 A / 3 PH/16 KA bh 1.000 65,000.00 65,000.00
MCB, 20 A / 3 PH/10 KA bh 1.000 210,000.00 210,000.00
MCB, 10 A / 1 PH/10 KA bh 1.000 125,000.00 125,000.00
MCB, 4 A / 1 PH/6 KA bh 3.000 75,000.00 225,000.00
Pilot Lamp bh 3.000 125,000.00 375,000.00
Puse Carrier 4 A bh 3.000 500.00 1,500.00
Box Panel bh 1.000 3,500,000.00 3,500,000.00
Wiring bh 1.000 1,575,525.00 1,575,525.00
JUMLAH HARGA BAHAN 6,077,025.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 100,000.00 100,000.00
JUMLAH HARGA PERALATAN 100,000.00

D. Jumlah (A+B+C) 6,304,525.00


E. Overhead & Profit 10% 630,452.50
F. Harga Satuan Pekerjaan (D+E) 6,934,977.50

1 M' Kabel Power NYY 4 x 2 ( 1 c x 150 mm2 ) + BCC 150 mm di tanam dalam tanah
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.166 85,000.00 14,110.00
Tukang L.02 OH 0.166 90,000.00 14,940.00
Kepala tukang L.03 OH 0.033 95,000.00 3,135.00
Mandor L.04 OH 0.017 100,000.00 1,660.00
JUMLAH TENAGA KERJA 33,845.00
B. BAHAN
NYY 1 x 150 MM2 m1 8.000 28,500.00 228,000.00
BCC 150 mm m1 1.000 25,000.00 25,000.00
Galian, urugan & pelindung kabel m1 1.000 -
JUMLAH HARGA BAHAN 253,000.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 6,325.00 6,325.00
JUMLAH HARGA PERALATAN 6,325.00

D. Jumlah (A+B+C) 293,170.00


E. Overhead & Profit 10% 29,317.00
F. Harga Satuan Pekerjaan (D+E) 322,487.00

1 M ' Kabel Power NYY 4 x 50 mm2 + BCC 35 mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.166 85,000.00 14,110.00
Tukang L.02 OH 0.166 90,000.00 14,940.00
Kepala tukang L.03 OH 0.033 95,000.00 3,135.00
Mandor L.04 OH 0.017 100,000.00 1,660.00
JUMLAH TENAGA KERJA 33,845.00
B. BAHAN
NYY 4 x 50 MM2 m1 1.000 35,000.00 35,000.00
BCC 35 mm m1 1.000 8,000.00 8,000.00
JUMLAH HARGA BAHAN 43,000.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 1,075.00 1,075.00
JUMLAH HARGA PERALATAN 1,075.00

D. Jumlah (A+B+C) 77,920.00


E. Overhead & Profit 10% 7,792.00
F. Harga Satuan Pekerjaan (D+E) 85,712.00

1 M Kabel Power NYY 4x16 mm + BCC 10 mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.033 85,000.00 2,762.50
Tukang L.02 OH 0.033 90,000.00 2,925.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 8,664.50
B. BAHAN
NYY 4 x16 MM2 m1 1.000 32,500.00 32,500.00
BCC 10 mm m1 1.000 7,000.00 7,000.00
JUMLAH HARGA BAHAN 39,500.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 987.50 987.50
JUMLAH HARGA PERALATAN 987.50

D. Jumlah (A+B+C) 49,152.00


E. Overhead & Profit 10% 4,915.20
F. Harga Satuan Pekerjaan (D+E) 54,067.20

1 M Kabel Power NYFGbY 4 x 10 mm + BCC 6 mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 85,000.00 2,125.00
Tukang L.02 OH 0.025 90,000.00 2,250.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 7,352.00
B. BAHAN
NYFGbY 4 x 10 MM2 m1 1.000 5,500.00 5,500.00
BCC 6 mm m1 1.000 6,000.00 6,000.00
JUMLAH HARGA BAHAN 11,500.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 287.50 287.50
JUMLAH HARGA PERALATAN 287.50

D. Jumlah (A+B+C) 19,139.50


E. Overhead & Profit 10% 1,913.95
F. Harga Satuan Pekerjaan (D+E) 21,053.45

1 M ' Kabel Power NYY 4 x 70 mm2 + BCC 35 mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.166 85,000.00 14,110.00
Tukang L.02 OH 0.166 90,000.00 14,940.00
Kepala tukang L.03 OH 0.033 95,000.00 3,135.00
Mandor L.04 OH 0.017 100,000.00 1,660.00
JUMLAH TENAGA KERJA 33,845.00
B. BAHAN
NYY 4 x 70 MM2 m1 1.000 21,000.00 21,000.00
BCC 35 mm m1 1.000 8,000.00 8,000.00
JUMLAH HARGA BAHAN 29,000.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 725.00 725.00
JUMLAH HARGA PERALATAN 725.00

D. Jumlah (A+B+C) 63,570.00


E. Overhead & Profit 10% 6,357.00
F. Harga Satuan Pekerjaan (D+E) 69,927.00

1 M Kabel Power NYY 4x 10 mm + BCC 6 mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.033 85,000.00 2,762.50
Tukang L.02 OH 0.033 90,000.00 2,925.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 8,664.50
B. BAHAN
NYY 4 x10 MM2 m1 1.000 19,000.00 19,000.00
BCC 6 mm m1 1.000 6,000.00 6,000.00
JUMLAH HARGA BAHAN 19,000.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 475.00 475.00
JUMLAH HARGA PERALATAN 475.00

D. Jumlah (A+B+C) 28,139.50


E. Overhead & Profit 10% 2,813.95
F. Harga Satuan Pekerjaan (D+E) 30,953.45

1 M Kabel Power NYY 3 x 6 mm + BCC 6 mm


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.033 85,000.00 2,762.50
Tukang L.02 OH 0.033 90,000.00 2,925.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 8,664.50
B. BAHAN
NYY 3 x6 MM2 m1 1.000 17,500.00 17,500.00
BCC 6 mm m1 1.000 6,000.00 6,000.00
JUMLAH HARGA BAHAN 23,500.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 587.50 587.50
JUMLAH HARGA PERALATAN 587.50

D. Jumlah (A+B+C) 32,752.00


E. Overhead & Profit 10% 3,275.20
F. Harga Satuan Pekerjaan (D+E) 36,027.20

1 M Kabel Tray 30 cm ( 300 x 100 )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.043 85,000.00 3,612.50
Tukang L.02 OH 0.043 90,000.00 3,825.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 10,414.50
B. BAHAN
Kabel Tray 30 cm ( 300 x 100 ) m1 1.000 500,000.00 500,000.00
Tee, Cros, Elbow, Reducer, & dudukan/penggantung ls 1.000 125,000.00 125,000.00
JUMLAH HARGA BAHAN 625,000.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 15,625.00 15,625.00
JUMLAH HARGA PERALATAN 15,625.00

D. Jumlah (A+B+C) 651,039.50


E. Overhead & Profit 10% 65,103.95
F. Harga Satuan Pekerjaan (D+E) 716,143.45

1 M Kabel Tray 20 cm ( 200 x 100 )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.043 85,000.00 3,612.50
Tukang L.02 OH 0.043 90,000.00 3,825.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 10,414.50
B. BAHAN
Kabel Tray 20 cm ( 200 x 100 ) m1 1.000 300,000.00 300,000.00
Tee, Cros, Elbow, Reducer, & dudukan/penggantung ls 1.000 75,000.00 75,000.00
JUMLAH HARGA BAHAN 375,000.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 7,500.00 7,500.00
JUMLAH HARGA PERALATAN 7,500.00

D. Jumlah (A+B+C) 392,914.50


E. Overhead & Profit 10% 39,291.45
F. Harga Satuan Pekerjaan (D+E) 432,205.95

1 M Kabel Tray 15 cm ( 150 x 100 )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.043 85,000.00 3,612.50
Tukang L.02 OH 0.043 90,000.00 3,825.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 10,414.50
B. BAHAN
Kabel Tray 15 cm ( 150 x 100 ) m1 1.000 250,000.00 250,000.00
Tee, Cros, Elbow, Reducer, & dudukan/penggantung ls 1.000 62,500.00 62,500.00
JUMLAH HARGA BAHAN 312,500.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 7,812.50 7,812.50
JUMLAH HARGA PERALATAN 7,812.50

D. Jumlah (A+B+C) 330,727.00


E. Overhead & Profit 10% 33,072.70
F. Harga Satuan Pekerjaan (D+E) 363,799.70

1 M Kabel Tray 10 cm ( 100 x 100 )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.043 85,000.00 3,612.50
Tukang L.02 OH 0.043 90,000.00 3,825.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 10,414.50
B. BAHAN
Kabel Tray 10 cm ( 100 x 100 ) m1 1.000 125,000.00 125,000.00
Tee, Cros, Elbow, Reducer, & dudukan/penggantung ls 1.000 31,250.00 31,250.00
JUMLAH HARGA BAHAN 156,250.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 3,906.25 3,906.25
JUMLAH HARGA PERALATAN 3,906.25

D. Jumlah (A+B+C) 170,570.75


E. Overhead & Profit 10% 17,057.08
F. Harga Satuan Pekerjaan (D+E) 187,627.83

1 M Kabel Leader 100 cm ( 1000 x 100 )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.043 85,000.00 3,612.50
Tukang L.02 OH 0.043 90,000.00 3,825.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 10,414.50
B. BAHAN
Kabel Leader 100 cm ( 1000 x 100 ) m1 1.000 100,000.00 100,000.00
dudukan ls 1.000 5,000.00 5,000.00
JUMLAH HARGA BAHAN 105,000.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 2,100.00 2,100.00
JUMLAH HARGA PERALATAN 2,100.00

D. Jumlah (A+B+C) 117,514.50


E. Overhead & Profit 10% 11,751.45
F. Harga Satuan Pekerjaan (D+E) 129,265.95

1 bh Lampu TL LED 1 x 16 Watt / Cover Clear Acrilic


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 85,000.00 8,500.00
Tukang L.02 OH 0.100 90,000.00 9,000.00
Kepala tukang L.03 OH 0.013 95,000.00 1,235.00
Mandor L.04 OH 0.011 100,000.00 1,100.00
JUMLAH TENAGA KERJA 19,835.00
B. BAHAN
TL LED 1 X 16 Watt / Cover Clear Acrilic bh 1.000 125,000.00 125,000.00
JUMLAH HARGA BAHAN 125,000.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 1,000.00 1,000.00
JUMLAH HARGA PERALATAN 1,000.00
D. Jumlah (A+B+C) 145,835.00
E. Overhead & Profit 10% 14,583.50
F. Harga Satuan Pekerjaan (D+E) 160,418.50

1 bh Lampu Down Light LED 18 watt


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.075 85,000.00 6,375.00
Tukang L.02 OH 0.075 90,000.00 6,750.00
Kepala tukang L.03 OH 0.013 95,000.00 1,235.00
Mandor L.04 OH 0.011 100,000.00 1,100.00
JUMLAH TENAGA KERJA 15,460.00
B. BAHAN
DOWN LIGHT/ ( LED 18 W ) bh 1.000 125,000.00 125,000.00
JUMLAH HARGA BAHAN 125,000.00
C. PERALATAN
Perlengkapan Instalasi ls -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 140,460.00


E. Overhead & Profit 10% 14,046.00
F. Harga Satuan Pekerjaan (D+E) 154,506.00

1 bh Spot lIght LED 3 Watt


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.075 85,000.00 6,375.00
Tukang L.02 OH 0.075 90,000.00 6,750.00
Kepala tukang L.03 OH 0.013 95,000.00 1,235.00
Mandor L.04 OH 0.011 100,000.00 1,100.00
JUMLAH TENAGA KERJA 15,460.00
B. BAHAN
Spot Light LED 3 Watt bh 85,000.00 -
JUMLAH HARGA BAHAN -
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 15,460.00


E. Overhead & Profit 10% 1,546.00
F. Harga Satuan Pekerjaan (D+E) 17,006.00

1 bh Lampu Baret-led 18 Watt


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.075 85,000.00 6,375.00
Tukang L.02 OH 0.075 90,000.00 6,750.00
Kepala tukang L.03 OH 0.013 95,000.00 1,235.00
Mandor L.04 OH 0.011 100,000.00 1,100.00
JUMLAH TENAGA KERJA 15,460.00
B. BAHAN
Baret LED 18 W bh 1.000 95,000.00 95,000.00
JUMLAH HARGA BAHAN 95,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 110,460.00


E. Overhead & Profit 10% 11,046.00
F. Harga Satuan Pekerjaan (D+E) 121,506.00

1 bh Lampu Spot Light LED 38 Watt


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.166 85,000.00 14,110.00
Tukang L.02 OH 0.166 90,000.00 14,940.00
Kepala tukang L.03 OH 0.033 95,000.00 3,135.00
Mandor L.04 OH 0.017 100,000.00 1,660.00
JUMLAH TENAGA KERJA 33,845.00
B. BAHAN
LAMPU SOROT LED 38 W bh 1.000 275,000.00 275,000.00
JUMLAH HARGA BAHAN 275,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 308,845.00


E. Overhead & Profit 10% 30,884.50
F. Harga Satuan Pekerjaan (D+E) 339,729.50

1 bh Saklar tunggal
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 85,000.00 2,125.00
Tukang L.02 OH 0.025 90,000.00 2,250.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 7,352.00
B. BAHAN
Saklar Tunggal bh 1.000 75,000.00 75,000.00
JUMLAH HARGA BAHAN 75,000.00
C. PERALATAN

JUMLAH HARGA PERALATAN

D. Jumlah (A+B+C) 82,352.00


E. Overhead & Profit 10% 8,235.20
F. Harga Satuan Pekerjaan (D+E) 90,587.20

1 bh Saklar Ganda
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 85,000.00 2,125.00
Tukang L.02 OH 0.025 90,000.00 2,250.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 7,352.00
B. BAHAN
Saklar Ganda bh 1.000 85,000.00 85,000.00
JUMLAH HARGA BAHAN 85,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 92,352.00


E. Overhead & Profit 10% 9,235.20
F. Harga Satuan Pekerjaan (D+E) 101,587.20

1 bh Saklar Hotel
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 85,000.00 2,125.00
Tukang L.02 OH 0.025 90,000.00 2,250.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 7,352.00
B. BAHAN
Saklar Hotel bh 1.000 175,000.00 175,000.00
JUMLAH HARGA BAHAN 175,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 182,352.00


E. Overhead & Profit 10% 18,235.20
F. Harga Satuan Pekerjaan (D+E) 200,587.20

1 bh Saklar Grid ( 6 modul )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 85,000.00 2,125.00
Tukang L.02 OH 0.025 90,000.00 2,250.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 7,352.00
B. BAHAN
Saklar Grid ( 6 modul ) bh 1.000 225,000.00 225,000.00
JUMLAH HARGA BAHAN 225,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 232,352.00


E. Overhead & Profit 10% 23,235.20
F. Harga Satuan Pekerjaan (D+E) 255,587.20

1 bh Stop Kontak daya 1 Ph


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 85,000.00 2,125.00
Tukang L.02 OH 0.025 90,000.00 2,250.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 7,352.00
B. BAHAN
Stop Kontak 10 A/16A/1Phase bh 1.000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 32,352.00


E. Overhead & Profit 10% 3,235.20
F. Harga Satuan Pekerjaan (D+E) 35,587.20

1 bh Stop Kontak daya 2 x 16 A


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 85,000.00 8,500.00
Tukang L.02 OH 0.100 90,000.00 9,000.00
Kepala tukang L.03 OH 0.050 95,000.00 4,750.00
Mandor L.04 OH 0.010 100,000.00 1,000.00
JUMLAH TENAGA KERJA 23,250.00
B. BAHAN
Stop kontak dinding 2 x16 A bh 1.000 75,000.00 75,000.00
JUMLAH HARGA BAHAN 75,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 98,250.00


E. Overhead & Profit 10% 9,825.00
F. Harga Satuan Pekerjaan (D+E) 108,075.00

1 Titik Instalasi Lampu


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang L.02 OH 0.150 90,000.00 13,500.00
Kepala tukang L.03 OH 0.100 95,000.00 9,500.00
Mandor L.04 OH 0.075 100,000.00 7,500.00
JUMLAH TENAGA KERJA 43,250.00
B. BAHAN
NYM 3 x 2,5 MM2 m1 9.000 17,000.00 153,000.00
Pipa Conduit m1 9.000 2,500.00 22,500.00
JUMLAH HARGA BAHAN 175,500.00
C. PERALATAN
Perlengkapan Instalasi ( tee doos, klamp, soket, fhiser, lasdop, dll ) ls 1.000 26,325.00 26,325.00
JUMLAH HARGA PERALATAN 26,325.00

D. Jumlah (A+B+C) 245,075.00


E. Overhead & Profit 10% 24,507.50
F. Harga Satuan Pekerjaan (D+E) 269,582.50

1 Titik Instalasi Stop kontak


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang L.02 OH 0.150 90,000.00 13,500.00
Kepala tukang L.03 OH 0.100 95,000.00 9,500.00
Mandor L.04 OH 0.075 100,000.00 7,500.00
JUMLAH TENAGA KERJA 43,250.00
B. BAHAN
NYM 3 x 2,5 MM2 m1 14.000 17,000.00 238,000.00
Pipa Conduit m1 14.000 2,500.00 35,000.00
JUMLAH HARGA BAHAN 273,000.00
C. PERALATAN
Perlengkapan Instalasi ( tee doos, klamp, soket, fhiser, lasdop, dll ) ls 1.000 40,950.00 40,950.00
JUMLAH HARGA PERALATAN 40,950.00

D. Jumlah (A+B+C) 357,200.00


E. Overhead & Profit 10% 35,720.00
F. Harga Satuan Pekerjaan (D+E) 392,920.00

1 m Hantaramn BC
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.011 85,000.00 910.71
Tukang L.02 OH 0.011 90,000.00 964.29
Kepala tukang L.03 OH 0.007 95,000.00 678.57
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 3,267.86
B. BAHAN
Hantaran BC m1 1.000 3,000.00 3,000.00
JUMLAH HARGA BAHAN 3,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 6,267.86


E. Overhead & Profit 10% 626.79
F. Harga Satuan Pekerjaan (D+E) 6,894.64

1 bh Distribution Switch
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 85,000.00 85,000.00
Tukang L.02 OH 1.000 90,000.00 90,000.00
Kepala tukang L.03 OH 0.500 95,000.00 47,500.00
Mandor L.04 OH 0.500 100,000.00 50,000.00
JUMLAH TENAGA KERJA 272,500.00
B. BAHAN
Distribution Switch Managable (Catalyst 3560-X series) unit 1.000 12,500,000.00 12,500,000.00
JUMLAH HARGA BAHAN 12,500,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 12,772,500.00


E. Overhead & Profit 10% 1,277,250.00
F. Harga Satuan Pekerjaan (D+E) 14,049,750.00

1 unit UPS
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 85,000.00 2,125.00
Tukang L.02 OH 0.025 90,000.00 2,250.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 7,352.00
B. BAHAN
UPS 2 kVa c/w Nicad Batere, Rectifier ( 2 Jam ) unit 1.000 750,000.00 750,000.00
JUMLAH HARGA BAHAN 750,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 757,352.00


E. Overhead & Profit 10% 75,735.20
F. Harga Satuan Pekerjaan (D+E) 833,087.20

1 M Kabel FO 4 Core
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 85,000.00 3,035.71
Tukang L.02 OH 0.036 90,000.00 3,214.29
Kepala tukang L.03 OH 0.007 95,000.00 678.57
Mandor L.04 OH 0.004 100,000.00 357.14
JUMLAH TENAGA KERJA 7,285.71
B. BAHAN
FO Kabel 4 Core m1 1.000 5,200.00 5,200.00
JUMLAH HARGA BAHAN 5,200.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 130.00 130.00
JUMLAH HARGA PERALATAN 130.00

D. Jumlah (A+B+C) 12,615.71


E. Overhead & Profit 10% 1,261.57
F. Harga Satuan Pekerjaan (D+E) 13,877.29

1 bh Stop Kontak-TELEPON pada dinding


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 85,000.00 2,125.00
Tukang L.02 OH 0.025 90,000.00 2,250.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 7,352.00
B. BAHAN
Socket Telephone bh 1.000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 20,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 27,352.00


E. Overhead & Profit 10% 2,735.20
F. Harga Satuan Pekerjaan (D+E) 30,087.20

1 buah Insalasi titik Telepon


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang L.02 OH 0.150 90,000.00 13,500.00
Kepala tukang L.03 OH 0.036 95,000.00 3,392.86
Mandor L.04 OH 0.021 100,000.00 2,142.86
JUMLAH TENAGA KERJA 31,785.71
B. BAHAN
ITC 2 x 2 x 0,6 mm2 m1 28.000 2,600.00 72,800.00
Pipa Conduit m1 14.000 2,500.00 35,000.00
JUMLAH HARGA BAHAN 107,800.00
C. PERALATAN
Perlengkapan Instalasi ( tee doos, klamp, soket, fhiser, lasdop, dll ) ls 1.000 16,170.00 16,170.00
JUMLAH HARGA PERALATAN 16,170.00

D. Jumlah (A+B+C) 155,755.71


E. Overhead & Profit 10% 15,575.57
F. Harga Satuan Pekerjaan (D+E) 171,331.29

1 bh Socket Data ( RG 45 )
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 85,000.00 2,125.00
Tukang L.02 OH 0.025 90,000.00 2,250.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 7,352.00
B. BAHAN
Socket Data ( RG-45 ) bh 1.000 22,500.00 22,500.00
JUMLAH HARGA BAHAN 22,500.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 29,852.00


E. Overhead & Profit 10% 2,985.20
F. Harga Satuan Pekerjaan (D+E) 32,837.20

1 bh Acces Point ( WiFi )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.057 85,000.00 4,857.14
Tukang L.02 OH 0.057 90,000.00 5,142.86
Kepala tukang L.03 OH 0.021 95,000.00 2,035.71
Mandor L.04 OH 0.011 100,000.00 1,071.43
JUMLAH TENAGA KERJA 13,107.14
B. BAHAN
Acces Point ( Wi-Fi ) unit 1.000 125,000.00 125,000.00
JUMLAH HARGA BAHAN 125,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 138,107.14


E. Overhead & Profit 10% 13,810.71
F. Harga Satuan Pekerjaan (D+E) 151,917.86

1 buah Insalasi titik Telepon


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang L.02 OH 0.150 90,000.00 13,500.00
Kepala tukang L.03 OH 0.036 95,000.00 3,392.86
Mandor L.04 OH 0.021 100,000.00 2,142.86
JUMLAH TENAGA KERJA 31,785.71
B. BAHAN
ITC 2 x 2 x 0,6 mm2 m1 28.000 2,600.00 72,800.00
Pipa Conduit m1 14.000 2,500.00 35,000.00
JUMLAH HARGA BAHAN 107,800.00
C. PERALATAN
Perlengkapan Instalasi ( tee doos, klamp, soket, fhiser, lasdop, dll ) ls 1.000 16,170.00 16,170.00
JUMLAH HARGA PERALATAN 16,170.00

D. Jumlah (A+B+C) 155,755.71


E. Overhead & Profit 10% 15,575.57
F. Harga Satuan Pekerjaan (D+E) 171,331.29

1 Unit MCFA ( Master Control Fire Alarm ) termasuk Repeat Panel, Nicad Battery + Charger ( 1 Loop )
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 85,000.00 85,000.00
Tukang L.02 OH 1.000 90,000.00 90,000.00
Kepala tukang L.03 OH 0.500 95,000.00 47,500.00
Mandor L.04 OH 0.500 100,000.00 50,000.00
JUMLAH TENAGA KERJA 272,500.00
B. BAHAN
MCFA ( Master Control Fire Alarm ) termasuk Repeat Panel, Nicad Battery + Charger 1 loop unit 1.000 4,000,000.00 4,000,000.00
JUMLAH HARGA BAHAN 4,000,000.00
C. PERALATAN
Perlengkapan ( seting & konekting ) ls 1.000 60,000.00 60,000.00
JUMLAH HARGA PERALATAN 60,000.00

D. Jumlah (A+B+C) 4,332,500.00


E. Overhead & Profit 10% 433,250.00
F. Harga Satuan Pekerjaan (D+E) 4,765,750.00

1 unit Anunciator Panel


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.166 85,000.00 14,110.00
Tukang L.02 OH 0.166 90,000.00 14,940.00
Kepala tukang L.03 OH 0.033 95,000.00 3,135.00
Mandor L.04 OH 0.017 100,000.00 1,660.00
JUMLAH TENAGA KERJA 33,845.00
B. BAHAN
Annunciataor Panel bh 1.000 5,500,000.00 5,500,000.00
JUMLAH HARGA BAHAN 5,500,000.00
C. PERALATAN
Perlengkapan ( konekting ) ls 1.000 137,500.00 137,500.00
JUMLAH HARGA PERALATAN 137,500.00

D. Jumlah (A+B+C) 5,671,345.00


E. Overhead & Profit 10% 567,134.50
F. Harga Satuan Pekerjaan (D+E) 6,238,479.50

1 M Kabel Power ( FRC 2 x 2,5 mm )


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 85,000.00 3,035.71
Tukang L.02 OH 0.036 90,000.00 3,214.29
Kepala tukang L.03 OH 0.007 95,000.00 678.57
Mandor L.04 OH 0.004 100,000.00 357.14
JUMLAH TENAGA KERJA 7,285.71
B. BAHAN
FRC 2C X 2,5 MM2 m1 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 15,000.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 375.00 375.00
JUMLAH HARGA PERALATAN 375.00

D. Jumlah (A+B+C) 22,660.71


E. Overhead & Profit 10% 2,266.07
F. Harga Satuan Pekerjaan (D+E) 24,926.79

1 M Kabel Power FRC 2 x 1,5 mm 2


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 85,000.00 3,035.71
Tukang L.02 OH 0.036 90,000.00 3,214.29
Kepala tukang L.03 OH 0.007 95,000.00 678.57
Mandor L.04 OH 0.004 100,000.00 357.14
JUMLAH TENAGA KERJA 7,285.71
B. BAHAN
FRC 2C X 1,5 MM2 m1 1.000 10,000.00 10,000.00
JUMLAH HARGA BAHAN 10,000.00
C. PERALATAN
Perlengkapan ( skun kabel ) ls 1.000 250.00 250.00
JUMLAH HARGA PERALATAN 250.00
D. Jumlah (A+B+C) 17,535.71
E. Overhead & Profit 10% 1,753.57
F. Harga Satuan Pekerjaan (D+E) 19,289.29

1 bh Smoke Detector
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.071 85,000.00 6,071.43
Tukang L.02 OH 0.071 90,000.00 6,428.57
Kepala tukang L.03 OH 0.021 95,000.00 2,035.71
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 15,250.00
B. BAHAN
Smoke Detector bh 1.000 450,000.00 450,000.00
JUMLAH HARGA BAHAN 450,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 465,250.00


E. Overhead & Profit 10% 46,525.00
F. Harga Satuan Pekerjaan (D+E) 511,775.00

1 bh Adressible Monitor Modul u/ Detector


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.071 85,000.00 6,071.43
Tukang L.02 OH 0.071 90,000.00 6,428.57
Kepala tukang L.03 OH 0.021 95,000.00 2,035.71
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 15,250.00
B. BAHAN
Addressable Monitor Module u/ Detektor unit 1.000 2,750,000.00 2,750,000.00
JUMLAH HARGA BAHAN 2,750,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 2,765,250.00


E. Overhead & Profit 10% 276,525.00
F. Harga Satuan Pekerjaan (D+E) 3,041,775.00

1 bh Manual push button


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.071 85,000.00 6,071.43
Tukang L.02 OH 0.071 90,000.00 6,428.57
Kepala tukang L.03 OH 0.021 95,000.00 2,035.71
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 15,250.00
B. BAHAN
Manual Breack glass bh 1.000 350,000.00 350,000.00
JUMLAH HARGA BAHAN 350,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 365,250.00


E. Overhead & Profit 10% 36,525.00
F. Harga Satuan Pekerjaan (D+E) 401,775.00

1 bh Main Bell
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.071 85,000.00 6,071.43
Tukang L.02 OH 0.071 90,000.00 6,428.57
Kepala tukang L.03 OH 0.021 95,000.00 2,035.71
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 15,250.00
B. BAHAN
Main Bell bh 1.000 750,000.00 750,000.00
JUMLAH HARGA BAHAN 750,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 765,250.00


E. Overhead & Profit 10% 76,525.00
F. Harga Satuan Pekerjaan (D+E) 841,775.00

1 bh Visual Alarm + modul


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.071 85,000.00 6,071.43
Tukang L.02 OH 0.071 90,000.00 6,428.57
Kepala tukang L.03 OH 0.021 95,000.00 2,035.71
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 15,250.00
B. BAHAN
Visual Alarm bh 1.000 175,000.00 175,000.00
JUMLAH HARGA BAHAN 175,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 190,250.00


E. Overhead & Profit 10% 19,025.00
F. Harga Satuan Pekerjaan (D+E) 209,275.00

1 bh Exit Lamp
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.071 85,000.00 6,071.43
Tukang L.02 OH 0.071 90,000.00 6,428.57
Kepala tukang L.03 OH 0.021 95,000.00 2,035.71
Mandor L.04 OH 0.007 100,000.00 714.29
JUMLAH TENAGA KERJA 15,250.00
B. BAHAN
Exit Lamp bh 1.000 250,000.00 250,000.00
JUMLAH HARGA BAHAN 250,000.00
C. PERALATAN
Perlengkapan Instalasi ls - - -
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 265,250.00


E. Overhead & Profit 10% 26,525.00
F. Harga Satuan Pekerjaan (D+E) 291,775.00

1 Titik Instalasi Telephone Jack


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang L.02 OH 0.150 90,000.00 13,500.00
Kepala tukang L.03 OH 0.036 95,000.00 3,392.86
Mandor L.04 OH 0.021 100,000.00 2,142.86
JUMLAH TENAGA KERJA 31,785.71
B. BAHAN
Kabel STP AWG # 18 1 pair m1 15.000 80,000.00 1,200,000.00
Pipa Conduit m1 12.000 2,500.00 30,000.00
JUMLAH HARGA BAHAN 1,230,000.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 61,500.00 61,500.00
JUMLAH HARGA PERALATAN 61,500.00

D. Jumlah (A+B+C) 1,323,285.71


E. Overhead & Profit 10% 132,328.57
F. Harga Satuan Pekerjaan (D+E) 1,455,614.29

1 titik Instalasi Flow Switch / Control Detector


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang L.02 OH 0.150 90,000.00 13,500.00
Kepala tukang L.03 OH 0.036 95,000.00 3,392.86
Mandor L.04 OH 0.021 100,000.00 2,142.86
JUMLAH TENAGA KERJA 31,785.71
B. BAHAN
FRC 2C X 2,5 MM2 m1 16.000 15,000.00 240,000.00
Pipa Conduit m1 16.000 2,500.00 40,000.00
JUMLAH HARGA BAHAN 280,000.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 14,000.00 14,000.00
JUMLAH HARGA PERALATAN 14,000.00

D. Jumlah (A+B+C) 325,785.71


E. Overhead & Profit 10% 32,578.57
F. Harga Satuan Pekerjaan (D+E) 358,364.29

1 Titik Instalasi Telephone Jack


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang L.02 OH 0.150 90,000.00 13,500.00
Kepala tukang L.03 OH 0.036 95,000.00 3,392.86
Mandor L.04 OH 0.021 100,000.00 2,142.86
JUMLAH TENAGA KERJA 31,785.71
B. BAHAN
Kabel ITC 2 x dia. 0,6 mm m1 20.000 3,500.00 70,000.00
Pipa Conduit m1 20.000 2,500.00 50,000.00
JUMLAH HARGA BAHAN 120,000.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 6,000.00 6,000.00
JUMLAH HARGA PERALATAN 6,000.00

D. Jumlah (A+B+C) 157,785.71


E. Overhead & Profit 10% 15,778.57
F. Harga Satuan Pekerjaan (D+E) 173,564.29

1 unit Mixer Pree Amp


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.166 85,000.00 14,110.00
Tukang L.02 OH 0.166 90,000.00 14,940.00
Kepala tukang L.03 OH 0.033 95,000.00 3,135.00
Mandor L.04 OH 0.017 100,000.00 1,660.00
JUMLAH TENAGA KERJA 33,845.00
B. BAHAN
Mixer Frame w/ Module unit 1.000 3,500,000.00 3,500,000.00
JUMLAH HARGA BAHAN 3,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 3,533,845.00


E. Overhead & Profit 10% 353,384.50
F. Harga Satuan Pekerjaan (D+E) 3,887,229.50

1 unit Call Station Interface


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.166 85,000.00 14,110.00
Tukang L.02 OH 0.166 90,000.00 14,940.00
Kepala tukang L.03 OH 0.033 95,000.00 3,135.00
Mandor L.04 OH 0.017 100,000.00 1,660.00
JUMLAH TENAGA KERJA 33,845.00
B. BAHAN
Call Station Inteface unit 1.000 2,500,000.00 2,500,000.00
JUMLAH HARGA BAHAN 2,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 2,533,845.00


E. Overhead & Profit 10% 253,384.50
F. Harga Satuan Pekerjaan (D+E) 2,787,229.50

1 unit Speaker Selector


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.166 85,000.00 14,110.00
Tukang L.02 OH 0.166 90,000.00 14,940.00
Kepala tukang L.03 OH 0.033 95,000.00 3,135.00
Mandor L.04 OH 0.017 100,000.00 1,660.00
JUMLAH TENAGA KERJA 33,845.00
B. BAHAN
Speaker Selector unit 1.000 750,000.00 750,000.00
JUMLAH HARGA BAHAN 750,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 783,845.00


E. Overhead & Profit 10% 78,384.50
F. Harga Satuan Pekerjaan (D+E) 862,229.50

1 Bh Ceiling Speaker 3 W
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 85,000.00 2,125.00
Tukang L.02 OH 0.025 90,000.00 2,250.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 7,352.00
B. BAHAN
Ceiling Speaker bh 1.000 750,000.00 750,000.00
JUMLAH HARGA BAHAN 750,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 757,352.00


E. Overhead & Profit 10% 75,735.20
F. Harga Satuan Pekerjaan (D+E) 833,087.20

1 Titik Instalasi titik ceiling Speaker / Horn Speaker


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang L.02 OH 0.150 90,000.00 13,500.00
Kepala tukang L.03 OH 0.036 95,000.00 3,392.86
Mandor L.04 OH 0.021 100,000.00 2,142.86
JUMLAH TENAGA KERJA 31,785.71
B. BAHAN
NYMHY 3 X 1,5 MM2 m1 14.000 7,500.00 105,000.00
Pipa Conduit m1 14.000 2,500.00 35,000.00
JUMLAH HARGA BAHAN 140,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 171,785.71


E. Overhead & Profit 10% 17,178.57
F. Harga Satuan Pekerjaan (D+E) 188,964.29

1 Titik Instalaasi CCTV


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 85,000.00 12,750.00
Tukang L.02 OH 0.150 90,000.00 13,500.00
Kepala tukang L.03 OH 0.036 95,000.00 3,392.86
Mandor L.04 OH 0.021 100,000.00 2,142.86
JUMLAH TENAGA KERJA 31,785.71
B. BAHAN
Kabel Coaxial RG-59 U m1 35.000 3,000.00 105,000.00
Kabel Coaxial RG-59 U m1 35.000 3,000.00 105,000.00
JUMLAH HARGA BAHAN 210,000.00
C. PERALATAN
Perlengkapan Instalasi ls 1.000 10,500.00 10,500.00
JUMLAH HARGA PERALATAN 10,500.00

D. Jumlah (A+B+C) 252,285.71


E. Overhead & Profit 10% 25,228.57
F. Harga Satuan Pekerjaan (D+E) 277,514.29

1 Unit NVR 16 Chanel


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 85,000.00 42,500.00
Tukang L.02 OH 0.500 90,000.00 45,000.00
Kepala tukang L.03 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.250 100,000.00 25,000.00
JUMLAH TENAGA KERJA 136,250.00
B. BAHAN
Network Video Recorder ( NVR ) m1 1.000 16,000.00 16,000.00
JUMLAH HARGA BAHAN 16,000.00
C. PERALATAN
Setting Program ls 1.000 10,000.00 10,000.00
JUMLAH HARGA PERALATAN 10,000.00

D. Jumlah (A+B+C) 162,250.00


E. Overhead & Profit 10% 16,225.00
F. Harga Satuan Pekerjaan (D+E) 178,475.00

1 set PC Computer
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 85,000.00 2,125.00
Tukang L.02 OH 0.025 90,000.00 2,250.00
Kepala tukang L.03 OH 0.017 95,000.00 1,577.00
Mandor L.04 OH 0.014 100,000.00 1,400.00
JUMLAH TENAGA KERJA 7,352.00
B. BAHAN
Personal Computer set 1.000 6,500,000.00 6,500,000.00
JUMLAH HARGA BAHAN 6,500,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 6,507,352.00


E. Overhead & Profit 10% 650,735.20
F. Harga Satuan Pekerjaan (D+E) 7,158,087.20

1 Buah Monitor LED 42 Inch


HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 85,000.00 17,000.00
Tukang L.02 OH 0.200 90,000.00 18,000.00
Kepala tukang L.03 OH 0.100 95,000.00 9,500.00
Mandor L.04 OH 0.100 100,000.00 10,000.00
JUMLAH TENAGA KERJA 54,500.00
B. BAHAN
42” Colour monitor & suport set 1.000 2,800,000.00 2,800,000.00
JUMLAH HARGA BAHAN 2,800,000.00
C. PERALATAN
JUMLAH HARGA PERALATAN -

D. Jumlah (A+B+C) 2,854,500.00


E. Overhead & Profit 10% 285,450.00
F. Harga Satuan Pekerjaan (D+E) 3,139,950.00
HARGA SATUAN
NO URAIAN SAT
( Rp )

I. HARGA BAHAN STRUKTUR DAN ARSITEKTUR


1 Air ltr 50.00
2 Alumunium composite panel T.4mm, Anti UV,Merk : Maco m2 125,000.00
3 Amparan batu pecah mesin 1-2 m3 85,000.00
4 Amparan batu pecah mesin 5-7 m3 85,000.00
5 Ampelas besi lbr 3,500.00
6 Ampelas kayu lbr 3,500.00
7 Ampelas tembok lbr 3,500.00
8 Angkur dia. 8mm kg 7,000.00
9 Aspal Hotmix kg 1,200.00
10 Baja Profil, Merk : DN kg 6,000.00
11 Balok Kayu Albasiah m3 1,500,000.00
12 Balok Kayu Kelas III m3 1,250,000.00
13 Balok Kayu Samarinda Oven m3 3,500,000.00
14 Bata Merah bh 1,000.00
15 Bata Ringan Tebal 10cm, Merk : Hebel, Liebel m3 550,000.00
16 Batako bh 1,500.00
17 Batu Alam m2 95,000.00
18 Batu pecah mesin 1-2 kg 25.00
19 Besi Beton Polos kg 9,500.00
20 Besi Beton Ulir kg 9,500.00
21 Besi Nako 8mm kg 10,000.00
22 Cat plafond, Merk : Vinilex ltr 35,000.00
23 Cat Petalac-2K Super Sanding sealer ltr 45,000.00
24 Cat Petalac-2K Clear Matt MV-3 ltr 35,000.00
25 Cat duco polyurethane clear matt MV-3, Merk : Petalac 2K ltr 50,000.00
26 Cat epoxy undercoat, Merk : Petalac ltr 35,000.00
27 Cat polyster putty, Merk : Petalac ltr 35,000.00
28 Cat tembok interior, setara Jotun Majestic True Beauty SHEEN ltr 35,000.00
29 Cat dasar Jotun Jotashield Primer 7 ltr 35,000.00
30 Cat dasar Jotun Base Coat Sealer ltr 35,000.00
31 Cat tembok eksterior, setara Jotun Jotashield Antifade ltr 35,000.00
32 Cat zinchromat, setara Meiji kg 35,000.00
33 Compound kg 35,000.00
34 Cover U-ditch 300 bh 110,000.00
35 Cutting ACP m2 1,500.00
36 Dolken Kayu Ø 8-10/400 cm btg 18,000.00
37 Drymix tile adhesive (40kg) zak 55,000.00
38 Drymix TA water repellent (40kg) zak 48,000.00
39 Drymix Thinbed M-101 (40kg) zak 45,000.00
40 flexible polycarbonate 2mm ultraviolet lbr 72,000.00
41 Floor hardener T.5mm, Merk : Fosroc, Delta, Sica kg 3,500.00
42 Genteng Keramik bh 9,500.00
43 GRC t.12mm lbr 238,000.00
44 Gypsumboard T.9mm, Merk : A-Plus lbr 49,000.00
45 Gypsumboard T.9mm, Merk : A-Plus lbr 49,000.00
46 Gypsumboard T.9mm, Merk : A-Plus lbr 49,000.00
47 Homogeneous Tile 600x600 Merk : Habitat Arabella m2 125,000.00
48 Homogeneous Tile 600x600 Merk : Vicenca GYK 6607 m2 150,000.00
49 Homogeneous Tile 600x600 Merk : Garuda Multipipe White m2 80,000.00
50 Homogeneous Tile 600x600 Pebbles Charcoal Grey GPL03 MATT, Merk : Niro granit m2 175,000.00
51 HPL 0.8mm ex Taco lbr 160,000.00
52 Jaring Kawat Baja Dilas kg 35,000.00
53 Kaca Polos 6mm, Merk : Asahimas m2 85,000.00
54 Kaca Tempered 12mm, Merk : Asahimas m2 125,000.00
55 Kaca tempered laminated T.10mm, Merk : Asahimas m2 175,000.00
(5mm polos tempered+PVB clear+5mm polos biasa)
56 Kalsiplank 8mm, uk. 0,2x3m lbr 43,000.00
57 Karpet, Tuntex m2 35,000.00
58 Kawat Beton kg 18,000.00
59 Kayu Kelas III m3 1,500,000.00
60 Kayu Papan Albasiah m3 1,750,000.00
61 Kayu papan kamper samarinda oven m3 3,250,000.00
62 Koral Beton m3 125,000.00
63 Kusen Aluminium 4", T.1,2mm, fin. Powder Coating Merk : Alexindo m1 95,000.00
64 Kwas 3" bh 15,000.00
65 Kwas cat rata-rata bh 5,000.00
66 Lem putih (Fox) kg 35,000.00
67 Lem Karpet kg 35,000.00
68 Lem Kayu kg 25,000.00
69 Lem Kayu & HPL kg 25,000.00
70 List plafond profil aluminium U, 1cm m1 7,000.00
71 List plafond profil aluminium U, 2cm m1 7,500.00
72 Megateak 3mm lbr 65,000.00
73 Meiji gum sealer kg 25,000.00
74 Metal square hollow 20/20, tebal 0,9mm m1 6,666.67
75 Metal square hollow 30/60, tebal 1,1mm m1 28,666.67
76 Metal square hollow 40/20, tebal 1,1mm m1 18,666.67
77 Metal square hollow 40/40, tebal 1,1mm m1 33,000.00
78 Metal square hollow 40/40, tebal 2,3mm m1 47,333.33
79 Metal square hollow 40/60, tebal 1,0mm m1 42,000.00
80 Metal square hollow 50/100, tebal 2,0mm m1 66,666.67
81 Minyak Bekisting ltr 10,000.00
82 MU Acian (40kg) kg 1,375.00
83 MU Plester (50kg) kg 2,125.00
84 Multiplek 9mm lbr 110,000.00
85 Multiplek 18mm lbr 220,000.00
86 Paku 5-10cm kg 18,000.00
87 Paku Biasa 2" - 3" kg 18,000.00
88 Paku triplek kg 22,000.00
89 Pasir Beton m3 250,000.00
90 Pasir Beton kg 250.00
91 Pasir Pasang m3 185,000.00
92 Pasir Urug m3 125,000.00
93 Paving Block 8cm Natural bh 3,500.00
94 Penjaga Jarak Bekisting/Spacer bh 100.00

95 Perancah :
Sewa Main Frame bh 5,000.00
Sewa Joint Pin bh 5,000.00
Sewa Cross Brase bh 5,000.00
Sewa Head Jack bh 5,000.00
Sewa Base Jack bh 5,000.00
Sewa Pipa Support + Accesories bh 5,000.00

96 Plamuur kg 35,000.00
97 Plywood 6mm lbr 85,000.00
98 Plywood tebal 9mm lbr 110,000.00
99 Reng zincalume m1 5,833.33
100 Rangka daun Jendela Aluminium, Merk : Powder Coating Merk : Alexindo m1 65,000.00
101 Rangka daun Pintu Aluminium, Merk : Powder Coating Merk : Alexindo m1 85,000.00
102 Rangka metal square zincalume, 40x40 m2 125,000.00
103 Rangka metal square Galvanized, 40x40 m1 135,000.00

104 Rangka Metal Furing :


Metal furing acoustic Tee m1 16,666.67
Metal furing acoustic wall angle m1 15,833.33
Suspension rod dia 4mm btg 4,000.00
Suspension clip bh 11,500.00
Rumset bh 1,500.00
105 Rooster Terakota uk. 200x200 bh 6,500.00
106 Rol cat bh 15,000.00

107 Rumput :
Bensin/Solar ltr 8,500.00
Oli ltr 6,500.00
Tanah Top Soil m3 25,000.00
Pupuk Kandang (1 karung : 40 Kg) krg 5,000.00
Furadan kg 35,000.00
Atonik/Rotone btl 25,000.00
Pupuk Kompos (5kg) kntg 15,000.00
Rumput Gajah Mini m2 25,000.00
Mobil Operasional hari 75,000.00
Mobil Tanki air 5000 lt hari 125,000.00
Truk engkel hari 75,000.00
Linggis/Blencong hari 1,000.00
Cangkul hari 1,000.00
pH Meter hari 2,500.00
Karung Plastik buah 100.00
Selang Penyiraman jam 500.00

108 Sealant m1 500.00


109 Sealant untuk ACP m1 1,000.00
110 Sekrup kg 150.00
111 Semen PC 50kg zak 50,000.00
112 Semen Portland kg 1,100.00
113 Semen Warna kg 7,500.00
114 Seng Gelombang lbr 45,000.00
115 Sirtu kg 85.00
116 Stainless Steel cm2 1,500.00
117 Stepnosing Granit 100x800 m1 5,000.00
118 Tactile tipe dot Aluminium bh 4,500.00
119 Tactile tipe line Aluminium bh 5,500.00
120 Thinner ltr 25,000.00
121 Thinner OS 2000 ltr 17,500.00
122 Thinner P.U. ltr 19,000.00
123 Thinner Super Sanding Sealer ltr 35,000.00
124 Thinner Slow Dry ltr 45,000.00
125 Triplek lbr 45,000.00
126 U-ditch 300x400 bh 110,000.00
127 U Runner 92.25 m1 350.00
128 Waterstop Lebar 150 mm m1 85,000.00
129 Waterproofing formdex WP system, Merk : Sika, Fosroc kg 17,500.00
130 Waterproofing Formdex Uniflex Cementitious Membrance, m2 8,500.00
Merk : Sika, Fosroc

131 Waterproofing De Boer :


Duo Composite Membrane roll 350,000.00
C Profile pcs 2,500.00
Fastener and Mechano Plate pcs 7,500.00
Duo Kit Sealant tube 75,000.00
Duo Primer pile 125,000.00

132 Wood filler + wood stain kg 45,000.00

133 Accessories Kusen, Pintu dan Jendela :


Casement Stay Dekkson FS SS 16 Inch Friction Stay Side Top Hung 16" unit 85,000.00
Cylinder Dekkson CYL DC DL70mm SN unit 125,000.00
Door Closer Dekkson DCL 300 HO unit 75,000.00
Engsel Dekkson Stainless ESS EL 4x3x3mm 4BB SSS unit 85,000.00
Escutcheon Dekkson ESCN DKS 855SSS unit 175,000.00
Handle Stainless Steel Dekkson PH-DKS-DL-1868 Dekson 120cm psg 110,000.00
Lever Handle Dekkson Solid LHSR DKS 058SSS psg 275,000.00
Handel Tanam Oval Dekkson Oval Flush Pull Plate Dekson PP 012 Dekson psg 325,000.00
Mortise Roller Dekkson MTS RL 8585 SSS SUS316 unit 75,000.00
Rambuncis Dekkson CH 439 R Lock Kunci MNJJ unit 25,000.00
Rel dan Roda set 125,000.00
Kunci Tanam bh 285,000.00

134 Plumbing Fixtures :


Closet Duduk tipe CW660NJ/SW660J, Merk : Toto unit 1,800,000.00
Floordrain tipe TX1C, Merk : Toto unit 45,000.00
Kran washtafel Tipe TX109LD, Merk : Toto unit 75,000.00
Washtafel tipe LW813CJ, Merk : Toto unit 1,250,000.00
Divider Urinoir tipe A100, Merk : Toto unit 950,000.00
Urinoir tipe U57, Merk : Toto unit 250,000.00
Jet Washer tipe THX20NB, Merk : Toto unit 125,000.00
Kaca Cermin dinding T.6mm, Merk : Asahimas m2 85,000.00
cubical PVC, tipe Compact - Phenolic 12mm, Ex. Wimas m1 12,500.00
Accessories Pintu Toilet, Ex. Wimas set 22,500.00
Handrail tipe T113B6, setara Toto unit 120,000.00

II HARGA BAHAN MEP


1 42” Colour monitor & suport set 2,800,000.00
2 Acces Point ( Wi-Fi ) unit 125,000.00
3 Addressable Monitor Module u/ Detektor unit 2,750,000.00
4 Annunciataor Panel bh 5,500,000.00
5 Alarm Check Valve bh 2,500,000.00
6 Arresster + MCB 25A/3p-w/25kA set 175,000.00
7 Baret LED 18 W bh 95,000.00
8 BCC 6 mm m1 6,000.00
9 BCC 10 mm m1 7,000.00
10 BCC 35 mm m1 8,000.00
11 BCC 50 mm m1 12,500.00
12 BCC 150 mm m1 25,000.00
13 Biaya Penyambungan Listrik ( BP + UJL ) va 1,750,000.00
14 Biaya SLO va 1,750,000.00
15 BJLS 60 ( 6 " x 6 " ) m1 25,000.00
16 BJLS 60 (8" x 6" ) m1 35,000.00
17 BJLS 60 ( 8" x 8" ) m1 45,000.00
18 BJLS 60 ( 12 " x 10 " ) m1 55,000.00
19 BJLS 60 ( 16 " x 10 " ) m1 65,000.00
20 Booster Pump Packaged, Kapasitas 165 lpm ; Head 10 meter unit 22,500,000.00
21 Box Meter bh 75,000.00
22 BSP SCH.40 Dia. 1” m1 366,666.67
23 BSP SCH.40 Dia. 1 1/4” m1 383,333.33
24 BSP SCH.40 Dia. 1 1/2” m1 391,666.67
25 BSP SCH.40 Dia. 2” m1 416,666.67
26 BSP SCH. 40 Dia. 2 1/2” m1 425,000.00
27 BSP SCH. 40 Dia. 3” m1 458,333.33
28 BSP SCH. Dia. 4” m1 583,333.33
29 BSP SCH. Dia. 6” m1 608,333.33
30 BSP SCH. Dia. 8” m1 600,000.00
31 Butterfly valve 10 K dia. 150 mm bh 7,500,000.00
32 Butterfly valve dia. 65 mm bh 7,500,000.00
33 Box Panel bh 3,500,000.00
34 Box Panel ( 800x600x300 ) bh 5,500,000.00
35 Box Panel ( 600x400x250 ) bh 4,500,000.00
36 Box Panel ( 400x300x200 ) bh 4,250,000.00
37 Box Panel ( 120 x 100 x 30 ) cm bh 3,750,000.00
38 Call Station Inteface unit 2,500,000.00
39 Capasitor Bank 120 kVAR unit 7,500,000.00
40 Carbon Filter kapasitas : 100 Lpm unit 12,500,000.00
41 Ceiling Speaker bh 750,000.00
42 Check valve 10 K dia. 25 mm bh 2,500,000.00
43 Check valve 10 K dia. 32 mm bh 3,000,000.00
44 Check valve 10 K dia. 40 mm bh 3,250,000.00
45 Check valve 10 K dia. 50 mm bh 3,500,000.00
46 Check valve kelas 16/20K dia. 100 mm bh 4,500,000.00
47 CO diameter 65 mm bh 175,000.00
48 CO diameter 100 mm bh 250,000.00
49 CT 800/5A CT 70 bh 650,000.00
50 Cubicle Incoming unit 36,000,000.00
51 Cubiclr Areester unit 10,500,000.00
52 Cubicle Outgoing unit 52,000,000.00
53 Diesel Fire Pump, kapasitas : 1890 lpm / 105 meter set 65,000,000.00
54 Digital power Meter bh 1,000,000.00
55 Distribution Switch Managable (Catalyst 3560-X series) unit 12,500,000.00
56 DOL 10 A bh 650,000.00
57 DOWN LIGHT/ ( LED 18 W ) bh 125,000.00
58 Electric Fire Pump, kapasitas : 500 Gpm / 105 meter set 17,500,000.00
59 Exhaust Air Grille uk. 8" x8" bh 275,000.00
60 Exhaust Air Grille uk. 22" x 14 " bh 450,000.00
61 Exhaust Fan, kap.150 Cfm - Wall Fan unit 750,000.00
62 Exhaust Fan, kap.850 Cfm - Axial/Inline fan unit 950,000.00
63 Exhaust Fan kapasitas 900 CFM / 0,6 InWg/ Axial-Inline Fan unit 1,250,000.00
64 Exit Lamp bh 250,000.00
65 Fire Extinguisher type Dry Chemical kap. 5 kg unit 450,000.00
66 Flexible Joint 10 K dia. 32 mm bh 650,000.00
67 Flexible Joint 10 K dia. 40 mm bh 750,000.00
68 Flexible Joint 10 K 50 mm bh 850,000.00
69 Flexible Joint 16/20 K dia. dia. 25 mm bh 950,000.00
70 Flexible Joint kelas 16/20K dia. 100 mm bh 1,500,000.00
71 Floating valve dia. 40 mm bh 350,000.00
72 Flow Switch bh 250,000.00
73 FRC 2C X 2,5 MM2 m1 15,000.00
74 FRC 2C X 1,5 MM2 m1 10,000.00
75 FRC 4C X 50 MM2 m1 25,000.00
76 FRC 4C X 6 MM2 m1 17,000.00
77 FO Kabel 4 Core m1 5,200.00
78 Gate valve 10 K dia. 32 mm bh 2,500,000.00
79 Gate valve 10 K dia. 40 mm bh 2,750,000.00
80 Gate valve 10 K dia. 50 mm bh 3,000,000.00
81 Gate valve 10 K dia. 65 mm bh 3,500,000.00
82 Gate valve 10 K dia. 80 mm bh 5,000,000.00
83 Gate valve 16 K dia. 50 mm bh 7,500,000.00
84 Gate valve 16 K dia. 40 mm bh 6,500,000.00
85 Gate valve 150 PSI dia. dia. 32 mm bh 8,500,000.00
86 Gate valve 150 PSI dia. dia. 25 mm bh 10,500,000.00
87 Gate valve kelas 16/20K dia. 65 mm bh 17,500,000.00
88 Gate valve kelas 16/20K dia. 100 mm bh 14,500,000.00
89 Gate valve kelas 16/20K dia. 150 mm bh 12,500,000.00
90 GIP Medium Dia. 1 1/2” m1 20,833.33
91 GIP Medium Dia. 2” m1 41,666.67
92 GIP Medium Dia. 6” m1 45,833.33
93 GSP Medium Dia. 4” ( 100 mm ) m1 91,666.67
94 Hantaran BC m1 3,000.00
95 head Sprinkler 68 derajat unit 125,000.00
96 Horn / Buzzer bh 55,000.00
97 Hydrant Pillar One Way 3 '' x 2,5 '' (H-13 ) + lengkap Hose Cabinet unit 3,500,000.00
98 In - Door Type B ( Uk. 125 x 75 x 18 ) cm lengkap bh 1,500,000.00
99 Interlock bh 750,000.00
100 ITC 2 x 2 x 0,6 mm2 m1 2,600.00
101 Jockey Fire Pump, kapasitas : 30 Lpm / 112 meter bh 17,500,000.00
102 Kabel NYM 3 X 4 mm2 m1 22,000.00
103 Kabel Tray 30 cm ( 300 x 100 ) m1 500,000.00
104 Kabel Tray 20 cm ( 200 x 100 ) m1 300,000.00
105 Kabel Tray 15 cm ( 150 x 100 ) m1 250,000.00
106 Kabel Tray 10 cm ( 100 x 100 ) m1 125,000.00
107 Kabel Leader 100 cm ( 1000 x 100 ) m1 100,000.00
108 Kabel STP AWG # 18 1 pair m1 80,000.00
109 Kabel ITC 2 x dia. 0,6 mm m1 3,500.00
110 LAMPU SOROT LED 38 W bh 275,000.00
111 Lift Pasanggers ( 15P/1000kG/60/5CO ) unit 625,000,000.00
112 Main Bell bh 750,000.00
113 Manual Breack glass bh 350,000.00
114 MCB, 32 A / 3 PH/ 16 kA bh 350,000.00
115 MCB, 25 A / 3 PH/10 KA bh 75,000.00
116 MCB, 20 A / 3 PH/16 KA bh 65,000.00
117 MCB, 20 A / 3 PH/10 KA bh 210,000.00
118 MCB, 20 A / 1 PH/10 KA bh 90,000.00
119 MCB, 16 A / 3 PH/10KA bh 450,000.00
120 MCB, 16 A / 1 PH/10 KA bh 450,000.00
121 MCB, 10 A / 3 PH/10KA bh 225,000.00
122 MCB, 10 A / 1 PH/10 KA bh 125,000.00
123 MCB, 6 A / 1 PH/10 KA bh 90,000.00
124 MCB, 6 A / 1 PH/6 KA bh 65,000.00
125 MCB, 4 A / 1 PH/6 KA bh 75,000.00
126 MCCB, 800 A / 4p/35 KA bh 850,000.00
127 MCCB, 350 - 630 A / 3p/25 KA bh 950,000.00
128 MCCB, 175 - 250 A / 32 KA bh 1,050,000.00
129 MCCB, 125 - 160 A / 36 KA bh 1,800,000.00
130 MCCB, 80 - 160 A / 22 KA bh 950,000.00
131 MCCB, 80 - 125 A / 22 KA bh 850,000.00
132 MCCB, 80 - 100 A / 22 KA bh 650,000.00
133 MCCB, 40 - 80 A / 22 KA bh 550,000.00
134 MCCB, 30 - 63 A / 22 KA bh 450,000.00
135 MCCB, 30 - 50 A / 3p/22 KA bh 425,000.00
136 MCFA ( Master Control Fire Alarm ) termasuk Repeat Panel, Nicad Battery + Charger 1 loop unit 4,000,000.00
137 Meter Air bh 175,000.00
138 Mixer Frame w/ Module unit 3,500,000.00
139 Motorized for MCCB' bh 4,000,000.00
140 Network Video Recorder ( NVR ) m1 16,000.00
141 NYM 3 x 2,5 MM2 m1 17,000.00
142 NYY 3 x 4 MM2 m1 18,000.00
143 NYY 1 x240 MM2 m1 19,000.00
144 NYY 4 x120 MM2 m1 20,500.00
145 NYY 4 x 70 MM2 m1 21,000.00
146 NYY 4 x 50 MM2 m1 35,000.00
147 NYY 1 x 150 MM2 m1 28,500.00
148 NYY 4 x16 MM2 m1 32,500.00
149 NYY 4 x10 MM2 m1 19,000.00
150 NYY 3 x6 MM2 m1 17,500.00
151 N2XSY,1c X 70 mm2 m1 3,900.00
152 NYFGbY 4 x 10 MM2 m1 5,500.00
153 NYMHY 3 X 1,5 MM2 m1 7,500.00
154 OU + IU, Kapasitas : 4500 Btuh/h - Wall Type unit 4,250,000.00
155 OU + IU, Kapasitas : 7600 Btuh/h - Wall Type unit 4,250,000.00
156 OU + IU, Kapasitas : 9000 Btuh/h - Wall Type unit 4,250,000.00
157 OU + IU, Kapasitas : 10500 Btuh/h - Wall Type unit 5,000,000.00
158 OU + IU, Kapasitas : 12000 Btuh/h - Wall Type unit 5,500,000.00
159 OU + IU, Kapasitas : 13600 Btuh/h - Wall Type unit 6,000,000.00
160 OU + IU, Kapasitas : 18000 Btuh/h - Wall Type Unit 6,500,000.00
161 OU + IU, Kapasitas : 22500 Btuh/h - Wall Type Unit 10,500,000.00
162 OU + IU, Kapasitas : 14500 Btuh/h - Cassete Type unit 22,500,000.00
163 OU + IU, Kapasitas : 15000 Btuh/h - Cassete Type unit 25,000,000.00
164 OU + IU, Kapasitas : 20000 Btuh/h - Cassete Type unit 22,500,000.00
165 OU + IU, Kapasitas : 21000 Btuh/h - Cassete Type unit 20,500,000.00
166 OU + IU, Kapasitas : 22500 Btuh/h - Cassete Type unit 22,500,000.00
167 OU + IU, Kapasitas : 25600 Btuh/h - Cassete Type unit 22,500,000.00
168 OU + IU, Kapasitas : 29000 Btuh/h - Cassete Type unit 22,500,000.00
169 OU + IU, Kapasitas : 32000 Btuh/h - Cassete Type unit 22,500,000.00
170 OU + IU, Kapasitas : 24000 Btuh/h - Cassete Type unit 22,500,000.00
171 OU + IU, Kapasitas : 42000 Btuh/h - Cassete Type (multy flow) unit 45,000,000.00
172 OU + IU, Kapasitas : 45000 Btuh/h - Cassete Type unit 42,500,000.00
173 Pelat Orifice dia 100 mm bh 750,000.00
174 Pelat Orifice dia. 50 mm bh 650,000.00
175 Personal Computer set 6,500,000.00
176 Pilot Lamp bh 125,000.00
177 Pipa Conduit m1 2,500.00
178 Pipa konduit PVC Hight Inpact m1 3,500.00
179 Pipa drain, PVC dia. 20 mm + Isolasi m1 12,500.00
180 Pipa Refrigerant, Ø 9,5 mm + Ø 19,5 mm + Isolasi EPDM m1 81,034.48
180 Pompa Transfer, kapasitas : 150 Lpm/ head 42 meter unit 22,500,000.00
181 Pompa Filter, kapasitas : 100 Lpm/ head 35 meter unit 15,000,000.00
182 Pompa Sumpit, kap. 50 Lpm/ head: 10 meter unit 17,500,000.00
183 Pressure Gauge bh 2,500,000.00
184 Puse Carrier 4 A bh 500.00
185 PVC dia. 1/2” m1 4,666.67
186 PVC dia. 3/4” m1 5,833.33
187 PVC Dia. 1” m1 12,500.00
188 PVC Dia. 1 1/4” m1 13,500.00
189 PVC Dia. 1 1/2” m1 17,500.00
190 PVC Dia. 2” m1 18,500.00
191 PVC Dia. 2 1/2” m1 22,500.00
192 PVC Dia. 3” m1 32,500.00
193 PVC Dia. 4” m1 37,500.00
194 PVC Dia. 6” m1 55,000.00
195 PVC Dia. 8” m1 65,000.00
196 Roof Drain dia. 50 mm m1 27,500.00
197 Roof Drain dia. 65 mm m1 35,000.00
198 Roof Drain dia. 100 mm m1 45,000.00
199 RM TL LED 2 x 16 Watt / Reflector M6 bh 285,000.00
200 RM TL LED 1 x 16 Watt / Reflector M6 bh 280,000.00
201 Roof Tank ( PRF ), kapasitas 6000 L unit 75,000,000.00
202 Safety Valve Dia. 100 mm bh 500,000.00
203 Saklar Tunggal bh 75,000.00
204 Saklar Ganda bh 85,000.00
205 Saklar Hotel bh 175,000.00
206 Saklar Grid ( 6 modul ) bh 225,000.00
207 sambungan aIir bersih, PDAM, diameter 40 mm ttk 25,000.00
208 Sand Filter kapasitas : 100 Lpm unit 12,500,000.00
209 Septic Tank ( Biological ) kapasitas : 60 m3/hari unit 3,500,000.00
210 Speaker Selector unit 750,000.00
211 Sight Glass diameter 25 mm bh 75,000.00
212 Siammesse Connection - Type S - 7 ( 4 '' x 2,5 " x 2,5 '' ) unit 1,250,000.00
213 Socket Telephone bh 20,000.00
214 Socket Data ( RG-45 ) bh 22,500.00
215 Spot Light LED 3 Watt bh 85,000.00
216 Sumur Resapan ( Buist beton + galian ) unit 1,750,000.00
217 Smoke Detector bh 450,000.00
218 Stop Kontak 10 A/16A/1Phase bh 25,000.00
219 Stop kontak dinding 2 x16 A bh 75,000.00
220 temper Switch bh 25,000.00
221 TL LED 1 X 16 Watt / Cover Clear Acrilic bh 125,000.00
222 Trafo, kap. 500 kVA unit 7,500,000.00
223 UPS 2 kVa c/w Nicad Batere, Rectifier ( 2 Jam ) unit 750,000.00
224 Visual Alarm bh 175,000.00
225 Water Level Control ( WLC ) set 7,500,000.00
226 Y - Strainer 10 K dia. 40 mm bh 250,000.00
227 Y - Strainer 10 K dia. 50 mm bh 250,000.00

III HARGA UPAH PEKERJA


1 Pekerja OH 85,000.00
2 Tukang OH 90,000.00
3 Tukang batu OH 90,000.00
4 Tukang besi OH 90,000.00
5 Tukang cat OH 90,000.00
6 Tukang kayu OH 90,000.00
7 Kepala tukang OH 95,000.00
8 Mandor OH 100,000.00
9 Supir OH 100,000.00
10 Tukang Gali OH 90,000.00
11 Tukang Tanam OH 90,000.00
12 Tukang Penyiraman OH 90,000.00
UPAH KERJA

NO TENAGA OH UPAH
1 2 3 4

1 Pekerja oh 85,000
2 Tukang oh 90,000
3 Kepala Tukang oh 95,000
4 Mandor oh 110,000
5 supir oh 95,000
6 Ass supir oh 85,000
7 Operator oh 125,000
8 Teknis Listrik oh 100,000