NO. URAIAN PEKERJAAN VOL SAT (Rp) (Rp) 1 2 9 10 11 12 I. Pekerjaan Fabrikasi & InstallTemporary Support 1. Fabrikasi Temporary Support (HB 400x400x13x21) 4,128.00 kg 32,500.00 134,160,000.00 2. Base Plate Temporary Support (Plat 20mm) 78.50 kg 26,000.00 2,041,000.00 Sub. Total 136,201,000.00 Pembulatan 136,210,000.00
II. Pekerjaan Perbaikan Kolom Coal Shed
1. Pembongkaran Kolom Beton Existhing 2.16 m3 1,950,000.00 4,212,000.00 2. Pembongkaran Pilecap Beton Existhing 7.50 m3 1,950,000.00 14,625,000.00 3. Pengecoran Pilecap 7.50 m3 1,300,000.00 9,750,000.00 4. Pembesian Pilecap 1,500.00 kg 10,000.00 15,000,000.00 5. Begesting Pilecap 30.00 m2 150,000.00 4,500,000.00 6. Pengecoran Kolom Beton 2.16 m3 1,300,000.00 2,808,000.00 7. Pembesian Kolom 432.00 kg 10,000.00 4,320,000.00 8. Begesting Kolom 8.64 m2 150,000.00 1,296,000.00 9. Pekerjaan Hilti antara beton baru dan lama 40.00 titik 455,000.00 18,200,000.00 Sub. Total 74,711,000.00 Pembulatan 74,720,000.00