Diketahui, Dibuat,
CAMAT GANTARANG KETUA PANITIA PEMBANGUNAN,
I Pek. Persiapan
1. Pek. Pas. Bownplank 1.00 Ls 500,000.00 500,000.00
2. Pek. Pembongkaran Atap Existing 1.00 Ls 1,500,000.00 1,500,000.00
Jumlah 2,000,000.00
II Pek. Tanah dan Pondasi
1. Pek. Galian Tanah Pondasi 12.50 m3 15,800.00 197,450.46
2. Pek. Urugan Kembali 3.12 m3 7,575.00 23,665.94
3. Pek. Pasir Urug (Di Bawah Pondasi) 1.02 m3 111,150.00 113,313.76
4. Pek. Lantai Kerja t = 5 cm (Di Bawah Poer) 1.20 m2 26,697.03 32,143.22
5. Pek. Pondasi Batu Kosong 2.30 m3 255,945.00 587,813.52
6. Pek. Pondasi Batu Gunung 1:4 3.60 m3 485,425.00 1,747,131.95
7. Pek. Pondasi Trassram 1/2 Bata (Tangga) 9.55 m2 72,295.00 690,325.98
8. Pek. Pondasi Poer P1 4.00 Bh 330,105.98 1,320,423.91
9. Pek. Stek Poer P1 4.00 Bh 264,670.41 1,058,681.66
Jumlah 5,770,950.40
III Pek. Beton Bertulang
1. Pek. Sloef S1 (15/20)
-Beton K175 0.51 m3 581,818.17 298,542.54
-Besi Beton 122.56 Kg 9,970.00 1,221,941.13
-Bekisting 3x Pakai 6.84 m2 45,109.67 308,622.30
2. Pek. Sloef S2 (15/20)
-Beton K175 0.15 m3 581,818.17 89,192.73
-Besi Beton 26.33 Kg 9,970.00 262,552.29
-Bekisting 3x Pakai 2.04 m2 45,109.67 92,204.16
3. Kolom Type K1
-Beton K175 2.04 m3 581,818.17 1,185,182.24
-Besi Beton 230.15 Kg 9,970.00 2,294,605.89
-Bekisting 3x Pakai 29.53 m2 87,121.00 2,572,292.83
4. Kolom Type K2 (Dia. 25cm)
-Beton K175 2.42 m3 581,818.17 1,408,862.32
-Besi Beton 133.32 Kg 9,970.00 1,329,152.78
-Bekisting 3x Pakai 23.78 m2 87,121.00 2,071,848.55
5. Kolom Type K3 15/15
-Beton K175 0.22 m3 581,818.17 130,503.21
-Besi Beton 34.53 kg 9,970.00 344,313.71
-Bekisting 3x Pakai 6.87 m2 87,121.00 598,207.63
6. Kolom Praktis di Atas Kolom Bundar (15/15)
-Beton K175 0.37 m3 581,818.17 215,528.72
-Besi Beton 81.79 kg 9,970.00 815,457.27
-Bekisting 3x Pakai 11.34 m2 87,121.00 987,952.14
7. Kolom 15/15 Pada Menara Bag. Atas
-Beton K175 0.34 m3 581,818.17 199,735.85
-Besi Beton 79.28 kg 9,970.00 790,384.11
-Bekisting 3x Pakai 14.30 m2 87,121.00 1,246,178.78
8. Kolom Dia. 10cm Pada Menara
-Beton K175 0.14 m3 581,818.17 78,994.28
-Besi Beton 57.79 Kg 9,970.00 576,213.04
-Bekisting 3x Pakai 5.43 m2 87,121.00 472,711.58
NO URAIAN PEKERJAAN VOL. SAT HRG. SAT. (Rp.) JML. HARGA
Rabat t=5cm
Lantai Keramik 30/30 (Teras)
Lantai Keramik 30/30 (Tangga)
Lantai Keramik 30/30 (Tempat Wudhu)
Lantai Keramik 30/30 (WC)
Dinding Keramik 20/25 (WC/t4 Wudhu)
30. Pek. Plesteran Beton kolom
31. Konsol
~beton k175
~Besi beton Diameter Panjang Kg/m1
10 1.8 0.62
10 3.75 0.62
~Bekisting
3.848 m3
0.288 m3
0.277 m3
0.060 m3
0.394 m3
1.152 m3
1.145 m3
1.872 m3
1.727 m3
9.549 m2
1.204 m2
0.483 m3
9.6696
10.1118
2.66352
89.77968 Kg
3.468 m2
0.356 m3
50.294
13.582
63.876 Kg
5.160 m2
0.51312 m3
99.542688
23.0191104
122.561798 Kg
6.8416 m2
0.1533 m3
19.54948
6.784752
26.334232 Kg
2.044 m2
2.037032 m3
170.928448
59.2225938
230.151042 Kg
29.52552 m2
2.421482 m3
106.61148
26.7037437
133.315224 Kg
9.79209
13.989186
23.781276 m2
0.224 m3
28.381
6.154
34.535 Kg 2645858-arfan
2473001-guntur
6.8664 m2 abd.dg sr no.123C
441515-90223
0.370 m3
73.656
8.1351
81.7911 Kg
11.34 m2
1.35 m3
156.112
45.94956
202.06156 Kg
21.6 m2
7.312
2.264
9.576 m2
20.277 m2
9.576 m2
3.6936 m2
21.78 m2
5.325 m2
5.85 m2
2.68974 m3
1.41205 m3 28.241
1.6893 m3
4.22325 m3
200.85228
70.122
76.5811029
347.555383
15/25
64.7565 m2
2.53395 m3
200.85228
89.34462
290.1969
42.2325 m2
0.7428 m3
61.6528
30.7982871
92.4510871 Kg
13.618 m2
0.513 m3
53.94
21.7693929
75.7093929 Kg
9.405 m2
0.7288125 m3
72.2982
26.44235
98.74055 Kg
12.63275 m2
86.8000 m2
28.408
115.2080 m2
196.4505 m2
5.4407 m3
10.250 m3
108.8130 m2
108.81 m2
8.30325 m2
7.6 m2
7.8 m2
44.6 m2
84.145946
53.7948
115.4232
253.363946 m2
0.21132 m3
26.784
55.8
82.584
4.618 m2
0.450 m3
51.584
19.2233143
70.8073143
12 m2
0.4824 m3
8.1344
21.731328
29.865728 Kg
8.844 m2
0.58305 m3 ###
29.295
6.80225 m2
0.77 m3
38.44
22.81496
61.25496 kg
6.16 m2
DAFTAR SATUAN HARG
PEMBANGUNAN MASJID A
No.
A
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
B
-
-
-
-
-
-
-
C
-
-
-
D
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
F
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
G
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
No.
1
2
4
DAFTAR SATUAN HARGA BAHAN DAN UPAH
PEMBANGUNAN MASJID ASY SYUKUR BULUKUMBA
BAHAN KAYU
Kayu Kelas I (Balok) Sawmil Rp 7,300,000.00
Kayu Kelas I (Papan) Sawmil Rp 7,400,000.00
Kayu Kelas II (Balok) Rp 3,300,000.00
Kayu Kelas II (Papan) Rp 3,600,000.00
Kayu Kelas III (Balok) Rp 1,850,000.00
Kayu Kelas III (Papan) Rp 2,100,000.00
Kayu Dolken dia 8 - 10/4 meter Rp 15,000.00
BAHAN LANTAI
Tegel Keramik Warna 60x60 cm Rp 142,000.00
Tegel Keramik Warna 40x40 cm Rp 53,000.00
Tegel Keramik Warna 30x30 cm Rp 4,818.18
Pelaksana,
SATUAN
/m3
/m3
/m3
/m3
/m3
/m3
/m3
/m3
/m3
/m3
/m3
/m3
/Kg
/Buah
/Kg
/m3
/m3
/m3
/m3
/m3
/m3
/Batang
/Dos
/Dos
/Bh 414,521.04
/m2 95,000.00
/m2
/m2
/M'
/Lbr
/Bh
/Bh
/Bh
/Bh
/Bh
/Bh
/Bh
/Bh
/Bh
/Bh
/Kg
/Kg
/Kg
/Kg
/Kg
/Kg
/Kg
/Bh
/Ltr
/Btg
/m1
/m1
/Roll
/Bh
/Bh
/Bh
SATUAN
Org/Hr
Org/Hr
Org/Hr
Org/Hr
Org/Hr
Org/Hr
Org/Hr
Org/Hr
Org/Hr
Org/Hr
Org/Hr
Org/Hr
Org/Hr
Org/Hr
D MUSTAFA, M.Si.
1 M3 URUGAN PASIR
1.20 M3 Pasir Timbunan / Urugan @ Rp
0.30 Oh Pekerja @ Rp
0.01 Oh Mandor @ Rp
1 M3 URUGAN KEMBALI
0.19 Oh Pekerja @ Rp
0.02 Oh Mandor @ Rp
1 M3 TIMBUNAN TANAH
1.20 M3 Tanah Timbunan @ Rp
0.30 Oh Pekerja @ Rp
0.01 Oh Mandor @ Rp
Faktor Penyusutan 10 %
Upah Kerja
0.10 Oh Pekerja @ Rp
0.05 Oh Tukang Kayu @ Rp
0.005 Oh Kepala Tukang Kayu @ Rp
0.005 Oh Mandor @ Rp
Faktor Penyusutan 10 %
Upah Kerja
0.10 Oh Pekerja @ Rp
0.05 Oh Tukang Kayu @ Rp
0.005 Oh Kepala Tukang Besi @ Rp
0.005 Oh Mandor @ Rp
35,000.00 Rp 14,000.00
45,000.00 Rp 1,800.00
Rp 15,800.00
83,500.00 Rp 100,200.00
35,000.00 Rp 10,500.00
45,000.00 Rp 450.00
Rp 111,150.00
35,000.00 Rp 6,720.00
45,000.00 Rp 855.00
Rp 7,575.00
83,000.00 Rp 99,600.00
35,000.00 Rp 10,500.00
45,000.00 Rp 450.00
Rp 110,550.00
150,000.00 Rp 165,000.00
1,050.00 Rp 171,150.00
115,000.00 Rp 59,800.00
35,000.00 Rp 52,500.00
50,000.00 Rp 30,000.00
60,000.00 Rp 3,600.00
45,000.00 Rp 3,375.00
Rp 485,425.00
150,000.00 Rp 180,000.00
83,500.00 Rp 25,050.00
35,000.00 Rp 27,300.00
50,000.00 Rp 19,500.00
60,000.00 Rp 2,340.00
45,000.00 Rp 1,755.00
Rp 255,945.00
TA, 1 Pc : 5 Ps
550.00 Rp 77,000.00
1,050.00 Rp 23,310.00
115,000.00 Rp 11,730.00
35,000.00 Rp 21,000.00
50,000.00 Rp 10,000.00
60,000.00 Rp 1,200.00
45,000.00 Rp 1,350.00
Rp 145,590.00
ATA, 1 Pc : 4 Ps
550.00 Rp 38,500.00
1,050.00 Rp 12,075.00
115,000.00 Rp 4,945.00
35,000.00 Rp 10,500.00
50,000.00 Rp 5,000.00
60,000.00 Rp 600.00
45,000.00 Rp 675.00
Rp 72,295.00
ATA, 1 Pc : 5 Ps
550.00 Rp 38,500.00
1,050.00 Rp 10,164.00
115,000.00 Rp 5,175.00
35,000.00 Rp 10,500.00
50,000.00 Rp 5,000.00
60,000.00 Rp 600.00
45,000.00 Rp 675.00
Rp 70,614.00
1,050.00 Rp 6,552.00
115,000.00 Rp 2,760.00
35,000.00 Rp 7,000.00
50,000.00 Rp 7,500.00
60,000.00 Rp 900.00
45,000.00 Rp 450.00
Rp 25,162.00
1,050.00 Rp 5,443.20
115,000.00 Rp 2,990.00
35,000.00 Rp 7,000.00
50,000.00 Rp 7,500.00
60,000.00 Rp 900.00
45,000.00 Rp 450.00
Rp 24,283.20
1,050.00 Rp 34,125.00
35,000.00 Rp 52,500.00
50,000.00 Rp 50,000.00
60,000.00 Rp 6,000.00
45,000.00 Rp 360.00
Rp 142,985.00
Rp 14,298.50
BUK, 1 Pc : 3 Ps : 5 Kr TEBAL 7 Cm
1,050.00 Rp 19,845.00
117,000.00 Rp 5,224.05
130,000.00 Rp 6,922.74
35,000.00 Rp 4,042.50
50,000.00 Rp 962.50
60,000.00 Rp 117.60
45,000.00 Rp 261.45
Rp 37,375.84
Untuk t = 10 cm Rp 53,394.06
U BESI ULIR
8,600.00 Rp 9,030.00
19,000.00 Rp 285.00
35,000.00 Rp 245.00
50,000.00 Rp 350.00
60,000.00 Rp 42.00
45,000.00 Rp 18.00
Rp 9,970.00
2,100,000.00 Rp 84,000.00
19,000.00 Rp 5,700.00
11,990.00 Rp 1,199.00
35,000.00 Rp 18,200.00
50,000.00 Rp 13,000.00
60,000.00 Rp 1,560.00
45,000.00 Rp 1,170.00
Rp 124,829.00
2,100,000.00 Rp 94,500.00
19,000.00 Rp 5,700.00
11,990.00 Rp 1,199.00
35,000.00 Rp 18,200.00
50,000.00 Rp 13,000.00
60,000.00 Rp 1,560.00
45,000.00 Rp 1,170.00
Rp 135,329.00
2,100,000.00 Rp 84,000.00
19,000.00 Rp 7,600.00
11,990.00 Rp 2,398.00
3,300,000.00 Rp 49,500.00
128,000.00 Rp 44,800.00
15,000.00 Rp 30,000.00
35,000.00 Rp 23,100.00
50,000.00 Rp 16,500.00
60,000.00 Rp 1,980.00
45,000.00 Rp 1,485.00
Rp 261,363.00
2,100,000.00 Rp 84,000.00
19,000.00 Rp 7,600.00
11,990.00 Rp 2,398.00
3,300,000.00 Rp 59,400.00
128,000.00 Rp 44,800.00
15,000.00 Rp 30,000.00
35,000.00 Rp 23,100.00
50,000.00 Rp 16,500.00
60,000.00 Rp 1,980.00
45,000.00 Rp 1,485.00
Rp 271,263.00
2,100,000.00 Rp 84,000.00
19,000.00 Rp 7,600.00
11,990.00 Rp 2,398.00
3,300,000.00 Rp 49,500.00
128,000.00 Rp 44,800.00
15,000.00 Rp 90,000.00
35,000.00 Rp 23,100.00
50,000.00 Rp 16,500.00
60,000.00 Rp 1,980.00
45,000.00 Rp 1,485.00
Rp 321,363.00
1,050.00 Rp 342,300.00
117,000.00 Rp 63,514.29
130,000.00 Rp 99,088.89
35,000.00 Rp 57,750.00
50,000.00 Rp 13,750.00
60,000.00 Rp 1,680.00
45,000.00 Rp 3,735.00
Rp 581,818.17
1,050.00 Rp 389,550.00
117,000.00 Rp 58,332.86
130,000.00 Rp 100,822.22
35,000.00 Rp 57,750.00
50,000.00 Rp 13,750.00
60,000.00 Rp 1,680.00
45,000.00 Rp 3,735.00
Rp 625,620.08
Rp 581,818.17
Rp 997,000.00
x Pakai.. Rp 892,317.93
Rp 2,471,136.10
KAYU KELAS - I
7,300,000.00 Rp 8,030,000.00
35,000.00 Rp 210,000.00
50,000.00 Rp 1,000,000.00
60,000.00 Rp 120,000.00
45,000.00 Rp 13,500.00
Rp 9,373,500.00
7,400,000.00 Rp 296,000.00
35,000.00 Rp 35,000.00
50,000.00 Rp 125,000.00
60,000.00 Rp 15,000.00
45,000.00 Rp 2,250.00
Rp 473,250.00
7,400,000.00 Rp 177,600.00
138,000.00 Rp 97,980.00
50,000.00 Rp 100,000.00
60,000.00 Rp 12,000.00
35,000.00 Rp 28,000.00
45,000.00 Rp 1,800.00
Rp 239,780.00
350,000.00 Rp 350,000.00
164,000.00 Rp 73,800.00
50,000.00 Rp 55,000.00
60,000.00 Rp 6,600.00
35,000.00 Rp 12,600.00
45,000.00 Rp 1,620.00
350,000.00 Rp 35,000.00
Rp 534,620.00
138,000.00 Rp 151,800.00
35,000.00 Rp 525.00
50,000.00 Rp 7,500.00
60,000.00 Rp 900.00
45,000.00 Rp 33.75
Rp 160,758.75
12,500.00 Rp 26,250.00
11,700.00 Rp 9,711.00
5,670.00 Rp 8,505.00
55,000.00 Rp 20,020.00
120,000.00 Rp 3,600.00
19,000.00 Rp 2,090.00
Rp 70,176.00
Rp 7,017.60
Bahan A Rp 77,193.60
35,000.00 Rp 3,500.00
50,000.00 Rp 2,500.00
60,000.00 Rp 300.00
45,000.00 Rp 225.00
Upah B Rp 6,525.00
Rp 83,718.60
12,500.00 Rp 26,250.00
11,700.00 Rp 9,711.00
5,670.00 Rp 8,505.00
51,000.00 Rp 18,564.00
120,000.00 Rp 3,600.00
19,000.00 Rp 2,090.00
Rp 68,720.00
Rp 6,872.00
Bahan A Rp 75,592.00
35,000.00 Rp 3,500.00
50,000.00 Rp 2,500.00
50,000.00 Rp 250.00
45,000.00 Rp 225.00
Upah B Rp 6,475.00
Rp 82,067.00
6,000.00 Rp 6,300.00
18,000.00 Rp 18,900.00
35,000.00 Rp 36,750.00
40,000.00 Rp 42,000.00
310.00 Rp 3.10
35,000.00 Rp 1,750.00
50,000.00 Rp 2,500.00
60,000.00 Rp 300.00
45,000.00 Rp 135.00
A Rp 10,988.10
B Rp 23,588.10
C Rp 41,438.10
D Rp 46,688.10
8,200.00 Rp 131,200.00
500.00 Rp 16,000.00
7,000.00 Rp 10,500.00
4,500.00 Rp 4,500.00
500.00 Rp 2,000.00
3,500.00 Rp 14,000.00
1,000.00 Rp 1,000.00
1,000.00 Rp 1,000.00
50,000.00 Rp 25,000.00
35,000.00 Rp 17,500.00
Rp 222,700.00
8,200.00 Rp 98,400.00
500.00 Rp 10,000.00
7,000.00 Rp 14,000.00
4,500.00 Rp 4,500.00
500.00 Rp 3,000.00
3,500.00 Rp 3,500.00
1,000.00 Rp 1,000.00
1,000.00 Rp 1,000.00
45,400.00 Rp 22,700.00
35,000.00 Rp 17,500.00
Rp 175,600.00
500,000.00 Rp 500,000.00
180,000.00 Rp 180,000.00
350,000.00 Rp 350,000.00
35,000.00 Rp 700.00
50,000.00 Rp 10,000.00
60,000.00 Rp 1,200.00
45,000.00 Rp 45.00
A Rp 511,945.00
B Rp 191,945.00
C Rp 361,945.00
40,000.00 Rp 40,000.00
25,000.00 Rp 25,000.00
17,500.00 Rp 17,500.00
56,000.00 Rp 56,000.00
55,000.00 Rp 55,000.00
25,000.00 Rp 25,000.00
17,500.00 Rp 17,500.00
26,000.00 Rp 26,000.00
35,000.00 Rp 525.00
50,000.00 Rp 7,500.00
60,000.00 Rp 900.00
45,000.00 Rp 33.75
A Rp 48,958.75
B Rp 33,958.75
C Rp 26,458.75
D Rp 64,958.75
E Rp 63,958.75
F Rp 33,958.75
G Rp 26,458.75
H Rp 34,958.75
15,800.00 Rp 220,410.00
79,542.50 Rp 1,407,902.25
110,550.00 Rp 138,187.50
2,200,000.00 Rp 881,100.00
7,575.00 Rp 10,567.13
28,885.20 Rp 511,268.04
85,767.00 Rp 214,417.50
2,500,000.00 Rp 750,000.00
14,298.50 Rp 253,083.45
50,000.00 Rp 50,000.00
130,000.00 Rp 162,500.00
175,560.00 Rp 2,633,400.00
Rp 7,232,835.87
4,818.18 Rp 53,530.00
8,480.00 Rp 53,000.00
51,134.32 Rp 143,176.09
110,000.00 110,000.00
1,050.00 Rp 10,500.00
115,000.00 Rp 5,175.00
1,000.00 Rp 1,500.00
35,000.00 Rp 21,700.00
50,000.00 Rp 17,500.00
60,000.00 Rp 2,100.00
45,000.00 Rp 1,350.00
Jum A Rp 113,355.00
Jum B Rp 112,825.00
Jum C Rp 203,001.09
Jum D Rp 169,825.00
1,363.64 Rp 4,540.92
22,000.00 Rp 36,666.67
15,000.00 Rp 37,500.00
1,050.00 Rp 1,197.00
115,000.00 Rp 345.00
1,000.00 Rp 25.00
35,000.00 Rp 3,150.00
50,000.00 Rp 4,500.00
60,000.00 Rp 540.00
45,000.00 Rp 225.00
Jum A Rp 14,522.92
Jum B Rp 46,648.67
Jum C Rp 47,482.00
2,250.00 Rp 45,000.00
1,900.00 Rp 47,500.00
6,100.00 Rp 45,201.00
51,134.32 Rp 143,176.09
1,050.00 Rp 9,765.00
115,000.00 Rp 2,070.00
1,000.00 Rp 1,500.00
35,000.00 Rp 21,000.00
50,000.00 Rp 22,500.00
60,000.00 Rp 2,700.00
45,000.00 Rp 1,350.00
Jum A Rp 105,885.00
Jum B Rp 108,385.00
Jum C Rp 106,086.00
Jum D Rp 204,061.09
68,000.00 Rp 81,600.00
1,000.00 Rp 4,000.00
50,000.00 Rp 6,000.00
60,000.00 Rp 3,600.00
35,000.00 Rp 210.00
45,000.00 Rp 270.00
Rp 95,680.00
50,000.00 Rp 55,000.000
1,000.00 Rp 6,000.000
50,000.00 Rp 7,500.000
60,000.00 Rp 4,200.000
35,000.00 Rp 280.000
45,000.00 Rp 270.000
Rp 73,250.00
ANK 2 x 30
20,000.00 Rp 1,200.00
12,500.00 Rp 37,500.00
15,000.00 Rp 15,750.00
50,000.00 Rp 5,000.00
60,000.00 Rp 600.00
35,000.00 Rp 3,500.00
45,000.00 Rp 2,250.00
4,725.00 Rp 4,725.00
Rp 70,525.00
3,300,000.00 Rp 3,630,000.00
8,750.00 Rp 131,250.00
19,000.00 Rp 57,000.00
50,000.00 Rp 360,000.00
60,000.00 Rp 43,200.00
35,000.00 Rp 84,000.00
45,000.00 Rp 5,400.00
Rp 4,310,850.00
Estimasi Biaya Proyek Pembvangunan Kantor DPR Kota Kendari
Gedung A
Lantai I
~Gedung Utama 1376 m2 3,000,000.00 4,128,000,000.00
~Teras 170 m2 1,500,000.00 255,000,000.00
~Selasar Kiri dan Kanan 56 m2 1,500,000.00 84,000,000.00
Lantai II
~Bagian Muka 320 m2 3,270,000.00 1,046,400,000.00
~Bagian Belakang 458 m2 3,270,000.00 1,497,660,000.00
~Selasar Atas Kiri dan Kanan 108 m2 1,635,000.00 176,580,000.00
7,187,640,000.00
Gedung B
~Bangunan 1430 m2 3,000,000.00 4,290,000,000.00
~Teras 36 m2 1,500,000.00 54,000,000.00
~Teras Belakang dn Apron 160 m2 1,500,000.00 240000000
4,584,000,000.00
11,771,640,000.00
Site Development
~Pematangan Tanah 29250 m2 50,000.00 1,462,500,000.00
~Jalan 2015 m2 179,000.00 360,685,000.00
~Parkir 4089 m2 179,000.00 731,931,000.00
~Rumput/Taman 3086 m2 20,000.00 61,720,000.00
~Pelataran Upacara 2721 m2 50,000.00 136,050,000.00
~Casteen
~Pagar Tembok 367 m1 300,000.00 110,100,000.00
~Pagar Profil 367 m1 500,000.00 183,500,000.00
~Saluran Air /Drainase Site 1 m1 90,937,000.00 90,937,000.00
~Listrik Kompleks 1 Ls 90,937,000.00 90,937,000.00
Total 15,000,000,000.00
Terbilang: Limabelas Milyar Rupiah
Arsitek/Cost Estimator
DIBUAT:
PANITIA PEMBANGUNAN
RENOVASI MASJID RAYA NURUL ITTIHAD PONRE BULUKUMBA