I Pekerjaan Persiapan
1 Pembersihan Lapangan 1.00 Ls
2 Pekerjaan Pemasangan Bouwplank 120.00 m'
3 Direksi Keet, Gudang Dan Los Kerja 24.00 m2
4 Listrik Proyek (Tahap III) 4.00 Bln
5 Air Proyek (Tahap III) 4.00 Bln
6 P3K (Tahap III) 1.00 Ls
7 Pagar Depan (Pintu Masuk) 1.00 Ls
8 Test / Uji Laboratorium 1.00 Ls
9 Pek. Anti Rayap System Injeksi 622.39 m2
10 Sewa Lift Barang 4.00 Bln
11 Sewa Tower Crane Kap. 50 Ton 4.00 Bln
12 Jamsostek/Asuransi Pekerja (Tahap III) 1.00 Ls
13 Keamanan Proyek = 4 Orang (2 Siff) (Tahap III) 4.00 Bln
14 Bak Penampungan Air Dan Instalasi 1.00 Ls
15 Shop Drawing & Asbuild Drawing (Tahap III) 1.00 Ls
Pek. Persiapan
HARGA SAT. JML. HARGA
10,000,000.00 Tahap I
93,300.00 Tahap I
500,000.00 Tahap I
3,000,000.00 12,000,000.00
1,500,000.00 6,000,000.00
4,000,000.00 4,000,000.00
2,000,000.00 Tahap I
5,000,000.00 Tahap I
150,000.00 -
20,000,000.00 Tahap I
31,000,000.00 Tahap I
18,795,000.00 18,795,000.00
4,800,000.00 19,200,000.00
5,000,000.00 Tahap I
3,500,000.00 3,500,000.00
63,495,000.00
Makassar, 2011
Konsultan Perencana,
CV. Bajirupa Konsultan
Ir. BADARUDDIN
Direktur
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN GEDUNG BADAN KOORDINASI PENANAMAN MODAL DAERA
PROVINSI SULAWESI SELATAN
Struktur - Ksll
HARGA SAT. JML. HARGA
2,650,000.00 Di CCO
0.00
Makassar, 2011
Konsultan Perencana,
CV. Bajirupa Konsultan
Ir. BADARUDDIN
Direktur
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN STADION BAROMBONG
PROVINSI SULAWESI SELATAN
I PEKERJAAN PERSIAPAN
1 Pengukuran dan penentuan titik 1.00 Ls Rp 19,120,000.00
2 Loading Test Tiang Pancang 2.00 ttk Rp 60,000,000.00
3 Mobilisasi Dan Demobilisasi Alat Pancang 1.00 Ls Rp 20,000,000.00
Jumlah I
Jumlah II
Real Cost
Jumlah
Dibulatkan
Makassar , Mare
Rp 19,120,000.00
Rp 120,000,000.00
Rp 20,000,000.00
Rp 159,120,000.00
Rp 6,571,890,000.00
Rp 5,398,998,750.00
Rp 323,492,400.00
Rp 126,900,000.00
Rp 12,421,281,150.00
Rp 12,580,401,150.00
Rp 1,258,040,115.00
Rp 13,838,441,265.00
Rp 13,838,440,000.00
I PEKERJAAN PERSIAPAN
1 Pengukuran dan penentuan titik 1.00 Ls Rp 9,555,000.00
2 Pembuatan Direksi Keet, Uk. 3 x 4 1.00 Ls Rp 10,200,000.00
3 Papan Nama Proyek 1.00 Ls Rp 600,000.00
4 Dokumentasi Dan Pelaporan 1.00 Ls Rp 7,500,000.00
5 Mobilisasi Dan Demobilisasi 1.00 Ls Rp 25,000,000.00
Jumlah I
Jumlah II
Jumlah III
Real Cost
Jumlah
Dibulatkan
Makassar , Mare
Rp 9,555,000.00
Rp 10,200,000.00
Rp 600,000.00
Rp 7,500,000.00
Rp 25,000,000.00
Rp 52,855,000.00
Rp 1,728,542,136.85
Rp 220,563,112.00
Rp 225,064,400.00
Rp 45,000,000.00
Rp 225,000,000.00
Rp 56,250,000.00
Rp 2,500,419,648.85
Rp 4,963,296,000.00
Rp 4,077,492,000.00
Rp 139,461,168.00
Rp 54,708,000.00
Rp 9,234,957,168.00
Rp 11,788,231,816.85
Rp 1,178,823,181.69
Rp 12,967,054,998.54
Rp 12,967,050,000.00
PEKERJAAN PENDAHULUAN
I PEKERJAAN PERSIAPAN
1 Pengukuran dan penentuan titik 1.00 Ls Rp 15,000,000.00
3 Pek. Pembersihan Lokasi 1.00 Ls Rp 15,000,000.00
3 Pembuatan Direksi Keet, Uk. 3 x 4 1.00 Ls Rp 10,200,000.00
4 Papan Nama Proyek 1.00 Ls Rp 600,000.00
5 Dokumentasi Dan Pelaporan 1.00 Ls Rp 11,572,000.00
6 Mobilisasi Dan Demobilisasi 1.00 Ls Rp 30,000,000.00
Jumlah I
Jumlah II
Jumlah I
II PEKERJAAN BETON
1 Pek. Pile Cap P1, Uk. 100 x 180 18.00 Bh
- Galian Tanah Pile Cap 37.62 m3 Rp 40,000.00
- Lantai Kerja Pile Cap, T = 5 cm 1.88 m3 Rp 725,281.88
(beton mutu f'c=7,4 Mpa (K 100), slump (3-6) cm, w/c=0,87)
- Beton mutu f'c=24,0 Mpa (K 275), slump (12 2) cm, w/c=0,53 21.87 m3 Rp 935,392.86
- Besi Beton Ulir 1,825.20 Kg Rp 13,905.00
- Bekisting 2 x Pemakaian 60.48 m2 Rp 114,650.00
Jumlah II
I PEKERJAAN BETON
1 Pek. Balok Beton B1, Uk. 30 x 70
- Beton mutu f'c=21,7 Mpa (K 250), slump (12 2) cm, w/c=0,56 23.21 m3 Rp 914,525.13
- Besi Beton Ulir 4,088.48 Kg Rp 13,905.00
- Besi Beton Polos 1,627.63 Kg Rp 12,855.00
- Bekisting 2 x Pemakaian 187.85 m2 Rp 203,775.00
Jumlah I
I PEKERJAAN BETON
1 Pek. Balok Beton B1, Uk. 30 x 70
- Beton mutu f'c=21,7 Mpa (K 250), slump (12 2) cm, w/c=0,56 32.22 m3 Rp 914,525.13
- Besi Beton Ulir 5,639.63 Kg Rp 13,905.00
- Besi Beton Polos 2,256.77 Kg Rp 12,855.00
- Bekisting 2 x Pemakaian 260.81 m2 Rp 203,775.00
- Beton mutu f'c=19,3 Mpa (K 225), slump (12 2) cm, w/c=0,58 16.49 m3 Rp 902,387.30
- Besi Beton Ulir 2,143.25 Kg Rp 13,905.00
- Besi Beton Polos 1,885.09 Kg Rp 12,855.00
- Bekisting 2 x Pemakaian 302.25 m2 Rp 203,775.00
Jumlah I
I PEKERJAAN BETON
1 Pek. Balok Beton B1, Uk. 30 x 70
- Beton mutu f'c=21,7 Mpa (K 250), slump (12 2) cm, w/c=0,56 24.21 m3 Rp 914,525.13
- Besi Beton Ulir 4,353.08 Kg Rp 13,905.00
- Besi Beton Polos 1,705.56 Kg Rp 12,855.00
- Bekisting 2 x Pemakaian 196.01 m2 Rp 203,775.00
Jumlah I
Real Cost
A ANGGARAN BIAYA (RAB)
N GEDUNG PUSAT PAMERAN
DUSTRIAN DAN PERDAGANGAN
NSI SULAWESI SELATAN
JUMLAH HARGA
KERJAAN PENDAHULUAN
Rp 15,000,000.00
Rp 15,000,000.00
Rp 10,200,000.00
Rp 600,000.00
Rp 11,572,000.00
Rp 30,000,000.00
Rp 82,372,000.00
Rp 2,960,535,909.96
Rp -
Rp -
Rp -
Rp -
Rp 2,960,535,909.96
Rp 3,042,907,909.96
Rp 639,232,000.00
Rp 812,697,600.00
Rp 1,059,657,500.00
Rp 19,768,980.00
Rp 15,510,000.00
Rp 2,546,866,080.00
Rp 1,504,800.00
Rp 1,364,255.21
Rp 20,457,041.79
Rp 25,379,406.00
Rp 6,934,032.00
Rp 3,785,600.00
Rp 3,432,033.85
Rp 43,372,296.00
Rp 47,666,428.99
JUMLAH HARGA
Rp 15,408,960.00
Rp 475,200.00
Rp 430,817.44
Rp 3,591,908.57
Rp 10,091,025.36
Rp 1,981,152.00
Rp 1,998,240.00
Rp 1,332,160.00
Rp 6,038,696.92
Rp 68,529,026.26
Rp 178,914,216.69
Rp 45,124,155.77
Rp 61,021,254.00
Rp 1,206,240.00
Rp 804,160.00
Rp 3,645,266.72
Rp 32,831,452.25
Rp 108,751,005.00
Rp 27,309,847.60
Rp 35,081,480.00
Rp 203,400.00
Rp 135,600.00
Rp 614,676.39
Rp 5,167,067.00
Rp 6,648,536.70
Rp 4,366,496.42
Rp 6,901,475.00
Rp 729,936.00
Rp 486,624.00
Rp 2,205,872.30
Rp 14,834,329.27
Rp 17,592,917.47
Rp 12,135,769.95
Rp 19,813,707.20
Rp 6,285,840.00
Rp 23,739,505.92
Rp 2,677,953.60
Rp 8,638,812.00
Rp 13,739,050.29
Rp 43,650,576.00
Rp 6,286,814.88
Rp 19,366,128.00
Rp 673,482.86
Rp 4,204,872.00
Rp 497,334.24
Rp 1,993,572.00
Rp 27,575,381.43
JUMLAH HARGA
Rp 56,076,973.92
Rp 11,747,927.40
Rp 37,897,645.50
Rp 76,709,697.43
Rp 114,032,124.00
Rp 35,101,383.08
Rp 108,127,548.00
Rp 3,760,279.29
Rp 10,061,658.00
Rp 2,776,782.84
Rp 11,130,777.00
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp 1,477,050,685.77
Rp 4,023,916,765.77
Rp 21,221,555.69
Rp 56,850,244.88
Rp 20,923,224.79
Rp 38,279,133.75
Rp 143,135,620.74
Rp 446,917,824.00
Rp 154,317,458.76
Rp 265,779,657.00
Rp 55,014,173.86
Rp 124,761,255.37
Rp 65,616,314.35
Rp 147,099,466.80
Rp 6,569,957.08
Rp 13,160,848.90
Rp 10,701,484.99
Rp 27,199,560.96
Rp 257,030,230.92
JUMLAH HARGA
Rp 569,429,878.40
Rp 540,649,792.19
Rp 53,848,696.00
Rp 109,506,079.87
Rp 22,941,135.84
Rp 74,005,822.80
Rp 69,234,037.71
Rp 102,919,248.00
Rp 31,680,616.16
Rp 97,590,096.00
Rp 5,769,503.14
Rp 15,437,887.20
Rp 4,260,496.66
Rp 17,078,266.80
Rp 3,506,532.67
Rp 10,296,869.81
Rp 16,102,365.84
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp 3,598,835,337.93
Rp 3,598,835,337.93
Rp 29,464,353.62
Rp 78,418,985.63
Rp 29,010,798.92
Rp 53,147,372.85
Rp 72,830,403.77
Rp 225,932,090.06
Rp 78,377,182.33
Rp 135,234,259.88
Rp 20,209,176.37
Rp 46,245,182.26
Rp 24,200,719.13
Rp 54,036,239.40
JUMLAH HARGA
Rp 14,877,262.39
Rp 29,801,930.18
Rp 24,232,852.37
Rp 61,591,727.34
Rp 114,020,440.02
Rp 252,603,147.35
Rp 239,836,096.25
Rp 35,395,265.71
Rp 71,979,399.36
Rp 15,079,429.20
Rp 48,644,739.00
Rp 57,919,525.71
Rp 86,099,760.00
Rp 26,503,239.20
Rp 81,641,520.00
Rp 4,826,627.14
Rp 12,914,964.00
Rp 3,564,228.72
Rp 14,287,266.00
Rp 3,431,490.14
Rp 10,076,508.78
Rp 15,757,762.68
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp 2,072,191,945.77
Rp 2,072,191,945.77
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
JUMLAH HARGA
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp 12,737,851,959.44
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN GEDUNG PUSAT PAMERAN
DINAS PERINDUSTRIAN DAN PERDAGANGAN
PROVINSI SULAWESI SELATAN
PEKERJAAN PENDAHULUAN
I PEKERJAAN PERSIAPAN Rp.
II PEKERJAAN TANAH DAN LAIN - LAIN Rp.
Makassar,
Disetujui, Konsultan Perencana
Pejabat Pelaksana Teknis Kegiatan (PPTK) CV. SYAFITRI ENGINEE
Mengetahui/Menyetujui,
KEPALA DINAS TATA RUANG DAN PERMUKIMAM
PROVINSI SULAWESI SELATAN
KERJAAN PENDAHULUAN
82,372,000.00
2,960,535,909.96
2,546,866,080.00
1,477,050,685.77
3,598,835,337.93
2,072,191,945.77
12,737,851,959.44
1,273,785,195.94
14,011,637,155.38
14,011,637,000.00
Makassar, 2012
Konsultan Perencana,
CV. SYAFITRI ENGINEERING
Direktur
Mengetahui/Menyetujui,
TATA RUANG DAN PERMUKIMAM
INSI SULAWESI SELATAN
I PEKERJAAN PERSIAPAN
1 Pengukuran dan penentuan titik 1.00 Ls Rp 25,000,000.00
2 Loading Test Tiang Pancang 2.00 ttk Rp 60,000,000.00
Jumlah I
Jumlah II
II
1 Pekerjaan Galian Tanah 306.37 m3 Rp 50,000.00
2 Pekerjaan Timbun Kembali 76.59 m3 Rp 21,500.00
3 Pekerjaan Pasir Urug Bawah Pondasi 29.37 m3 Rp 125,000.00
4 Pekerjaan Pasir Urug Bawah Lantai 28.64 m3 Rp 125,000.00
5 Pekerjaan Tanah Timbunan 172.44 m3 Rp 85,000.00
III
1 Pekerjaan Pile Cap Type A 8.00 bh
Beton K275 24.39 m3 Rp 823,210.00
Pembesian 4,209.66 kg Rp 9,863.44
Bekisting 44.35 m2 Rp 118,000.00
2 Pekerjaan Pile Cap Type B 10.00 bh
Beton K275 22.18 m3 Rp 823,210.00
Pembesian 4,594.33 kg Rp 9,863.44
Bekisting 46.12 m2 Rp 118,000.00
3 Pekerjaan Pile Cap Type C 4.00 bh
Beton K275 6.09 m3 Rp 823,210.00
Pembesian 1,186.14 kg Rp 9,863.44
Bekisting 16.38 m2 Rp 118,000.00
4 Pekerjaan Pile Cap Type D 8.00 bh
Beton K275 6.67 m3 Rp 823,210.00
Pembesian 1,188.07 kg Rp 9,863.44
Bekisting 23.18 m2 Rp 118,000.00
5 Pekerjaan Poer K5 uk. 1m x 1m 4.00 bh
Beton K275 0.84 m3 Rp 823,210.00
Pembesian 225.58 kg Rp 9,863.44
Bekisting 3.36 m2 Rp 118,000.00
6 Pekerjaan Lantai Lift 1.00 bh
Beton K275 6.37 m3 Rp 823,210.00
Pembesian 687.33 kg Rp 9,863.44
Bekisting 7.31 m2 Rp 118,000.00
7 Pekerjaan Dinding Lift
Beton K275 2.66 m3 Rp 823,210.00
Pembesian 460.69 kg Rp 9,863.44
Bekisting 35.47 m2 Rp 118,000.00
8 Pekerjaan Pedestal Kolom K1 uk. 60x60 14.00 bh
Beton K275 6.35 m3 Rp 823,210.00
Pembesian 2,565.97 kg Rp 9,863.44
Bekisting 42.34 m2 Rp 206,205.00
9 Pekerjaan Pedestal Kolom K3 uk. 60x60 6.00 bh
Beton K275 2.72 m3 Rp 823,210.00
Pembesian 1,265.22 kg Rp 9,863.44
NO. VOL. SAT. HARGA SAT.
Real Cost
ANA ANGGARAN BIAYA (RAB)
GUNAN STADION BAROMBONG
VINSI SULAWESI SELATAN
Rp 25,000,000.00
Rp 120,000,000.00
Rp 145,000,000.00
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
Rp -
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN GEDUNG BADAN KOORDINASI PENANAMAN MODAL DAERA
PROVINSI SULAWESI SELATAN
B. Lantai II (Dua)
1. Balok Utama B1 & B1+, Uk. 40 x 50
~Beton K275 41.04 m3
~Besi Beton :
- Besi Beton Polos 2,041.73 Kg
- Besi Beton Ulir 5,470.63 Kg
~BeKisting 2x Pakai 287.28 m2
D. Lantai IV (Empat)
1. Balok Utama B2, Uk. 35 x 50
~Beton K275 25.41 m3
~Besi Beton :
- Besi Beton Polos 738.17 Kg
- Besi Beton Ulir 3,544.33 Kg
~BeKisting 2x Pakai 196.02 m2
E. Lantai V (Lima)
1. Balok Utama B2, Uk. 35 x 50
~Beton K275 25.41 m3
~Besi Beton :
- Besi Beton Polos 738.17 Kg
- Besi Beton Ulir 3,544.33 Kg
~BeKisting 2x Pakai 196.02 m2
Struktur
Tahap I
Tahap I
Tahap I
Tahap I
Tahap I
-
-
-
-
Makassar, 2011
Konsultan Perencana,
CV. Bajirupa Konsultan
Ir. BADARUDDIN
Direktur
NCANA ANGGARAN BIAYA (RAB)
G BADAN KOORDINASI PENANAMAN MODAL DAERAH
PROVINSI SULAWESI SELATAN
Struktur
HARGA SAT. JML. HARGA
13,905.00 Tahap I
13,905.00 Tahap I
13,905.00 Tahap I
13,905.00 Tahap I
13,905.00 Tahap I
13,905.00 Tahap I
13,905.00 Tahap I
13,905.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
Struktur
HARGA SAT. JML. HARGA
902,387.30 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
902,387.30 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
902,387.30 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
Struktur
HARGA SAT. JML. HARGA
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
13,905.00 Tahap I
227,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
902,387.30 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
902,387.30 Tahap I
Struktur
HARGA SAT. JML. HARGA
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
13,905.00 Tahap I
227,775.00 Tahap I
902,387.30 Tahap I
13,905.00 Tahap I
215,275.00 Tahap I
902,387.30 Tahap I
13,905.00 Tahap I
227,775.00 Tahap I
902,387.30 Tahap I
13,905.00 Tahap I
215,275.00 Tahap I
902,387.30 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
Struktur
HARGA SAT. JML. HARGA
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
13,905.00 Tahap I
227,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
902,387.30 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
Struktur
HARGA SAT. JML. HARGA
902,387.30 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
13,905.00 Tahap I
227,775.00 Tahap I
935,392.86 Tahap I
Struktur
HARGA SAT. JML. HARGA
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
902,387.30 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
902,387.30 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
Struktur
HARGA SAT. JML. HARGA
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
13,905.00 Tahap I
227,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
902,387.30 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
902,387.30 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap I
13,905.00 Tahap I
227,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
Struktur
HARGA SAT. JML. HARGA
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap I
12,855.00 Tahap I
13,905.00 Tahap I
197,775.00 Tahap I
902,387.30 Tahap II
13,905.00 Tahap I
197,775.00 Tahap I
902,387.30 Tahap II
13,905.00 Tahap I
197,775.00 Tahap I
935,392.86 Tahap II
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap II
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap II
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap II
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap II
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
Struktur
HARGA SAT. JML. HARGA
935,392.86 Tahap II
12,855.00 Tahap I
13,905.00 Tahap I
203,775.00 Tahap I
935,392.86 Tahap II
13,905.00 Tahap II
227,775.00 Tahap II
935,392.86 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
197,775.00 Tahap II
935,392.86 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
197,775.00 Tahap II
935,392.86 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
197,775.00 Tahap II
902,387.30 Tahap II
13,905.00 Tahap II
197,775.00 Tahap II
902,387.30 Tahap II
13,905.00 Tahap II
197,775.00 Tahap II
902,387.30 Tahap II
13,905.00 Tahap II
197,775.00 Tahap II
Struktur
HARGA SAT. JML. HARGA
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
935,392.86 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
935,392.86 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
902,387.30 Tahap II
13,905.00 Tahap II
227,775.00 Tahap II
935,392.86 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
Struktur
HARGA SAT. JML. HARGA
197,775.00 Tahap II
935,392.86 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
197,775.00 Tahap II
902,387.30 Tahap II
13,905.00 Tahap II
197,775.00 Tahap II
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
935,392.86 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
902,387.30 Tahap II
13,905.00 Tahap II
227,775.00 Tahap II
935,392.86 Tahap II
Struktur
HARGA SAT. JML. HARGA
12,855.00 Tahap II
13,905.00 Tahap II
197,775.00 Tahap II
Jumlah I -
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
902,387.30 Tahap II
13,905.00 Tahap II
197,775.00 Tahap II
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
902,387.30 Tahap II
13,905.00 Tahap II
227,775.00 Tahap II
Jumlah II -
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN GEDUNG BADAN KOORDINASI PENANAMAN MODAL DAERA
PROVINSI SULAWESI SELATAN
IV Pekerjaan Langit-langit/Plafond
A. Lantai I (Dasar) Rp.
B. Lantai II (Dua) Rp.
C. Lantai III (Tiga) Rp.
D. Lantai IV (Empat) Rp.
E. Lantai V (Lima) Rp.
F. Lantai VI (Enam) Rp.
G. Lantai VII (Tujuh) Rp.
H. Lantai VIII (Delapan) Rp.
V Pekerjaan Pengecatan
A. Lantai I (Dasar) Rp.
B. Lantai II (Dua) Rp.
C. Lantai III (Tiga) Rp.
D. Lantai IV (Empat) Rp.
E. Lantai V (Lima) Rp.
F. Lantai VI (Enam) Rp.
G. Lantai VII (Tujuh) Rp.
H. Lantai VIII (Delapan), IX (Sembilan) Dan Dudukan Tangki Air Rp.
VI Pekerjaan Lantai
A. Lantai I (Dasar) Rp.
B. Lantai II (Dua) Rp.
C. Lantai III (Tiga) Rp.
D. Lantai IV (Empat) Rp.
E. Lantai V (Lima) Rp.
F. Lantai VI (Enam) Rp.
G. Lantai VII (Tujuh) Rp.
H. Lantai VIII (Delapan) Dan Lantai IX (Sembilan) Rp.
B. Lantai II (Dua)
1. Pek. Kolom Praktis KP, Uk. 12 x 15
~Beton K175 3.40 m3
~Besi Beton :
- Besi Beton Polos 782.00 Kg
~BeKisting 2x Pakai 56.67 m2
D. Lantai IV (Empat)
1. Pek. Kolom Praktis KP, Uk. 12 x 15
~Beton K175 3.18 m3
~Besi Beton :
- Besi Beton Polos 731.40 Kg
~BeKisting 2x Pakai 53.00 m2
E. Lantai V (Lima)
1. Pek. Kolom Praktis KP, Uk. 12 x 15
~Beton K175 3.18 m3
~Besi Beton :
- Besi Beton Polos 731.40 Kg
~BeKisting 2x Pakai 53.00 m2
F. Lantai VI (Enam)
1. Pek. Kolom Praktis KP, Uk. 12 x 15
~Beton K175 2.12 m3
~Besi Beton :
- Besi Beton Polos 487.60 Kg
~BeKisting 2x Pakai 35.33 m2
b. Plat Level, T = 12 Cm
~Beton K175 1.07 m3
~Besi Beton :
- Besi Beton Polos 113.88 Kg
~BeKisting 2x Pakai 8.92 m2
NO. URAIAN PEKERJAAN VOL. SAT.
b. Plat Level, T = 12 Cm
~Beton K175 4.94 m3
~Besi Beton :
- Besi Beton Polos 525.76 Kg
~BeKisting 2x Pakai 41.17 m2
B. Lantai II (Dua)
1. Pas. Dinding Tembok 1/2 Bata (1Pc : 5Ps) 319.20 m2
2. Plesteran Biasa (1Pc : 5Ps) 638.40 m2
3. Plesteran Beton (1Pc : 3Ps) (yang nampak) 455.06 m2
4. Pekerjaan Acian Semen Dinding 556.93 m2
5. Pekerjaan Acian Semen Beton 455.06 m2
D. Lantai IV (Empat)
1. Pas. Dinding Tembok 1/2 Bata (1Pc : 5Ps) 233.18 m2
2. Plesteran Biasa (1Pc : 5Ps) 466.37 m2
3. Plesteran Beton (1Pc : 3Ps) (yang nampak) 382.35 m2
4. Pekerjaan Acian Semen Dinding 394.22 m2
5. Pekerjaan Acian Semen Beton 382.35 m2
E. Lantai V (Lima)
1. Pas. Dinding Tembok 1/2 Bata (1Pc : 5Ps) 233.18 m2
2. Plesteran Biasa (1Pc : 5Ps) 466.37 m2
3. Plesteran Beton (1Pc : 3Ps) (yang nampak) 382.35 m2
4. Pekerjaan Acian Semen Dinding 394.22 m2
5. Pekerjaan Acian Semen Beton 382.35 m2
F. Lantai VI (Enam)
1. Pas. Dinding Tembok 1/2 Bata (1Pc : 5Ps) 345.03 m2
2. Plesteran Biasa (1Pc : 5Ps) 690.06 m2
3. Plesteran Beton (1Pc : 3Ps) (yang nampak) 492.18 m2
4. Pekerjaan Acian Semen Dinding 618.30 m2
5. Pekerjaan Acian Semen Beton 492.18 m2
B. Lantai II (Dua)
1. Pintu Type PJ1 = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 59.10 m1
~Pas. Pintu Kaca Tempered 12 mm, Uk. 0,75 x 2,16 2 Buah
~Pas. Kaca Mati Bening 5 mm 18.82 m2
~Flooring Engsel 2 Set
~Pegangan Pintu/Door Holder 2 Set
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
2. Pintu Type P3 = 2 Unit
~Kusen Aluminium 4" x 1 3/4" 10.60 m1
~Pas. Daun Pintu Aluminium, Uk. 0,82x2,15 3.52 m2
~Engsel Pintu 6 Buah
~Kunci Pintu Aluminium (Bulat) 2 Buah
~Grendel Pintu 2 Buah
3. Pintu Type P4.a (Partisi Km/Lavatory) = 1 Unit
~Pas. Panel Cubical 12 mm Laminated, T = 2,00 M 3.35 m1
4. Pintu Type P4.b (Partisi Km/Lavatory) = 1 Unit
~Pas. Panel Cubical 12 mm Laminated, T = 2,00 M 3.35 m1
5. Pintu Type P6 (Pintu Emergency) = 1 Unit
~Kusen Pintu Dari Rangka Siku Dan Plat 1.00 Bh
NO. URAIAN PEKERJAAN VOL. SAT.
~Pas. Daun Pintu Plat Baja, Rangka Hollow 4 x 4 1.00 Bh
6. Jendela Type J3 = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 15.32 m1
~Pas. Kaca Mati Ryben 5mm 13.52 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
7. Jendela Type J6 = 2 Unit
~Kusen Aluminium 4" x 1 3/4" 81.54 m1
~Pas. Kaca Mati Snapsol Laminated 8 mm 38.50 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
D. Lantai IV (Empat)
1. Pintu Type PJ2.a = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 29.84 m1
~Pas. Pintu Kaca Tempered 12 mm, Uk. 0,75 x 2,16 2 Buah
~Pas. Kaca Mati Bening 5 mm 8.35 m2
~Flooring Engsel 2 Set
~Pegangan Pintu/Door Holder 2 Set
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
2. Pintu Type P2 = 2 Unit
NO. URAIAN PEKERJAAN VOL. SAT.
~Kusen Aluminium 4" x 1 3/4" 9.54 m1
~Pas. Daun Pintu Kaca Ryben 5 mm Bingkai Aluminium 6.13 m2
~Pas. Kaca Mati Ryben 5mm 1.82 m2
~Engsel Pintu 6 Buah
~Kunci Pintu Aluminium 1 Buah
~Pegangan Pintu/Door Holder 2 Set
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
3. Pintu Type P3 = 2 Unit
~Kusen Aluminium 4" x 1 3/4" 10.60 m1
~Pas. Daun Pintu Aluminium, Uk. 0,82x2,15 3.52 m2
~Engsel Pintu 6 Buah
~Kunci Pintu Aluminium (Bulat) 2 Buah
~Grendel Pintu 2 Buah
4. Pintu Type P4.a (Partisi Km/Lavatory) = 1 Unit
~Pas. Panel Cubical 12 mm Laminated, T = 2,00 M 3.35 m1
E. Lantai V (Lima)
1. Pintu Type PJ2.a = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 29.84 m1
~Pas. Pintu Kaca Tempered 12 mm, Uk. 0,75 x 2,16 2 Buah
~Pas. Kaca Mati Bening 5 mm 8.35 m2
~Flooring Engsel 2 Set
~Pegangan Pintu/Door Holder 2 Set
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
2. Pintu Type P2 = 2 Unit
~Kusen Aluminium 4" x 1 3/4" 9.54 m1
~Pas. Daun Pintu Kaca Ryben 5 mm Bingkai Aluminium 6.13 m2
~Pas. Kaca Mati Ryben 5mm 1.82 m2
~Engsel Pintu 6 Buah
~Kunci Pintu Aluminium 1 Buah
~Pegangan Pintu/Door Holder 2 Set
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
3. Pintu Type P3 = 2 Unit
~Kusen Aluminium 4" x 1 3/4" 10.60 m1
~Pas. Daun Pintu Aluminium, Uk. 0,82x2,15 3.52 m2
~Engsel Pintu 6 Buah
~Kunci Pintu Aluminium (Bulat) 2 Buah
~Grendel Pintu 2 Buah
4. Pintu Type P4.a (Partisi Km/Lavatory) = 1 Unit
~Pas. Panel Cubical 12 mm Laminated, T = 2,00 M 3.35 m1
5. Pintu Type P4.b (Partisi Km/Lavatory) = 1 Unit
~Pas. Panel Cubical 12 mm Laminated, T = 2,00 M 3.35 m1
6. Pintu Type P5 = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 5.20 m1
~Pas. Daun Pintu Aluminium, Uk. 0,74x2,15 1.59 m2
~Engsel Pintu 3 Buah
~Kunci Pintu Aluminium (Bulat) 1 Buah
~Grendel Pintu 1 Buah
7. Pintu Type P6 (Pintu Emergency) = 1 Unit
~Kusen Pintu Dari Rangka Siku Dan Plat 1.00 Bh
~Pas. Daun Pintu Plat Baja, Rangka Hollow 4 x 4 1.00 Bh
8. Jendela Type J4 = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 14.24 m1
~Pas. Kaca Mati Ryben 5mm 11.42 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
9. Jendela Type J8 = 8 Unit
~Kusen Aluminium 4" x 1 3/4" 104.64 m1
~Pas. Daun Jendela Kaca Mati Ryben 5mm Bingkai Aluminium 34.88 m2
~Pas. Engsel Jendela 24.00 Buah
~Pas. Kait Angin Jendela 24.00 Buah
~Pas. Grendel Jendela 12.00 Buah
10. Jendela Type J10.a = 2 Unit
~Kusen Aluminium 4" x 1 3/4" 61.80 m1
~Pas. Kaca Mati Bening 5 mm 23.22 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
11. Jendela Type J11 = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 9.30 m1
~Pas. Kaca Mati Ryben 5mm 4.71 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
12. Jendela Type J12 = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 9.10 m1
~Pas. Kaca Mati Ryben 5mm 4.43 m2
NO. URAIAN PEKERJAAN VOL. SAT.
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
13. Jendela Type J13 = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 8.04 m1
~Pas. Kaca Mati Ryben 5mm 3.01 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
14. Jendela Type JS (Jendela Sudut) = 4 Unit
~Kusen Aluminium 4" x 1 3/4" 72.64 m1
~Pas. Kaca Mati Ryben 5mm 10.52 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
15. Ventilasi Type V1 = 3 Unit
~Kusen Aluminium 4" x 1 3/4" 6.60 m1
~Pas. Kaca Mati Ryben 5mm 0.63 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
F. Lantai VI (Enam)
1. Pintu Type PJ2.b = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 30.14 m1
~Pas. Pintu Kaca Tempered 12 mm, Uk. 0,75 x 2,16 2 Buah
~Pas. Kaca Mati Bening 5 mm 8.63 m2
~Flooring Engsel 2 Set
~Pegangan Pintu/Door Holder 2 Set
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
2. Pintu Type P2 = 2 Unit
~Kusen Aluminium 4" x 1 3/4" 9.54 m1
~Pas. Daun Pintu Kaca Ryben 5 mm Bingkai Aluminium 6.13 m2
~Pas. Kaca Mati Ryben 5mm 1.82 m2
~Engsel Pintu 6 Buah
~Kunci Pintu Aluminium 1 Buah
~Pegangan Pintu/Door Holder 2 Set
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
3. Pintu Type P3 = 2 Unit
~Kusen Aluminium 4" x 1 3/4" 10.60 m1
~Pas. Daun Pintu Aluminium, Uk. 0,82x2,15 3.52 m2
~Engsel Pintu 6 Buah
~Kunci Pintu Aluminium (Bulat) 2 Buah
~Grendel Pintu 2 Buah
4. Pintu Type P4.a (Partisi Km/Lavatory) = 1 Unit
~Pas. Panel Cubical 12 mm Laminated, T = 2,00 M 3.35 m1
5. Pintu Type P4.b (Partisi Km/Lavatory) = 1 Unit
~Pas. Panel Cubical 12 mm Laminated, T = 2,00 M 3.35 m1
6. Pintu Type P5 = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 5.20 m1
~Pas. Daun Pintu Aluminium, Uk. 0,74x2,15 1.59 m2
~Engsel Pintu 3 Buah
~Kunci Pintu Aluminium (Bulat) 1 Buah
~Grendel Pintu 1 Buah
7. Pintu Type P6 (Pintu Emergency) = 1 Unit
~Kusen Pintu Dari Rangka Siku Dan Plat 1.00 Bh
~Pas. Daun Pintu Plat Baja, Rangka Hollow 4 x 4 1.00 Bh
8. Jendela Type J5 = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 10.66 m1
~Pas. Kaca Mati Ryben 5mm 3.50 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
9. Jendela Type J9 = 40 Unit
~Kusen Aluminium 4" x 1 3/4" 216.00 m1
~Pas. Daun Jendela Kaca Mati Ryben 5mm Bingkai Aluminium 35.60 m2
~Pas. Engsel Jendela 80.00 Buah
~Pas. Kait Angin Jendela 80.00 Buah
NO. URAIAN PEKERJAAN VOL. SAT.
~Pas. Grendel Jendela 40.00 Buah
10. Jendela Type J10.b = 2 Unit
~Kusen Aluminium 4" x 1 3/4" 62.10 m1
~Pas. Kaca Mati Bening 5 mm 23.94 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
11. Jendela Type J11 = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 9.30 m1
~Pas. Kaca Mati Ryben 5mm 4.71 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
12. Jendela Type J12 = 1 Unit
~Kusen Aluminium 4" x 1 3/4" 9.10 m1
~Pas. Kaca Mati Ryben 5mm 4.43 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
13. Ventilasi Type V1 = 2 Unit
~Kusen Aluminium 4" x 1 3/4" 70.40 m1
~Pas. Kaca Mati Ryben 5mm 0.42 m2
~Acsesoris, Karet list Kaca, Silikon, Dll (Pada Kaca Mati) 1 Ls
IV Pekerjaan Langit-langit/Plafond
A. Lantai I (Dasar)
1. Pas. Plafond Gypsum Rangka Hollow Galvaniz 258.04 m2
2. Pas. Plafond GRC Rangka Hollow Galvaniz (Km/Lavatory) 16.66 m2
B. Lantai II (Dua)
1. Pas. Plafond Gypsum Rangka Hollow Galvaniz 455.24 m2
2. Pas. Plafond GRC Rangka Hollow Galvaniz (Km/Lavatory) 16.66 m2
D. Lantai IV (Empat)
1. Pas. Plafond Gypsum Rangka Hollow Galvaniz 315.67 m2
2. Pas. Plafond GRC Rangka Hollow Galvaniz (Km/Lavatory) 20.85 m2
E. Lantai V (Lima)
1. Pas. Plafond Gypsum Rangka Hollow Galvaniz 315.67 m2
2. Pas. Plafond GRC Rangka Hollow Galvaniz (Km/Lavatory) 20.85 m2
F. Lantai VI (Enam)
1. Pas. Plafond Gypsum Rangka Hollow Galvaniz 374.70 m2
NO. URAIAN PEKERJAAN VOL. SAT.
2. Pas. Plafond GRC Rangka Hollow Galvaniz (Km/Lavatory) 21.03 m2
V Pekerjaan Pengecatan
A. Lantai I (Dasar)
1. Cat Tembok Dinding Luar Dan Dalam 426.72 m2
2. Cat Tembok Beton 554.89 m2
3. Cat Plafond Gypsum Biasa 258.04 m2
4. Cat Plafond GRC (Km Dan Lavatory) 16.66 m2
5. Cat Coating Batu Alam 4.97 m2
B. Lantai II (Dua)
1. Cat Tembok Dinding Luar Dan Dalam 556.93 m2
2. Cat Tembok Beton 455.06 m2
3. Cat Plafond Gypsum Biasa 455.24 m2
4. Cat Plafond GRC (Km Dan Lavatory) 16.66 m2
5. Lapisan Waterproofing (Lantai Dan Dinding Kolam) 61.76 m2
D. Lantai IV (Empat)
1. Cat Tembok Dinding Luar Dan Dalam 394.22 m2
2. Cat Tembok Beton 382.35 m2
3. Cat Plafond Gypsum Biasa 315.67 m2
4. Cat Plafond GRC (Km Dan Lavatory) 20.85 m2
E. Lantai V (Lima)
1. Cat Tembok Dinding Luar Dan Dalam 394.22 m2
2. Cat Tembok Beton 382.35 m2
3. Cat Plafond Gypsum Biasa 315.67 m2
4. Cat Plafond GRC (Km Dan Lavatory) 20.85 m2
F. Lantai VI (Enam)
1. Cat Tembok Dinding Luar Dan Dalam 618.30 m2
2. Cat Tembok Beton 492.18 m2
3. Cat Plafond Gypsum Biasa 374.70 m2
NO. URAIAN PEKERJAAN VOL. SAT.
4. Cat Plafond GRC (Km Dan Lavatory) 21.03 m2
VI Pekerjaan Lantai
A. Lantai I (Dasar)
1. Pas. Lantai Marmer 60/60 Lantai Utama 258.89 m2
2. Pas. Lantai Marmer 60/60 (Kasar) Entrance 16.00 m2
3. Pas. Marmer Tangga Utama 37.73 m2
4. Pas. Lantai Keramik 40/40 (Bawah Tangga Darurat) 16.07 m2
5. Pas. Lantai Keramik Tangga Darurat 40/40 (Lt. 1 - Lt. 2) 14.46 m2
6. Pas. Lantai Keramik 30/30 (Lavatory) 19.88 m2
7. Pas. Keramik Dinding 30/50 (Lavatory), T = 2.00 m 50.76 m2
8. Pas. Batu Alam undersheet Gawangan Pintu utama 4.97 m2
9. Pek. Rabat Beton Alas Bangunan, T = 7 cm 21.76 m3
B. Lantai II (Dua)
1. Pas. Lantai Marmer 60/60 Lantai Utama 313.23 m2
2. Pas. Lantai Keramik 40/40 (Depan Lift) 16.05 m2
3. Pas. Lantai Keramik Tangga Darurat 40/40 (Lt. 2 - Lt. 3) 20.49 m2
4. Pas. Lantai Keramik 30/30 (Lavatory) 19.88 m2
5. Pas. Keramik Dinding 30/50 (Lavatory), T = 2.00 m 50.76 m2
6. Pas. Keramik Kolam Renang
- Rest Area Kolam (sekitar Kolam) 30 x 30 30.12 m2
- Dinding Selasar Kolam 30 x 50 23.55 m2
- Selasar Kolam + Tangga Kolam 30 x 30 86.04 m2
- Lantai Dasar Kolam Keramik 30 x 30 26.66 m2
- Dinding Kolam Keramik 30 x 50 35.10 m2
D. Lantai IV (Empat)
1. Pas. Lantai Keramik 40/40 Lantai Utama + Ruang Staff 279.09 m2
2. Pas. Lantai Keramik 40/40 (Depan Lift) 28.18 m2
3. Pas. Lantai Keramik Tangga Darurat 40/40 (Lt. 4 - Lt. 5) 20.49 m2
4. Pas. Lantai Keramik 30/30 (Lavatory + Km) 24.07 m2
NO. URAIAN PEKERJAAN VOL. SAT.
5. Pas. Keramik Dinding 30/50 (Lavatory + Km), T = 2.00 m 65.52 m2
E. Lantai V (Lima)
1. Pas. Lantai Keramik 40/40 Lantai Utama + Ruang Staff 279.09 m2
2. Pas. Lantai Keramik 40/40 (Depan Lift) 28.18 m2
3. Pas. Lantai Keramik Tangga Darurat 40/40 (Lt. 5 - Lt. 6) 20.49 m2
4. Pas. Lantai Keramik 30/30 (Lavatory + Km) 24.07 m2
5. Pas. Keramik Dinding 30/50 (Lavatory + Km), T = 2.00 m 65.52 m2
F. Lantai VI (Enam)
1. Pas. Lantai Keramik 40/40 Lantai Utama + Ruang Staff 338.18 m2
2. Pas. Lantai Keramik 40/40 (Depan Lift) 28.18 m2
3. Pas. Lantai Keramik Tangga Darurat 40/40 (Lt. 6 - Lt. 7) 20.49 m2
4. Pas. Lantai Keramik 30/30 (Lavatory + Km) 24.25 m2
5. Pas. Keramik Dinding 30/50 (Lavatory + Km), T = 2.00 m 66.12 m2
B. Lantai II (Dua)
1. Kran Air, Ex Toto 7 Buah
2. Pas. Wastafel, Ex. Toto 3 Buah
3. Pas. Kloset Duduk, Ex Toto 4 Buah
4. Urinoir Lengkap,Type U57 Ex. Toto 3 Buah
5. Pas. Floor Drain, Ex. Toto 4 Buah
6. Pas. Tempat Sabun 3 Buah
7. Pas. Cermin Washtafel 3 Buah
NO. URAIAN PEKERJAAN VOL. SAT.
C. Lantai III (Tiga)
1. Kran Air, Ex Toto 8 Buah
2. Kran Air Shower, Ex Toto 1 Buah
3. Shower + Acs 1 Set
4. Pas. Wastafel, Ex. Toto 4 Buah
5. Pas. Kloset Duduk, Ex Toto 5 Buah
6. Urinoir Lengkap,Type U57 Ex. Toto 3 Buah
7. Pas. Floor Drain, Ex. Toto 5 Buah
8. Pas. Tempat Sabun 4 Buah
9. Pas. Cermin Washtafel 4 Buah
10. Pas. Roof Drain (Atap Plat Kolam Renang Dan Caf) 8 Buah
D. Lantai IV (Empat)
1. Kran Air, Ex Toto 8 Buah
2. Kran Air Shower, Ex Toto 1 Buah
3. Shower + Acs 1 Set
4. Pas. Wastafel, Ex. Toto 4 Buah
5. Pas. Kloset Duduk, Ex Toto 5 Buah
6. Urinoir Lengkap,Type U57 Ex. Toto 3 Buah
7. Pas. Floor Drain, Ex. Toto 5 Buah
8. Pas. Tempat Sabun 4 Buah
9. Pas. Cermin Washtafel 4 Buah
E. Lantai V (Lima)
1. Kran Air, Ex Toto 8 Buah
2. Kran Air Shower, Ex Toto 1 Buah
3. Shower + Acs 1 Set
4. Pas. Wastafel, Ex. Toto 4 Buah
5. Pas. Kloset Duduk, Ex Toto 5 Buah
6. Urinoir Lengkap,Type U57 Ex. Toto 3 Buah
7. Pas. Floor Drain, Ex. Toto 5 Buah
8. Pas. Tempat Sabun 4 Buah
9. Pas. Cermin Washtafel 4 Buah
F. Lantai VI (Enam)
1. Kran Air, Ex Toto 8 Buah
2. Kran Air Shower, Ex Toto 1 Buah
3. Shower + Acs 1 Set
4. Pas. Wastafel, Ex. Toto 4 Buah
5. Pas. Kloset Duduk, Ex Toto 5 Buah
6. Urinoir Lengkap,Type U57 Ex. Toto 3 Buah
7. Pas. Floor Drain, Ex. Toto 5 Buah
8. Pas. Tempat Sabun 4 Buah
9. Pas. Cermin Washtafel 4 Buah
Arsitektur
TOTAL HARGA (Rp.)
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
47,416,212.02
65,396,719.23
41,874,246.41
41,874,246.41
41,874,246.41
56,663,364.38
71,910,912.15
15,642,595.39
9,604,463.56
9,604,463.56
12,184,001.71
12,184,001.71
12,184,001.71
12,290,024.79
9,604,463.56
-
20,711,612.50
20,711,612.50
24,969,325.00
24,497,325.00
24,497,325.00
24,497,325.00
20,711,612.50
11,000,000.00
670,347,197.56
1,302,251,298.09
Makassar, 2011
Konsultan Perencana,
CV. Bajirupa Konsultan
Ir. BADARUDDIN
Direktur
NCANA ANGGARAN BIAYA (RAB)
G BADAN KOORDINASI PENANAMAN MODAL DAERAH
PROVINSI SULAWESI SELATAN
Arsitektur
HARGA SAT. JML. HARGA
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
227,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
Arsitektur
HARGA SAT. JML. HARGA
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
227,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
227,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
Arsitektur
HARGA SAT. JML. HARGA
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
227,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
227,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
227,775.00 Tahap II
Arsitektur
HARGA SAT. JML. HARGA
902,387.30 Tahap II
12,855.00 Tahap II
13,905.00 Tahap II
203,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
227,775.00 Tahap II
855,842.06 Tahap II
12,855.00 Tahap II
197,775.00 Tahap II
Jumlah I -
83,807.00 Tahap II
79,273.00 Tahap II
39,928.60 Tahap II
37,452.40 Tahap II
39,928.60 Tahap II
39,928.60 Tahap II
19,875.00 Tahap II
19,875.00 Tahap II
Jumlah Lt. 1 (A) -
79,273.00 Tahap II
37,452.40 Tahap II
39,928.60 Tahap II
19,875.00 Tahap II
19,875.00 Tahap II
Jumlah Lt. 2 (B) -
79,273.00 Tahap II
37,452.40 Tahap II
39,928.60 Tahap II
39,928.60 Tahap II
Arsitektur
HARGA SAT. JML. HARGA
19,875.00 Tahap II
19,875.00 Tahap II
Jumlah Lt. 3 (C) -
79,273.00 Tahap II
37,452.40 Tahap II
39,928.60 Tahap II
19,875.00 Tahap II
19,875.00 Tahap II
Jumlah Lt. 4 (D) -
79,273.00 Tahap II
37,452.40 Tahap II
39,928.60 Tahap II
19,875.00 Tahap II
19,875.00 Tahap II
Jumlah Lt. 5 (E) -
79,273.00 Tahap II
37,452.40 Tahap II
39,928.60 Tahap II
19,875.00 Tahap II
19,875.00 Tahap II
Jumlah Lt. 6 (F) -
79,273.00 Tahap II
37,452.40 Tahap II
39,928.60 Tahap II
19,875.00 Tahap II
19,875.00 Tahap II
Jumlah Lt. 7 (G) -
79,273.00 Tahap II
37,452.40 Tahap II
39,928.60 Tahap II
39,928.60 Tahap II
19,875.00 Tahap II
19,875.00 Tahap II
Jumlah Lt. 8 & 9 (H) -
Jumlah II -
102,110.70 Tahap II
5,652,497.94 Tahap II
89,825.00 Tahap II
924,825.00 Tahap II
192,750.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
1,027,520.00 Tahap II
Arsitektur
HARGA SAT. JML. HARGA
40,825.00 Tahap II
386,000.00 Tahap II
25,000.00 Tahap II
3,250,000.00 Tahap II
3,250,000.00 Tahap II
2,153,253.42 Tahap II
2,891,519.93 Tahap II
102,110.70 Tahap II
348,321.80 Tahap II
33,550.00 Tahap II
32,825.00 Tahap II
36,550.00 Tahap II
102,110.70 Tahap II
348,321.80 Tahap II
33,550.00 Tahap II
32,825.00 Tahap II
36,550.00 Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
4,063,449.25 Tahap II
89,825.00 Tahap II
924,825.00 Tahap II
192,750.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
1,027,520.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
25,000.00 Tahap II
3,250,000.00 Tahap II
3,250,000.00 Tahap II
2,153,253.42 Tahap II
Arsitektur
HARGA SAT. JML. HARGA
2,891,519.93 Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
713,910.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
348,321.80 Tahap II
33,550.00 Tahap II
32,825.00 Tahap II
36,550.00 Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
4,063,449.25 Tahap II
89,825.00 Tahap II
924,825.00 Tahap II
192,750.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
1,800.00 Tahap II
177,825.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
192,750.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
1,027,520.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
25,000.00 Tahap II
Arsitektur
HARGA SAT. JML. HARGA
3,250,000.00 Tahap II
3,250,000.00 Tahap II
102,110.70 Tahap II
1,027,520.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
25,000.00 Tahap II
2,153,253.42 Tahap II
2,891,519.93 Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
348,321.80 Tahap II
33,550.00 Tahap II
32,825.00 Tahap II
36,550.00 Tahap II
102,110.70 Tahap II
89,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
4,063,449.25 Tahap II
89,825.00 Tahap II
924,825.00 Tahap II
192,750.00 Tahap II
#VALUE! Tahap II
Arsitektur
HARGA SAT. JML. HARGA
102,110.70 Tahap II
4,800.00 Tahap II
177,825.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
192,750.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
1,027,520.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
25,000.00 Tahap II
3,250,000.00 Tahap II
3,250,000.00 Tahap II
102,110.70 Tahap II
1,027,520.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
25,000.00 Tahap II
2,153,253.42 Tahap II
2,891,519.93 Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
348,321.80 Tahap II
33,550.00 Tahap II
32,825.00 Tahap II
36,550.00 Tahap II
102,110.70 Tahap II
89,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
Arsitektur
HARGA SAT. JML. HARGA
#VALUE! Tahap II
102,110.70 Tahap II
4,063,449.25 Tahap II
89,825.00 Tahap II
924,825.00 Tahap II
192,750.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
8,000.00 Tahap II
177,825.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
192,750.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
1,027,520.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
25,000.00 Tahap II
3,250,000.00 Tahap II
3,250,000.00 Tahap II
102,110.70 Tahap II
1,027,520.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
25,000.00 Tahap II
2,153,253.42 Tahap II
2,891,519.93 Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
348,321.80 Tahap II
33,550.00 Tahap II
32,825.00 Tahap II
36,550.00 Tahap II
102,110.70 Tahap II
89,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
Arsitektur
HARGA SAT. JML. HARGA
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
4,063,449.25 Tahap II
89,825.00 Tahap II
924,825.00 Tahap II
192,750.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
600.00 Tahap II
177,825.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
192,750.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
1,027,520.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
25,000.00 Tahap II
3,250,000.00 Tahap II
3,250,000.00 Tahap II
102,110.70 Tahap II
1,027,520.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
25,000.00 Tahap II
2,153,253.42 Tahap II
2,891,519.93 Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
348,321.80 Tahap II
33,550.00 Tahap II
32,825.00 Tahap II
Arsitektur
HARGA SAT. JML. HARGA
36,550.00 Tahap II
102,110.70 Tahap II
89,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
4,063,449.25 Tahap II
89,825.00 Tahap II
924,825.00 Tahap II
192,750.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
1,027,520.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
25,000.00 Tahap II
3,250,000.00 Tahap II
3,250,000.00 Tahap II
2,153,253.42 Tahap II
2,891,519.93 Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
348,321.80 Tahap II
33,550.00 Tahap II
32,825.00 Tahap II
Arsitektur
HARGA SAT. JML. HARGA
36,550.00 Tahap II
102,110.70 Tahap II
348,321.80 Tahap II
33,550.00 Tahap II
32,825.00 Tahap II
36,550.00 Tahap II
102,110.70 Tahap II
177,825.00 Tahap II
#VALUE! Tahap II
102,110.70 Tahap II
523,723.40 Tahap II
177,825.00 Tahap II
40,825.00 Tahap II
386,000.00 Tahap II
192,750.00 Tahap II
#VALUE! Tahap II
2,153,253.42 Tahap II
2,891,519.93 Tahap II
Jumlah III -
139,568.80 Tahap II
134,400.00 Tahap II
Jumlah Lt. 1 (A) -
139,568.80 Tahap II
134,400.00 Tahap II
Jumlah Lt. 2 (B) -
139,568.80 Tahap II
134,400.00 Tahap II
Jumlah Lt. 3 (C) -
139,568.80 Tahap II
134,400.00 Tahap II
Jumlah Lt. 4 (D) -
139,568.80 Tahap II
134,400.00 Tahap II
Jumlah Lt. 5 (E) -
139,568.80 Tahap II
Arsitektur
HARGA SAT. JML. HARGA
134,400.00 Tahap II
Jumlah Lt. 6 (F) -
139,568.80 Tahap II
134,400.00 Tahap II
Jumlah Lt. 7 (G) -
139,568.80 Tahap II
Jumlah Lt. 8 (H) -
Jumlah IV -
37,620.00 16,053,206.40
37,620.00 20,874,961.80
37,620.00 9,707,423.42
37,620.00 626,749.20
30,960.00 153,871.20
Jumlah Lt. 1 (A) 47,416,212.02
37,620.00 20,951,706.60
37,620.00 17,119,357.20
37,620.00 17,126,106.23
37,620.00 626,749.20
155,000.00 9,572,800.00
Jumlah Lt. 2 (B) 65,396,719.23
37,620.00 14,830,556.40
37,620.00 14,384,007.00
37,620.00 11,875,343.63
37,620.00 784,339.38
155,000.00 Tahap II
Jumlah Lt. 3 (C) 41,874,246.41
37,620.00 14,830,556.40
37,620.00 14,384,007.00
37,620.00 11,875,343.63
37,620.00 784,339.38
Jumlah Lt. 4 (D) 41,874,246.41
37,620.00 14,830,556.40
37,620.00 14,384,007.00
37,620.00 11,875,343.63
37,620.00 784,339.38
Jumlah Lt. 5 (E) 41,874,246.41
37,620.00 23,260,446.00
37,620.00 18,515,811.60
37,620.00 14,096,082.33
Arsitektur
HARGA SAT. JML. HARGA
37,620.00 791,024.45
Jumlah Lt. 6 (F) 56,663,364.38
37,620.00 26,582,668.20
37,620.00 34,126,606.80
37,620.00 10,574,887.95
37,620.00 626,749.20
Jumlah Lt. 7 (G) 71,910,912.15
37,620.00 10,403,434.80
37,620.00 4,395,520.80
37,620.00 843,639.79
155,000.00 Tahap II
Jumlah Lt. 8 & 9 (H) 15,642,595.39
Jumlah V 382,652,542.41
753,986.50 Tahap II
753,986.50 Tahap II
753,986.50 Tahap II
141,405.00 Tahap II
141,405.00 Tahap II
134,159.09 2,667,082.73
136,681.00 6,937,380.84
288,300.00 Tahap II
774,453.57 Tahap II
Jumlah Lt. 1 (A) 9,604,463.56
753,986.50 Tahap II
141,405.00 Tahap II
141,405.00 Tahap II
134,159.09 2,667,082.73
136,681.00 6,937,380.84
134,159.09 Tahap II
136,681.00 Tahap II
134,159.09 Tahap II
134,159.09 Tahap II
136,681.00 Tahap II
Jumlah Lt. 2 (B) 9,604,463.56
141,405.00 Tahap II
141,405.00 Tahap II
141,405.00 Tahap II
134,159.09 3,229,209.32
136,681.00 8,954,792.40
Jumlah Lt. 3 (C) 12,184,001.71
141,405.00 Tahap II
141,405.00 Tahap II
141,405.00 Tahap II
134,159.09 3,229,209.32
Arsitektur
HARGA SAT. JML. HARGA
136,681.00 8,954,792.40
Jumlah Lt. 4 (D) 12,184,001.71
141,405.00 Tahap II
141,405.00 Tahap II
141,405.00 Tahap II
134,159.09 3,229,209.32
136,681.00 8,954,792.40
Jumlah Lt. 5 (E) 12,184,001.71
141,405.00 Tahap II
141,405.00 Tahap II
141,405.00 Tahap II
134,159.09 3,253,223.80
136,681.00 9,036,801.00
Jumlah Lt. 6 (F) 12,290,024.79
141,405.00 Tahap II
141,405.00 Tahap II
141,405.00 Tahap II
134,159.09 2,667,082.73
136,681.00 6,937,380.84
Jumlah Lt. 7 (G) 9,604,463.56
141,405.00 Tahap II
141,405.00 Tahap II
Jumlah Lt. 8 & 9 (H) -
Jumlah VI 77,655,420.62
45,087.50 315,612.50
642,350.00 1,927,050.00
2,219,100.00 8,876,400.00
2,638,850.00 7,916,550.00
44,000.00 176,000.00
150,000.00 450,000.00
350,000.00 1,050,000.00
Jumlah Lt. 1 (A) 20,711,612.50
45,087.50 315,612.50
642,350.00 1,927,050.00
2,219,100.00 8,876,400.00
2,638,850.00 7,916,550.00
44,000.00 176,000.00
150,000.00 450,000.00
350,000.00 1,050,000.00
Jumlah Lt. 2 (B) 20,711,612.50
Arsitektur
HARGA SAT. JML. HARGA
45,087.50 360,700.00
60,087.50 60,087.50
275,087.50 275,087.50
642,350.00 2,569,400.00
2,219,100.00 11,095,500.00
2,638,850.00 7,916,550.00
44,000.00 220,000.00
150,000.00 600,000.00
350,000.00 1,400,000.00
59,000.00 472,000.00
Jumlah Lt. 3 (C) 24,969,325.00
45,087.50 360,700.00
60,087.50 60,087.50
275,087.50 275,087.50
642,350.00 2,569,400.00
2,219,100.00 11,095,500.00
2,638,850.00 7,916,550.00
44,000.00 220,000.00
150,000.00 600,000.00
350,000.00 1,400,000.00
Jumlah Lt. 4 (D) 24,497,325.00
45,087.50 360,700.00
60,087.50 60,087.50
275,087.50 275,087.50
642,350.00 2,569,400.00
2,219,100.00 11,095,500.00
2,638,850.00 7,916,550.00
44,000.00 220,000.00
150,000.00 600,000.00
350,000.00 1,400,000.00
Jumlah Lt. 5 (E) 24,497,325.00
45,087.50 360,700.00
60,087.50 60,087.50
275,087.50 275,087.50
642,350.00 2,569,400.00
2,219,100.00 11,095,500.00
2,638,850.00 7,916,550.00
44,000.00 220,000.00
150,000.00 600,000.00
350,000.00 1,400,000.00
Jumlah Lt. 6 (F) 24,497,325.00
45,087.50 315,612.50
642,350.00 1,927,050.00
2,219,100.00 8,876,400.00
2,638,850.00 7,916,550.00
44,000.00 176,000.00
150,000.00 450,000.00
350,000.00 1,050,000.00
Jumlah Lt. 7 (G) 20,711,612.50
Arsitektur
HARGA SAT. JML. HARGA
2,750,000.00 11,000,000.00
150,000,000.00 150,000,000.00
713,910.00 15,970,166.70
605,029.58 30,088,121.18
605,029.58 24,164,881.56
Jumlah 1 220,223,169.44
605,029.58 179,233,963.77
Jumlah 2 179,233,963.77
605,029.58 92,357,765.90
Jumlah 3 92,357,765.90
713,910.00 43,162,998.60
4,316,299.86 4,316,299.86
Jumlah 4 47,479,298.46
850,000.00 22,746,000.00
850,000.00 5,661,000.00
850,000.00 6,315,500.00
850,000.00 6,315,500.00
850,000.00 6,315,500.00
850,000.00 6,315,500.00
850,000.00 6,315,500.00
850,000.00 6,817,000.00
850,000.00 7,684,000.00
850,000.00 21,972,500.00
850,000.00 34,595,000.00
Jumlah 5 131,053,000.00
I Pekerjaan Instalasi Pemipaan Air Bersih, Air Kotor Dan Venting Rp.
Pemipaan
- Pipa GIP Medium Class Dia. 100 mm (4") Lantai 1 2.00 m'
- Pipa GIP Medium Class Dia. 65 mm (2 1/2") Lantai 1 8.00 m'
- Pipa GIP Medium Class Dia. 50 mm (2") Lantai 1 21.00 m'
- Pipa GIP Medium Class Dia. 40 mm (1 1/2") Lantai 1 56.00 m'
- Pipa GIP Medium Class Dia. 32 mm (1 1/4") Lantai 1 - 7 28.00 m'
- Pipa GIP Medium Class Dia. 25 mm (1") Lantai 1 - 7 42.00 m'
- Pipa GIP Medium Class Dia. 20 mm (3/4") Lantai 1 - 7 35.00 m'
- Pipa GIP Medium Class Dia. 15 mm (1/2") Lantai 1 - 7 28.00 m'
- Gate Valve Dia. 65 mm (2 1/2") 10 K 2.00 Bh
- Gate Valve Dia. 40 mm (1 1/2") 10 K 7.00 Bh
- Gate Valve Dia. 32 mm (1 1/4") 10 K 7.00 Bh
- Fitting 1.00 Ls
II Fire Hydrant
Peralatan Utama
NO. URAIAN PEKERJAAN VOL. SAT.
1. Electric Hydrant Pump 1.00 Bh
- Kapasitas : 500 Gpm
- Head : 30 m
Valve, Acsesories
7. Gate Valve, Dia. 65 mm (2 1/2") 10 K 2.00 Bh
8. Check Valve, Dia. 65 mm (2 1/2") 10 K 1.00 Bh
9. Strainer, Dia. 65 mm (2 1/2") 10 K 1.00 Bh
10. Flexible Joint, Dia. 65 mm (2 1/2") 10 K 2.00 Bh
11. Gate Valve, Dia. 80 mm (3") 10 K 4.00 Bh
12. Check Valve, Dia. 80 mm (3") 10 K 1.00 Bh
13. Strainer, Dia. 80 mm (3") 10 K 1.00 Bh
14. Flexible Joint, Dia. 80 mm (3") 10 K 2.00 Bh
15. Preasure Switch 10 K 1.00 Bh
16. Preasure Guage 10 K 2.00 Bh
Pemipaan
15. Header, Dia. 80 mm (3"), 12.00 m'
16. Pipa BS SCH 40, Dia. 65 mm (2 1/2") 30.00 m'
17. Pipa BS SCH 40, Dia. 50 mm (2") 15.00 m'
18. Pipa BS SCH 40, Dia. 40 mm (1 1/2") 28.00 m'
Acsesories
19. Hydrant Box (Type Indoor) 8.00 Bh
(c/w Selang, Landing, Valve, Nozle)
20. Hydrant Box (Type Outdoor) 2.00 Bh
(c/w Selang, Landing, Valve, Nozle)
21. Siamese Conection 1.00 Bh
22. Hydrant Pillar 1.00 Bh
23. Testing & Commisioning 1.00 Ls
ULASI RENCANA ANGGARAN BIAYA (RAB)
NG BADAN KOORDINASI PENANAMAN MODAL DAERAH
PROVINSI SULAWESI SELATAN
Mekanikal
TOTAL HARGA (Rp.)
223,077,084.93
234,529,464.00
457,606,548.93
Makassar, 2011
Konsultan Perencana,
CV. Bajirupa Konsultan
Ir. BADARUDDIN
Direktur
ENCANA ANGGARAN BIAYA (RAB)
NG BADAN KOORDINASI PENANAMAN MODAL DAERAH
PROVINSI SULAWESI SELATAN
Mekanikal
HARGA SAT. JML. HARGA
6,200,000.00 6,200,000.00
16,400,000.00 16,400,000.00
7,600,000.00 7,600,000.00
12,400,000.00 12,400,000.00
748,000.00 2,992,000.00
756,000.00 1,512,000.00
684,000.00 1,368,000.00
228,000.00 912,000.00
7,600,000.00 15,200,000.00
485,240.00 970,480.00
270,366.30 2,162,930.40
216,603.00 4,548,663.00
159,789.30 8,948,200.80
140,628.20 3,937,589.60
106,537.20 4,474,562.40
73,745.40 2,581,089.00
60,018.60 1,680,520.80
1,816,000.00 3,632,000.00
716,500.00 5,015,500.00
525,000.00 3,675,000.00
16,650,614.40 16,650,614.40
122,861,150.40
119,818.30 7,908,007.80
83,359.20 1,167,028.80
54,882.30 1,997,715.72
45,081.65 2,997,929.73
31,321.30 1,797,842.62
6,347,409.87 6,347,409.87
48,000,000.00 48,000,000.00
30,000,000.00 30,000,000.00
100,215,934.53
Jumlah (A + B) 223,077,084.93
HARGA SAT. JML. HARGA
56,000,000.00 56,000,000.00
18,600,000.00 18,600,000.00
7,800,000.00 7,800,000.00
36,000,000.00 36,000,000.00
1,256,000.00 1,256,000.00
1,816,000.00 1,816,000.00
1,860,000.00 3,720,000.00
1,740,000.00 1,740,000.00
1,680,000.00 1,680,000.00
256,000.00 512,000.00
2,156,000.00 8,624,000.00
2,240,000.00 2,240,000.00
2,178,000.00 2,178,000.00
316,000.00 632,000.00
214,000.00 214,000.00
176,000.00 352,000.00
326,000.00 3,912,000.00
234,040.50 7,021,215.00
188,145.00 2,822,175.00
139,645.50 3,910,074.00
6,200,000.00 49,600,000.00
6,300,000.00 12,600,000.00
4,600,000.00 4,600,000.00
4,200,000.00 4,200,000.00
2,500,000.00 2,500,000.00
234,529,464.00
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN GEDUNG BADAN KOORDINASI PENANAMAN MODAL DAERA
PROVINSI SULAWESI SELATAN
I Pekerjaan Listrik
A. Panel Instalasi
- Panel Utama (P.U) 1.00 Unit
- LP.1 1.00 Unit
- PP.1 1.00 Unit
- LP.2 - 7 6.00 Unit
- PP.2 - 7 6.00 Unit
- PP.Lift 1.00 Unit
- PP.HD 1.00 Unit
- LP.Tn 1.00 Unit
B. Kabel Distribusi
- Kabel NYY 4 x 16 mm2 116.00 m'
- TL 1 x 36 Watt, Balk
- Lantai 1 128.00 Buah
- Lantai 2 128.00 Buah
- Downlight DL SL 23 Watt
- Lantai 1 46.00 Buah
- Lantai 2 62.00 Buah
- Lantai 3 14.00 Buah
- Lantai 4 14.00 Buah
- Lantai 5 14.00 Buah
- Lantai 6 14.00 Buah
- Lantai 7 10.00 Buah
- Stop Kontak 16 A
NO. URAIAN PEKERJAAN VOL. SAT.
- Lantai 1 4.00 Buah
- Lantai 2 4.00 Buah
- Lantai 3 14.00 Buah
- Lantai 4 14.00 Buah
- Lantai 5 14.00 Buah
- Lantai 6 14.00 Buah
- Lantai 7 4.00 Buah
- Saklar Tunggal
- Lantai 1 3.00 Buah
- Lantai 2 3.00 Buah
- Lantai 3 4.00 Buah
- Lantai 4 4.00 Buah
- Lantai 5 4.00 Buah
- Lantai 6 4.00 Buah
- Lantai 7 3.00 Buah
- Saklar Ganda
- Lantai 1 10.00 Buah
- Lantai 2 10.00 Buah
- Lantai 3 10.00 Buah
- Lantai 4 10.00 Buah
- Lantai 5 10.00 Buah
- Lantai 6 10.00 Buah
- Lantai 7 4.00 Buah
D. Pekerjaan Instalasi
- Instalasi Penerangan 365.00 Titik
- Instalasi Stop Kontak 68.00 Titik
- Instalasi Stop Kontak Lantai 36.00 Titik
- Instalasi Stop Kontak AC 32.00 Titik
Jumlah I (A+B+C+D
Instalasi
- TB - SS 8.00 Unit
- Instalasi Sound System, Kabel NYMhy 3 x 1,5 mm in Conduit 30.00 Titik
- Ceilling Speaker 5 Watt 28.00 Bh
- Horn Speaker 25 Watt 2.00 Bh
- Testing & Commisioning 1.00 Ls
B. Pekerjaan Telepon
Peralatan Utama
- PABX 3/24 EXT, Lengkap Battery Canger & Acsesories 1.00 Set
- Operator Consule, Type Digital 1.00 Unit
- MDF (Main Distribution Frame) 1.00 Unit
- Pengabelan System 1.00 Ls
- Grounding System 1.00 Ls
Instalasi
- TBT (Terminal Box Telephone) 7.00 Bh
- Instalasi Telepon, Kabel ITC 2 x 2 x 0,5 mm, in conduit 12.00 Titik
- Socket Outlet Telepon 12.00 Bh
- Testing & Commisioning 1.00 Ls
Elektrikal
TOTAL HARGA (Rp.)
417,880,400.00
365,680,000.00
77,562,000.00
861,122,400.00
Makassar, 2011
Konsultan Perencana,
CV. Bajirupa Konsultan
Ir. BADARUDDIN
Direktur
ENCANA ANGGARAN BIAYA (RAB)
NG BADAN KOORDINASI PENANAMAN MODAL DAERAH
PROVINSI SULAWESI SELATAN
Elektrikal
HARGA SAT. JML. HARGA
21,400,000.00 21,400,000.00
6,900,000.00 6,900,000.00
6,700,000.00 6,700,000.00
6,900,000.00 41,400,000.00
6,700,000.00 40,200,000.00
5,200,000.00 5,200,000.00
5,800,000.00 5,800,000.00
3,600,000.00 3,600,000.00
131,200,000.00
128,000.00 14,848,000.00
14,848,000.00
828,000.00 31,464,000.00
828,000.00 31,464,000.00
828,000.00 31,464,000.00
828,000.00 31,464,000.00
828,000.00 31,464,000.00
828,000.00 3,312,000.00
72,000.00 9,216,000.00
72,000.00 9,216,000.00
198,600.00 9,135,600.00
198,600.00 12,313,200.00
198,600.00 2,780,400.00
198,600.00 2,780,400.00
198,600.00 2,780,400.00
198,600.00 2,780,400.00
198,600.00 1,986,000.00
916,000.00 7,328,000.00
7,500,000.00 7,500,000.00
286,000.00 2,288,000.00
78,000.00 312,000.00
78,000.00 312,000.00
78,000.00 312,000.00
78,000.00 312,000.00
78,000.00 312,000.00
78,000.00 312,000.00
78,000.00 312,000.00
HARGA SAT. JML. HARGA
40,000.00 160,000.00
40,000.00 160,000.00
40,000.00 560,000.00
40,000.00 560,000.00
40,000.00 560,000.00
40,000.00 560,000.00
40,000.00 160,000.00
96,000.00 -
96,000.00 576,000.00
96,000.00 576,000.00
96,000.00 576,000.00
96,000.00 576,000.00
96,000.00 576,000.00
96,000.00 576,000.00
86,000.00 344,000.00
86,000.00 344,000.00
86,000.00 430,000.00
86,000.00 430,000.00
86,000.00 430,000.00
86,000.00 430,000.00
86,000.00 344,000.00
40,000.00 120,000.00
40,000.00 120,000.00
40,000.00 160,000.00
40,000.00 160,000.00
40,000.00 160,000.00
40,000.00 160,000.00
40,000.00 120,000.00
46,000.00 460,000.00
46,000.00 460,000.00
46,000.00 460,000.00
46,000.00 460,000.00
46,000.00 460,000.00
46,000.00 460,000.00
46,000.00 184,000.00
245,792,400.00
364,440.00 Tahap II
425,620.00 Tahap II
425,620.00 Tahap II
425,620.00 Tahap II
-
18,000,000.00 Tahap II
76,000.00 Tahap II
2,500,000.00 Tahap II
-
316,000.00 Tahap II
248,000.00 Tahap II
- -
-
HARGA SAT. JML. HARGA
1,860,000.00 26,040,000.00
8,600,000.00 361,200,000.00
320,000.00 4,480,000.00
365,680,000.00
7,200,000.00 7,200,000.00
5,600,000.00 5,600,000.00
5,200,000.00 5,200,000.00
3,560,000.00 3,560,000.00
3,416,000.00 3,416,000.00
276,000.00 276,000.00
1,480,000.00 1,480,000.00
8,200,000.00 8,200,000.00
2,176,000.00 2,176,000.00
1,578,000.00 1,578,000.00
416,000.00 3,328,000.00
278,000.00 Tahap II
216,000.00 6,048,000.00
427,000.00 854,000.00
2,500,000.00 2,500,000.00
51,416,000.00
14,600,000.00 14,600,000.00
3,200,000.00 3,200,000.00
1,240,000.00 1,240,000.00
700,000.00 700,000.00
1,620,000.00 1,620,000.00
346,000.00 2,422,000.00
298,000.00 Tahap II
72,000.00 864,000.00
1,500,000.00 1,500,000.00
26,146,000.00
Makassar, 2
Disetujui, Konsultan Perencana
Pejabat Pelaksana Teknis Kegiatan (PPTK) CV. BAJIRUPA CONSUL
Mengetahui/Menyetujui,
KEPALA BADAN KOORDINASI PENANAMAN MODAL DAERAH
PROVINSI SULAWESI SELATAN
63,495,000.00
Di CCO (Tahap I)
(Ganti KSLL) (Tahap I)
Selesai Tahap II
1,302,251,298.09
457,606,548.93
861,122,400.00
661,443,617.47
3,345,918,864.49
334,591,886.45
3,680,510,750.94
3,680,510,000.00
Makassar, 2011
Konsultan Perencana,
CV. BAJIRUPA CONSULTANT
BADARUDDIN, ST
Direktur
Mengetahui/Menyetujui,
ORDINASI PENANAMAN MODAL DAERAH
INSI SULAWESI SELATAN
25,978.80 135,940,912.80
21,672.00 38,908,435.10
32,519.18 65,935,072.50
38,259.60 11,087,791.50
605,029.58 344,791,233.80
25,082.69 36,031,077.66
25,000.00 2,300,000.00
12,500.00 6,500,000.00
15,000,000.00 15,000,000.00
10,050.00 2,587,843.34
219.00 2,361,250.76
661,443,617.47
661,443,617.47
Makassar, 2011
Konsultan Perencana,
CV. Bajirupa Konsultan
Ir. BADARUDDIN
Direktur
No. Uraian Pekerjaan Perhitungan Volume Satuan
1. Kolom K1 (30/30), T = 6.30
~Beton K225 Penampang Panjang Jumlah
0.09 6.3 28 15.876 m3
~Besi Beton Diameter Panjang Kg/m'
16 1523.2 1.58 2406.656
8 1266.608 0.393 497.776944
2904.433 Kg
Data Berat Besi Polos
berat d19/m 2.23 kg/m1
berat d16/m 1.58 kg/m1
berat d14/m 1.209 kg/m1
berat d12/m 0.887 kg/m1
berat d10/m 0.62 kg/m1
berat d8/m 0.393 kg/m1
berat d6/m 0.22 kg/m1
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN:
Pekerjaan:
PEMELIHARAAN ASRAMA DAYUNG
Konsultan Perencana:
(RAB)
PLP
G
SYARAT - SYARAT TEKNIS PELAKSANAAN
KEGIATAN:
Pekerjaan:
PEMELIHARAAN ASRAMA DAYUNG
Konsultan Perencana:
KSANAAN
PLP
G
PEMERINTAH PROVINSI SULAWESI S
DINAS PEMUDA DAN OLAHRAGA
KEGIATAN:
Pekerjaan:
Konsultan Perencana:
H PROVINSI SULAWESI SELATAN
S PEMUDA DAN OLAHRAGA
ANGGARAN BIAYA
KEGIATAN:
Pekerjaan:
onsultan Perencana:
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
B.6 PEKERJAAN TANAH
A. Tenaga :
1.00 Oh Mandor @ Rp 100,000.00 Rp
1.00 Oh Operator terampil @ Rp 120,000.00 Rp
1.00 Oh Sopir terampil @ Rp 120,000.00 Rp
2.00 Oh Buruh tak terampil @ Rp 40,000.00 Rp
Rp
B. Bahan :
160.00 M3 Tanah timbunan (Pilihan) @ Rp 150,000.00 Rp
0.40 Set Alat Bantu @ Rp 5,000.00 Rp
Rp
C. Peralatan :
4.00 Jam Buldozer 110 HP @ Rp 250,000.00 Rp
5.00 Jam Mesin Gilas 3 roda 8 - 10 T @ Rp 150,000.00 Rp
5.00 Jam Mesin Gilas Bergetar 1 Tonne @ Rp 150,000.00 Rp
6.00 Jam Truck Tangki Air 68 Hp @ Rp 100,000.00 Rp
Rp
Untuk 120 M3 Penimbunan (A + B + C) Rp
Untuk 1 M3 Penimbunan Rp
D.6.2 Memasang 1 M2 dinding bata merah uk. (5x11x22) cm tebal 1 bt. camp. 1PC : 3PP
140.000 Bh Batu merah @ Rp 550.00 Rp
32.950 Kg Semen Portland @ Rp 1,100.00 Rp
0.091 M3 Pasir pasang @ Rp 125,000.00 Rp
0.600 Oh Pekerja @ Rp 50,000.00 Rp
0.200 Oh Tukang batu @ Rp 70,000.00 Rp
0.020 Oh Kepala Tukang Batu @ Rp 100,000.00 Rp
0.030 Oh Mandor @ Rp 100,000.00 Rp
Rp
D.6.3 Memasang 1 M2 dinding bata merah uk. (5x11x22) cm tebal 1 bt. camp. 1PC : 4PP
140.000 Bh Batu merah @ Rp 550.00 Rp
26.550 Kg Semen Portland @ Rp 1,100.00 Rp
0.093 M3 Pasir pasang @ Rp 125,000.00 Rp
0.600 Oh Pekerja @ Rp 50,000.00 Rp
0.200 Oh Tukang batu @ Rp 70,000.00 Rp
0.020 Oh Kepala Tukang Batu @ Rp 100,000.00 Rp
0.030 Oh Mandor @ Rp 100,000.00 Rp
Rp
D.6.4 Memasang 1 M2 dinding bata merah uk. (5x11x22) cm tebal 1 bt. camp. 1PC : 5PP
140.000 Bh Batu merah @ Rp 550.00 Rp
22.200 Kg Semen Portland @ Rp 1,100.00 Rp
0.102 M3 Pasir pasang @ Rp 125,000.00 Rp
0.600 Oh Pekerja @ Rp 50,000.00 Rp
0.200 Oh Tukang batu @ Rp 70,000.00 Rp
0.020 Oh Kepala Tukang Batu @ Rp 100,000.00 Rp
0.030 Oh Mandor @ Rp 100,000.00 Rp
Rp
D.6.8 Memasang1 M2 dinding bata merah uk. (5x11x22) cm tebal 1/2 bt. camp. 1PC : 3PP
70.000 Bh Batu merah @ Rp 550.00 Rp
14.370 Kg Semen Portland @ Rp 1,100.00 Rp
0.040 M3 Pasir pasang @ Rp 125,000.00 Rp
0.300 Oh Pekerja @ Rp 50,000.00 Rp
0.100 Oh Tukang batu @ Rp 70,000.00 Rp
0.010 Oh Kepala Tukang Batu @ Rp 100,000.00 Rp
0.015 Oh Mandor @ Rp 100,000.00 Rp
Rp
D.6.9 Memasang1 M2 dinding bata merah uk. (5x11x22) cm tebal 1/2 bt. camp. 1PC : 4PP
70.000 Bh Batu merah @ Rp 550.00 Rp
11.500 Kg Semen Portland @ Rp 1,100.00 Rp
0.043 M3 Pasir pasang @ Rp 125,000.00 Rp
0.300 Oh Pekerja @ Rp 50,000.00 Rp
0.100 Oh Tukang batu @ Rp 70,000.00 Rp
0.010 Oh Kepala Tukang Batu @ Rp 100,000.00 Rp
0.015 Oh Mandor @ Rp 100,000.00 Rp
Rp
D.6.10 Memasang 1 M2 dinding bata merah uk. (5x11x22) cm tebal 1/2 bt. camp. 1PC : 5PP
70.000 Bh Batu merah @ Rp 550.00 Rp
9.680 Kg Semen Portland @ Rp 1,100.00 Rp
0.045 M3 Pasir pasang @ Rp 125,000.00 Rp
0.300 Oh Pekerja @ Rp 50,000.00 Rp
0.100 Oh Tukang batu @ Rp 70,000.00 Rp
0.010 Oh Kepala Tukang Batu @ Rp 100,000.00 Rp
0.015 Oh Mandor @ Rp 100,000.00 Rp
Rp
F.6.6 Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu kelas I
0.024 M3 Kayu klas I (papan) listplank dan pintu/jendela @ Rp 9,000,000.00 Rp
0.300 Kg Lem kayu @ Rp 25,000.00 Rp
0.800 Oh Pekerja @ Rp 50,000.00 Rp
2.400 Oh Tukang kayu @ Rp 70,000.00 Rp
0.240 Oh Kepala Tukang Kayu @ Rp 100,000.00 Rp
0.040 Oh Mandor @ Rp 100,000.00 Rp
Rp
F.6.8 1 M2 Membuat daun pintu kayu lapis (plywood) rangkap, rangka tertutup kayu kls. II
0.025 M3 Kayu klas II (papan) @ Rp 4,500,000.00 Rp
0.030 Kg Paku Biasa 1/2" - 1" @ Rp 15,000.00 Rp
0.500 Kg Lem kayu @ Rp 25,000.00 Rp
1.000 Lbr Plywood Uk.80x240 cm Tebal 4 mm @ Rp 85,000.00 Rp
0.600 Oh Pekerja @ Rp 50,000.00 Rp
2.000 Oh Tukang kayu @ Rp 70,000.00 Rp
0.200 Oh Kepala Tukang Kayu @ Rp 100,000.00 Rp
0.030 Oh Mandor @ Rp 100,000.00 Rp
Rp
F.6.8 - SPL 1 M2 Membuat daun pintu Teakwood rangkap Lapis HPL, rangka tertutup kayu kls. II
0.025 M3 Kayu klas II (papan) @ Rp 4,500,000.00 Rp
0.030 Kg Paku Biasa 1/2" - 1" @ Rp 15,000.00 Rp
0.500 Kg Lem kayu @ Rp 25,000.00 Rp
1.000 Lbr Teakwood Uk. 80 x 240 x 4 mm @ Rp 65,000.00 Rp
0.700 Lbr HPL Uk. 120 x 240 @ Rp 185,000.00 Rp
0.600 Oh Pekerja @ Rp 50,000.00 Rp
2.500 Oh Tukang kayu @ Rp 70,000.00 Rp
0.250 Oh Kepala Tukang Kayu @ Rp 100,000.00 Rp
0.030 Oh Mandor @ Rp 100,000.00 Rp
Rp
SPL Membuat 1 Bh daun pintu Acoustic Multipleks rangkap Lapis HPL, rangka tertutup Besi Hollow, Uk. 80 x 240
8.800 M' Besi Hollow 30 x 30 x 2.3 mm @ Rp 26,400.00 Rp
36.000 Bh Srews/sekrup @ Rp 1,000.00 Rp
0.960 Kg Lem kayu @ Rp 25,000.00 Rp
1.418 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 129,000.00 Rp
1.467 Lbr HPL Uk. 120 x 240 @ Rp 185,000.00 Rp
0.730 Roll Glass Wool DN City 48 kg/m2, Uk. 1.2 x 2.3 m, T = @ Rp 230,000.00 Rp
1.152 Oh Pekerja @ Rp 50,000.00 Rp
4.800 Oh Tukang kayu @ Rp 70,000.00 Rp
0.480 Oh Kepala Tukang Kayu @ Rp 100,000.00 Rp
0.058 Oh Mandor @ Rp 100,000.00 Rp
Rp
SPL Memasang 1 M2 langit-langit gypsum board Acoustic ukuran (60x80), tebal 9 mm + rangka Besi Hollow
4.400 M Besi Hollow 40 x 40 x 2.3 mm @ Rp 37,000.00 Rp
8.000 Bh Sektrup Fixer @ Rp 1,850.00 Rp
1.050 M2 Kawat Rang 3 x 3 @ Rp 17,500.00 Rp
0.381 Roll Glass Wool DN City 48 kg/m2, Uk. 1.2 x 2.3 m, T = @ Rp 230,000.00 Rp
0.353 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 129,000.00 Rp
0.364 Lbr HPL Uk. 120 x 240 @ Rp 185,000.00 Rp
0.263 Kg Lem kayu @ Rp 25,000.00 Rp
11.500 Bh Srews/sekrup @ Rp 1,000.00 Rp
0.010 Lbr Kertas Amplas @ Rp 2,500.00 Rp
0.070 Oh Pekerja @ Rp 50,000.00 Rp
0.700 Oh Tukang besi @ Rp 80,000.00 Rp
0.007 Oh Kepala Tukang Besi @ Rp 100,000.00 Rp
0.012 Oh Mandor @ Rp 100,000.00 Rp
Rp
F.6.19 1 M2 Memasang rangka langit-langit (50x100) cm, kayu kls. II atau III
0.0154 M3 Kayu klas II (balok) @ Rp 4,000,000.00 Rp
0.200 Kg Paku biasa 2" - 5" @ Rp 15,000.00 Rp
0.150 Oh Pekerja @ Rp 50,000.00 Rp
0.250 Oh Tukang kayu @ Rp 70,000.00 Rp
0.025 Oh Kepala Tukang Kayu @ Rp 100,000.00 Rp
0.075 Oh Mandor @ Rp 100,000.00 Rp
Rp
F.6.22 1 M' Memasang lisplank ukuran (3x30) cm, kayu kls. I atau II
0.0108 M3 Kayu klas I (papan) listplank dan pintu/jendela @ Rp 9,000,000.00 Rp
0.050 Kg Paku biasa 2" - 5" @ Rp 15,000.00 Rp
0.100 Oh Pekerja @ Rp 50,000.00 Rp
0.200 Oh Tukang kayu @ Rp 70,000.00 Rp
0.020 Oh Kepala Tukang Kayu @ Rp 100,000.00 Rp
0.005 Oh Mandor @ Rp 100,000.00 Rp
Rp
G.6.4 Membuat 1 M3 lantai kerja beton mutu f'c=7,4 Mpa (K 100), slump (3-6) cm, w/c=0,87
230.000 Kg Semen Portland @ Rp 1,100.00 Rp
893.000 Kg Pasir beton (Kg) @ Rp 103.57 Rp
1,027.000 Kg split/chipping 2-3 cm(Kg) @ Rp 192.59 Rp
200.000 Ltr Air @ Rp 500.00 Rp
1.200 Oh Pekerja @ Rp 50,000.00 Rp
0.200 Oh Tukang batu @ Rp 70,000.00 Rp
0.020 Oh Kepala Tukang Batu @ Rp 100,000.00 Rp
0.060 Oh Mandor @ Rp 100,000.00 Rp
Rp
G.6.5 Membuat 1 M3 beton mutu f'c=14,5 Mpa (K 175), slump (12 2) cm, w/c=0,66
326.000 Kg Semen Portland @ Rp 1,100.00 Rp
760.000 Kg Pasir beton (Kg) @ Rp 103.57 Rp
1,029.000 Kg split/chipping 2-3 cm(Kg) @ Rp 192.59 Rp
215.000 Ltr Air @ Rp 500.00 Rp
1.650 Oh Pekerja @ Rp 50,000.00 Rp
0.275 Oh Tukang batu @ Rp 70,000.00 Rp
0.028 Oh Kepala Tukang Batu @ Rp 100,000.00 Rp
0.083 Oh Mandor @ Rp 100,000.00 Rp
Rp
G.6.7 Membuat 1 M3 beton mutu f'c=19,3 Mpa (K 225), slump (12 2) cm, w/c=0,58
371.000 Kg Semen Portland @ Rp 1,100.00 Rp
698.000 Kg Pasir beton (Kg) @ Rp 103.57 Rp
1,047.000 Kg split/chipping 2-3 cm(Kg) @ Rp 192.59 Rp
215.000 Ltr Air @ Rp 500.00 Rp
1.650 Oh Pekerja @ Rp 50,000.00 Rp
0.275 Oh Tukang batu @ Rp 70,000.00 Rp
0.028 Oh Kepala Tukang Batu @ Rp 100,000.00 Rp
0.083 Oh Mandor @ Rp 100,000.00 Rp
Rp
G.6.8 Membuat 1 M3 beton mutu f'c=21,7 Mpa (K 250), slump (12 2) cm, w/c=0,56
384.000 Kg Semen Portland @ Rp 1,100.00 Rp
692.000 Kg Pasir beton (Kg) @ Rp 103.57 Rp
1,039.000 Kg split/chipping 2-3 cm(Kg) @ Rp 192.59 Rp
215.000 Ltr Air @ Rp 500.00 Rp
1.650 Oh Pekerja @ Rp 50,000.00 Rp
0.275 Oh Tukang batu @ Rp 70,000.00 Rp
0.028 Oh Kepala Tukang Batu @ Rp 100,000.00 Rp
0.083 Oh Mandor @ Rp 100,000.00 Rp
Rp
G.6.9 Membuat 1 M3 beton mutu f'c=24,0 Mpa (K 275), slump (12 2) cm, w/c=0,53
406.000 Kg Semen Portland @ Rp 1,100.00 Rp
684.000 Kg Pasir beton (Kg) @ Rp 103.57 Rp
1,026.000 Kg split/chipping 2-3 cm(Kg) @ Rp 192.59 Rp
215.000 Ltr Air @ Rp 500.00 Rp
1.650 Oh Pekerja @ Rp 50,000.00 Rp
0.275 Oh Tukang batu @ Rp 70,000.00 Rp
0.028 Oh Kepala Tukang Batu @ Rp 100,000.00 Rp
0.083 Oh Mandor @ Rp 100,000.00 Rp
Rp
G.6.10 Membuat 1 M3 beton mutu f'c=26,4 Mpa (K 300), slump (12 2) cm, w/c=0,52
413.000 Kg Semen Portland @ Rp 1,100.00 Rp
681.000 Kg Pasir beton (Kg) @ Rp 103.57 Rp
1,021.000 Kg split/chipping 2-3 cm(Kg) @ Rp 192.59 Rp
215.000 Ltr Air @ Rp 500.00 Rp
1.650 Oh Pekerja @ Rp 50,000.00 Rp
0.275 Oh Tukang batu @ Rp 70,000.00 Rp
0.028 Oh Kepala Tukang Batu @ Rp 100,000.00 Rp
0.083 Oh Mandor @ Rp 100,000.00 Rp
Rp
I.6.1 Memasang 1 M2 langit-langit asbes semen, tebal 4mm, 5mm, dan 6mm
1.100 M2 Eternit @ Rp #N/A Rp
0.010 Kg Paku biasa 1/2" - 1" @ Rp 15,000.00 Rp
0.030 Oh Pekerja @ Rp 50,000.00 Rp
0.070 Oh Tukang kayu @ Rp 70,000.00 Rp
0.007 Oh Kepala Tukang Kayu @ Rp 100,000.00 Rp
0.002 Oh Mandor @ Rp 100,000.00 Rp
Rp
SPL Memasang 1 M2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm + rangka Hollow
4.400 M Besi Hollow Galvanis 2 x 4 MB, Tbl 0.7 mm @ Rp 5,800.00 Rp
1.500 Bh Ramsel nails @ Rp 5,000.00 Rp
0.364 Lbr Gypsumboard 9 mm @ Rp 69,200.00 Rp
0.03 Zak ( 0.600 Kg UB 888/400 Compoud @ Rp 9,000.00 Rp
0.016 Roll Isolasi Gypsun @ Rp 35,000.00 Rp
11.500 Bh Srews/sekrup @ Rp 1,000.00 Rp
1.000 Lbr Kertas Amplas @ Rp 2,500.00 Rp
0.070 Oh Pekerja @ Rp 50,000.00 Rp
0.700 Oh Tukang besi @ Rp 80,000.00 Rp
0.007 Oh Kepala Tukang Besi @ Rp 100,000.00 Rp
0.012 Oh Mandor @ Rp 100,000.00 Rp
Rp
SPL Memasang 1 M2 langit-langit Calsyboard board ukuran (120x240) mm, tebal 6 mm + rangka Hollow
4.400 M Besi Hollow Galvanis 2 x 4 MB, Tbl 0.7 mm @ Rp 5,800.00 Rp
1.500 Bh Ramsel nails @ Rp 5,000.00 Rp
0.364 Lbr Calsyboard 4 mm @ Rp 55,000.00 Rp
0.03 Zak ( 0.600 Kg UB 888/400 Compoud @ Rp 9,000.00 Rp
0.016 Roll Isolasi Gypsun @ Rp 35,000.00 Rp
11.500 Bh Srews/sekrup @ Rp 1,000.00 Rp
1.000 Lbr Kertas Amplas @ Rp 2,500.00 Rp
0.070 Oh Pekerja @ Rp 50,000.00 Rp
0.700 Oh Tukang besi @ Rp 80,000.00 Rp
0.007 Oh Kepala Tukang Besi @ Rp 100,000.00 Rp
0.012 Oh Mandor @ Rp 100,000.00 Rp
Rp
SPL Memasang 1 M2 langit-langit gypsum board Acoustic ukuran (60x80), tebal 9 mm + rangka Besi Hollow
4.400 M Besi Hollow 40 x 40 x 2.3 mm @ Rp 37,000.00 Rp
1.500 Bh Ramsel nails @ Rp 5,000.00 Rp
1.050 M2 Kawat Rang 3 x 3 @ Rp 17,500.00 Rp
0.381 Roll Glass Wool DN City 48 kg/m2, Uk. 1.2 x 2.3 m, T = @ Rp 230,000.00 Rp
0.364 Lbr Gypsumboard 9 mm @ Rp 69,200.00 Rp
0.03 Zak ( 0.600 Kg UB 888/400 Compoud @ Rp 9,000.00 Rp
0.016 Roll Isolasi Gypsun @ Rp 35,000.00 Rp
11.500 Bh Srews/sekrup @ Rp 1,000.00 Rp
1.000 Lbr Kertas Amplas @ Rp 2,500.00 Rp
0.070 Oh Pekerja @ Rp 50,000.00 Rp
0.700 Oh Tukang besi @ Rp 80,000.00 Rp
0.007 Oh Kepala Tukang Besi @ Rp 100,000.00 Rp
0.012 Oh Mandor @ Rp 100,000.00 Rp
Rp
J.6.22 - SPL A Memasang 1 M' pipa GIP Medium class diameter 1 1/4"
1.200 M' Pipa GIP Medium Class Dia. 32 mm (1 1/4") @ Rp 76,444.00 Rp
35 % Perlengkapan Rp
0.108 Oh Pekerja @ Rp 50,000.00 Rp
0.180 Oh Tukang pipa @ Rp 80,000.00 Rp
0.018 Oh Kepala Tukang pipa @ Rp 100,000.00 Rp
0.005 Oh Mandor @ Rp 100,000.00 Rp
Rp
J.6.22 - SPL B Memasang 1 M' pipa GIP Medium class diameter 2"
1.200 M' Pipa GIP Medium Class Dia. 50 mm (2") @ Rp 125,460.00 Rp
35 % Perlengkapan Rp
0.108 Oh Pekerja @ Rp 50,000.00 Rp
0.180 Oh Tukang pipa @ Rp 80,000.00 Rp
0.018 Oh Kepala Tukang pipa @ Rp 100,000.00 Rp
0.005 Oh Mandor @ Rp 100,000.00 Rp
Rp
J.6.22 - SPL C Memasang 1 M' pipa GIP Medium class diameter 2 1/2"
1.200 M' Pipa GIP Medium Class Dia. 65 mm (2 1/2") @ Rp 160,146.00 Rp
35 % Perlengkapan Rp
0.108 Oh Pekerja @ Rp 50,000.00 Rp
0.180 Oh Tukang pipa @ Rp 80,000.00 Rp
0.018 Oh Kepala Tukang pipa @ Rp 100,000.00 Rp
0.005 Oh Mandor @ Rp 100,000.00 Rp
Rp
Memasang 1 M' pipa PVC tipe AW diameter 1/2" Untuk Instalasi Air Panas
1.200 M' Pipa PVC Air Panas 1/2'' @ Rp 41,250.00 Rp
35 % Perlengkapan Rp
0.036 Oh Pekerja @ Rp 50,000.00 Rp
0.060 Oh Tukang pipa @ Rp 80,000.00 Rp
0.006 Oh Kepala Tukang pipa @ Rp 100,000.00 Rp
0.002 Oh Mandor @ Rp 100,000.00 Rp
Rp
Memasang 1 Bh Shower
1.000 Bh Shower + Acc @ Rp 265,000.00 Rp
0.025 Bh Seal tape @ Rp 3,500.00 Rp
0.010 Oh Pekerja @ Rp 50,000.00 Rp
0.100 Oh Tukang pipa @ Rp 80,000.00 Rp
0.010 Oh Kepala Tukang pipa @ Rp 100,000.00 Rp
0.005 Oh Mandor @ Rp 100,000.00 Rp
Rp
SPL 1 Unit Pasang Pintu Kaca Tempered, Tebal 12 Mm, Uk. 1.065 x 216 cm
2.415 M2 Pintu Kaca Tempered 12 mm @ Rp 1,435,000.00 Rp
1.000 Oh Pekerja @ Rp 50,000.00 Rp
2.500 Oh Tukang Besi @ Rp 80,000.00 Rp
0.250 Oh Kepala Tukang Besi @ Rp 100,000.00 Rp
0.050 Oh Mandor @ Rp 100,000.00 Rp
1.000 Set Frame List, Baut / Sekrup DLL Rp
1.000 Ls Alat bantu + Fabrikasi dll Rp
Rp
SPL 1 Unit Membuat Dan Memasang Kosen Pintu Emergency Rangka Baja Siku, Uk. 90 x 220
22.957 Kg Besi Siku L. 50. 50. 5 @ Rp 9,955.75 Rp
44.696 Kg Besi Siku L. 70. 70. 7 @ Rp 10,227.27 Rp
34.572 Kg Plat Baja T = 5 mm @ Rp 16,452.00 Rp
1.000 Ls Alat Bantu + Assesories @ Rp 125,445.22 Rp
5.333 Oh Pekerja @ Rp 50,000.00 Rp
5.333 Oh Tukang las @ Rp 80,000.00 Rp
0.533 Oh Kepala Tukang Besi @ Rp 100,000.00 Rp
0.267 Oh Mandor @ Rp 100,000.00 Rp
Rp
SPL 1 Unit Membuat Dan Memasang Pintu Emergency Rangka Hollow 4 x 4, Uk. 90 x 220
11.730 M' Besi Hollow 40 x 40 x 2.3 mm @ Rp 37,000.00 Rp
73.844 Kg Plat Baja T = 2 mm @ Rp 16,488.00 Rp
1.000 Ls Alat Bantu + Assesories @ Rp 495,466.82 Rp
5.134 Oh Pekerja @ Rp 50,000.00 Rp
5.134 Oh Tukang las @ Rp 80,000.00 Rp
0.513 Oh Kepala Tukang Besi @ Rp 100,000.00 Rp
0.257 Oh Mandor @ Rp 100,000.00 Rp
Rp
N.6.8 Mengecat 1 M2 bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup
0.200 Kg Cat meni @ Rp 12,500.00 Rp
0.150 Kg Dempul @ Rp 21,000.00 Rp
0.170 Kg Cat dasar @ Rp 17,000.00 Rp
0.260 Kg Cat kayu @ Rp 50,000.00 Rp
0.070 Oh Pekerja @ Rp 50,000.00 Rp
0.009 Oh Tukang cat @ Rp 70,000.00 Rp
0.006 Oh Kepala Tukang Cat @ Rp 100,000.00 Rp
0.0025 Oh Mandor @ Rp 100,000.00 Rp
Rp
N.6.14 Mengecat 1 M2 tembok baru (1 lapis plamir, 1 lapis cat dasar, dan 2 lapis cat penutup)
0.100 Kg Plamur tembok @ Rp 21,000.00 Rp
0.100 Kg Cat dasar @ Rp 17,000.00 Rp
0.260 Kg Cat tembok Kw. 1 @ Rp 57,500.00 Rp
0.060 Oh Pekerja @ Rp 50,000.00 Rp
0.189 Oh Tukang cat @ Rp 70,000.00 Rp
0.0189 Oh Kepala Tukang Cat @ Rp 100,000.00 Rp
0.0075 Oh Mandor @ Rp 100,000.00 Rp
Rp
N.6.14 - SPL Mengecat 1 M2 tembok baru (1 lapis plamir, 1 lapis cat dasar, dan 2 lapis cat penutup), (Eksterior)
0.100 Kg Plamur tembok @ Rp 21,000.00 Rp
0.100 Kg Cat dasar @ Rp 17,000.00 Rp
0.260 Kg Cat tembok Kw. 2 @ Rp 29,000.00 Rp
0.060 Oh Pekerja @ Rp 50,000.00 Rp
0.189 Oh Tukang cat @ Rp 70,000.00 Rp
0.0189 Oh Kepala Tukang Cat @ Rp 100,000.00 Rp
0.0075 Oh Mandor @ Rp 100,000.00 Rp
Rp
N.6.15 - SPL Mengecat 1 M2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
0.120 Kg Cat dasar @ Rp 17,000.00 Rp
0.180 Kg Cat tembok Kw. 2 @ Rp 29,000.00 Rp
0.084 Oh Pekerja @ Rp 50,000.00 Rp
0.1260 Oh Tukang cat @ Rp 70,000.00 Rp
0.0126 Oh Kepala Tukang Cat @ Rp 100,000.00 Rp
0.0150 Oh Mandor @ Rp 100,000.00 Rp
Rp
N.6.23 Mengecat 1 M2 permukaan baja lapis seng (galbani) secara manual sistem 1 lapis
cat mutakhir dengan tebal 200 m
0.300 Kg Cat meni @ Rp 12,500.00 Rp
0.006 Oh Pekerja @ Rp 50,000.00 Rp
0.060 Oh Tukang cat @ Rp 70,000.00 Rp
0.012 Oh Kepala Tukang Cat @ Rp 100,000.00 Rp
0.006 Oh Mandor @ Rp 100,000.00 Rp
Rp
PEKERJAAN LISTRIK
1.000 M2 RUMPUT
1.000 M2 Rumput Gajah Mini @ Rp 14,500.00 Rp
Pekerjaan Penanaman 1 M2 Rumput @ Rp 17,606.25 Rp
Rp
37,500.00
2,500.00
40,000.00
45,000.00
4,500.00
49,500.00
60,000.00
4,500.00
64,500.00
12,500.00
800.00
13,300.00
25,000.00
5,000.00
30,000.00
144,000.00
15,000.00
1,000.00
160,000.00
180,000.00
15,000.00
1,000.00
196,000.00
192,000.00
12,500.00
2,500.00
207,000.00
100,000.00
120,000.00
-
80,000.00
300,000.00
24,000,000.00
2,000.00
24,002,000.00
1,000,000.00
-
-
-
1,000,000.00
25,302,000.00
210,850.00
192,000.00
179,300.00
65,000.00
105,000.00
37,500.00
7,500.00
7,500.00
593,800.00
192,000.00
149,600.00
68,000.00
105,000.00
37,500.00
7,500.00
7,500.00
567,100.00
192,000.00
51,840.00
39,000.00
27,300.00
3,900.00
3,900.00
317,940.00
4,500.00
17,000.00
5,000.00
4,250.00
2,500.00
159,900.00
106,600.00
138,125.00
437,875.00
55,250.00
1,968.00
50,000.00
5,000.00
37,500.00
10,000.00
20,000.00
179,718.00
100,000.00
1,000.00
40,000.00
141,000.00
77,000.00
36,245.00
11,375.00
30,000.00
14,000.00
2,000.00
3,000.00
173,620.00
77,000.00
29,205.00
11,625.00
30,000.00
14,000.00
2,000.00
3,000.00
166,830.00
77,000.00
24,420.00
12,750.00
30,000.00
14,000.00
2,000.00
3,000.00
163,170.00
38,500.00
15,807.00
5,000.00
15,000.00
7,000.00
1,000.00
1,500.00
83,807.00
38,500.00
12,650.00
5,375.00
15,000.00
7,000.00
1,000.00
1,500.00
81,025.00
38,500.00
10,648.00
5,625.00
15,000.00
7,000.00
1,000.00
1,500.00
79,273.00
8,553.60
2,875.00
15,000.00
10,500.00
1,500.00
1,500.00
39,928.60
6,864.00
3,000.00
15,000.00
10,500.00
1,500.00
1,500.00
38,364.00
5,702.40
3,250.00
15,000.00
10,500.00
1,500.00
1,500.00
37,452.40
550.00
1,625.00
4,000.00
28,000.00
4,000.00
400.00
38,575.00
3,575.00
7,500.00
7,000.00
1,000.00
800.00
19,875.00
9,900,000.00
18,750.00
25,000.00
350,000.00
1,470,000.00
210,000.00
35,000.00
12,008,750.00
360,000.00
12,500.00
50,000.00
210,000.00
30,000.00
5,000.00
667,500.00
216,000.00
7,500.00
40,000.00
168,000.00
24,000.00
4,000.00
459,500.00
112,500.00
450.00
12,500.00
85,000.00
30,000.00
140,000.00
20,000.00
3,000.00
403,450.00
112,500.00
450.00
12,500.00
65,000.00
129,500.00
30,000.00
175,000.00
25,000.00
3,000.00
552,950.00
232,320.00
36,000.00
24,000.00
182,922.00
271,395.00
167,900.00
57,600.00
336,000.00
48,000.00
5,760.00
1,361,897.00
162,800.00
14,800.00
18,375.00
87,630.00
45,537.00
67,340.00
6,562.50
11,500.00
25.00
3,500.00
56,000.00
700.00
1,200.00
475,969.50
61,600.00
3,000.00
7,500.00
17,500.00
2,500.00
7,500.00
99,600.00
97,200.00
750.00
5,000.00
14,000.00
2,000.00
500.00
119,450.00
271,700.00
90,003.57
192,400.00
107,500.00
82,500.00
19,250.00
2,800.00
8,300.00
774,453.57
253,000.00
92,489.29
197,792.59
100,000.00
60,000.00
14,000.00
2,000.00
6,000.00
725,281.88
358,600.00
78,714.29
198,177.78
107,500.00
82,500.00
19,250.00
2,800.00
8,300.00
855,842.06
408,100.00
72,292.86
201,644.44
107,500.00
82,500.00
19,250.00
2,800.00
8,300.00
902,387.30
422,400.00
71,671.43
200,103.70
107,500.00
82,500.00
19,250.00
2,800.00
8,300.00
914,525.13
446,600.00
70,842.86
197,600.00
107,500.00
82,500.00
19,250.00
2,800.00
8,300.00
935,392.86
454,300.00
70,532.14
196,637.04
107,500.00
82,500.00
19,250.00
2,800.00
8,300.00
941,819.18
115,500.00
2,850.00
3,500.00
5,600.00
700.00
400.00
128,550.00
12,855.00
126,000.00
2,850.00
3,500.00
5,600.00
700.00
400.00
139,050.00
13,905.00
120,000.00
4,500.00
750.00
26,000.00
18,200.00
2,600.00
2,600.00
174,650.00
60,000.00
4,500.00
750.00
26,000.00
18,200.00
2,600.00
2,600.00
114,650.00
135,000.00
4,500.00
750.00
26,000.00
18,200.00
2,600.00
2,600.00
189,650.00
67,500.00
4,500.00
750.00
26,000.00
18,200.00
2,600.00
2,600.00
122,150.00
120,000.00
6,000.00
1,500.00
60,000.00
45,150.00
30,000.00
33,000.00
23,100.00
3,300.00
3,300.00
325,350.00
60,000.00
6,000.00
1,500.00
30,000.00
22,575.00
15,000.00
33,000.00
23,100.00
3,300.00
3,300.00
197,775.00
120,000.00
6,000.00
1,500.00
72,000.00
45,150.00
30,000.00
33,000.00
23,100.00
3,300.00
3,300.00
337,350.00
60,000.00
6,000.00
1,500.00
36,000.00
22,575.00
15,000.00
33,000.00
23,100.00
3,300.00
3,300.00
203,775.00
120,000.00
6,000.00
1,500.00
60,000.00
45,150.00
90,000.00
33,000.00
23,100.00
3,300.00
3,300.00
385,350.00
60,000.00
6,000.00
1,500.00
30,000.00
22,575.00
45,000.00
33,000.00
23,100.00
3,300.00
3,300.00
227,775.00
90,000.00
6,000.00
1,500.00
80,000.00
45,150.00
45,000.00
30,000.00
33,000.00
23,100.00
3,300.00
3,300.00
360,350.00
45,000.00
6,000.00
1,500.00
40,000.00
22,575.00
22,500.00
15,000.00
33,000.00
23,100.00
3,300.00
3,300.00
215,275.00
90,000.00
6,000.00
1,125.00
60,000.00
45,150.00
30,000.00
33,000.00
23,100.00
3,300.00
3,300.00
294,975.00
45,000.00
6,000.00
1,125.00
30,000.00
22,575.00
15,000.00
33,000.00
23,100.00
3,300.00
3,300.00
182,400.00
144,000.00
7,500.00
5,250.00
800.00
800.00
158,350.00
95,000.00
8,800.00
4,000.00
20,000.00
14,000.00
2,000.00
200.00
144,000.00
#N/A
3,000.00
10,000.00
7,000.00
1,000.00
100.00
#N/A
207,366.00
25,500.00
10,000.00
7,000.00
1,000.00
100.00
250,966.00
#N/A
750.00
12,500.00
10,500.00
1,500.00
1,300.00
#N/A
97,440.00
15,000.00
12,500.00
10,500.00
1,500.00
1,300.00
138,240.00
#N/A
#N/A
6,000.00
4,200.00
600.00
600.00
#N/A
#N/A
#N/A
10,500.00
7,000.00
400.00
600.00
#N/A
22,000.00
3,500.00
20,020.00
5,000.00
7,000.00
1,000.00
5,000.00
5,000.00
68,520.00
44,000.00
2,625.00
170,940.00
5,000.00
7,000.00
1,000.00
5,000.00
5,000.00
240,565.00
15,750.00
7,500.00
3,500.00
500.00
800.00
28,050.00
#N/A
150.00
1,500.00
4,900.00
700.00
200.00
#N/A
67,500.00
150.00
30,000.00
56,000.00
8,000.00
3,000.00
164,650.00
25,188.80
4,400.00
5,000.00
3,500.00
500.00
500.00
39,088.80
25,520.00
7,500.00
25,188.80
5,400.00
560.00
11,500.00
2,500.00
3,500.00
56,000.00
700.00
1,200.00
139,568.80
25,520.00
7,500.00
20,020.00
5,400.00
560.00
11,500.00
2,500.00
3,500.00
56,000.00
700.00
1,200.00
134,400.00
162,800.00
7,500.00
18,375.00
87,630.00
25,188.80
5,400.00
560.00
11,500.00
2,500.00
3,500.00
56,000.00
700.00
1,200.00
382,853.80
20,300.00
477,750.00
11,500.00
3,500.00
56,000.00
700.00
1,200.00
570,950.00
10,500.00
4,000.00
2,500.00
3,500.00
500.00
300.00
21,300.00
1,850,000.00
111,000.00
165,000.00
77,000.00
100.00
16,000.00
2,219,100.00
175,000.00
6,600.00
1,250.00
50,000.00
105,000.00
150,000.00
16,000.00
503,850.00
1,900,000.00
570,000.00
6,600.00
1,250.00
50,000.00
70,000.00
30,000.00
11,000.00
2,638,850.00
400,000.00
48,000.00
6,600.00
1,250.00
60,000.00
101,500.00
15,000.00
10,000.00
642,350.00
8,500,000.00
170,000.00
375.00
6,000.00
750.00
380.00
8,677,505.00
36,014.40
10,504.20
2,700.00
7,200.00
900.00
2,700.00
60,018.60
46,641.60
13,603.80
2,700.00
7,200.00
900.00
2,700.00
73,745.40
72,028.80
21,008.40
2,700.00
7,200.00
900.00
2,700.00
106,537.20
106,567.20
31,082.10
5,400.00
14,400.00
1,800.00
540.00
159,789.30
91,732.80
26,755.40
5,400.00
14,400.00
1,800.00
540.00
140,628.20
150,552.00
43,911.00
5,400.00
14,400.00
1,800.00
540.00
216,603.00
192,175.20
56,051.10
5,400.00
14,400.00
1,800.00
540.00
270,366.30
250,034.40
72,926.70
5,400.00
14,400.00
1,800.00
540.00
345,101.10
354,240.00
103,320.00
6,750.00
18,000.00
2,250.00
680.00
485,240.00
30,744.00
8,967.00
2,700.00
7,200.00
900.00
2,700.00
53,211.00
39,816.00
11,613.00
2,700.00
7,200.00
900.00
2,700.00
64,929.00
61,488.00
17,934.00
2,700.00
7,200.00
900.00
2,700.00
92,922.00
90,972.00
26,533.50
5,400.00
14,400.00
1,800.00
540.00
139,645.50
79,128.00
23,079.00
5,400.00
14,400.00
1,800.00
540.00
124,347.00
128,520.00
37,485.00
5,400.00
14,400.00
1,800.00
540.00
188,145.00
164,052.00
47,848.50
5,400.00
14,400.00
1,800.00
540.00
234,040.50
213,444.00
62,254.50
5,400.00
14,400.00
1,800.00
540.00
297,838.50
302,400.00
88,200.00
6,750.00
18,000.00
2,250.00
680.00
418,280.00
9,025.20
2,632.35
1,800.00
4,800.00
600.00
180.00
19,037.55
49,500.00
14,437.50
1,800.00
4,800.00
600.00
180.00
71,317.50
7,272.00
2,121.00
1,800.00
4,800.00
600.00
180.00
16,773.00
10,540.80
3,074.40
1,800.00
4,800.00
600.00
180.00
20,995.20
18,535.20
5,406.10
1,800.00
4,800.00
600.00
180.00
31,321.30
26,331.60
7,680.05
2,700.00
7,200.00
900.00
270.00
45,081.65
33,919.20
9,893.10
2,700.00
7,200.00
900.00
270.00
54,882.30
51,676.80
15,072.40
4,050.00
10,800.00
1,350.00
410.00
83,359.20
79,903.20
23,305.10
4,050.00
10,800.00
1,350.00
410.00
119,818.30
250,000.00
50,000.00
1,500.00
21,000.00
3,000.00
150.00
325,650.00
35,000.00
87.50
500.00
8,000.00
1,000.00
500.00
45,087.50
250,000.00
87.50
500.00
8,000.00
1,000.00
500.00
260,087.50
50,000.00
87.50
500.00
8,000.00
1,000.00
500.00
60,087.50
265,000.00
87.50
500.00
8,000.00
1,000.00
500.00
275,087.50
45,000.00
87.50
500.00
8,000.00
1,000.00
500.00
55,087.50
35,000.00
500.00
7,000.00
1,000.00
500.00
44,000.00
50,000.00
500.00
7,000.00
1,000.00
500.00
59,000.00
11,449.11
3,000.00
4,800.00
600.00
300.00
20,149.11
12,578.13
3,000.00
4,800.00
600.00
300.00
21,278.13
11,761.36
3,000.00
4,800.00
600.00
300.00
20,461.36
16,382.69
3,000.00
4,800.00
600.00
300.00
25,082.69
10,396.68
3,000.00
4,800.00
600.00
300.00
19,096.68
12,650.00
3,000.00
4,800.00
600.00
300.00
21,350.00
23,819.18
3,000.00
4,800.00
600.00
300.00
32,519.18
29,559.60
3,000.00
4,800.00
600.00
300.00
38,259.60
17,278.80
3,000.00
4,800.00
600.00
300.00
25,978.80
12,972.00
3,000.00
4,800.00
600.00
300.00
21,672.00
5,000.00
2,500.00
5,000.00
8,000.00
100.00
500.00
800.00
21,900.00
219.00
86,780.70
3,700.00
5,400.00
2,150.00
3,440.00
430.00
210.00
102,110.70
80,190.00
68,681.25
55,242.00
5,400.00
2,150.00
3,440.00
430.00
210.00
6,803.78
98,623.78
87,115.03
73,675.78
3,466,127.70
50,000.00
200,000.00
25,000.00
5,000.00
1,733,063.85
173,306.39
5,652,497.94
2,440,935.00
50,000.00
200,000.00
25,000.00
5,000.00
1,220,467.50
122,046.75
4,063,449.25
320,760.00
122,034.00
22,000.00
46,479.40
4,250.00
6,800.00
900.00
500.00
523,723.40
157,439.70
56,017.50
50,000.00
15,675.00
27,913.22
2,108.43
3,373.48
446.49
242.00
313,215.82
880,000.00
52,500.00
84,000.00
10,500.00
520.00
1,027,520.00
220,968.00
62,370.00
22,000.00
30,533.80
4,250.00
6,800.00
900.00
500.00
348,321.80
228,558.63
457,117.04
568,776.49
125,445.22
266,674.50
426,679.20
53,334.90
26,667.45
2,153,253.42
434,010.00
1,217,546.06
495,466.82
256,723.13
410,757.00
51,344.63
25,672.31
2,891,519.93
3,151,041.67
864,000.00
740,000.00
43,750.00
216,000.00
175,000.00
280,000.00
100,000.00
5,000.00
475,504.17
6,050,295.83
605,029.58
227,000.00
500.00
35,000.00
1,000.00
500.00
264,000.00
350,000.00
250.00
35,000.00
500.00
250.00
386,000.00
28,000.00
750.00
10,500.00
1,500.00
75.00
40,825.00
900,000.00
750.00
21,000.00
3,000.00
75.00
924,825.00
25,000.00
500.00
7,000.00
1,000.00
50.00
33,550.00
20,000.00
750.00
10,500.00
1,500.00
75.00
32,825.00
28,000.00
500.00
7,000.00
1,000.00
50.00
36,550.00
250,000.00
2,500.00
35,000.00
5,000.00
250.00
292,750.00
500,000.00
225,000.00
1,000.00
14,000.00
2,000.00
100.00
517,100.00
242,100.00
150,000.00
2,500.00
35,000.00
5,000.00
250.00
192,750.00
165,000.00
750.00
10,500.00
1,500.00
75.00
177,825.00
77,000.00
750.00
10,500.00
1,500.00
75.00
89,825.00
701,085.00
750.00
10,500.00
1,500.00
75.00
713,910.00
251,805.05
10,560.00
5,625.00
2,475.00
12,500.00
8,400.00
1,200.00
1,300.00
293,865.05
247,418.97
10,780.00
5,625.00
2,145.00
12,500.00
8,400.00
1,200.00
1,300.00
289,368.97
56,355.00
10,780.00
5,625.00
2,145.00
35,000.00
24,500.00
3,500.00
3,500.00
141,405.00
48,559.09
11,000.00
5,625.00
2,475.00
35,000.00
24,500.00
3,500.00
3,500.00
134,159.09
50,350.00
11,440.00
5,625.00
2,673.00
31,000.00
24,500.00
3,500.00
3,000.00
132,088.00
50,400.00
10,230.00
2,250.00
3,201.00
30,000.00
31,500.00
4,500.00
3,000.00
135,081.00
52,000.00
10,230.00
2,250.00
3,201.00
30,000.00
31,500.00
4,500.00
3,000.00
136,681.00
30,600.00
1,254.00
375.00
165.00
4,500.00
6,300.00
900.00
500.00
44,594.00
445,200.00
9,009.00
5,625.00
1,072.50
31,000.00
24,500.00
3,500.00
3,000.00
522,906.50
676,280.00
9,009.00
5,625.00
1,072.50
31,000.00
24,500.00
3,500.00
3,000.00
753,986.50
428,400.00
50,000.00
13,684.00
3,125.00
1,072.50
36,000.00
45,500.00
6,500.00
3,500.00
587,781.50
209,000.00
12,925.00
4,375.00
31,000.00
24,500.00
3,500.00
3,000.00
288,300.00
59,500.00
1,254.00
375.00
165.00
4,500.00
6,300.00
900.00
500.00
73,494.00
367,500.00
6,125.00
8,500.00
11,900.00
1,700.00
900.00
396,625.00
78,750.00
6,125.00
6,000.00
8,400.00
1,200.00
600.00
101,075.00
2,500.00
3,150.00
2,890.00
13,000.00
3,500.00
630.00
600.00
250.00
26,520.00
18,000.00
2,000.00
4,410.00
6,300.00
250.00
30,960.00
2,100.00
1,700.00
14,950.00
3,000.00
13,230.00
1,890.00
750.00
37,620.00
2,100.00
1,700.00
7,540.00
3,000.00
13,230.00
1,890.00
750.00
30,210.00
2,040.00
5,220.00
4,200.00
8,820.00
1,260.00
1,500.00
23,040.00
2,100.00
1,400.00
2,940.00
420.00
250.00
7,110.00
3,750.00
300.00
4,200.00
1,200.00
600.00
10,050.00
209,440.00
16,000.00
8,000.00
5,000.00
2,000.00
28,000.00
500.00
500.00
45,000.00
50,000.00
364,440.00
235,620.00
18,000.00
40,000.00
5,000.00
3,000.00
28,000.00
500.00
500.00
45,000.00
50,000.00
425,620.00
281.25
9,375.00
1,875.00
1,500.00
375.00
2,100.00
2,100.00
17,606.25
14,500.00
17,606.25
32,106.25
DAFTAR HARGA BAHAN DAN UPAH
Tahun Anggaran 2012
I. HARGA BAHAN
BAHAN SEMEN
Semen PC 50kg (zak) Zak Rp.
Semen Portland Kg Rp.
Semen PC 40 kg (zak) Zak Rp.
Semen Nat Kg Rp.
Semen Putih Zak Rp.
Semen warna Kg Rp.
BAHAN BESI
Besi beton polos Kg Rp.
Besi beton ulir Kg Rp.
Besi Siku L. 50. 50. 5 Kg Rp.
Besi Siku L. 60. 60. 6 Kg Rp.
Besi Siku L. 70. 70. 7 Kg Rp.
Besi Profil Kanal C. 125 x 50 x 20 x 2,3 Kg Rp.
Besi Profil H Beam 300 x 300 x 10 x 15 Kg Rp.
Besi Profil H Beam 200 x 200 x 8 x 12 Kg Rp.
Besi Profil IWF Kg Rp.
Plat Baja T = 10 mm Kg Rp.
Plat Baja T = 8 mm Kg Rp.
Plat Baja T = 5 mm Kg Rp.
Plat Baja T = 2 mm Kg Rp.
Kawat beton Kg Rp.
Kawat Rang 3 x 3 M2 Rp.
Paku Biasa 1/2" - 1" Kg Rp.
Paku biasa 2" - 5" Kg Rp.
Paku asbes Kg Rp.
Paku beton Dos Rp.
Paku pancing Kg Rp.
Paku Sekrup Galvaniz Dia. 3 mm Bj Rp.
Besi Hollow 20 x 40 x 1.8 mm M Rp.
Besi Hollow 30 x 30 x 1.8 mm M Rp.
Besi Hollow 30 x 30 x 2.3 mm M Rp.
Besi Hollow 40 x 40 x 1.8 mm M Rp.
Besi Hollow 40 x 40 x 2.3 mm M Rp.
Besi Hollow Galvanis 2 x 4 MB, Tbl 0.7 mm M Rp.
Besi Hollow Galvanis 4 x 4 MB, Tbl 0.7 mm M Rp.
Besi strip Kg Rp.
Baut - Baut Bh Rp.
Baut Dia. 16 mm Bh Rp.
Paku sekrup 3,5" Kg Rp.
Paku sekrup 4"-6" Kg Rp.
Jarum Pengeras Bh Rp.
Srews/sekrup Bh Rp.
BAHAN SENG/ALUMINIUM
Seng plat BJLS 0.30 Lbr Rp.
Seng plat BJLS 0.28 Lbr Rp.
Seng gelombang BWG 34 " BJLS 0.18 mm Kaki Rp.
Seng gelombang BWG 33 " BJLS 0.22 mm Kaki Rp.
Seng gelombang BWG 32 " BJLS 0.30 mm Kaki Rp.
Seng gelombang BWG 28 " BJLS 0.35 mm Kaki Rp.
BAHAN KAYU
Kayu klas I (balok) untuk kuda-kuda M3 Rp.
Kayu klas II (balok) M3 Rp.
Kayu klas II (papan) M3 Rp.
Kayu klas III (balok) M3 Rp.
Kayu klas III (papan) M3 Rp.
Kayu klas I (papan) listplank dan pintu/jendela M3 Rp.
Dolken kayu 8-10/400 cm Btg Rp.
Kayu klas I (balok) untuk kosen pintu/jendela M3 Rp.
53,000.00
1,100.00
44,000.00
7,500.00
53,000.00
1,650.00
11,000.00
12,000.00
9,955.75
10,937.50
10,227.27
9,040.59
11,873.92
15,025.04
11,280.00
14,245.82
15,775.40
16,452.00
16,488.00
19,000.00
17,500.00
15,000.00
15,000.00
27,500.00
25,000.00
25,000.00
1,500.00
21,600.00
20,800.00
26,400.00
28,800.00
37,000.00
5,800.00
7,000.00
9,700.00
7,500.00
12,500.00
40,000.00
25,000.00
175,000.00
1,000.00
50,500.00
82,000.00
129,000.00
69,200.00
55,000.00
5,000.00
9,000.00
35,000.00
49,100.00
60,000.00
6,450.00
6,800.00
11,500.00
16,000.00
8,000,000.00
4,000,000.00
4,500,000.00
2,500,000.00
3,000,000.00
9,000,000.00
15,000.00
9,000,000.00
533,000.00
507,000.00
572,000.00
581,120.00
615,680.00
65,000.00
7,500.00
5,000.00
25,000.00
100,000.00
100,000.00
250,000.00
150,000.00
150,000.00
100,000.00
15,000.00
25,000.00
35,000.00
35,000.00
14,500.00
70,000.00
80,000.00
80,000.00
70,000.00
70,000.00
80,000.00
70,000.00
90,000.00
80,000.00
100,000.00
100,000.00
100,000.00
100,000.00
100,000.00
100,000.00
100,000.00
50,000.00
120,000.00
85,000.00
120,000.00
87,000.00
40,000.00
45,000.00
50,000.00
90,000.00
85,000.00
100,000.00
85,000.00
50,000.00
14,011,637,000
Sesuaikan sel yang berwarna merah dengan Sel yang akan ditulis terbilang pada Sheet anda
Copy Sheet ini Ke File Anda
Empat Belas Milyar Sebelas Juta Enam Ratus Tiga Puluh Tujuh Ribu 0 Rupiah
merah dengan Sel yang akan ditulis terbilang pada Sheet anda
0
1
2
3
4
5
6
7
8
9
14011637000
Satu
Dua 14 Milyaran
Tiga Tujuh Ribu 011 Jutaan
Empat Tiga Puluh 637 Ribuan
Lima Enam Ratus 000 Ratusan
Enam Juta
Tujuh Sebelas
Delapan
Sembilan Milyar
Empat Belas
14011637000