Anda di halaman 1dari 12

DAFTAR KUANTITAS DAN HARGA

PEMBANGUNAN GARDU INDUK 150 KV JAKABARING

NO URAIAN PEKERJAAN JUMLAH (RP)

I PEKERJAAN ELEKTROMEKANIK
A PERALATAN ELEKTROMEKANIK 150 kV LINE BAY UNTUK 4 LB 8,305,922,677
B PERALATAN ELEKTROMEKANIK 150/20 KV TRANSFORMER BAY UNTUK 1 TB 963,296,012
C PERALATAN ELEKTROMEKANIK 150/20KV BUS COUPLER BAY : 1 BC 1,831,042,581
D 150/20 kV, 30 MVA POWER TRANSFORMER & ACCESSORIES 6,654,044,770
E 20 kV SWITCHGEAR, POWER CABLES AND AUXIALARY 1,902,363,722
F STEEL STRUCTURE/GANTRY, CONDUCTOR, INSULATOR SET, HV CONECTOR, 4,648,193,647
LIGHTING SYSTEM AND CONTROL CABLE
G SUBSTATION AUTOMATION SYSTEM (SAS) 9,370,722,994
SUB-TOTAL - I 33,675,586,403

II PEKERJAAN SIPIL
1 PEKERJAAN PEMATANGAN TANAH & TEMBOK PENAHAN 1,660,418,980
2 PEKERJAAN JALAN 1,147,687,442
3 PEKERJAAN GEDUNG KONTROL 2,705,176,760
4 PEKERJAAN PONDASI TRAFO, SERANDANG & PERALATAN 2,770,503,164
5 PEKERJAAN SALURAN KABEL SWITCHYARD AREA 1,407,340,000
6 PEKERJAAN DRAINAGE 605,000,000
7 PEKERJAAN PAGAR SWITCHYARD & PAGAR SITE 806,630,000
8 PEKERJAAN HAMPARAN KORAL 315,150,000
9 PEKERJAAN LAIN-LAIN 329,505,000
SUB-TOTAL - II 11,747,411,346
TOTAL (I +II) 45,422,997,749
PPN 10 % 4,542,299,775
JUMLAH KESELURUHAN 49,965,297,000
Terbilang : Empat Puluh Sembilan Milyar Sembilan Ratus Enam Puluh Lima Juta Dua Ratus Sembilan Puluh Tujuh Ribu Rupiah

JAKARTA, 30 November 2012


PT. WISMA SARANA TEKNIK

Ir. Tjahjadi Aquasa


Ketua KSO
Page 1 of 11
Ir. Tjahjadi Aquasa
Ketua KSO

Page 2 of 11
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN GARDU INDUK 150 KV JAKABARING
I. PEKERJAAN ELEKTROMEKANIK
(dalam Rupiah)
PENGADAAN MATERIAL PEMASANGAN MATERIAL
No. URAIAN JUMLAH KESELURUHAN
SATUAN HARGA SATUAN JUMLAH HARGA SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 = (3 x 4) 6 7 8 = (6 x 7) 9 = (5 + 8)

A. PERALATAN ELEKTROMEKANIK 150 kV LINE BAY UNTUK 4 LB


1 Three phase circuit breaker 1600A, 31.5 kA symmetrical short circuit current for 1 sec, 4.00 set 377,087,204 1,508,348,817 4.00 set 6,756,682 27,026,728 1,535,375,545
complete w/supporting structure
2 Three phase busbar disconnector, 1600A, 31.5 kA, 1 sec with 3 phase driving mechanism, 8.00 sets 92,097,372 736,778,977 8.00 sets 5,469,695 43,757,560 780,536,536
motor operated, complete w/supporting structure
3 Three phase line disconnector w/earthing swicth, 1600A, 31.5 kA, 1 sec with 3 phase 4.00 sets 124,536,460 498,145,839 4.00 sets 5,276,647 21,106,588 519,252,426
driving mechanism, motor operated, complete w/supporting structure
4 Single Phase Current Transformer complete w/ supporting structure 12.00 pcs 98,800,837 1,185,610,046 12.00 pcs 3,217,468 38,609,611 1,224,219,657
- core 1: class X ratio 800-1600/1 A, for distance protection
- core 2: class 5P20 ratio 800-1600/1A, 40 VA for OCEF protection and class 0.2 for
instrumen & metering
- core 3: class x ratio 1000-2000/1 A for main bus zone protection
- core 4: class x ratio 1000-2000/1 A for check bus zone protection
5 Single Phase Capacitor Voltage transformer ratio 150000 :√3 /100:√3/ 100:√3 volt, class 12.00 pcs 68,333,221 819,998,648 12.00 pcs 4,504,455 54,053,456 874,052,104
0.2 and 3P 100 VA burden for each ratio, complete w/supporting structure, the CVT shall
be capable to support the associated Line trap

6 Heavy duty outdoor single phase surge arrester, metal oxide, gapless type, 10 kA with 12.00 pcs 41,790,638 501,487,655 12.00 pcs 2,445,275 29,343,305 530,830,960
surge counter, complete w/supporting structure
7 Outdoor marshalling Kiosk 4.00 unit 27,247,355 108,989,420 4.00 unit 4,118,359 16,473,434 125,462,855
8 Fiber Optic Communication facilities, each set consist of
Node SDH - ADM,STM4 Line Interface, 2 MB interface,2 MB digital branchDIU
Datainterfacing unit 64 Kbps, VF 2/4 wire E/M interface, VF Subsc Interface,rack
/cabineting

- Miscellaneous equipment and material including, cable, fibre optic,patch cord, pig tail,
telephone cable, connector, compresion terminal, conection to individual item of
equipment, etc to complete the scope of work

To installed ;
- GI Jakabaring : 1 set multiflexer with 1.00 sets 1,159,092,708 1,159,092,708 1.00 sets 28,957,209 28,957,209 1,188,049,916
- 2 set TP for feeder 1 & 2 keramasan
- 2 set TP for feeder 1 & 2 mariana
- GI Keramasan for feeder 1 & 2 Jakabaring : 1 set multiflexer, 2 set TP include 1.00 sets 265,408,903 265,408,903 1.00 sets 32,174,676 32,174,676 297,583,580
functioned well (operation)
- GI Mariana for feeder 1 & 2 Jakabaring : 2 set TP include functioned well (operation) 1.00 sets 181,626,047 181,626,047 1.00 sets 32,174,676 32,174,676 213,800,723

Nama Penyedia Jasa :


Page 2 of 11
Stempel dan Tanda Tangan :
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN GARDU INDUK 150 KV JAKABARING
I. PEKERJAAN ELEKTROMEKANIK
(dalam Rupiah)
PENGADAAN MATERIAL PEMASANGAN MATERIAL
No. URAIAN JUMLAH KESELURUHAN
SATUAN HARGA SATUAN JUMLAH HARGA SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 = (3 x 4) 6 7 8 = (6 x 7) 9 = (5 + 8)

9 PAX 1.00 sets 216,535,570 216,535,570 1.00 sets 10,939,390 10,939,390 227,474,960
- Cabinet : 160 Port ( expandable up to 640 ports)
- CPU-4000 and S/W 810
- BSPlicence ( Port licence) up to 96 extension
- 8 Line E&M Networking 4 wire ( expandable)
- 16 Line Extension Analog ( expandable)
- Mdf 2 x 100 pairs (krone) LSA + solder less with metal box
- Support to SDH,PDH
- 2 set Analogue Telephone Set " Baseline"
- cable network 2x2x0.6 mm include supporting material for analogue telephone set "
Baseline" (2 Point)
- cable layout from PAX to MDF
- PAX Programing
- System Testing & Commissioning

10 110 V/DC supply system, Minimum for consumption 9 bay 1.00 sets 395,870,780 395,870,780 1.00 sets 8,365,416 8,365,416 404,236,196
a. 110V DC Battery, complete with rack and accessories
b. 110V DC charger 80A
c. 110V DC Distribution Board with under and over voltage relay ,minimum for 9 bays
11 48 V/DC supply system, consist of 1.00 sets 141,806,668 141,806,668 1.00 sets 7,078,429 7,078,429 148,885,096
a. 48V DC Battery, 150Ah, complete with rack and accessories
b. 48V DC charger 60A
c. 48V DC Distribution Board with under and over voltage relay ,minimum for 9 bays
12 AC Distribution Board 220/380 volt with under and over voltage relay ,minimum for 9 1.00 sets 231,657,668 231,657,668 1.00 sets 4,504,455 4,504,455 236,162,123
bays
SUB JUMLAH (A) 7,951,357,746 354,564,931 8,305,922,677

Nama Penyedia Jasa :


Page 3 of 11
Stempel dan Tanda Tangan :
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN GARDU INDUK 150 KV JAKABARING
I. PEKERJAAN ELEKTROMEKANIK
(dalam Rupiah)
PENGADAAN MATERIAL PEMASANGAN MATERIAL
No. URAIAN JUMLAH KESELURUHAN
SATUAN HARGA SATUAN JUMLAH HARGA SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 = (3 x 4) 6 7 8 = (6 x 7) 9 = (5 + 8)

B. PERALATAN ELEKTROMEKANIK 150/20KV TRANSFORMER BAY UNTUK 1 TB


1 Three phase Circuit Breaker, 1250A, 31.5kA symmetrical short circuit current for 1 sec, 1.00 set 302,184,558 302,184,558 1.00 set 6,756,682 6,756,682 308,941,240
complete with supporting structure ,

2 Three phase busbar disconnecting swicth, 1250A, 31.5kA, 1 sec. with stand current, 2.00 sets 88,564,528 177,129,057 2.00 sets 5,276,647 10,553,294 187,682,350
without earthing swicth complete w/supporting structure

3 Single phase Current Transformer comprising : 3.00 pcs 97,648,855 292,946,565 3.00 pcs 3,217,468 9,652,403 302,598,968
- core 1: class X ratio 150-300/1A for differential protection
- core 2: class 5P20 ratio 150-300/1A, 40 VA, for OCEF protection, and class 0.2 for
instrument and metering with supporting structure
- core 3: class X ratio 1000-2000/1A for main bus zone protection
- core 4: class X ratio 1000-2000/1A for check zone busbar protection complete
w/supporting structure
4 Heavy duty oudoor single phase surge arrester, metal oxide, gapless type, 10 kA with surge 3.00 pcs 41,790,638 125,371,914 3.00 pcs 2,445,275 7,335,826 132,707,740
counter complete w/supporting structure
5 Outdoor marshaling kiosk 1.00 pcs 27,247,355 27,247,355 1.00 pcs 4,118,359 4,118,359 31,365,714

SUB JUMLAH (B) 924,879,449 38,416,563 963,296,012

C PERALATAN ELEKTROMEKANIK BUS COUPLER BAY : 1 BC


1 Three phase circuit breaker 2000A, 31.5 kA symmetrical short circuit current for 1 sec, 1.00 sets 302,184,558 302,184,558 1.00 sets 6,756,682 6,756,682 308,941,240
complete w/supporting structure

2 Three phase busbar disconnector, 2000A, 31.5 kA, 1 sec with 3 phase driving mechanism, 2.00 sets 305,115,285 610,230,570 2.00 sets 5,276,647 10,553,294 620,783,864
motor operated, complete w/supporting structure

3 Single Phase Current Transformer complete w/ supporting structure 6.00 pcs 141,774,493 850,646,957 6.00 pcs 3,217,468 19,304,806 869,951,763
- core 1: class x ratio 1000-2000/1 A for main bus zone protection
- core 2: class x ratio 1000-2000/1 A for check bus zone protection

4 Outdoor marshalling Kiosk 1.00 unit 27,247,355 27,247,355 1.00 unit 4,118,359 4,118,359 31,365,714

SUB JUMLAH (C) 1,790,309,441 40,733,140 1,831,042,581

Nama Penyedia Jasa :


Page 4 of 11
Stempel dan Tanda Tangan :
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN GARDU INDUK 150 KV JAKABARING
I. PEKERJAAN ELEKTROMEKANIK
(dalam Rupiah)
PENGADAAN MATERIAL PEMASANGAN MATERIAL
No. URAIAN JUMLAH KESELURUHAN
SATUAN HARGA SATUAN JUMLAH HARGA SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 = (3 x 4) 6 7 8 = (6 x 7) 9 = (5 + 8)

D 150/20 kV, 30 MVA POWER TRANSFORMER & ACCESSORIES


1 150/20 kV, 30 MVA, 3 phase power transformer, vacuum OLTC, include NCT 150 kV, cable 1.00 unit 6,216,469,175 6,216,469,175 1.00 unit 135,133,640 135,133,640 6,351,602,815
support, post insulator, oil treatment and all necessary works/

2 20 kV NGR, 40 ohm, 10 sec, 20 kV NCT for REF and EF& accessories to complete scope of 1.00 set 299,224,488 299,224,488 1.00 set 3,217,468 3,217,468 302,441,956
work

SUB JUMLAH (D) 6,515,693,663 138,351,107 6,654,044,770

E 20 kV SWITCHGEAR, POWER CABLES AND AUXIALARY


1 20 kv XLPE cable, 2X630 sqmm CU , include cable support, post insulator, metal bars, cable 1.00 lot 223,971,742 223,971,742 1.00 lot 19,304,806 19,304,806 243,276,547
terminations and accessories to complete scope of work
2 Incoming cubicle with 1-phase VT and busbar VT cubicle include 20 kV CB, digital 1.00 sets 303,246,323 303,246,323 1.00 sets 4,182,708 4,182,708 307,429,030
voltmeter, single tariff rate metering digital kWH meter, class 0.2( All equipment are
according to IEC 61850 )

3 Outgoing cubicle incl. 20 KV CB, single rate tarif metering digital KWH meter cl 0.2( All 5.00 sets 207,204,914 1,036,024,571 5.00 set 4,182,708 20,913,539 1,056,938,111
equipment are according to IEC 61850 )
4 Auxialiary transformer 20/0.4 kV , 200 KVA include power cable and termination, etc to 1.00 sets 113,254,860 113,254,860 1.00 set 32,818,170 32,818,170 146,073,030
complete scope of work
5 Auxiliary transformer cubicle include all accessories to complete scope of work 1.00 sets 144,464,296 144,464,296 1.00 set 4,182,708 4,182,708 148,647,004
(semua fungsi control data dan status 20 kv incoming dan out going harus bisa di akses dari HMI).

SUB JUMLAH (E) 1,820,961,791 81,401,931 1,902,363,722

Nama Penyedia Jasa :


Page 5 of 11
Stempel dan Tanda Tangan :
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN GARDU INDUK 150 KV JAKABARING
I. PEKERJAAN ELEKTROMEKANIK
(dalam Rupiah)
PENGADAAN MATERIAL PEMASANGAN MATERIAL
No. URAIAN JUMLAH KESELURUHAN
SATUAN HARGA SATUAN JUMLAH HARGA SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 = (3 x 4) 6 7 8 = (6 x 7) 9 = (5 + 8)

F STEEL STRUCTURE/GANTRY,CONDUCTOR,INSULATORSET, HV CONECTOR,LIGHTING SYSTEM


AND
1 CONTROL CABLE
Steel structure/gantry ( refer to drawing ) comprising ;
column Type I height = 18 m 14.00 unit 69,406,220 971,687,085 14.00 unit 6,113,188 85,584,639 1,057,271,724
column Type II height = 9 m 4.00 unit 43,008,533 172,034,132 4.00 unit 5,276,647 21,106,588 193,140,720
Beam length = 14 m upper 12.00 unit 29,074,646 348,895,753 12.00 unit 4,504,455 54,053,456 402,949,209
Beam length = 14 m bottom 8.00 unit 29,074,646 232,597,169 8.00 unit 4,118,359 32,946,868 265,544,037
2. conductor 1XHALL 1000 mm2 for double main busbar arrangement to complete scoup of 1.00 lot 67,598,995 67,598,995 1.00 lot 10,167,198 10,167,198 77,766,192
work
3 conductor 1XHALL 800 sqmm2 for cross busbar & droppers/jumpers to complete scoup of 1.00 lot 177,578,472 177,578,472 1.00 lot 21,557,033 21,557,033 199,135,505
work
4 Single tension string insulator set & hardware ( 1set consist of 12 discs) 72.00 sets 4,337,146 312,274,537 72.00 sets 321,747 23,165,767 335,440,303
5 Single suspension string insulator set & hardware ( 1set consist of 12 discs) 36.00 sets 3,114,509 112,122,311 36.00 sets 321,747 11,582,883 123,705,195
6 Bolted type HV connector suitable for : HAL 1000 mm2, HAL 1000 mm2 to HV equipment 1.00 lot 196,021,267 196,021,267 1.00 lot 38,480,913 38,480,913 234,502,180
line bay, HAL 1000 mm to ACSR 2 x 340/30 mm2, include GSW 55 mm2 and instalation
grounding system in control building and raiser to all apparatus & cubicle and HV
equipment w/ size BCC 120 mm2,etc to complete scope of work

7 Mercury vapour flourescent lamp 1x250 watt for switchyard, complete with fitting, fuse 26.00 titik 15,443,845 401,539,958 26.00 titik 579,144 15,057,748 416,597,707
box, grounding, cable, etc to complete the scope of work
8 LV power and Multicore control cables, grounding wire from mess to all equipment include 1.00 lot 1,284,226,458 1,284,226,458 1.00 lot 57,914,417 57,914,417 1,342,140,875
all accessories to complete the scope of work ( 4LB, 1 TB,1BC cubicle 20 kV)

SUB JUMLAH (F) 4,276,576,137 371,617,509 4,648,193,647

Nama Penyedia Jasa :


Page 6 of 11
Stempel dan Tanda Tangan :
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN GARDU INDUK 150 KV JAKABARING
I. PEKERJAAN ELEKTROMEKANIK
(dalam Rupiah)
PENGADAAN MATERIAL PEMASANGAN MATERIAL
No. URAIAN JUMLAH KESELURUHAN
SATUAN HARGA SATUAN JUMLAH HARGA SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 = (3 x 4) 6 7 8 = (6 x 7) 9 = (5 + 8)

G SUBSTATION AUTOMATION SYSTEM (SAS)


1 Protection and Control Cubicle for 150 kV line Bay : 4.00 sets 1,143,245,894 4,572,983,578 4.00 sets 7,464,525 29,858,099 4,602,841,677
- IED Main Line Protection (distance, autoreclose, synchrocheck, etc)
- IED Back Up Protection( OC,DEF,fault locator,metering, etc)
- IED Control ( Bay Control Unit)
- KWH Meter Digital cl 0.2
- Ethernet Swicth for Inter- bay System (ring type)
- Mimic diagram
- misca 1 set of discrepancy switch and indicator
- wiring including connection to outdoor MK, terminal block and switches, links, fuses, test
facilities, etc, to complete the scope of work
All equipment shall comply to IEC 61850
2 Protection and Control Cubicle for 150/20kV Transformer Bay : 1.00 set 1,296,431,170 1,296,431,170 1.00 set 7,464,525 7,464,525 1,303,895,695
- IED Main transformer Protection (differential, REF HV/LV side, DFR etc)
- IED Back Up Protection for primer side (OC, DEF, GFR, fault locator, metering, etc)

- IED Back Up Protection for sekunder side (OC, DEF, GFR, TOR, SBEFR fault locator,
metering, etc)
- IED Control ( Bay Control Unit)
- IED AVR
- Mimic diagram
- 1 set of discrepancy switch and indicator
- wiring including connection to outdoor MK, terminal block and switches, links, fuses, test
facilities, etc. to complete the scope of work.
All equipment shall comply to IEC 61850
3 Protection and Control Cubicle for 150 kV Coupler Bay including low impedance busbar 1.00 set 667,889,006 667,889,006 1.00 set 7,464,525 7,464,525 675,353,530
protection minimum for 9 bay feeder and synchro coloumn
- IED Main Busbar Protection (Buspro, CBF, check dan short zone etc)
- IED Back Up Protection( OC,GFR, UFR, syncrocheck relay ,fault locator,metering, etc)
- IED Control ( Bay Control Unit)
- Ethernet Swicth for Inter- bay System (ring type)
- misca 1 set of discrepancy switch and indicator
-Local Mimic and Control panel for Coupler bay
- synchro column
- wiring including connection to outdoor MK, terminal block and switches, links, fuses, test
facilities, etc, to complete the scope of wor
All equipment shall comply to IEC 61850

Nama Penyedia Jasa :


Page 7 of 11
Stempel dan Tanda Tangan :
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN GARDU INDUK 150 KV JAKABARING
I. PEKERJAAN ELEKTROMEKANIK
(dalam Rupiah)
PENGADAAN MATERIAL PEMASANGAN MATERIAL
No. URAIAN JUMLAH KESELURUHAN
SATUAN HARGA SATUAN JUMLAH HARGA SATUAN HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 = (3 x 4) 6 7 8 = (6 x 7) 9 = (5 + 8)

4 Central Control Equipment/ HMI Client & Server (Operator Workstation) with 1.00 set 1,788,236,527 1,788,236,527 1.00 set 33,869,638 33,869,638 1,822,106,165
redundancy system :
- CPU/ Keyboard & Mouse /VDU, 2 set
- Logger printer, 1 set
- Color laser Printer, 1 set
- GPS Time Reference Clock, 1 set
- Gateway, 1 pcs
- Modem, 1 set
- Server 2 set
- Ethernet Swicth for Inter- bay ( Ring System )
- Ethernet Swicth for connection to WAN inter-bay system
- optical cable for inter bay connection
- rack for server, gateway and ethernet swicth
- furniture
- Engineering tool and test equipment (laptop)
- Miscellaneous material equipment including rack, vabinet cable, cable clamp, compresion
terminal, connection to individual item of equipment,test terminal, auxiliary relay, interior
LAN, heater, install FO to Joint Box, etc to complete the scope of work

5 Substation automation software 1.00 set 416,825,196 416,825,196 1.00 set 7,464,525 7,464,525 424,289,720
- Operating Software
- Basic SAS software
- comunication protocol to control center, consist of
IEC 60870-5-101
IEC 60870-5-104
-HMI software
- Configuration and setting software for IED
- Training ( computer system hardware & software)
- Design architecture for 7 bays (4 LB, 2 TB,1 BC)
6 AC supply Equipment 1.00 set 303,951,836 303,951,836 1.00 set 7,464,525 7,464,525 311,416,361
Inverter and Mounting Panel for AC Supply
7 CCTV System Complete as specified in technical specification 1.00 set 223,355,321 223,355,321 1.00 set 7,464,525 7,464,525 230,819,846

SUB JUMLAH (G) 9,269,672,633 101,050,362 9,370,722,994


JUMLAH 32,549,450,860 1,126,135,543 33,675,586,403
PPN 10 % 3,367,558,640
JUMLAH KESELURUHAN 37,043,145,043

Nama Penyedia Jasa :


Page 8 of 11
Stempel dan Tanda Tangan :
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN GARDU INDUK 150 JAKABARING
II. PEKERJAAN SIPIL

No. Item Uraian Pekerjaan unit Volume Harga Satuan Jumlah Harga
1 2 3 4 5 6=4x5

1. PEKERJAAN PEMATANGAN TANAH & TEMBOK PENAHAN


1. 1 Pengukuran dan Pemasangan Bouwplank m1 600.00 73,843 44,305,800
1. 2 Pematangan tanah (termasuk penggalian dan pengupasan lap. atas tanah ) m3 2,000.00 35,200 70,400,000
1. 3 Pekerjaan Timbunan Material pilihan (Tanah Puru) m3 14,621.00 86,680 1,267,348,280
1. 4 Pasangan batu belah 1 : 4 m3 270.00 822,250 222,007,500
1. 5 Plesteran 1 PC : 3 PP t = 20 mm m2 810.00 67,540 54,707,400
1. 6 Pipa dan ijuk drain ls 1.00 1,650,000 1,650,000
SUB-TOTAL-1 1,660,418,980

2. PEKERJAAN JALAN
2. 1 Pengukuran dan Pemasangan Bouwplank m1 294.00 73,843 21,709,842
2. 2 Plat beton bertulang K.175 (Besi 20 kg) m3 375.00 2,365,000 886,875,000
2. 3 Hamparan Sirtu m3 334.00 440,000 146,960,000
2. 4 Box Culvert Rangkap 2 K.175 (Besi 75 kg) m3 15.00 3,740,000 56,100,000
2. 5 Kanstin uk. 60 x 28 x 15 cm m1 381.00 94,600 36,042,600
SUB-TOTAL-2 1,147,687,442

3. PEKERJAAN GEDUNG KONTROL


3. 1 Pekerjaan pendahuluan :
3. 1.1 Pengukuran dan Pemasangan Bouwplank m1 75.00 73,843 5,538,225
3. 1.2 Penyondiran tanah titik 6.00 4,306,500 25,839,000

3. 2 Pekerjaan tanah :
3. 2.1 Galian tanah pondasi m3 96.00 71,500 6,864,000
3. 2.2 Tiang pancang ∆ (Ukr. 32 cm /"pile terpancang") m1 1,116.00 220,000 245,520,000
3. 2.3 Timbunan kembali m3 80.00 17,600 1,408,000
3. 2.4 Hamparan Pasir m3 12.00 165,000 1,980,000

3. 3 Pekerjaan beton dibawah (elevasi 0,00 sd -2,10m) :


3. 3.1 Beton lantai kerja (untuk pondasi setempat) K.100 m3 3.00 1,210,000 3,630,000
3. 3.2 Beton lantai kerja (untuk pondasi menerus) pas. batu kali m3 9.00 1,210,000 10,890,000
3. 3.3 Beton K.225 (foot plate, sloof, dan kolom) m3 24.00 1,320,000 31,680,000
3. 3.4 Pembesian ulir (foot plate, sloof, dan kolom) kg 0.00 17,600 -
3. 3.5 Pembesian polos (foot plate, sloof, dan kolom) kg 3,075.00 17,160 52,767,000
3. 3.6 Pas. batu belah 1:3 (untuk pondasi menerus) m3 34.00 822,250 27,956,500
3. 3.7 Bekisting (foot plate, sloof, dan kolom) tanpa perancah m3 348.00 184,580 64,233,840

3. 4 Pekerjaan beton diatas (elevasi 0,00 sd 4,70m) :


3. 4.1 Beton K.225 expose (kolom, balok, luefel & listplank) m3 38.00 1,320,000 50,160,000
3. 4.2 Pembesian ulir (kolom, balok, luefel & listplank) kg 4,750.00 17,600 83,600,000
3. 4.3 Pembesian polos (kolom, balok, luefel & listplank) kg 1,187.00 17,160 20,368,920
3. 4.4 Bekisting (kolom, balok, luefel & listplank) dengan perancah m2 515.00 184,580 95,058,700
3. 4.5 Beton K.225 (ring balok) m3 11.00 1,320,000 14,520,000
3. 4.6 Pembesian polos(ring balok) kg 825.00 17,160 14,157,000
3. 4.7 Beton bertulang plat lantai K.175 (besi 10 kg) m3 36.00 1,210,000 43,560,000

3. 5 Pekerjaan atap dan Plafond :


3. 5.1 Kuda-kuda rangka baja IWF lengkap ( mur baut dan pengelasan) kg 4,621.00 33,000 152,493,000
3. 5.2 Penutup atap dari bahan campuran fiber, bitumen dan resin m2 304.00 148,500 45,144,000
3. 5.3 Bubungan atap dari bahan fiber, bitumen dan resin m1 46.00 40,700 1,872,200
3. 5.4 Gording purlin C 200 x 75 x 20 x 3,2 dan
Besi siku 130 x130 x 12 kg 26,441.00 34,100 901,638,100
3. 5.5 Plat sambungan kg 401.00 23,100 9,263,100
3. 5.6 Wind Bracing dia. 16 mm kg 237.00 28,600 6,778,200
3. 5.7 Sagrod dia. 12 mm kg 202.00 25,300 5,110,600
3. 5.8 Angkur baut dia. 16 panjang 700 mm bh 104.00 23,100 2,402,400
3. 5.9 Plafond tripleks t=6 mm m2 234.00 59,400 13,899,600
3. 5.10 Rangka kayu untuk Plafond m2 327.00 105,600 34,531,200
3. 5.11 Plafond akustik uk. 60 x 120 cm m2 118.00 33,000 3,894,000

3. 6 Pekerjaan Kosen & Pintu :


3. 6.1 Kosen dan Pintu Alumunium type P1 lengkap plus kaca unit 1.00 2,508,000 2,508,000
3. 6.2 Kosen dan Pintu Alumunium type P2 lengkap plus kaca unit 3.00 1,760,000 5,280,000
3. 6.3 Kosen dan Pintu Alumunium type P3 lengkap plus kaca unit 3.00 1,540,000 4,620,000
3. 6.4 Kosen Pintu Fibre type P4 (komplit) unit 2.00 935,000 1,870,000
3. 6.5 Kosen dan Jendela Alumunium type J1 plus jendela unit 3.00 1,980,000 5,940,000
3. 6.6 Kosen dan Jendela Alumunium type J2 plus jendela unit 1.00 1,089,000 1,089,000
3. 6.7 Kosen Ventilasi type V1 unit 3.00 1,089,000 3,267,000
3. 6.8 Kosen Ventilasi type V2 unit 7.00 1,089,000 7,623,000
3. 6.9 Kosen Ventilasi type V3 unit 8.00 1,089,000 8,712,000
3. 6.10 Kosen Ventilasi type V4 unit 2.00 1,089,000 2,178,000
3. 6.11 Kosen dan pintu untuk ruang trafo unit 1.00 4,950,000 4,950,000
3. 6.12 Pintu Rolling door Besi Type PG m2 13.00 847,000 11,011,000
3. 6.13 Pasangan profil / dudukan kabel tray (besi siku) kg 147.00 33,000 4,851,000

Nama Penyedia Jasa :


Page 9 of 11
Stempel dan Tanda Tangan :
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN GARDU INDUK 150 JAKABARING
Pen II. PEKERJAAN SIPIL
gec
ata
No. Item n Uraian Pekerjaan unit Volume Harga Satuan Jumlah Harga
din
1 din 2 3 4 5 6=4x5
g
lua
3. 7 rPekerjaan lantai & dinding :
3. 7.1 dan
Lantai keramik uk. 40 x 40 ( bagian dalam gedung) m2 204.00 207,900 42,411,600
3. 7.2 dal
Lantai keramik uk. 40 x 40 anti licin ( bagian selasar gedung) m2 95.00 215,325 20,455,875
am
3. 7.3 Lantai Hardener m2 100.00 84,700 8,470,000
(3
3. 7.4 Plint
Pen ubin keramik uk. 10 x 40 cm
kali m1 239.00 59,400 14,196,600
3. 7.5 )Keramik
gec untuk dinding (ruang batterai t = 1,5 m) m2 29.00 210,980 6,118,420
3. 7.6 set
Keramik
ata untuk uk. 20 x 20 untuk KM/WC, dan Dapur m2 11.00 210,980 2,320,780
3. 7.7 nara
Pasangan. batu bata 1 : 4 m2 650.00 132,000 85,800,000
3. 7.8 Em
bes
Plesteran dinding pas 1 : 4 m2 1,300.00 48,400 62,920,000
3. 7.9 iulti
Water proofing dak talang beton m2 114.00 121,000 13,794,000
on
kon
ICI
stru
3. 8 Pekerjaan
Dul
ksi pengecatan :
3. 8.1 ux.
ata m2 1,300.00 22,000 28,600,000
3. 8.2 p m2 307.00 18,150 5,572,050

3. 9 Pekerjaan Drainase :
3. 9.1 Saluran keliling bangunan Pipa beton dia.30 cm m1 85.00 352,000 29,920,000
3. 9.2 Bak kontrol pas. Bata 45 x45 bh 12.00 407,000 4,884,000

3. 10 Pekerjaan Sanitair & Instalasi Air :


3. 10.1 Kloset jongkok setara Toto bh 1.00 660,000 660,000
3. 10.2 Wastafel setara Toto bh 1.00 330,000 330,000
3. 10.3 Septiktank & peresapan bh 1.00 6,050,000 6,050,000
3. 10.4 Bak mandi pasangan bata bh 1.00 1,595,000 1,595,000
3. 10.5 Pembuatan sumur + pompa air setara Sanyo type PH100D ls 1.00 27,500,000 27,500,000
3. 10.6 Instalasi air bersih ls 1.00 4,235,000 4,235,000
3. 10.7 Meja dapur porselen, wash bak dan almari gantung ls 1.00 8,140,000 8,140,000
3. 10.9 Tiang bendera tinggi 7m ls 1.00 2,997,500 2,997,500

3. 11 Pekerjaan instalasi listrik dan pentanahan :


3. 11.1 Instalasi listrik (pengkabelan + pemasangan titi-titik instalasi) ttk 135.00 275,000 37,125,000
3. 11.2 Lampu SL 18 watt Down Light RD 150 bh 6.00 126,500 759,000
3. 11.3 Lampu SL 23 watt Down Light RD 175 bh 31.00 126,500 3,921,500
3. 11.4 Lampu SL 23 watt fitting biasa set 8.00 126,500 1,012,000
3. 11.5 Saklar tunggal bh 5.00 18,150 90,750
3. 11.6 Saklar ganda bh 6.00 23,100 138,600
3. 11.7 Stop Kontak 16 A 220 Volt bh 11.00 192,500 2,117,500
3. 11.8 Stop AC + Fan bh 12.00 423,500 5,082,000
3. 11.9 Exhaust Fan 60 watt/220 volt (12") bh 6.00 770,000 4,620,000
3. 11.10 AC split 2 PK unit 3.00 4,950,000 14,850,000
3. 11.11 AC split 1 PK unit 1.00 4,620,000 4,620,000
3. 11.12 Panel Induk 30 grup 64A/500V lemgkap dengan lampu unit 1.00 3,850,000 3,850,000
3. 11.13 Danger Lamp unit 10.00 1,848,000 18,480,000
3. 11.14 Instalasi penangkal dan penyalur petir ls 3.00 19,250,000 57,750,000
3. 11.15 Instalasi pentanahan/grounding ls 1.00 16,500,000 16,500,000

3. 12 Pekerjaan Cable Duct dalam gedung:


3. 12.1 Cable Duct (130W / 100H) include galvanis rack cable m1 20.00 2,420,000 48,400,000
3. 12.2 Cable Duct (100W / 100H) include galvanis rack cable m1 12.00 2,200,000 26,400,000
3. 12.3 Cable Duct (80W / 100H) include galvanis rack cable m1 7.00 1,925,000 13,475,000
3. 12.4 Cable Duct (50W / 50H) m1 11.00 1,210,000 13,310,000
3. 12.5 Cable Duct (30W / 30H) m1 18.00 836,000 15,048,000
SUB-TOTAL-3 2,705,176,760

4. PEKERJAAN PONDASI TRAFO, SERANDANG & PERALATAN


4. 1 Pengukuran dan Pemasangan Bouwplank m1 308.00 73,843 22,743,644
4. 2 Tiang pancang ∆ (Ukr. 32 cm /"pile terpancang") m1 1,789.00 220,000 393,580,000
4. 3 Galian tanah pondasi m3 1,245.00 71,500 89,017,500
4. 4 Hamparan Pasir m3 64.00 165,000 10,560,000
4. 5 Timbunan kembali m3 830.00 17,600 14,608,000
4. 6 Pembuangan & perataan tanah ex-galian m3 415.00 33,000 13,695,000
4. 7 Lantai Kerja Beton K.100 m3 33.00 1,210,000 39,930,000
4. 8 Beton K.225 m3 355.00 1,320,000 468,600,000
4. 9 Besi beton ulir kg 5,289.00 17,600 93,086,400
4. 10 Besi beton polos kg 21,155.00 17,160 363,019,800
4. 11 Bekisting pondasi m2 1,204.00 184,580 222,234,320
4. 12 Beton Grouting 1:1:1 bh 63.00 115,500 7,276,500
4. 13 Sparing 60/60 -125 bh 8.00 121,000 968,000
4. 14 Sparing 50/50 -125 bh 72.00 93,500 6,732,000
4. 15 Sparing 25/25 -70 bh 540.00 63,800 34,452,000
4. 16 Pekerjaan pengadaan dan pemasangan grounding bay 6.00 165,000,000 990,000,000
SUB-TOTAL-4 2,770,503,164

Nama Penyedia Jasa :


Page 10 of 11
Stempel dan Tanda Tangan :
DAFTAR KUANTITAS DAN HARGA
PEMBANGUNAN GARDU INDUK 150 JAKABARING
II. PEKERJAAN SIPIL

No. Item Uraian Pekerjaan unit Volume Harga Satuan Jumlah Harga
1 2 3 4 5 6=4x5

5. PEKERJAAN SALURAN KABEL SWITCHYARD AREA


5. 1 Cable Duct (100W / 100H) include galvanis rack cable m1 30.00 2,200,000 66,000,000
5. 2 Cable Duct (80W / 100H) include galvanis rack cable m1 106.00 2,090,000 221,540,000
5. 3 Cable Duct (50W / 50H) m1 298.00 1,540,000 458,920,000
5. 4 Cable Duct (30W / 30H) m1 428.00 1,430,000 612,040,000
5. 5 Box Culvert 100 X 100 m1 12.00 4,070,000 48,840,000
SUB-TOTAL-5 1,407,340,000

6. PEKERJAAN DRAINAGE
6. 1 Drainase Type "55" m1 491.00 1,210,000 594,110,000
6. 2 Saluran keliling bangunan Pipa beton dia.30 cm m1 45.00 242,000 10,890,000
SUB-TOTAL-6 605,000,000

7. PEKERJAAN PAGAR SWITCHYARD & PAGAR SITE


7. 1 PAGAR SWITCHYARD
7. 1.1 Pag m1 179.00 605,000 108,295,000
7. 1.2 ar
Pintu pagar L 4 m bh 1.00 6,380,000 6,380,000
7. 2 lio
PAGAR SITE
7. 2.1 n m1 485.00 737,000 357,445,000
Pag
me
7. 2.2 ar
Pintu pagar L 6 m bh 1.00 5,610,000 5,610,000
sh /
7. 2.3 lio
Pagar pasangan batu 1 : 4, h = 2m (bagian belakang dan samping site) m1 400.00 822,250 328,900,000
BR
n SUB-TOTAL-7 806,630,000
C
me
h=
sh /
8. 120
PEKERJAAN HAMPARAN KORAL
BR
8. 1 cm
Hamparan Pasir t=10cm m3 390.00 165,000 64,350,000
C
8. 2 h=
Hamparan Koral t=15cm m3 570.00 440,000 250,800,000
175 SUB-TOTAL-8 315,150,000
cm
9. PEKERJAAN LAIN-LAIN
9. 1 Lampu penerangan site titik 20.00 4,620,000 92,400,000
9. 2 Gardu jaga 16m2 unit 1.00 58,080,000 58,080,000
9. 3 Pengurusan IMB ls 1.00 108,460,000 108,460,000

9. 4 Pengadaan Alat Pemadam Api Ringan (APAR)


9. 4.1 APAR 3,5 Kg Dry Chemical Powder bh 2.00 770,000 1,540,000
9. 4.2 APAR 6,8 Kg CO2 bh 2.00 4,950,000 9,900,000
9. 4.3 APAR 25 Kg Dry Chemical Powder (Pakai Roda) bh 2.00 22,000,000 44,000,000

9. 5 Pengadaan dan Pemasangan Smoke Detector bh 25.00 605,000 15,125,000

SUB-TOTAL-9 329,505,000

Nama Penyedia Jasa :


Page 11 of 11
Stempel dan Tanda Tangan :

Anda mungkin juga menyukai