RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMASANGAN PIPA DAN ACCESSORIES PIPA


LOKASI : IKK PANGKALAN BANTENG KABUPATEN KOTAWARINGIN BARAT
TAHUN : 2018

HARGA SATUAN JUMLAH HARGA


NO URAIAN KEGIATAN ANALISA VOLUME
(Rp.) (Rp.)

I PEMASANGAN PIPA

1 Galian Pipa HDPE dia. 160 mm A 2.3.1.1 2,913.75 m3 99,144.38 288,881,937.23


2 Pemasangan Pipa HDPE PN.10 dia. 160 mm A. 8.4.1.20.a 5,550.00 m' 407,275.95 2,260,381,522.50
3 Urugan Pipa HDPE dia. 160 mm A 2.3.1.9 2,802.22 m3 67,519.38 189,204,157.02
4 Pengetesan Pipa HDPE PN.10 Ø 160 mm A. 8.4.5.5.a 5,550.00 m' 2,168.74 12,036,507.00
5 Galian Pipa HDPE dia. 110 mm A 2.3.1.1 1,282.56 m3 99,144.38 127,158,616.01
6 Pemasangan Pipa HDPE PN.10 dia. 110 mm A.8.4.1.21.a 4,008.00 m' 211,750.94 848,697,767.52
7 Urugan Pipa HDPE dia. 110 mm A 2.3.1.9 1,244.49 m3 67,519.38 84,027,193.22
8 Pengetesan Pipa HDPE PN.10 Ø 110 mm A. 8.4.5.3.a 4,008.00 m' 2,168.72 8,692,229.76

JUMLAH I 3,819,079,930.26

II PENGADAAN ACCESSORIES PIPA


2 Gilbout Joint dia. 160 mm 2.00 bh 589,500.00 1,179,000.00
3 Gilbout Joint dia. 110 mm 2.00 bh 442,000.00 884,000.00
5 Tee 6"x4" mm 3.00 bh 1,269,000.00 3,807,000.00
6 Tee 4"x4" mm 2.00 bh 680,100.00 1,360,200.00
8 Pemasangan Gate Valve dia. 160 mm A.8.4.3.1.a 2.00 bh 3,355,821.33 6,711,642.66
9 Pemasangan Gate Valve dia. 110 mm A.8.4.3.1.d 3.00 bh 2,052,756.70 6,158,270.10
11 Blind Flange dia. 110 mm 3.00 bh 744,500.00 2,233,500.00
13 Bend Lass GI 45o dia. 160 mm 10.00 bh 818,500.00 8,185,000.00
15 Flange Lass dia. 160 mm 12.00 bh 778,000.00 9,336,000.00
17 Stub end Flange HDPE dia.160 mm 24.00 bh 1,374,500.00 32,988,000.00
18 Stub end Flange HDPE dia.110 mm 25.00 bh 780,000.00 19,500,000.00
19 Clamp Sadel Cl 6" X 1" 2.00 bh 294,000.00 588,000.00
21 Air Valve dia. 160x25 mm lengkap A.8.4.3.1.b 2.00 bh 892,176.33 1,784,352.66
23 Karet Packing dia. 160mm 20.00 bh 24,000.00 480,000.00
24 Karet Packing dia. 110mm 18.00 bh 22,000.00 396,000.00
25 Mur + baut 272.00 bh 13,500.00 3,672,000.00
JUMLAH II 99,262,965.42

III PEKERJAAN LAINNYA


4 Pemasangan Pipa GI Ø 6" A.8.4.1.36 24.00 m' 553,873.93 13,292,974.32
5 Pengelasan Pipa GI Ø 6' LA.12.d.b 75.00 ttk 333,563.28 25,017,246.00
6 Pengecatan Pipa GI Ø 6" A.4.7.1.19 12.06 m2 43,506.23 524,685.13
7 Pemancangan Cerucuk F.02. 360.00 m' 43,829.95 15,778,782.00
8 Pembuatan Jembatan WF
- Besi IWF. 300 40.00 m' 516,000.00 20,640,000.00
-Besi Kanal Unp 10 40.00 m' 94,000.00 3,760,000.00
-Plat Pengikat Pipa 80.00 bh 10,000.00 800,000.00
- Abutmen Block beton Bertulang A 4.1.1.33.a 11.90 m3 7,266,440.03 86,470,636.36
- Pemas. Besi IWF.300 dan pengelasan Ls 1.00 Unit 13,735,000.00 13,735,000.00
9 Box Gate Valve A 4.1.1.33.a 5.51 m3 7,266,440.03 40,038,084.57
10 Cor rabat jalur Pipa A 4.1.1.1 10.50 m3 2,156,196.42 22,640,062.41
11 Trust Block+Bekisting ukuran 40×40×80 cm TB 40.00 bh 591,183.67 23,647,346.80
HARGA SATUAN JUMLAH HARGA
NO URAIAN KEGIATAN ANALISA VOLUME
(Rp.) (Rp.)
12 Patok Beton Bertulang A 4.1.1.33.a 0.11 m3 7,266,440.03 817,474.50
13 Pemasangan SR Ls 100.00 Unit 845,000.00 84,500,000.00

JUMLAH III 351,662,292.09

REKAPITULASI

I PEMASANGAN PIPA 3,819,079,930.26


II PENGADAAN ACCESSORIES PIPA 99,262,965.42
III PEKERJAAN LAINNYA 351,662,292.09
JUMLAH 4,270,004,187.77
DIBULATKAN 4,270,000,000.00
SKEMATIK SISTEM PELAYANAN AIR MINUM
PDAM “TIRTA ARUT” KABUPATEN KOTAWARINGIN BARAT
UNIT IKK. PANGKALAN BANTENG

Intake : SistimProduksi :
Pompa 1 buah Terpasang = 10 Lt/dtk
Q = 10 Lt/dtk Produksi = 15 Lt/dtk
Sungai Hijau
Debit Q = 5.000 Lt/dtk Distribusi
Pompa 3 buah
Q = 5 Lt/dtk
H = 40 m
Res = 200 m3

PipaTransmisi :
Jenis Pipa Pvc
L =500 m Dia =160 mm

Sambungan Rumah 1.796 Unit


Pelayanan 24 jam/hari

Sumber Data :
PDAM “Tirta Arut” Kabupaten Kotawaringin Barat
Tahun 2016
WILAYAH PETA JARINGAN
PDAM “TIRTA ARUT” UNIT IKK. PANGKALAN BANTENG

Sumber Data :
PDAM “Tirta Arut” Kabupaten Kotawaringin Barat
Tahun 2016
SKEMATIK SISTEM PELAYANAN AIR MINUM
PDAM “TIRTA ARUT” KABUPATEN KOTAWARINGIN BARAT
UNIT IKK. PANGKALAN LADA

Intake : SistimProduksi :
Pompa 1 buah Terpasang = 25 Lt/dtk
Q = 25 Lt/dtk Produksi = 10 Lt/dtk
Sungai Hijau
Debit Q = 5.000 Lt/dtk Distribusi
Pompa 3 buah
Q = 10 Lt/dtk
H = 40 m
Res = 300 m3

PipaTransmisi :
Jenis Pipa Pvc
L =500 m Dia =200 mm

Sambungan Rumah 1.035 Unit


Pelayanan 18 jam/hari

Sumber Data :
PDAM “Tirta Arut” Kabupaten Kotawaringin Barat
Tahun 2016
WILAYAH PETA JARINGAN
PDAM “TIRTA ARUT” UNIT IKK. PANGKALAN LADA

Sumber Data :
PDAM “Tirta Arut” Kabupaten Kotawaringin Barat
Tahun 2016

Anda mungkin juga menyukai