KELAS : 4MRK6
NIM : 1741320157
TUGAS 2- ADMINISTRASI PROYEK
341.985.
I BIAYA PERSIAPAN
458
1 Kantor Proyek m2 195,2 764.730 149.275.338
2 Bengkel Alat m2 78,75 546.017 42.998.868
3 Gudang Material m2 109,5 535.311 58.616.571
4 Pagar Sementara m' 165,25 430.225 71.094.681