DAFTAR ANALISA PEKERJAAN

PEMBANGUNAN GARDU LISTRIK POLITEKNIK NEGERI MALANG

No JENIS PEKERJAAN HARGA SATUAN


PEKERJAAN PERSIAPAN
1 1 m² Pembersihan lokasi + perataan (SNI:8.11) Pembulatan Rp 17.200,00
2 1 m³ Bongkar beton (SNI : 10.11) Lt. 1 = Koef Upah Kerja X 1,000 Rp 749.090,80
3 1 m³ Bongkar dinding bata (SNI : 10.11 ) Lt. 1 = Koef Upah Kerja X 1,000 Rp 709.100,80
4 1 m² Bongkar lantai Lt. 1 = Koef Upah Kerja X 1,000 Rp 22.473,00
5 1 m² Bongkar plafon eternit (Ans.BOW L.8) 1 m² Rp 7.338,00
6 1 m² Bongkar konstruksi atap kayu (Ans.BOW L.12) 1 m² Rp 125.142,00
7 1 m² Bongkar rangka atap usuk & reng (Anl.BOW L.9) 1 m² Rp 14.578,00
8 1 m² Bongkar atap genteng (Anl.BOW L.7) 1 m² Rp 3.447,00

PEKERJAAN TANAH
9 1 m' Galian tanah pondasi strous Pembulatan Rp 146.500,00
10 1 m³ Galian tanah BIASA sedalam 1 m (RSNI : 3.7) Pembulatan Rp 82.600,00
11 1 m³ Galian tanah BIASA sedalam 2 m (RSNI : 3.7) Pembulatan Rp 101.100,00
12 1 m' Galian bor strouss Pembulatan Rp 146.500,00

13 1 m³ Urugan PASIR (RSNI : 4.7) Lt. 1 = Koef Upah Kerja X 1,000 Rp 58.723,00
Lt. 2 = Koef Upah Kerja X 1,090 Rp 61.696,87
Lt. 3 = Koef Upah Kerja X 1,120 Rp 62.688,16

14 1 m³ Urugan SIRTU padat untuk leveling (RSNI : 5.7) Pembulatan Rp 263.800,00


15 1 m³ Urugan TANAH kembali bekas galian (SNI : 6.9) Pembulatan Rp 22.800,00
16 1 m³ Pemadatan per 20 cm (RSNI : 4.7) Pembulatan Rp 59.500,00
17 1 m³ Pengangkutan tanah keluar proyek Pembulatan Rp 48.900,00

PEKERJAAN PASANGAN, PLESTERAN & FINISHING


18 1 m³ Pasang batu kosong / Aanstamping (SNI:5.8) Pembulatan Rp 451.400,00
19 1 m³ Pasangan batu belah, 1pc:4ps (RSNI : 3.8) Pembulatan Rp 915.700,00
20 1 m² Pasangan bata merah tbl 1 bata, 1pc:6ps (RSNI : 4.11) Pembulatan Rp 264.000,00

21 1 m² Pasangan bata merah tbl 1/2 bata, 1pc:4ps (RSNI:5.11) Lt. 1 = Koef Upah Kerja X 1,000 Rp 130.458,70
Lt. 2 = Koef Upah Kerja X 1,090 Rp 134.695,50
Lt. 3 = Koef Upah Kerja X 1,120 Rp 136.107,76

22 1 m² Pasangan bata merah tbl 1/2 bata, 1pc:6ps (RSNI:6.11) Lt. 1 = Koef Upah Kerja X 1,000 Rp 127.581,10
Lt. 2 = Koef Upah Kerja X 1,090 Rp 131.817,90
Lt. 3 = Koef Upah Kerja X 1,120 Rp 133.230,16

23 1 m² Plesteran dinding 1pc:4ps, tbl 15 mm (RSNI:4.11) Lt. 1 = Koef Upah Kerja X 1,000 Rp 57.555,60
Lt. 2 = Koef Upah Kerja X 1,090 Rp 61.382,58
Lt. 3 = Koef Upah Kerja X 1,120 Rp 62.658,24

24 1 m² Plesteran dinding 1pc:6ps, tbl 15 mm (RSNI:7.11) Lt. 1 = Koef Upah Kerja X 1,000 Rp 55.789,20
Lt. 2 = Koef Upah Kerja X 1,090 Rp 59.616,18
Lt. 3 = Koef Upah Kerja X 1,120 Rp 60.891,84

25 1 m² Finishing dinding / Acian (RSNI : 9.11) Lt. 1 = Koef Upah Kerja X 1,000 Rp 34.837,40
Lt. 2 = Koef Upah Kerja X 1,090 Rp 37.563,27
Lt. 3 = Koef Upah Kerja X 1,120 Rp 38.471,89

26 1 m² Finishing beton Expose Lt. 1 = Koef Upah Kerja X 1,000 Rp 36.524,00


Lt. 2 = Koef Upah Kerja X 1,090 Rp 38.888,98
Lt. 3 = Koef Upah Kerja X 1,120 Rp 39.677,31

27 1 m' Benangan sudut Lt. 1 = Koef Upah Kerja X 1,000 Rp 26.254,50


Lt. 2 = Koef Upah Kerja X 1,090 Rp 27.695,23
Lt. 3 = Koef Upah Kerja X 1,120 Rp 28.175,47

28 1 m² Water proofing 2 lapis Lt. 1 = Koef Upah Kerja X 1,000 Rp 135.747,43


Lt. 2 = Koef Upah Kerja X 1,090 Rp 138.368,50
No JENIS PEKERJAAN HARGA SATUAN
Lt. 3 = Koef Upah Kerja X 1,120 Rp 139.242,19

PEKERJAAN BETON
Spesi Beton :
29 1 m³ Lantai kerja beton mutu fc'=7,4 Mpa (K100) slump (3 - 6) cm, w/c = 0,87 (RSNI:4.16) Pembulatan Rp 682.600,00
30 1 m³ Membuat beton mutu f'c = 7,4 Mpa (K.100), slump (12±2) cm, w/c = 0,87 (RSNI:3.16) Pembulatan Rp 761.700,00

31 1 m³ Membuat beton mutu f'c = 14,5 Mpa (K.175), slump (12±2) cm, w/c =Lt.0,66
1 = (RSNI:4.16)
Koef Upah Kerja X 1,000 Rp 875.776,23
Lt. 2 = Koef Upah Kerja X 1,090 Rp 895.782,62
Lt. 3 = Koef Upah Kerja X 1,120 Rp 902.451,42

32 1 m³ Membuat beton mutu f'c = 21,7 Mpa (K.250), slump (12±2) cm, Lt. 1 = Koef Upah Kerja X 1,000 Rp 957.568,08
w/c = 0,56 (RSNI:5.16) Lt. 2 = Koef Upah Kerja X 1,090 Rp 977.574,47
Lt. 3 = Koef Upah Kerja X 1,120 Rp 984.243,27

33 1 m³ Membuat beton mutu f'c = 24,0 Mpa (K.275), slump (12±2) cm, Lt. 1 = Koef Upah Kerja X 1,000 Rp 985.906,33
w/c = 0,53 (RSNI:5.16) Lt. 2 = Koef Upah Kerja X 1,090 Rp 1.005.912,71
Lt. 3 = Koef Upah Kerja X 1,120 Rp 1.012.581,51

Pembesian :
34 1 kg Pembesian polos (RSNI:7.16) Lt. 1 = Koef Upah Kerja X 1,000 Rp 16.809,84
Lt. 2 = Koef Upah Kerja X 1,090 Rp 16.965,44
Lt. 3 = Koef Upah Kerja X 1,120 Rp 17.017,30

35 1 kg Pembesian ulir (RSNI:7.16) Lt. 1 = Koef Upah Kerja X 1,000 Rp 19.959,84


Lt. 2 = Koef Upah Kerja X 1,090 Rp 20.115,44
Lt. 3 = Koef Upah Kerja X 1,120 Rp 20.167,30

36 1 kg Pembesian jaring kawat baja / Wire mesh (RSNI:7.16) Lt. 1 = Koef Upah Kerja X 1,000 Rp 25.829,83
Lt. 2 = Koef Upah Kerja X 1,090 Rp 25.912,34
Lt. 3 = Koef Upah Kerja X 1,120 Rp 25.939,85

37 1 kg Pembesian baja profil + cat Zincromate Lt. 1 = Koef Upah Kerja X 1,000 Rp 49.099,46

Membuat Begisting :
38 1 m² Pasang begisting PONDASI, 1x pakai (RSNI:7.16) Jumlah Rp 471.541,40
39 1 m² Pasang begisting SLOOF, 2x pakai (RSNI:8.16) 1,00 Rp 306.797,65

40 1 m² Pasang begisting KOLOM, 2x pakai (RSNI:8.16) Lt. 1 = Koef Upah Kerja X 1,000 Rp 435.986,45
Lt. 2 = Koef Upah Kerja X 1,090 Rp 446.630,63
Lt. 3 = Koef Upah Kerja X 1,120 Rp 450.178,69

41 1 m² Pasang begisting BALOK, 2x pakai (RSNI:8.16) Lt. 1 = Koef Upah Kerja X 1,000 Rp 441.451,25
Lt. 2 = Koef Upah Kerja X 1,090 Rp 452.095,43
Lt. 3 = Koef Upah Kerja X 1,120 Rp 455.643,49

42 1 m² Pasang begisting PLAT LANTAI DASAR, 2x pakai Jumlah Rp 282.361,40

43 1 m² Pasang begisting PLAT LANTAI, 2x pakai (RSNI:9.16) Lt. 1 = Koef Upah Kerja X 1,00 Rp 634.278,95
Lt. 2 = Koef Upah Kerja X 1,09 Rp 644.923,13
Lt. 3 = Koef Upah Kerja X 1,12 Rp 648.471,19

44 1 m² Pasang begisting TANGGA, 2x pakai (RSNI:9.16) Lt. 1 = Koef Upah Kerja X 1,00 Rp 388.358,95
Lt. 2 = Koef Upah Kerja X 1,09 Rp 399.003,13
Lt. 3 = Koef Upah Kerja X 1,12 Rp 402.551,19

45 1 m² Pasang begisting DINDING, 2x pakai (RSNI : 9.16) Lt. 1 = Koef Upah Kerja X 1,00 Rp 447.455,08
Lt. 2 = Koef Upah Kerja X 1,09 Rp 458.099,26
Lt. 3 = Koef Upah Kerja X 1,12 Rp 461.647,32

Pek. Beton Per M³ :


46 1 m³ Beton STROUS Ø 30 cm, mutu K.250 Jumlah Lt.1 Rp 3.180.900,00
47 1 m³ Beton PONDASI FOOTPLAT, mutu K.250 Jumlah Lt.1 Rp 6.929.700,00
48 1 m³ Beton PONDASI GENSET, mutu K.250 Jumlah Lt.1 Rp 3.603.300,00
49 1 m³ Beton SLOOF Praktis 15/20 cm, mutu K.175 Jumlah Lt.1 Rp 5.754.900,00
No JENIS PEKERJAAN HARGA SATUAN

50 1 m³ Beton KOLOM 40/40 cm (K1), mutu K.250 Jumlah Lt.1 Rp 7.887.800,00


Jumlah Lt.2 Rp 8.004.700,00

51 1 m³ Beton KOLOM PRAKTIS 15/15 cm, mutu K.175 Jumlah Lt.1 Rp 7.347.400,00
Jumlah Lt.2 Rp 7.471.300,00

52 1 m³ Beton BALOK INDUK 30/50 cm, mutu K.250 Jumlah Lt.1 Rp 7.247.300,00
Jumlah Lt.2 Rp 7.346.300,00

53 1 m³ Beton BALOK ATAP (1) 30/50 cm, mutu K.250 Jumlah Lt.1 Rp 7.247.300,00
Jumlah Lt.2 Rp 7.346.300,00

54 1 m³ Beton BALOK 25/40 cm, mutu K.250 Jumlah Lt.1 Rp 5.556.000,00


Jumlah Lt.2 Rp 5.646.000,00

55 1 m³ Beton BALOK KONSOL LANTAI 30/30 - 30/50 cm, mutu K.250 Jumlah Lt.1 Rp 7.789.400,00
Jumlah Lt.2 Rp 7.893.200,00

56 1 m³ Beton BALOK KONSOL ATAP 30/30 - 30/50 cm, mutu K.250 Jumlah Lt.1 Rp 7.789.400,00
Jumlah Lt.2 Rp 7.893.200,00

57 1 m³ Beton RING BALK & GEWEL 15/20 cm (BR.2), mutu K.175 Jumlah Lt.1 Rp 6.657.800,00
Jumlah Lt.2 Rp 6.775.100,00

58 1 m³ Beton BALOK LEUFEL 15/30 cm, mutu K.175 Jumlah Lt.1 Rp 7.167.600,00
Jumlah Lt.2 Rp 7.293.200,00

59 1 m³ Beton BALOK LATEI 15/20 cm, mutu K.175 Jumlah Lt.1 Rp 7.761.500,00
Jumlah Lt.2 Rp 7.905.300,00

60 1 m³ Beton PLAT LANTAI DASAR Tbl 10 cm, mutu K.250 (Tul. Wire Mesh_Tunggal) Pembulatan Rp 2.644.100,00

61 1 m³ Beton PLAT LANTAI Tbl 12 cm, mutu K.250 (Tul. Konvensional_Tump-Lap) Jumlah Lt.1 Rp 6.558.400,00
Jumlah Lt.2 Rp 6.654.100,00

62 1 m³ Beton PLAT ATAP Tbl 12 cm, mutu K.250 (Tul. Konvensional_Tump-Lap) Jumlah Lt.1 Rp 6.558.400,00
Jumlah Lt.2 Rp 6.654.100,00

63 1 m³ Beton PLAT CANOPI tbl 10 cm, mutu K.175 (Tul. Tunggal) Jumlah Lt.1 Rp 5.380.800,00
Jumlah Lt.2 Rp 5.467.900,00

PEKERJAAN PENUTUP LANTAI & DINDING


64 1 m² Pasang keramik lantai 40/40 cm Lt. 1 = Koef Upah Kerja X 1,000 Rp 183.418,90
Lt. 2 = Koef Upah Kerja X 1,090 Rp 193.887,16
Lt. 3 = Koef Upah Kerja X 1,120 Rp 197.376,58

PEKERJAAN KUSEN, KACA, PENGGANTUNG & BESI


65 1 m² Pasang jalusi besi hollow Lt. 1 = Koef Upah Kerja X 1,00 Rp 808.218,10

PEKERJAAN PENGECATAN
1 m² Pengecatan dinding / plafond BARU (1 lapis plamir, 1 lapis cat
66 Lt. 1 = Koef Upah Kerja X 1,000 Rp 21.403,83
dasar, 2 lapis), (SNI:9.14)
Lt. 2 = Koef Upah Kerja X 1,090 Rp 22.381,93
Lt. 3 = Koef Upah Kerja X 1,120 Rp 22.707,97

1 m² Pengecatan dinding Eksterior watershield BARU (1 lapis plamir,


67 Lt. 1 = Koef Upah Kerja X 1,000 Rp 35.347,83
1 lapis cat dasar, 2 lapis), (SNI:9.14)
Lt. 2 = Koef Upah Kerja X 1,090 Rp 36.325,93
Lt. 3 = Koef Upah Kerja X 1,120 Rp 36.651,97

1 m² Pengecatan kayu BARU (1 lap plamir, 1 lap cat dasar, 2 lap cat
68 Lt. 1 = Koef Upah Kerja X 1,000 Rp 64.074,75
penutup) (SNI:7.14)
Lt. 2 = Koef Upah Kerja X 1,090 Rp 64.941,16
No JENIS PEKERJAAN HARGA SATUAN
Lt. 3 = Koef Upah Kerja X 1,120 Rp 65.229,96

69 1 m² Pengecatan besi (1 lap meni, 1 lap cat dasar, 2 lap cat penutup) Lt. 1 = Koef Upah Kerja X 1,000 Rp 39.856,75
Lt. 2 = Koef Upah Kerja X 1,090 Rp 40.723,16
Lt. 3 = Koef Upah Kerja X 1,120 Rp 41.011,96

1 m² Pengecatan besi (1 lap meni, 1 lap cat dasar, 2 lap cat


70 Lt. 1 = Koef Upah Kerja X 1,00 Rp 35.276,75
penutup)_Meni lama
Lt. 2 = Koef Upah Kerja X 1,09 Rp 36.143,16
Lt. 3 = Koef Upah Kerja X 1,12 Rp 36.431,96

PEKERJAAN INSTALASI LISTRIK


71 1 Titik Pasang instalasi lampu Lt. 1 = Koef Upah Kerja X 1,00 Rp 822.480,00
Lt. 2 = Koef Upah Kerja X 1,09 Rp 843.412,20
Lt. 3 = Koef Upah Kerja X 1,12 Rp 850.389,60

72 1 Titik Pasang saklar tunggal, setara merk Panasonic Lt. 1 = Koef Upah Kerja X 1,00 Rp 257.913,00
Lt. 2 = Koef Upah Kerja X 1,09 Rp 263.854,17
Lt. 3 = Koef Upah Kerja X 1,12 Rp 265.834,56

73 1 Titik Pasang saklar ganda, setara merk Panasonic Lt. 1 = Koef Upah Kerja X 1,00 Rp 255.213,00
Lt. 2 = Koef Upah Kerja X 1,09 Rp 261.154,17
Lt. 3 = Koef Upah Kerja X 1,12 Rp 263.134,56

PEKERJAAN SANITAIR

74 1 m' Pasang pipa air Galvanis Ø 4" Lt. 1 = Koef Upah Kerja X 1,00 Rp 721.204,44
Lt. 2 = Koef Upah Kerja X 1,09 Rp 725.276,89
Lt. 3 = Koef Upah Kerja X 1,12 Rp 726.634,37