Anda di halaman 1dari 6

URUTAN PEKERJAN FCFS A-B-C-D-E

URUTAN PEKERJAAN WAKTU PEMROSESAN ALIRAN WAKTU


A 4 4
B 7 11
C 8 19
D 12 31
E 7 38
JUMLAH 38 103

a. WAKTU PENYELESAIAN RATA2 20.6


b. UTILITAS 0.368932038834951
C. JUMLAH PEKERJAAN RATA2 2.71052631578947
d. KETERLAMBATAN 11.6
PEKERJAN FCFS A-B-C-D-E

BATAS WAKTU PENGERJAAN KETERLAMBATAN


12 0
10 1
8 11
11 20
12 26
58
URUTAN PEKERJAN SPT A-B-E-C-D

URUTAN PEKERJAAN WAKTU PEMROSESAN ALIRAN WAKTU BATAS WAKTU PENGERJAAN


A 4 4 12
B 7 11 10
E 7 18 12
C 8 26 8
D 12 38 11
JUMLAH 38 97

a. WAKTU PENYELESAI 19.4


b. UTILITAS 0.391752577319588
C. JUMLAH PEKERJAAN 2.55263157894737
d. KETERLAMBATAN 10.4
KETERLAMBATAN
0
1
6
18
27
52
URUTAN PEKERJAN LPT D-C-E-B-A

URUTAN PWAKTU PEALIRAN W BATAS WAKETERLAMBATAN


D 12 12 11 1
C 8 20 8 12
E 7 27 12 15
B 7 34 10 24
A 4 38 12 26
JUMLAH 38 131 78

a. WAKTU 26.2
b. UTILITAS 0.290076
C. JUMLAH 3.447368
d. KETERL 15.6
URUTAN PEKERJAN EDD C-B-D-A-E

URUTAN PWAKTU PEALIRAN W BATAS WAKETERLAMBATAN


C 8 8 8 0
B 7 15 10 5
D 12 27 11 16
A 4 31 12 19
E 7 38 12 26
JUMLAH 38 119 66

a. WAKTU 23.8
b. UTILITAS 0.319328
C. JUMLAH 3.131579
d. KETERL 13.2