TOTAL
NO URAIAN
1 PEKERJAAN STRUKTUR -
2 PEKERJAAN ARSITEKTUR -
3 PEKERJAAN MEKANIKAL & ELEKTRIKAL -
TOTAL………. Rp. -
DIBULATKAN……....Rp. -
TERBILANG :
RENCANA ANGGARAN BIAYA
PEKERJAAN STRUKTUR
PASAR SUMUR BATU - PERUMDA PASAR JAYA
PEKERJAAN STRUKTUR
I. LANTAI DASAR
A Pekerjaan Pondasi Mini Pile
1 C.5 Pas. Tiang Pancang 25.25, D16 Mutu beton K-450 m 2,352.00 -
B Pekerjaan Pilecap
2 B.1 Galian tanah biasa sedalam 1 m m3 146.04 -
3 B.2 Buang tanah sejauh ±15 m m3 53.67 -
4 B.3 Urug kembali tanah galian m3 92.37 -
5 B.4 Urugan pasir urug m3 5.68 -
6 D.1a Lantai kerja beton tumbuk 1:3:5; t. 50 mm m2 81.21 -
Pilecap P2 uk. 500/1250/750
7 D.3 -Beton Readymix K-300 m3 1.88 -
8 D.6 -Bekisting Pondasi m2 10.50 -
-Tulangan besi U-24
9 K.1a -dia. 10 mm kg 7.99 -
-Tulangan besi U-39
10 K.1b -dia. D10 mm kg 16.99 -
11 K.1b -dia. D16 mm kg 89.98 -
Pilecap P3 uk. 1250/1151/750
12 D.3 -Beton Readymix K-300 m3 14.28 -
13 D.6 -Bekisting Pondasi m2 38.16 -
-Tulangan besi U-24
14 K.1a -dia. 10 mm kg 32.14 -
-Tulangan besi U-39
15 K.1b -dia. D13 mm kg 151.97 -
16 K.1b -dia. D16 mm kg 387.95 -
Pilecap P4 uk. 1250/1250/1000
17 D.3 -Beton Readymix K-300 m3 12.50 -
18 D.6 -Bekisting Pondasi m2 40.00 -
-Tulangan besi U-24
19 K.1a -dia. 10 mm kg 46.82 -
-Tulangan besi U-39
20 K.1b -dia. D13 mm kg 144.81 -
21 K.1b -dia. D19 mm kg 567.76 -
Pilecap P5 uk. 1250/1799/1000
22 D.3 -Beton Readymix K-300 m3 53.97 -
23 D.6 -Bekisting Pondasi m2 146.35 -
-Tulangan besi U-24
24 K.1a -dia. 10 mm kg 173.14 -
-Tulangan besi U-39
25 K.1b -dia. D13 mm kg 587.80 -
26 K.1b -dia. D19 mm kg 2,154.11 -
F Pekerjaan Kolom
Kolom K1 uk. 400/400
76 D.3 Beton Readymix K-300 m3 31.26 -
77 D.7 Bekisting Kolom m2 312.58 -
Tulangan besi U-39
78 K.1b -dia. D10 mm kg 1,034.21 -
79 K.1b -dia. D16 mm kg 5,328.46 -
Kolom KR uk. 300/300
80 D.3 Beton Readymix K-300 m3 1.11 -
81 D.7 Bekisting Kolom m2 14.84 -
Tulangan besi U-39
82 K.1b -dia. D10 mm kg 41.61 -
83 K.1b -dia. D16 mm kg 174.27 -
Balok Tangga
92 D.3 Beton Readymix K-300 m3 0.68 -
93 D.8 Bekisting Balok m2 7.14 -
Tulangan besi U-39
94 K.1b -dia. D10 mm kg 30.10 -
95 K.1b -dia. D16 mm kg 113.44 -
Kolom Tangga
96 D.3 Beton Readymix K-300 m3 0.26 -
97 D.7 Bekisting kolom m2 5.25 -
Tulangan besi U-39
98 K.1b -dia. D10 mm kg 11.63 -
99 K.1b -dia. D16 mm kg 67.45 -
II. LANTAI 1
A Pekerjaan Kolom
Kolom K1 uk. 400/400
1 D.3 Beton Readymix K-300 m3 19.41 -
2 D.7 Bekisting Kolom m2 194.11 -
Tulangan besi U-39
3 K.1b -dia. D10 mm kg 2,791.15 -
4 K.1b -dia. D16 mm kg 603.29 -
B Pekerjaan Balok
Balok B1 uk. 300/600
5 D.8 Beton Readymix K-300 m3 30.79 -
6 D.8 Bekisting Balok m2 270.82 -
Tulangan besi U-39
7 K.1b -dia. D10 mm kg 1,849.54 -
8 K.1b -dia. D16 mm kg 4,088.45 -
Balok B1K uk. 300/600
9 D.3 Beton Readymix K-300 m3 1.33 -
10 D.8 Bekisting Balok m2 11.66 -
Tulangan besi U-39
11 K.1b -dia. D10 mm kg 76.38 -
12 K.1b -dia. D16 mm kg 102.73 -
Balok B2 uk. 200/400
13 D.3 Beton Readymix K-300 m3 3.46 -
14 D.8 Bekisting Balok m2 47.42 -
Tulangan besi U-39
15 K.1b -dia. D10 mm kg 188.67 -
16 K.1b -dia. D16 mm kg 399.83 -
Balok B3 uk. 200/600
17 D.3 Beton Readymix K-300 m3 7.49 -
18 D.8 Bekisting Balok m2 90.89 -
Tulangan besi U-39
19 K.1b -dia. D10 mm kg 411.68 -
20 K.1b -dia. D16 mm kg 746.22 -
Balok G1 uk. 300/600
21 D.3 Beton Readymix K-300 m3 33.16 -
No Code Uraian Pekerjaaan Satuan Qty Harga Satuan Jumlah Harga
V. GWT
A Pekerjaan Pondasi Batukali
1 B.1 Galian tanah kedalaman 1 m m3 10.86 -
2 B.2 Buang tanah sejauh ±15 m m3 8.70 -
3 B.3 Urugan kembali tanah galian m3 2.16 -
4 B.4 Urugan pasir urug m3 1.40 -
5 D.1a Lantai kerja beton tumbuk 1:3:5; t. 50 mm m2 13.97 -
6 C.3 Pas. Aanstamping t.200 mm m3 2.79 -
7 C.2 Pas. Pondasi batu belah 1 PC. : 5 PS. m3 3.05 -
8 D.3 Beton Readymix K-300 m3 0.76 -
9 K.1a Angkur Ø 10 mm kg 5.96 -
D Pekerjaan Telapak
12 B.1 Galian tanah biasa sedalam 1 m m3 1.44 -
13 B.2 Buang tanah sejauh ±15 m m3 0.67 -
14 B.3 Urug kembali tanah galian m3 0.77 -
No Code Uraian Pekerjaaan Satuan Qty Harga Satuan Jumlah Harga
E Pekerjaan Tiebeam
21 B.1 Galian tanah biasa sedelam 1 m m3 1.95 -
22 B.2 Buang tanah sejauh ±15 m m3 0.98 -
23 B.3 Urug kembali tanah galian m3 0.98 -
TB1 uk. 200/400
24 D.3 -Beton Readymix K-300 m3 0.98 -
25 D.6 -Bekisting Pondasi m2 9.76 -
-Tulangan besi U-39
26 K.1b -dia. D10 mm kg 49.59 -
27 K.1b -dia. D13 mm kg 164.24 -
G Pekerjaan Dinding
36 D.3 Beton Readymix K-300 m3 20.10 -
37 D.9 Bekisting Plat Dinding m2 201.00 -
Tulangan besi U-39
38 K.1b -dia. D10 mm kg 600.42 -
39 K.1b -dia. D13 mm kg 1,440.65 -
H Pekerjaan Kolom
40 D.3 Beton Readymix K-300 m3 0.30 -
41 D.7 Bekisting Kolom m2 6.00 -
Tulangan besi U-39
42 K.1b -dia. D10 mm kg 18.47 -
43 K.1b -dia. D16 mm kg 66.77 -
I Pekerjaan Balok
44 D.3 Beton Readymix K-300 m3 0.83 -
45 D.8 Bekisting Balok m2 11.96 -
Tulangan besi U-39
46 K.1b -dia. D10 mm kg 56.60 -
47 K.1b -dia. D16 mm kg 161.38 -
No Code Uraian Pekerjaaan Satuan Qty Harga Satuan Jumlah Harga
REKAPITULASI
I. LANTAI DASAR -
II. LANTAI 1 -
V. GWT -
PEKERJAAN PERSIAPAN
1 A.1 Mobilisasi peralatan dan tenaga kerja ls 1.00 -
2 A.2 Pagar sementara seng gelombang T. 2 m m 259.00 -
3 Bongkaran bangunan Existing, berikut pembuangan m2 3,398 -
4 A.3 Pembersihan lapangan m2 3,337.00 -
5 A.4 Pengukuran kembali site m2 3,337.00 -
6 A.5 Papan Nama Proyek bh 1.00 -
7 A.6 Pek. Bowplank m 495.70 -
8 A.7 Pembuatan Direksikeet uk. 3,00 x 8,00 m m2 24.00 -
9 A.8 Pembuatan Gudang barang uk. 3,00 x 12,00 m m2 36.00 -
10 A.9 Air ( sumber air existing ) dan Listrik kerja bln 8.00 -
11 A.10 Test PDA ( Pile Driving Analisis) ttk 5.00 -
Kios
14 E.3 Pas. Bata beton ringan dry area m2 202.00 -
15 D.7 Pas. Kolom praktis 100 x 100 m 94.50 -
16 D.7 Pas. Balok praktis 100 x 100 m 118.75 -
17 E.6 Pas. Partisi Gypsumboard t.9 mm rangka hollow satu muka m2 62.46 -
18 E.7 Pas. Kawat harmonika galvanis rangka besi siku m2 86.69 -
19 F.3 Pas. Plester dry area, mortar instan m2 355.16 -
20 F.6 Pas. Acian mortar instan m2 355.16 -
21 F.6 Pas. Acian kolom, mortar instan m2 14.18 -
22 N.1 Cat Acrilyc Emulsion dinding Interior m2 494.26 -
Meja / Los
23 D.10 Pek. Meja beton 800 x 2700 x 100 mm unt 96.00 -
24 D.10 Pek. Meja beton 800 x 2700 x 100 mm unt 34.00 -
25 E.3 Pas. Bata beton ringan dry area m2 471.13 -
26 D.7 Pas. Kolom praktis 100 x 100 m 515.20 -
27 F.3 Pas. Plester dry area, mortar instan m2 1373.75 -
No Code Uraian Pekerjaaan Satuan Qty Harga Satuan Jumlah Harga
B Pekerjaan Lantai
Bangunan
31 E.1 Pas. Rolag 1/2 bata merah t. 25 cm (peninggian lantai toilet) m2 2.55 -
32 D.1 Pas. Screed ( pengisi peninggian lantai toilet ) m3 0.54 -
33 M.4 Pas. Lantai Keramik anti slip 300/300; Type KR4; Toilet m2 25.69 -
34 M.1 Pas. Lantai Keramik 300/300; Type KR1; Koridor m2 406.18 -
35 M.9 Pas. Plint Lantai Keramik 100/300; Type KR1 m 16.27 -
36 M.11 Pas. Border Lantai Keramik 100/300; Type KR3; Koridor m 116.98 -
37 D.8 Pek. Waterproofing coating m2 23.38 -
Kios
38 M.1 Pas. Lantai Keramik 300/300; Type KR1 m2 88.00 -
Meja / Los
39 M.5 Pas. Lantai Keramik anti slip 200/200; Type KR1A m2 168.06 -
40 D.1a Pas. Lantai Screed t. 5 cm m2 162.72 -
41 F.5 Pas. Acian lantai m2 162.72 -
42 D.8 Pek. Waterproofing coating m2 120.89 -
43 P.10 Pek. Saluran Greffel 20 cm & penutup uk.225 x 250 mm m 502.30 -
C Pekerjaan Plafond
Bangunan
44 I.1 Pas. Plafond Kasiboard t. 6 mm; rangka besi hollow m2 43.99 -
45 F.5 Pas. Plafond beton exposed, acian m2 1111.79 -
46 N.3 Cat Acrilyc Emulsion plafond Interior m2 1155.78 -
Kios
47 I.2 Pas. Plafond Gypsumboard t.9 mm; rangka metal besi hollow m2 88.00 -
48 N.3 Cat Acrilyc Emulsion plafond Interior m2 88.00 -
Kios
58 PJ.7 Pintu Rolling door PK1; 1900 x 2150 unt 12.00 -
59 PJ.8 Pintu Rolling door PK2; 1775 x 2150 unt 10.00 -
60 PJ.9 Pintu Rolling door PK3; 1900 x 3150 unt 4.00 -
61 PJ.10 Pintu Rolling door PK4; 1775 x 3150 unt 5.00 -
E Pekerjaan Sanitary
Bangunan
No Code Uraian Pekerjaaan Satuan Qty Harga Satuan Jumlah Harga
F Pekerjaan Tangga
Bangunan
71 M.1 Pas. Keramik 300/300; Type KR1; Tread Tangga selasar m2 31.49 -
72 M.1 Pas. Keramik 300/300; Type KR1; Riser Tangga selasar m2 31.49 -
73 M.2 Pas. Keramik 300/300; Type KR2; Tread Tangga utama m2 13.86 -
74 M.2 Pas. Keramik 300/300; Type KR2; Riser Tangga utama m2 13.86 -
75 M.2 Pas. Keramik 300/300; Type KR2; Bordes Tangga utama m2 7.92 -
76 M.12 Pas. Keramik step nosing 100/300 m 75.90 -
77 F.5 Pas. Plafond beton exposed, acian m2 84.77 -
78 N.3 Cat Acrilyc Emulsion plafond Interior m2 57.09 -
79 K.8 Railling besi hollow T.900 mm m 74.52 -
II. LANTAI 1
A Pekerjaan Dinding
Bangunan
1 E.3 Pas. Bata beton ringan dry area m2 203.24 -
2 E.4 Pas. Bata beton ringan wet area; Toilet m2 48.54 -
3 D.7 Pas. Kolom praktis 100 x 100 m 119.00 -
4 F.3 Pas. Plester dry area, mortar instan m2 274.06 -
5 F.3 Pas. Plester wet area, mortar instan m2 111.25 -
6 F.3 Pas. Plester dry area; mortar instan, Eksternal m2 61.30 -
7 F.6 Pas. Acian mortar instan m2 313.20 -
8 F.6 Pas. Acian kolom, mortar instan m2 141.83 -
9 M.6 Pas. Dinding Keramik 300/300; Type KR1 m2 90.41 -
10 M.10 Pas. Border Dinding Keramik 100/300 ex Roman; Type KR3 m 42.99 -
11 N.1 Cat Acrilyc Emulsion dinding Interior m2 432.42 -
12 N.2 Cat weathershield dinding Eksterior m2 61.30 -
13 D.8 Pek. Waterproofing coating m2 13.51 -
Kios
14 E.3 Pas. Bata beton ringan dry area m2 1248.00 -
15 D.7 Pas. Kolom praktis 100 x 100 m 670.95 -
16 D.7 Pas. Balok praktis 100 x 100 m 767.28 -
17 E.6 Pas. Partisi Gypsumboard t.9 mm rangka hollow satu muka m2 414.88 -
18 E.7 Pas. Kawat harmonika galvanis rangka besi siku m2 560.11 -
19 F.3 Pas. Plester dry area, mortar instan m2 2386.91 -
20 F.3 Pas. Plester dry area; mortar instan, Eksternal m2 25.20 -
No Code Uraian Pekerjaaan Satuan Qty Harga Satuan Jumlah Harga
B Pekerjaan Lantai
Bangunan
25 E.1 Pas. Rolag 1/2 bata merah t. 25 cm m2 2.77 -
26 D.1 Pas. Screed ( pengisi peninggian lantai toilet ) m3 0.63 -
27 M.4 Pas. Lantai Keramik anti slip 300/300; Type KR4; Toilet m2 22.49 -
28 M.1 Pas. Lantai Keramik 300/300; Type KR1; Koridor m2 187.01 -
29 M.9 Pas. Plint Lantai Keramik 100/300; Type KR1 m 44.48 -
30 M.11 Pas. Border Lantai Keramik 100/300; Type KR3; Koridor m 505.06 -
31 D.8 Pek. Waterproofing coating m2 22.49 -
Kios
32 M.1 Pas. Lantai Keramik 300/300; Type KR1 m2 580.00 -
C Pekerjaan Plafond
Bangunan
33 I.1 Pas. Plafond Kasiboard t. 6 mm; rangka besi hollow m2 22.49 -
34 I.2 Pas. Plafond Gypsumboard t.9 mm; rangka metal besi hollow m2 33.78 -
35 N.3 Cat Acrilyc Emulsion plafond Interior m2 56.27 -
Kios
36 I.2 Pas. Plafond Gypsumboard t.9 mm; rangka metal besi hollow m2 580.00 -
37 N.3 Cat Acrilyc Emulsion plafond Interior m2 580.00 -
Kios
44 PJ.7 Pintu Rolling door PK1; 1900 x 2150 unt 100.00 -
45 PJ.8 Pintu Rolling door PK2; 1775 x 2150 unt 43.00 -
46 PJ.9 Pintu Rolling door PK3; 1900 x 3150 unt 37.00 -
47 PJ.10 Pintu Rolling door PK2; 1775 x 3150 unt 18.00 -
E Pekerjaan Sanitary
Bangunan
48 O.1 Closet Jongkok; CL1 bh 3.00 -
49 O.2 Closet Duduk; CL2 bh 2.00 -
50 O.3 Washtafel; WT1 bh 4.00 -
51 O.4 Urinal; UR1 bh 3.00 -
52 O.5 Shower spray; SW1 bh 2.00 -
53 O.6 Kran dinding; KN1 bh 3.00 -
54 O.7 Floor drain; FD1 bh 7.00 -
55 O.7 Floor drain;FD1; Area Selasar bh 9.00 -
56 L.11.a Pas Kaca t.3 mm; 600 x 1000 bh 4.00 -
No Code Uraian Pekerjaaan Satuan Qty Harga Satuan Jumlah Harga
III. ATAP
A Pekerjaan Dinding
1 E.26 Pas. Dinding Kasiboard t. 6 mm 1 rangkap; rangka besi hollow m2 56.58 -
2 E.3 Pas. Bata beton ringan dry area m2 103.00 -
3 F.3 Pas. Plester dry area, mortar instan m2 64.55 -
4 F.3 Pas. Plester dry area; mortar instan, Eksternal m2 108.16 -
5 F.6 Pas. Acian mortar instan m2 172.71 -
6 N.1 Cat Acrilyc Emulsion dinding Interior m2 121.13 -
7 N.2 Cat weathershield dinding Eksterior m2 164.74 -
B Pekerjaan Lantai
8 D.1a Pas. Lantai screed t. 5 cm; dak m2 22.25 -
9 D.9 Pek. Waterproofing membrane m2 29.73 -
D Pekerjaan Atap
12 H.3 Penutup atap PVC Doff m2 1138.13 -
13 H.2 Penutup atap PVC Transparant m2 326.00 -
14 H.12 Pek. Kanopi Polycarbonate rangka hollow dengan Kabel sling m2 321.38 -
15 I.1 Pek. Plafond Kalsiboard t.6 mm rangka hollow m2 140.78 -
16 H.6 Pek. Talang datar PVC m 135.85 -
17 H.9 Flashing seng plat l. 30 cm; atap kanopi m 254.25 -
18 H.10 Flashing seng plat l. 90 cm; talang datar pvc m 135.85 -
19 N.4 Cat weathershield plafond Eksterior m 140.78 -
20 O.9 Roof drain bh 0.00 -
IV. FAÇADE
V. POS JAGA
A Pekerjaan Dinding
1 E.3 Pas. Bata beton ringan dry area m2 17.90 -
2 D.7 Pas. Kolom praktis 100 x 100 m2 10.80 -
3 F.3 Pas. Plester dry area, mortar instan m2 17.90 -
No Code Uraian Pekerjaaan Satuan Qty Harga Satuan Jumlah Harga
B Pekerjaan Lantai
8 M.1 Pas. Lantai Keramik 300/300; Type KR1 m2 6.00 -
9 M.9 Pas. Plint Keramik 100/300; Type KR1 m 9.12 -
C Pekerjaan Plafond
10 I.2 Pas. Plafond Gypsumboard t.9 mm; rangka metal furing system m2 6.00 -
11 N.3 Cat Acrilyc Emulsion plafond Interior m2 6.00 -
E Pekerjaan Atap
18 E.3 Pas. Bata beton ringan dry area m2 3.00 -
19 F.3 Pas. Plester dry area; mortar instan, Eksternal m2 6.00 -
20 F.6 Pas. Acian mortar instan m2 6.00 -
21 F.5 Pas. Acian kanopi beton m2 17.14 -
22 N.2 Cat weathershield dinding Eksterior m2 23.14 -
23 D.1a Pas. Lantai screed; dak m2 6.00 -
24 D.8 Pek. Waterproofing coating m2 6.00 -
25 O.9 Roof drain bh 1.00 -
V. POS JAGA -
B Pekerjaan Lantai
10 M.5 Pas. Lantai Keramik 200/200; Type KR1 m2 52.46 -
11 D.8 Pek. Waterproofing coating m2 35.26 -
C Pekerjaan Plafond
12 F.5 Pas. Plafond beton exposed, acian m2 52.46 -
13 N.3 Cat Acrilyc Emulsion plafond Interior m2 52.46 -
E Pekerjaan Atap
16 D.1a Pas. Lantai screed; dak m2 51.59 -
17 D.8 Pek. Waterproofing coating m2 51.59 -
18 O.9 Roof drain bh 2.00 -
19 K.10 Tangga Ladder Besi BSP 2" m 2.50 -
VII. EKSTERNAL
REKAPITULASI BANGUNAN
KONTRAK
NO. URAIAN PEKERJAAN SAT VOLUME
HARGA SAT. TOTAL HARGA
I.C CCTV
Virtual Console
Spesifikasi Teknis:
● Make live announcements via a microphone
● Transmission of preset files
● Set authorisation levels for each user
● Designate type of broadcasting to area
● Assign area to user
● Enable user with highest authorisation to select areas
to which their announcements are broadcast themselves
I. E FIRE ALARM
I.E.1 MAIN EQUIPMENT
1 MCFA ( Master Control Fire Alarm ) termasuk Repeat Pan set 1.00 -
Kapasitas : 10 Zona
Type : Konvensional
3 Power Supply 220 V / 1 Ph / 50 Hz lengkap Arrester dan set 1.00 -
4 LCD Announciator set 1.00 -
5 Main Distribution Fire Alarm (MDFA) unit 1.00 -
6 Main Bell unit 1.00 -
KONTRAK
NO. URAIAN PEKERJAAN SAT VOLUME
HARGA SAT. TOTAL HARGA
7 Main Red Lamp unit 1.00 -
8 Module- module :
- Power Supply 220 V / 1 Ph / 50 Hz lengkap Arrester unit 1.00 -
- Main Bell unit 1.00 -
- Main Red Lamp unit 1.00 -
- Addressable Control Module to P. Sound System unit 1.00 -
9 Instalasi Peralatan Utama lot 1.00 -
I.E.2 CABELING
1 Kabel NYA 2 x 1,5 mm2 dari MDFA TB.FA in conduit PVC m 20.00 -
2 Kabel NYA 3 x 1,5 mm2 untuk kabel Power TB.FA in cond m 20.00 -
3 Kabel NYA 3 x 1,5 mm2 dari MCFA ke Sound System in c m 10.00 -
4 Kabel STP #18 2 pair + NYA 2 x 1,5 mm2 dari MCFA to An m 10.00 -
II.A MECHANICAL
II.A.1 CLEAN WATER SUPPLY INSTALATION SYSTEM
II.A.1.1 MAIN EQUIPMENT
1 Transfer Pump Centrifugal Type unit 2 -
- Capacity 130 liter/menit
- Head 40 m
- Control Panel & cable (Auto-Manual)
- Parallel Alternate
- Include base frame
3 Jockey Fire Pump (Untuk Fire Hydrant & Fire Sprinkler) set 1 -
Type : Vertikal Multistage In Line
Kapasitas : 25 GPM
Total Head : 90 meter
Elec. Power : 3.7 KW, 380 V / 3 Ph / 50 Hz
Standard : NFPA20 Standard
C/W: Panel Control & Accessories
3 Check Valve 16 K :
- dia. 100 mm unit 2 -
- dia. 50 mm unit 1 -
4 Strainer 16 K :
- dia. 100 mm unit 2 -
- dia. 50 mm unit 1 -
6 Fleksible Joint 20 K
- dia. 100 mm unit 2 -
- dia. 50 mm unit 1 -
7 Pressure Gauge + Valve unit 4 -
8 Pressure Switch unit 3 -
9 Fire Extinguisher Dry chemical type ABC unit 1 -
Class ABC 25 Kg c/w include box kaca
II.E.4 PEMIPAAN SITE (OUT DOOR HYDRANT) & RISER FROM PUMP ROOM
Black Steel Pipe Sch 40
1 Black steel pipe sch 40 dia. 150mm m 20 -
2 Black steel pipe sch 40 dia. 100mm m 129 -
3 Excavation & Back Filling m 149 -
ELECTRICAL, ELECTRONIC
ELECTRICAL DISTRIBUTION POWER PANEL -
ELECTRICAL ARMATURE & LIGHTNING PROTECTION INSTALATION -
CCTV -
PUBLIC ADDRESS & GENERAL ANNOUNCEMENT -
FIRE ALARM -
MECHANICAL, PLUMBING
CLEAN WATER SUPPLY INSTALATION -
SEWAGE WATER INSTALATION -
WASTE WATER INSTALATION -
RAIN WATER INSTALATION -
FIRE FIGHTING INSTALATION -
AIR CONDITIONING & EXHAUST FAN -
GENERATOR SET -