BAB IV
RENCANA ANGGARAN BIAYA
PEKERJAAN LANTAI - 1
Urugan Tanah TB 1
Vol timbunan tanah kembali = 0.25 x 21.150 = 5.288 m3
Urugan Tanah TB 2
Vol timbunan tanah kembali = 0.25 x 95.34 = 23.835 m3
Urugan Tanah TB 3
Vol timbunan tanah kembali = 0.25 x 45.890 = 11.473 m3
30
Urugan Tanah TB A1
Vol timbunan tanah kembali = 0.25 x 9.630 = 2.41 m3
Urugan Pasir TB 1
Tinggi = 0.10 m
Lebar = 0.35 m
31
Panjang = 80.57 m
Vol timbunan Pasir 10 cm = 0.10 x 0.35 x 80.57 = 2.820 m3
Urugan Pasir TB 2
Tinggi = 0.10 m
Lebar = 0.30 m
Panjang = 128.21 m
Vol timbunan Pasir 10 cm = 0.10 x 0.30 x 128.21 = 3.846 m3
Urugan Pasir TB 3
Tinggi = 0.10 m
Lebar = 0.50 m
Panjang = 183.56 m
Vol timbunan Pasir 10 cm = 0.10 x 0.50 x 183.56 = 9.178 m3
Urugan Pasir TB A1
Tinggi = 0.10 m
Lebar = 0.25 m
Panjang = 51.47 m
Vol timbunan Pasir 10 cm = 0.10 x 0.25 x 51.47 = 1.287 m3
URUGAN SIRTU BAWAH LANTAI 30 cm
Luas bangunan = 886.60 m
Tebal = 0.30 m
Tebal = 0.05 m
Lebar = 0.75 m
Panjang = 2.51 m
Jumlah = 2.00 bh
Vol timbunan Pasir 5 cm = 0.05 x 0.75 x 2.51 x 2.00 = 0.188 m3
Lantai Kerja TB 1
Tebal = 0.05 m
Lebar = 0.35 m
Panjang = 80.57 m
Vol timbunan Pasir 5 cm = 0.05 x 0.35 x 80.57 = 1.410 m3
Lantai Kerja TB 2
Tebal = 0.05 m
Lebar = 0.30 m
Panjang = 128.21 m
Vol timbunan Pasir 5 cm = 0.05 x 0.30 x 128.21 = 1.923 m3
Lantai Kerja TB 3
Tebal = 0.05 m
Lebar = 0.50 m
Panjang = 183.56 m
Vol timbunan Pasir 5 cm = 0.05 x 0.50 x 183.56 = 4.589 m3
Lantai Kerja TB A1
Tebal = 0.05 m
Lebar = 0.25 m
Panjang = 51.47 m
Vol timbunan Pasir 5 cm = 0.05 x 0.25 x 51.47 = 0.643 m3
Lantai Kerja Plat Lantai
Luas bangunan = 886.60 m
Tebal = 0.05 m
Tinggi = 3.67 m
Lebar Depan (L1) = 0.654 m
Lebar Samping (L2) = 0.5 m
Jumlah = 4 bh
Volume = 3.67 x 0.654 x 0.5 x 4.00 = 4.800 m3
Kolom Praktis
- KPSA (17,5x50 cm)
Tinggi = 7 m
Lebar Depan (L1) = 0.175 m
Lebar Samping (L2) = 0.5 m
Jumlah = 3 bh
Volume = 7 x 0.175 x 0.5 x 3.00 = 1.840 m3
Balok
Balok Beton elv. +04.20
- BB2 (30x60)
Tinggi = 0.6 m
Lebar = 0.3 m
Panjang = 21.9 m
Volume = 0.6 x 0.3 x 21.9 = 3.940 m3
- BB3 (25x40)
Tinggi = 0.4 m
Lebar = 0.25 m
Panjang = 20.8 m
Volume = 0.4 x 0.25 x 20.8 = 2.080 m3
Plat Lantai
Lantai 1
- Plat beton lantai, t = 15 cm (S1) elev -00.30
35
Tebal = 0.15 m
Total luas lantai 1 = 758.93 m
Volume = 0.15 x 758.93 = 113.840 m3
Lantai 3
- Plat beton lantai, t = 12 cm (S2) elev. +04.05
Tebal = 0.12 m
Total luas lantai 1 = 557.15 m
Volume = 0.12 x 555.15 = 66.620 m3
Dak Utilitas
- Plat beton lantai, t = 12 cm (S2) elev. +07.82
Tebal = 0.12 m
Total luas lantai 1 = 11.92 m
Volume = 0.12 x 11.92 = 1.430 m3
Tangga
-Tangga Showroom
Volume 1 anak tangga = 0.29 x 0.19 x 1.2 = 0.066 m3
Volume 21 anak tangga = 0.066 x 22 = 1.452 m3
volume plat = 1.2 x 0.12 x 8 = 1.152 m3
Volume = 1.452 + 1.152 = 2.604 m3
-Tangga Bengkel
Volume 1 anak tangga = 0.29 x 0.19 x 1.2 = 0.066 m3
Volume 21 anak tangga = 0.066 x 22 = 1.452 m3
volume plat = 1.2 x 0.12 x 9 = 1.296 m3
Volume = 1.452 + 1.296 = 2.748 m3
PEKERJAAN BEKISTING
Bekisting multipleks 12 mm
- Kolom Pedestal lt. 1
Tinggi kolom = 1.1 m
Lebar = 0.6 m
Jumlah = 82 bh
Volume = 1.1 x 0.6 x 82 = 216.470 m2
- Kolom Praktis
Tinggi kolom = 4.25 m
Lebar = 0.5 m
Jumlah = 40 bh
Volume = 4.25 x 0.5 x 40 = 79.120 m2
Bekisting multipleks 12 mm `
- Balok Elv. +04.20
Tinggi = 0.6 x 21.9 x 2 = 13.140 m2
Lebar = 0.3 x 21.9 x 1 = 6.570 m2
Panjang = 21.9
Volume = 13.140 + 6.570 = 19.710 m2
Pile cap
P1, besi D13, D16
Diameter tulangan pokok atas = D 13 mm 1.040 kg/m1
jumlah tulangan pokok atas = 8 bh
pajang tul pokok atas = 0.90 m
Diameter tulangan pokok bawah = D 16 mm 1.576 kg/m1
jumlah tulangan pokok bawah = 8 bh
pajang tul pokok bawah = 0.90 m
Jumlah (n) = 8.00 bh
Volume Tulangan atas = 0.90 x 8.00 x 1.040 x 8 = 59.904 kg
Volume tulangan Bawah = 0.90 x 8.00 x 1.58 x 8 = 90.778 kg
Volume = 59.90 + 90.778 = 150.682 kg
Tie Beam
TB1 (35x75 cm) , D10, D13, D19
Panjang (p) = 80.57 m
Lebar = 0.35 m
39
Tinggi = 0.75 m
tulangan pokok (diameter ) = D 19 mm 2.23 kg/m1
jumlah tul pokok = 13 bh
tulangan ekstra (diameter ) = D13 mm 1.04 kg/m1
jumlah tul ekstra = 2 bh
tul pembagi = 10 mm 0.61 kg/m1
jarak tul. Pembagi tumpuan = 0.15 m
jarak tul. Pembagi Lapangan = 0.15 m
TUMPUAN
Panjang = p x 40%
= 32.23 m
diameter 19 = 2.23 x 13.00 x 32.23 = 932.614
diameter 13 = 1.04 x 2.00 x 32.23 = 67.034
diameter 10 = 0.610 x 214.85 x 2.20 = 288.333
1,287.981 kg
LAPANGAN
Panjang = p x 60%
= 48.34 m
diameter 19 = 2.23 x 13.00 x 48.34 = 1,398.921
diameter 13 = 1.04 x 2.00 x 48.34 = 100.551
diameter 10 = 0.610 x 322.28 x 2.20 = 432.500
1,499.472 kg
Volume = Tumpuan + Lapangan
= 1287.9813 + 1499.472 = 2,787.453 kg
LAPANGAN
Panjang = p x 60%
= 77.23 m
diameter 19 = 2.23 x 12.00 x 77.23 = 2,062.861
diameter 10 = 0.610 x 514.84 x 1.90 = 596.700
2,062.861 kg
Volume = Tumpuan + Lapangan
= 1773.0403 + 2062.861 = 3,835.901 kg
TB3 (30x50 cm) , D10, D19
Panjang (p) = 183.00 m
Lebar = 0.30 m
Tinggi = 0.50 m
tulangan pokok (diameter ) = D 19 mm 2.23 kg/m1
jumlah tul pokok = 12 bh
tul pembagi = 10 mm 0.61 kg/m1
jarak tul. Pembagi tumpuan = 0.15 m
jarak tul. Pembagi Lapangan = 0.15 m
TUMPUAN
Panjang = p x 40%
= 73.20 m
diameter 19 = 2.23 x 12.00 x 73.20 = 1,955.318
diameter 10 = 0.610 x 488.00 x 1.60 = 476.288
2,431.606 kg
LAPANGAN
Panjang = p x 60%
= 109.80 m
diameter 19 = 2.23 x 12.00 x 109.80 = 2,932.978
diameter 10 = 0.610 x 732.00 x 1.60 = 714.432
2,932.978 kg
Volume = Tumpuan + Lapangan
= 2431.6064 + 2932.978 = 5,364.584 kg
TBA1 (25x45 cm) , D10 , D19
Panjang (p) = 51.47 m
Lebar = 0.25 m
Tinggi = 0.45 m
tulangan pokok (diameter ) = D 19 mm 2.23 kg/m1
jumlah tul pokok = 9 bh
40
LAPANGAN
Panjang = p x 60%
= 30.88 m
diameter 19 = 2.23 x 9.00 x 30.88 = 618.690
diameter 10 = 0.610 x 205.88 x 1.40 = 175.822
618.690 kg
Volume = Tumpuan + Lapangan
= 529.67434 + 618.69 = 1,148.364 kg
Kolom
Kolom Pedestal lt. 1
Perhitungan kolom pedestal sudah termasuk kolom composite s/d elv. +01.05
- KP1 (50x50 cm), D10, D19
Tinggi (H) = 1.15 m
Lebar depan = 0.50 m
Lebar samping = 0.50 m
Jumlah (n) = 12.00 bh
tulangan pokok (diameter ) = D 19 mm 2.23 kg/m1
jumlah tul pokok (diameter ) = 18 bh
tul pembagi = 10 mm 0.610 kg/m1
jarak tul. Pembagi = 0.15 m
Kolom Praktis
- KPSA (17,5x50 cm) , besi D10, D16
Tinggi (H) = 7 m
Lebar depan = 0.175 m
Lebar samping = 0.5 m
Jumlah (n) = 3 bh
tulangan pokok (diameter ) = D 19 mm 2.23 kg/m1
jumlah tul pokok (diameter ) = 18 bh
tul pembagi = 10 mm 0.610 kg/m1
jarak tul. Pembagi = 0.15 m
Plat Lantai
Lantai 1
- Plat beton lantai, t = 15 cm (S1) elev -00.15 (Wiremesh M7 (deform)-2 layer, volume sdh dihitung 2x)
- Plat beton lantai, t = 15 cm (S4) elev -00.10 (Wiremesh M7 (deform)-2 layer, volume sdh dihitung 2x)
Lantai 2
- Plat beton lantai, t = 12 cm (S2) elev. +04.20 (Wiremesh M7 (deform)-1 layer)
Dak Utilitas
- Plat beton lantai, t = 12 cm (S2) elev. +07.70 (Wiremesh M7 (deform)-1 layer)
43
Tangga
-Tangga Showroom
Panjang (p) = 9.00 m
Lebar ( L ) = 1.20 m
tulangan pokok (diameter ) = 16 mm 1.578 kg/m1
tulangan pokok (diameter ) = 13 mm 1.04 kg/m1
jarak tulangan = 0.10 m
jumlah = 3.00 bh
Volume Besi
Plat = 1.04 x 1.20 x 91.00 x 3.00 = 340.704
= 1.58 x 9.00 x 13.00 x 3.00 = 553.878
894.582 kg
-Tangga Bengkel
Panjang (p) = 9.00 m
Lebar ( L ) = 1.20 m
tulangan pokok (diameter ) = 16 mm 1.578 kg/m1
tulangan pokok (diameter ) = 13 mm 1.04 kg/m1
jarak tulangan = 0.10 m
jumlah = 3.00 bh
Volume Besi
Plat = 1.04 x 1.20 x 91.00 x 3.00 = 340.704
= 1.58 x 9.00 x 13.00 x 3.00 = 553.878
894.582 kg
Kolom
Kolom Baja Lt. 1 Elv. +01.05
- KBJ1 (HB 250.250.9.14)
berat baja per m = 72.417 kg/m
Tinggi = 3.15 m
jumlah = 20.00 bh
Volume = 72.417 x 3.15 x 20.00 = 4,562.271 kg
Balok
Balok Baja Elv. +02.50
- B3 (WF 450.200.9.14)
berat baja per m = 76.000 kg/m
panjang total = 31.21 m
jumlah = 1.00 bh
Volume = 76.000 x 31.21 x 1.00 = 2,371.880 kg
- B4 (WF 400.200.8.13)
berat baja per m = 66.200 kg/m
panjang total = 13.15 m
jumlah = 1.00 bh
Volume = 66.200 x 13.15 x 1.00 = 870.82 kg
- B5 (WF 350.175.7.11)
berat baja per m = 49.600 kg/m
panjang total = 32.54 m
jumlah = 1.00 bh
Volume = 49.600 x 32.54 x 1.00 = 1,613.77 kg
- B6 (WF 300.150.6,5.9)
berat baja per m = 36.700 kg/m
panjang total = 40.58 m
jumlah = 1.00 bh
Volume = 36.700 x 40.58 x 1.00 = 1,489.13 kg
- B8 (WF 200.100.5,5.8)
berat baja per m = 21.333 kg/m
45
- B2 (Cast. 525.175.7.11)
berat baja per m = 49.600 kg/m
panjang total = 12.86 m
jumlah = 1.00 bh
Volume = 49.600 x 12.86 x 1.00 = 637.98 kg
- B3 (WF 450.200.9.14)
berat baja per m = 76.000 kg/m
panjang total = 10.82 m
jumlah = 1.00 bh
Volume = 76.000 x 10.82 x 1.00 = 822.56 kg
- B4 (WF 400.200.8.13)
berat baja per m = 66.000 kg/m
panjang total = 55.62 m
jumlah = 1.00 bh
Volume = 66.000 x 55.62 x 1.00 = 3,671.18 kg
- B5 (WF 350.175.7.11)
berat baja per m = 49.600 kg/m
panjang total = 52.39 m
jumlah = 1.00 bh
Volume = 49.600 x 52.39 x 1.00 = 2,598.33 kg
- B6 (WF 300.150.6,5.9)
berat baja per m = 36.700 kg/m
panjang total = 141.81 m
jumlah = 1.00 bh
Volume = 36.700 x 141.81 x 1.00 = 5,204.30 kg
- B7 (WF 250.125.6.9)
berat baja per m = 29.600 kg/m
panjang total = 16.72 m
jumlah = 1.00 bh
Volume = 29.600 x 16.72 x 1.00 = 494.77 kg
- B4 (WF 400.200.8.13)
berat baja per m = 66.000 kg/m
panjang total = 13.19 m
jumlah = 1.00 bh
Volume = 66.000 x 13.19 x 1.00 = 870.82 kg
- B5 (WF 350.175.7.11)
berat baja per m = 49.600 kg/m
panjang total = 32.54 m
jumlah = 1.00 bh
Volume = 49.600 x 32.54 x 1.00 = 1,613.77 kg
- B6 (WF 300.150.6,5.9)
berat baja per m = 36.700 kg/m
panjang total = 51.91 m
jumlah = 1.00 bh
Volume = 36.700 x 51.91 x 1.00 = 1,904.94 kg
- B8 (WF 200.100.5,5.8)
berat baja per m = 29.600 kg/m
panjang total = 29.37 m
jumlah = 1.00 bh
Volume = 29.600 x 29.37 x 1.00 = 869.35 kg
- B2 (Cast. 525.175.7.11)
berat baja per m = 49.600 kg/m
panjang total = 24.72 m
jumlah = 1.00 bh
Volume = 49.600 x 24.72 x 1.00 = 1,226.11 kg
- B3 (WF 450.200.9.14)
berat baja per m = 76.000 kg/m
panjang total = 39.60 m
jumlah = 1.00 bh
Volume = 76.000 x 39.60 x 1.00 = 3,009.87 kg
- B4 (WF 400.200.8.13)
berat baja per m = 66.000 kg/m
panjang total = 38.02 m
jumlah = 1.00 bh
Volume = 66.000 x 38.02 x 1.00 = 2,509.14 kg
- B5 (WF 350.175.7.11)
berat baja per m = 49.600 kg/m
panjang total = 106.55 m
jumlah = 1.00 bh
Volume = 49.600 x 106.55 x 1.00 = 5,284.95 kg
- B6 (WF 300.150.6,5.9)
berat baja per m = 36.700 kg/m
panjang total = 109.69 m
jumlah = 1.00 bh
Volume = 36.700 x 109.69 x 1.00 = 4,025.47 kg
- B7 (WF 250.125.6.9)
berat baja per m = 29.600 kg/m
panjang total = 189.71 m
jumlah = 1.00 bh
Volume = 29.600 x 189.71 x 1.00 = 5,615.28 kg
- B8 (WF 200.100.5,5.8)
berat baja per m = 29.600 kg/m
panjang total = 29.37 m
jumlah = 1.00 bh
Volume = 29.600 x 29.37 x 1.00 = 869.35 kg
- BB1(WF 450.200.9.14)
berat baja per m = 76.000 kg/m
panjang total = 4.12 m
jumlah = 1.00 bh
Volume = 76.000 x 4.12 x 1.00 = 313.12 kg
Balok Ramp
- B6 (WF 300.150.6,5.9)
berat baja per m = 36.700 kg/m
panjang total = 66.95 m
jumlah = 1.00 bh
Volume = 36.700 x 66.95 x 1.00 = 2,457.07 kg
- UNP (U 200.80.7,5)
berat baja per m = 25.833 kg/m
panjang total = 49.05 m
jumlah = 1.00 bh
Volume = 25.833 x 49.05 x 1.00 = 1,267.16 kg
- Siku (L 60.60.5)
berat baja per m = 4.570 kg/m
panjang total = 41.05 m
jumlah = 1.00 bh
Volume = 4.570 x 41.05 x 1.00 = 187.58 kg
Tangga
47
Tangga Showroom
- UNP 100.50.5
Panjang (p) = 9.00 m
Lebar ( L ) = 1.20 m
Berat baja per meter = 9.367 kg/m
Panjang Baja = 0.6 m 1.578 kg/m1
Jumlah Baja = 5.0 bh 1.04 kg/m1
Volume = 0.6 x 5.0 x 9.367 = 28.101 kg
Tangga Bengkel
- UNP 100.50.5
Panjang (p) = 9.00 m
Lebar ( L ) = 1.20 m
Berat baja per meter = 9.367 kg/m
Panjang Baja = 0.6 m 1.578 kg/m1
Jumlah Baja = 5.0 bh 1.04 kg/m1
Volume = 0.6 x 5.0 x 9.367 = 28.101 kg
- Chequered plat mezanine lt. 4 elv. +07.70 (Termasuk untuk daerah showroom)
Lebar Total Plat = 712.74 Propertis autocad
- UNP (U 100.50.5)
- Siku (L 60.60.5)
Rafter
Atap Depan
- R1 (Cast. 600.200.8.13)
berat baja per m = 66.000 kg/m
panjang total = 18.54 m
jumlah = 1.00 bh
Volume = 66.000 x 18.54 x 1.00 = 1,223.64 kg
- R2 (Cast. 525.175.7.11)
berat baja per m = 49.600 kg/m
panjang total = 37.08 m
jumlah = 1.00 bh
Volume = 49.600 x 37.08 x 1.00 = 1,839.17 kg
- R3 (WF 350.175.7.11)
berat baja per m = 49.600 kg/m
panjang total = 9.27 m
jumlah = 1.00 bh
Volume = 49.600 x 9.27 x 1.00 = 459.79 kg
- R4 (WF 250.125.6.9)
berat baja per m = 29.600 kg/m
panjang total = 25.13 m
jumlah = 1.00 bh
Volume = 29.600 x 25.13 x 1.00 = 743.91 kg
Atap Belakang
- R3 (WF 350.175.7.11)
berat baja per m = 49.600 kg/m
panjang total = 21.31 m
jumlah = 1.00 bh
Volume = 49.600 x 21.31 x 1.00 = 1,056.91 kg
- R4 (WF 250.125.6.9)
berat baja per m = 29.600 kg/m
panjang total = 38.33 m
jumlah = 1.00 bh
Volume = 29.600 x 38.33 x 1.00 = 1,134.46 kg
Atap Loading/Unloading
- R4 (WF 200.100.5,5.8)
berat baja per m = 29.600 kg/m
panjang total = 14.42 m
jumlah = 1.00 bh
Volume = 29.600 x 14.42 x 1.00 = 426.83 kg
Tie Beam
48
- B7 (WF 250.125.6.9)
berat baja per m = 29.600 kg/m
panjang total = 151.59 m
jumlah = 1.00 bh
Volume = 29.600 x 151.59 x 1.00 = 4,487.01 kg
Gording
Termasuk gording pada atap loading/unloading
- GD1 (CNP 200.75.20.3,2)
berat baja per m = 9.270 kg/m
panjang total = 484.04 m
jumlah = 1.00 bh
Volume = 9.270 x 484.04 x 1.00 = 4,487.01 kg
- GD2 (CNP150.50.20.2,3)
berat baja per m = 7.517 kg/m
panjang total = 596.92 m
jumlah = 1.00 bh
Volume = 7.517 x 596.92 x 1.00 = 4,487.01 kg
Trekstang dia. 12 mm
Panjang total besi = 280.29 m
berat besi per meter = 0.891 kg
Volume = 280.29 x 0.891 = 249.74 kg
Tutup GWT (Plat besi t = 2,3 dan rangka siku 50.50.5.10 keliling dan diagonal
Volume = 1 bh
PEKERJAAN ATAP
Penutup Atap Zincalume ex Lysaght type Trimdek Optima, BMT 0,45
Total luas atap = 758.95 m2 Propetis autocad
Insulation for roof : Zelltech Insulation ZT 05BBR 8mm, big bubble, 2 side aluminium foil
pemasangan pada sambungan menggunakan aluminium tape dan plat strip lebar 6 cm
Total kebutuhan insulation = 758.95 m2 Propetis autocad
Talang datar zincalume TCT 0,5 lapis fiberglass tebal 4mm, angkul talang plat strip 40x4 mm jarak 30 cm
- Ukuran lebar bawah = 100 cm , Lebar bahan 2.40 m
- Ukuran lebar bawah = 80 cm , lebar bahan = 1.75 cm
Talang canopy lebar 60 cm , lebar bahan 1,20 m
Skylight Fiber Lux lebar = 20 cm, tebal = 1,5 mm ex. ALKA LT-7 type clear + accesories
49
939 Pompa Submersible ( Deep well ) - SAER (Italy) Kapasitas 10 l/det - T. Unit
Head 70 m - Head
124,890,000.00
2900 RPM - Power 13 KW
940 Pompa Submersible ( Deep well ) - SAER (Italy) Kapasitas 10 l/det - T. Unit
Head 80 m - Head
124,890,000.00
2900 RPM - Power 13 KW
941 Pompa Submersible ( Deep well ) - SAER (Italy) Kapasitas 10 l/det - T. Unit
Head 100 m - Head
157,500,000.00
2900 RPM - Power 18,5 KW
942 Pompa Submersible ( Deep well ) - SAER (Italy) Kapasitas 15 l/det - T. Unit
Head 80 m - Head
196,790,000.00
2900 RPM - Power 18,5 KW
943 Porselen Putih uk 11 x 11 Buah 3,300.00
944 Porselen warna uk 11 x 11 Buah 3,500.00
945 Porselen Putih uk 15 x 15 Buah 3,600.00
946 Porselen warna uk 15 x 15 Buah 3,850.00
947 Profil Aluminium T m' 3,500.00
948 PVC (Sambungan) Ø 1 1/4" Buah 3,400.00
949 PVC (Sambungan) Ø 1 3/4" Buah 4,500.00
950 PVC (Sambungan) Ø 1" Buah 3,400.00
951 PVC (Sambungan) Ø 1/2" Buah 1,700.00
952 PVC (Sambungan) Ø 2" Buah 4,000.00
953 PVC (Sambungan) Ø 3/4" Buah 2,300.00
954 PVC (Sambungan) Ø 1 1/2" Buah 4,000.00
955 PVC (Sambungan) Ø 2 1/2" Buah 12,200.00
956 PVC (Sambungan) Ø 3" Buah 21,500.00
957 PVC (Sambungan) Ø 4" Buah 30,900.00
958 Ram Ayam m2 10,800.00
959 Ram Kawat 1 x 1 cm m2 14,700.00
960 Ram Nyamuk Aluminium m2 9,000.00
961 Ram Nyamuk Hijau m2 11,500.00
962 Ramset /Dina Bolt buah 2,710.00
963 Rangka Atap Zinc Alume m2 195,000.00
964 Rangka Plafond Hollow m2 27,000.00
965 Readymix Beton K 175, Tampa Pompa (Selang) m3 391,350.00
966 Readymix Beton K 225, Tampa Pompa (Selang) m3 414,100.00
967 Readymix Beton K 250 m3 720,000.00
968 Readymix Beton K 300 m3 744,000.00
969 Reflektor (Mata Kucing) Buah 127,250.00
970 Reflekto High Intensity Grade 10 x 20 cm Buah 27,950.00
971 Rel Henderson lengkap Buah 636,000.00
972 Rel Maraton 1 Pintu Unit 73,500.00
973 Rivet 5 mm Buah 600.00
974 Roll Cat Tembok Buah 17,500.00
975 Roll Door m2 259,000.00
976 Roll Meter 30 Meter (Bahan Plastik) Buah 66,000.00
977 Roll Meter 5 Meter (Bahan Plastik) Buah 14,700.00
978 Roster Beton 20 x 20 Buah 12,000.00
979 Roster Beton 30 x 30 Buah 4,500.00
980 Roster Tanah Liat Buah 5,000.00
981 Rumah Panel 30 x 60 cm (Kosong) Unit 110,200.00
982 Rumah TL In Bow / Out Bw 2 x 20 W (Kosong) Buah 75,000.00
983 Saklar Broco Seri Standard ( 1 Phase) Buah 17,600.00
71
PK10 11 TUKANG CAT / PELITUR SETENGAH TERAMPIL 95,000 1 ORANG/ HR/ 8 JAM
PK13 14 TUKANG BESI BETON SETENGAH TERAMPIL 80,000 1 ORANG/ HR/ 8 JAM
PK16 17 TUKANG BESI PROFIL SETENGAH TERAMPIL 80,000 1 ORANG/ HR/ 8 JAM
PEKERJAAN BONGKARAN
A 007 1 M3 MEMBONGKAR DINDING BATA
(Jika bongkaran di pakai lagi )
Pekerja Setengah Terampil 1.0000 org 80,000.00 80,000
Mandor 0.0500 org 110,000.00 5,500
Jumlah 85,500.00
Keuntungan Max. -
Jumlah 85,500.00
Dibulatkan 85,500.00
A 008 1 M3 MEMBONGKAR DINDING BATA
(Jika bongkaran tidak di pakai lagi )
Pekerja Setengah Terampil 1.0000 org 80,000.00 80,000
Mandor 0.0900 org 110,000.00 9,900
Jumlah 89,900.00
Keuntungan Max. -
Jumlah 89,900.00
Dibulatkan 89,900.00
A 009 1 M2 MEMBONGKAR PLESTERAN DINDING
Pekerja Setengah Terampil 0.0500 org 80,000.00 4,000
Mandor 0.0250 org 110,000.00 2,750
Jumlah 6,750.00
Keuntungan Max. -
Jumlah 6,750.00
Dibulatkan 6,750.00
A 010 1 M2 MEMBONGKAR GENTENG / SIRAP
(Jika bongkaran tidak di pakai )
Pekerja Setengah Terampil 0.0200 org 80,000.00 1,600
Mandor 0.0100 org 110,000.00 1,100
Jumlah 2,700.00
Keuntungan Max. -
Jumlah 2,700.00
Dibulatkan 2,700.00
A 011 1 M2 MEMBONGKAR GENTENG / SIRAP
(Jika bongkaran di pakai )
Pekerja Setengah Terampil 0.4000 org 80,000.00 32,000
Mandor 0.1000 org 110,000.00 11,000
Jumlah 43,000.00
Keuntungan Max. -
Jumlah 43,000.00
Dibulatkan 43,000.00
A 012 1 M2 MEMBONGKAR RANGKA ATAP / RENG KASO
(Jika bongkaran tidak di pakai )
Pekerja Setengah Terampil 0.1000 org 80,000.00 8,000
Tk kayu setengah terampil 0.0250 org 80,000.00 2,000
Kepala Tukang kayu 0.0025 org 100,000.00 250
Mandor 0.0050 org 110,000.00 550
Jumlah 10,800.00
Keuntungan Max. -
Jumlah 10,800.00
Dibulatkan 10,800.00
A 013 1 M2 MEMBONGKAR RANGKA ATAP / RENG KASO
(Jika bongkaran di pakai )
Pekerja Setengah Terampil 0.2000 org 80,000.00 16,000
Tk kayu setengah terampil 0.0500 org 80,000.00 4,000
Kepala Tukang kayu 0.0050 org 100,000.00 500
Mandor 0.0100 org 110,000.00 1,100
Jumlah 21,600.00
Keuntungan Max. -
Jumlah 21,600.00
Dibulatkan 21,600.00
78
Dibulatkan 297,690.00
A 098 1 M1 PASANG LIST PLAFON - KAYU PROFIL
Kayu Profil 1.0500 m1 11,800.00 12,390
Pekerja 0.0210 org 75,000.00 1,575
Tukang Kayu Terampil 0.0210 org 90,000.00 1,890
Kep. Tukang Kayu 0.0020 org 100,000.00 200
Mandor 0.0010 org 110,000.00 110
Jumlah 16,165.00
Keuntungan Max. -
Jumlah 16,165.00
Dibulatkan 16,160.00
A 099 1 M3 KUSEN KAYU KAMPER BANJARMASIN
Kayu kamper Banjar 1.1000 m³ 6,000,000.00 6,600,000
Paku 1.2500 kg 13,000.00 16,250
Lem Putih (FOX) 1.0000 kg 12,500.00 12,500
Pekerja terampil 4.0000 org 85,000.00 340,000
Tk. kayu terampil 15.5000 org 90,000.00 1,395,000
Kep. tukang kayu 2.7000 org 100,000.00 270,000
Mandor 0.5000 org 110,000.00 55,000
Jumlah 8,688,750.00
Keuntungan Max. -
Jumlah 8,688,750.00
Dibulatkan 8,688,750.00
A 100 1 M3 KUSEN KAYU BORNEO SUPER
Kayu Borneo Super 1.1000 m³ 3,000,000.00 3,300,000
Paku 1.2500 kg 13,000.00 16,250
Lem Putih (FOX) 1.0000 kg 12,500.00 12,500
Pekerja terampil 4.0000 org 85,000.00 340,000
Tk. kayu terampil 15.5000 org 90,000.00 1,395,000
Kep. tukang kayu 2.7000 org 100,000.00 270,000
Mandor 0.5000 org 110,000.00 55,000
Jumlah 5,388,750.00
Keuntungan Max. -
Jumlah 5,388,750.00
Dibulatkan 5,388,750.00
A 101 1 M3 KUSEN KAYU KAMPER MEDAN/ KRUING
Kayu Kamper Medan / Kruing 1.1000 m³ 6,000,000.00 6,600,000
Paku 1.2500 kg 13,000.00 16,250
Lem Putih (FOX) 1.0000 kg 12,500.00 12,500
Pekerja terampil 4.0000 org 85,000.00 340,000
Tk. kayu terampil 15.5000 org 90,000.00 1,395,000
Kep. tukang kayu 2.7000 org 100,000.00 270,000
Mandor 0.5000 org 110,000.00 55,000
Jumlah 8,688,750.00
Keuntungan Max. -
Jumlah 8,688,750.00
Dibulatkan 8,688,750.00
A 102 1 M3 KUSEN KAYU KAMPER SAMARINDA
Kayu kamper Samarinda 1.1000 m³ 9,000,000.00 9,900,000
Paku 1.2500 kg 13,000.00 16,250
Lem Putih (FOX) 1.0000 kg 12,500.00 12,500
Pekerja terampil 4.0000 org 85,000.00 340,000
Tk. kayu terampil 15.0000 org 90,000.00 1,350,000
Kep. tukang kayu 2.7000 org 100,000.00 270,000
Mandor 0.5000 org 110,000.00 55,000
Jumlah 11,943,750.00
Keuntungan Max. -
Jumlah 11,943,750.00
Dibulatkan 11,943,750.00
91
Dibulatkan 436,180.00
A 113 1 M2 DAUN PINTU TRIPLEK LAPIS SENG PLAT (KM/WC)
Rangka kayu kamper Medan 0.0150 m³ 6,000,000.00 90,000
Triplek 4 mm (ukuran pintu) 2.0000 lbr 36,500.00 73,000
Seng plat BJLS 30 1.8000 m2 19,400.00 34,920
Paku triplek 0.2000 kg 13,000.00 2,600
Lem putih (FOX) 0.5000 kg 12,500.00 6,250
Lem kuning (Aicabon) 1.0000 kg 14,100.00 14,100
Pekerja setengah terampil 0.3000 org 80,000.00 24,000
Tk. kayu terampil 1.3000 org 90,000.00 117,000
Kep. tukang kayu 0.1300 org 100,000.00 13,000
Mandor 0.0130 org 110,000.00 1,430
Jumlah 376,300.00
Keuntungan Max. -
Jumlah 376,300.00
Dibulatkan 376,300.00
A 114 1 SET DAUN PINTU PVC KM/WC
Pintu PVC 1.0000 bh 275,000 275,000
Pekerja Terampil 0.2000 org 85,000.00 17,000
Kepala Tukang Kayu 0.1520 org 100,000.00 15,200
Mandor 0.0200 org 110,000.00 2,200
Jumlah 309,400.00
Keuntungan Max. -
Jumlah 309,400.00
Dibulatkan 309,400.00
A 115 1 M2 DAUN JENDELA KACA (TANPA KACA)
Rangka kayu kamper Medan 0.0170 m³ 6,000,000.00 102,000
Lem Putih (FOX) 0.3000 kg 12,500.00 3,750
List Kayu 4.0000 m1 10,600.00 42,400
Pekerja setengah terampil 0.3000 org 80,000.00 24,000
Tk. kayu terampil 1.2000 org 90,000.00 108,000
Kep. tukang kayu 0.1200 org 100,000.00 12,000
Mandor 0.0200 org 110,000.00 2,200
Jumlah 294,350.00
Keuntungan Max. -
Jumlah 294,350.00
Dibulatkan 294,350.00
A 116 1 M2 DAUN PINTU KACA (TANPA KACA)
Rangka Kayu Kamper Medan 0.0200 m³ 6,000,000.00 120,000
Lem putih (FOX) 0.6000 kg 12,500.00 7,500
List Kayu 4.0000 m1 10,600.00 42,400
Pekerja setengah terampil 0.4000 org 80,000.00 32,000
Tk. kayu terampil 1.4000 org 90,000.00 126,000
Kep. tukang kayu 0.1400 org 100,000.00 14,000
Mandor 0.0140 org 110,000.00 1,540
Jumlah 343,440.00
Keuntungan Max. -
Jumlah 343,440.00
Dibulatkan 343,440.00
A 117 1 M2 DAUN PINTU / JENDELA JALUSI
Rangka kayu kamper Medan 0.0170 m³ 6,000,000.00 102,000
Lem putih (FOX) 0.3000 kg 12,500.00 3,750
Jalusi kayu Kamper Medan ( 1 m2 = 15 m1 ) 0.0225 m³ 6,000,000.00 135,000
List Kayu 4.0000 m1 10,600.00 42,400
Pekerja setengah terampil 0.7000 org 80,000.00 56,000
Tk. kayu terampil 1.8000 org 90,000.00 162,000
Kep. tukang kayu 0.2600 org 100,000.00 26,000
Mandor 0.0150 org 110,000.00 1,650
Jumlah 528,800.00
Keuntungan Max. -
Jumlah 528,800.00
Dibulatkan 528,800.00
94
PEKERJAAN PLESTERAN
A 118 1 M2 ACIAN PC
P.C (50 kg) 0.0800 zak 70,000.00 5,600
Pekerja setengah trampil 0.1430 org 80,000.00 11,440
Tk. batu setengah trampil 0.1070 org 80,000.00 8,560
Kep. Tukang batu 0.0105 org 100,000.00 1,050
Mandor 0.0100 org 110,000.00 1,100
Jumlah 27,750.00
Dibulatkan 27,750.00
A 119 1 M2 PLESTERAN DINDING 1 : 2 + ACIAN
P.C (50 kg) 0.2368 zak 70,000.00 16,576
Pasir pasang 0.0190 m³ 220,000.00 4,180
Pekerja setengah trampil 0.1250 org 80,000.00 10,000
Tk. batu setengah trampil 0.1000 org 80,000.00 8,000
Kep. Tukang batu 0.0210 org 100,000.00 2,100
Mandor 0.0200 org 110,000.00 2,200
Jumlah 43,056.00
Keuntungan Max. -
Jumlah 43,056.00
Dibulatkan 43,050.00
A 120 1 M2 PLESTERAN DINDING 1 : 3 + ACIAN
P.C (50 kg) 0.1750 zak 70,000.00 12,250
Pasir pasang 0.0190 m³ 220,000.00 4,180
Pekerja setengah trampil 0.1250 org 80,000.00 10,000
Tk. batu setengah trampil 0.1000 org 80,000.00 8,000
Kep. Tukang batu 0.0210 org 100,000.00 2,100
Mandor 0.0200 org 110,000.00 2,200
Jumlah 38,730.00
Keuntungan Max. -
Jumlah 38,730.00
Dibulatkan 38,730.00
A 121 1 M2 PLESTERAN DINDING 1 : 4 + ACIAN
P.C (50 kg) 0.2000 zak 70,000.00 14,000
Pasir pasang 0.0227 m³ 190,000.00 4,313
Pekerja setengah trampil 0.1250 org 80,000.00 10,000
Tk. batu setengah trampil 0.1000 org 80,000.00 8,000
Kep. Tukang batu 0.0250 org 100,000.00 2,500
Mandor 0.0200 org 110,000.00 2,200
Jumlah 41,013.00
Dibulatkan 41,010.00
A 122 1 M2 PLESTERAN DINDING 1 : 5 + ACIAN
P.C (50 kg) 0.1000 zak 70,000.00 7,000
Pasir pasang 0.0190 m³ 220,000.00 4,180
Pekerja setengah trampil 0.1250 org 80,000.00 10,000
Tk. batu setengah trampil 0.1000 org 80,000.00 8,000
Kep. Tukang batu 0.0210 org 100,000.00 2,100
Mandor 0.0200 org 110,000.00 2,200
Jumlah 33,480.00
Keuntungan Max. -
Jumlah 33,480.00
Dibulatkan 33,480.00
PEKERJAAN LANGIT-LANGIT
A 123 1 M2 PAS. PLAFOND TRIPLEK 6 MM BERIKUT RANGKA K-BANJAR
Triplek 6 mm 0.3470 lbr 73,000.00 25,331
Kaso-kaso 5/7 banjar 0.0140 m³ 6,000,000.00 84,000
Kayu 5/10 Banjar 0.0070 m³ 6,000,000.00 42,000
Paku 0.2200 kg 13,000.00 2,860
Pekerja setengah terampil 0.2800 org 80,000.00 22,400
Tk. kayu terampil 0.2000 org 90,000.00 18,000
Kep. tukang kayu 0.0800 org 100,000.00 8,000
Mandor 0.0140 org 110,000.00 1,540
Jumlah 204,131.00
Keuntungan Max. -
Jumlah 204,131.00
Dibulatkan 204,130.00
95
Dibulatkan 142,860.00
A 135 1 M2 LANTAI KERAMIK VIVAS PERLA
Keramik 30 x 30 VIVAS PERLA ex. Roman 1.0100 m² 81,000.00 81,810
P.C (50 kg) 0.1600 zak 70,000.00 11,200
Pasir pasang 0.0300 m³ 280,000.00 8,400
Semen warna 0.0130 kg 12,000.00 156
Pekerja trampil 0.1875 org 85,000.00 15,938
Tk. batu trampil 0.3750 org 85,000.00 31,875
Kep. Tukang batu 0.0750 org 120,000.00 9,000
Mandor 0.0188 org 175,000.00 3,290
Jumlah 161,668.50
Dibulatkan 161,650.00
A 136 1 M2 LANTAI SERENITY
Keramik 20 x 40 Sereniti ex. Roman 1.0100 m² 89,600.00 90,496
P.C (50 kg) 0.1600 zak 70,000.00 11,200
Pasir pasang 0.0300 m³ 280,000.00 8,400
Semen warna 0.0130 kg 12,000.00 156
Pekerja trampil 0.1875 org 85,000.00 15,938
Tk. batu trampil 0.3750 org 85,000.00 31,875
Kep. Tukang batu 0.0750 org 120,000.00 9,000
Mandor 0.0188 org 175,000.00 3,290
Jumlah 170,354.50
Dibulatkan 170,350.00
A 139 1 M2 LANTAI WHITE ONYX UKURAN 60 x 60
Keramik 60 x 60 White Onyx ex.Indogress 1.0000 m² 285,000.00 285,000
P.C (50 kg) 0.2600 zak 70,000.00 18,200
Pasir pasang 0.0300 m³ 220,000.00 6,600
Campuran kedap air 1.0000 lot 12,000.00 12,000
Pekerja trampil 0.4000 org 85,000.00 34,000
Kep. Tukang batu 0.0500 org 100,000.00 5,000
Mandor 0.0250 org 110,000.00 2,750
Alat bantu 0.0240 lot 363,550.00 8,725
Jumlah 372,275.20
Dibulatkan 372,275.00
A 140 1 M2 LANTAI GRANITO TILE ESSENZA UKURAN 40 x 40 POLISHED
Granito Tile Essenza 40 x 40 Polished 1.0000 m² 343,000.00 343,000
P.C (50 kg) + Campuran khusus 0.2600 zak 70,000.00 18,200
Pasir pasang 0.0300 m³ 220,000.00 6,600
Campuran kedap air 1.0000 lot 12,000.00 12,000
Pekerja trampil 0.2500 org 85,000.00 21,250
Tk. batu trampil 0.6000 org 90,000.00 54,000
Kep. Tukang batu 0.0500 org 100,000.00 5,000
Mandor 0.0250 org 110,000.00 2,750
Alat bantu 0.0240 lot 462,800.00 11,107
Jumlah 473,907.20
Keuntungan Max. -
Jumlah 473,907.20
Dibulatkan 473,900.00
A 141 1 M2 LANTAI MARMER EX LAMPUNG UKURAN BESAR
Marmer Ex Lampung 1.0000 m² 275,000.00 275,000
P.C (50 kg) + Campuran khusus 0.2600 zak 70,000.00 18,200
Pasir pasang 0.0300 m³ 220,000.00 6,600
Campuran kedap air 1.0000 lot 12,000.00 12,000
Pekerja trampil 0.5000 org 85,000.00 42,500
Tk. batu trampil 1.5000 org 90,000.00 135,000
Kep. Tukang batu 0.0500 org 100,000.00 5,000
Mandor 0.0250 org 110,000.00 2,750
Alat bantu 0.0320 lot 497,050.00 15,906
Jumlah 512,955.60
Keuntungan Max. -
Jumlah 512,955.60
Dibulatkan 512,950.00
98
Jumlah 23,844.70
Dibulatkan 23,840.00
A 158 1 M2 PENGECATAN DINDING AQUAPROOF (3x)
Cat tembok Aquaproof 0.3330 kg 42,000.00 13,986
Rol cat 0.0100 bh 17,500.00 175
Ampelas Halus 0.5000 lbr 12,000.00 6,000
Kep. tukang cat 0.0300 org 95,000.00 2,850
Mandor 0.0100 org 110,000.00 1,100
Steger Werk 0.0450 lot 24,111.00 1,085
Jumlah 25,196.00
Dibulatkan 25,190.00
A 157 1 M2 PENGECATAN DINDING INTERIOR
Cat tembok Ex-Dulux V gloss 0.0333 lt 86,000.00 2,867
Cat dasar sebelum pengecatan 0.0333 lt 85,000.00 2,833
Rol cat 0.0260 bh 27,800.00 723
Ampelas Halus 0.5000 lbr 1,200.00 600
Pekerja setengah terampil 0.0500 org 85,000.00 4,250
Tk. cat setengah terampil 0.0400 org 95,000.00 3,800
Kep. tukang cat 0.0400 org 95,000.00 3,800
Mandor 0.0250 org 110,000.00 2,750
Steger Werk 0.0600 lot 21,622.80 1,297
Jumlah 22,920.17
Dibulatkan 22,920.00
A 159 1 M2 PENGECATAN PLAFOND VINILEX (3x)
Cat tembok Vinilex 0.0333 kg 17,400.00 580
Plamir tembok 0.0333 kg 23,000.00 767
Rol cat 0.0200 bh 17,500.00 350
Ampelas Halus 0.2500 lbr 12,000.00 3,000
Pekerja setengah terampil 0.0500 org 80,000.00 4,000
Tk. cat setengah terampil 0.0400 org 95,000.00 3,800
Kep. tukang cat 0.0300 org 95,000.00 2,850
Mandor 0.0100 org 110,000.00 1,100
Steger Werk 0.0600 lot 16,446.67 987
Jumlah 17,433.47
Dibulatkan 17,430.00
A 160 1 M2 PENGECATAN DINDING SANLEX (3x)
Cat tembok Sanlex 0.1750 kg 10,000.00 1,750
Plamir tembok 0.1600 kg 23,000.00 3,680
Rol cat 0.0100 bh 17,500.00 175
Ampelas Halus 0.5000 lbr 12,000.00 6,000
Pekerja setengah terampil 0.1040 org 80,000.00 8,320
Tk. cat setengah terampil 0.1820 org 95,000.00 17,290
Kep. tukang cat 0.0195 org 95,000.00 1,853
Mandor 0.0100 org 110,000.00 1,100
Steger Werk 0.0450 lot 40,167.50 1,808
Jumlah 41,975.04
Keuntungan Max. -
Jumlah 41,975.04
Dibulatkan 41,970.00
A 161 1 M2 PENGECATAN PLAFOND SANLEX (3x)
Cat tembok Sanlex 0.2000 kg 10,000.00 2,000
Plamir tembok 0.1600 kg 23,000.00 3,680
Rol cat 0.0100 bh 17,500.00 175
Steger Werk 1.0000 lot 862.50 863
Ampelas Halus 0.5000 lbr 12,000.00 6,000
Pekerja setengah terampil 0.1040 org 80,000.00 8,320
Tk. cat setengah terampil 0.1820 org 95,000.00 17,290
Kep. tukang cat 0.0195 org 95,000.00 1,853
Mandor 0.0100 org 110,000.00 1,100
Jumlah 41,280.00
Keuntungan Max. -
Jumlah 41,280.00
Dibulatkan 41,280.00
A 162 1 M2 PENGECATAN KAYU (3X) BERIKUT MENI
Meni kayu 0.1670 kg 22,000.00 3,674
Plamir kayu 0.0830 kg 23,000.00 1,909
102
Keuntungan Max. -
Jumlah 18,925.00
Dibulatkan 18,920.00
A 174 1 BH PASANG SAKLAR TUNGGAL EX BROCO
Saklar Tunggal Ex Broco 1.0000 bh 17,600 17,600
Pekerja 0.0350 org 75,000.00 2,625
Mandor 0.0800 org 110,000.00 8,800
Jumlah 29,025.00
Keuntungan Max. -
Jumlah 29,025.00
Dibulatkan 29,020.00
A 175 1 BH PASANG STOP KONTAK TUNGGAL EX BROCO
Stop Kontak Ex Broco 1.0000 bh 19,000 19,000
Pekerja 0.0350 org 75,000.00 2,625
Mandor 0.0800 org 110,000.00 8,800
Jumlah 30,425.00
Keuntungan Max. -
Jumlah 30,425.00
Dibulatkan 30,420.00
A 176 1 TITIK INSTALASI PENERANGAN
Instalasi Penerangan 0.8000 ttk 110,200 88,160
Pekerja Terampil 0.2000 org 85,000.00 17,000
Mandor 0.1000 org 110,000.00 11,000
Jumlah 116,160.00
Keuntungan Max. -
Jumlah 116,160.00
Dibulatkan 116,160.00
PEKERJAAN JALAN DAN PAVING BLOK
A 177 1 M2 PAS. ONDERLAG BATU BELAH T = 20 CM
Pasir pasang 0.1500 m³ 220,000.00 33,000
Batu Belah 0.2500 m³ 228,000.00 57,000
Pekerja Trampil (Gali + Urug + Ampar) 0.1500 org 85,000.00 12,750
Peralatan 0.1200 lot 102,750.00 12,330
Jumlah 115,080.00
Keuntungan Max. -
Jumlah 115,080.00
Dibulatkan 115,080.00
A 178 1 M2 AMPARAN BATU PECAH MESIN 5/7 t=10 cm
Batu Pecah Mesin 5/7 0.1200 m³ 225,000.00 27,000
Pekerja Trampil (Gali + Urug + Ampar) 0.1100 org 85,000.00 9,350
Peralatan 0.3200 lot 36,350.00 11,632
Jumlah 47,982.00
Keuntungan Max. -
Jumlah 47,982.00
Dibulatkan 47,980.00
A 179 1 M2 AMPARAN BATU PECAH MESIN 2/3 t=5 cm
Batu Pecah Mesin 2/3 0.0600 m³ 275,000.00 16,500
Pekerja Trampil (Gali + Urug + Ampar) 0.0800 org 85,000.00 6,800
Peralatan 0.5000 lot 23,300.00 11,650
Jumlah 34,950.00
Keuntungan Max. -
Jumlah 34,950.00
Dibulatkan 34,950.00
A 180 1 M2 LAPISAN PENGISI /PENUTUP
Batu pecah mesin 1/2 0.0120 m³ 220,000.00 2,640
Pasir Beton 0.0100 m³ 210,000.00 2,100
Pekerja Trampil (Gali + Urug + Ampar) 0.0500 org 85,000.00 4,250
Peralatan 0.9500 lot 8,990.00 8,541
Jumlah 17,530.50
Keuntungan Max. -
Jumlah 17,530.50
Dibulatkan 17,530.00
A 181 1 M2 PENGASPALAN MANUAL
Batu abu /pasir beton 0.0050 m³ 210,000.00 1,050
Aspal 4.0000 kg 6,000.00 24,000
Kayu Bakar 0.0300 m³ 70,200.00 2,106
105
Dibulatkan 21,680.00
A 205 1 M2 GRANITE TILE 60x60 cm ex CINA
Granite tile 60x60 cm ex CINA 1.0100 m² -
Semen PC 6.0000 kg -
Pasir pasang 0.0250 m³ -
Semen warna 0.2000 kg -
Pekerja 0.1000 org 75,000.00 7,500
Tk. batu 0.2000 org 90,000.00 18,000
Mandor 0.0125 org 110,000.00 1,375
Jumlah 25,500.00
Keuntungan Max. -
Jumlah 25,500.00
Dibulatkan 25,500.00
A 206 1 M2 Partisi Gypsum t=9 mm ex. Jayaboard + Rangka Hollow 50x50, t =1,2 mm (2 sisi)
hollow 50 x 50 2.6400 m'
hollow 40 x 40 1.3200 m'
Paku rivet 4.0000 bh
Sekrup 6x1-1,5 8.0000 bh
Gypsumboard 120x240 cm 12 mm 1.0286 lbr
Textile tape 0.2400 roll
Compound gypsum 0.1200 zak
Sekrup gypsum 24.0000 bh
Amplas 0.5000 lbr -
Pekerja 0.1000 oh -
Tukang Gypsum 0.2000 oh 90,000.00 18,000
Kepala Tukang 0.0200 oh 100,000.00 2,000
Mandor 0.0500 oh 110,000.00 5,500
Jumlah 25,500.00
Keuntungan Max. -
Jumlah 25,500.00
Dibulatkan 25,500.00
A 207 1 M1 Plint Kayu kamper fin. Duco, h=10 cm.
Lem putih ( FOX ) 0.1000 kg -
paku , skup , etc 0.1000 ls -
List kayu profil 10 cm 1.2000 m1 -
finish duco 1.0000 m1 -
Upah kerja 0.2500 ls -
Jumlah -
Keuntungan Max. -
Jumlah -
Dibulatkan -
A 208 1M2 Gypsum 9 mm ex Jayaboard + Rangka Hollow & penggantung
Gypsum ex. Jayaboard 0.3788 lbr
rangka hollow 1.0000 btg
Paku + skrup gypsum 0.2000 kg
kompone dll 0.7500 ls
Pekerja 0.2000 org
Tk. Gypsum 0.1250 org
Mandor 0.0100 org
Jumlah -
Keuntungan Max. -
Jumlah -
Dibulatkan -
A 209 1M2 GRC 4 mm ex Jayaboard + Rangka Hollow & penggantung
GRC board 0.3788 lbr 71,000.00 26,894
rangka hollow 1.0000 btg -
Paku + skrup gypsum 0.2000 kg -
kompone dll 0.5000 ls -
Pekerja 0.2000 org -
Tk. Gypsum 0.1500 org -
Mandor 0.0200 org -
Jumlah 26,893.94
Keuntungan Max. -
Jumlah 26,893.94
Dibulatkan 26,890.00
A 210 1M2 Pengecatan Dinding dasar sealer
110
Semen PC 150.0000 kg
Pasir Pasang 0.4400 m³
Pekerja 1.2500 org
Tk.batu 0.5000 org
Jumlah -
Keuntungan Max. -
Jumlah -
Dibulatkan -
A 218 1M3 Cor Beton K-225 ReadyMix
Beton K-250 Readymix 1.0000 m³
Pekerja 1.2500 org
Tk.batu 0.1000 org
Mandor 0.0100 org
Jumlah -
Keuntungan Max. -
Jumlah -
Dibulatkan -
A 219 1M3 Pek. Bekisting pas. Bataco
Bataco 22.0000 bh
Pekerja 0.2000 org
Tk. batu 0.1500 org
Mandor 0.0050 org
Jumlah -
Keuntungan Max. -
Jumlah -
Dibulatkan -
A 220
Besi Beton rata - rata 1.1000 kg
Kawat Beton 0.0200 kg
Pekerja 0.0100 org
Tk. Besi Beton terampil 0.0200 org
Mandor 0.0010 org
Jumlah -
Keuntungan Max. -
Jumlah -
Dibulatkan -
A 221
Peralatan, Spancer 0.0100 lot
Pekerja 0.2000 org
Tk. batu 0.1500 org
Mandor 0.0050 org
Jumlah -
Keuntungan Max. -
Jumlah -
Dibulatkan -
A 222
Pekerja terampil 0.0500 org
Tk. Besi Beton terampil 0.0200 org
Mandor 0.0100 org
Jumlah -
Keuntungan Max. -
Jumlah -
Dibulatkan -
A 223 1M2 Pek. Waterproofing
Waterproofing ex. Sika 1.1000 m2 65,000.00 71,500
Pekerja 0.0500 org 75,000.00 3,750
Mandor 0.0400 org 110,000.00 4,400
Jumlah 79,650.00
Dibulatkan 79,650.00
A 224 1M2 Pek. Screeding
Semen PC 10.0000 kg
Pasir pasang 0.0750 m³
Ram kawat 1.0000 m2
Pekerja 0.2500 org
Tk. batu 0.1500 org
Mandor 0.0100 org
112
Jumlah -
Keuntungan Max. -
Jumlah -
Dibulatkan -
A 225 1M3 Lapisan Sirdam setebal 40 cm padat, CBR=50 % di bawah :
Sirtu 1.1000 m³
Pekerja 0.2500 org
Mandor 0.0500 org
Pemadatan tanah dengan vibro 2.5000 lot
Jumlah -
Keuntungan Max. -
Jumlah -
Dibulatkan -
PEKERJAAN KACA, PINTU, JENDELA DAN AKSESORIS
A 205 PINTU KACA DAN AKSESORIS (FR 1A)
Kaca Tempered 12mm Clear 13.0500 m² 513,000.00 6,694,650
Gosok Halus 35.7000 m1 15,000.00 535,500
Melubangi kaca' 11.0000 ttk 25,000.00 275,000
Mencoak Kaca 8.0000 ttk 55,000.00 440,000
Sealant 17.8500 m1 3,500.00 62,475
Alumunium U 2cm 10.3500 m1 17,500.00 181,125
Pull Handle SS Hairlaine Type PH 802, 38x1200 PPS+SSS 2.0000 psg 1,313,000.00 2,626,000
Floor Hinge BTS 80 3x. DORMA 2.0000 psc 4,811,400.00 9,622,800
Path Fitting. Top PT 40 PSS Cover 2.0000 pcs 1,144,425.00 2,288,850
Path Fitting. Top PT 20 PSS Cover 2.0000 pcs 623,700.00 1,247,400
Bottom Fitting PT 10 PSS Cover 2.0000 pcs 523,700.00 1,047,400
Corner Lock Path US 20+ Cyliner Ex. Dorma 2.0000 pcs 1,247,400.00 2,494,800
Pekerja trampil 1.5000 org 85,000.00 127,500
Tk. trampil 1.5000 org 80,000.00 120,000
Kep. Tukang 0.2000 org 100,000.00 20,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.2500 lot 1,250,000.00 312,500
Jumlah 28,107,000.00
Keuntungan Max. -
Jumlah 28,107,000.00
Dibulatkan 28,107,000.00
A 206 KACA FRAMELESS (FR 1B)
Kaca Tempered 12mm Clear 13.0500 m² 513,000.00 6,694,650
Gosok Halus 20.7000 m1 15,000.00 310,500
Sealant 20.7000 m1 3,500.00 72,450
Alumunium U 2cm 14.7000 m1 17,500.00 257,250
Pekerja trampil 1.5000 org 100,000.00 150,000
Tk. trampil 1.5000 org 80,000.00 120,000
Kep. Tukang 0.2000 org 100,000.00 20,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.2500 lot 1,250,000.00 312,500
Jumlah 7,948,350.00
Keuntungan Max. -
Jumlah 7,948,350.00
Dibulatkan 7,948,350.00
A 207 KACA FRAMELESS (FR 2)
Kaca Tempered 12mm Clear 12.1500 m² 513,000.00 6,232,950
Gosok Halus 20.1000 m1 15,000.00 301,500
Sealant 20.1000 m1 3,500.00 70,350
Alumunium U 2cm 14.1000 m1 17,500.00 246,750
Pekerja trampil 1.5000 org 100,000.00 150,000
Tk. trampil 1.5000 org 80,000.00 120,000
Kep. Tukang 0.2000 org 100,000.00 20,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.2500 lot 1,250,000.00 312,500
Jumlah 7,465,050.00
Keuntungan Max. -
Jumlah 7,465,050.00
Dibulatkan 7,465,050.00
A 208 PINTU KACA DAN AKSESORIS (FR 3)
Kaca Tempered 12mm Clear 11.8300 m² 513,000.00 6,068,790
113
Keuntungan Max. -
Jumlah 16,939,990.00
Dibulatkan 16,939,990.00
A 214 KACA FRAMELESS (FR 10)
Kaca Tempered 12mm Clear 14.4200 m² 513,000.00 7,397,460
Gosok Halus 21.5000 m1 15,000.00 322,500
Sealant 21.5000 m1 3,500.00 75,250
Alumunium U 2cm 15.9000 m1 17,500.00 278,250
Pekerja trampil 0.5000 org 100,000.00 50,000
Tk. trampil 0.5000 org 80,000.00 40,000
Kep. Tukang 0.1000 org 100,000.00 10,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.1000 lot 1,250,000.00 125,000
Jumlah 8,309,460.00
Keuntungan Max. -
Jumlah 8,309,460.00
Dibulatkan 8,309,460.00
A 215 KACA FRAMELESS (FR 11)
Kaca Tempered 12mm Clear 12.1800 m² 513,000.00 6,248,340
Gosok Halus 19.9000 m1 15,000.00 298,500
Sealant 19.9000 m1 3,500.00 69,650
Alumunium U 2cm 14.3000 m1 17,500.00 250,250
Pekerja trampil 0.5000 org 100,000.00 50,000
Tk. trampil 0.5000 org 80,000.00 40,000
Kep. Tukang 0.1000 org 100,000.00 10,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.1000 lot 1,250,000.00 125,000
Jumlah 7,102,740.00
Keuntungan Max. -
Jumlah 7,102,740.00
Dibulatkan 7,102,740.00
A 216 KACA FRAMELESS (FR 12)
Kaca Tempered 12mm Clear 11.3400 m² 513,000.00 5,817,420
Gosok Halus 19.3000 m1 15,000.00 289,500
Sealant 19.3000 m1 3,500.00 67,550
Alumunium U 2cm 13.7000 m1 17,500.00 239,750
Pekerja trampil 0.5000 org 100,000.00 50,000
Tk. trampil 0.5000 org 80,000.00 40,000
Kep. Tukang 0.1000 org 100,000.00 10,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.1000 lot 1,250,000.00 125,000
Jumlah 6,650,220.00
Keuntungan Max. -
Jumlah 6,650,220.00
Dibulatkan 6,650,220.00
A 217 KACA FRAMELESS (FR 12B)
Kaca Tempered 12mm Clear 0.2535 m² 513,000.00 130,046
Gosok Halus 3.3380 m1 15,000.00 50,070
Sealant 3.3380 m1 3,500.00 11,683
Alumunium U 2cm 3.3380 m1 17,500.00 58,415
Pekerja trampil 0.5000 org 100,000.00 50,000
Tk. trampil 0.5000 org 80,000.00 40,000
Kep. Tukang 0.1000 org 100,000.00 10,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.1000 lot 1,250,000.00 125,000
Jumlah 486,213.50
Keuntungan Max. -
Jumlah 486,213.50
Dibulatkan 486,210.00
A 218 PINTU MULTIPLEKS LAPIS HPL KUSEN ALM (P4)
Rangka Alumunium 3" Silver Anodize ex. Alexindo 7.0000 m1 75,000.00 525,000
Kaca Clear Glass h=6mm 0.5396 m1 115,000.00 62,054
Karet Kaca 4.5840 m1 5,000.00 22,920
Pintu Multipleks Lapis MDF + HPL ex. Taco 1.0000 unit 2,026,000.00 2,026,000
Hinge ESS 4x3x3mm 4BB ex. Dekson 1.0000 set 188,000.00 188,000
Lockcase dan Cylinder ex. Dekson 1.0000 set 150,000.00 150,000
116
Handle type LHSR 0058 SSS ex. Dekson 1.0000 set 480,000.00 480,000
Door stopper DKS 886 SN ex. Dekson 1.0000 set 35,000.00 35,000
Pekerja trampil 0.5000 org 100,000.00 50,000
Tk. Trampil Kayu 0.5000 org 80,000.00 40,000
Kep. Tukang Kayu 0.1000 org 100,000.00 10,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.1000 lot 1,250,000.00 125,000
Jumlah 3,724,974.00
Dibulatkan 4,624,000.00
A 219 PINTU MULTIPLEKS LAPIS HPL KUSEN ALM (P5)
Rangka Alumunium 3" Silver Anodize ex. Alexindo 7.4000 m² 75,000.00 555,000
Kaca Clear Glass h=6mm 0.4692 m1 115,000.00 53,958
Karet Kaca 2.9600 m1 5,000.00 14,800
Pintu Multipleks Lapis MDF + HPL ex. Taco 1.0000 unit 2,026,000.00 2,026,000
Hinge ESS 4x3x3mm 4BB ex. Dekson 1.0000 set 188,000.00 188,000
Lockcase dan Cylinder ex. Dekson 1.0000 set 150,000.00 150,000
Handle type LHSR 0058 SSS ex. Dekson 1.0000 set 480,000.00 480,000
Door stopper DKS 886 SN ex. Dekson 1.0000 set 35,000.00 35,000
Pekerja trampil 0.5000 org 100,000.00 50,000
Tk. Trampil Kayu 0.5000 org 80,000.00 40,000
Kep. Tukang Kayu 0.1000 org 100,000.00 10,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.1000 lot 1,250,000.00 125,000
Jumlah 3,738,758.00
Dibulatkan 4,638,000.00
A 220 PINTU UPVC (P3)
Rangka Kusen dan pintu UPVC 1.0000 unit 1,250,000.00 1,250,000
Jalusi UPVC 1.0000 unit 70,000.00 70,000
Karet Kaca 5.0000 m1 5,000.00 25,000
Aksesoris 1.0000 set 30,000.00 30,000
Pekerja trampil 1.5000 org 100,000.00 150,000
Tk. Trampil 1.0000 org 80,000.00 80,000
Kep. Tukang 0.1000 org 100,000.00 10,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.0250 lot 1,250,000.00 31,250
Jumlah 1,657,250.00
Dibulatkan 1,657,250.00
A 221 PINTU MULTIPLEKS LAPIS HPL KUSEN ALM (P4)
Rangka Alumunium 3" Silver Anodize ex. Alexindo 7.0000 m² 78,000.00 546,000
Kaca Clear Glass h=6mm 0.3772 m1 115,000.00 43,378
Karet Kaca 2.5600 m1 5,000.00 12,800
Pintu Multipleks Lapis MDF + HPL ex. Taco 1.0000 unit 2,026,000.00 2,026,000
Hinge ESS 4x3x3mm 4BB ex. Dekson 1.0000 set 188,000.00 188,000
Lockcase dan Cylinder ex. Dekson 1.0000 set 150,000.00 150,000
Handle type SP 003 HDL + CYL Hole SSS & SP 002CYL SSS ex.1.0000
Dekson set 700,000.00 700,000
Door stopper DKS 886 SN ex. Dekson 1.0000 set 35,000.00 35,000
Door Closser TS68 ex. Dekson 1.0000 set 720,000.00 720,000
Pekerja trampil 0.5000 org 100,000.00 50,000
Tk. Trampil Kayu 0.5000 org 80,000.00 40,000
Kep. Tukang Kayu 0.2000 org 100,000.00 20,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.1000 lot 1,250,000.00 125,000
Jumlah 4,667,178.00
Keuntungan Max. -
Jumlah 4,667,178.00
Dibulatkan 4,667,170.00
A 222 PINTU MULTIPLEKS LAPIS HPL KUSEN ALM (P5)
Rangka Alumunium 3" Silver Anodize ex. Alexindo 6.8000 m² 78,000.00 530,400
Kaca Clear Glass h=6mm 0.3312 m1 115,000.00 38,088
Karet Kaca 2.3600 m1 5,000.00 11,800
Pintu Multipleks Lapis MDF + HPL ex. Taco 1.0000 unit 2,026,000.00 2,026,000
Hinge ESS 4x3x3mm 4BB ex. Dekson 1.0000 set 188,000.00 188,000
Lockcase dan Cylinder ex. Dekson 1.0000 set 150,000.00 150,000
Handle type LHSR 0058 SSS ex. Dekson 1.0000 set 480,000.00 480,000
Door stopper DKS 886 SN ex. Dekson 1.0000 set 35,000.00 35,000
Pekerja trampil 0.5000 org 100,000.00 50,000
117
Handle type LHSR 0058 SSS ex. Dekson 1.0000 set 480,000.00 480,000
Door stopper DKS 886 SN ex. Dekson 1.0000 set 35,000.00 35,000
Pekerja trampil 0.5000 org 100,000.00 50,000
Tk. Trampil Kayu 0.5000 org 80,000.00 40,000
Kep. Tukang Kayu 0.2000 org 100,000.00 20,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.1000 lot 1,250,000.00 125,000
Jumlah 4,422,642.00
Dibulatkan 5,200,000.00
A 227 PINTU JENDELA KUSEN ALM (PJ-5)
Rangka Alumunium 3" Silver Anodize ex. Alexindo 11.3600 m1 75,000.00 852,000
Kaca Clear Glass h=6mm 1.8600 m2 115,000.00 213,900
Karet Kaca 21.0400 m1 5,000.00 105,200
Pintu Multipleks Lapis MDF + HPL ex. Taco 1.0000 unit 2,026,000.00 2,026,000
Hinge ESS 4x3x3mm 4BB ex. Dekson 1.0000 set 188,000.00 188,000
Lockcase dan Cylinder ex. Dekson 1.0000 set 150,000.00 150,000
Handle type LHSR 0058 SSS ex. Dekson 1.0000 set 480,000.00 480,000
Door stopper DKS 886 SN ex. Dekson 1.0000 set 35,000.00 35,000
Pekerja trampil 0.5000 org 100,000.00 50,000
Tk. Trampil Kayu 0.5000 org 80,000.00 40,000
Kep. Tukang Kayu 0.2000 org 100,000.00 20,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.1000 lot 1,250,000.00 125,000
Jumlah 4,296,100.00
Dibulatkan 5,078,000.00
A 228 PINTU JENDELA KUSEN ALM (PJ-6)
Rangka Alumunium 3" Silver Anodize ex. Alexindo 23.7800 m1 75,000.00 1,783,500
Kaca Clear Glass h=6mm 8.8150 m2 115,000.00 1,013,725
Karet Kaca 12.5917 m1 5,000.00 62,958
Pintu Multipleks Lapis MDF + HPL ex. Taco 1.0000 unit 2,026,000.00 2,026,000
Hinge ESS 4x3x3mm 4BB ex. Dekson 1.0000 set 188,000.00 188,000
Lockcase dan Cylinder ex. Dekson 1.0000 set 150,000.00 150,000
Handle type LHSR 0058 SSS ex. Dekson 1.0000 set 480,000.00 480,000
Door stopper DKS 886 SN ex. Dekson 1.0000 set 35,000.00 35,000
Pekerja trampil 0.5000 org 100,000.00 50,000
Tk. Trampil 0.5000 org 80,000.00 40,000
Kep. Tukang 0.2000 org 100,000.00 20,000
Mandor 0.1000 org 110,000.00 11,000
Alat bantu 0.1000 lot 1,250,000.00 125,000
Jumlah 5,985,183.40
Dibulatkan 6,767,000.00
A 229 PINTU JENDELA KUSEN ALM (PJ-7)
Rangka Alumunium 3" Silver Anodize ex. Alexindo 21.9600 m² 75,000.00 1,647,000.00
Kaca Clear Glass h=6mm 8.0840 m1 115,000.00 929,660.00
Karet Kaca 12.5917 m1 5,000.00 62,958.40
Pintu Multipleks Lapis MDF + HPL ex. Taco 1.0000 unit 2,026,000.00 2,026,000.00
Hinge ESS 4x3x3mm 4BB ex. Dekson 1.0000 set 188,000.00 188,000.00
Lockcase dan Cylinder ex. Dekson 1.0000 set 150,000.00 150,000.00
Handle type LHSR 0058 SSS ex. Dekson 1.0000 set 480,000.00 480,000.00
Door stopper DKS 886 SN ex. Dekson 1.0000 set 35,000.00 35,000.00
Pekerja trampil 0.5000 org 100,000.00 50,000.00
Tk. Trampil 0.5000 org 80,000.00 40,000.00
Kep. Tukang 0.2000 org 100,000.00 20,000.00
Mandor 0.1000 org 110,000.00 11,000.00
Alat bantu 0.1000 lot 1,250,000.00 125,000.00
Jumlah 5,764,618.40
Dibulatkan 6,547,000.00
A 300 PINTU JENDELA KUSEN ALM (PJ-8)
Rangka Alumunium 3" Silver Anodize ex. Alexindo 18.7250 m² 75,000.00 1,404,375.00
Kaca Clear Glass h=6mm 6.2100 m1 115,000.00 714,150.00
Karet Kaca 12.5917 m1 5,000.00 62,958.40
Pintu Multipleks Lapis MDF + HPL ex. Taco 1.0000 unit 2,026,000.00 2,026,000.00
Hinge ESS 4x3x3mm 4BB ex. Dekson 1.0000 set 188,000.00 188,000.00
Lockcase dan Cylinder ex. Dekson 1.0000 set 150,000.00 150,000.00
Handle type LHSR 0058 SSS ex. Dekson 1.0000 set 480,000.00 480,000.00
Door stopper DKS 886 SN ex. Dekson 1.0000 set 35,000.00 35,000.00
119
I PEKERJAAN PERSIAPAN
1 Biaya untuk Proyek Manajemen Kontraktor ( Site Management Cost ) ls 1.00 20,000,000 20,000,000
2 Mobilisasi & demobilisasi tenaga kerja dan peralatan ls 1.00 20,000,000 20,000,000
3 Pagar Sementara dari Seng H = 180 cm + Pintu m' 43.00 225,000 9,675,000
4 Penjagaan dan perawatan infrastruktur lingkungan akibat kegiatan proyek ls 1.00 10,000,000 10,000,000
5 Keamanan lapangan selama pekerjaan berlangsung ls 1.00 8,000,000 8,000,000
6 Listrik dan Air kerja berikut instalasinya ls 1.00 10,000,000 10,000,000
7 Asuransi ( C.A.R, ASTEK dan Personal Incident 2 person ) ls 1.00 10,000,000 10,000,000
8 Pembersihan lapangan termasuk membuang sampah keluar ls 1.00 10,000,000 10,000,000
9 Pembuatan gambar kerja (shop drawing) & gambar terlaksana ( as built drawing ) ls 1.00 5,000,000 5,000,000
10 Kantor direksi uk. 12m2 dan R Rapat uk. 16m2 berikut AC , perlengkapan kantor , ls 1.00 10,000,000 10,000,000
sambungan tilp/fax dan Toilet untuk direksi lapangan
11 Peralatan Pengaman dan APD (sepatu boot, helm, fire extinguiser , dsb) ls 1.00 8,000,000 8,000,000
12 Testing material & hasil pekerjaan yang diperlukan ls 1.00 5,000,000 5,000,000
13 Laporan Progres pekerjaan dilengkapi dengan dokumen photo , setiap minggu ls 1.00 5,000,000 5,000,000
14 Pekerjaan Pengukuran yang diperlukan selama proyek berlangsung ls 1.00 8,000,000 8,000,000
15 Kantor dan Gudang kontraktor sementara dan Los kerja , sesuai kebutuhan ls 1.00 10,000,000 10,000,000
16 Koordinasi Lingkungan dan Perijinan yang berkaitan dengan pelaksanaan diluar IMB ls 1.00 10,000,000 10,000,000
(mis : ijin inrit , dll)
II PEMATANGAN LAHAN
1 Pembersihan & stripping area lahan dari semak, rumput, alang-alang, pohon m2 1,122.00 2,000 2,244,000
termasuk bobokan pondasi/lantai existing pada posisi titik-titik pancang dan
pagar/dinding eksiting bangunan lama termasuk pondasinya
2 Pembuangan keluar bekas pembersihan Ls 1.00 10,000,000 10,000,000
3 Bongkar bangunan eksisting termasuk buang keluar puing bekas Ls 1.00 5,000,000 5,000,000
bongkaran sampai dengan siap dilaksanakan konstruksi
1 Dinding Penahan Batu kali (PB) sekaligus sebagai pondasi pagar/dinding sisi samping m3 151.52 581,700 88,136,276
kiri dan kanan termasuk pekerjaan galian, adukan 1:4
2 Sloof diatas batu kali beton 20x25 tulangan 4D16 sengkang D10-200 m1 155.40 185,000 28,749,000
temasuk bekisting
3 Urugan tanah untuk peninggian halaman dan lantai bangunan dengan CBR 6% m3 824.67 109,440 90,251,885
dan kepadatan 95%
1 PEKERJAAN STRUKTUR
1 Pile cap
P1 m3 1.30 949,170 1,231,833
P2 m
3
4.67 949,170 4,434,598
P2A m3 3.03 949,170 2,874,277
P2B m3 1.56 949,170 1,478,199
P2C m3 0.73 949,170 691,195
P2D m
3
1.18 949,170 1,122,337
P2E m
3
1.20 949,170 1,142,867
P2F m3 2.49 949,170 2,367,856
P3 m3 3.02 949,170 2,866,064
P4 m3 9.89 949,170 9,389,304
2 Tie Beam
Elv. -00.15
TB1 m3 14.51 949,170 13,776,254
TB2 m
3
16.25 949,170 15,423,984
TB3 m
3
28.68 949,170 27,222,039
TBA1 m3 3.39 949,170 3,213,434
4 Kolom
Kolom Pedestal lt. 1
Perhitungan kolom pedestal sudah termasuk kolom composite s/d elv. +01.05
- KP1 (50x50 cm) m
3
3.30 949,170 3,132,261
- KP1A (65.4x50 cm) m3 1.44 949,170 1,366,805
- KP1B (57.7x63.7 cm) m3 0.40 949,170 377,299
- KP1C (63.1x50 cm) m3 0.76 949,170 721,369
- KP2 (50x35 cm) m
3
0.40 949,170 379,668
- KP2A (52,5x50 cm) m
3
0.90 949,170 854,253
- KP2B (52,5x67,3 cm) m3 0.40 949,170 379,668
- KP2C (52,4x79,8 cm) m3 0.48 949,170 455,602
- KP3A (93,4x55 cm) m
3
0.59 949,170 560,010
- KP3B (80,7x55 cm) m
3
0.48 949,170 455,602
Kolom Composite lt. 1, tinggi = 3,13 m
- KP1 (50x50 cm) m3 9.39 949,170 8,912,706
- KP1A (65.4x50 cm) m3 4.09 949,170 3,882,105
- KP1B (57.7x63.7 cm) m3 1.15 949,170 1,091,546
- KP1C (63.1x50 cm) m
3
1.97 949,170 1,869,865
Kolom Composite lt. 3, tinggi = 3,67 m
- KP1 (50x50 cm) m3 11.01 949,170 10,450,646
- KP1A (65.4x50 cm) m3 4.84 949,170 4,598,131
- KP1B (57.7x63.7 cm) m
3
1.30 949,170 1,236,172
- KP1C (63.1x50 cm) m3 1.58 949,170 1,499,689
5 Kolom Praktis
- KPSA (17,5x50 cm) m3 1.84 949,170 1,745,097
- KPSB (17,5x63,1 cm) m3 0.77 949,170 733,708
- KPSC (17,5x78,9 cm) m3 0.97 949,170 917,847
- KPSD (63,4x55 cm) m3 2.44 949,170 2,318,153
- KPSE (50,7x55 cm) m
3
1.96 949,170 1,860,373
6 Balok
Balok Beton elv. +04.20
- BB2 (30x60) m3 3.94 949,170 3,735,680
- BB3 (25x60) m3 2.08 949,170 1,975,919
Balok Beton elv. +07.80
- BB1 (45x60) m3 1.11 949,170 1,055,857
7 Plat Lantai
129
a Lantai 1
- Plat beton lantai, t = 15 cm (S1) elev -00.30 m3 113.84 949,170 108,055,202
b Lantai 3
- Plat beton lantai, t = 12 cm (S2) elev. +04.05 m3
66.62 949,170 63,235,258
c Dak Utilitas
- Plat beton lantai, t = 12 cm (S2) elev. +07.82 m3 1.43 949,170 1,360,882
d Ground Water Tank
- Plat beton lantai, t = 15 cm elev -03.00 m m3 1.63 949,170 1,549,045
- Plat beton tepi, t = 15 cm m3 6.65 949,170 6,308,744
8 Tangga
-Tangga Showroom m3 2.60 949,170 2,471,639
-Tangga Bengkel m3 2.75 949,170 2,608,319
E PEKERJAAN BEKISTING
1 Pile cap
P1, besi D13, D16 kg 270.38 10,500 2,838,938
P2 , besi D13, besi D16 kg 734.91 10,500 7,716,503
P2A, besi D13, besi D16 kg 468.65 10,500 4,920,825
P2b, besi D13, D16 kg 244.97 10,500 2,572,168
P2c, besi D13, D16 kg 131.23 10,500 1,377,894
P2d, besi D16 kg 193.73 10,500 2,034,187
P2e, besi D16 kg 189.18 10,500 1,986,366
P2F, besi D16 kg 401.75 10,500 4,218,379
P3, besi D13, besi D16 kg 385.05 10,500 4,043,026
P4, besi D13, besi D16 kg 1,208.20 10,500 12,686,055
2 Tie Beam
TB1 (35x75 cm) , D10, D13, D19 kg 2,079.72 10,500 21,837,082
TB2 (30x65 cm) , D10, D19 kg 2,718.82 10,500 28,547,560
TB3 (30x50 cm) , D10, D19 kg 6,225.87 10,500 65,371,602
TBA1 (25x45 cm) , D10 , D19 kg 692.17 10,500 7,267,836
4 Kolom
Kolom Pedestal lt. 1
Perhitungan kolom pedestal sudah termasuk kolom composite s/d elv. +01.05
- KP1 (50x50 cm), D10, D19 kg 1,372.81 10,500 14,414,477
- KP1A (65.4x50 cm) , D10, D19 kg 446.41 10,500 4,687,351
- KP1B (57.7x63.7 cm) , D10, D19 kg 81.60 10,500 856,763
- KP1C (63.1x50 cm) , D10, D19 kg 221.32 10,500 2,323,834
- KP2 (50x35 cm) , D10, D16 kg 63.13 10,500 662,820
- KP2A (52,5x50 cm) , besi D10, D16 kg 101.86 10,500 1,069,548
- KP2B (52,5x67,3 cm) , besi D10, D16 kg 57.79 10,500 606,819
- KP2C (52,4x79,8 cm) , besi D10, D16 kg 60.90 10,500 639,498
- KP3A (93,4x55 cm) , besi D10, D16 kg 61.54 10,500 646,140
- KP3B (80,7x55 cm) , besi D10, D16 kg 57.50 10,500 603,773
5 Kolom Composite
Kolom Composite lt. 1
- KP1 (50x50 cm), D10, D19 kg 2,030.03 10,500 21,315,266
- KP1A (65.4x50 cm) , D10, D19 kg 798.44 10,500 8,383,662
- KP1B (57.7x63.7 cm) , D10, D19 kg 145.94 10,500 1,532,382
- KP1C (63.1x50 cm) , D10, D19 kg 395.84 10,500 4,156,344
Kolom Composite lt. 3, elv. +04.20
- KP1 (50x50 cm), D10, D19 kg 2,380.25 10,500 24,992,660
- KP1A (65.4x50 cm) , D10, D19 kg 936.19 10,500 9,830,044
- KP1B (57.7x63.7 cm) , D10, D19 kg 171.12 10,500 1,796,754
- KP1C (63.1x50 cm) , D10, D19 kg 464.13 10,500 4,873,413
6 Kolom Praktis
- KPSA (17,5x50 cm) , besi D10, D16 kg 190.76 10,500 2,002,961
- KPSB (17,5x63,1 cm) , besi D10, D16 kg 87.36 10,500 917,228
- KPSC (17,5x78,9 cm) , besi D10, D16 kg 101.29 10,500 1,063,557
- KPSD (63,4x55 cm) , besi D10, D16 kg 133.94 10,500 1,406,409
- KPSE (50,7x55 cm) , besi D10, D16 kg 112.16 10,500 1,177,697
7 Lisplank
Lisplank uk. 100 x 144,5 cm, D10, D16 kg 289.64 10,500 3,041,238
8 Plat Lantai
a Lantai 1
- Plat beton lantai, t = 15 cm (S1) elev -00.15 (Wiremesh M7 (deform)-2 layer, volume sdh dihitung 2x) m
2
1,110.36 75,960 84,342,991
- Plat beton lantai, t = 15 cm (S4) elev -00.10 (Wiremesh M7 (deform)-2 layer, volume sdh dihitung 2x) m2 49.65 75,960 3,771,110
b Lantai 2
- Plat beton lantai, t = 12 cm (S2) elev. +04.20 (Wiremesh M7 (deform)-1 layer) m2 555.18 75,960 42,171,496
c Dak Utilitas
- Plat beton lantai, t = 12 cm (S2) elev. +07.70 (Wiremesh M7 (deform)-1 layer) m
2
11.94 75,960 906,788
d Ground Water Tank
130
1 Kolom
Kolom Baja Lt. 1 Elv. +01.05
- KBJ1 (HB 250.250.9.14) kg 4,435.82 13,940 61,835,299
- KBJ2 (WF 350.175.7.11) kg 1,251.66 13,940 17,448,085
- KBJ3 (WF 450.200.9.14) kg 547.96 13,940 7,638,562
Kolom Baja Lt. 3 Elv. +04.20
- KBJ1 (HB 250.250.9.14) kg 5,201.10 13,940 72,503,370
- KBJ2 (WF 350.175.7.11) kg 1,124.96 13,940 15,681,911
- KBJ3 (WF 450.200.9.14) kg 547.96 13,940 7,638,562
Kolom Baja Lt. 5 Elv. +07.70
- KBJ1 AS 1 (HB 250.250.9.14) kg 1,253.10 13,940 17,468,186
- KBJ1 AS 2 (HB 250.250.9.14) kg 783.19 13,940 10,917,616
- KBJ1 AS 3 (HB 250.250.9.14) kg 438.58 13,940 6,113,865
- KBJ1 AS 4 (HB 250.250.9.14) kg 1,181.49 13,940 16,470,004
- KBJ1 AS 5 (HB 250.250.9.14) kg 1,640.96 13,940 22,875,006
- KBJ3 AS 3 (WF 450.200.9.14) kg 250.50 13,940 3,491,914
- KBJ3 AS 4 (WF 450.200.9.14) kg 328.78 13,940 4,583,137
- KBJ2 AS 4.1 (WF 350.175.7.11) kg 312.71 13,940 4,359,150
- KBJ2 AS 6 (WF 350.175.7.11) kg 696.80 13,940 9,713,322
- KBJ2 AS 7 (WF 350.175.7.11) kg 748.46 13,940 10,433,530
2 Balok
Balok Baja Elv. +02.50
- B3 (WF 450.200.9.14) kg 2,371.88 13,940 33,064,063
- B4 (WF 400.200.8.13) kg 870.82 13,940 12,139,284
- B5 (WF 350.175.7.11) kg 1,613.77 13,940 22,495,922
- B6 (WF 300.150.6,5.9) kg 1,489.13 13,940 20,758,508
- B8 (WF 200.100.5,5.8) kg 869.35 13,940 12,118,780
Balok Baja Elv. +04.20
- B1 (Cast. 600.200.8.13) kg 1,631.52 13,940 22,743,389
- B2 (Cast. 525.175.7.11) kg 1,226.11 13,940 17,092,001
- B3 (WF 450.200.9.14) kg 637.98 13,940 8,893,469
- B4 (WF 400.200.8.13) kg 822.56 13,940 11,466,459
- B5 (WF 350.175.7.11) kg 3,671.18 13,940 51,176,300
- B6 (WF 300.150.6,5.9) kg 2,598.33 13,940 36,220,683
- B7 (WF 250.125.6.9) kg 5,204.30 13,940 72,547,964
- UNP (U 200.80.7,5) (bagian sambungan as C, as E dan as 4) kg 494.77 13,940 6,897,086
Balok Baja Elv. +05.10
- B3 (WF 450.200.9.14) kg 2,371.88 13,940 33,064,063
- B4 (WF 400.200.8.13) kg 870.82 13,940 12,139,284
- B5 (WF 350.175.7.11) kg 1,613.77 13,940 22,495,922
- B6 (WF 300.150.6,5.9) kg 1,904.94 13,940 26,554,914
- B8 (WF 200.100.5,5.8) kg 869.35 13,940 12,118,780
Balok Baja Elv. +07.70
- B1 (Cast. 600.200.8.13) kg 1,631.52 13,940 22,743,389
- B2 (Cast. 525.175.7.11) kg 1,226.11 13,940 17,092,001
- B3 (WF 450.200.9.14) kg 3,009.87 13,940 41,957,532
- B4 (WF 400.200.8.13) kg 2,509.14 13,940 34,977,437
- B5 (WF 350.175.7.11) kg 5,284.95 13,940 73,672,223
- B6 (WF 300.150.6,5.9) kg 4,025.47 13,940 56,115,000
- B7 (WF 250.125.6.9) kg 5,615.28 13,940 78,277,001
- B8 (WF 200.100.5,5.8) kg 869.35 13,940 12,118,780
- BB1(WF 450.200.9.14) kg 313.12 13,940 4,364,893
Balok Beton elv. +04.20 area toilet
- BB2 (UNP 250.90.9) kg 909.59 13,940 12,679,707
Balok Ramp
- B6 (WF 300.150.6,5.9) kg 2,457.07 13,940 34,251,486
- UNP (U 200.80.7,5) kg 1,267.16 13,940 17,664,176
- Siku (L 60.60.5) kg 187.58 13,940 2,614,836
- Besi D13 - 20 cm kg 321.07 13,940 4,475,720
3 Tangga
Tangga Showroom
- UNP 100.50.5 kg 28.94 13,940 403,465
Tangga Bengkel
- UNP 100.50.5 kg 28.94 13,940 403,465
Tangga Darurat
- WF 200.100.5,5.8 kg 204.35 13,940 2,848,667
- Chequered plat t = 4,2 mm m2 22.98 400,200 9,196,596
- UNP (U 200.80.7,5) kg 1,158.54 13,940 16,150,103
- siku (L 50.50.5) kg 278.10 13,940 3,876,714
Plat chequered t = 4,2 mm, termasuk cat zinchromate hijau + cat finish grey pada bag. atas dan cat zinchromate
3 grey pada bag. Bawah. Sambungan las p = 2 cm tiap jarak 40 cm dan dempul ex. Sanpolax pada pertemuan
chequered dengan rangka baja.
- Chequered plat mezanine lt. 2 elv. +02.50 m2 173.73 400,200 69,526,746
- Chequered plat mezanine lt. 3 elv. +05.10 m
2
173.73 400,200 69,526,746
- Chequered plat mezanine lt. 4 elv. +07.70 (Termasuk untuk daerah showroom) m2 712.74 400,200 285,238,548
- Chequered plat untuk ramp m2 59.15 400,200 23,671,830
- UNP (U 100.50.5) kg 7,775.05 13,940 108,384,261
- Siku (L 60.60.5) kg 2,691.97 13,940 37,526,085
4 Rafter
Atap Depan
- R1 (Cast. 600.200.8.13) kg 1,223.64 13,940 17,057,542
- R2 (Cast. 525.175.7.11) kg 1,839.17 13,940 25,638,002
- R3 (WF 350.175.7.11) kg 459.79 13,940 6,409,500
- R4 (WF 250.125.6.9) kg 743.91 13,940 10,370,066
131
Atap Belakang
- R3 (WF 350.175.7.11) kg 1,056.91 13,940 14,733,305
- R4 (WF 250.125.6.9) kg 1,134.46 13,940 15,814,351
Atap Loading/Unloading
- R4 (WF 200.100.5,5.8) kg 426.83 13,940 5,950,038
5 Tie Beam
- B7 (WF 250.125.6.9) kg 4,487.01 13,940 62,548,925
7 Gording
Termasuk gording pada atap loading/unloading
- GD1 (CNP 200.75.20.3,2) kg 3,001.92 13,940 41,846,802
- GD2 (CNP150.50.20.2,3) kg 19,385.29 13,940 270,230,896
8 Rangka FASCIA dari CNP 100 dan Besi D13
- Type FC1 AS G-3 s/d G-4, tinggi = 0,7 m, panjang = 6.24 m unit 1.00 1,113,840 1,113,840
- Type FC1 AS 2-F s/d 2-H, tinggi = 0,7 m, panjang = 8.9 m unit 1.00 1,588,650 1,588,650
- Type FC1 AS 4-A s/d 4-G1, tinggi = 0,7 m, panjang = 26.9 m unit 1.00 4,801,650 4,801,650
9 Trekstang dia. 12 mm kg 249.74 10,500 2,622,227
10 Ikatan Angin dia. 16 mm kg 329.13 10,500 3,455,915
11 Turn buckle dia. 16 mm bh 22.00 95,000 2,090,000
12 Tutup GWT (Plat besi t = 2,3 dan rangka siku 50.50.5.10 keliling dan diagonal unit 1.00 350,000 350,000
13 Base Plate, Plat Sambung & Stiffener kg 15,498.22 13,940 216,045,142
14 Anchor Bolt joint Baja ke Beton
- Anchor Bolt dia. 19 mm, panjang = 1000 mm bh 114.00 105,000 11,970,000
- Anchor Bolt dia. 19 mm, panjang = 600 mm bh 78.00 87,500 6,825,000
- Anchor Bolt dia. 19 mm, panjang = 100 mm bh 24.00 25,000 600,000
15 Pengecatan dengan Zinchromate + finish cat ex. FTALIT Hella Grey kg 143,403.69 550 78,872,031
16 Pengecatan bondek dak utilitas elv. +07.70 m2 7.98 6,500 51,886
H PEKERJAAN ATAP
- Bahan Atap Zincalume ex Lysaght type Trimdek Optima lebar efektif 1015 mm,
BMT 0,45 mm, Screw kelas 3/4 ukuran 12-14x50 HGS
- Bahan Cladding Zincalume WARNA Gull Grey ex Lysaght Bluescope type V-Crimp,
TCT 0,4, BMT 0,35, lebar efektif 860 cm
- Bahan Flashing Zincalume, TCT 0,45
- Bahan Talang datar Zincalume TCT 0,5 ,dilapis fiberglass tebal 4mm (2x coating)
I PEKERJAAN WATERPROOFING
2 PEKERJAAN ARSITEKTUR
A PEKERJAAN PASANGAN BATU BATA & PLESTERAN
1 Pekerjaan batu bata press dengan adukan 1:4 lengkap dengan Balok dan Kolom Praktis
setiap luasan 9 m2 , termasuk opening jendela, pintu dan penebalan dinding urinal dan kloset
2
a Lantai 1 Showroom, dan Bengkel (elv. +/- 00.00 dan -00.10 s/d +04.20) m 665.15 106,700 70,971,292
b Lantai 1 WH Unit (-00.10 s/d +02.50) m2 168.74 106,700 18,004,558
c Lantai 2 WH Unit (+02.50 s/d +05.10) m2 145.86 106,700 15,563,262
d Lantai 2 Office dan Lantai 3 WH Unit (+04.20 s/d +07.70) m2 552.37 106,700 58,937,346
e Lantai 4 WH Unit (+05.10 s/d +07.70) m2 145.86 106,700 15,563,262
f Lantai 5 WH Unit (+07.70 s/d top dinding sopi-sopi) m2 483.45 106,700 51,584,115
B PEKERJAAN LANTAI
Pemasangan lantai dengan screeding semen dan pasir (1 : 4) tebal rata-rata 25 mm,
pengisian naad, pemotongan, dan plint. Sesuai gambar dan spesifikasi
> Keramik Tile uk. 30x30cm (L4), type Graniti Smoke unpolished G337403 ex. Roman , area
a. Bengkel, R. Loker, R. Ka. WS, dan Gd. Claim m2 223.30 169,040 37,746,632
b. R. Cuci dan PDI m2 29.70 169,040 5,020,488
> Keramik Tile uk. 10x30cm (L10), type Graniti Smoke Charcoal unpolished G337409 ex. Roman , area
a. Border Pit Bengkel + FI m' 92.52 51,400 4,755,528
b. Border PDI m' 15.88 51,400 816,232
> Keramik Tile uk. 30x30cm (L3), type Graniti Wheat ex. Roman , area
2
a. Ramp Bengkel (sudah termasuk penambahan besi D10 setiap nat sebagai anti selip) m 17.70 169,040 2,992,008
b. Teras Showroom m2 34.98 169,040 5,913,019
> Keramik Tile uk. 40x40cm (L6), type Lexus Cream polished ex.Platinum , area:
2
a. Tangga, untuk tangga bengkel dan tangga showroom m 41.08 142,860 5,868,117
> Keramik Tile uk. 20x20cm (L5), type Granity Paper ex. Roman , area
2
a. Toilet (toilet loker, toilet showroom, dan Janitor) m 11.99 117,330 1,406,787
> Floor harderner finishing lantai sikadur natural non metalic 5kg/m2 incl trowel dan curing (L7),
2
a. WH UNIT lantai1 m 191.40 97,000 18,565,800
b. Ruang Pompa / R. Genset m2 15.40 97,000 1,493,800
> Keramik Tile uk. 30x30 cm ex. Mulia untuk keramik GWT m2 10.56 117,330 1,239,005
> Step nosing tangga showroom dan bengkel uk. 100x400mm, di groove tiga baris m' 70.18 90,000 6,316,200
dengan bevel di ujung, type Homogenius tile Frost White, ex. Granito
> Step nosing tangga teras depan keramik uk. 80x300mm type Ivory White, ex. SG m' 57.42 95,000 5,454,900
2 LANTAI 2 OFFICE
> Keramik Tile uk. 40x40cm (L2), type Lexus Cream polished ex.Platinum , area m2 374.00 142,860 53,429,640
a. Office , dll
> Keramik Tile uk. 20x20cm (L5), type Granity Paper ex. Roman , area
2
a. Toilet m 5.28 117,330 619,502
2
b. T. Wudlu m 5.83 117,330 684,034
> Floor harderner finishing lantai sikadur natural non metalic 5kg/m2 incl trowel dan curing (L7),
2
b.WH UNIT lantai 3 (Area Office lt.2) m 181.50 97,000 17,605,500
> Keramik Tile uk. 10x30cm, type Graniti Smoke unpolished G337403 ex. Roman , area
a. Ruang Kepala Workshop m1 12.10 33,410 404,261
b. Gd. Claim m1 13.20 33,410 441,012
> Keramik Tile uk. 40x40cm, type Lexus Cream polished ex.Platinum , area
a. Tangga m1 70.88 35,715 2,531,479
2 LANTAI 2 OFFICE
> Keramik Tile uk. 40x40cm, type Lexus Cream polished ex.Platinum , area
a. Office , dll m1 213.70 35,715 7,632,296
> Keramik Tile uk. 20x40 cm type Serenity White polished ex. Roman, tinggi 2,15m
2
a. Dinding Toilet m 45.64 170,350 7,775,541
b. Dinding Janitor m2 17.74 170,350 3,021,583
c. Dinding Washtafel tinggi 120cm m2 5.28 170,350 899,448
> Border keramik Tile uk. 20x5 cm type Urban Escala ex. Roman
1
a. Dinding Toilet m 21.23 161,650 3,431,830
b. Dinding Janitor m1 8.25 161,650 1,333,613
c. Dinding Washtafel tinggi 120cm m1 4.40 161,650 711,260
> Keramik Tile uk. 30x30 cm ex. Mulia untuk keramik GWT m2 44.88 117,330 110,760
2 LANTAI 2 OFFICE
> Keramik Tile uk. 20x40 cm type Serenity White polished ex. Roman, tinggi 2,15m
a. Dinding Toilet m2 30.27 170,350 5,156,835
b. T. Wudlu m2 23.65 170,350 4,028,778
2
c. Dinding Washtafel tinggi 120cm m 7.00 170,350 1,191,769
> Border keramik Tile uk. 20x5 cm type Urban Escala ex. Roman
a. Dinding Toilet m1 14.08 161,650 2,276,032
1
b. T. Wudlu m 11.00 161,650 1,778,150
c. Dinding Washtafel tinggi 120cm m1 5.83 161,650 942,420
2 Partisi Gypsum t=9 mm ex. Jayaboard berikut Rangka Double Hollow 40x40, t=0.45 mm
partisi, h = 40 cm termasuk cornerbit pada sudut pertemuan partisi dan opening keliling sisi luar
dan dalam
- Lantai 1 ( antara Showroom dan Bengkel di atas partisi kaca meja observasi setinggi 40 cm ) m2 5.28 125,000 660,000
3 Partisi Gypsum t=9 mm ex. Jayaboard berikut Rangka Double Hollow 40x40, t=0.45 mm
Full partisi, h = 2.8 m termasuk cornerbit pada sudut pertemuan partisi dan opening keliling sisi luar
dan dalam
- Lantai 2 ( R. Ka - SO, Administrasi, dan TL ) m2 72.69 125,000 9,086,000
2
1 Pada Fascia Tampak Depan windoes display ex. Seven colour Brigt Silver QS 3101 m 33.12 757,810 25,098,667
LANTAI 1 SHOWROOM, DAN BENGKEL (elv. +/- 00.00 dan -00.10 s/d +04.20)
1 Pintu lipat besi Type FG1 (uk. 7500x3000mm), tebal plat besi 1.2mm. Fin. Duco Stone Grey ex.Vigor unit 1.00 15,750,000 15,750,000
Showroom As E - As F
- termasuk rangka, perkuatan dan accessories
2 Pintu lipat besi Type FG2 (uk. 3500x3000mm), tebal plat besi 1.2mm. Fin. Duco Stone Grey ex.Vigor unit 3.00 4,725,000 14,175,000
Showroom As A - As E
- termasuk rangka, perkuatan dan accessories
3 Rolling door Type RD 1 (uk. 5500x2700 mm ) ex. Super Teknik T=0,8mm Kombinasi solid dan perforated unit 2.00 7,053,750 14,107,500
setinggi pandangan mata finishing powder coating 2 sisi, termasuk aksesoris dan penggantung
pada area Bengkel
4 Type FR1 (3500x3000 mm) untuk Pintu Entrance Depan, Showroom unit 1.00 25,000,000 25,000,000
- Tempered Glass, t=12 mm, Frameless, ex. Asahimas
- Accessories
* Pull Handel Stainless Steel Hairline type PH802, 38x1200 PPS+SSS, ex. Dekson
* Floor Hinge BTS 80 ex. DORMA
* Top, bottom & corner lock Patch ex. DORMA
5 Type FR2 (3500x3000 mm) untuk Jendela Entrance Utama unit 2.00 9,975,000 19,950,000
- Tempered Glass, t=12 mm, Frameless, ex. Asahimas
6 Type FR3 (5500x2600 mm) untuk Pintu & partisi Entrance Samping dari Showroom ke bengkel unit 1.00 29,700,000 29,700,000
- Tempered Glass, t=12 mm, Frameless, ex. Asahimas
- Accessories
* Pull Handel Stainless Steel Hairline type PH802, 38x1200 PPS+SSS, ex. Dekson
* Floor Hinge BTS 80 ex. DORMA
* Top, bottom & corner lock Patch ex. DORMA
134
7 Type FR4 (2900x3000 mm) untuk Pintu & partisi Showroom ke WH Part unit 1.00 24,450,000 24,450,000
- Tempered Glass, t=12 mm, Frameless, ex. Asahimas
- Accessories
* Pull Handel Stainless Steel Hairline type PH802, 38x1200 PPS+SSS, ex. Dekson
* Floor Hinge BTS 80 ex. DORMA
* Top, bottom & corner lock Patch ex. DORMA
8 Type FR5 (3300x3000 mm) untuk partisi Showroom - WH Part unit 1.00 9,405,000 9,405,000
- Clear Glass, t=12 mm, Frameless, ex. Asahimas
9 Type FR6 (2900x3000 mm) untuk partisi Showroom - WH Part unit 1.00 8,265,000 8,265,000
- Clear Glass, t=12 mm, Frameless, ex. Asahimas
10 Type FR7 (uk.5500x1700 mm) untuk jendela Showroom ke bengkel unit 2.00 8,882,500 17,765,000
- Clear Glass, t=12 mm, Frameless, ex. Asahimas
11 Type P3 (700x2100 mm) untuk Pintu Toilet Showroom (2) dan Toilet Loker (1) unit 3.00 1,657,250 4,971,750
- UPVC ex. ISSI
- Accessories
* Cilinder dead lock
* Door handle
* Butt Hinge
12 Type P4 (900x2600 mm) untuk Pintu R.Administrasi-Kasir unit 1.00 4,624,000 4,624,000
- Frame alluminium 1,5/3" Silver Anodize ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
- Accessories
* Cilinder dead lock ex Dekson
* Door closer TS 68 ex. DORMA
* Door stoper DKS 886 SN ex. Dekson
* Door handle ex. Dekkson hanya pada sisi bagian dalam & luar tanpa handle
(SP003HDL+CYL HOLE & SP002D CYL SSS)
* Butt Hinge ES 4x3x3 MM 4BB ex. Dekson
13 Type P5 (900x2600 mm) untuk Pintu Janitor unit 1.00 4,638,000 4,638,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
- Accessories
* Cilinder dead lock ex Dekson
* Door stoper DKS 886 SN ex. Dekson
* Door handle LHSR 0058 SSS ex. Dekson
15 Type PJ1 (2250x2700 mm) untuk Pintu R. Ka - WS unit 1.00 5,900,000 5,900,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
- Fix window clear glass 6 mm
- Accessories
* Cilinder dead lock ex Dekson
* Door closer TS 68 ex. DORMA
* Door stoper DKS 886 SN ex. Dekson
* Door handle LHSR 0058 SSS ex. Dekson
16 Type PJ2 (2017x2700 mm) untuk Pintu G. Claim unit 1.00 5,796,000 5,796,000
- Frame alluminium 1,5/3" Silver Anodize ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
- Fix window clear glass 6 mm
- Accessories
* Cilinder dead lock ex Dekson
* Door stoper DKS 886 SN ex. Dekson
* Door handle LHSR 0058 SSS ex. Dekson
17 Type PJ3 (3110x2600 mm) untuk Pintu G. Promosi unit 1.00 5,943,000 5,943,000
- Frame alluminium 1,5/3" Silver Anodize ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
- Fix window clear glass 6 mm
- Accessories
* Cilinder dead lock ex Dekson
* Door stoper DKS 886 SN ex. Dekson
* Door handle LHSR 0058 SSS ex. Dekson
135
18 Pintu dan partisi SWADAYA MESH Type WD1 (uk.2850x2300mm) untuk R.Pompa&Genset unit 1.00 3,200,000 3,200,000
pipa pembagi pipa black steel dia. 2.5 " penjepit plat strip 2cm,
Swadaya mesh 50x50x4mm type 228 finish cat minyak Ftalit Hella Grey
termasuk assesoris (engsel,handle,lockset,doors stoper,rel dan perkuatan)
19 Partisi SWADAYA MESH Type WD2 (uk.9960x2300mm) untuk Gudang KSU unit 1.00 8,500,000 8,500,000
pipa pembagi pipa black steel dia. 2.5 " penjepit plat strip 2cm,
Swadaya mesh 50x50x4mm type 228 finish cat minyak Ftalit Hella Grey
termasuk assesoris (engsel,handle,lockset,doors stoper,rel dan perkuatan)
20 Tirai PVC typr TP (uk. 1850x2200mm) type tebal 2mm lebar 20cm untuk washing unit 1.00 1,657,250 1,657,250
penggantung pipa stainless steel termasuk aksesories
21 Type PB2 (4750x2400 mm) untuk Pintu samping Loading/Unloading Warehouse unit 1.00 26,466,000 26,466,000
- Door cover steel plate t=2,3 sisi luar
- Double swing door (lebar masing-masingpintu 2.375 mm)
- Rangka Hollow 50x100x2,3
- Rangka pembagi siku 50.50
- Pintu tambahan untuk orang + lubang pengunci + padlock sisi dalam
- Cat finish duco warna Stone Grey
- Accessories
* Padlock untuk gembok (sisi dalam)
* Door handle custom
* Hing custom
* termasuk pegangan terhadap dinding
22 Type PB3 (3000x2200 mm) untuk Pintu Warehouse unit 1.00 15,426,000 15,426,000
- Pintu besi ex. Vigor
- Single sliding door
- Frame canal C 100,t=medium+plat strip 2 cm fin. Duco Stone Grey
- Door cover steel plate t=2,3 double (luar-dalam rangka hollow)
- Accessories
* Cilinder dead lock
* Door handle custom
* REL atas include accessories ex. Herderson
* REL bawah roda besi custom
23 Type LV2 (uk.300x600 mm) Showroom (antara plafond dan plat lantai) unit 2.00 508,000 1,016,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Jalusi aluminium (10 bh)
24 Pintu P6 (uk. 900x2600 mm) untuk ruang kasir unit 1.00 3,950,000 3,950,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
- Accessories
* Cilinder dead lock ex Dekson
* Door stoper DKS 886 SN ex. Dekson
* Rel SR 8901 D4 Track 2000 mm Kapasitas 100 kg ex. Dekson
* Door handle HDL DKS PP 012 SSS ex. Dekson
25 Pintu P7 (uk. 700x2600 mm) untuk WH Part unit 1.00 3,750,000 3,750,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
Clear glass 6 mm ex. Asahimas
- Accessories
* Cilinder dead lock ex Dekson
* Door stoper DKS 886 SN ex. Dekson
* Door handle HDL DKS PP 012 SSS ex. Dekson
* Grendel DP DKS SQ 3 SSS ex. Dekson
1 Type LV3 (uk. 4200x1200 mm) untuk G. Unit dengan halaman loading unit 1.00 2,166,000 2,166,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Jalusi aluminium (26 bh + tralis)
Tralis frame siku 30x30x3 mm rangka pembagi besi 4 persegi 9,9 mm fibish cat duco
1 Type FR8 (3500x2800 mm) untuk Pintu & partisi Office ke Window display unit 1.00 2,520,000 2,520,000
- Tempered Glass untuk pintu dan kaca diatas pintu, t=12 mm, Frameless, ex. Asahimas
- Clear Glass untuk partisi kaca disamping pintu, t=12 mm, Frameless, ex. Asahimas
- Accessories
* Pull Handel Stainless Steel Hairline type PH802, 38x1200 PPS+SSS, ex. Dekson
* Floor Hinge BTS 80 ex. DORMA
* Top, bottom & corner lock Patch ex. DORMA
136
2 Type FR9 (uk.3500x2800 mm) untuk jendela Office ke Window display unit 2.00 9,310,000 18,620,000
- Clear Glass, t=12 mm, Frameless, ex. Asahimas
3 Type FR10 (uk.7500x2800 mm) untuk jendela Office ke Window display unit 1.00 19,500,000 19,500,000
- Clear Glass, t=12 mm, Frameless, ex. Asahimas
4 Type FR11 (uk.450x1500 mm) untuk partisi ke Window display unit 2.00 650,000 1,300,000
- Clear Glass, t=12 mm, Frameless, ex. Asahimas
5 Type FR12 (19560x2800 mm) untuk Jendela Window Display unit 1.00 32,500,000 32,500,000
- Tempered Glass, t=12 mm, Frameless, ex. Asahimas
6 Type P1 (900x2600 mm) untuk Pintu R. Makan unit 1.00 4,624,000 4,624,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
- Accessories
* Cilinder dead lock ex Dekson
* Door stoper DKS 886 SN ex. Dekson
* Door handle LHSR 0058 SSS ex. Dekson
7 Type P3 (700x2100 mm) untuk Pintu Toilet unit 2.00 1,657,250 3,314,500
- UPVC ex. ISSI
- Accessories
* Cilinder dead lock
* Door handle
* Butt Hinge
8 Type J2 (uk.2465x1700 mm) untuk jendela G. Part unit 1.00 1,840,975 1,840,975
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- FIX window, Clear Glass, t=6 mm, ex. Asahimas
9 Type J3 (uk.3046x1700 mm) untuk jendela R. Makan unit 1.00 3,877,000 3,877,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Kombinasi OPEN (type sliding) / FIX window, Clear Glass, t=6 mm, ex. Asahimas
10 Type PJ4 (2300x2600 mm) untuk Pintu R. Server unit 1.00 5,200,000 5,200,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
- Fix window clear glass 6 mm
- Accessories
* Cilinder dead lock ex Dekson
* Door closer TS 68 ex. DORMA
* Door stoper DKS 886 SN ex. Dekson
* Door handle LHSR 0058 SSS ex. Dekson
11 Type PJ5 (1800x2600 mm) untuk Pintu R. Customer unit 1.00 5,078,000 5,078,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
- Fix window clear glass 6 mm
- Accessories
* Cilinder dead lock ex Dekson
* Door closer TS 68 ex. DORMA
* Door stoper DKS 886 SN ex. Dekson
* Door handle LHSR 0058 SSS ex. Dekson
12 Type PJ6 (5751x2600 mm) untuk Pintu Gd. Part unit 1.00 6,767,000 6,767,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
- Fix window clear glass 6 mm
- Accessories
* Cilinder dead lock ex Dekson
* Door stoper DKS 886 SN ex. Dekson
* Door handle LHSR 0058 SSS ex. Dekson
13 Type PJ7 (5320x2600 mm) untuk Pintu R. Ka. SO/AD.SO/TL unit 1.00 6,547,000 6,547,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
- Fix window clear glass 6 mm
- Accessories
* Cilinder dead lock ex Dekson
* Door closer TS 68 ex. DORMA
* Door stoper DKS 886 SN ex. Dekson
* Door handle LHSR 0058 SSS ex. Dekson
137
14 Type PJ8 (4215x2600 mm) untuk Pintu Gd. File unit 1.00 6,080,000 6,080,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Daun pintu: rangka kayu kamper 2/20 lapis multiplek 4 mm+MDF, fin HPL ex. Taco
TH019AA Egg White dan TH217AA Brilliant Teak
- Fix window clear glass 6 mm
- Accessories
* Cilinder dead lock ex Dekson
* Door stoper DKS 886 SN ex. Dekson
* Door handle LHSR 0058 SSS ex. Dekson
15 Type PB1 (1120x2100 mm) untuk Pintu Warehouse ke R.Makan unit 1.00 5,655,000 5,655,000
- Pintu besi ex. Vigor
- Single swing door
- Frame canal C 100,t=medium+plat strip 2 cm fin. Duco Stone Grey
- Door cover steel plate t=2,3 double (luar-dalam rangka hollow)
- Accessories
* Cilinder dead lock ex. Dekson
* Door handle ex. Dekson
* Butt Hinge ES 4x3x3 MM 4BB ex. Dekson
16 Type LV1 (uk.4750x800 mm) untuk G. Unit dengan halaman loading unit 1.00 2,058,000 2,058,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Jalusi aluminium (10 bh)
17 Type BV1 (uk.1020x540 mm) untuk area Gd. File unit 1.00 325,000 325,000
- Frame alluminium 1,5/3" Silver Anodize ex. Alexindo
- Jendela kaca mati tebal 6 mm ex. Asahimas
- Aksesories
18 Type BV2 (uk.1990x540 mm) untuk area Gd. File unit 3.00 650,000 1,950,000
- Frame alluminium 1,5/3" Silver Anodize ex. Alexindo
- Jendela kaca mati tebal 6 mm ex. Asahimas
- Aksesories
19 Type BV3 (uk.2960x540 mm) untuk area Gd. Part/R.Customer/R.Ka.SO unit 1.00 950,000 950,000
- Frame alluminium 1,5/3" Silver Anodize ex. Alexindo
- Jendela kaca mati tebal 6 mm ex. Asahimas
- Aksesories
20 Type BV4 (uk.3930x540 mm) untuk area Gd. Part/R.Customer/R.Ka.SO unit 1.00 1,565,000 1,565,000
- Frame alluminium 1,5/3" Silver Anodize ex. Alexindo
- Jendela kaca mati tebal 6 mm ex. Asahimas
- Aksesories
1 Type LV3 (uk. 4200x1200 mm) untuk G. Unit dengan halaman loading unit 1.00 2,166,000 2,166,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Jalusi aluminium (26 bh + tralis)
Tralis frame siku 30x30x3 mm rangka pembagi besi 4 persegi 9,9 mm fibish cat duco
1 Type LV1 (uk.4750x800 mm) untuk G. Unit unit 6.00 2,058,000 12,348,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Jalusi aluminium (10 bh)
2 Type LV3 (uk. 4200x1200 mm) untuk G. Unit dengan halaman loading unit 3.00 2,166,000 6,498,000
- Frame alluminium 1,5/3" Silver Anodes ex. Alexindo
- Jalusi aluminium (26 bh + tralis)
Tralis frame siku 30x30x3 mm rangka pembagi besi 4 persegi 9,9 mm fibish cat duco
H PEKERJAAN PLAFOND
1 Pekerjaan Plafond gypsum tebal 9mm ex Jayaboard + rangka hollow 40x40cm tebal 0.45mm
termasuk penggantung, ramset, screw, aksesories standard pemasangan plafond, pelubangan
dan perkuatan rangka, serta alat bantu dan harga satuan sudah termasuk shadowline untuk
pertemuan plafon dengan dinding
> Lantai 1 (Showroom, Gd. Promosi, R. Ka. WS, Gd. Claim dan Bengkel ) m2 478.50 93,115 44,555,528
2
> Lantai 2 ( Window display dan R.Makan ) m 78.10 93,115 7,272,282
3 Plafond Gyptile 60x120 rangka metal furing lengkap assesories, ex Jayaboard type Byhua m2 283.80 93,115 26,426,037
> Lantai 2 ( termasuk tambahan rangka support ke baja )
4 Pekerjaan Touch up dak beton diatas R. Genset dan Pompa dengan MU 200 acian beton m2 16.50 27,750 457,875
I PEKERJAAN PENGECATAN
1 Pengecatan Dinding bagian luar ( termasuk parapet ) dengan m2 70.03 26,770 1,874,757
Dulux weathershield type Brilliant White
3 Pengecatan Dinding bagian dalam dengan Emulsion Paint ex. Vinilex Type 300 White
a Lantai 1 Showroom, dan Bengkel (elv. +/- 00.00 dan -00.10 s/d +04.20) m2 858.46 17,430 14,962,993
2
b Lantai 1 WH Unit (-00.10 s/d +02.50) m 120.01 17,430 2,091,774
c Lantai 2 WH Unit (+02.50 s/d +05.10) m2 145.86 17,430 2,542,340
2
d Lantai 2 Office dan Lantai 3 WH Unit (+04.20 s/d +07.70) m 821.23 17,430 14,313,987
e Lantai 4 WH Unit (+05.10 s/d +07.70) m2 145.86 17,430 2,542,340
f Lantai 5 WH Unit (+07.70 s/d top dinding sopi-sopi) m2 483.45 17,430 8,426,534
4 Pengecatan Dinding bagian dalam diatas keramik sampai dengan plafond dengan
Cat Minyak ex. Dulux type White V Gloss
- Lantai 1 ( Bengkel dan Loker) m2 88.35 22,920 2,025,028
2
- Lantai 1 (PDI dan R.Cuci) m 42.24 22,920 968,141
5 Pengecatan Dinding Partisi Gypsum dengan Emulsion Paint ex. Vinilex Type 300 White
- Lantai 1 ( Showroom ) m2 95.11 17,430 1,657,698
- Lantai 2 (Office) m2 159.91 17,430 2,787,294
6 Pengecatan plat beton bawah tangga dengan Emulsion Paint ex. Vinilex Type 300 White m2 30.25 17,430 527,258
7 Pengecatan Plafond Gypsum dengan Emulsion Paint ex. Vinilex 300 SS White
> Lantai 1 (Showroom, Gd. Promosi, R. Ka. WS, Gd. Claim dan Bengkel ) m2 478.50 17,430 8,340,255
2
> Lantai 2 ( Window display dan R.Makan ) m 78.10 17,430 1,361,283
8 Pengecatan Plafond Gypsum dengan Emulsion Paint ex. Vinilex 300 SS White
> Lantai 1 ( Toilet, R. Loker, dan Teras Depan) m2 61.93 17,430 1,079,440
> Lantai 2 ( Toilet, R.Wudlu, Musholla, R. Server) m2 31.02 17,430 540,679
9 Pekerjaan Touch up dak beton diatas R. Genset dan Pompa dengan MU 200 acian beton m2 16.50 27,750 457,875
J PEKERJAAN SANITAIR
LANTAI 1 & 2
1 Closet Duduk type CW 421J/SW420JP Ex TOTO + Jet Washer TX403SB unit 2.00 2,050,000 4,100,000
2 Closet Jongkok type CE7 lengkap dengan peninggian lantai unit 3.00 450,000 1,350,000
3 Paper Holder ex TS116R unit 2.00 375,000 750,000
4 Floor Drain ex TOTO TX 1 BN unit 9.00 325,000 2,925,000
5 Lavatory LW230J EX TOTO unit 2.00 1,600,000 3,200,000
6 Cermin Beveled t=6 mm uk.900x110 cm u/ washtafel unit 2.00 250,000 500,000
7 Kran ex. TOTO Type T 23B13V7N u/ Toilet, Janitor & toilet mekanik unit 7.00 425,000 2,975,000
8 Gantungan ex. Toto double robe hook type TX 704 ACW unit 5.00 215,000 1,075,000
139
Pantry
1 Meja pantry beton finish granite tile 60x60 cm White Onyx ex. Indogress dan keramik dinding unit 1.00 5,880,000 5,880,000
tinggi=60cm uk. 60x60 cm White Onyx ex. Indogress, meja dengan ukuran l=60 cm, panjang 2800 mm
2 Lemari gantung multiplek 18 mm, l=40 cm, h=750 cm, p=2800 cm unit 1.00 6,000,000 6,000,000
sisi LUAR lapis HPL TH217AA Brilliant Teak ex. Taco, sisi DALAM lapis melaminto
3 Lemari dibawah meja beton multiplek 18 mm, l=60 cm,h=850,p=2800 unit 1.00 2,100,000 2,100,000
sisi LUAR lapis HPL TH217AA Brilliant Teak ex. Taco, sisi DALAM lapis melaminto
4 Kitchen sink 1 lubang ex. Royal type SB-45 termasuk P-trap unit 1.00 765,000 765,000
5 Kran zink type T30AR13 V7 (N) ex. Toto unit 1.00 540,000 540,000
Janitor
1 Lemari gantung multiplek 18 mm, l=40 cm, h=800 cm, p=800 cm unit 1.00 2,100,000 2,100,000
sisi LUAR lapis HPL TH217AA Brilliant Teak ex. Taco, sisi DALAM lapis melaminto
2 Gantungan stainless steel (5 kaitan) unit 1.00 250,000 250,000
K PEKERJAAN RAILING
1 Railing tangga dari hollow 40x40, 20x40, dan handrailling 40x60 finish duco Hella Grey, untuk tangga bengkel m1 15.40 385,000 5,929,000
140
L PEKERJAAN LAIN-LAIN
1 Pekerjaan canopy rangka WF 200x100x5,5x8 mm + pipa black steel dia. 2" expose finish cat duco warna Grey Silever,
finish atap kaca laminate 2x6mm , lengkap dengan assesories
- Depan Showroom & Bengkel m1 20.65 1,800,000 37,170,000
2 Pekerjaan atap polycarbonat (penutup canopy sementara), lengkap assesories
1
- Depan Showroom & Bengkel m 20.65 655,000 13,525,750
3 Saluran pada pit bengkel + Stall Heavy Repair dengan beton uk. 20x30cm + penutup chequerplat m1 27.20 275,000 7,480,000
tebal 2,3mm + siku 20.20.2 untuk dudukan tutup lubang saluran pit finish zincromate dan
cat galvanize
4 Saluran area washing motor dengan beton uk. 20x30cm + sandtrap uk 20x20x40cm di ujung m1 2.00 315,000 630,000
saluran + tutup grill plat strip lebar 3cm tebal 3mm jarak 3cm termasuk zincromate
dan cat finish galvanize + dudukan siku 30.30.3
5 Chequer plat alumunium lebar 30 cm, type Doof, tebal 2,3mm terpasang termasuk sekrup+fisher S8 ke plat lantai m1 6.85 380,000 2,603,000
untuk tumpuan motor PDI, FI, dan R.Cuci
6 Cat garis batas motor lebar 10 cm ex. Tennocote warna putih untuk halaman parkir samping m1 50.80 27,500 1,397,000
1
7 Cat garis batas motor lebar 5 cm ex. Ftalit type 115-147 Lemon Yellow KF-47 untuk stock WH Unit m 638.45 17,500 11,172,893
8 Karpet musholla lantai 2 (area office) ex. Bali warna hijau type BL-364, t=4 mm m2 9.46 275,000 2,601,500
1
9 Tanggulan T. Wudlu dan Janitor termasuk pasangan keramik m 5.00 125,000 625,000
10 Ramp plat cheguerplate dengan rangka 2WF200 dengan panjang 5,5meter, lebar 1.5meter, dan beda unit 1.00 5,568,750 5,568,750
elevasi untuk ramp 90cm (penghubung warehouse unit ke office lantai 2/WH. Unit lt.3)
- TERMASUK anti slip dari besi D-13 perjarak 300mm
11 Chequer plat alumunium lebar 30 cm, tebal 2,3mm finish zincromate dan cat minyak ex.Ftalit warna Hella Grey
terpasang termasuk sekrup + fisher S8 ke plat lantai
untuk tumpuan motor area:
- Mezzanine Lt. 1 Elev.-00.10 m1 12.15 380,000 4,617,000
1
- Mezzanine Lt. 3 Elev.+04.20 (area office lt.2) m 37.95 380,000 14,421,000
- Mezzanine Lt. 5 Elev. +07.70 area depan As 1 m1 11.55 380,000 4,389,000
12 Finishing Floor Hardener Mezzanine
Floor harderner finishing lantai sikadur natural non metalic 5kg/m2 incl trowel dan curing
2
- Mezzanine Lt. 5 Elev. +07.70 area depan As 1 m 40.70 97,000 3,947,900
13 Tangga maintanance rangka hollow 40/40 untuk roof tank, termasuk kolom pedestal, dan perkuatan unit 2.00 2,000,000 4,000,000
sesuai gambar
14 Cat walk plat chequareplate 4.2mm termasuk support balok & kolom 2xC100 , untuk m1 9.00 850,000 7,650,000
maintenance ke atap
1
15 Tangga monyet untuk maintanance ke roof tank (Ukuran & spesifikasi sesuai gambar) m 13.20 525,000 6,930,000
- Rangka tangga dan hand railling pipa hitam dia. 2", fin. cat minyak
- Anak tangga pipa hitam dia. 1 " perjarak 35 cm, fin cat minyak
- Cover pengaman 11 baris besi dia.13, plat strip 50x3@100cm, fin. cat minyak
- Floor chekerplate t=4,2 mm, fin cat minyak
- Support rangka tangga pipa hitam dia. 2", CNP 100x50x6, dinabolt 3M12 jarak sesuai gambar
- termasuk kolom pedestal
16 Cover balok baja dengan gypsum t=9 mm ex. Jayaboard berikut Rangka Hollow 40x40, t=0.45 mm m2 10.53 93,115 980,222
pada area bengkel as F - (as 3s/d 4')
17 Sun shadding (uk. 6000x1000 mm) pada AS G - (3 s/d 4), detail sesuai gambar unit 4.00 2,000,000 8,000,000
Rangka shadding menggunakan siku uk. 50x50x5 mm finish cat duco, bahan penutup kombinasi cladding dan
skylight ex. Fiberlux dengan gelombang disesuaiakan dengan type gelombang atap
2
18 Tralis Void Warehouse Unit dengan rangka hollow uk. 40x40x2,3 jarak 60x60cm dengan kawat burung m 10.00 350,000 3,500,000
baja coating dan plat strip sebagai penjepit pada bagian atas hollow (pemasangan dengan screw)
IV PEKERJAAN LUAR
A PEKERJAAN SALURAN
2
1 Pagar pasangan dinding batu bata merah t = 3.5 meter termasuk kolom m 128.59 106,700 13,720,553
dan balok praktis
2 Plesteran luar dalam adukan 1:4 dengan tebal rata-rata 2 cm m2 257.18 41,010 10,546,952
3 Acian skimcoat MU 200 tebal 2cm termasuk sudutan m2 257.18 27,750 7,136,745
4 Pengecatan Dinding dalam dengan Dulux weathershield type Brilliant White m2 128.59 26,770 3,442,354
2
5 Pengecatan Dinding luar dengan cat waterproof ex. Aquaproof warna putih m 128.59 25,190 3,239,182
6 Kawat duri ex. Cochrane Steel Product type Sirip Flatwrap dia. 50cm m' 36.00 300,000 10,800,000
termasuk rangka siku 40.40.3 tiap jarak 3 meter finish zincromate, dan besi beton
dia. 8 mm dan cat minyak warna abu-abu
1 Pagar depan, pintu lipat dorong besi tinggi 1.5 m finish cat m' 31.24 575,000 17,963,000
termasuk perkuatan engsel, roda, rel dan accesories lainnya
E PEKERJAAN LAIN-LAIN
1 Sumur Resapan lengkap dengan lap. Ijuk + tutup (H=3 m) unit 4.00 2,150,000 8,600,000
2 Ramp beton jalan masuk dan ramp loading tebal 20 cm penutup saluran kota
2
depan besi M8 - 2 layer termasuk bekisting (termasuk perbaikan trotoar) m 75.60 385,000 29,106,000
3 Ramp beton loading / unloading tebal 20 cm, besi M8 - 2 layer termasuk bekisting m2 10.32 385,000 3,973,200
4 Pekerjaan Oil Trap struktur beton , Ukuran & spesifikasi sesuai gambar unit 1.00 6,750,000 6,750,000
- sudah termasuk galian tanah dan bekisting
5 Rumah Bioteck struktur beton , Ukuran & spesifikasi sesuai gambar unit 1.00 8,000,000 8,000,000
sudah termasuk galian tanah dan bekisting untuk :
- Biotech kapasitas 3 m3
6 Bak penampungan oli bekas struktur beton , Ukuran & spesifikasi sesuai gambar unit 1.00 3,575,000 3,575,000
- sudah termasuk galian tanah dan bekisting
7 Tangga stainless steel , untuk groundtank unit 1.00 1,000,000 1,000,000
8 Tiang Bendera Stainless Steel tinggi 9 m' (1 tiang), sesuai dengan gambar unit 1.00 2,250,000 2,250,000
9 Pipa pvc 4" + tutup dicor setempat , tinggi 50cm untuk dudukan tiang umbul-umbul unit 6.00 175,000 1,050,000
10 Pekerjaan Pos Jaga (sesuai dengan gambar), sudah termasuk pekerjaan galian unit 1.00 11,450,000 11,450,000
dan bekisting
11 Dudukan Plat Beton bak sampah+saluran buangan (sesuai dengan gambar) unit 1.00 725,000 725,000
12 Pekerjaan landscape m2 16.50 155,000 2,557,500
13 Bak exhoust knalpot struktur beton, ukuran & spesifikasi sesuai gambar unit 1.00 1,000,000 1,000,000
termasuk galian tanah serta bekisting
2
14 Pekerjaan cutter ramp beton shiping dan receiving area bentuk 'V' m 75.60 125,000 9,450,000
dengan gerinda dengan ukuran siku 40
15 Pekerjaan saluran beton jalan raya lebar 60cm dengan kedalaman 1 m, dengan m' 31.24 700,000 21,868,000
beton tebal 15cm. Dalam pembuatan sudah termasuk bongkar saluran eksisting
dan kordinasi dengan Dinas terkait sehubungan dengan ukuran dan debit saluran
16 Pekerjaan planter box (sesuai dengan gambar) unit 4.00 500,000 2,000,000
e. Pekerjaan air tanah (SIPA) & pengetesan mutu baku air tanah lot 1.00 13,000,000 13,000,000
B PEKERJAAN PLUMBING
3 Pengkabelan dari Radar s/d pompa transfer lot 1.00 491,500 491,500
NYMHY 2 x 1,5 mm2 dalam pipa konduit dia 20
6 Roof Tank
Kapasitas : 2m3 unit 2.00 8,565,000 17,130,000
Type : Cilinder Stainless
ACCESSORIES
1. Gate Valve
- ø 40 mm bh 3.00 322,975 968,925
- ø 32 mm bh 4.00 270,050 1,080,200
- ø 25 mm bh 2.00 197,850 395,700
3. Float Valve
- ø 32 mm bh 1.00 404,000 404,000
5. Foot valve
- ø 40 mm bh 2.00 404,000 808,000
6. Check valve
- ø 40 mm bh 2.00 507,000 1,014,000
7 Strainer
- ø 40 mm bh 2.00 609,553 1,219,105
8 Flexibel joint
- ø 40 mm bh 2.00 413,055 826,110
c. Pekerjaan Pipa
Pipa galvanis l / d accesoris
1. GIP Medium Class
- ø 50 mm Header lot 1.00 158,120 158,120
- ø 40 mm Transfer ml 25.00 102,180 2,554,500
- ø 32 mm Riser ml 78.00 94,870 7,399,860
- ø 25 mm Riser ml 52.00 77,490 4,029,480
e. Material Bantu dan pengecatan warna biru ex FTALIT lot 1.00 1,000,000 1,000,000
1. Site Plan
a. Pekerjaan Pemipaan
Pipa GIP Medium Class
- ø 40 mm (Dari PDAM ke GWT) ml 42.00 102,180 4,291,560
- ø 32 mm (Dari air sumur ke GWT) ml 12.00 94,870 1,138,440
- ø 20 mm (kran taman & pos jaga) ml 6.00 54,710 328,260
- ø 15 mm (kran taman & pos jaga) ml 16.00 43,320 693,120
b. Valve
1. Gate Valve
ø 40 mm bh 2.00 322,975 645,950
ø 32 mm bh 2.00 270,050 540,100
2. Kran Taman
ø 15 mm bh 1.00 By Sipil
d. Material Bantu dan pengecatan warna biru Ex Ftalit lot 1.00 1,000,000 1,000,000
2. LANTAI 1
145
d. Material Bantu dan pengecatan warna biru Ex Ftalit lot 1.00 1,000,000 1,000,000
3 LANTAI 2
a. Pekerjaan Pemipaan
Pipa GIP Medium Class
- ø 32 mm ml 10.00 94,870 948,700
- ø 25 mm ml 12.00 77,490 929,880
- ø 20 mm ml 4.00 54,710 218,840
- ø 15 mm ml 48.00 43,320 2,079,360
b. Valve
1. Gate Valve
ø 32 mm bh 1.00 270,050 270,050
2. Kran
ø 15 mm bh 3.00 By Sipil
c. Fitting lot 1.00 417,678 417,678
d. Material Bantu dan pengecatan warna biru Ex Ftalit lot 1.00 1,000,000 1,000,000
1. PERALATAN UTAMA
a. SITE PLAN
4 Pipa Bak oil Trap dia 100 mm lot 1.00 3,470,000 3,470,000
b PEMIPAAN Air bekas ke OIL TRAP (STALL BENGKEL & STALL CUCI)
1 Pekerjaan Pemipaan
Pipa air bekas ke Oil trap l/d accessories.
Pipa PVC Class 10 kg/cm²
ø 80 mm ml 4.00 61,910 247,640
ø 65 mm ml 26.00 37,380 971,880
b. LANTAI 2
1 Pekerjaan Pemipaan
Pipa air kotor dan air bekas l/d accessories.
Pipa PVC Class 10 kg/cm²
- SW
ø 100 mm ml 16.00 90,240 1,443,840
- WW
ø 80 mm ml 6.00 61,910 371,460
ø 65 mm ml 4.00 50,330 201,320
ø 50 mm ml 22.00 37,380 822,360
Pipa PVC Class 5 kg/cm²
- VT
ø 40 mm ml 8.00 26,880 215,040
ø 25 mm ml 8.00 23,980 191,840
2 Floor Drain & Clean Out
- Floor Drain
ø 50 mm bh 4.00 By Sipil
- Clean Out
ø 100 mm bh 1.00 197,500 197,500
ø 80 mm bh 1.00 175,000 175,000
a. PERALATAN UTAMA
Peralatan Utama l / d accesoris
b. ACCESSORIES
1. Ball Valve
- ø 20 mm bh 4.00 219,500 878,000
- ø 15 mm bh 23.00 172,000 3,956,000
2. Gate valve
- ø 32 mm bh 2.00 270,050 540,100
3. Quick Joint
- ø 15 mm bh 7.00 By owner By owner
4. Flexible Joint
- ø 32 mm bh 7.00 376,138 2,632,963
8. Penggantung pipa konstruksi dobel CNP 100.50.3,2 set 18.00 610,000 10,980,000
Include pengecatan Ex Ftalit (Permanen red KF-43 No- 143)
c. Pekerjaan Pipa
Pipa BS Class Medium l/d Accessories
e. Support Alat Bantu dan Pengecatan Warna Abu-abu lot 1.00 1,000,000 1,000,000
IV PEKERJAAN TALANG
148
c. Elbow
- ø 150 mm bh 20.00 265,000 5,300,000
- ø 100 mm bh 4.00 198,940 795,760
d. Roff drain
- ø 150 mm bh 5.00 462,200 2,311,000
- ø 100 mm bh 2.00 380,200 760,400
e. Support Alat Bantu dan Pengecatan (warna putih) ex FTALIT lot 1.00 1,750,000 1,750,000
A.1 LANTAI 1
1 PERALATAN UTAMA
2 PEKERJAAN PEMIPAAN
A.2 LANTAI 2
1 PERALATAN UTAMA
Simbol Unit : IU/0U- 2.1, 2.2. 2.7 & 2.8 unit 4.00 4,732,500 18,930,000
Kapasitas 1,5 PK
2 PEKERJAAN PEMIPAAN
C PEKERJAAN ELEKTRIKAL
I PEKERJAAN PANEL
- Outlet Stop Kontak Exhaust centrifugal (Knalpot Bengkel) bh 1.00 71,000 71,000
b. Instalasi pengkabelan
- Instalasi titik lampu ttk 121.00 201,978 24,439,338
NYM 3 x 2,5 mm² dalam PVC Conduit ø 20 mm
- Instalasi Stop Kontak Exhaust centrifugal (Knalpot Bengkel) ttk 1.00 227,654 227,654
151
2 OFFICE LANTAI 2
a. Armature Lampu
- TL LED 2 x 16 Watt TKI MIRROR REFLEKTOR bh 34.00 622,500 21,165,000
- TL LED 1 x 16 W TKO bh 13.00 261,690 3,401,970
- TL LED 1 x 10 W diatas wastafel bh 1.00 308,050 308,050
- Down light LED 12 W bh 28.00 180,750 5,061,000
- Lampu Exit 10 W bh 2.00 727,950 1,455,900
- Saklar Tunggal bh 8.00 66,250 530,000
- Saklar Seri bh 7.00 71,000 497,000
- Saklar Hotel bh 2.00 77,750 155,500
- Saklar Grid swich 6 Gang bh 1.00 298,000 298,000
- Outlet Stop Kontak 200 W bh 18.00 71,000 1,278,000
b. Instalasi Pengkabelan
- Instalasi titik lampu ttk 78.00 201,978 15,754,284
NYM 3 x 2,5 mm² dalam PVC Conduit ø 20 mm
a. Armature Lampu
- TL LED 1 x 16 W TKO bh 27.00 261,690 7,065,630
- Lampu Baret 20 W bh 2.00 215,900 431,800
- Saklar Tunggal bh 2.00 66,250 132,500
- Saklar Seri bh 2.00 71,000 142,000
- Saklar Grid swich 5 Gang bh 1.00 269,500 269,500
- Outlet Stop Kontak 200 W bh 2.00 71,000 142,000
b. Instalasi Pengkabelan
- Instalasi titik lampu ttk 29.00 201,978 5,857,362
NYM 3 x 2,5 mm² dalam PVC Conduit ø 20 mm
a. Armature Lampu
- TL LED 1 x 16 W TKO bh 27.00 261,690 7,065,630
- Lampu Baret 20 W bh 1.00 215,900 215,900
- Saklar Tunggal bh 1.00 66,250 66,250
- Saklar Grid swich 6 Gang bh 2.00 298,000 596,000
- Outlet Stop Kontak 200 W bh 2.00 71,000 142,000
b. Instalasi Pengkabelan
- Instalasi titik lampu ttk 28.00 201,978 5,655,384
NYM 3 x 2,5 mm² dalam PVC Conduit ø 20 mm
5 WAREHOUSE LANTAI 5
152
b. Instalasi Pengkabelan
- Instalasi titik lampu ttk 59.00 201,978 11,916,702
NYM 3 x 2,5 mm² dalam PVC Conduit ø 20 mm
a. Armature Lampu
- Lampu Taman 50 W bh 4.00 513,400 2,053,600
- Lampu Baret 20 W bh 2.00 215,900 431,800
- Saklar Tunggal bh 1.00 66,250 66,250
- Outlet Stop Kontak 200 W bh 1.00 71,000 71,000
b. Instalasi Pengkabelan
- Instalasi titik lampu ttk 2.00 201,978 403,956
NYM 3 x 2,5 mm² dalam PVC Conduit ø 20 mm
c. Besi CNP
- 100 x 50 mm m' 34.00 100,000 3,400,000
4. WAREHOUSE LANTAI 5
a. Besi CNP
- 100 x 50 mm m' 263.00 100,000 26,300,000
b. Pekerjaan Instalasi
> SHOWROOM & BENGKEL
- Rate of Rise Heat Detector bh 9.00 83,850 754,650
- Photoelectric Smoke Detector bh 7.00 207,825 1,454,775
- Alarm Bell bh 1.00 187,875 187,875
- Indicator Lamp bh 1.00 69,505 69,505
- Manual Push Button bh 1.00 143,770 143,770
- End Of Line bh 1.00 169,625 169,625
- Terminal Box bh 1.00 467,500 467,500
- Instalasi Fire Alarm(NYA 1,5 mm2 dalam PVC conduit High Impact) ttk 16.00 167,286 2,676,576
- Instalasi Intercome l/d Jack Intercome ttk 1.00 155,000 155,000
(ITC 2 Pairs dalam PVC conduit High Impact)
c. Pekerjaan Kabel
- Kabel dari MCP-FA ke MDF
,NYA 10 x 1 x 1,5 mm2) m 10.00 20,400 204,000
- Kabel dari MDF ke :
- JBFA 1 NYA 5 x 1 x 1,5 mm2 m 21.00 12,800 268,800
,ITC 2(2 x 2 x 0,6 mm2) m 21.00 8,760 183,960
- JBFA 2 NYA 5 x 1 x 1,5 mm2 m 9.00 12,800 115,200
,ITC 2(2 x 2 x 0,6 mm2) m 9.00 8,760 78,840
- JBFA 3 NYA 5 x 1 x 1,5 mm2 m 26.00 12,800 332,800
,ITC 2(2 x 2 x 0,6 mm2) m 26.00 8,760 227,760
- JBFA 4 NYA 5 x 1 x 1,5 mm2 m 32.00 12,800 409,600
,ITC 2(2 x 2 x 0,6 mm2) m 32.00 8,760 280,320
- Annunciator NYA 5 x 1 x 1,5 mm2 m 63.00 12,800 806,400
(Pos jaga)
b. Pekerjaan Kabel
- Kabel dari MDF Telkom luar ke MDF Showroom
OTC,( 8 x 2 Pairs x 0,6 mm2) Dlm PVC Konduit m 57.00 67,200 3,830,400
JBTP Lantai 1 ITC, 12(2 Pairs x 0,6 mm2) Dlm PVC Konduit m 21.00 52,800 1,108,800
JBTP Lantai 2 ITC, 12(2 Pairs x 0,6 mm2) Dlm PVC Konduit m 9.00 52,800 475,200
c. Instalasi Telepon
- Showroom & Bengkel
- Instalasi Telepon (ITC, 2 Pairs Dlm PVC Konduit) ttk 9.00 230,986 2,078,874
- Pesawat Telepon bh BY OWNER
- Outlet Telepon bh 8.00 101,300 810,400
- Outlet Telepon lantai bh 1.00 101,300 101,300
- Office Lantai 2
- Instalasi Telepon (ITC Cat. 2 Pairs Dlm PVC Konduit) ttk 7.00 230,986 1,616,902
- Pesawat Telepon bh BY OWNER
- Outlet Telepon bh 7.00 101,300 709,100
b. Instalasi Data (Kabel UTP Cat. 6 E Dlm PVC Konduit) + Acces Point
- Lantai 1 ttk 8.00 466,676 3,733,408
- Lantai 2 ttk 7.00 466,676 3,266,732
c. Outlet Data
- Lantai 1 Outlet dinding bh 5.00 154,500 772,500
Outlet lantai bh 1.00 154,500 154,500
- Lantai 2 bh 6.00 154,500 927,000
- Colour Camera Type Day / Night (Outdoor) 1,3 Mega fixel ttk 6.00 1,953,500 11,721,000
- Instalasi Camera dan kabel power ttk 10.00 1,774,000 17,740,000
XI PEKERJAAN GROUNDING/PENTANAHAN
Pengadaan dan pemasangan grounding/pentanahan lengkap terpasang dengan server
bangunan showroom sampai ke outlet data lengkap terpasang dengan kabel BC, bak
a. Grounding SDP dan Panel (Tahanan pentanahan max. 5 Ohm) lot 1.00 2,550,000 2,550,000
b. Grounding PABX (Tahanan pentanahan max. 1 Ohm) lot 1.00 2,550,000 2,550,000
c. Grounding Data (Tahanan pentanahan max. 1 Ohm) lot 1.00 2,550,000 2,550,000
d. Grounding Bangunan (Tahanan pentanahan max. 1 Ohm) lot 1.00 2,550,000 2,550,000
f. Grounding Genset (Tahanan pentanahan max. 5 Ohm) lot 1.00 2,550,000 2,550,000
Testing & commissioning peralatan dan instalasi lot 1.00 3,600,000 3,600,000
JUMLAH
NO URAIAN PEKERJAAN ( Rp. )
I PERSIAPAN 158,675,000
II PEMATANGAN LAHAN 224,381,160
III BANGUNAN SHOWROOM, OFFICE, BENGKEL, DAN WH UNIT
- PEKERJAAN STRUKTUR 4,191,696,199
- PEKERJAAN ARSITEKTUR 1,656,081,123
IV PEKERJAAN LUAR 271,304,881
JUMLAH
NO URAIAN PEKERJAAN
( Rp. )
REKAPITULASI TOTAL
TOTAL 1 + 2 7,710,610,174
JASA KONTRAKTOR 5% 385,530,509
TOTAL 8,096,140,682
PEMBULATAN 8,096,000,000
PPN 10% 809,600,000