Rp. Rp.

A ORIGINAL KONTRAK

1 Pile work
Driven piles
- Dia. 400 mm length 24 m (12 m + 12 m) 2897 nos 69.528 m' 82.000 5.701.296.000
- Dia. 600 mm length 24 m (12 m + 12 m) 2864 nos 68.736 m' 93.000 6.392.448.000

2 Handling piles
- Dia. 400 mm length 24 m (12 m + 12 m) 2897 nos 69.528 m' 11.000 764.808.000
- Dia. 600 mm length 24 m (12 m + 12 m) 2864 nos 68.736 m' 16.000 1.099.776.000

3 Welding joint with AWS E-7016 (3 layer)


- Dia. 400 mm length 24 m (12 m + 12 m) 2897 nos 2.897 Joint 170.000 492.490.000
- Dia. 600 mm length 24 m (12 m + 12 m) 2864 nos 2.864 Joint 235.000 673.040.000

4 Preboring
- Dia. 400 mm length 24 m (12 m + 12 m) 2897 nos 1 m' 325.000 Harga satuan saja
- Dia. 600 mm length 24 m (12 m + 12 m) 2864 nos 1 m' 425.000 Harga satuan saja

5 Mobilisasi dan Demobilisasi 1 Ls 2.400.000.000


5 unit diesel hammer, 5 unit crane service dan 8
unit mesin las

SUB TOTAL A 17.523.858.000

B KERJA TAMBAH

1 Pekerjaan tambah 1 Lot 2.806.294.920


( Detail break down terlampir )

SUB TOTAL B 2.806.294.920

C KERJA KURANG ( PILING AREA PONDASI COAL SHELTER )

Driven piles
- Dia. 600 mm length 22 m (12 m + 10 m) 324 nos 7.128 m' 93.000 662.904.000

Handling piles
- Dia. 600 mm length 22 m (12 m + 10 m) 324 nos 7.128 m' 16.000 114.048.000

Welding joint with AWS E-7016 (3 layer)


- Dia. 600 mm length 22 m (12 m + 10 m) 324 nos 324 Joint 235.000 76.140.000

SUB TOTAL C 853.092.000

SUB TOTAL (A+B-C) 19.477.060.920


PPN 10% 1.947.706.092
TOTAL 21.424.767.012