draft contract change order (CCO)

PAKET PELEBARAN DAN PENINGKATAN JALAN LAMPU MERAH WAENA - PERUMNAS III (MYC)
Nama Paket : Pelebaran Dan Peningkatan Jalan Lampu Merah Waena _ Perumnas III (MYC) Bulan : Mei 2020
Nomor Kontrak : 050 / 1247 Nilai Kontrak : RP. 12.000.000,000,-
Tanggal Kontrak : 23 April 2020 Kontraktor : PT. Anugerah Nedi Kasih
Konsultan Supervisi : CV. Cipta Buana Lestari
Pekerjaan Kurang Pekerjaan Tambah Rencana CCO
Uraian Volume Bobot Harga satuan Jumlah

No. Sat. Bobot


Volume Jumlah Volume Jumlah Volume Jumlah
tertim bang Keterangan
Pekerjaan Kontrak (%) (Rp) (Rp)
(Rp) (Rp) (Rp) (%)
DEVISI. I UMUM
1.2 Mobilisasi Ls 1.00 1.513 165,055,000.00 165,055,000.00 0.00 0.00 0.00 0.00 1.00 165,055,000.00 1.513 Tetap
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 0.451 49,200,000.00 49,200,000.00 0.00 0.00 0.00 0.00 1.00 49,200,000.00 0.451 Tetap
1.8.(2) Jembatan Sementara Ls 0.00 0.000 30,000,000.00 - 0.00 0.00 1.00 30,000,000.00 1.00 30,000,000.00 0.275 Baru
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 0.518 56,550,003.83 56,550,003.83 0.00 0.00 0.00 0.00 1.00 56,550,003.83 0.518 Tetap
Skh-1.1.18(1) Relokasi Tiang Telepon Yang Ada Buah 0.00 0.00 1,500,000.00 - 0.00 0.00 8.00 12,000,000.00 8.00 12,000,000.00 0.110 Baru
Skh-1.1.18(2) Relokasi Tiang Listrik Yang ada, Tegangan Rendah Buah 0.00 0.00 1,500,000.00 - 0.00 0.00 2.00 3,000,000.00 2.00 3,000,000.00 0.027 Baru
Skh-1.1.18(4) Relokasi Pipa Utilitas Gas/Air yang ada M1 0.00 0.00 135,000.00 - 0.00 0.00 5,000.00 675,000,000.00 5,000.00 675,000,000.00 6.187 Baru
Skh-1.1.18(4) Relokasi Pipa Utilitas Fiber optik yang ada M1 0.00 0.00 60,000.00 - 0.00 0.00 1,000.00 60,000,000.00 1,000.00 60,000,000.00 0.550 Baru
Skh-1.1.18(9) Relokasi Tiang Lampu Penerangan Jalan Buah 0.00 0.00 1,500,000.00 - 0.00 0.00 18.00 27,000,000.00 18.00 27,000,000.00 0.247 Baru
Pengantian Pagar Halaman yang di bongkar ls 0.00 0.00 15,000,000.00 - 0.00 0.00 1.00 15,000,000.00 1.00 15,000,000.00 0.137 Baru
270,805,003.83 0.00 822,000,000.00 1,092,805,003.83
DIVISI. II DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 829.00 0.761 100,199.07 83,065,029.03 0.00 0.00 1,171.00 117,333,110.97 2,000.00 200,398,140.00 1.837 bertambah
2.2.(1) Pasangan Batu dengan Mortar M3 300.00 4.646 1,689,408.21 506,822,461.83 0.00 0.00 13.31 22,487,955.50 313.31 529,310,417.33 4.852 bertambah
589,887,490.86 0.00 139,821,066.47 729,708,557.33
DIVISI. III PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(9) Galian Perkerasan Berbutir M3 1,100.00 2.459 243,878.91 268,266,804.43 0.00 0.00 500.00 121,939,456.56 1,600.00 390,206,260.99 3.577 bertambah
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 495.10 2.226 490,409.90 242,801,941.49 0.00 0.00 304.90 149,525,978.51 800.00 392,327,920.00 3.596 bertambah
511,068,745.92 0.00 271,465,435.07 782,534,180.99
DIVISI. V PEKERJAAN PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN
5.3.(1a) Perkerasan Beton Semen M3 1,260.00 32.777 2,837,862.79 3,575,707,121.12 0.00 0.00 0.00 0.00 1,260.000 3,575,707,121.12 32.777 Tetap
3,575,707,121.12 0.00 0.00 3,575,707,121.12
DIVISI. VI PEKERJAAN ASPAL
6.1(2)(a) Lapis Perekat - Aspal Cair Liter 4,872.00 0.874 19,580.22 95,394,831.84 1,722.00 33,717,138.84 0.00 0.00 3,150.000 61,677,693.00 0.565 Berkurang
6.3.(5a) Laston Lapis Aus (AC-WC) Ton 1,614.72 29.288 1,978,677.20 3,195,009,652.44 786.72 1,556,664,928.76 0.00 0.00 828.000 1,638,344,723.68 15.018 Berkurang
6.3.(8) Bahan Anti Pengelupasan Kg 175.77 0.118 73,500.00 12,919,095.00 85.64 6,294,410.44 0.00 0.00 90.132 6,624,684.56 0.061 Berkurang
3,303,323,579.28 1,596,676,478.03 0.00 1,706,647,101.24
DIVISI. VII STRUKTUR
7.1 (6) Beton Mutu sedang fc 25 Mpa M3 696.00 17.547 2,750,349.08 1,914,242,958.55 696.00 1,914,242,958.55 0.00 0.00 0.000 0.00 - Hilang
7.1 (7) a Beton Mutu sedang fc 20 Mpa M3 305.00 6.660 2,381,937.59 726,490,966.01 0.00 0.00 495.00 1,179,059,108.78 800.000 1,905,550,074.79 17.468 bertambah
7.3 (1) Baja Tulangan U 24 Polos Kg 862.50 0.161 20,365.27 17,565,043.52 0.00 0.00 53,943.50 1,098,573,826.27 54,806.000 1,116,138,869.79 10.231 bertambah
2,658,298,968.09 1,914,242,958.55 2,277,632,935.04 3,021,688,944.58

Total = 100.00 10,909,090,909.09 3,510,919,436.59 3,510,919,436.59 10,909,090,909.09 100.000 12.56


PPN (10%) 1,090,909,090.91 PPN (10%) 1,090,909,090.91
Total 12,000,000,000.00 Total 12,000,000,000.00

PEJABAT PEMBUAT KOMITMEN, PEJABAT PELAKSANA TEKNIS KEGIATAN , KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG Pelebaran Dan Peningkatan Jalan CV. CIPTA BUANA LESTARI, PT. ANUGERAH NEDI KASIH
PROVINSI PAPUA Lampu Merah Waena - Perumnas III (MYC)

GIRIUS ONE YOMAN, S.Pd, M.Si YOHANIS MOMOT, ST. MT EDO HARDI, ST AGUNG SUCIPTO, ST
Pembina Tk.I NIP . 19720626 200502 1 008 Supervision Engineering Site Manager
NIP. 19760314 200112 1 007