HARGA SATUAN UPAH BORONG PEKERJAAN KONSTRUKSI

SEBAGAI DASAR PENYUSUNAN RAP


TIM PERENCANAAN
PT ANGKASA PURA PROPERTI
SUB PEKERJAAN SIPIL HARGA 2019
ARSITEKTUR

Harga Satuan (Rp) Lokasi Harga Satuan (Rp) Lokasi


No Uraian Pekerjaan Satuan Pulau Kalimantan Pulau Kalimantan Keterangan
( Minimal ) ( Maksimal )
A PEKERJAAN TANAH / URUGAN
1 PEK. GALIAN TANAH LUNAK M3
2 PEK. URUGAN PASIR URUG M3
3 PEK. URUGAN TANAH M3
4 PEK. PONDASI BATU KALI M3
5 PEK. TIMBUNAN TANAH M3

B PEKERJAAN PASANGAN
1 PEK. PASANGAN BATU KALI M3
2 PEK. PASANGAN BATU GUNUNG M3
3 PEK. PASANGAN BATACO M3
4 PEK. STAMPING BATU KALI M3
5 PEK. PASANGAN BATU ALAM M2
6 PEK. PASANGAN ROOSTER BETON M2
7 PEK. PASANGAN GLASS BLOCK M2
8 PEK. PASANG BATU BATA MERAH M2
9 PEK. PASANGAN BATU BATA RINGAN M2
10 PEK. PASANGAN BATU ALAM HITAM M2

C PEKEERJAAN PLESTERAN
1 PEK. PLESTERAN TEBAL 1,5 - 2 CM M2
2 PEK. ACIAN DINDING M2

D PEKERJAAN BETON
1 PEK. PEMBESIAN KG
2 BEKISTING SLOOF M3
3 BEKISTING KOLOM M2
4 BEKISTING BALOK M2
5 BEKISTING PLAT LANTAI 1 M2
6 BEKISTING PLAT LANTAI 2 M2
7 PENGECORAN BETON READY MIX M3
8 PENGECORAN BETON SITE MIX M3
9 BEKISTING LISTPLANK, TANGGA M2
10 PEK. BETON BERTULANG M3
11 PEK. BONGKARAN BETON M3
12 PEKERJAAN RABAT BETON M3

E PEKERJAAN KAYU
1 PEK. KUSEN PINTU / JENDELA KAYU M3
2 PEK. KAP KUDA-KUDA KAYU M3
3 PEK. DAUN PINTU / JENDELA PANEL KAYU M2
4 PEK. DAUN PINTU / JENDELA KACA M2
5 PEK. DAUN PINTU / JENDELA JALUSI KAYU M2
6 PEK. DINDING PARTISI TRIPLEX + RANGKA M2
7 PEK. DINDING PARTISI DOUBLE GYPSUM + RANGKA HOLLOW M2
8 PEK. PLAFOND RGK KAYU LPS ETERNIT M2
9 PEK. PLAFOND LAPIS ETERNIT TANPA RANGKA M2
10 PEK. PLAFOND RANGKA KAYU M2
11 PEK. PLAFOND TRIPLEX TANPA RANGKA M2
12 PEK. PLAFOND GYPSUM RANGKA KAYU M2
13 PEK. KUSEN ALUMINIUM m'

F PEKERJAAN ATAP
1 PEK. PASANGAN ATAP GENTENG BETON M2
2 PEK. PASANGAN ATAP ASBES M2
3 PEK. PASANGAN ATAP SENG M2
4 PEK. PASANG NOK GENTENG BETON M'
5 PEK. PASANG NOK ASBES M'
6 PEK. PASANG NOK SENG M'
7 PEK. PASANG TALANG M'
8 PEK. PASANGAN ATAP METAL/ZINCALUME M2
9 PEK. PLAT BAJA 10 mm KG
10 PEK. PASANGAN BAJA RINGAN M2
11 PEK. PASANGAN PENUTUP ATAP ZINCALUME M2
12 PEK. PASANG RANGKA PLAFOND m2
13 PEK. PASANG GYPSUM BOARD m2
14 PEK. PASANG LIST PLAFOND m2
G PEKERJAAN PEMASANGAN LANTAI
1 PAS. LANTAI UBIN KERAMIK PUTIH 20X20 M2
2 PAS. LANTAI UBIN KERAMIK PUTIH 30X30 M2
3 PAS. LANTAI UBIN KERAMIK PUTIH 40X40 M2
4 PAS. LANTAI UBIN KERAMIK PUTIH 10X20 M2
5 PAS. DINDING KERAMIK PUTIH 20X20 M2
6 PAS. DINDING KERAMIK PUTIH 20X25 M2
7 PAS. LANTAI MARMER HITAM 60 X 60 M2
8 PAS.DINDING MARMER PUTIH 60 X 60 M2
9 PAS. DINDING BATU PALIMANAN M2
10 PAS. LANTAI GRANIT 60 X 60 M2
11 PAS. DINDING GRANIT 60 X 60 M2
12 PAS. LANTAI HT 60 X 60 M2
13 PAS. PLINT LANTAI 10 X 60 M1
14 PAS. LANTAI KERAMIK 50 X 50 M2
15 PAS. LANTAI KERAMIK 40 X 40 M2
16 PAS. DINDING KERAMIK 25 X 40 M2
17 PAS. DINDING KERAMIK 25 X 50 M2
18 PEK. NAT KERAMIK M2

H PEKERJAAN PENGECATAN
1 PEK. MENGECAT MENIE M2
2 PEK. CAT DASAR MENGKILAP KAYU M2
3 PEK. CAT MENGKILAP KAYU M2
4 PEK. CAT DINDING (BARU) M2
5 PEK. CAT DINDING (ULANGAN) M2
6 PEK. CAT DINDING KAMPROTAN M2
7 PEK. CAT RESIDU KAYU M2
8 PEK. POLITUR / TEAK OIL KAYU M2
9 PEK. CAT ATAP SENG M2
10 PEK. WATERPROOFING PLAT BETON M2
11 PEK. PENGECATAN DINDING INTERIOR ( 3 LAPIS ) M2
12 PEK. PENGECATAN DINDING EXTERIOR ( 3 LAPIS ) M2
13 PEK. PENGECATAN PLAFOND M2

I PEKERJAAN BONGKARAN
1 PEK. BONGKARAN BETON M3
2 PEK. BONGKARAN LANTAI KERAMIK M2
3 PEK. BONGKARAN DINDING KERAMIK M2
4 PEK. BONGKARAN PLAFOND M2
5 PEK. BONGKARAN URINOIR/CLOSET/WASHTAFEL SET

J PEKERJAAN SANITARI
1 PAS. CLOSET DUDUK unit
2 PAS. CLOSET JONGKOK unit
3 PAS. WASTAFEL unit
4 PAS. SOAP HOLDER unit
5 PAS. KRAN AIR unit
6 PAS. HAND DRYER unit
7 PAS. FLOOR DRAIN unit

Dibuat Oleh

Nama
Jabatan
ANALISA HARGA SATUAN PEKERJAAN
A PEKERJAAN TANAH / URUGAN
2 PEK. URUGAN PASIR URUG / Mᵌ
Bahan : Pasir urug

Upah : Pekerja
Mandor

3 PEK. URUGAN TANAH BEKAS GALIAN / Mᵌ


Upah : Pekerja
Mandor

4 PEK. PASANGAN BATU GUNUNG 1 : 4 / M³


Bahan : Semen Abu-abu (kg)
Pasir Putih/Pasangan
Batu Quarry/Batu Gunung/Batu Belah

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

5 PEK. URUGAN TANAH BEKAS GALIAN / Mᵌ


Upah : Pekerja
Mandor

B PEKERJAAN PASANGAN
1 PEK. PASANGAN BATU GUNUNG 1 : 4 / M³
Bahan : Semen Abu-abu (kg)
Pasir Putih/Pasangan
Batu Quarry/Batu Gunung/Batu Belah

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

2 PEK. PASANGAN BATU GUNUNG 1 : 4 / M³


Bahan : Semen Abu-abu (kg)
Pasir Putih/Pasangan
Batu Quarry/Batu Gunung/Batu Belah
Upah : Tukang
Kepala Tukang
Pekerja
Mandor

3 PEK. PASANGAN BATACO / M2


Bahan : Bataco 15x20x40
Semen Abu-abu (kg)
Pasir Putih/Pasangan

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

9 PEK. PASANGAN BATA RINGAN / M2


Bahan : Semen Perekat Bata Ringan 25kg
Bata Ringan 10x20x60cm

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

C PEKERJAAN PLESTERAN
1 PEK. PLESTERAN 1 : 4
Bahan : Semen Abu-abu (kg)
Pasir Putih/Pasangan

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

2 PEK. ACIAN DINDING


Bahan : Semen Abu-abu (kg)

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

D PEKERJAAN BETON
1 PEMBESIAN / KG
Bahan : Besi Beton Polos per kg
Kawat Bendrat

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

** Pembesian untuk 1 kg

2 BEKISTING SLOOF / M2
Bahan : Kayu kelas III
Paku 5-10 cm
Minyak Bekisting

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

3 BEKISTING KOLOM / M2
Bahan : Kayu kelas III
Paku 5-12 cm
Minyak Bekisting
Balok kayu kelas II
Plywood tebal 9 mm
Dolken kayu Ø8-10 cm-panj 4 m

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

4 BEKISTING BALOK / M2
Bahan : Kayu kelas III
Paku 5-12 cm
Minyak Bekisting
Balok kayu kelas II
Plywood tebal 9 mm
Dolken kayu Ø8-10 cm-panj 4 m

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

7 BETON READY MIX K-350 / M3


Bahan : Beton Ready Mix K-350

Alat : Alat bantu beton

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

11 PEK. PEMBONGKARAN DAN MEMBERSIHKAN BETON BERTULANG / M³


Upah : Tukang
Pekerja
Mandor

E PEKERJAAN KAYU

F PEKERJAAN ATAP
7 PEK. PEMASANGAN TALANG DATAR BJLS 30 / M
Bahan : Seng Plat BJLS 30
Paku Biasa
Kayu Papan Meranti 1.5/18
Flincoat

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

10 PEK. PEMASANGAN RANGKA ATAP BAJA RINGAN / M2


Bahan : Trus/Baja ringan 75x75/ m'
Paku skrup baja ringan

Upah : Tukang
Kepala Tukang
Pekerja
Mandor
11 PEK. PEMASANGAN PENUTUP ATAP ZINKCZLUME / M2
Bahan : Atap Almunium Zinkcalume 0,55mm
Paku anti karat

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

G PEKERJAAN PEMASANGAN LANTAI


1 PEK. PEMASANGAN LANTAI KERAMIK 20 X 20 cm (Setara asia tile) / M2
Bahan : Keramik 20x20 (asia)
Semen Abu-abu (kg)
Pasir Putih/Pasangan
Semen Putih (kg)

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

2 PEK. PEMASANGAN LANTAI KERAMIK 30 X 30 cm (Setara asia tile) / M2


Bahan : Keramik 30x30 (Asia)
Semen Abu-abu (kg)
Pasir Putih/Pasangan
Semen Putih (kg)

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

3 PEK. PEMASANGAN LANTAI KERAMIK 40 X 40 cm (Setara platinum) / M2


Bahan : Keramik 40x40 (Platinum)
Semen Abu-abu (kg)
Pasir Putih/Pasangan
Semen Putih (kg)
Upah : Tukang
Kepala Tukang
Pekerja
Mandor

6 PEK. PEMASANGAN DINDING KERAMIK 20/25 (Setara asia tile) / M²


Bahan : Semen Abu-abu (kg)
Semen Putih (kg)
Pasir Putih/Pasangan
Keramik 20x25 (lkad)

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

10 PEK. PEMASANGAN LANTAI GRANIT 60 X 60 cm (Setara indogress) / M2


Bahan : Semen Abu-abu (kg)
Semen Putih (kg)
Pasir Putih/Pasangan
Granite Tile 60x60cm (setara indogress)

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

11 PEK. PEMASANGAN DINDING GRANIT 60 X 60 (Setara indogress) / M²


Bahan : Semen Abu-abu (kg)
Semen Putih (kg)
Pasir Putih/Pasangan
Granite Tile 60x60cm (setara indogress)

Upah : Tukang
Kepala Tukang
Pekerja
Mandor
15 PEK. PEMASANGAN LANTAI KERAMIK 40 X 40 cm (Setara platinum) / M2
Bahan : Keramik 40x40 (Platinum)
Semen Abu-abu (kg)
Pasir Putih/Pasangan
Semen Putih (kg)

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

16 PEK. PEMASANGAN DINDING KERAMIK 25/40 (Setara platinum) / M²


Bahan : Semen Abu-abu (kg)
Semen Putih (kg)
Pasir Putih/Pasangan
Keramik 25x40 (kia)

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

H PEKERJAAN PENGECATAN
5 PEK. CAT DASAR DINDING BARU (Setara Exterior Weathershield) / M²
Bahan : Plamur tembok
Cat Dasar Tembok Weatershield (Setara ICI Dulux/Warna Stan
Cat Penutup Tembok Weatershield (Setara ICI Dulux/Warna St

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

6 PEK. CAT DASAR DINDING LAMA (Setara Exterior Weathershield) / M²


Bahan : Cat Dasar Tembok Weatershield (Setara ICI Dulux/Warna Stan
Cat Penutup Tembok Weatershield (Setara ICI Dulux/Warna St

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

13 PEK. CAT DASAR PLAFOND BARU (Setara Vinilex) / M²


Bahan : Cat Dasar Plafond (Setara Vinilex/Warna Standar Brosur) /kg
Cat Penutup (Setara Vinilex/Warna Standar Brosur) /kg

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

I PEKERJAAN BONGKARAN
1 PEK. PEMBONGKARAN DAN MEMBERSIHKAN BETON BERTULANG / M³
Upah : Tukang
Pekerja
Mandor

2 PEK. PEMBONGKARAN DAN MEMBERSIHKAN LANTAI KERAMIK/GRANIT / M²


Upah : Pekerja
Mandor

J PEKERJAAN SANITARI
1 PEK. PEK. PEMASANGAN CLOSET DUDUK / BH
Bahan : Closet duduk Kohler K-5503T-C-O
Harga closet (perlengkapan)

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

2 PEK. PEMASANGAN CLOSET JONGKOK DENGAN FLUSHER / BH


Bahan : Closet jongkok Rapi DX Top Spud Squad + Flush Amstad
Semen Abu-abu (kg)
Pasir Putih/Pasangan

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

3 PEK. PEMASANGAN WASTAFEL KERAMIK + KRAN SENSOR / BH


Bahan : Wastafel Toto LW523NJ
Kran Air Sensor Toto TN78-9V811
Harga wastafel + kran air (perlengkapan)
Semen Abu-abu (kg)
Pasir Putih/Pasangan

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

5 PEK. PEMASANGAN KRAN AIR DINDING / UNIT


Bahan : Kran air KRT067 atau setara
Seal Tape

Upah : Tukang
Kepala Tukang
Pekerja
Mandor

7 PEK. PEMASANGAN FLOOR DRAIN


Bahan : Floor drain

Upah : Tukang
Kepala Tukang
Pekerja
Mandor
1.2000 m3 x Rp 184,100.00 = Rp 220,920.00

0.3000 org x Rp 114,200.00 = Rp 34,260.00


0.0100 org x Rp 161,800.00 = Rp 1,618.00
Jumlah = Rp 35,878.00

0.3451 org x Rp 114,200.00 = Rp 39,410.00


0.0500 org x Rp 161,800.00 = Rp 8,090.00
Jumlah = Rp 47,500.00

163.0000 kg x Rp 1,232.00 = Rp 200,816.00


0.5200 m3 x Rp 321,000.00 = Rp 166,920.00
1.1000 m3 x Rp 449,400.00 = Rp 494,340.00

0.6000 org x Rp 152,300.00 = Rp 91,380.00


0.0600 org x Rp 171,300.00 = Rp 10,278.00
1.5000 org x Rp 114,200.00 = Rp 171,300.00
0.0750 org x Rp 161,800.00 = Rp 12,135.00
Jumlah = Rp 1,147,169.00

0.3451 org x Rp 114,200.00 = Rp 39,410.00


0.0500 org x Rp 161,800.00 = Rp 8,090.00
Jumlah = Rp 47,500.00

163.0000 kg x Rp 1,232.00 = Rp 200,816.00


0.5200 m3 x Rp 321,000.00 = Rp 166,920.00
1.1000 m3 x Rp 449,400.00 = Rp 494,340.00

0.6000 org x Rp 152,300.00 = Rp 91,380.00


0.0600 org x Rp 171,300.00 = Rp 10,278.00
1.5000 org x Rp 114,200.00 = Rp 171,300.00
0.0750 org x Rp 161,800.00 = Rp 12,135.00
Jumlah = Rp 1,147,169.00

163.0000 kg x Rp 1,232.00 = Rp 200,816.00


0.5200 m3 x Rp 321,000.00 = Rp 166,920.00
1.1000 m3 x Rp 449,400.00 = Rp 494,340.00
0.6000 org x Rp 152,300.00 = Rp 91,380.00
0.0600 org x Rp 171,300.00 = Rp 10,278.00
1.5000 org x Rp 114,200.00 = Rp 171,300.00
0.0750 org x Rp 161,800.00 = Rp 12,135.00
Jumlah = Rp 1,147,169.00

12.5000 bh x Rp 9,300.00 = Rp 116,250.00


12.5000 kg x Rp 1,232.00 = Rp 15,400.00
0.0400 m³ x Rp 321,000.00 = Rp 12,840.00

0.1000 org x Rp 152,300.00 = Rp 15,230.00


0.0100 org x Rp 171,300.00 = Rp 1,713.00
0.5000 org x Rp 114,200.00 = Rp 57,100.00
0.0250 org x Rp 161,800.00 = Rp 4,045.00
Jumlah = Rp 222,578.00

0.4730 kg x Rp 7,176.00 = Rp 3,394.25


12.5000 bh x Rp 15,800.00 = Rp 197,500.00

0.1500 org x Rp 152,300.00 = Rp 22,845.00


0.0150 org x Rp 171,300.00 = Rp 2,569.50
0.3571 org x Rp 114,200.00 = Rp 40,778.85
0.0180 org x Rp 161,800.00 = Rp 2,912.40
Jumlah = Rp 270,000.00

6.2400 kg x Rp 1,232.00 = Rp 7,687.68


0.0240 m3 x Rp 321,000.00 = Rp 7,704.00

0.1500 org x Rp 152,300.00 = Rp 22,845.00


0.0150 org x Rp 171,300.00 = Rp 2,569.50
0.3000 org x Rp 114,200.00 = Rp 34,260.00
0.0150 org x Rp 161,800.00 = Rp 2,427.00
Jumlah = Rp 77,493.18

3.2500 kg x Rp 1,232.00 = Rp 4,004.00

0.1000 org x Rp 152,300.00 = Rp 15,230.00


0.0100 org x Rp 171,300.00 = Rp 1,713.00
0.2000 org x Rp 114,200.00 = Rp 22,840.00
0.0100 org x Rp 161,800.00 = Rp 1,618.00
Jumlah = Rp 45,405.00
10.5000 kg x Rp 13,000.00 = Rp 136,500.00
0.1500 kg x Rp 21,400.00 = Rp 3,210.00

0.0700 org x Rp 152,300.00 = Rp 10,661.00


0.0070 org x Rp 171,300.00 = Rp 1,199.10
0.0700 org x Rp 114,200.00 = Rp 7,994.00
0.0040 org x Rp 161,800.00 = Rp 647.20
Jumlah = Rp 160,211.30
Jumlah = Rp 16,021.13

0.0450 m3 x Rp 2,862,300.00 = Rp 128,803.50


0.3000 kg x Rp 30,700.00 = Rp 9,210.00
0.1000 liter x Rp 4,000.00 = Rp 400.00

0.2600 org x Rp 152,300.00 = Rp 39,598.00


0.0260 org x Rp 171,300.00 = Rp 4,453.80
0.5200 org x Rp 114,200.00 = Rp 59,384.00
0.0260 org x Rp 161,800.00 = Rp 4,206.80
Jumlah = Rp 246,056.10

0.0400 m3 x Rp 2,862,300.00 = Rp 114,492.00


0.4000 kg x Rp 30,700.00 = Rp 12,280.00
0.2000 liter x Rp 4,000.00 = Rp 800.00
0.0150 m³ x Rp 6,420,000.00 = Rp 96,300.00
0.3500 lbr x Rp 123,100.00 = Rp 43,085.00
2.0000 batang x Rp 31,500.00 = Rp 63,000.00

0.3300 org x Rp 152,300.00 = Rp 50,259.00


0.0330 org x Rp 171,300.00 = Rp 5,652.90
0.6600 org x Rp 114,200.00 = Rp 75,372.00
0.0330 org x Rp 161,800.00 = Rp 5,339.40
Jumlah = Rp 466,580.30

0.0400 m3 x Rp 2,862,300.00 = Rp 114,492.00


0.4000 kg x Rp 30,700.00 = Rp 12,280.00
0.2000 liter x Rp 4,000.00 = Rp 800.00
0.0180 m³ x Rp 6,420,000.00 = Rp 115,560.00
0.3500 lbr x Rp 123,100.00 = Rp 43,085.00
2.0000 batang x Rp 31,500.00 = Rp 63,000.00

0.3300 org x Rp 152,300.00 = Rp 50,259.00


0.0330 org x Rp 171,300.00 = Rp 5,652.90
0.6600 org x Rp 114,200.00 = Rp 75,372.00
0.0330 org x Rp 161,800.00 = Rp 5,339.40
Jumlah = Rp 485,840.30

1.0000 m3 x Rp 1,685,800.00 = Rp 1,685,800.00

1.0000 ls x Rp 2,000.00 = Rp 2,000.00

1.0000 org x Rp 152,300.00 = Rp 152,300.00


0.1000 org x Rp 171,300.00 = Rp 17,130.00
6.0000 org x Rp 114,200.00 = Rp 685,200.00
0.3000 org x Rp 161,800.00 = Rp 48,540.00
Jumlah = Rp 2,590,970.00

0.2000 org x Rp 152,300.00 = Rp 30,460.00


8.0000 org x Rp 114,200.00 = Rp 913,600.00
0.1000 org x Rp 161,800.00 = Rp 16,180.00
Jumlah = Rp 960,240.00

0.5000 lbr x Rp 85,800.00 = Rp 42,900.00


0.0150 kg x Rp 30,700.00 = Rp 460.50
0.0096 m3 x Rp 2,289,800.00 = Rp 21,982.08
0.2500 kg x Rp 39,000.00 = Rp 9,750.00

0.4000 org x Rp 152,300.00 = Rp 60,920.00


0.0250 org x Rp 171,300.00 = Rp 4,282.50
0.1500 org x Rp 114,200.00 = Rp 17,130.00
0.0013 org x Rp 161,800.00 = Rp 210.34
Jumlah = Rp 157,635.42

4.5000 m1 x Rp 16,400.00 = Rp 73,800.00


0.0100 ktk x Rp 125,000.00 = Rp 1,250.00

0.5000 org x Rp 152,300.00 = Rp 76,150.00


0.0500 org x Rp 171,300.00 = Rp 8,565.00
0.2500 org x Rp 114,200.00 = Rp 28,550.00
0.0125 org x Rp 161,800.00 = Rp 2,022.50
Jumlah = Rp 190,337.50

0.2463 lbr x Rp 224,800.00 = Rp 55,369.46


0.2000 kg x Rp 100,000.00 = Rp 20,000.00

0.0360 org x Rp 152,300.00 = Rp 5,482.80


0.0600 org x Rp 171,300.00 = Rp 10,278.00
0.0060 org x Rp 114,200.00 = Rp 685.20
0.0018 org x Rp 161,800.00 = Rp 291.24
Jumlah = Rp 92,106.70

1.1000 dos x Rp 95,200.00 = Rp 104,720.00


4.0800 kg x Rp 1,232.00 = Rp 5,026.56
0.0090 m3 x Rp 321,000.00 = Rp 2,889.00
0.6000 kg x Rp 3,125.00 = Rp 1,875.00

0.5000 org x Rp 152,300.00 = Rp 76,150.00


0.0500 org x Rp 171,300.00 = Rp 8,565.00
0.2500 org x Rp 114,200.00 = Rp 28,550.00
0.0125 org x Rp 161,800.00 = Rp 2,022.50
Jumlah = Rp 229,798.06

1.1000 dos x Rp 120,100.00 = Rp 132,110.00


4.0800 kg x Rp 1,232.00 = Rp 5,026.56
0.0090 m3 x Rp 321,000.00 = Rp 2,889.00
0.6000 kg x Rp 3,125.00 = Rp 1,875.00

0.5000 org x Rp 152,300.00 = Rp 76,150.00


0.0500 org x Rp 171,300.00 = Rp 8,565.00
0.2500 org x Rp 114,200.00 = Rp 28,550.00
0.0125 org x Rp 161,800.00 = Rp 2,022.50
Jumlah = Rp 257,188.06

1.0500 dos x Rp 126,500.00 = Rp 132,825.00


9.8000 kg x Rp 1,232.00 = Rp 12,073.60
0.0450 m3 x Rp 321,000.00 = Rp 14,445.00
0.5000 kg x Rp 3,125.00 = Rp 1,562.50
0.3500 org x Rp 152,300.00 = Rp 53,305.00
0.0350 org x Rp 171,300.00 = Rp 5,995.50
0.7000 org x Rp 114,200.00 = Rp 79,940.00
0.0350 org x Rp 161,800.00 = Rp 5,663.00
Jumlah = Rp 305,809.60

9.3000 kg x Rp 1,232.00 = Rp 11,457.60


1.9400 kg x Rp 3,125.00 = Rp 6,062.50
0.0180 m3 x Rp 321,000.00 = Rp 5,778.00
1.0000 m2 x Rp 113,700.00 = Rp 113,700.00

0.4500 org x Rp 152,300.00 = Rp 68,535.00


0.0450 org x Rp 171,300.00 = Rp 7,708.50
0.9000 org x Rp 114,200.00 = Rp 102,780.00
0.0450 org x Rp 161,800.00 = Rp 7,281.00
Jumlah = Rp 323,302.60

9.6000 kg x Rp 1,232.00 = Rp 11,827.20


1.3000 kg x Rp 3,125.00 = Rp 4,062.50
0.0450 m3 x Rp 321,000.00 = Rp 14,445.00
1.0500 m2 x Rp 601,932.00 = Rp 632,028.60

0.3500 org x Rp 152,300.00 = Rp 53,305.00


0.0350 org x Rp 171,300.00 = Rp 5,995.50
0.7000 org x Rp 114,200.00 = Rp 79,940.00
0.0350 org x Rp 161,800.00 = Rp 5,663.00
Jumlah = Rp 807,266.80

12.5000 kg x Rp 1,232.00 = Rp 15,400.00


1.5000 kg x Rp 3,125.00 = Rp 4,687.50
0.0500 m3 x Rp 321,000.00 = Rp 16,050.00
1.0500 m2 x Rp 601,932.00 = Rp 632,028.60

0.5500 org x Rp 152,300.00 = Rp 83,765.00


0.0500 org x Rp 171,300.00 = Rp 8,565.00
0.5500 org x Rp 114,200.00 = Rp 62,810.00
0.0400 org x Rp 161,800.00 = Rp 6,472.00
Jumlah = Rp 829,778.10
1.0500 dos x Rp 126,500.00 = Rp 132,825.00
9.8000 kg x Rp 1,232.00 = Rp 12,073.60
0.0450 m3 x Rp 321,000.00 = Rp 14,445.00
0.5000 kg x Rp 3,125.00 = Rp 1,562.50

0.3500 org x Rp 152,300.00 = Rp 53,305.00


0.0350 org x Rp 171,300.00 = Rp 5,995.50
0.7000 org x Rp 114,200.00 = Rp 79,940.00
0.0350 org x Rp 161,800.00 = Rp 5,663.00
Jumlah = Rp 305,809.60

5.2000 kg x Rp 1,232.00 = Rp 6,406.40


3.5000 kg x Rp 3,125.00 = Rp 10,937.50
0.0350 m3 x Rp 321,000.00 = Rp 11,235.00
1.0000 m2 x Rp 216,000.00 = Rp 216,000.00

0.2000 org x Rp 152,300.00 = Rp 30,460.00


0.0200 org x Rp 171,300.00 = Rp 3,426.00
0.4000 org x Rp 114,200.00 = Rp 45,680.00
0.0200 org x Rp 161,800.00 = Rp 3,236.00
Jumlah = Rp 327,380.90

0.1000 kg x Rp 34,700.00 = Rp 3,470.00


0.1000 kg x Rp 126,280.00 = Rp 12,628.00
0.2600 kg x Rp 126,280.00 = Rp 32,832.80

0.0630 org x Rp 152,300.00 = Rp 9,594.90


0.0063 org x Rp 171,300.00 = Rp 1,079.19
0.0200 org x Rp 114,200.00 = Rp 2,284.00
0.0025 org x Rp 161,800.00 = Rp 404.50
Jumlah = Rp 62,293.39

0.1200 kg x Rp 126,280.00 = Rp 15,153.60


0.1800 kg x Rp 126,280.00 = Rp 22,730.40

0.0420 org x Rp 152,300.00 = Rp 6,396.60


0.0042 org x Rp 171,300.00 = Rp 719.46
0.0280 org x Rp 114,200.00 = Rp 3,197.60
0.0025 org x Rp 161,800.00 = Rp 404.50
Jumlah = Rp 48,602.16

0.1000 kg x Rp 56,600.00 = Rp 5,660.00


0.2600 kg x Rp 56,600.00 = Rp 14,716.00

0.0630 org x Rp 152,300.00 = Rp 9,594.90


0.0063 org x Rp 171,300.00 = Rp 1,079.19
0.0200 org x Rp 114,200.00 = Rp 2,284.00
0.0025 org x Rp 161,800.00 = Rp 404.50
Jumlah = Rp 33,738.59

0.2000 org x Rp 152,300.00 = Rp 30,460.00


8.0000 org x Rp 114,200.00 = Rp 913,600.00
0.1000 org x Rp 161,800.00 = Rp 16,180.00
Jumlah = Rp 960,240.00

2.0000 org x Rp 114,200.00 = Rp 228,400.00


0.1000 org x Rp 161,800.00 = Rp 16,180.00
Jumlah = Rp 244,580.00
244.580/10 m2 = Rp 24,458.00

1.0000 unit x Rp 8,624,000.00 = Rp 8,624,000.00


0.0600 ls x Rp 8,624,000.00 = Rp 517,440.00

1.1000 org x Rp 152,300.00 = Rp 167,530.00


0.0100 org x Rp 171,300.00 = Rp 1,713.00
3.3000 org x Rp 114,200.00 = Rp 376,860.00
0.1600 org x Rp 161,800.00 = Rp 25,888.00
Jumlah = Rp 9,713,431.00

1.0000 unit x Rp 4,851,720.00 = Rp 4,851,720.00


6.0000 kg x Rp 1,232.00 = Rp 7,392.00
0.0100 m3 x Rp 321,000.00 = Rp 3,210.00

1.5000 org x Rp 152,300.00 = Rp 228,450.00


0.1500 org x Rp 171,300.00 = Rp 25,695.00
1.0000 org x Rp 114,200.00 = Rp 114,200.00
0.1600 org x Rp 161,800.00 = Rp 25,888.00
Jumlah = Rp 5,256,555.00

1.0000 unit x Rp 2,146,000.00 = Rp 2,146,000.00


1.0000 bh x Rp 10,980,608.00 = Rp 10,980,608.00
12.0000 % x Rp 13,126,608.00 = Rp 1,575,192.96
6.0000 kg x Rp 1,232.00 = Rp 7,392.00
0.0100 m3 x Rp 321,000.00 = Rp 3,210.00

1.4500 org x Rp 152,300.00 = Rp 220,835.00


0.1500 org x Rp 171,300.00 = Rp 25,695.00
1.2000 org x Rp 114,200.00 = Rp 137,040.00
0.0600 org x Rp 161,800.00 = Rp 9,708.00
Jumlah = Rp 15,105,680.96

1.0000 unit x Rp 233,750.00 = Rp 233,750.00


0.0250 bh x Rp 6,300.00 = Rp 157.50

0.4000 org x Rp 152,300.00 = Rp 60,920.00


0.0400 org x Rp 171,300.00 = Rp 6,852.00
0.0100 org x Rp 114,200.00 = Rp 1,142.00
0.0050 org x Rp 161,800.00 = Rp 809.00
Jumlah = Rp 303,630.50

1.0000 unit x Rp 430,700.00 = Rp 430,700.00

0.1000 org x Rp 152,300.00 = Rp 15,230.00


0.0100 org x Rp 171,300.00 = Rp 1,713.00
0.0100 org x Rp 114,200.00 = Rp 1,142.00
0.0050 org x Rp 161,800.00 = Rp 809.00
Jumlah = Rp 449,594.00
57,100.00 0.35
39,410.00
65,190.00 47,500.00 17,690.00

70 bh Bata mera 78
14.37 kg Semen 11.5
0.04 m3 Pasir pasa 0.043
0.3 oh Pekerja 0.3

57,100.00 0.35
39,410.00
65,190.00 47,500.00 17,690.00

70 bh Bata mera 78
14.37 kg Semen 11.5
0.04 m3 Pasir pasa 0.043
0.3 oh Pekerja 0.3
70 bh Bata mera 78
14.37 kg Semen 11.5
0.04 m3 Pasir pasa 0.043
0.3 oh Pekerja 0.3

39,970.00 0.36
40,778.85
269,191.15 270,000.00 808.85
Err:509
0.04 25
Err:509

Err:509
10700000
12846000 13126608 280608
10980608

14791400 15105680.96 314280.96


NO MATERIAL SATUAN PEMKOT
Kayu meranti Uk. 5×7×400 cm m3 Rp 2,862,300
Paku biasa 4" kg Rp 30,700
Pasir urug m3 Rp 184,100
Minyak bekisting liter Rp 4,000
Plywood 9 mm lbr Rp 123,100
Kayu bangkirai Uk. 6×12×400 cm m3 Rp 6,420,000
Dolken K.Galam Ø10 panj. 400 cm btg Rp 31,500
Dolken K.Galam Ø8 panj. 400 cm btg Rp 13,900
AKTUAL KONTRAK PAYUNG
HARGA SATUAN UPAH BORONG PEKERJAAN KONSTRUKSI
SEBAGAI DASAR PENYUSUNAN RAP
TIM PERENCANAAN
PT ANGKASA PURA PROPERTI
SUB PEKERJAAN SIPIL HARGA 2019
ARSITEKTUR

Harga Satuan (Rp) Lokasi Harga Satuan (Rp) Lokasi


No Uraian Pekerjaan Satuan
Pulau Jawa ( Minimal ) Pulau Jawa ( Maksimal )
Keterangan

A PEKERJAAN TANAH / URUGAN


1 PEK. GALIAN TANAH LUNAK M3 Rp 85,000.00 Rp 90,000.00
2 PEK. URUGAN PASIR URUG M3 Rp 65,000.00 Rp 70,000.00
3 PEK. URUGAN TANAH M3
4 PEK. PONDASI BATU KALI M3 Rp 75,000.00 Rp 85,000.00
5 PEK. TIMBUNAN TANAH M3

B PEKERJAAN PASANGAN
1 PEK. PASANGAN BATU KALI M3
2 PEK. PASANGAN BATU GUNUNG M3
3 PEK. PASANGAN BATACO M3
4 PEK. STAMPING BATU KALI M3
5 PEK. PASANGAN BATU ALAM M2
6 PEK. PASANGAN ROOSTER BETON M2
7 PEK. PASANGAN GLASS BLOCK M2
8 PEK. PASANG BATU BATA MERAH M2 Rp 28,000.00 Rp 32,000.00
9 PEK. PASANGAN BATU BATA RINGAN M2 Rp 25,000.00 Rp 31,000.00
10 PEK. PASANGAN BATU ALAM HITAM M2
C PEKEERJAAN PLESTERAN
1 PEK. PLESTERAN TEBAL 1,5 - 2 CM M2 Rp 28,000.00 Rp 35,000.00
2 PEK. ACIAN DINDING M2 Rp 18,000.00 Rp 22,500.00

D PEKERJAAN BETON
1 PEK. PEMBESIAN KG Rp 900.00 Rp 1,250.00
2 BEKISTING SLOOF M3 Rp 89,000.00 Rp 95,000.00
3 BEKISTING KOLOM M2 Rp 90,000.00 Rp 110,000.00
4 BEKISTING BALOK M2 Rp 125,000.00 Rp 135,000.00
5 BEKISTING PLAT LANTAI 1 M2 Rp 125,000.00 Rp 145,000.00
6 BEKISTING PLAT LANTAI 2 M2 Rp 131,250.00 Rp 152,250.00
7 PENGECORAN BETON READY MIX M3 Rp 75,000.00 Rp 82,000.00
8 PENGECORAN BETON SITE MIX M3 Rp 225,000.00 Rp 250,000.00
9 BEKISTING LISTPLANK, TANGGA M2
10 PEK. BETON BERTULANG M3
11 PEK. BONGKARAN BETON M3
12 PEKERJAAN RABAT BETON M3

E PEKERJAAN KAYU
1 PEK. KUSEN PINTU / JENDELA KAYU M3
2 PEK. KAP KUDA-KUDA KAYU M3
3 PEK. DAUN PINTU / JENDELA PANEL KAYU M2
4 PEK. DAUN PINTU / JENDELA KACA M2
5 PEK. DAUN PINTU / JENDELA JALUSI KAYU M2
6 PEK. DINDING PARTISI TRIPLEX + RANGKA M2
7 PEK. DINDING PARTISI DOUBLE GYPSUM + RANGKA HOLLOW M2
8 PEK. PLAFOND RGK KAYU LPS ETERNIT M2
9 PEK. PLAFOND LAPIS ETERNIT TANPA RANGKA M2
10 PEK. PLAFOND RANGKA KAYU M2
11 PEK. PLAFOND TRIPLEX TANPA RANGKA M2
12 PEK. PLAFOND GYPSUM RANGKA KAYU M2
13 PEK. KUSEN ALUMINIUM m'

F PEKERJAAN ATAP
1 PEK. PASANGAN ATAP GENTENG BETON M2
2 PEK. PASANGAN ATAP ASBES M2
3 PEK. PASANGAN ATAP SENG M2
4 PEK. PASANG NOK GENTENG BETON M'
5 PEK. PASANG NOK ASBES M'
6 PEK. PASANG NOK SENG M'
7 PEK. PASANG TALANG M'
8 PEK. PASANGAN ATAP METAL/ZINCALUME M2
9 PEK. PLAT BAJA 10 mm KG
10 PEK. PASANGAN BAJA RINGAN M2 Rp 25,000.00 Rp 32,000.00
11 PEK. PASANGAN PENUTUP ATAP ZINCALUME M2 Rp 25,000.00 Rp 30,000.00
12 PEK. PASANG RANGKA PLAFOND m2 Rp 18,000.00 Rp 25,000.00
13 PEK. PASANG GYPSUM BOARD m2 Rp 25,000.00 Rp 35,000.00
14 PEK. PASANG LIST PLAFOND m2 Rp 5,000.00 Rp 11,000.00

G PEKERJAAN PEMASANGAN LANTAI


1 PAS. LANTAI UBIN KERAMIK PUTIH 20X20 M2
2 PAS. LANTAI UBIN KERAMIK PUTIH 30X30 M2
3 PAS. LANTAI UBIN KERAMIK PUTIH 40X40 M2
4 PAS. LANTAI UBIN KERAMIK PUTIH 10X20 M2
5 PAS. DINDING KERAMIK PUTIH 20X20 M2
6 PAS. DINDING KERAMIK PUTIH 20X25 M2
7 PAS. LANTAI MARMER HITAM 60 X 60 M2
8 PAS.DINDING MARMER PUTIH 60 X 60 M2
9 PAS. DINDING BATU PALIMANAN M2
10 PAS. LANTAI GRANIT 60 X 60 M2
11 PAS. DINDING GRANIT 60 X 60 M2
12 PAS. LANTAI HT 60 X 60 M2 Rp 55,000.00 Rp 65,000.00
13 PAS. PLINT LANTAI 10 X 60 M1 Rp 15,000.00 Rp 22,500.00
14 PAS. LANTAI KERAMIK 50 X 50 M2 Rp 35,000.00 Rp 50,000.00
15 PAS. LANTAI KERAMIK 40 X 40 M2 Rp 35,000.00 Rp 50,000.00
16 PAS. DINDING KERAMIK 25 X 40 M2 Rp 85,000.00 Rp 125,000.00
17 PAS. DINDING KERAMIK 25 X 50 M2 Rp 85,000.00 Rp 125,000.00
18 PEK. NAT KERAMIK M2 Rp 12,500.00 Rp 18,000.00
H PEKERJAAN PENGECATAN
1 PEK. MENGECAT MENIE M2
2 PEK. CAT DASAR MENGKILAP KAYU M2
3 PEK. CAT MENGKILAP KAYU M2
4 PEK. CAT DINDING (BARU) M2
5 PEK. CAT DINDING (ULANGAN) M2
6 PEK. CAT DINDING KAMPROTAN M2
7 PEK. CAT RESIDU KAYU M2
8 PEK. POLITUR / TEAK OIL KAYU M2
9 PEK. CAT ATAP SENG M2
10 PEK. WATERPROOFING PLAT BETON M2
11 PEK. PENGECATAN DINDING INTERIOR ( 3 LAPIS ) M2 Rp 12,000.00 Rp 15,000.00
12 PEK. PENGECATAN DINDING EXTERIOR ( 3 LAPIS ) M2 Rp 19,000.00 Rp 21,000.00
13 PEK. PENGECATAN PLAFOND M2 Rp 12,000.00 Rp 15,000.00

I PEKERJAAN BONGKARAN
1 PEK. BONGKARAN BETON M3
2 PEK. BONGKARAN LANTAI KERAMIK M2
3 PEK. BONGKARAN DINDING KERAMIK M2
4 PEK. BONGKARAN PLAFOND M2
5 PEK. BONGKARAN URINOIR/CLOSET/WASHTAFEL SET

J PEKERJAAN SANITARI
1 PAS. CLOSET DUDUK unit Rp 85,000.00 Rp 115,000.00
2 PAS. CLOSET JONGKOK unit Rp 85,000.00 Rp 115,000.00
3 PAS. WASTAFEL unit Rp 85,000.00 Rp 115,000.00
4 PAS. SOAP HOLDER unit Rp 50,000.00 Rp 65,000.00
5 PAS. KRAN AIR unit Rp 50,000.00 Rp 65,000.00
6 PAS. HAND DRYER unit
7 PAS. FLOOR DRAIN unit

Dibuat Oleh

Nama
Jabatan
HARGA SATUAN UPAH BORONG PEKERJAAN KONSTRUKSI
SEBAGAI DASAR PENYUSUNAN RAP
TIM PERENCANAAN
PT ANGKASA PURA PROPERTI
SUB PEKERJAAN SIPIL HARGA 2019
ARSITEKTUR

Harga Satuan (Rp) Lokasi Harga Satuan (Rp) Lokasi


No Uraian Pekerjaan Satuan
Pulau Bali ( Minimal ) Pulau Bali ( Maksimal )
Keterangan

A PEKERJAAN TANAH / URUGAN


1 PEK. GALIAN TANAH LUNAK M3
2 PEK. URUGAN PASIR URUG M3
3 PEK. URUGAN TANAH M3
4 PEK. PONDASI BATU KALI M3
5 PEK. TIMBUNAN TANAH M3

B PEKERJAAN PASANGAN
1 PEK. PASANGAN BATU KALI M3
2 PEK. PASANGAN BATU GUNUNG M3
3 PEK. PASANGAN BATACO M3
4 PEK. STAMPING BATU KALI M3
5 PEK. PASANGAN BATU ALAM M2
6 PEK. PASANGAN ROOSTER BETON M2
7 PEK. PASANGAN GLASS BLOCK M2
8 PEK. PASANG BATU BATA MERAH M2
9 PEK. PASANGAN BATU BATA RINGAN M2
10 PEK. PASANGAN BATU ALAM HITAM M2
C PEKEERJAAN PLESTERAN
1 PEK. PLESTERAN TEBAL 1,5 - 2 CM M2
2 PEK. ACIAN DINDING M2

D PEKERJAAN BETON
1 PEK. PEMBESIAN KG
2 BEKISTING SLOOF M3
3 BEKISTING KOLOM M2
4 BEKISTING BALOK M2
5 BEKISTING PLAT LANTAI 1 M2
6 BEKISTING PLAT LANTAI 2 M2
7 PENGECORAN BETON READY MIX M3
8 PENGECORAN BETON SITE MIX M3
9 BEKISTING LISTPLANK, TANGGA M2
10 PEK. BETON BERTULANG M3
11 PEK. BONGKARAN BETON M3
12 PEKERJAAN RABAT BETON M3

E PEKERJAAN KAYU
1 PEK. KUSEN PINTU / JENDELA KAYU M3
2 PEK. KAP KUDA-KUDA KAYU M3
3 PEK. DAUN PINTU / JENDELA PANEL KAYU M2
4 PEK. DAUN PINTU / JENDELA KACA M2
5 PEK. DAUN PINTU / JENDELA JALUSI KAYU M2
6 PEK. DINDING PARTISI TRIPLEX + RANGKA M2
7 PEK. DINDING PARTISI DOUBLE GYPSUM + RANGKA HOLLOW M2
8 PEK. PLAFOND RGK KAYU LPS ETERNIT M2
9 PEK. PLAFOND LAPIS ETERNIT TANPA RANGKA M2
10 PEK. PLAFOND RANGKA KAYU M2
11 PEK. PLAFOND TRIPLEX TANPA RANGKA M2
12 PEK. PLAFOND GYPSUM RANGKA KAYU M2
13 PEK. KUSEN ALUMINIUM m'

F PEKERJAAN ATAP
1 PEK. PASANGAN ATAP GENTENG BETON M2
2 PEK. PASANGAN ATAP ASBES M2
3 PEK. PASANGAN ATAP SENG M2
4 PEK. PASANG NOK GENTENG BETON M'
5 PEK. PASANG NOK ASBES M'
6 PEK. PASANG NOK SENG M'
7 PEK. PASANG TALANG M'
8 PEK. PASANGAN ATAP METAL/ZINCALUME M2
9 PEK. PLAT BAJA 10 mm KG
10 PEK. PASANGAN BAJA RINGAN M2
11 PEK. PASANGAN PENUTUP ATAP ZINCALUME M2
12 PEK. PASANG RANGKA PLAFOND m2
13 PEK. PASANG GYPSUM BOARD m2
14 PEK. PASANG LIST PLAFOND m2

G PEKERJAAN PEMASANGAN LANTAI


1 PAS. LANTAI UBIN KERAMIK PUTIH 20X20 M2
2 PAS. LANTAI UBIN KERAMIK PUTIH 30X30 M2
3 PAS. LANTAI UBIN KERAMIK PUTIH 40X40 M2
4 PAS. LANTAI UBIN KERAMIK PUTIH 10X20 M2
5 PAS. DINDING KERAMIK PUTIH 20X20 M2
6 PAS. DINDING KERAMIK PUTIH 20X25 M2
7 PAS. LANTAI MARMER HITAM 60 X 60 M2
8 PAS.DINDING MARMER PUTIH 60 X 60 M2
9 PAS. DINDING BATU PALIMANAN M2
10 PAS. LANTAI GRANIT 60 X 60 M2
11 PAS. DINDING GRANIT 60 X 60 M2
12 PAS. LANTAI HT 60 X 60 M2
13 PAS. PLINT LANTAI 10 X 60 M1
14 PAS. LANTAI KERAMIK 50 X 50 M2
15 PAS. LANTAI KERAMIK 40 X 40 M2
16 PAS. DINDING KERAMIK 25 X 40 M2
17 PAS. DINDING KERAMIK 25 X 50 M2
18 PEK. NAT KERAMIK M2
H PEKERJAAN PENGECATAN
1 PEK. MENGECAT MENIE M2
2 PEK. CAT DASAR MENGKILAP KAYU M2
3 PEK. CAT MENGKILAP KAYU M2
4 PEK. CAT DINDING (BARU) M2
5 PEK. CAT DINDING (ULANGAN) M2
6 PEK. CAT DINDING KAMPROTAN M2
7 PEK. CAT RESIDU KAYU M2
8 PEK. POLITUR / TEAK OIL KAYU M2
9 PEK. CAT ATAP SENG M2
10 PEK. WATERPROOFING PLAT BETON M2
11 PEK. PENGECATAN DINDING INTERIOR ( 3 LAPIS ) M2
12 PEK. PENGECATAN DINDING EXTERIOR ( 3 LAPIS ) M2
13 PEK. PENGECATAN PLAFOND M2

I PEKERJAAN BONGKARAN
1 PEK. BONGKARAN BETON M3
2 PEK. BONGKARAN LANTAI KERAMIK M2
3 PEK. BONGKARAN DINDING KERAMIK M2
4 PEK. BONGKARAN PLAFOND M2
5 PEK. BONGKARAN URINOIR/CLOSET/WASHTAFEL SET

J PEKERJAAN SANITARI
1 PAS. CLOSET DUDUK unit
2 PAS. CLOSET JONGKOK unit
3 PAS. WASTAFEL unit
4 PAS. SOAP HOLDER unit
5 PAS. KRAN AIR unit
6 PAS. HAND DRYER unit
7 PAS. FLOOR DRAIN unit

Dibuat Oleh

Nama
Jabatan
HARGA SATUAN UPAH BORONG PEKERJAAN KONSTRUKSI
SEBAGAI DASAR PENYUSUNAN RAP
TIM PERENCANAAN
PT ANGKASA PURA PROPERTI
SUB PEKERJAAN SIPIL HARGA 2019
ARSITEKTUR

Harga Satuan (Rp) Lokasi Harga Satuan (Rp) Lokasi


No Uraian Pekerjaan Satuan Pulau Sulawesi Pulau Sulawesi Keterangan
( Minimal ) ( Maksimal )
A PEKERJAAN TANAH / URUGAN
1 PEK. GALIAN TANAH LUNAK M3
2 PEK. URUGAN PASIR URUG M3
3 PEK. URUGAN TANAH M3
4 PEK. PONDASI BATU KALI M3
5 PEK. TIMBUNAN TANAH M3

B PEKERJAAN PASANGAN
1 PEK. PASANGAN BATU KALI M3
2 PEK. PASANGAN BATU GUNUNG M3
3 PEK. PASANGAN BATACO M3
4 PEK. STAMPING BATU KALI M3
5 PEK. PASANGAN BATU ALAM M2
6 PEK. PASANGAN ROOSTER BETON M2
7 PEK. PASANGAN GLASS BLOCK M2
8 PEK. PASANG BATU BATA MERAH M2
9 PEK. PASANGAN BATU BATA RINGAN M2
10 PEK. PASANGAN BATU ALAM HITAM M2
C PEKEERJAAN PLESTERAN
1 PEK. PLESTERAN TEBAL 1,5 - 2 CM M2
2 PEK. ACIAN DINDING M2

D PEKERJAAN BETON
1 PEK. PEMBESIAN KG
2 BEKISTING SLOOF M3
3 BEKISTING KOLOM M2
4 BEKISTING BALOK M2
5 BEKISTING PLAT LANTAI 1 M2
6 BEKISTING PLAT LANTAI 2 M2
7 PENGECORAN BETON READY MIX M3
8 PENGECORAN BETON SITE MIX M3
9 BEKISTING LISTPLANK, TANGGA M2
10 PEK. BETON BERTULANG M3
11 PEK. BONGKARAN BETON M3
12 PEKERJAAN RABAT BETON M3

E PEKERJAAN KAYU
1 PEK. KUSEN PINTU / JENDELA KAYU M3
2 PEK. KAP KUDA-KUDA KAYU M3
3 PEK. DAUN PINTU / JENDELA PANEL KAYU M2
4 PEK. DAUN PINTU / JENDELA KACA M2
5 PEK. DAUN PINTU / JENDELA JALUSI KAYU M2
6 PEK. DINDING PARTISI TRIPLEX + RANGKA M2
7 PEK. DINDING PARTISI DOUBLE GYPSUM + RANGKA HOLLOW M2
8 PEK. PLAFOND RGK KAYU LPS ETERNIT M2
9 PEK. PLAFOND LAPIS ETERNIT TANPA RANGKA M2
10 PEK. PLAFOND RANGKA KAYU M2
11 PEK. PLAFOND TRIPLEX TANPA RANGKA M2
12 PEK. PLAFOND GYPSUM RANGKA KAYU M2
13 PEK. KUSEN ALUMINIUM m'

F PEKERJAAN ATAP
1 PEK. PASANGAN ATAP GENTENG BETON M2
2 PEK. PASANGAN ATAP ASBES M2
3 PEK. PASANGAN ATAP SENG M2
4 PEK. PASANG NOK GENTENG BETON M'
5 PEK. PASANG NOK ASBES M'
6 PEK. PASANG NOK SENG M'
7 PEK. PASANG TALANG M'
8 PEK. PASANGAN ATAP METAL/ZINCALUME M2
9 PEK. PLAT BAJA 10 mm KG
10 PEK. PASANGAN BAJA RINGAN M2
11 PEK. PASANGAN PENUTUP ATAP ZINCALUME M2
12 PEK. PASANG RANGKA PLAFOND m2
13 PEK. PASANG GYPSUM BOARD m2
14 PEK. PASANG LIST PLAFOND m2

G PEKERJAAN PEMASANGAN LANTAI


1 PAS. LANTAI UBIN KERAMIK PUTIH 20X20 M2
2 PAS. LANTAI UBIN KERAMIK PUTIH 30X30 M2
3 PAS. LANTAI UBIN KERAMIK PUTIH 40X40 M2
4 PAS. LANTAI UBIN KERAMIK PUTIH 10X20 M2
5 PAS. DINDING KERAMIK PUTIH 20X20 M2
6 PAS. DINDING KERAMIK PUTIH 20X25 M2
7 PAS. LANTAI MARMER HITAM 60 X 60 M2
8 PAS.DINDING MARMER PUTIH 60 X 60 M2
9 PAS. DINDING BATU PALIMANAN M2
10 PAS. LANTAI GRANIT 60 X 60 M2
11 PAS. DINDING GRANIT 60 X 60 M2
12 PAS. LANTAI HT 60 X 60 M2
13 PAS. PLINT LANTAI 10 X 60 M1
14 PAS. LANTAI KERAMIK 50 X 50 M2
15 PAS. LANTAI KERAMIK 40 X 40 M2
16 PAS. DINDING KERAMIK 25 X 40 M2
17 PAS. DINDING KERAMIK 25 X 50 M2
18 PEK. NAT KERAMIK M2
H PEKERJAAN PENGECATAN
1 PEK. MENGECAT MENIE M2
2 PEK. CAT DASAR MENGKILAP KAYU M2
3 PEK. CAT MENGKILAP KAYU M2
4 PEK. CAT DINDING (BARU) M2
5 PEK. CAT DINDING (ULANGAN) M2
6 PEK. CAT DINDING KAMPROTAN M2
7 PEK. CAT RESIDU KAYU M2
8 PEK. POLITUR / TEAK OIL KAYU M2
9 PEK. CAT ATAP SENG M2
10 PEK. WATERPROOFING PLAT BETON M2
11 PEK. PENGECATAN DINDING INTERIOR ( 3 LAPIS ) M2
12 PEK. PENGECATAN DINDING EXTERIOR ( 3 LAPIS ) M2
13 PEK. PENGECATAN PLAFOND M2

I PEKERJAAN BONGKARAN
1 PEK. BONGKARAN BETON M3
2 PEK. BONGKARAN LANTAI KERAMIK M2
3 PEK. BONGKARAN DINDING KERAMIK M2
4 PEK. BONGKARAN PLAFOND M2
5 PEK. BONGKARAN URINOIR/CLOSET/WASHTAFEL SET

J PEKERJAAN SANITARI
1 PAS. CLOSET DUDUK unit
2 PAS. CLOSET JONGKOK unit
3 PAS. WASTAFEL unit
4 PAS. SOAP HOLDER unit
5 PAS. KRAN AIR unit
6 PAS. HAND DRYER unit
7 PAS. FLOOR DRAIN unit

Dibuat Oleh

Nama
Jabatan
HARGA SATUAN UPAH BORONG PEKERJAAN KONSTRUKSI
SEBAGAI DASAR PENYUSUNAN RAP
TIM PERENCANAAN
PT ANGKASA PURA PROPERTI
SUB PEKERJAAN SIPIL HARGA 2019
ARSITEKTUR

Harga Satuan (Rp) Lokasi Harga Satuan (Rp) Lokasi


No Uraian Pekerjaan Satuan Pulau Papua Pulau Papua Keterangan
( Minimal ) ( Maksimal )
A PEKERJAAN TANAH / URUGAN
1 PEK. GALIAN TANAH LUNAK M3
2 PEK. URUGAN PASIR URUG M3
3 PEK. URUGAN TANAH M3
4 PEK. PONDASI BATU KALI M3
5 PEK. TIMBUNAN TANAH M3

B PEKERJAAN PASANGAN
1 PEK. PASANGAN BATU KALI M3
2 PEK. PASANGAN BATU GUNUNG M3
3 PEK. PASANGAN BATACO M3
4 PEK. STAMPING BATU KALI M3
5 PEK. PASANGAN BATU ALAM M2
6 PEK. PASANGAN ROOSTER BETON M2
7 PEK. PASANGAN GLASS BLOCK M2
8 PEK. PASANG BATU BATA MERAH M2
9 PEK. PASANGAN BATU BATA RINGAN M2
10 PEK. PASANGAN BATU ALAM HITAM M2
C PEKEERJAAN PLESTERAN
1 PEK. PLESTERAN TEBAL 1,5 - 2 CM M2
2 PEK. ACIAN DINDING M2

D PEKERJAAN BETON
1 PEK. PEMBESIAN KG
2 BEKISTING SLOOF M3
3 BEKISTING KOLOM M2
4 BEKISTING BALOK M2
5 BEKISTING PLAT LANTAI 1 M2
6 BEKISTING PLAT LANTAI 2 M2
7 PENGECORAN BETON READY MIX M3
8 PENGECORAN BETON SITE MIX M3
9 BEKISTING LISTPLANK, TANGGA M2
10 PEK. BETON BERTULANG M3
11 PEK. BONGKARAN BETON M3
12 PEKERJAAN RABAT BETON M3

E PEKERJAAN KAYU
1 PEK. KUSEN PINTU / JENDELA KAYU M3
2 PEK. KAP KUDA-KUDA KAYU M3
3 PEK. DAUN PINTU / JENDELA PANEL KAYU M2
4 PEK. DAUN PINTU / JENDELA KACA M2
5 PEK. DAUN PINTU / JENDELA JALUSI KAYU M2
6 PEK. DINDING PARTISI TRIPLEX + RANGKA M2
7 PEK. DINDING PARTISI DOUBLE GYPSUM + RANGKA HOLLOW M2
8 PEK. PLAFOND RGK KAYU LPS ETERNIT M2
9 PEK. PLAFOND LAPIS ETERNIT TANPA RANGKA M2
10 PEK. PLAFOND RANGKA KAYU M2
11 PEK. PLAFOND TRIPLEX TANPA RANGKA M2
12 PEK. PLAFOND GYPSUM RANGKA KAYU M2
13 PEK. KUSEN ALUMINIUM m'

F PEKERJAAN ATAP
1 PEK. PASANGAN ATAP GENTENG BETON M2
2 PEK. PASANGAN ATAP ASBES M2
3 PEK. PASANGAN ATAP SENG M2
4 PEK. PASANG NOK GENTENG BETON M'
5 PEK. PASANG NOK ASBES M'
6 PEK. PASANG NOK SENG M'
7 PEK. PASANG TALANG M'
8 PEK. PASANGAN ATAP METAL/ZINCALUME M2
9 PEK. PLAT BAJA 10 mm KG
10 PEK. PASANGAN BAJA RINGAN M2
11 PEK. PASANGAN PENUTUP ATAP ZINCALUME M2
12 PEK. PASANG RANGKA PLAFOND m2
13 PEK. PASANG GYPSUM BOARD m2
14 PEK. PASANG LIST PLAFOND m2

G PEKERJAAN PEMASANGAN LANTAI


1 PAS. LANTAI UBIN KERAMIK PUTIH 20X20 M2
2 PAS. LANTAI UBIN KERAMIK PUTIH 30X30 M2
3 PAS. LANTAI UBIN KERAMIK PUTIH 40X40 M2
4 PAS. LANTAI UBIN KERAMIK PUTIH 10X20 M2
5 PAS. DINDING KERAMIK PUTIH 20X20 M2
6 PAS. DINDING KERAMIK PUTIH 20X25 M2
7 PAS. LANTAI MARMER HITAM 60 X 60 M2
8 PAS.DINDING MARMER PUTIH 60 X 60 M2
9 PAS. DINDING BATU PALIMANAN M2
10 PAS. LANTAI GRANIT 60 X 60 M2
11 PAS. DINDING GRANIT 60 X 60 M2
12 PAS. LANTAI HT 60 X 60 M2
13 PAS. PLINT LANTAI 10 X 60 M1
14 PAS. LANTAI KERAMIK 50 X 50 M2
15 PAS. LANTAI KERAMIK 40 X 40 M2
16 PAS. DINDING KERAMIK 25 X 40 M2
17 PAS. DINDING KERAMIK 25 X 50 M2
18 PEK. NAT KERAMIK M2
H PEKERJAAN PENGECATAN
1 PEK. MENGECAT MENIE M2
2 PEK. CAT DASAR MENGKILAP KAYU M2
3 PEK. CAT MENGKILAP KAYU M2
4 PEK. CAT DINDING (BARU) M2
5 PEK. CAT DINDING (ULANGAN) M2
6 PEK. CAT DINDING KAMPROTAN M2
7 PEK. CAT RESIDU KAYU M2
8 PEK. POLITUR / TEAK OIL KAYU M2
9 PEK. CAT ATAP SENG M2
10 PEK. WATERPROOFING PLAT BETON M2
11 PEK. PENGECATAN DINDING INTERIOR ( 3 LAPIS ) M2
12 PEK. PENGECATAN DINDING EXTERIOR ( 3 LAPIS ) M2
13 PEK. PENGECATAN PLAFOND M2

I PEKERJAAN BONGKARAN
1 PEK. BONGKARAN BETON M3
2 PEK. BONGKARAN LANTAI KERAMIK M2
3 PEK. BONGKARAN DINDING KERAMIK M2
4 PEK. BONGKARAN PLAFOND M2
5 PEK. BONGKARAN URINOIR/CLOSET/WASHTAFEL SET

J PEKERJAAN SANITARI
1 PAS. CLOSET DUDUK unit
2 PAS. CLOSET JONGKOK unit
3 PAS. WASTAFEL unit
4 PAS. SOAP HOLDER unit
5 PAS. KRAN AIR unit
6 PAS. HAND DRYER unit
7 PAS. FLOOR DRAIN unit