Anda di halaman 1dari 11

DAFTAR REKAPITULASI

Bantuan Pembangunan embung dan bangunan penampung air lainnya Kutai Timur Tender Ulang
Kec. Teluk Pandan Kabupaten Kutai Timur
APBN Tahun Anggaran 2019

HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN VOLUME (Rp) JUMLAH HARGA (Rp)

I. PEKERJAAN PERSIAPAN
1 Mobilisasi Ls 1.00 18,750,000.00 18,750,000.00
18,750,000.00
II. PEKERJAAN EMBUNG
1 Pintu Air Ls 1.00 4,350,000.00 4,350,000.00
2 Galian Biasa m³ 2,058.00 90,565.76 186,384,334.59
3 Timbunan Biasa dari Galian m³ 1,470.00 1,994.93 2,932,542.64
4 Timbunan Pilihan dari Sumber Galian m³ 330.75 #VALUE! #VALUE!
5 Pembersihan dan Pengupasan Lahan m² 800.00 8,382.47 6,705,975.31
6 Pondasi Cerucuk Penyedia dan Pemancangan Cerucuk m¹ 114.00 964,425.20 109,944,472.84
7 Pasangan Batu m³ 114.00 771,373.14 87,936,537.75

#VALUE!

JUMLAH #VALUE!
PPN 10% #VALUE!
TOTAL #VALUE!
TOTAL DIBULATKAN #VALUE!
Terbiang : Err:511
DAFTAR ANALISA HARGA SATUAN

HARGA SATUAN HARGA (Rp) JUMLAH HARGA


KODE INDEX SAT URAIAN (Rp) (Rp)
BAHAN UPAH

A. PEKERJAAN PERSIAPAN
1 1 M' Mengukur & Memasang Bouplank - SNI 03-2835-2002
0.007 M3 Kayu Papan Meranti 2,072,638.30 14,508.47
0.020 KG Paku biasa 20,977.70 419.55
0.100 OH Pekerja 101,076.60 10,107.66
0.005 OH Mandor 117,815.40 589.08
Jumlah Total 14,928.02 10,696.74 25,624.76
Overhead + Profit (15%) 3,843.71
Jumlah Total 29,468.47

1 1 M² Pembersihan dan Pengupasan Lahan


0.060 OH Pekerja 111,377.40 6,682.64
0.006 OH Mandor 101,076.60 606.46
Jumlah Total 0.00 7,289.10 7,289.10
Overhead + Profit (15%) 1,093.37
Jumlah Total 8,382.47

B. PEKERJAAN TANAH DAN PONDASI


B.1 1 M3 Galian tanah biasa - SNI 2835 : 2008
0.750 OH Pekerja 101,076.60 75,807.45
0.025 OH Mandor 117,815.40 2,945.39
Jumlah Total 78,752.84 78,752.84
Overhead + Profit (15%) 11,812.93
Jumlah Total 90,565.76

1 M3 Galian Tanah (Mekanis)


0.051 Oh Operator 160,950.00 8,224.55
0.053 Oh Mandor 117,815.40 6,197.09
0.026 Jam Excavator 1,247,941.92 31,947.31
0.334 Jam Dump Truck 1,247,941.92 417,311.78
1.000 ls Alat Bantu 1,900.00 1,900.00
Jumlah Total 465,580.73 465,580.73
Overhead + Profit (15%) 69,837.11
Jumlah Total 535,417.84

B.2 1 M3 Urugan Tanah kembali - SNI 2835 : 2008


0.025 OH Pekerja 101,076.60 2,526.92
0.008 OH Mandor 117,815.40 942.52
Jumlah Total 3,469.44 1,734.72
Overhead + Profit (15%) 260.21
Jumlah Total 1,994.93

B.6 1 M3 Pas batu SNI 2838:2008


1.200 M3 Batu Belah 185,808.42 222,970.10
136.000 Kg Semen Pc 785.94 106,887.40
0.544 M3 Pasir pasangan 167,240.04 90,978.58
0.750 OH Tukang 108,158.40 81,118.80
0.075 OH Kepala tukang 111,377.40 8,353.31
1.500 OH Pekerja 101,076.60 151,614.90
0.075 OH Mandor 117,815.40 8,836.16
Jumlah Total 420,836.09 249,923.16 670,759.25
Overhead + Profit (15%) 100,613.89
Jumlah Total 771,373.14

1 M3 Timbunan Tanah (Manual)


1.200 M3 Tanah Timbunan 61,936.14 74,323.37
0.250 OH Pekerja 101,076.60 25,269.15
0.025 OH Mandor 117,815.40 2,945.39
1,00 ls Alat Bantu 1,900.00 #VALUE!
Jumlah Total 74,323.37 #VALUE! #VALUE!
Overhead + Profit (15%) #VALUE!
Jumlah Total #VALUE!
1 M3 Timbunan Tanah (Mekanis)
1.200 M3 Tanah Timbunan 61,936.14 74,323.37
0.051 Oh Operator 160,950.00 8,224.55
0.053 Oh Mandor 117,815.40 6,197.09
0.026 Jam Excavator 1,247,941.92 31,947.31
0.334 Jam Dump Truck 1,247,941.92 417,311.78
1,00 ls Alat Bantu 1,900.00 #VALUE!
Jumlah Total 74,323.37 #VALUE! #VALUE!
Overhead + Profit (15%) #VALUE!
Jumlah Total #VALUE!

C. PEKERJAAN PANCANG
C.1 1 M' Biaya Memancang kayu 10/10 (manual)
0.125 Oh Pekerja 101,076.60 12,634.58
0.050 Oh Tukang 108,158.40 5,407.92
0.005 Oh Kep. Tukang 111,377.40 556.89
0.013 Oh mandor 117,815.40 1,472.69
Jumlah Total 0.00 20,072.07 20,072.07
Overhead + Profit (15%) 3,010.81
Jumlah Total 23,082.89

C.2 1 m Memancang kayu 10/10


1.200 m' Kayu 10/10 629,988.72 755,986.46
1.000 m' Memancang tiang 42,500.00 42,500.00
Jumlah Total 755,986.46 42,500.00 798,486.46
Overhead + Profit (15%) 119,772.97
Jumlah Total 918,259.43
TOTAL (C.1 + C.2) 941,342.31
HARGA DASAR BAHAN

No Uraian Satuan Harga Keterangan


1 2 3 7
UPAH PEKERJA
1 Pekerja Biasa Hari 101,076.60
2 Mandor Hari 117,815.40
3 Tukang Hari 108,158.40
4 Kepala Tukang Hari 111,377.40
31 Operator Hari 160,950.00
34 Juru Ukur Hari 170,607.00
BAHAN
Bahan Dinding dan Pondasi
1 Batu
Batu Pecah 1-2 cm m³ 304,945.14
Batu Pecah 0,5-1 cm m³ 295,390.94
Batu Gunung m³ 184,105.28
Batu Padas m³ 185,808.42
Batu Pasang (Bulat) m³ 185,808.42
Batu Kali m³ 182,942.16
Batu Belah m³ 185,808.42
2 Koral/batu split (crusher) -
Split Cor (Palu) m³ 222,986.72
Split Cor (Palu) Kg 159.10
Timbunan (Lokal) m³ 61,936.14
3 Pasir -
Pasir Pasangan (Lokal) m³ 150,582.50
Pasir Beton / Cor (Palu) m³ 167,240.04
Pasir Beton / Cor (Palu) Kg 128.77
Pasir Urug (Lokal) m³ 104,805.42
4 Sirtu m³ 180,117.44
5 Kapur Padam m³ 214,429.48
6 Tanah Urug / Timbunan m³ 23,345.48
7 Tanah Liat m³ 61,936.14
8 Batu Bata -
Bata Merah Bh 581.56
10 Beton Cetak (Paving Stone) -
Segi(natural)Empat 30 x 30 x 8 cm K 225 = 11/m2 Bh 7,144.88
Segi(full warna)Empat 30 x 30 x 8 cm K 225 = 11/m2 Bh 8,557.24
Segi(natural)Empat 30 x 30 x 8 cm K 400 = 11/m2 Bh 9,055.72
Segi(full warna)Empat 30 x 30 x 8 cm K 400 = 11/m2 Bh 10,468.08
13 Batu Tempel -
Batu Tempel Palimanan 15 x 30 Bh 61,936.14
Batu Tempel Paras 15 x 30 Bh 66,713.24
Batu Tempel Hitam (Candi) Bh 47,646.38
Batu Tempel Alur Andersit Bh 81,003.00
Batu Tempel Acak / Lempeng Bh 66,713.24
14 Semen PC 50 kg Zak 39,296.84
Semen PC 50 kg Kg 785.94
Semen Putih 40 Kg zak 60,980.72
Semen Putih 40 Kg Kg 1,524.52
Semen Warna Kg 1,661.60
Semen Merah Kg 664.64
Semen Abu-abu Kg 1,080.04
Bahan Besi -
1 Besi Plat -
Besi Plat 12 mm Lbr 1,405,588.98
Besi Plat 10 mm Lbr 1,167,357.08
Besi Plat 8 mm Lbr 1,029,153.50
Besi Plat 6 mm Lbr 781,408.94
Besi Plat 5 mm Lbr 595,600.52
Besi Plat 4 mm Lbr 452,661.38
Besi Plat 3 mm Lbr 366,881.28
Besi Plat 2 mm Lbr 238,231.90
Besi Plat 1 mm Lbr 166,783.10
2 Besi Beton Polos Kg 10,966.56
3 Besi Beton Kg 11,423.50
4 Besi beton Polos -
Besi Beton Ø 6 ( 5,0 ) x 11,0 m Btg 14,289.76
Besi Beton Ø 8 ( 6,4 ) x 11,0 m Btg 26,211.74
Besi Beton Ø 8 ( 7,0 ) x 11,0 m Btg 29,534.94
Besi Beton Ø 8 ( 8,0 ) x 12,0 m Btg 41,456.92
Besi Beton Ø 10 ( 8,2 ) x 11,4 m Btg 42,869.28
Besi Beton Ø 10 ( 8,5 ) x 11,4 m Btg 45,278.60
Besi Beton Ø 10 ( 9,4 ) x 11,4 m Btg 52,423.48
Besi Beton Ø 12 ( 10,4 ) x 11,4 m Btg 57,159.04
Besi Beton Ø 12 ( 10,9 ) x 11,4 m Btg 71,490.34
Besi Beton Ø 14 ( 12,9 ) x 11,5 m Btg 100,069.86
Besi Beton Ø 16 ( 13,9 ) x 10,4 m Btg 104,805.42
Besi Beton Ø 16 ( 14,2 ) x 11,5 m Btg 119,136.72
5 Besi Beton Ulir -
Besi Beton Ø 10 x 12,0 m Btg 57,159.04
Besi Beton D13 x 12,0 m Btg 100,069.86
Besi Beton D16 x 12,0 m Btg 152,451.80
Besi Beton D19 x 12,0 m Btg 209,652.38
Besi Beton D22 x 12,0 m Btg 281,101.18
6 Kawat -
Kawat Ikat Beton / Bendrat Kg 13,334.34
Kawat Wiremesh M6 Roll 2,067,196.56
Kawat Wiremesh M5 Roll 1,577,896.90
Kawat Wiremesh M8 Roll 3,435,316.46
Kawat Wiremesh Kg 9,055.72
Kawat Las Listrik dos 71,947.28
Kawat Burung Btg 19,523.80
8 Pagar 6 mm BRC 120 cm x 240 cm dia. Kawat m 405,015.00
9 Baja Profil Kg 13,334.34
10 Baja WF Kg 6,687.94
11 Baja Strip Kg 5,732.52
Bahan Paku -
1 Paku Kayu 0,5" - 1,5" / 1 - 2,5 cm Kg 18,568.38
2 Paku Kayu 2" - 6" / 5 - 7 cm Kg 18,568.38
3 Paku Beton Kg 16,657.54
4 Paku Ulin 1" Kg 18,568.38
5 Paku Ulin 1,5" - 5" Kg 18,568.38
6 Paku Seng Kg 17,612.96
7 Paku Plywood Kg 18,568.38
8 Paku Sekrup Kg 26,668.68
9 Paku Sekrup 1 - 2,5 cm Bh 5,732.52
10 Paku Asbes Kg 20,479.22
11 Paku Sirap Kg 20,479.22
12 Paku Gypsum Kg 21,933.12
13 Paku Kait Bh 1,038.50
14 Paku Sumbet Bh 623.10
15 Paku Reng Kg 13,334.34
16 Paku Genteng Metal Kg 18,568.38
17 Paku Pancing 60 x 230 Kg 18,568.38
18 Paku Pancing 50 x 231 Kg 20,479.22
19 Paku Hak Panjang 15 cm Kg 21,933.12
20 Paku Biasa Kg 20,977.70
Bahan Kayu -
1 Ulin -
Balok m³ 2,267,959.38
Balok btng 2,267,959.38
Papan m³ 2,501,455.72
Papan Siring Pagar kpj 8,557.24
2 Bengkirai -
Balok m³ 1,727,191.66
Papan m³ 2,072,638.30
3 Meranti -
Balok m³ 1,727,191.66
Papan m³ 2,072,638.30
4 Kapur -
Balok m³ 1,727,191.66
Papan m³ 2,072,638.30
11 Papan Bouwplank m³ 1,091,089.64
12 Papan Listplank m³ 2,186,956.38
30 Perancah Kayu m³ 1,308,842.32
Bahan Finishing -
1 Amplas Kayu / Besi Lbr 2,990.88
2 Meni Kayu Kg 27,624.10
3 Meni Besi Kg 28,122.58
4 Dampul Kayu Kg 22,888.54
5 Plamir Tembok Kg 24,757.84
6 Plamir Kayu Kg 26,211.74
7 Tiner A Spesial Ltr 61,936.14
8 Tiner B Spesial Ltr 31,902.72
9 Tiner A Biasa Ltr 15,743.66
10 Cat Dasar Tembok Kg 29,078.00
11 Cat Dasar Kayu Kg 19,523.80
12 Cat Dasar Besi Kg 26,211.74
13 Cat Tembok Kg 45,278.60
16 Undercoat Ltr 61,936.14
17 Cat Interior Ltr 71,490.34
18 Cat Eksterior Ltr 123,872.28
19 Alkali Primer Ltr 30,490.36
20 Alkali Ltr 38,133.72
21 Wood Filler (Dampul Melamin) Ltr 26,211.74
29 Lem Kayu Kg 22,888.54
30 Lem Vinyl Kg 22,888.54
31 Lem Aibon Kg 32,858.14
32 Sealent bh 19,523.80
38 Minyak Bekisting Ltr 1,910.84
50 Solar Ltr 3,323.20
51 Minyak Pelumas Ltr 30,988.84
55 Kuas Bh 2,492.40
57 Instalasi Listrik Titik 66,713.24
DAFTAR HARGA UPAH,BAHAN DAN PERALATAN

NO URAIAN SAT HARGA (Rp)


Daftar Harga Upah
1 Pekerja Oh 96,800.00
2 Tukang Oh 102,850.00
3 Kepala Tukang Oh 106,700.00
4 Mandor Oh 112,750.00
5 Operator Oh 154,133.07

Daftar Harga Satuan Bahan


1 Tanah Timbunan m³ 81,250.00
2 Semen kg 1,248.89
3 Pasir m³ 229,400.00
4 Koral m³ 305,866.50
5 Besi Beton kg 15,050.00
6 Kawat Bendrat kg 17,500.00
7 Wiremesh kg 11,850.00
8 Paku biasa kg 27,550.00
9 Paku Ulin kg 24,350.00
10 Karet Deletasi m¹ 242,500.00
11 Balok Ulin m³ 3,235,100.00
12 Papan Ulin m³ 3,567,750.00
13 Balok Kayu kapur m³ 2,463,750.00
14 Papan Kayu Kapur m³ 2,956,400.00
15 Kayu Perancah m³ 1,866,750.00
16 Kayu Bekisting m³ 2,053,150.00
17 Minyak Solar ltr 4,350.00
18 Cat Minyak kg 63,350.00
19 Tiner A Spesial ltr 43,150.00

Daftar Harga Sewa Peralatan


1 Con. Mixer Jam 63,250.00
2 Excavator Jam 489,500.00
3 Dump Truck 6 ton Jam 244,750.00
4 Buldozer Jam 624,250.00
5 Vibro Roller Jam 309,650.00
6 Water Tanker Jam 233,750.00
7 Compressor Jam 123,200.00
8 Jack Hammer Jam 24,200.00
TIME SCHEDULE
Pekerjaan : Bantuan Pembangunan embung dan bangunan penampung air lainnya Kutai Timur Tender Ulang
Lokasi : Kec. Teluk Pandan Kabupaten Kutai Timur
Th. Anggaran 2019

WAKTU PELAKSANAAN
BOBOT
No URAIAN PEKERJAAN JUMLAH (Rp) BULAN I BULAN II BULAN III BULAN IV Ket
%
I II III IV I II III IV I II III IV I II III
I PEKERJAAN PERSIAPAN #VALUE! ### 100
1 Mobilisasi 18,750,000.00 #VALUE! ### ###
Chart Title
II PEKERJAAN EMBUNG #VALUE! ### ### ###
1 Pintu Air 4,350,000.00 #VALUE! ### ### 75
2 Galian Biasa 186,384,334.59 #VALUE! ### ###
3 Timbunan Biasa dari Galian 2,932,542.64 #VALUE! ###
50
4 Timbunan Pilihan dari Sumber Galian #VALUE! #VALUE! ### ### ### ### #VALUE!
5 Pembersihan dan Pengupasan Lahan 6,705,975.31 #VALUE! ### ###
6 Pondasi Cerucuk Penyedia dan Pemancangan 109,944,472.84 #VALUE! ### ### 25
7 Pasangan Batu 87,936,537.75 #VALUE! ### ### ###
#VALUE!
0
TOTAL BOBOT #VALUE! #VALUE!
BOBOT RENCANA PERMINGGU ### ### ### ### ### ### ### ### ### ### ### ### ### ### #VALUE!
KOMULATIF BOBOT RENCANA PERMINGGU ### ### ### ### ### ### ### ### ### ### ### ### ### ### #VALUE!

CV. ALFI MANDIRI

MULYATI
Direktur
Satuan
No Jenis Barang/Jasa Volume
Unit
1 Mobilisasi Ls 1.00
2 Manajemen dan Keselamatan Lalu Lintas Ls 1.00
3 Galian Untuk Saluran Drainase m³ 451.08
4 Saluran Berbentuk U Tipe DS 1 (Tipe 1) m¹ 600.00
5 Saluran Berbentuk U Tipe DS 1 (Tipe 2) m¹ 72.00
6 Galian Biasa m³ 100.00
7 Timbunan Biasa dari Sumber Galian m³ 282.24
8 Lapis Pondasi Agregat Kelas A m³ 736.97
9 Lapis Pondasi Agregat Kelas B m³ 233.28
10 Perkerasan Beton Semen Fc 20 Mpa m³ 361.92
11 Perkerasan Beton Semen Fc 30 Mpa m³ 1112.02
12 Lapis Pondasi Beton Kurus m³ 491.31
13 Beton Struktur Fc 20 Mpa m³ 4.48
14 Baja Tulangan Polos BjTP 280 kg 214.60
15 Fondasi Cerucuk Penyediaan dan Pemancangan m¹ 202.00
16 Pasangan Batu m³ 22.25
17 Marka Jalan Termoplastik m² 160.85
Harga Satuan Jumlah Harga

Anda mungkin juga menyukai