DAFTAR KUANTITAS DAN HARGA

NAMA KEGIATAN : PENATAAN RTH


PEKERJAAN : PERENCANAAN TEKNIS LANJUTAN PENATAAN TAMAN MEDIAN JALAN POROS PERKOTAAN
LOKASI : TANJUNG REDEB

HARGA JUMLAH
NO SPESIFIKASI Kode SAT VOLUME SATUAN HARGA
(RP) (RP)

1 PEKERJAAN PERSIAPAN
1.0 Papan Nama Proyek Bh 1.00 150,000.00 150,000.00
1.1 Administrasi dan Dokumentasi Is 1.00 2,500,000.00 2,500,000.00
1.2 Mobilisasi dan Demobilisasi LS 1.00 3,500,000.00 3,500,000.00
1.3 Rambu Lalu Lintas ( Selama Pengerjaan ) Ls 1.00 3,000,000.00 3,000,000.00
1.4 RK3 Ls 1.00 10,000,000.00 10,000,000.00
JUMLAH 19,150,000.00

2.0 PEKERJAAN TANAH DAN BETON


2.1 Timbunan Tanah Biasa P.T 01 M3 96.00 132,182.00 12,689,472.00
2.2 Pembongkaran Kanstin Lama P.P 1 M1 400.00 21,421.00 8,568,400.00
2.3 Pembesian Besi whare Mash D 6 P.B 02 M2 186.00 103,616.00 19,272,576.00
2.4 Begisting P.B 03 M2 186.00 68,269.00 12,698,034.00
2.5 Pengecoran Leveling & pot Bunga B.T 01 M3 25.35 1,596,476.00 40,470,666.60
2.6 Pengadaan Dan Pemasanagan Kanstin M1 823.80 261,994.00 215,830,657.20
2.7 Plesteran Dan Acian P.PLES 1 M2 186.00 104,558.00 19,447,788.00
JUMLAH 328,977,593.80

3.0 PEKERJAAN PENGECATAN


3.1 Pengecatan Exterior ( Termasuk Pengecatan Tulisan ) P.CAT 1 M2 234.76 148,320.00 34,819,603.20
3.2 Pengecatan Exterior Pintu Gerbang ( Gapura ) P.CAT 1 M2 49.54 148,320.00 7,347,980.45

JUMLAH 42,167,583.65

4.0 PEKERJAAN TAMANAN


4.1 Penanaman Ruput Gajah Mini' LSC.01 M2 612.80 121,808.50 74,644,248.80
Penanaman bunga
- Asoka ( Merah/Kuning) LSC. 04 Polibag 80.00 92,466.00 7,397,280.00
- Bugenvil ( Berbunga ) & Bogenvil
LSC. 07 Polibag 8.00 310,238.50 2,481,908.00
variegata ( Berbunga )

-Ketapang Kencana LSC-08 Pohon 3.00 1,205,666.00 3,616,998.00


- Cemara Udang LSC. 02 Polibag 6.00 1,992,166.00 11,952,996.00
- Robusa LSC. 05 Polibag 81.00 86,498.50 7,006,378.50
- Sikas Sedang LSC. 03 Polibag 6.00 842,666.00 5,055,996.00
-Tabebuya Merah/kuning LSC-06 Pohon 3.00 1,508,166.00 4,524,498.00
- Pangkas Kuning/ Lagestum LSC-09 Polibag 40.00 91,888.50 3,675,540.00
- Kuncup Merah ( Minimal 1 M ) LSC-10 Polibag 8.00 448,838.50 3,590,708.00
- Pule ( Alsonia Scholaris ) Min 1,5 M LSC-11 Pohon 6.00 721,116.00 4,326,696.00
- Lili Paris Polibag 100.00 92,466.00 9,246,600.00

JUMLAH 137,519,847.30

5.0 PEKERJAAN ELEKTRIKAL


Instalasi Titik Lampu + Perlengkapan Titik 10.00 550,000.00 5,500,000.00
Box MCB + Perlengkapan Bh 2.00 350,000.00 700,000.00
Lampu LED Strip Outdoor + Perlengkapan M 30.00 75,000.00 2,250,000.00

JUMLAH 8,450,000.00

RAB MEDIAN JALAN Revisi Halaman 1