KERTAS KERJA
( WORK SHEET )

KOD DAN NAMA


PROGRAM / TP-300-2:2013
PROGRAM’S CODE & AUTOMOTIVE AFTER SALES SERVICE
NAME

TAHAP / LEVEL L2

NO. DAN TAJUK UNIT


KOMPETENSI / C19 : BRAKE SYSTEM RECTIFICATION WORK
COMPETENCY UNIT NO.
AND TITLE
1. Perform hydraulic brake system components
condition inspection
NO. DAN PENYATAAN
AKTIVITI KERJA / WORK 2. Service disc brake
ACTIVITIES NO. AND 3. Service drum brake
STATEMENT
4. Service brake booster and master pump
5. Service parking brake
Muka Surat / Page : 1
NO. KOD / CODE NO. TP-300-2:2013-C19/T(3/5)
Drpd / of : 12

TAJUK/TITLE : MEMBUKA,MEROMBAK, MEMERIKSA, MEMASANG DAN


MENGUJI FUNGSI DRUM BRAKE ASSEMBLY
Muka Surat / Page : 2
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

TUJUAN PEMBELAJARAN/INSTRUCTIONAL AIMS :

Pelatih mesti boleh:

1. Membuka drum brake assembly daripada kenderaan.


2. Merombak komponen drum brake assembly.
a. Drum
b. Wheel cylinder
c. Brake lining
3. Memasang komponen disc brake assembly.
4. Memasang disc brake assembly pada kenderaan
5. Bleeding sistem brake
6. Menguji kefungsian drum brake assembly

ARAHAN :

Anda dikehendaki melakukan kerja-kerja membuka, merombak, memeriksa,


memasang dan menguji drum brake assembly mengikut kaedah yang betul dan
mengetahui langkah-langkah keselamatan semasa melakukan kerja.

LUKISAN, DATA DAN JADUAL :


Muka Surat / Page : 3
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

PERALATAN, PERKAKASAN DAN BAHAN/ TOOLS, EQUIPMENT AND MATERIAL

Peralatan/Perkakasan/Bahan yang diperlukan oleh pelatih untuk melaksanakan kerja tersebut.


KUANTITI
BIL BAHAN UKURAN
(Bahan:Calon)
1 Brake fluid - 1:2
2 Rubber grease - 1:2

KUANTITI
BIL PERALATAN / PERKAKASAN UKURAN
(Bahan:Calon)
1 Hand Tools - 1:2
2 Manual service - 1:2
3 Fander cover - 1:2
4 Floor jack - 1:2
5 Tray - 1:2
6 Safety stand - 1:2
7 Steel rule - 1:2
8 Vernier caliper - 1:2

SOALAN/QUESTION :
1. Nyatakan fungsi master cylinder?
Muka Surat / Page : 4
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

LANGKAH KERJA BUTIRAN KERJA


Muka Surat / Page : 5
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

1.1) Letak kenderaan ditempat yang rata


1. Mengeluarkan brake
1.2) Tarik hand brake.
drum assembly dari
1.3) Longgarkan nat roda belakang.
kenderaan.
1.4) Jek kenderaan (pastikan lokasi yang betul)

-Buka nat roda dan keluarkan roda.Letak roda di bawah


kenderaan

2. Mengeluarkan drum
brake
2.1) Menanggalkan drum brake. Sekiranya sukar untuk
menanggal sila lakukan langkah berikut :-

-Masukkan screw driver melalui lubang pada backing


plate dan tolakkan tuil pelaras automatik daripada screw
pelaras.
-Putarkan menggunakan screw driver plate untuk
melepas larasan

2.2) Tanggalkan spring penegang.


Muka Surat / Page : 6
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

LANGKAH KERJA BUTIRAN KERJA

2.3) Tanggalkan hold-down spring

2.4) Keluarkan front shoe dan anchor spring

2.5) Tanggalkan hold-down spring dan pin


2.6) Tanggalkan rear shoe
2.7) Tanggalkan parking brake cable
Muka Surat / Page : 7
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

LANGKAH KERJA BUTIRAN KERJA

3. Merombak komponen 3.1) Tanggalkan brake tube daripada wheel cylinder


wheel cylinder 3.2) Tanggalkan screw dan keluarkan wheel cylinder
daripada back plate

PERHATIAN:
SEBELUM MENANGGALKAN BRAKE TUBE SEDIAKAN
TAKUNGAN UNTUK MENGGELAK CECAIR BREK JATUH
DI ATAS LANTAI

3.3) Keluarkan komponen berikut daripada wheel cylinder :-


 2 rubber boot
 2 piston
 2 piston cup
 spring
Muka Surat / Page : 8
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

LANGKAH KERJA BUTIRAN KERJA

4. Memeriksa brake lining 4.1 Menyukat ketebalan brake lining

Standard thickness : 5.0 mm


Minimim thickness : 1.0 mm

5.1 Menyukat inside diameter drum brake.

MAXIMUM DIAMETER – STANDARD DIAMETER =


5. Memeriksa drum brake WEAR

WEAR LIMIT : 2 mm / rujuk servis manual

5.2 Memeriksa sentuhan brake lining dengan brake


drum.Pastikan sentuhan sama rata.
Muka Surat / Page : 9
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

LANGKAH KERJA BUTIRAN KERJA

6. Memeriksa komponen 6.1 Bersih dan keringkan komponen cylinder


cylinder 6.2 Periksa Kehausan dan kerosakan .

 Cylinder housing
 Piston
 Spring
 Dush boot
Muka Surat / Page : 10
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

LANGKAH KERJA BUTIRAN KERJA

7. Memasang komponen 7.1 Sapukan rubber grease pada piston cup


whell cylinder. 7.2 Pasangkan spring dan piston cup

7.3 Memasang wheel cylinder pada baking plate

.
7.4 Sapukan high temperature graese pasa
bahagian yang bersentuhan :-

(a) Baking plate dengan brake shoe


(b) Anchor plate dengan brake shoe
(c) Strut dengan adjusting blot
Muka Surat / Page : 11
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

LANGKAH KERJA BUTIRAN KERJA

8. Memasang komponen
8.1 Memasang strut pada rear shoe.
drum brake.

8.2 Pasangkan parking brake cable pada lever

8.3 Pasangkan rear shoe dan hold-down


spring
Muka Surat / Page : 12
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13
Muka Surat / Page : 13
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

LANGKAH KERJA BUTIRAN KERJA

8.3 Pasangkan front shoe

8.5 Pasangkan hold-down spring dan pin


8.6 Pasangkan tension spring

8.7 Sambungkan cylinder pada flexible hose,


kemudian pasangkan cylinder pada main
pin. Masukkan cylinder di atas brake pad
Muka Surat / Page : 14
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

LANGKAH KERJA BUTIRAN KERJA

8.8 Laraskan panjang strut, pasang drum dan tarik hand


brake.
8.9 Laraskan semula sekiranya hand brake masih tinggi

8.10 Pasangkan brake drum.

8.11 Isikan brake fluid dan lakukan bleeding


8.12 Periksa kebocoran
Muka Surat / Page : 15
NO. KOD / CODE NO. TP-300-2:2013-C19/K(3/5)
Drpd / of : 13

SENARAI SEMAK KERJA/CHECKLIST


Tidak
Bil Tahap Pencapaian / Level of Terima / Catatan/
Terima / Not
No. Achievement Accepted Remark
Accepted

A. PROSES KERJA/WORK PROCESS

 Kaedah penggunaan alat


 Prosedur kerja
 Tempoh masa

B. HASIL KERJA/END RESULT

 kebolehan mengunakan alatan


 kebolehan rombak komponen
 keberkesanan memberi laporan lisan

C. SIKAP/ATTITUDE

 Kerjasama
 Menepati masa

D. KESELAMATAN KERJA/WORK SAFETY

 Kaedah kerja yang betul serta


 menitikberatkan keselamatan kerja

................................................... ....................................................
( Tandatangan dan Nama Calon ) ( Tandatangan dan Nama Pegawai Penilai )
Candidate’s Name and Signature Assessor’s Name and Signature

Tarikh/Date: ____________________ Tarikh/Date: ____________________


Muka Surat / Page : 16