Hps Pemeliharaan Gedung Kantor 3
Hps Pemeliharaan Gedung Kantor 3
1 2 3 4
A. UPAH:
1 Kepala Tukang Org/Hr 160,000.00
2 Mandor Org/Hr 155,000.00
3 Tukang Org/Hr 150,000.00
4 Pekerja Org/Hr 100,000.00
B. BAHAN:
1 Pasir Pasang M3 250,000.00
2 Pasir Beton M3 250,000.00
3 Kerikil M3 250,000.00
4 Bata Merah Bh 700.00
5 Semen PC @ 40 kg Kg 1,700.00
6 Semen Warna Kg 15,000.00
7 Kayu Bekisting (Klas III) M3 3,300,000.00
8 Kayu Meranti (Klas II) M3 5,500,000.00
9 Kayu Klas I M3 7,500,000.00
10 Dolken Kayu Btg 50,000.00
11 Besi Beton Polos Kg 15,000.00
12 Kawat Ikat Kg 15,000.00
13 Granit 60 x 60 cm M2 200,000.00
14 Plywood 9 mm Lbr 130,000.00
15 Minyak Bekisting Liter 6,000.00
16 Atap Genteng Metal M2 95,000.00
17 Paku Kayu Kg 17,000.00
18 Plamir Kg 15,000.00
19 Cat Dasar Tembok Kg 15,000.00
20 Cat Tembok Kg 30,000.00
21 Cat Minyak Kg 65,000.00
22 Kuas Buah 25,000.00
23 Air Ltr 50.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.300 100,000.00 30,000.00
Tukang Batu L.02 OH 0.100 150,000.00 15,000.00
Kepala Tukang L.03 OH 0.010 160,000.00 1,600.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 48,925.00
B BAHAN
Bata Merah Bh 70.000 700.00 49,000.00
Semen Portland Kg 18.950 1,700.00 32,215.00
Pasir Pasang M3 0.038 250,000.00 9,500.00
JUMLAH HARGA BAHAN 90,715.00
C PERALATAN
A.4.4.2.2.
Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm :
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.300 100,000.00 30,000.00
Tukang L.02 OH 0.150 150,000.00 22,500.00
Kepala Tukang L.03 OH 0.015 160,000.00 2,400.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 57,225.00
B BAHAN
Semen Portland Kg 10.224 1,700.00 17,380.80
Pasir Pasang M3 0.020 250,000.00 5,000.00
JUMLAH HARGA BAHAN 22,380.80
C PERALATAN
A.4.1.1.7.
Membuat 1 m3 beton :
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.650 100,000.00 165,000.00
Tukang L.02 OH 0.275 150,000.00 41,250.00
Kepala Tukang L.03 OH 0.028 160,000.00 4,480.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 223,595.00
B BAHAN
Semen Portland Kg 371.000 1,700.00 630,700.00
Pasir Beton Kg 698.000 250.00 174,500.00
Kerikil ( Maks 30 mm ) Kg 1047.000 250.00 261,750.00
Air Liter 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 1,077,700.00
C PERALATAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.070 100,000.00 7,000.00
Tukang Besi L.02 OH 0.070 150,000.00 10,500.00
Kepala Tukang L.03 OH 0.007 160,000.00 1,120.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 19,240.00
B BAHAN
Besi Beton ( Polos / Ulir ) Kg 10.500 15,000.00 157,500.00
Kawat Beton Kg 0.150 15,000.00 2,250.00
JUMLAH HARGA BAHAN 159,750.00
C PERALATAN
A.4.1.1.22.
(K3) Pemasangan 1 m2 bekisting untuk kolom :
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.660 100,000.00 66,000.00
Tukang Kayu L.02 OH 0.330 150,000.00 49,500.00
Kepala Tukang L.03 OH 0.033 160,000.00 5,280.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 125,895.00
B BAHAN
Kayu Klas III M3 0.040 3,300,000.00 132,000.00
Paku 5 Cm - 12 Cm Kg 0.400 17,000.00 6,800.00
Minyak Bekisting Liter 0.200 6,000.00 1,200.00
Balok Kayu Klas II M3 0.015 5,500,000.00 82,500.00
Plywood Tebal 9 mm Lembar 0.350 130,000.00 45,500.00
Dolken Kayu Galam, Ø ( 8 - 10 ) Cm, Panjang 4 M Batang 2.000 50,000.00 100,000.00
JUMLAH HARGA BAHAN 368,000.00
C PERALATAN
A.4.1.1.23.
(K3) Pemasangan 1 m2 bekisting untuk Balok :
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.660 100,000.00 66,000.00
Tukang Kayu L.02 OH 0.330 150,000.00 49,500.00
Kepala Tukang L.03 OH 0.033 160,000.00 5,280.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 125,895.00
B BAHAN
Kayu Klas III M3 0.040 3,300,000.00 132,000.00
Paku 5 Cm - 12 Cm Kg 0.400 17,000.00 6,800.00
Minyak Bekisting Liter 0.200 6,000.00 1,200.00
Balok Kayu Klas II M3 0.018 5,500,000.00 99,000.00
Plywood Tebal 9 mm Lembar 0.350 130,000.00 45,500.00
Dolken Kayu Galam, Ø ( 8 - 10 ) Cm, Panjang 4 M Batang 2.000 50,000.00 100,000.00
JUMLAH HARGA BAHAN 384,500.00
C PERALATAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.660 100,000.00 66,000.00
Tukang Kayu L.02 OH 0.330 150,000.00 49,500.00
Kepala Tukang L.03 OH 0.033 160,000.00 5,280.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 125,895.00
B BAHAN
Kayu Klas III M3 0.040 3,300,000.00 132,000.00
Paku 5 Cm - 12 Cm Kg 0.400 17,000.00 6,800.00
Minyak Bekisting Liter 0.200 6,000.00 1,200.00
Balok Kayu Klas II M3 0.015 5,500,000.00 82,500.00
Plywood Tebal 9 mm Lembar 0.350 130,000.00 45,500.00
Dolken Kayu Galam, Ø ( 8 - 10 ) Cm, Panjang 4 M Batang 6.000 50,000.00 300,000.00
JUMLAH HARGA BAHAN 568,000.00
C PERALATAN
SUPL I.
1 M3 Beton bertulang Plat Lantai :
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
SUPL II.
1 M3 Beton bertulang Ring Balok :
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
SUPL III.
1 M3 Beton bertulang kolom :
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A.4.4.3.35. a
Pemasangan 1m2 lantai Granit ukuran 60 cm x 60 cm :
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.700 100,000.00 70,000.00
Tukang L.02 OH 0.350 150,000.00 52,500.00
Kepala Tukang L.03 OH 0.035 160,000.00 5,600.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 133,525.00
B BAHAN
Granit 60 x 60 cm M2 2.780 71,942.45 200,000.00
Semen Portland Kg 10.000 1,700.00 17,000.00
Pasir Pasang M3 0.045 250,000.00 11,250.00
Semen Warna Kg 1.500 15,000.00 22,500.00
JUMLAH HARGA BAHAN 250,750.00
C PERALATAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.200 100,000.00 20,000.00
Tukang L.02 OH 0.100 150,000.00 15,000.00
Kepala Tukang L.03 OH 0.010 160,000.00 1,600.00
Mandor L.04 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 36,755.00
B BAHAN
Atap Genteng Metal M2 1.300 95,000.00 123,500.00
Paku Biasa Kg 0.020 17,000.00 340.00
JUMLAH HARGA BAHAN 123,840.00
C PERALATAN
A.4.7.1.10.
Pengecatan 1 m2 tembok baru ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup ) :
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.020 100,000.00 2,000.00
Tukang Cat L.02 OH 0.063 150,000.00 9,450.00
Kepala Tukang L.03 OH 0.0063 160,000.00 1,008.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 12,923.00
B BAHAN
Palamuur Kg 0.100 15,000.00 1,500.00
Cat Dasar Kg 0.100 15,000.00 1,500.00
Cat Penutup Kg 0.260 30,000.00 7,800.00
JUMLAH HARGA BAHAN 10,800.00
C PERALATAN