RENCANA ANGGARAN BIAYA ( RAB )

PROYEK : PEMBANGUNAN APARTEMEN PANORAMA PARAHYANGAN


PEKERJAAN : PEKERJAAN ELEKTRIKAL
LOKASI : JL. CIGADUNG RAYA BARAT, CIBEUNYING KALER - BANDUNG
BID. PEKERJAAN : PENYALUR PETIR

HARGA SATUAN JUMLAH


NO URAIAN PEKERJAAN VOLUME SAT
(Rp) (Rp)
1 2 3 4 5 6
XI. PENYALUR PETIR
Instalasi peralatan Penyalur Petir lengkap dengan Down Conductor, Head
Penyalur Petir, Tiang Penyangga, Sumuran Grounding, Assessoris,
galian, dan bobokan.

Flash Vectron FV3. Lightenig Protection Air Terminal Early Streamer


1. Emission (ESE) No Power Supply or Solar Cells No Radioactive, 1.0 LS 14,877,720.00 14,877,720.00
Discharger Current 300 kA Protection Radius 25-85 m.

Kabel Penghantar NYY 1x50mm2 merk Supreme (4 besar) Double


2. 70.0 M 143,705.25 10,059,367.50
Isolator
Grounding System. Earth Resistent < 3 Ohm Bak Kontrol, Connector
1.0 LS 29,586,375.00 29,586,375.00
3. Cable 50mm, Busbar Plate 3x150x2,5mm, Insulator.
Instalasi Diatas Bangunan. Tiang Penyangga 5m, Pipa Galvanis 2' anti
4,564,755.00 4,564,755.00
4. Karat. 1.0 LS
5. Material Bantu dan Alat Bantu Kerja 1.0 LS 2,535,975.00 2,535,975.00
6. Biaya Instal 1.0 LS 5,917,275.00 5,917,275.00
7. Akomodasi Lengkap 1.0 LS 3,381,300.00 3,381,300.00
GRAND TOTAL PEKERJAAN PENYALUR PETIR 70,922,767.50
PEMBULATAN 70,922,000.00