Anda di halaman 1dari 2

RENCANA ANGGARAN BIAYA ( RAB )

PROYEK : PEMBANGUNAN APARTEMEN PANORAMA PARAHYANGAN


PEKERJAAN : STRUKTUR DAN ARSITEKTUR
LOKASI : JL. CIGADUNG RAYA BARAT, CIBEUNYING KALER - BANDUNG
BID. PEKERJAAN : PEKERJAAN STRUKTUR

HARGA SATUAN JUMLAH (RP)


NO URAIAN PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 3 4 5 6
III PEKERJAAN STRUKTUR
1.1 Lantai parkir - 2
1.Lantai beton t=15cm (k-300) M3 566.41 4,006,726.77 2,269,450,107.53
2.lantai Ramp beton (k- 300) M3 18.90 4,006,726.77 75,727,135.88
3.lantai tangga beton 0 42.18 4,019,750.00 169,553,055.00
4.kolom beton 60 x 380 (k-300) M3 319.20 4,431,900.00 1,414,662,480.00
5.kolom beton 60 x 680 (k-300) M3 45.36 4,431,900.00 201,030,984.00
6.kolom beton 60 x 430 (k-300) M3 5.16 4,431,900.00 22,868,604.00
7.kolom beton 60 x 150 (k-300) M3 1,003.50 4,431,900.00 4,447,411,650.00
8.dinding beton t = 30 cm (k-300) M3 531.45 3,429,473.36 1,822,593,618.50
3
9.dinding core beton t = 15cm (k-300) M 217.56 3,429,473.36 746,116,224.75
10.dinding beton tinggi 100 t = 5 cm (k- 300) M3 8.54 3,429,473.36 29,287,702.52
3
11.dinding beton tinggi 160 t = 5 cm (k- 300) M 15.06 3,429,473.36 51,647,868.84
12.beton balok utama 35 x 75 (k-300) M3 393.67 5,353,670.00 2,107,579,268.90
13.beton balok anak 20 x30 (k-300) M3 86.98 5,353,670.00 465,662,216.60
14. Water profing integral liter 1,132.81 147,210.00 166,760,960.10
15.floor harder M2 4,720.05 254,381.82 1,200,694,909.49
Sub Total III.1.1 15,191,046,786.10
1.2 Lantai Parkir - 1
1.Lantai beton t=15cm (k-300) M3 566.41 4,006,726.77 2,269,450,107.53
2.lantai Ramp beton (k- 300) M3 82.83 4,006,726.77 331,877,178.03
3.lantai tangga beton M3 42.18 4,019,750.00 169,553,055.00
3
4.kolom beton 60 x380 (k-300) M 319.20 4,431,900.00 1,414,662,480.00
5.kolom beton 60 x680 (k-300) M3 45.36 4,431,900.00 201,030,984.00
3
6.kolom beton 60 x430 (k-300) M 5.16 4,431,900.00 22,868,604.00
7.kolom beton 60 x150 (k-300) M3 360.00 4,431,900.00 1,595,484,000.00
8.dinding beton t =30 cm (k-300) M3 531.45 3,429,473.36 1,822,593,618.50
3
9.dinding core beton t = 15cm (k-300) M 217.56 3,429,473.36 746,116,224.75
10.dinding beton tinggi 100 t = 5 cm (k- 300) M3 8.54 3,429,473.36 29,287,702.52
11.dinding beton tinggi 160 t = 5 cm (k- 300) M3 15.06 3,429,473.36 51,647,868.84
12.beton balok utama 35 x 75 (k-300) M3 430.63 5,353,670.00 2,305,450,912.10
13.beton balok anak 20 x30 (k-300) M3 90.82 5,353,670.00 486,220,309.40
14. Water profing integral M2 4,738.53 147,210.00 697,559,001.30
Sub Total III.1.2 12,143,802,045.96
1.3 Lantai lower gound floor
1.Lantai beton t=15cm (k-300) M3 573.35 4,006,726.77 2,297,256,791.29
2.lantai Ramp beton (k- 300) M3 18.90 4,006,726.77 75,727,135.88
3.lantai tangga beton M3 42.18 4,019,750.00 169,553,055.00
3
4.kolom beton 60 x380 (k-300) M 319.20 4,431,900.00 1,414,662,480.00
3
5.kolom beton 60 x680 (k-300) M 45.36 4,431,900.00 201,030,984.00
6.kolom beton 60 x430 (k-300) M3 5.16 4,431,900.00 22,868,604.00
7.kolom beton 60 x150 (k-300) M3 360.00 4,431,900.00 1,595,484,000.00
8.dinding beton t =30 cm (k-300) M3 217.56 3,429,473.36 746,116,224.75
9.dinding core beton t = 15cm (k-300) M3 217.56 3,429,473.36 746,116,224.75
10.dinding beton tinggi 100 t = 5 cm (k- 300) M3 8.54 3,429,473.36 29,287,702.52
11.dinding beton tinggi 160 t = 5 cm (k- 300) M3 16.61 3,429,473.36 56,963,552.55
12.beton balok utama 35 x 75 (k-300) M3 430.63 5,353,670.00 2,305,450,912.10
13.beton balok anak 20 x30 (k-300) M3 91.22 5,353,670.00 488,361,777.40
14. Water profing integral M2 199.77 147,210.00 29,408,141.70
Sub Total III.1.3 10,178,287,585.92
1.4 Lantai ground floor
1.Lantai beton t=15cm (k-300) M3 599.05 4,006,726.77 2,400,229,669.17
2.lantai Ramp beton (k- 300) M3 21.50 4,006,726.77 86,144,625.47
3.lantai tangga beton M3 42.18 4,019,750.00 169,553,055.00
4.kolom beton 60 x380 (k-300) M3 319.20 4,431,900.00 1,414,662,480.00
5.kolom beton 60 x680 (k-300) M3 45.36 4,431,900.00 201,030,984.00
6.kolom beton 60 x430 (k-300) M3 5.16 4,431,900.00 22,868,604.00
7.kolom beton 60 x150 (k-300) M3 360.00 4,431,900.00 1,595,484,000.00
8.dinding beton t =30 cm (k-300) M3 217.56 3,429,473.36 746,116,224.75
9.dinding core beton t = 15cm (k-300) M3 217.56 3,429,473.36 746,116,224.75
10.dinding beton tinggi 100 t = 5 cm (k- 300) M3 8.54 3,429,473.36 29,287,702.52
11.dinding beton tinggi 160 t = 5 cm (k- 300) M3 15.06 3,429,473.36 51,647,868.84
3
12.beton balok utama 35 x 75 (k-300) M 430.63 5,353,670.00 2,305,450,912.10
13.beton balok anak 20 x30 (k-300) M3 93.22 5,353,670.00 499,069,117.40
Sub Total III.1.4 10,267,661,467.99
1.5 Upper ground floor - 2
1.Lantai beton t=15cm (k-300) M3 577.93 4,006,726.77 2,315,607,599.87
2.lantai Ramp beton (k- 300) M3 21.50 4,006,726.77 86,144,625.47
3.lantai tangga beton M3 42.18 4,019,750.00 169,553,055.00
4.kolom beton 60 x380 (k-300) M3 319.20 4,431,900.00 1,414,662,480.00
5.kolom beton 60 x680 (k-300) M3 45.36 4,431,900.00 201,030,984.00
6.kolom beton 60 x430 (k-300) M3 5.16 4,431,900.00 22,868,604.00
7.kolom beton 60 x150 (k-300) M3 180.90 4,431,900.00 801,730,710.00
8.dinding beton t =30 cm (k-300) M3 217.56 3,429,473.36 746,116,224.75
9.dinding core beton t = 15cm (k-300) M3 8.54 3,429,473.36 29,287,702.52
3
10.dinding beton tinggi 100 t = 5 cm (k- 300) M 24.67 3,429,473.36 84,605,107.85
11.dinding beton tinggi 160 t = 5 cm (k- 300) M3 430.63 3,429,473.36 1,476,834,114.09
12.beton balok utama 35 x 75 (k-300) M3 93.22 5,353,670.00 499,069,117.40
Sub Total III.1.5 7,847,510,324.95
1.6 Upper grond floor - 1
1.Lantai beton t=15cm (k-300) M3 319.66 4,006,726.77 1,280,790,278.02
2.lantai Ramp beton (k- 300) M3 42.18 4,006,726.77 169,003,734.99
3
3.lantai tangga beton M 319.20 4,136,440.00 1,320,351,648.00
3
4.kolom beton 60 x380 (k-300) M 45.36 4,431,900.00 201,030,984.00
5.kolom beton 60 x680 (k-300) M3 5.16 4,431,900.00 22,868,604.00
6.kolom beton 60 x430 (k-300) M3 180.90 4,431,900.00 801,730,710.00
7.kolom beton 60 x150 (k-300) M3 217.56 4,431,900.00 964,204,164.00
8.dinding beton t =30 cm (k-300) M3 51.00 3,429,473.36 174,903,141.49
9.dinding core beton t = 15cm (k-300) M3 34.72 3,429,473.36 119,071,315.15
10.dinding beton tinggi 100 t = 5 cm (k- 300) M3 301.44 3,429,473.36 1,033,780,450.39
11.dinding beton tinggi 160 t = 5 cm (k- 300) M3 65.26 3,429,473.36 223,807,431.64
Sub Total III.1.6 6,311,542,461.67
TOTAL PEKERJAAN STRUKTUR 61,939,850,672.59
PEMBULATAN 61,939,850,000.00