RENCANA ANGGARAN BIAYA


PEKERJAAN STRUKTURAL GEDUNG VIP RSUD
TAHUN 2009
HARGA SATUAN TOTAL
NO. URAIAN PEKERJAAN VOLUME ANALISA
UPAH (Rp.) HARGA (Rp.)

A STRUKTUR LANTAI SEMI BASEMENT


1 Galian Tanah 4.185,41 m3 Tn.2 28.077,75 117.516.895,63
2 Urugan Tanah 1.046,35 m3 Tn.9.b. 9.359,25 9.793.074,64
3 Sloof beton bertulang K-225 96,12 m3 Bt.29 3.678.421,33 353.569.858,24
4 Pondasi batu kali 80/80 1:6 293,04 m3 Pn.4 398.477,25 116.769.773,34
5 Pondasi footplate 120/120 11,81 m3 Bt.28 2.946.923,53 34.810.534,20
6 Pondasi tiang f60cm 7.524,00 m' LS 325.000,00 2.445.300.000,00
7 Pile cap (poer) 489,29 m3 LS 3.500.000,00 1.712.515.000,00
8 Pelat semi basement tbl. 20cm 889,20 m3 LS 3.500.000,00 3.112.200.000,00
9 Kolom struktur 308,28 m3 Bt.30 5.826.431,83 1.796.143.272,39
10 Dinding beton bertulang K-225 108,00 m3 Bt.34 4.145.481,33 447.711.983,64
11 Tangga beton bertulang 21,00 m3 LS 3.750.000,00 78.750.000,00
Jumlah A 10.225.080.392,07

B STRUKTUR LANTAI DASAR


1 Balok struktur beton bertulang K-225 393,30 m3 Bt.40 3.827.454,75 1.505.337.953,18
2 Pelat lantai tebal 12cm 507,60 m3 LS 3.500.000,00 1.776.600.000,00
3 Pelat lantai ramp 14,04 m3 LS 3.500.000,00 49.140.000,00
4 Kolom struktur 307,60 m3 Bt.30 5.826.431,83 1.792.210.430,91
5 Dinding beton bertulang K-225 108,00 m3 Bt.34 4.145.481,33 447.711.983,64
6 Tangga beton bertulang 25,20 m3 LS 3.750.000,00 94.500.000,00
Jumlah B 5.665.500.367,72
C STRUKTUR LANTAI 1
1 Balok struktur beton bertulang K-225 402,51 m3 Bt.40 3.827.454,75 1.540.588.811,42
2 Pelat lantai tebal 12cm 505,44 m3 LS 3.500.000,00 1.769.040.000,00
3 Kolom struktur 307,60 m3 Bt.30 5.826.431,83 1.792.210.430,91
4 Dinding beton bertulang K-225 108,00 m3 Bt.34 4.145.481,33 447.711.983,64
5 Tangga beton bertulang 25,20 m3 LS 3.750.000,00 94.500.000,00
Jumlah C 5.644.051.225,97
D STRUKTUR LANTAI 2
1 Balok struktur beton bertulang K-225 370,17 m3 Bt.40 3.827.454,75 1.416.808.924,81
2 Pelat lantai tebal 12cm 505,44 m3 LS 3.500.000,00 1.769.040.000,00
3 Kolom struktur 302,40 m3 Bt.30 5.826.431,83 1.761.912.985,39
4 Dinding beton bertulang K-225 108,00 m3 Bt.34 4.145.481,33 447.711.983,64
5 Tangga beton bertulang 21,00 m3 LS 3.750.000,00 78.750.000,00
Jumlah D 5.474.223.893,84
E STRUKTUR LANTAI 3
1 Balok struktur beton bertulang K-225 385,70 m3 Bt.40 3.827.454,75 1.476.230.159,80
2 Pelat lantai tebal 12cm 544,32 m3 LS 3.500.000,00 1.905.120.000,00
3 Kolom struktur 302,40 m3 Bt.30 5.826.431,83 1.761.912.985,39
4 Dinding beton bertulang K-225 108,00 m3 Bt.34 4.145.481,33 447.711.983,64
5 Tangga beton bertulang 21,00 m3 LS 3.750.000,00 78.750.000,00
Jumlah E 5.669.725.128,83
F STRUKTUR ATAP DAG 1
1 Balok struktur beton bertulang K-225 385,70 m3 Bt.40 3.827.454,75 1.476.230.159,80
2 Pelat lantai tebal 10cm 453,60 m3 LS 3.500.000,00 1.587.600.000,00
3 Kolom struktur 236,16 m3 Bt.30 5.826.431,83 1.375.970.140,97
4 Dinding beton bertulang K-225 82,80 m3 Bt.34 4.145.481,33 343.245.854,12
Jumlah F 4.783.046.154,90
G STRUKTUR ATAP DAG 2
1 Balok struktur beton bertulang K-225 17,98 m3 Bt.40 3.827.454,75 68.808.067,77
2 Pelat lantai tebal 10cm 16,20 m3 LS 3.500.000,00 56.700.000,00
3 Kolom struktur 177,12 m3 Bt.30 5.826.431,83 1.031.977.605,73
4 Rangka kuda2 baja 3.355,19 kg Bs.1 15.012,60 50.370.184,08
Jumlah G 1.207.855.857,57

REKAPITULASI:
A STRUKTUR LANTAI SEMI BASEMENT 10.225.080.392,07
B STRUKTUR LANTAI DASAR 5.665.500.367,72
C STRUKTUR LANTAI 1 5.644.051.225,97
D STRUKTUR LANTAI 2 5.474.223.893,84
E STRUKTUR LANTAI 3 5.669.725.128,83
F STRUKTUR ATAP DAG 1 4.783.046.154,90
G STRUKTUR ATAP DAG 2 1.207.855.857,57
Total Biaya Struktural 38.669.483.020,91
Pembulatan 38.669.480.000,00

Terbilang : ( Tiga puluh enam milyar enam ratus enam puluh sembilan juta empat ratus delapan puluh ribu rupiah )