B. PEKERJAAN STRUKTUR
I. STRUKTUR BAWAH
1 PEKERJAAN TANAH
- Galian Tanah untuk pondasi menerus m3 189.00 83,520.00 15,785,280.00
3
- Galian Tanah Pondasi setempat (Foot Plate) m 81.80 83,520.00 6,831,936.00
3
- Urugan pasir di bawah pondasi menerus m 9.45 385,100.00 3,639,195.00
3
- Urugan tanah kembali m 47.25 17,450.00 824,512.50
3
- Urugan tanah peninggian peil lantai m 129.00 175,100.00 22,587,900.00
3
- Urugan pasir dibawah lantai 1 m 21.50 385,100.00 8,279,650.00
SUB TOTAL B.I.1 57,948,473.50
2 PEKERJAAN PONDASI
- Lantai Kerja Pondasi Telapak Beton Rabat 1PC : 3Psr : 5 Krl (t=5 cm)m3 7.34 1,062,075.00 7,795,630.50
3
- Beton Bertulang Footplate [K-225] m 15.30 15,463,343.56 236,589,156.42
3
- Beton Bertulang Kolom bawah sloof/pedestal [30/30] K-225 m 6.66 16,945,998.86 112,784,095.39
3
- Beton Bertulang Footplate Tangga [K-225] m 0.83 13,051,575.36 10,832,807.55
3
- Pasangan Batu Kosong/ Aanstamping m 37.80 600,420.00 22,695,876.00
3
- Pasangan Batu untuk pondasi menerus dalam gedung (1Pc : 5Psr) m 103.95 943,080.00 98,033,166.00
3
- Beton Bertulang Sloof Struktur 30 /25 [K-225] m 14.18 18,036,023.36 255,750,811.20
3
- Beton Bertulang Sloof Struktur 20/25 [K-225] m 6.65 18,036,023.36 119,939,555.33
SUB TOTAL B.I.2 744,481,543.07
TOTAL PEK. STRUKTUR BAWAH 802,430,016.57
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
II. STRUKTUR ATAS
1 PEKERJAAN LANTAI 1
- Beton Bertulang Kolom [30/30] K-225 m3 18.36 16,945,998.86 311,128,539.02
3
- Beton Tangga [K-225] m 4.75 15,698,573.36 74,568,223.45
SUB TOTAL B.II.1 385,696,762.46
2 PEKERJAAN LANTAI 2
Beton Bertulang Kolom [30/30] K-225 m3 18.36 16,945,998.86 311,128,539.02
3
- Beton Bertulang Balok Induk [25/30] K-225 m 23.63 17,665,091.36 417,426,108.77
3
- Beton Bertulang Balok Anak [20/25] K-225 m 0.53 17,079,312.72 9,052,035.74
3
- Beton Bertulang Pelat Lantai 2 (t=12 cm) K-225 m 50.08 17,173,454.36 860,046,594.21
SUB TOTAL B.II.2 ##########
TOTAL PEK. STRUKTUR ATAS ##########
III. STRUKTUR ATAP
1 PEKERJAAN ATAP
- Beton Bertulang Ring Balok [20/15] K-225 m3 5.07 4,592,520.00 23,284,076.40
- Beton Balok Gewel m3 0.27 4,592,520.00 1,239,980.40
3
- Kolom Gewel m 0.12 4,592,520.00 551,102.40
2
- Penutup Atap Spandex m 613.85 140,710.00 86,374,833.50
- Rangka atap baja Ringan m2 249.93 263,210.00 65,784,075.30
- Lisplank Kayu klas I m' 118.00 169,800.00 20,036,400.00
- Pek. Bubungan m' 45.00 104,455.00 4,700,475.00
TOTAL PEK. STRUKTUR ATAP 201,970,943.00
TOTAL PEK. STRUKTUR ##########
C. PEKERJAAN ARSITEKTUR
I. LANTAI 1
1 PEKERJAAN LANTAI :
1. Lantai Ubin Keramik 40x40 cm + screed mortar m2 430.00 176,467.50 75,881,025.00
2
4 Lantai Ubin Keramik 40x40 cm + screed mortar (Pada tangga) m 13.17 129,217.50 1,701,471.43
SUB TOTAL C.I.1 77,582,496.43
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
2 PEKERJAAN DINDING :
- Pasangan Dinding Batako (1Pc : 4Psr) m2 481.86 268,825.00 129,536,014.50
2
- Plesteran Dinding (1Pc : 4Psr) tebal 15 mm m 963.72 53,580.00 51,636,117.60
2
- Acian Dinding, Plat Canopy dan kolom m 995.93 21,325.00 21,238,207.25
SUB TOTAL C.I.2 202,410,339.35
3 PEKERJAAN PINTU DAN JENDELA DAN ALAT PENGGANTUNG
Kusen Pintu dan Jendela Kayu Kls I 5/11 M3 1.93 17,133,000.00 33,135,222.00
Daun Pintu Panil Kayu Kls 1 3cm M2 9.60 843,000.00 8,092,800.00
Daun Jendela Kaca Mati 5 mm M2 12.00 853,258.25 10,239,099.00
Daun Jendela Panil Kaca 5 mm M2 28.00 853,258.25 23,891,231.00
Jelusi Kayu M2 16.85 318,000.00 5,358,300.00
Ense Pintu dan Jendela Bh 6.00 34,932.50 209,595.00
Grendel Pintu Bh 48.00 29,932.50 1,436,760.00
Kunci Pintu Bh 4.00 392,450.00 1,569,800.00
Kait Angin M2 80.00 15,000.00 1,200,000.00
SUB TOTAL C.I.3 85,132,807.00
3 PEKERJAAN INSTALASI LISTRIK
Titik Sambung Instalasi Ttk 45.00 315,500.00 14,197,500.00
Box Sekring Bh 2.00 87,000.00 174,000.00
Saklar Ganda Bh 5.00 78,000.00 390,000.00
Saklar Tunggal Bh 5.00 78,000.00 390,000.00
Stop Kontak Bh 5.00 78,000.00 390,000.00
Lampu Philips 23 Watt Bh 26.00 110,000.00 2,860,000.00
Lmpu Philips 18 Watt Bh 10.00 60,000.00 600,000.00
SUB TOTAL C.I.3 19,001,500.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
4 PEKERJAAN PLAFON
- Plafon Hardpleks 5 mm, + rangka metal hollow m2 540.00 139,788.40 75,485,736.00
- List Plafond Gypsum / Cornice m' 484.00 63,845.00 30,900,980.00
SUB TOTAL C.I.4 106,386,716.00
5 PEKERJAAN PENGECATAN
- Menie Kayu Kusen m2 64.42 23,342.50 1,503,607.14
2
- Menie Lisplank m 23,342.50 -
2
- Cat Kayu m 64.42 61,547.50 3,964,582.21
2
- Cat Lisplank m - 61,547.50 -
2
Cat Tembok seluuh m 963.72 22,788.00 21,961,251.36
Cat Plafon m2 540.00 22,788.00 12,305,520.00
2
- Pleletur Daun Pintu Jendela m 40.96 23,365.00 957,030.40
SUB TOTAL C.I.5 40,691,991.11
6 PEKERJAAN LAIN-LAIN
- Pasangan Tembok Ralling Tangga m2 10.72 268,825.00 2,881,804.00
- Plesteran Dinding Tembok Tangga (1Pc : 4Psr) tebal 15 mm m2 22.33 53,580.00 1,196,441.40
2
- Acian Dinding m 22.33 21,325.00 476,187.25
3
- Beton Bertulang Kolom praktis 15 x 15 Cm m 0.10 4,251,908.57 430,505.74
- Tangga Service pipa GIP Unit 1.00 4,251,908.57 4,251,908.57
SUB TOTAL C.I.6 9,236,846.96
TOTAL PEK. LANTAI 1 540,442,696.86
I. LANTAI 1I
1 PEKERJAAN LANTAI :
1. Lantai Ubin Keramik 40x40 cm + screed mortar m2 430.00 176,467.50 75,881,025.00
2
4 Lantai Ubin Keramik 40x40 cm + screed mortar (Pada tangga) m 13.17 129,217.50 1,701,471.43
SUB TOTAL C.I.1 77,582,496.43
2 PEKERJAAN DINDING :
- Pasangan Dinding Batako (1Pc : 4Psr) m2 500.97 268,825.00 134,673,260.25
2
- Plesteran Dinding (1Pc : 4Psr) tebal 15 mm m 1,001.94 53,580.00 53,683,945.20
2
- Acian Dinding, Plat Canopy dan kolom m 1,034.15 21,325.00 22,053,248.75
SUB TOTAL C.I.2 210,410,454.20
3 PEKERJAAN PINTU DAN JENDELA DAN ALAT PENGGANTUNG
Kusen Pintu dan Jendela Kayu Kls I 5/11 M3 1.93 17,133,000.00 33,135,222.00
Daun Pintu Panil Kayu Kls 1 3cm M2 9.60 843,000.00 8,092,800.00
Daun Jendela Kaca Mati 5 mm M2 12.00 853,258.25 10,239,099.00
Daun Jendela Panil Kaca 5 mm M2 28.00 853,258.25 23,891,231.00
Jelusi Kayu M2 16.85 318,000.00 5,358,300.00
Ense Pintu dan Jendela Bh 6.00 34,932.50 209,595.00
Grendel Pintu Bh 48.00 29,932.50 1,436,760.00
Kunci Pintu Bh 4.00 392,450.00 1,569,800.00
Kait Angin M2 80.00 15,000.00 1,200,000.00
SUB TOTAL C.I.3 85,132,807.00
3 PEKERJAAN INSTALASI LISTRIK
Titik Sambung Instalasi Ttk 45.00 315,500.00 14,197,500.00
Box Sekring Bh 2.00 87,000.00 174,000.00
Saklar Ganda Bh 5.00 78,000.00 390,000.00
Saklar Tunggal Bh 5.00 78,000.00 390,000.00
Stop Kontak Bh 5.00 78,000.00 390,000.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
Lampu Philips 23 Watt Bh 26.00 110,000.00 2,860,000.00
Lmpu Philips 18 Watt Bh 10.00 60,000.00 600,000.00
SUB TOTAL C.I.3 19,001,500.00
4 PEKERJAAN PLAFON
- Plafon Hardpleks 5 mm, + rangka metal hollow m2 540.00 139,788.40 75,485,736.00
- List Plafond Gypsum / Cornice m' 484.00 63,845.00 30,900,980.00
SUB TOTAL C.I.4 106,386,716.00
5 PEKERJAAN PENGECATAN
- Menie Kayu Kusen m2 64.42 23,342.50 1,503,607.14
2
- Menie Lisplank m 23.60 23,342.50 550,883.00
2
- Cat Kayu m 64.42 61,547.50 3,964,582.21
2
- Cat Lisplank m 23.60 61,547.50 1,452,521.00
Cat Tembok seluuh m2 963.76 22,788.00 21,962,162.88
Cat Plafon m2 540.00 22,788.00 12,305,520.00
2
- Pleletur Daun Pintu Jendela m 40.96 23,365.00 957,030.40
SUB TOTAL C.I.4 42,696,306.63
TOTAL PEK. LANTAI 1I 541,210,280.26
TOTAL PEK. ARSITEKTUR ##########
3 PEKERJAAN PENGADAAN MEUBELEUR
Ongkos Angkut Ls 1.00 3,000,000.00 3,000,000.00
Meja Siswa Tunggal Bh 320.00 350,000.00 112,000,000.00
Meja Guru Bh 8.00 400,000.00 3,200,000.00
Kursi Siswa Bh 320.00 350,000.00 112,000,000.00
Kusi Guru Bh 8.00 400,000.00 3,200,000.00
White Boaed Bh 8.00 350,000.00 2,800,000.00
Almari Ruang Kelas Bh 8.00 1,500,000.00 12,000,000.00
SUB TOTAL C.I.3 248,200,000.00
REKAPITULASI
RENCANA ANGGARAN BIAYA
B. PEKERJAAN STRUKTUR
JUMLAH 4,023,725,437.87
DI BULATKAN 4,023,725,000.00
SALEH BUNGA, SH
EDGARD BOELAN TAUFIK T. AMBAO, ST
NIP. 19531217 197902 1 002
NIP. Ka. Perwakilan
Mengetahui
Ketua Pengadilan Negeri Kalabahi
B. PEKERJAAN STRUKTUR
I. STRUKTUR BAWAH
1 PEKERJAAN TANAH
- Galian Tanah untuk pondasi menerus m3 64.00 83,520.00 5,345,280.00
3
- Galian Tanah Pondasi setempat (Foot Plate) m 30.60 83,520.00 2,555,712.00
3
- Urugan pasir di bawah pondasi menerus m 3.20 385,100.00 1,232,320.00
3
- Urugan tanah kembali m 21.33 17,450.00 372,266.67
3
- Urugan tanah peninggian peil lantai m 28.80 175,100.00 5,042,880.00
3
- Urugan pasir dibawah lantai 1 m 4.80 385,100.00 1,848,480.00
SUB TOTAL B.I.1 16,396,938.67
2 PEKERJAAN PONDASI
m3
- Lantai Kerja Pondasi Telapak Beton Rabat 1PC : 3Psr : 5 Krl (t= 10cm) 2.04 1,062,075.00 2,166,633.00
3
- Beton Bertulang Footplate [K-225] m 5.10 15,463,343.56 78,863,052.14
3
- Beton Bertulang Kolom bawah sloof/pedestal [30/30] K-225 m 2.22 16,945,998.86 37,620,117.46
3
- Beton Bertulang Footplate Tangga [K-225] m 0.83 13,051,575.36 10,832,807.55
3
- Pasangan Batu Kosong/ Aanstamping m 12.80 600,420.00 7,685,376.00
3
- Pasangan Batu untuk pondasi menerus dalam gedung (1Pc : 5Psr) m 35.20 943,080.00 33,196,416.00
3
- Beton Bertulang Sloof Struktur 30 /25 [K-225] m 4.80 18,036,023.36 86,572,912.11
3
- Beton Bertulang Sloof Struktur 20/25 [K-225] m 0.95 18,036,023.36 17,134,222.19
SUB TOTAL B.I.2 256,937,314.27
TOTAL PEK. STRUKTUR BAWAH 273,334,252.93
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
II. STRUKTUR ATAS
1 PEKERJAAN LANTAI 1
- Beton Bertulang Kolom [30/30] K-225 m3 6.12 16,945,998.86 103,709,513.01
3
- Beton Tangga [K-225] m 3.25 15,698,573.36 51,020,363.41
SUB TOTAL B.II.1 154,729,876.42
2 PEKERJAAN LANTAI 2
Beton Bertulang Kolom [30/30] K-225 m3 5.40 16,945,998.86 91,508,393.83
3
- Beton Bertulang Balok Induk [25/30] K-225 m 6.08 17,665,091.36 107,315,429.99
3
- Beton Bertulang Balok Anak [20/25] K-225 m 0.15 17,079,312.72 2,561,896.91
3
- Beton Bertulang Pelat Konsol Keliling (t=10 cm) K-225 m 4.86 160,000.00 776,960.00
3
- Beton Bertulang Pelat Lantai 2 (t=12 cm) K-225 m 10.08 17,173,454.36 173,108,419.92
SUB TOTAL B.II.2 283,762,706.82
TOTAL PEK. STRUKTUR ATAS 438,492,583.24
III. STRUKTUR ATAP
1 PEKERJAAN ATAP
- Beton Bertulang Ring Balok [20/15] K-225 m3 5.07 4,592,520.00 23,284,076.40
3
- Beton Balok Gewel m 0.11 4,592,520.00 505,177.20
3
- Kolom Gewel m 0.06 4,592,520.00 275,551.20
2
- Penutup Atap Spandex m 300.63 140,710.00 42,301,647.30
2
- Rangka atap baja Ringan m 249.93 263,210.00 65,784,075.30
- Lisplank Kayu klas I m' 60.00 169,800.00 10,188,000.00
- Pek. Jurai Luar m' 31.24 1,650.00 51,546.00
Pek. Jurai Dalam m' 7.20 104,455.00 752,076.00
- Pek. Bubungan m' 1.07 104,455.00 111,766.85
TOTAL PEK. STRUKTUR ATAP 143,253,916.25
TOTAL PEK. STRUKTUR 855,080,752.42
C. PEKERJAAN ARSITEKTUR
I. LANTAI 1
1 PEKERJAAN LANTAI :
1. Lantai Ubin Keramik 40x40 cm + screed mortar m2 96.00 176,467.50 16,940,880.00
2
4 Lantai Ubin Keramik 40x40 cm + screed mortar (Pada tangga) m 13.17 129,217.50 1,701,471.43
SUB TOTAL C.I.1 18,642,351.43
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
2 PEKERJAAN DINDING :
- Pasangan Dinding Batako (1Pc : 4Psr) m2 184.29 268,825.00 49,541,759.25
2
- Plesteran Dinding (1Pc : 4Psr) tebal 15 mm m 368.58 53,580.00 19,748,516.40
2
- Acian Dinding, Plat Canopy dan kolom m 400.79 21,325.00 8,546,846.75
SUB TOTAL C.I.2 77,837,122.40
3 PEKERJAAN PINTU DAN JENDELA DAN ALAT PENGGANTUNG
Kusen Pintu dan Jendela Kayu Kls I 5/11 M3 0.54 17,133,000.00 9,183,288.00
Pasang Door Closer Bh 1.00 1,052,950.00 1,052,950.00
Daun Pintu Panil Kayu Kls 1 3cm M2 7.20 843,000.00 6,069,600.00
Daun Jendela Kaca Mati 5 mm M2 9.80 853,258.25 8,361,930.85
Daun Jendela Panil Kaca 5 mm M2 4.20 853,258.25 3,583,684.65
Jelusi Kayu M2 2.26 318,000.00 719,634.00
Ense Pintu dan Jendela Bh 24.00 34,932.50 838,380.00
Grendel Pintu dan Jendela Bh 12.00 29,932.50 359,190.00
Kunci Pintu Bh 3.00 392,450.00 1,177,350.00
Kait Angin M2 12.00 15,000.00 180,000.00
SUB TOTAL C.I.3 31,526,007.50
3 PEKERJAAN INSTALASI LISTRIK
Titik Sambung Instalasi Ttk 20.00 315,500.00 6,310,000.00
Box Sekring Bh 1.00 87,000.00 87,000.00
Saklar Ganda Bh 5.00 78,000.00 390,000.00
Saklar Tunggal Bh 5.00 78,000.00 390,000.00
Stop Kontak Bh 5.00 78,000.00 390,000.00
Lampu Philips 23 Watt Bh 26.00 110,000.00 2,860,000.00
Lmpu Philips 18 Watt Bh 10.00 60,000.00 600,000.00
SUB TOTAL C.I.3 11,027,000.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
4 PEKERJAAN PLAFON
- Plafon Hardpleks 5 mm, + rangka metal hollow m2 132.00 139,788.40 18,452,068.80
- List Plafond Gypsum / Cornice m' 146.00 63,845.00 9,321,370.00
SUB TOTAL C.I.4 27,773,438.80
5 PEKERJAAN PENGECATAN
- Menie Kayu Kusen m2 17.59 23,342.50 410,594.58
2
- Menie Lisplank m 23,342.50 -
2
- Cat Kayu m 17.59 61,547.50 1,082,620.53
2
- Cat Lisplank m - 61,547.50 -
2
Cat Tembok seluuh m 368.58 22,788.00 8,399,201.04
Cat Plafon m2 132.00 22,788.00 3,008,016.00
2
- Pleletur Daun Pintu Jendela m 17.66 23,365.00 412,625.90
SUB TOTAL C.I.5 13,313,058.04
6 PEKERJAAN LAIN-LAIN
- Pasangan Tembok Ralling Tangga m2 6.88 268,825.00 1,849,516.00
- Plesteran Dinding Tembok Tangga (1Pc : 4Psr) tebal 15 mm m2 14.65 53,580.00 784,947.00
2
- Acian Dinding m 14.65 21,325.00 312,411.25
3
- Beton Bertulang Kolom praktis 15 x 15 Cm m 0.10 4,251,908.57 430,505.74
- Tangga Service pipa GIP Unit 1.00 4,251,908.57 4,251,908.57
SUB TOTAL C.I.6 7,629,288.56
TOTAL PEK. LANTAI 1 187,748,266.74
I. LANTAI 1I
1 PEKERJAAN LANTAI :
1. Lantai Ubin Keramik 40x40 cm + screed mortar m2 97.00 176,467.50 17,117,347.50
2
4 Lantai Ubin Keramik 40x40 cm + screed mortar (Pada tangga) m 13.17 129,217.50 1,701,471.43
SUB TOTAL C.I.1 18,818,818.93
2 PEKERJAAN DINDING :
- Pasangan Dinding Batako (1Pc : 4Psr) m2 213.72 268,825.00 57,453,279.00
2
- Plesteran Dinding (1Pc : 4Psr) tebal 15 mm m 427.44 53,580.00 22,902,235.20
2
- Acian Dinding, Plat Canopy dan kolom m 459.65 21,325.00 9,802,036.25
SUB TOTAL C.I.2 90,157,550.45
3 PEKERJAAN PINTU DAN JENDELA DAN ALAT PENGGANTUNG
Kusen Pintu dan Jendela Kayu Kls I 5/11 M3 0.68 17,133,000.00 11,616,174.00
Daun Pintu Panil Kayu Kls 1 3cm M2 7.20 843,000.00 6,069,600.00
Daun Jendela Kaca Mati 5 mm M2 3.60 853,258.25 3,071,729.70
Daun Jendela Panil Kaca 5 mm M2 8.40 853,258.25 7,167,369.30
Jelusi Kayu M2 13.61 318,000.00 4,327,344.00
Ense Pintu dan Jendela Bh 36.00 34,932.50 1,257,570.00
Grendel Pintu dan Jendela Bh 18.00 29,932.50 538,785.00
Kunci Pintu Bh 3.00 392,450.00 1,177,350.00
Kait Angin M2 24.00 15,000.00 360,000.00
SUB TOTAL C.I.3 35,585,922.00
3 PEKERJAAN INSTALASI LISTRIK
Titik Sambung Instalasi Ttk 45.00 315,500.00 14,197,500.00
Box Sekring Bh 2.00 87,000.00 174,000.00
Saklar Ganda Bh 5.00 78,000.00 390,000.00
Saklar Tunggal Bh 5.00 78,000.00 390,000.00
Stop Kontak Bh 5.00 78,000.00 390,000.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
Lampu Philips 23 Watt Bh 26.00 110,000.00 2,860,000.00
Lmpu Philips 18 Watt Bh 10.00 60,000.00 600,000.00
SUB TOTAL C.I.3 19,001,500.00
4 PEKERJAAN PLAFON
- Plafon Hardpleks 5 mm, + rangka metal hollow m2 132.00 139,788.40 18,452,068.80
- List Plafond Gypsum / Cornice m' 146.00 63,845.00 9,321,370.00
SUB TOTAL C.I.4 27,773,438.80
5 PEKERJAAN PENGECATAN
- Menie Kayu Kusen m2 22.61 23,342.50 527,727.24
2
- Menie Lisplank m 12.00 23,342.50 280,110.00
2
- Cat Kayu m 22.61 61,547.50 1,391,465.88
2
- Cat Lisplank m 12.00 61,547.50 738,570.00
Cat Tembok seluuh m2 427.44 22,788.00 9,740,502.72
Cat Plafon m2 132.00 22,788.00 3,008,016.00
2
- Pleletur Daun Pintu Jendela m 96.00 23,365.00 2,243,040.00
SUB TOTAL C.I.4 17,929,431.84
5 PEKERJAAN RABAT LANTAI HALAMAN
- Menie Kayu Kusen m2 22.61 268,825.00 6,077,595.60
2
- Menie Lisplank m 12.00 53,580.00 642,960.00
2
- Cat Kayu m 22.61 21,325.00 482,115.60
- Cat Lisplank m2 12.00 4,251,908.57 51,022,902.86
Cat Tembok seluuh m2 36.00 4,251,908.57 153,068,708.57
2
Cat Plafon m 132.00 4,251,908.57 561,251,931.43
- Pleletur Daun Pintu Jendela m2 96.00 - -
SUB TOTAL C.I.4 772,546,214.06
TOTAL PEK. LANTAI 1I 209,266,662.02
TOTAL PEK. ARSITEKTUR 397,014,928.76
3 PEKERJAAN PENGADAAN MEUBELEUR
Ongkos Angkut Ls 1.00 3,000,000.00 3,000,000.00
Meja Biro Olimpic Bh 7.00 2,500,000.00 17,500,000.00
kursi putar ( Direktur ) Bh 7.00 750,000.00 5,250,000.00
Kursi Olimpic Utk Rapat Bh 20.00 500,000.00 10,000,000.00
Meja Rapat Bh 1.00 3,000,000.00 3,000,000.00
White Boaed Bh 1.00 350,000.00 350,000.00
Almari Arsip Bh 4.00 1,500,000.00 6,000,000.00
SUB TOTAL C.I.3 45,100,000.00
REKAPITULASI
RENCANA ANGGARAN BIAYA
B. PEKERJAAN STRUKTUR
JUMLAH 1,314,445,681.18
JUMLAH 1,314,445,000.00
RENCANA ANGGARAN BIAYA
(RAB)
HARGA JUMLAH
NO. URAIAN PEKERJAAN SAT. VOLUME SATUAN HARGA
( Rp ) ( Rp )
a b c d e f = (d x e)
A. UMUM
1 Mobilisasi dan Demobilisasi Ls 1.00 2,500,000.00 2,500,000.00
2,500,000.00
35,000,000.00
80,000,000.00 206,980,000.00
1,325.00
9,329,883.75
7,814,495.70
84.00
44.00
51.00
206,980,000.00
colom 0.09
1.20 6.30 4
5 KVA = 4500 Watt 7.56 0.57 0.36
6 KVA = 4800 Watt 30.24 2.27
7 KVA = 5600 Watt 2.99
6 2.99
0.23
1.65 6.60
1.35 5.40
12.00
0.36
21.60
30.24
1.80
7.20
37.44 59.04
1.35
0.45 800.00 360
800.00 0
206,980,000.00 800.00 0
800.00 0
REKAPITULASI
RENCANA ANGGARAN BIAYA
(RAB)
JUMLAH HARGA
NO. JENIS PEKERJAAN
( Rp )
A. UMUM 2,500,000.00
B. PEKERJAAN BOR SUMUR 80,000,000.00
C PEK. PENGADAAN DAN PEMASANGAN PIPA+ASSESORIS 22,784,031.33
D PEK. ELEKTRIKAL DAN POMPA 47,500,000.00
E PEK. BAK PENMPUNG 54,196,905.15
Real Cost 206,980,936.47
PPN 10 % -
Jumlah 206,980,936.47
Dibulatkan 206,980,000.00
TERBILANG : Dua Ratus Enam Juta Sembilan Ratus Delapan Puluh Ribu Rupiah
RENCANA ANGGARAN BIAYA
B. PEKERJAAN STRUKTUR
I. STRUKTUR BAWAH
1 PEKERJAAN TANAH
- Galian Tanah untuk pondasi menerus m3 68.00 83,520.00 5,679,360.00
3
- Galian Tanah Pondasi setempat (Foot Plate) m 36.00 83,520.00 3,006,720.00
3
- Urugan pasir di bawah pondasi menerus m 6.80 385,100.00 2,618,680.00
3
- Urugan tanah kembali m 22.67 17,450.00 395,533.33
3
- Urugan tanah peninggian peil lantai m 43.30 175,100.00 7,581,830.00
3
- Urugan pasir dibawah lantai 1 m 7.20 385,100.00 2,772,720.00
SUB TOTAL B.I.1 22,054,843.33
2 PEKERJAAN PONDASI
- Lantai Kerja Pondasi Telapak Beton Rabat 1PC : 3Psr : 5 Krl (t=5 cm)m3 2.88 1,062,075.00 3,058,776.00
3
- Beton Bertulang Footplate [K-225] m 6.00 15,463,343.56 92,780,061.34
3
- Beton Bertulang Kolom bawah sloof/pedestal [30/30] K-225 m 2.61 16,945,998.86 44,229,057.02
3
- Beton Bertulang Footplate Tangga [K-225] m 0.83 13,051,575.36 10,832,807.55
3
- Pasangan Batu Kosong/ Aanstamping m 16.32 600,420.00 9,798,854.40
3
- Pasangan Batu untuk pondasi menerus dalam gedung (1Pc : 5Psr) m 37.40 943,080.00 35,271,192.00
3
- Beton Bertulang Sloof Struktur 30 /25 [K-225] m 5.10 18,036,023.36 91,983,719.12
3
- Beton Bertulang Sloof Struktur 20/25 [K-225] m 2.50 18,036,023.36 45,090,058.39
SUB TOTAL B.I.2 287,954,467.43
TOTAL PEK. STRUKTUR BAWAH 310,009,310.76
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
II. STRUKTUR ATAS
1 PEKERJAAN LANTAI 1
- Beton Bertulang Kolom [30/30] K-225 m3 7.20 16,945,998.86 122,011,191.77
3
- Beton Tangga [K-225] m 4.25 15,698,573.36 66,718,936.77
SUB TOTAL B.II.1 188,730,128.54
2 PEKERJAAN LANTAI 2
Beton Bertulang Kolom [30/30] K-225 m3 7.20 16,945,998.86 122,011,191.77
3
- Beton Bertulang Balok Induk [25/30] K-225 m 8.85 17,665,091.36 156,336,058.51
3
- Beton Bertulang Balok Anak [20/25] K-225 m 17,079,312.72 -
3
- Beton Bertulang Pelat Lantai 2 (t=12 cm) K-225 m 17.28 17,173,454.36 296,757,291.29
SUB TOTAL B.II.2 453,093,349.80
TOTAL PEK. STRUKTUR ATAS 641,823,478.34
III. STRUKTUR ATAP
1 PEKERJAAN ATAP
- Beton Bertulang Ring Balok [20/15] K-225 m3 2.04 4,592,520.00 9,368,740.80
- Beton Balok Gewel m3 0.67 4,592,520.00 3,091,684.46
3
- Kolom Gewel m 0.14 4,592,520.00 642,952.80
2
- Penutup Atap Spandex m ### 140,710.00 33,027,451.20
- Rangka atap baja Ringan m2 39.47 263,210.00 10,389,161.91
- Lisplank Kayu klas I m' 50.00 169,800.00 8,490,000.00
- Pek. Bubungan m' 18.00 104,455.00 1,880,190.00
TOTAL PEK. STRUKTUR ATAP 66,890,181.17
TOTAL PEK. STRUKTUR ##########
C. PEKERJAAN ARSITEKTUR
I. LANTAI 1
1 PEKERJAAN LANTAI :
1. Lantai Ubin Keramik 40x40 cm + screed mortar m2 ### 176,467.50 25,411,320.00
2
4 Lantai Ubin Keramik 40x40 cm + screed mortar (Pada tangga) m 13.17 129,217.50 1,701,471.43
SUB TOTAL C.I.1 27,112,791.43
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
2 PEKERJAAN DINDING :
- Pasangan Dinding Batako (1Pc : 4Psr) m2 ### 268,825.00 50,380,493.25
2
- Plesteran Dinding (1Pc : 4Psr) tebal 15 mm m ### 53,580.00 20,082,855.60
2
- Acian Dinding, Plat Canopy dan kolom m ### 21,325.00 8,679,914.75
SUB TOTAL C.I.2 79,143,263.60
3 PEKERJAAN PINTU DAN JENDELA DAN ALAT PENGGANTUNG
Kusen Pintu dan Jendela Kayu Kls I 5/11 M3 0.71 17,133,000.00 12,147,297.00
Daun Pintu Panil Kayu Kls 1 3cm M2 4.80 843,000.00 4,046,400.00
Daun Jendela Kaca Mati 5 mm M2 4.20 853,258.25 3,583,684.65
Daun Jendela Panil Kaca 5 mm M2 9.80 853,258.25 8,361,930.85
Jelusi Kayu M2 6.15 318,000.00 1,955,700.00
Ense Pintu dan Jendela Bh 36.00 34,932.50 1,257,570.00
Grendel Pintu Bh 18.00 29,932.50 538,785.00
Kunci Pintu Bh 2.00 392,450.00 784,900.00
Kait Angin M2 28.00 15,000.00 420,000.00
SUB TOTAL C.I.3 33,096,267.50
3 PEKERJAAN INSTALASI LISTRIK
Titik Sambung Instalasi Ttk 18.00 315,500.00 5,679,000.00
Box Sekring Bh 1.00 87,000.00 87,000.00
Saklar Ganda Bh 2.00 78,000.00 156,000.00
Saklar Tunggal Bh 1.00 78,000.00 78,000.00
Stop Kontak Bh 2.00 78,000.00 156,000.00
Lampu Philips 23 Watt Bh 12.00 110,000.00 1,320,000.00
Lmpu Philips 18 Watt Bh 2.00 60,000.00 120,000.00
SUB TOTAL C.I.3 7,596,000.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
4 PEKERJAAN PLAFON
- Plafon Hardpleks 5 mm, + rangka metal hollow m2 ### 139,788.40 30,194,294.40
- List Plafond Gypsum / Cornice m' ### 63,845.00 12,002,860.00
SUB TOTAL C.I.4 42,197,154.40
5 PEKERJAAN PENGECATAN
- Menie Kayu Kusen m2 23.64 23,342.50 551,816.70
2
- Menie Lisplank m 23,342.50 -
2
- Cat Kayu m 23.64 61,547.50 1,454,982.90
2
- Cat Lisplank m - 61,547.50 -
2
Cat Tembok seluuh m ### 22,788.00 8,541,398.16
Cat Plafon m2 ### 22,788.00 4,922,208.00
2
- Pleletur Daun Pintu Jendela m 17.22 23,365.00 402,251.84
SUB TOTAL C.I.5 15,872,657.60
6 PEKERJAAN LAIN-LAIN
- Pasangan Tembok Ralling Tangga m2 10.01 268,825.00 2,690,938.25
- Plesteran Dinding Tembok Tangga (1Pc : 4Psr) tebal 15 mm m2 20.91 53,580.00 1,120,357.80
2
- Acian Dinding m 20.91 21,325.00 445,905.75
3
- Beton Bertulang Kolom praktis 15 x 15 Cm m 0.10 4,251,908.57 430,505.74
- Tangga Service pipa GIP Unit 1.00 4,251,908.57 4,251,908.57
SUB TOTAL C.I.6 8,939,616.11
TOTAL PEK. LANTAI 1 213,957,750.65
I. LANTAI 1I
1 PEKERJAAN LANTAI :
1. Lantai Ubin Keramik 40x40 cm + screed mortar m2 ### 176,467.50 25,411,320.00
2
4 Lantai Ubin Keramik 40x40 cm + screed mortar (Pada tangga) m 13.17 129,217.50 1,701,471.43
SUB TOTAL C.I.1 27,112,791.43
2 PEKERJAAN DINDING :
- Pasangan Dinding Batako (1Pc : 4Psr) m2 ### 268,825.00 58,794,715.75
2
- Plesteran Dinding (1Pc : 4Psr) tebal 15 mm m ### 53,580.00 23,436,963.60
2
- Acian Dinding, Plat Canopy dan kolom m ### 21,325.00 10,014,859.75
SUB TOTAL C.I.2 92,246,539.10
3 PEKERJAAN PINTU DAN JENDELA DAN ALAT PENGGANTUNG
Kusen Pintu dan Jendela Kayu Kls I 5/11 M3 0.71 17,133,000.00 12,147,297.00
Daun Pintu Panil Kayu Kls 1 3cm M2 4.80 843,000.00 4,046,400.00
Daun Jendela Kaca Mati 5 mm M2 4.20 853,258.25 3,583,684.65
Daun Jendela Panil Kaca 5 mm M2 9.80 853,258.25 8,361,930.85
Jelusi Kayu M2 6.15 318,000.00 1,955,700.00
Ense Pintu dan Jendela Bh 36.00 34,932.50 1,257,570.00
Grendel Pintu Bh 18.00 29,932.50 538,785.00
Kunci Pintu Bh 2.00 392,450.00 784,900.00
Kait Angin M2 28.00 15,000.00 420,000.00
SUB TOTAL C.I.3 33,096,267.50
3 PEKERJAAN INSTALASI LISTRIK
Titik Sambung Instalasi Ttk 18.00 315,500.00 5,679,000.00
Box Sekring Bh 1.00 87,000.00 87,000.00
Saklar Ganda Bh 2.00 78,000.00 156,000.00
Saklar Tunggal Bh 1.00 78,000.00 78,000.00
Stop Kontak Bh 2.00 78,000.00 156,000.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)
Lampu Philips 23 Watt Bh 12.00 110,000.00 1,320,000.00
Lmpu Philips 18 Watt Bh 2.00 60,000.00 120,000.00
SUB TOTAL C.I.3 7,596,000.00
4 PEKERJAAN PLAFON
- Plafon Hardpleks 5 mm, + rangka metal hollow m2 ### 139,788.40 30,194,294.40
- List Plafond Gypsum / Cornice m' ### 63,845.00 12,002,860.00
SUB TOTAL C.I.4 42,197,154.40
5 PEKERJAAN PENGECATAN
- Menie Kayu Kusen m2 23.64 23,342.50 551,816.70
2
- Menie Lisplank m 10.00 23,342.50 233,425.00
2
- Cat Kayu m 23.64 61,547.50 1,454,982.90
2
- Cat Lisplank m 10.00 61,547.50 615,475.00
Cat Tembok seluuh m2 ### 22,788.00 9,967,926.96
Cat Plafon m2 ### 22,788.00 4,922,208.00
2
- Pleletur Daun Pintu Jendela m 17.22 23,365.00 402,251.84
SUB TOTAL C.I.4 18,148,086.40
TOTAL PEK. LANTAI 1I 220,396,838.83
TOTAL PEK. ARSITEKTUR 434,354,589.48
3 PEKERJAAN PENGADAAN MEUBELEUR
Ongkos Angkut Ls 1.00 3,000,000.00 3,000,000.00
Meja Siswa Tunggal Bh ### 350,000.00 56,000,000.00
Meja Guru Bh 4.00 400,000.00 1,600,000.00
Kursi Siswa Bh ### 350,000.00 56,000,000.00
Kusi Guru Bh 4.00 400,000.00 1,600,000.00
White Boaed Bh 4.00 350,000.00 1,400,000.00
Almari Ruang Kelas Bh 4.00 1,500,000.00 6,000,000.00
SUB TOTAL C.I.3 125,600,000.00
REKAPITULASI
RENCANA ANGGARAN BIAYA
B. PEKERJAAN STRUKTUR
JUMLAH 1,595,927,559.75
DI BULATKAN 1,595,927,000.00
REKAPITULASI
RENCANA ANGGARAN BIAYA
JUMLAH 284,268,750.00
DI BULATKAN 284,268,000.00
SALEH BUNGA, SH
EDGARD BOELAN TAUFIK T. AMBAO, ST
NIP. 19531217 197902 1 002
NIP. Ka. Perwakilan
Mengetahui
Ketua Pengadilan Negeri Kalabahi
TOTAL 250,000,000.00