Anda di halaman 1dari 2

RENCANA ANGGARAN BIAYA

PEMBANGUNAN RUMAH TINGGAL TIPE 50/91


LOKASI : AL-HAMRA CIBITUNG

Harga Satuan Total


No. Uraian Pekerjaan Sat Volume
(Rp) (Rp)
I. PEKERJAAN PERSIAPAN :
1 Listrik Kerja ls 1,00 775.979 775.979
2 Air Kerja ls 1,00 775.979 775.979
3 Bowplang M' 60,00 40.017 2.400.999
4 Keamanan ls 1,00 1.551.958 1.551.958
5.504.915
II. PEKERJAAN GALIAN DAN URUGAN -
1 Galian Sloof M3 3,84 106.503 408.573
2 Galian Pondasi Tapak M3 5,67 106.503 603.873
3 Urugan Pasir M3 0,70 444.850 310.283
4 Urugan Tanah Kembali M3 4,35 26.910 116.979
1.439.707
III. PEKERJAAN PONDASI : -
1 Pondasi 1 Bata 1:5 (Rollag) M1 66,75 123.575 8.248.608
8.248.608
IV. PEKERJAAN KONSTRUKSI BETON : -
1 Lantai kerja 1:3: 5 tebal 5 cm ( Pondasi Plat Setempat ) M3 0,11 444.850 48.044
2 Lantai kerja 1:3: 5 tebal 5 cm Plat Lantai M3 2,25 444.850 1.000.913
3 Cor Pondasi Plat Setempat 60 x 40 x 25 cm M3 0,84 3.096.935 2.601.425
4 Cor Sloof Beton 15/20 M3 1,76 2.334.335 4.096.758
5 Cor Sloof Beton 15/15 M3 0,94 3.096.935 2.922.732
6 Cor Kolom Struktur 15/25 M3 2,86 2.334.335 6.676.198
7 Cor Kolom Praktis 15/15 M3 2,43 3.224.035 7.829.972
8 Cor Balok Struktur 15/25 M3 2,15 2.334.335 5.018.820
9 Cor Ring Balok 15/15 M3 2,15 3.224.035 6.931.675
10 Cor Plat Meja Dapur t. 8 cm M3 0,11 2.781.142 300.363
11 Cor Kanopi Dak t. 10 cm M3 0,47 2.136.341 1.009.421
12 Cor Aksen Tiang t. 15 cm M3 0,20 3.627.534 734.576
39.170.896
V. PEKERJAAN DINDING : -
1 Pas. Dinding M2 198,05 139.810 27.689.371
27.689.371
VI. PEKERJAAN PELAPIS DINDING : -
1 Acian Dinding M2 258,86 19.764 5.116.231
2 Pasangan Dinding - -
Keramik Dinding Pantry Ex.Lokal t =1 m M2 4,56 93.098 424.527
Keramik Dinding KM/WC Ex.Lokal t =3 m M2 13,50 77.578 1.047.310
6.588.068
VII. PEKERJAAN ATAP : -
1 Rangka Atap Baja Ringan M 69,12 122.136 8.442.059
2 Atap Genteng Beton Flat M2 66,60 71.979 4.793.790
3 Nok Genteng Flat M1 9,45 41.023 387.671
13.623.521
VIII. PEKERJAAN PLAFOND : -
1 Plafond gypsumboard + Rangka Hollow M2 49 133.837 6.558.011
6.558.011
IX. PEKERJAAN LANTAI : -
1 R. Utama keramik M2 41,63 121.378 5.052.341
2 Teras keramik M2 3,25 132.817 431.654
3 KM/WC Keramik M2 2,25 114.193 256.934
4 Dapur Keramik M2 2,80 116.521 326.259
5 Carport M2 12,00 309.385 3.712.619
9.779.807
X. PEKERJAAN KUSEN, PINTU & JENDELA : -
1 Jendela Alumunium 1 Daun Kaca Clear 5mm Unit 2,00 1.447.620 2.895.240
2 Jendela Alumunium 2 Daun Kaca Clear 5mm Unit 2,00 1.447.620 2.895.240
3 Pintu Panel Unit 1,00 1.753.712 1.753.712
4 Pintu Multipleks Unit 3,00 895.483 2.686.449
5 Pintu PVC Unit 1,00 387.989 387.989
10.618.631
XI. PEKERJAAN PENGECATAN : -
1 Cat Dinding Luar (putih) M2 58,30 28.894 1.684.495
2 Cat Dinding Luar (abu-abu) M2 10,56 28.894 305.116
3 Cat Dinding Luar Kanopi Dak (cokelat) M2 0,73 28.894 21.128
4 Cat Dinding Luar Tiang (maroon) M2 0,47 28.894 13.652
5 Cat Dinding Dalam M2 182,80 28.894 5.281.746
6 Cat Plafond M2 45,00 28.894 1.300.211
8.606.349
XII. PEKERJAAN INSTALASI AIR : -
1 Instalasi Air Bersih 3/4" Paralon AW M1 17,50 16.398 286.965
2 Instalasi Air Sabun 3" Paralon D M1 14,00 58.301 816.212
3 Instalasi Air Kotor 3" Paralon D M1 9,00 58.301 524.708
4 Bak kontrol Unit 1,00 505.306 505.306
5 Septictank Unit 1,00 1.417.183 1.417.183
3.550.373
XIII. PEKERJAAN INSTALASI LISTRIK : -
1 Instalasi Titik Lampu Ttk 8,00 104.654 837.230
2 Instalasi Stop Kontak Ttk 5,00 119.051 595.253
3 MCB Ttk 1,00 66.269 66.269
1.498.752
XIV. PEKERJAAN ACCESSORIES SANITAIR : -
1 Kitchen sink (1 Lobang) Bh 1,00 393.503 393.503
2 Kloset Jongkok Bh 1,00 573.047 573.047
3 Kran Shower Bh 1,00 82.904 82.904
4 Kran Air Bh 2,00 44.105 88.211
5 Floor Drain Bh 1,00 65.066 65.066
1.202.731
XV. PEKERJAAN LAIN-LAIN -
1 Pembersihan Lahan setelah selesai pekerjaan M2 45,00 20.165 907.414
Sub total 907.414
Grand Total ( I s/d XV) Rp. 144.987.152
Dibulatkan Rp. 145.000.000
Per meter 2.900.000