KEMAJUAN PEKERJAAN (LKP) BULANAN
PENGADAAN & PEMASANGAN SARANA PENANGKAL/ PENCEGAH HEWAN DI G
SPKPJ NO. 139.SKPJ/DAN.01.02/UPT.KRW
BULAN 3
PERIODE : 01 s/d 31 Oktober 2021
No. URAIAN PEKERJAAN VOLUME SATUAN BOBOT (%) AKUMULASI BULAN LALU
PROGRESS (%)
III JASA
2:24 Pemasangan Ijuk Pengaman Tower 70 & 150 kV 33.0 Tower 6.46
3.2 Pemasangan Ijuk Pengaman Tower 500 kV 4.0 Tower 0.92
3.3 Pemasangan Ijuk Kabel Tower 52.0 Trafo 6.46
68.57
31.43 100.00
100.00 100.00
PT. PLN (PERSERO) UITJBT - UPT KARAWANG DIREKSI PEKERJAAN
.................................................
PT. PLN (PERSERO) UITJBT - UPT KARAWANG
DIREKSI LAPANGAN
.................................................
BOGOR, 15 NOVEMBER 2021
PT. TRIDASA JAYA
DIFA FERDIANSYAH DIREKTUR