LAPORAN PRESTASI PEKERJAAN (PROGRESS OPNAME)

Paket Pekerjaan : Rumah Tinggal Type Keira Sudut Kontraktor : PT.Sanjaya Putra Utama
Proyek : Pesona Rorotan - Jakarta Utara No. SPK : SPU.R/NK15/21/04/003
Lokasi : Blok C2 No.11 Laporan : Ke 9(Sembilan) - Termin VIII - 100%
Jumlah : 1 Unit Periode : 30 April s/d 28 Januari 2023

PRESTASI BOBOT
BOBOT
NO NAMA PEKERJAAN LALU SKRG JUMLAH PRESTASI
(%) (%) (%) (%) (%)

1 PEKERJAAN PERSIAPAN 89.35 10.65 100.00 4.70 4.70


2 PEK.PASANGAN 91.12 8.88 100.00 32.29 32.29
3 PEK.BETON LT.DASAR 96.71 3.29 100.00 10.08 10.08
4 PEK.BETON LT.ATAS 93.82 6.18 100.00 9.25 9.25
5 PEK.BETON LT.ATAP 90.43 9.57 100.00 3.25 3.25
6 PEK. KUSEN, DAUN PINTU & RANGKA JENDELA 70.00 30.00 100.00 9.91 9.91
7 PEK. PENGGANTUNG & KACA 95.00 5.00 100.00 1.39 1.39
8 PEK. ATAP 95.00 5.00 100.00 2.46 2.46
9 PEK. PLAFOND 85.10 14.90 100.00 3.67 3.67
10 PEK. LANTAI 87.99 12.01 100.00 3.40 3.40
11 PEK. INSTALASI AIR KOTOR 77.84 22.16 100.00 3.43 3.43
12 PEK. INSTALASI AIR BERSIH 84.40 15.60 100.00 2.84 2.84
13 PEK. INSTALASI LISTRIK 71.49 28.51 100.00 3.03 3.03
14 PEK. KM / WC BAWAH 36.62 63.38 100.00 1.42 1.42
15 PEK. KM / WC ATAS 38.81 61.19 100.00 1.51 1.51
16 PEK. MEJA DAPUR 65.25 34.75 100.00 0.40 0.40
17 PEK. CAT 73.65 26.35 100.00 3.95 3.95
18 PEK.FINISHING TANGGA 82.31 17.69 100.00 1.30 1.30
19 PEK.BESI 80.00 20.00 100.00 2.10 2.10
20 PEK. LAIN-LAIN 80.00 20.00 100.00 1.55 1.55
.
. JUMLAH 100.00 100.00

CATATAN : JUMLAH BOBOT PRESTASI 100.00


BOBOT PRESTASI YANG LALU 84.93
BOBOT PRESTASI SEKARANG 15.07

Jakarta, 28 Januari 2023

Disetujui, Diperiksa, Diajukan Oleh,


Head Office Project Pesona Rorotan Kontraktor Pelaksana
PT. Nusa Kirana R.E PT. Nusa Kirana R.E PT. Sanjaya Putra Utama

Aditiya Fajar Joko Yongki Gunawan


GM Property Development & Project Project Manager Direktur