TIME SCHEDULE

BIAYA BOBOT WAKTU PELAKSANAAN MINGGU KE-


NO PEKERJAAN
(RP) (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1 PEK. PERSIAPAN 126.051.189,40 1,11 1,106
2 PEK. JALAN 2.409.976.819,96 21,15 5,288 5,288 5,288 5,288
3 PEK. TANAH 3.025.141.137,20 26,55 5,31 5,31 5,31 5,31 5,31
4 PEK. PENDOPO 1.682.000.000,00 14,76 3,691 3,691 3,691 3,691
5 PEK. RUANG GANTI 480.000.000,00 4,21 1,053 1,053 1,053 1,053
6 PEK. MUSEUM 900.000.000,00 7,90 1,975 1,975 1,975 1,975
7 PEK. DINDNG & PLESTERAN 398.483.539,28 3,50 1,749 1,749
8 PEK. RUMAH MAKAN DAN STAND KULINER 283.680.000,00 2,49 1,245 1,245
9 PEK. MINIATUR RUMAH ADAT 156.800.000,00 1,38 0,688 0,688
10 PEK. RUMAH ADAT 1.366.200.000,00 11,99 2,998 3 3 3
11 PEK. ELEKTRIKAL,PLUMBING DAN AKSESORIS 565.000.000,00 4,96 2,48 2,48
JUMLAH 11.393.332.685,84 100,00
RENCANA PROGRES MINGGUAN (%) 6,394 5,288 5,288 10,6 5,31 5,31 5,31 9,001 3,691 3,691 4,744 1,053 1,053 3,028 1,975 1,975 3,724 2,994 1,933 3,686 3 3 5,48 2,48
KOMULATIF PROGRES MINGGUAN (%) 6,394 11,68 16,97 27,57 32,88 38,19 43,5 52,5 56,19 59,88 64,63 65,68 66,73 69,76 71,74 73,71 77,43 80,43 82,36 86,05 89,05 92,05 97,53 100