WAKTU PELAKSANAAN

No URAIAN JUMLAH HARGA (Rp.) BOBOT (%) BULAN BULAN BULAN


1 2 3 4 1 2 3 4 1 2 3 4
3.10 3.10 3.10
1 PEKERJAAN PERSIAPAN Rp 5,495,815.00 9.31

1.47 1.47 1.47 1.47


2 PEK. TANAH DAN PONDASI Rp 3,478,352.74 5.89

2.39 2.39 2.39 2.39 2.39


3 PEK. DINDING DAN PLESTERAN Rp 7,042,344.96 11.93

5.05 5.05 5.05 5.05 5.05 5.05 5.05


4 PEK. BETON Rp 20,885,240.62 35.38

1.57 1.57 1.57 1.57 1.57


5 PEK. KUSEN, PINTU, DAN JENDELA Rp 4,630,388.60 7.84

3.13 3.13 3.13 3.13 3.13


6 PEK. ATAP DAN PLAFOND Rp 9,230,976.44 15.64

1.53 1.53 1.53 1.53


7 PEK. LANTAI Rp 3,619,515.70 6.13

1.91 1.91
8 PEK. PENGECATAN Rp 2,257,686.66 3.82

1.63
9 PEK. INSTALASI LISTRIK Rp 964,500.00 1.63

2.42
10 PEK. INSTALASI AIR/SANITASI Rp 1,429,930.58 2.42

JUMLAH FISIK Rp 59,034,751.29 100.00


RENCANA PROGRES MINGGUAN KE- 3.10 4.58 9.63 12.04 13.61 13.67 15.30 18.00 10.07
KOMULATIF PROGRES MINGGUAN KE- 3.10 7.68 17.31 29.35 42.96 56.63 71.93 89.93 100.00

Chart Title Chart Title


18.00
100.00
15.30 89.93
13.61 13.67
12.04 71.93

9.63 10.07 56.63


42.96

4.58 29.35
3.10 17.31
7.68
3.10
1 2 3 4 5 6 7 8 9 1 2 3 4 5 6 7 8 9