NO WO URAIAN USER EXCECUTION STATUS PEKERJAAN PERMIT IH SPK LPJ
START FINISH
1 WO123540 COMMON - TANAH TERGERUS AIR DI JALAN TURUNAN TEBING MENUJU UNIT 11/9/2020 8:00 12/9/2020 16:00 MRIADI (CIVIL) JAINUL ON PROGRES OPEN
2 WO124391 AUXILIARY BOILER - ISOLASI AUXILIARY BOILER SISI UTARA BAWAH UPPER DRUM KEROPOS 11/11/2020 18:58 11/30/2020 18:58 ARDHI W (MESIN 1) PURWANTO FINISH OPEN
3 WO128071 PEMASANGAN KASTIN (PEDESTRIAN) AREA MED SAMPAI WWTP 1/26/2021 8:00 2/26/2021 16:00 MRIADI (CIVIL) EKO P ON PROGRES OPEN
4 WO129687 PEMBUATAN GEDUNG OLAHRAGA DI AREA DOMITORY (PENGECORAN) 15/02/2021 MRIADI (CIVIL) ZAINUL/PURWANTO ON PROGRES
“P T P R ATAM A LEN TERA WIJAYA”
Badan Hukum Nomor : 0008/BH.13-35/X/2013
Jl.Pacitan – Trenggalek KM 55 Ds.Sukorejo Kec.Sudimoro
Kab. Pacitan Jawa Timur

MONITORING PEKERJAAN
CLERANCE
NO WO/PO URAIAN NOMINAL STATUS PEKERJAN LEVERING PERMIT PAK
STAF
SUARI
1 NL0625 JASA BONGKAR PASANG ISOALSI AREA TURBIN - MO M1 Rp 99,000,000.00 80% 60 HARI SEJAK SAFETY PERMIT OPEN
2 NK0327 JASA PENGGANTIAN BOLLARD AREA JETTY Rp 20,900,000.00 30% 20 HARI SEJAK SAFETY PERMIT OPEN
3 02.PO/GS/IX/2021 JASA REFRACTORY HIP TURBIN, BFPT & VALVE MAIN TURBIN Rp 9,000,000.00 100% 10 HARI GOLD STAR
4 WO155559 PENAMBAHAN ANCHOR IDF#2 Rp 29,810,000.00 100% 18 0KTOBER - 18 NOVEMBER 2021 OPEN
5 NL0719 PENGADAAN JASA PEMBUATAN GOR DORMITORY - CIVIL Rp 252,467,100.00 75% 14 DESEMBER 2021 OPEN
TOTAL Rp 411,177,100.00