Anda di halaman 1dari 8

RENCANA ANGGARAN BIAYA

PEKERJAAN PEMBUATAN PAGAR BATA RINGAN


LOKASI : JL. KAPTEN PIERE TENDEAN, KOTA BANJARMASIN

NO. KODE URAIAN SAT VOLUME HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN
1- Mobilisasi alat dan bahan ls 1.00 500,000.00 500,000.00
2 PS001 Pembersihan lokasi m2 121.00 5,600.00 677,600.00

Sub Total 1,177,600.00

II PEKERJAAN DINDING TINGGI 2,6 METER


1 PB001 Kolom 30/30 Beton M3 1.20 1,282,800.00 1,535,511.60
2 PB002 Pembesian Kg 148.58 27,753.00 4,123,518.54
3 PB003 Bekisting M2 14.52 243,500.00 3,535,620.00
4 PD001 Pasangan bata ringan uk.20x60cm, t.10cm M2 38.30 176,300.00 6,752,290.00
5 PD002 Plesteran, Camp. 1 : 4 M2 76.60 125,100.00 9,582,660.00
6 PD003 Acian Dinding M2 76.60 56,500.00 4,327,900.00
7 PD004 Pengecetan Tembok cat exterior Ex. Mowilex M2 76.60 54,600.00 4,182,360.00

Sub Total 34,039,860.14


III PEKERJAAN LAINNYA
1 PL001 Pas. Pecahan kaca diatas dinding pagar M' 11.00 76,400.00 840,400.00
2 PL002 Pas. Pintu besi dengan besi eksisting M2 4.50 373,100.00 1,678,950.00
3 PL003 Pas. Pintu plat besi t.2mm dengan besi eksisting M2 9.00 40,800.00 367,200.00

Sub Total 2,886,550.00


Jumlah 38,104,010.14
PPN 10% 3,810,401.01
Total 41,914,411.15
DIBULATKAN 41,914,400.00
TERBILANG : "EMPAT PULUH SATU JUTA SEMBILAN RATUS EMPAT BELAS RIBU EMPAT RATUS RUPIAH"

Banjarmasin, 21 Oktober 2021


Diperiksa Oleh; Dibuat oleh,
Penyelia Ynr.

Anthon Riyan Ansari


Asisten Manager Konsultan Sipil
Mengetahui;
Kepala Divisi

R. Bambang Setyo P.
Deputi Direktur
ANALISA HARGA SATUAN PEKERJAAN
PEKERJAAN PEMBUATAN PAGAR BATA RINGAN

HARGA JUMLAH HARGA JUMLAH


NO KODE URAIAN SAT KOEF BAHAN / UPAH BAHAN UPAH BAHAN + UPAH
Rp. Rp. Rp. Rp.
1 PS001 Urugan 1 m3 tanah dengan tanah urug 82,500.00
Tenaga kerja :
Pekerja Oh 0.500 132,200.00 66,100.00 66,100.00
Mandor Oh 0.050 178,800.00 8,940.00 8,940.00
Total 75,040.00
Keuntungan 10% 7,504.00
2 PS002 Pemindahan 1 m3 tanah dan perataan tanah 2,600.00
Pekerja Oh 0.013 132,200.00 1,652.50 1,652.50
Mandor Oh 0.004 178,800.00 715.20 715.20
Total 2,367.70
Keuntungan 10% 236.77
3 PS003 Pembersihan 1 m2 eks. Pekerjaan di area proyek 15,800.00
Pekerja Oh 0.075 132,200.00 9,915.00 9,915.00
Mandor Oh 0.025 178,800.00 4,470.00 4,470.00
Total 14,385.00
Keuntungan 10% 1,438.50
ANALISA HARGA SATUAN PEKERJAAN
PEKERJAAN PEMBUATAN PAGAR BATA RINGAN
LOKASI : JL. KAPTEN PIERE TENDEAN, KOTA BANJARMASIN

HARGA JUMLAH HARGA JUMLAH


NO KODE URAIAN SAT KOEF BAHAN / UPAH BAHAN UPAH BAHAN + UPAH
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8
I PEKERJAAN PERSIAPAN
1 PS001 Pembersihan 1 m2 eks. Pekerjaan di area proyek 5,600.00
Tenaga kerja :
Pekerja Oh 0.025 132,200.00 3,305.00 3,305.00
Mandor Oh 0.010 178,800.00 1,788.00 1,788.00
Total 5,093.00
Keuntungan 10% 509.30
II PEKERJAAN PAGAR
A Pekerjaan Beton
1 PB001 Pek. Beton Mutu K-250 1,282,800.00
Bahan :
Semen Portland Kg 352.000 1,825.00 642,400.00 642,400.00
Pasir Beton M3 0.522 233,800.00 122,043.60 122,043.60
Kerikil (Maks 30mm) M3 0.764 286,400.00 218,809.60 218,809.60
Air Ltr 215.000 20.00 4,300.00 4,300.00
Tenaga kerja : -
Pekerja Oh 1.650 132,200.00 218,130.00 218,130.00
Tukang Batu Oh 0.275 155,400.00 42,735.00 42,735.00
Kepala tukang Oh 0.028 170,900.00 4,785.20 4,785.20
Mandor Oh 0.083 178,800.00 14,840.40 14,840.40
Total 1,268,043.80
Keuntungan 10% 126,804.38
2 PB002 Pek. 100 Kg Pembesian 2,775,300.00
Bahan :
Besi beton (polos/ulir) Kg 105.000 18,320.00 1,923,600.00 1,923,600.00
Kawat beton Kg 2.100 20,380.00 42,798.00 42,798.00
Tenaga kerja : -
Pekerja Oh 2.100 132,200.00 277,620.00 277,620.00
Tukang Besi Oh 1.400 155,400.00 217,560.00 217,560.00
Kepala tukang Oh 0.140 170,900.00 23,926.00 23,926.00
Mandor Oh 0.210 178,800.00 37,548.00 37,548.00
Total 2,523,052.00
Keuntungan 10% 252,305.20
3 PB003 Pek. Bekesting 243,500.00
Bahan :
Kayu kelas III M3 0.045 2,102,470.00 94,611.15 94,611.15
Paku 5 - 10 cm Kg 0.300 27,760.00 8,328.00 8,328.00
Minyak bekisting Ltr 0.100 2,190.00 219.00 219.00
Tenaga kerja : -
Pekerja Oh 0.520 132,200.00 68,744.00 68,744.00
Tukang Besi Oh 0.260 155,400.00 40,404.00 40,404.00
Kepala tukang Oh 0.026 170,900.00 4,443.40 4,443.40
Mandor Oh 0.026 178,800.00 4,648.80 4,648.80
Total 221,398.35
Keuntungan 10% 22,139.84
B Pekerjaan Dinding
1 PD001 Pek. Pasangan Bata Ringan Camp. 1:4 176,300.00
Bahan :
Bata ringan uk.60x20 tebal.10cm Bh 10.000 7,000.00 70,000.00 70,000.00
Semen portlan Kg 11.500 1,825.00 20,987.50 20,987.50
Pasir Pasang M3 0.043 227,400.00 9,778.20 9,778.20
Tenaga kerja : -
Pekerja Oh 0.300 132,200.00 39,660.00 39,660.00
Tukang Besi Oh 0.100 155,400.00 15,540.00 15,540.00
Kepala tukang Oh 0.010 170,900.00 1,709.00 1,709.00
Mandor Oh 0.015 178,800.00 2,682.00 2,682.00
Total 160,356.70
Keuntungan 10% 16,035.67
2 PD002 Pemasangan 1 m2 plesteran 1SP : 4PP tebal 20 mm 125,100.00
Bahan :
Semen portlan Kg 8.320 1,825.00 15,184.00 15,184.00
Pasir Pasang M3 0.032 227,400.00 7,276.80 7,276.80
Tenaga kerja : -
Pekerja Oh 0.400 132,200.00 52,880.00 52,880.00
Tukang Besi Oh 0.200 155,400.00 31,080.00 31,080.00
Kepala tukang Oh 0.020 170,900.00 3,418.00 3,418.00
Mandor Oh 0.022 178,800.00 3,933.60 3,933.60
Total 113,772.40
Keuntungan 10% 11,377.24

3 PD003 Pemasangan 1 m2 acian 56,500.00


Bahan :
Semen portlan Kg 3.250 1,825.00 5,931.25 5,931.25
Tenaga kerja : -
Pekerja Oh 0.200 132,200.00 26,440.00 26,440.00
Tukang Besi Oh 0.100 155,400.00 15,540.00 15,540.00
Kepala tukang Oh 0.010 170,900.00 1,709.00 1,709.00
Mandor Oh 0.010 178,800.00 1,788.00 1,788.00
Total 51,408.25
Keuntungan 10% 5,140.83

4 PD004 Pengecetan Tembok cat exterior Ex. Mowilex 54,600.00


Bahan :
Plamuur Kg 0.100 58,850.00 5,885.00 5,885.00
Cat dasar Kg 0.100 57,000.00 5,700.00 5,700.00
Cat Penutup Kg 0.260 92,533.33 24,058.67 24,058.67
Tenaga kerja : -
Pekerja Oh 0.020 132,200.00 2,644.00 2,644.00
Tukang Cat Oh 0.063 155,400.00 9,790.20 9,790.20
Kepala tukang Oh 0.006 170,900.00 1,076.67 1,076.67
Mandor Oh 0.003 178,800.00 536.40 536.40
Total 49,690.94
Keuntungan 10% 4,969.09
C Pekerjaan Lainnya
1 PL001 Pas. 1m2 Pecahan kaca diatas dinding pagar 76,400.00
Bahan :
Kaca beling Kg 1.200 20,000.00 24,000.00 24,000.00
Tenaga kerja : -
Pekerja Oh 0.200 132,200.00 26,440.00 26,440.00
Tukang Besi Oh 0.100 155,400.00 15,540.00 15,540.00
Kepala tukang Oh 0.010 170,900.00 1,709.00 1,709.00
Mandor Oh 0.010 178,800.00 1,788.00 1,788.00
Total 69,477.00
Keuntungan 10% 6,947.70
2 PL002 Pas. 1m2 pintu besi dengan besi eksisting 373,100.00
Bahan :
Perlengkapam Ls 1.000 10,000.00 10,000.00 10,000.00
Tenaga kerja : -
Pekerja Oh 1.050 132,200.00 138,810.00 138,810.00
Tukang Batu Oh 1.050 155,400.00 163,170.00 163,170.00
Kepala tukang Oh 0.105 170,900.00 17,944.50 17,944.50
Mandor Oh 0.052 178,800.00 9,297.60 9,297.60
Total 339,222.10
Keuntungan 10% 33,922.21
3 PL003 Pengecatan 1m2 besi dengan cat anti karat ex. Dulux 40,800.00
Bahan :
Dempul besi Kg 0.050 40,000.00 2,000.00 2,000.00
Meni Besi Kg 0.100 55,000.00 5,500.00 5,500.00
Cat besi ex.Dulux Kg 0.260 60,000.00 15,600.00 15,600.00
Tenaga kerja : -
Pekerja Oh 0.020 132,200.00 2,644.00 2,644.00
Tukang cat Oh 0.063 155,400.00 9,790.20 9,790.20
Kepala tukang cat Oh 0.006 170,900.00 1,076.67 1,076.67
Mandor Oh 0.003 178,800.00 536.40 536.40
Total 37,147.27
Keuntungan 10% 3,714.73

Banjarmasin, 21 Oktober 2021


Diperiksa Oleh; Dibuat oleh,
Penyelia Ynr.

Anthon Riyan Ansari


Asisten Manager Konsultan Sipil

Mengetahui;
Kepala Divisi

R. Bambang Setyo P.
Deputi Direktur
ANALISA HARGA SATUAN PEKERJAAN KOLAM
PEKERJAAN PEMBUATAN PAGAR BATA RINGAN
RUMAH PANGAN LESTARI KPw BANK INDONESIA BANJARMASIN

HARGA JUMLAH HARGA JUMLAH


NO KODE URAIAN SAT KOEF BAHAN / UPAH BAHAN UPAH BAHAN + UPAH
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8
1 PR001 Menggali 1 m3 tanah biasa sedalam 2.5 - 3m 165,800.00
Tenaga kerja : -
Pekerja Oh 1.050 132,200.00 138,810.00 138,810.00
Mandor Oh 0.067 178,800.00 11,979.60 11,979.60
Total 150,789.60
Keuntungan 10% 15,078.96
2 PR002 Pas. Papan siring ulin Kelas III + rangka ulin uk. 4/6 Err:509
- Pas. 1 m2 Papan siring ulin kelas III Err:509
Bahan :
Papan siring ulin kelas III M3 0.055 Err:509 Err:509 Err:509
Paku Ulin 1-2 inc Kg 0.400 Err:509 Err:509 Err:509
Tenaga kerja : -
Pekerja Oh 0.133 132,200.00 17,582.60 17,582.60
Tukang Kayu Oh 0.333 155,400.00 51,748.20 51,748.20
Kepala Tukang Oh 0.033 155,400.00 5,128.20 5,128.20
Mandor Oh 0.006 178,800.00 1,072.80 1,072.80
Total Err:509
Keuntungan 10% Err:509
- Pas. 1 m3 Rangka Balok ulin uk. 4/6 Err:509
Bahan :
Balok Ulin uk. 4/6 M3 1.010 Err:509 Err:509 Err:509
Baut Dia. 10-12 cm Bh 24.000 2,500.00 60,000.00 60,000.00
Tenaga kerja : -
Pekerja Oh 3.000 132,200.00 396,600.00 396,600.00
Tukang Kayu Oh 5.000 155,400.00 777,000.00 777,000.00
Kepala Tukang Oh 0.500 155,400.00 77,700.00 77,700.00
Mandor Oh 0.150 178,800.00 26,820.00 26,820.00
Total Err:509
Keuntungan 10% Err:509
ANALISA HARGA SATUAN PEKERJAAN KOLAM
PEKERJAAN PEMBUATAN PAGAR BATA RINGAN
RUMAH PANGAN LESTARI KPw BANK INDONESIA BANJARMASIN

HARGA JUMLAH HARGA JUMLAH


NO KODE URAIAN SAT KOEF BAHAN / UPAH BAHAN UPAH BAHAN + UPAH
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8
1 PJ001 Pas. Gorong-gorong dia. 40cm 356,000.00
Bahan :
Gorong-gorong dia.40 cm bh 1.000 250,000.00 250,000.00 250,000.00
Tenaga kerja : -
Pekerja Oh 0.500 115,600.00 57,800.00 57,800.00
Tukang Batu Oh 0.100 135,900.00 13,590.00 13,590.00
Kepala Tukang Oh 0.010 149,500.00 1,495.00 1,495.00
Mandor Oh 0.005 156,400.00 782.00 782.00
Total 323,667.00
Keuntungan 10% 32,366.70
2 PJ002 Pas. 1m2 Paving block conblock4 t.6cm K-300 285,400.00
Bahan :
Paving Block Tebal 6 cm ex. Conblock4 M2 1.010 121,000.00 122,210.00 122,210.00
Pasir Beton M3 0.050 233,750.00 11,687.50 11,687.50
Semen PC ex.Tiga roda Zak 0.100 70,000.00 7,000.00 7,000.00
Tenaga kerja : -
Pekerja Oh 0.250 115,600.00 28,900.00 28,900.00
Tukang Batu Oh 0.500 135,900.00 67,950.00 67,950.00
Kepala Tukang Oh 0.050 149,500.00 7,475.00 7,475.00
Mandor Oh 0.001 156,400.00 203.32 203.32
Peralatan :
Peralatan % 10.000 140,897.50 14,089.75 14,089.75
Total 259,515.57
Keuntungan 10% 25,951.56
3 PS003 Pas. 1m2 Plesteran samping jalan paving cam. 1SP : 4PP 106,600.00
Bahan :
Semen portlan ex. Tiga roda Kg 8.320 1,400.00 11,648.00 11,648.00
Pasir Pasang m3 0.032 170,500.00 5,456.00 5,456.00
Tenaga kerja : -
Pekerja Oh 0.400 115,600.00 46,240.00 46,240.00
Tukang Batu Oh 0.200 135,900.00 27,180.00 27,180.00
Kepala Tukang Oh 0.020 149,500.00 2,990.00 2,990.00
Mandor Oh 0.022 156,400.00 3,440.80 3,440.80
Total 96,954.80
Keuntungan 10% 9,695.48
ANALISA HARGA SATUAN PEKERJAAN KOLAM
PEKERJAAN PEMBUATAN PAGAR BATA RINGAN
RUMAH PANGAN LESTARI KPw BANK INDONESIA BANJARMASIN

HARGA JUMLAH HARGA JUMLAH


NO KODE URAIAN SAT KOEF BAHAN / UPAH BAHAN UPAH BAHAN + UPAH
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8
1 PPS001 Pengecatan pagar tembok ex. Dulux Weathershield Err:509
Bahan :
Plamuur Kg 0.100 Err:509 Err:509 Err:509
Cat dasar ex. Dulux Kg 0.100 Err:509 Err:509 Err:509
Cat Penutup ex. Dulux weathershield Kg 0.260 Err:509 Err:509 Err:509
Tenaga kerja : -
Pekerja Oh 0.020 115,600.00 2,312.00 2,312.00
Tukang Batu Oh 0.063 135,900.00 8,561.70 8,561.70
Kepala Tukang Oh 0.006 149,500.00 941.85 941.85
Mandor Oh 0.003 156,400.00 469.20 469.20
Total Err:509
Keuntungan 10% Err:509
2 PPS002 Pas. pipa PVC 3/4" dari meteran PDAM ke pipa mesin air Err:509
Bahan :
Pipa PVC 3/4" ex. Wapin M' 1.000 Err:509 Err:509 Err:509
Perlengkapan % 0.060 Err:509 Err:509 Err:509
Tenaga kerja : -
Pekerja Oh 0.036 115,600.00 4,161.60 4,161.60
Tukang Batu Oh 0.060 135,900.00 8,154.00 8,154.00
Kepala Tukang Oh 0.006 149,500.00 897.00 897.00
Mandor Oh 0.002 156,400.00 312.80 312.80
Total Err:509
Keuntungan 10% Err:509
3 PPS003 Pas. Kran air ex. Flo Err:509
Bahan :
Kran Air ex. Flo Unit 1.000 Err:509 Err:509 Err:509
Tenaga kerja : -
Pekerja Oh 0.001 115,600.00 115.60 115.60
Tukang Batu Oh 0.001 135,900.00 135.90 135.90
Kepala Tukang Oh 0.010 149,500.00 1,495.00 1,495.00
Mandor Oh 0.005 156,400.00 782.00 782.00
Total Err:509
Keuntungan 10% Err:509
HARGA SATUAN UPAH KERJA DAN MATERIAL
PEKERJAAN PEMBUATAN PAGAR BATA RINGAN
LOKASI : JL. KAPTEN PIERE TENDEAN, KOTA BANJARMASIN

No ITEM SATUAN HARGA


I HARGA SATUAN UPAH KERJA
1 Pekerja oh 132,200.00
2 Mandor oh 178,800.00
3 Tukang batu oh 155,400.00
4 Kepala tukang batu oh 170,900.00
5 Tukang Kayu oh 155,400.00
6 Kepala Tukang Kayu oh 170,900.00
7 Tukang Besi Beton oh 155,400.00
8 Kepala Tukang Besi Beton oh 170,900.00

II HARGA SATUAN MATERIAL


1 Tanah urug m3 121,400.00
2 Koral beton m3 286,400.00
3 Pasir urug m3 181,500.00
4 Pasir pasang m3 227,400.00
5 Pasir beton m3 233,800.00
6 Bata ringan uk.60x20 tebal.10cm bh 7,000.00
7 Semen PC kg 1,825.00
8 Besi beton kg 18,320.00
9 Kawat Bindrat kg 20,380.00
10 Kayu papan bekisting lanan kayu kls III m3 2,102,470.00
11 Balok Lanan Bekesting lanan kls III m3 2,102,470.00
12 Paku 4 cm s/d 7 cm kg 27,760.00
13 Pecahan kaca kg 20,000.00
14 Lem fox kg 74,520.00
15 Oli Bekastink ltr 2,190.00
16 Plamuur Kg 58,850.00
17 Dempul Besi ex.sanpaloc kg 40,000.00
18 Meni besi ex.kansai kg 55,000.00
19 Cat anti karat besi.ex. Setara Dulux kg 60,000.00
20 Cat dasar ex. Mowilex precoat Kg 57,000.00
21 Cat tembok exterior ex. Mowilex Kg 92,533.33
22 Cat tembok ICI exterior Kg 92,533.33
23 Air ltr 20.00

Banjarmasin, 21 Oktober 2021


Mengetahui; Dibuat oleh,
Penyelia Ynr.

Anthon Riyan Ansari


Asisten Manager Konsultan Sipil

Mengetahui;
Kepala Divisi

R. Bambang Setyo P.
Deputi Direktur

Anda mungkin juga menyukai