Anda di halaman 1dari 2

Pekerjaan : Pengendalian Banjir Dan Rob Pekalongan Paket I

Tahun Anggaran : 2017 - 2019

Sumber Dana : APBN

KONTRAK
NO. URAIAN SATUAN HARGA SATUAN
VOLUME TOTAL HARGA

A PEKERJAAN PERSIAPAN

1 Mobilisasi Dan Demobilisasi Ls 120,175,000.00 1.00 120,175,000.00


2 Perbaikan Jalan Masuk Ke Lokasi M3 1,127,400.00 264.00 297,633,600.00
3 Pengukuran, Penggambaran Ls 89,815,000.00 1.00 89,815,000.00
4 Pembuatan Direksi Keet M2 1,783,400.00 50.00 89,170,000.00
5 Foto Dokumentasi Ls 4,594,300.00 1.00 4,594,300.00
Sub Total A 601,387,900.00
B PENGENDALIAN BANJIR DAN ROB PEKALONGAN

Pekerjaan Normalisasi Sungai Mrican


1 Galian Tanah Dengan Alat M3 20,000.00 220,206.00 4,404,120,000.00
2 Buangan Hasil Dari Galian Jarak Angkut 0.05 < L < 1 Km M3 16,000.00 154,144.00 2,466,304,000.00
3 Buangan Hasil Dari Galian Jarak Angkut 1 < L < 3 Km M3 23,000.00 44,041.00 1,012,943,000.00
4 Buangan Hasil Dari Galian Jarak Angkut > 3 Km M3 40,000.00 22,021.00 880,840,000.00
5 Tanah Dihampar, Diratakan Dan Dirapihkan M3 12,900.00 33,031.00 426,099,900.00
9,190,306,900.00
Pekerjaan Long Storage Dan Tanggul Sragi Baru - Mrican
1 Timbunan Tanah Mendatangkan Untuk Tanggul Dan Pemadatan M3 165,600.00 45,440.00 7,524,864,000.00
2 Galian Tanah Dengan Alat M3 20,000.00 429,408.00 8,588,160,000.00
3 Galian Tanah Dengan Ponton < 50 M M3 30,100.00 68,160.00 2,051,616,000.00
4 Buangan Hasil Dari Galian Jarak Angkut 0.05 < L < 1 Km M3 16,000.00 300,586.00 4,809,376,000.00
5 Buangan Hasil Dari Galian Jarak Angkut 1 < L < 3 Km M3 23,000.00 85,882.00 1,975,286,000.00
6 Buangan Hasil Dari Galian Jarak Angkut > 3 Km M3 40,000.00 42,941.00 1,717,640,000.00
7 Tanah Dihampar, Diratakan Dan Dirapihkan M3 12,900.00 74,635.00 962,791,500.00
8 Pengadaan Dan Pemancangan Cerucuk Bambu Btg 55,300.00 136,320.00 7,538,496,000.00
9 Matras Bambu, T = 2 Cm M2 80,800.00 136,320.00 11,014,656,000.00
10 Pengadaan Mini Pile 20 Cm x 20 Cm, L = 6 M M1 150,400.00 85,200.00 12,814,080,000.00
11 Pemancangan dan Langsiran Mini Pile 20 Cm x 20 Cm, L = 6 M M1 75,000.00 68,160.00 5,112,000,000.00
12 Bongkaran Beton M3 199,300.00 102.00 20,328,600.00
13 Beton K.250 Menggunakan Semen Type 5 M3 1,250,400.00 9,708.00 12,138,883,200.00
14 Pembesian Kg 14,500.00 970,840.00 14,077,180,000.00
15 Bekisting M2 101,000.00 36,716.00 3,708,316,000.00
16 Rip Rap M3 390,000.00 1,704.00 664,560,000.00
17 Pengadaan Dan Pemasangan Geotextile Non Woven M2 24,200.00 5,680.00 137,456,000.00
18 Pengadaan CCSP K.500 W 500 - 1000 M1 1,025,600.00 3,120.00 3,199,872,000.00
19 Pemancangan CCSP K.500 W 500 - 1000 M1 147,700.00 2,496.00 368,659,200.00
20 Langsiran CCSP K.500 W 500 - 1000 M1 17,800.00 3,120.00 55,536,000.00
KONTRAK
NO. URAIAN SATUAN HARGA SATUAN
VOLUME TOTAL HARGA

21 Bongkaran CCSP M3 199,300.00 10.00 1,993,000.00


22 Timbunan Tanah Mendatangkan Untuk Tanggul Tanpa Pemadatan M3 154,000.00 260.00 40,040,000.00
98,521,789,500.00
Pekerjaan Parapet S. Mrican
1 Beton K.250 Menggunakan Semen Type 5 M3 1,250,400.00 7,500.00 9,378,000,000.00
2 Pengadaan Mini Pile K.500 Segitiga 12 Cm x 12 Cm x 12 Cm M1 62,700.00 60,000.00 3,762,000,000.00
3 Pemancangan Dan Langsiran Mini Pile K.500 Segitiga 12 Cm x 12 Cm x 12 C M1 75,000.00 60,000.00 4,500,000,000.00
4 Bongkaran Mini Pile M3 199,300.00 6.00 1,195,800.00
5 Pekerjaan Water Stop M1 125,100.00 450.00 56,295,000.00
6 Pembesian Kg 14,500.00 750,000.00 10,875,000,000.00
7 Bekisting M2 101,000.00 18,000.00 1,818,000,000.00
30,390,490,800.00
Pekerjaan Pengadaan Pompa
1 Pengadaan Pompa Submersible Kapasitas 2 M3/Detik Unit 2,622,000,000.00 2.00 5,244,000,000.00

Pekerjaan Rumah Pompa S. Mrican


1 Pasangan Batu 1 : 4 M3 700,100.00 30.00 21,003,000.00
2 Beton Ready Mix K.225 M3 1,200,600.00 160.00 192,096,000.00
3 Pembesian Kg 14,500.00 16,000.00 232,000,000.00
4 Bekisting M2 101,000.00 120.00 12,120,000.00
5 Pasangan Batu Bata M3 986,300.00 30.00 29,589,000.00
6 Plesteran M2 51,000.00 500.00 25,500,000.00
7 Atap (Asbes Gelombang Besar Dan Rangka Baja Ringan) M2 282,100.00 140.00 39,494,000.00
8 Cat Tembok M2 22,600.00 500.00 11,300,000.00

Pekerjaan Collector Drain


1 Pengadaan Dan Pemasangan U Ditch 100 x 100 x 120 Cm Unit 1,807,400.00 1,500.00 2,711,100,000.00

Sub Total B 146,620,789,200.00


JUMLAH TOTAL A + B 147,222,177,100.00
PPN 10% 14,722,217,710.00
TOTAL 161,944,394,810.00
PEMBULATAN 161,944,395,000.00