Enterdesa (Rab Gudang Perkakas)
Enterdesa (Rab Gudang Perkakas)
Kebutuhan bahan
Pasir pasang 12.87 13.00 m3
Batu kali 16.20 16.00 m3
Batu pecah 2 - 3 2.24 2.50 m3
Batu bata 6,300.00 6,300.00 bh
Semen PC 3,493.07 40 87.33 zak 80.00
Besi 299.99 308.00 kg
Papan 40.00 40.00 lbr
Kayu 5 - 7 73.50 24.50 btg 25.00
Asbes 73.50 - m2
Tukang 23.10 30.00
Tenaga 61.44 60.00
Harga
No. Uraian Bahan Satuan
Rp.
Harga
No. Uraian Upah Satuan
Rp.
Harga
No. Uraian Pekerjaan Satuan
Rp.
16 PEKERJAAN BETON
a. 1 M3 BETON 1 : 2 : 3
304.00 kg Semen PC Rp 1,375.00 Rp 418,000.00
0.540 m3 Pasir beton Rp 160,000.00 Rp 86,400.00
0.820 m3 Batu pecah 2/3 Rp 235,000.00 Rp 192,700.00
0.200 Org/hr Tukang batu Rp 65,000.00 Rp 13,000.00
0.020 Org/hr Kepala tukang Rp 70,000.00 Rp 1,400.00
1.200 Org/hr Pekerja Rp 55,000.00 Rp 66,000.00
0.200 Org/hr Mandor Rp 65,000.00 Rp 13,000.00
Rp 790,500.00
b. 1 M3 BETON BERTULANG DENGAN BESI 110 KG
110.00 kg Besi beton Rp 10,500.00 Rp 1,155,000.00
1.000 kg Kawat beton Rp 17,000.00 Rp 17,000.00
2.000 Org/hr Tukang besi Rp 65,000.00 Rp 130,000.00
4.000 Org/hr Kepala tukang Rp 70,000.00 Rp 280,000.00
1.000 Org/hr Pekerja Rp 55,000.00 Rp 55,000.00
Rp 1,637,000.00
c. 1 M3 BETON BERTULANG DENGAN BESI 150 KG
150.00 kg Besi beton Rp 10,500.00 Rp 1,575,000.00
1.000 kg Kawat beton Rp 17,000.00 Rp 17,000.00
2.000 Org/hr Tukang besi Rp 65,000.00 Rp 130,000.00
4.000 Org/hr Kepala tukang besi Rp 70,000.00 Rp 280,000.00
1.000 Org/hr Pekerja Rp 55,000.00 Rp 55,000.00
Rp 2,057,000.00
d. 1 M3 KAYU CETAKAN UNTUK BETON BERTULANG
0.410 m3 Kayu tahun Rp 2,000,000.00 Rp 820,000.00
1.000 kg Paku rata-rata Rp 17,000.00 Rp 17,000.00
0.500 Org/hr Tukang kayu Rp 65,000.00 Rp 32,500.00
0.050 Org/hr Kepala tukang kayu Rp 70,000.00 Rp 3,500.00
0.200 Org/hr Pekerja Rp 55,000.00 Rp 11,000.00
0.010 Org/hr Mandor Rp 65,000.00 Rp 650.00
0.400 Org/hr Pekerja untuk bongkar Rp 55,000.00 Rp 22,000.00
Rp 906,650.00
#REF!
#REF!
#REF!
#REF!
Rencana Anggaran Biaya
Rp 28,341,500.00
Jumlah Total Rp 28,341,500.00