I PEKERJAAN PENDAHULUAN
1 Pengukuran /Uitzet & Bouplank 36.00 m LS 5,000.00 180,000.00
2 Bongkar Bangunan Lama 1.00 unit Ls 500,000.00 500,000.00
680,000.00
II. TANAH DAN PASIR
1 Galian tanah pondasi 22.500 m3 SNI DT-91-006-2007(6.2) 35,100.00 789,750.00
2 Mengurug kembali 1/3 X Galian 263,250.00
3 Urugan Tanah Peninggian Lantai 32.400 m3 SNI DT-91-006-2007(6.10) 69,000.00 2,235,600.00
4 Urugan Pasir Pondasi 3.375 m3 SNI DT-91-006-2007(6.11) 59,400.00 200,475.00
5 Urugan Pasir Lantai 8.100 m3 SNI DT-91-006-2007(6.11) 59,400.00 481,140.00
3,970,215.00
III. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pas. Batu Kosong 2.100 m3 SNI DT-91-007-2007(6.9) 153,345.00 322,024.50
2 Pas. Pondasi batu kali 5.160 m3 SNI DT-91-007-2007(6.1) 409,120.00 2,111,059.20
3 Pas. tembok bata camp. 1pc : 5 ps 216.000 m2 SNI DT-91-0009-2007(6.10) 66,953.20 14,461,891.20
4 Pas. tembok bata trasram camp. 1pc : 3 ps 24.600 m2 SNI DT-91-0009-2007(6.8) 72,468.80 1,782,732.48
5 Plesteran dinding bata camp. 1pc : 5 ps 481.200 m2 SNI DT-91-0010-2007(6.5) 24,113.16 11,603,252.59
6 Plesteran Beton Kolom ,Listplank 1pc : 3 ps 51.020 m2 SNI DT-91-0010-2007(6.3) 27,147.24 1,385,052.18
7 Finishing Plesteran ( Acian ) 481.200 m2 SNI DT-91-0010-2007(6.27) 15,460.00 7,439,352.00
39,105,364.16
IV. PEKERJAAN BETON MUTU K. 225
1 Beton lantai kerja bawah Pondasi 1.600 m3 SNI DT-91-0008-2007(6.4) 515,346.55 824,554.48
2 Beton pondasi plat setempat 2,5 x 2,5 2.210 m3 SNI DT-91-0008-2007(6.7a1) 2,025,415.12 4,476,167.41
3 Beton pondasi plat setempat 1,25x1,25 1.920 m3 SNI DT-91-0008-2007(6.7a1) 2,025,415.12 3,888,797.02
4 Beton sloof 20/35 cm 2.501 m3 SNI DT-91-0008-2007(6.7b) 2,953,903.52 7,387,712.71
5 Beton sloof 15/20 cm 0.813 m3 SNI DT-91-0008-2007(6.7b) 2,953,903.52 2,401,523.57
6 Beton kolom 40/40 cm (L1) 1.012 m3 SNI DT-91-0008-2007(6.7h) 4,716,949.05 4,773,552.44
7 Beton kolom 25/25 cm (L1) 1.550 m3 SNI DT-91-0008-2007(6.7h1) 5,299,686.11 8,214,513.47
8 Beton Tangga 1.041 m3 SNI DT-91-0008-2007(6.7b) 2,953,903.52 3,075,013.57
9 Beton kolom praktis 10/10 cm Lantai 1 (Kp1) 0.645 m3 SNI DT-91-0008-2007(6.7i) 6,176,201.57 3,983,650.01
10 Beton Balok Lantai 30/70 0.252 m3 SNI DT-91-0008-2007(6.7n1) 3,759,481.90 947,389.44
11 Beton Balok Lantai 25/60 0.468 m3 SNI DT-91-0008-2007(6.7n1) 3,759,481.90 1,757,557.79
12 Beton Balok Lantai 25/35 0.297 m3 SNI DT-91-0008-2007(6.7n2) 3,273,551.78 971,835.68
13 Beton Plat Lantai T = 12 cm 9.720 m3 SNI DT-91-0008-2007(6.7L) 3,072,423.33 29,863,954.80
14 Beton kolom 25/25cm ( L.2) 0.864 m3 SNI DT-91-0008-2007(6.7h) 4,716,949.05 4,074,264.74
15 Beton kolom praktis 10/10 cm Lantai 2 (Kp 2 ) 0.360 m3 SNI DT-91-0008-2007(6.7j) 6,182,539.00 2,225,714.04
16 Beton Balok Ring 15/20 0.619 m3 SNI DT-91-0008-2007(6.7n) 4,835,402.39 2,990,696.38
81,856,897.55
V. PEKERJAAN KUSEN DAN DAUN
1 Kusen pintu / jendela 0.960 M3 LS 6,000,000.00 5,760,000.00
2 Daun jendela kaca 3 mm 20.000 BH LS 110,000.00 2,200,000.00
3 Daun pintu panil 4.000 BH LS 250,000.00 1,000,000.00
4 Kaca 5 mm (bening) 8.000 m2 LS 90,000.00 720,000.00
9,680,000.00
VI PEKERJAAN KUDA KUDA BAJA DAN ATAP
1 Kuda kuda Baja Ringan 172.90 m2 ls 132,500.00 22,909,250.00
2 Listplank Kalsi 44.00 m' LS 50,000.00 2,200,000.00
3 Atap Genteng Multi roof 172.90 m2 LS 55,000.00 9,509,500.00
4 Bubungan Genteng Multi roof 24.00 m' LS 25,000.00 600,000.00
35,218,750.00
VII. PEKERJAAN LANTAI,PELAPIS DINDING DAN PLAFOND
1 Pas. lantai keramik 40 x 40 cm 182.000 m2 SNI DT-91-0012-2007(6.35) 114,895.00 20,910,890.00
2 Plafond Kalsibort (Rangka Kayu) 121.000 m2 ls 60,000.00 7,260,000.00
3 List pinggir plafond 72.000 m LS 3,500.00 252,000.00
28,422,890.00
VIII. PEKERJAAN BESI / PENGUNCI
1 Kunci tanam 2.00 bh LS 125,000.00 250,000.00
2 Grendel Tanam 2.00 bh LS 15,000.00 30,000.00
3 Engsel jendela 40.00 bh LS 10,000.00 400,000.00
4 Hak angin 40.00 bh LS 10,000.00 400,000.00
5 Grendel jendela 20.00 bh LS 10,000.00 200,000.00
6 Engsel pintu 4.00 bh LS 20,000.00 80,000.00
1,360,000.00
IX. PEKERJAAN INSTALASI LISTRIK
1 Instalasi Penerangan(titik Lampu ) 9.000 Titik LS 35,000.00 315,000.00
2 Lampu Pilip XL 18 Wat 8.000 bh Ls 27,500.00 220,000.00
3 Instalasi Stop Kontak 2.000 bh LS 25,000.00 50,000.00
4 Saklar tunggal 2.000 bh Ls 20,000.00 40,000.00
5 Saklar double 2.000 bh Ls 25,000.00 50,000.00
675,000.00
X. PEKERJAAN PENGECATAN
1 Cat tembok 481.200 m2 M6.11b 13,841.50 6,660,529.80
2 Cat Plafond 121.000 m2 M6.11b 13,841.50 1,674,821.50
3 Cat kayu 41.700 m2 M6.8 16,710.00 696,807.00
9,032,158.30
XI. PENGADAAN MEUBELAIR
1 Pengadaan Meubelair Ruang Kelas Lengkap 2.000 kls ls 15,000,000.00 30,000,000.00
30,000,000.00
REKAPITULASI TOTAL
JUMLAH Rp 240,001,275.01
DIBULATKAN Rp 240,000,000.00
BAIDAWI, SE
DAFTAR ANALISA HARGA SATUAN TH 2012
1. PEKERJAAN TANAH
SNI 6.4 1 M PENGUKURAN DAN PEMASANGAN BOUPLANK UNTUK GEDUNG
0.0120 M3 Kayu kls II 3,500,000.00 42,000.00
0.0200 kg Paku 15,000.00 300.00
0.0070 m3 Papan kayu kls II 3,500,000.00 24,500.00
0.1000 hari Tukang kayu 50,000.00 5,000.00
0.0100 hari Kepala tukang kayu 55,000.00 550.00
0.1000 Hari Pekerja 36,000.00 3,600.00
0.0050 Hari Mandor 60,000.00 300.00
76,250.00
SNI-DT-91-0011-2007( 6.20a) 4.8 M2 PAGAR PEMGAMAN DG SENG GELOMBANG
0.0560 m³ Kayu kls II 3,500,000.00 196,000.00
0.1000 kg Paku 15,000.00 1,500.00
0.0500 kg Paku Seng 15,000.00 750.00
6.0000 lbr Seng Gelombang 35,000.00 210,000.00
0.1000 Hari Tukang kayu 50,000.00 5,000.00
0.0100 Hari Kepala tukang kayu 55,000.00 550.00
0.1605 Hari Pekerja 36,000.00 5,778.00
0.0161 Hari Mandor 60,000.00 963.00
420,541.00
Untuk 1 m2 Pagar Pengaman Proyek 87,612.71
SNI DT-91-0008-2007(6.4) 1 M3 BETON mutu f' = 7.4 MPa(K100) ,slump (12+2) cm,w/c 0.87
247.0000 kg Semen/kg 1,240.00 306,280.00
0.6952 m3 Krikil pecah 2/3 125,000.00 86,896.55
0.5400 m3 Pasir Beton 75,000.00 40,500.00
200.0000 ltr Air 10.00 2,000.00
0.2750 Hari Tukang batu 50,000.00 13,750.00
0.0280 Hari Kepala tukang batu 55,000.00 1,540.00
1.6500 Hari Pekerja 36,000.00 59,400.00
0.0830 Hari Mandor 60,000.00 4,980.00
515,346.55
SNI DT-91-0008-2007(6.7) 1 M3 BETON mutu f' = 19.3 Mpa (K225) ,slump (12+2) cm,w/c 0.58
371.000 kg Semen/kg 1,240.00 460,040.00
0.720 m3 Krikil pecah 2/3 125,000.00 90,000.00
0.440 m3 Pasir Beton 75,000.00 33,000.00
215.000 ltr Air 10.00 2,150.00
0.275 Hari Tukang batu 50,000.00 13,750.00
0.028 Hari Kepala tukang batu 55,000.00 1,512.50
1.650 Hari Pekerja 36,000.00 59,400.00
0.083 Hari Mandor 60,000.00 4,980.00
664,832.50
SNI DT-91-0008-2007(6.7a) 1 m3 PONDASI FOOT PLAT BETON BERTULANG (2.50 x 2.50 m)
1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
1.2759 m2 BEGISTING PONDASI /SNI DT-91-0008-2007(6.20) 59,705.00 76,178.63
134.5531 kg Besi Beton Ulir (SNI DT- 91-0008- 2007(6.17) 9,199.50 1,237,821.34
61.7033 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 567,639.96
, 2,546,472.43
1 2 3 4 5 6
I PEKERJAAN PENDAHULUAN
1 Pengukuran /Uitzet & Bouplank 36.00 m 0.07 100.00 0.07
2 Bongkar Bangunan Lama 1.00 unit 0.21 100.00 0.21
-
II. TANAH DAN PASIR -
1 Galian tanah pondasi 22.500 m3 0.33 100.00 0.33
2 Mengurug kembali 1/3 X Galian 0.11 100.00 0.11
3 Urugan Tanah Peninggian Lantai 32.400 m3 0.93 100.00 0.93
4 Urugan Pasir Pondasi 3.375 m3 0.08 100.00 0.08
5 Urugan Pasir Lantai 8.100 m3 0.20 0.00 -
-
III. PEKERJAAN PASANGAN DAN PLESTERAN -
1 Pas. Batu Kosong 2.100 m3 0.13 100.00 0.13
2 Pas. Pondasi batu kali 5.160 m3 0.88 100.00 0.88
3 Pas. tembok bata camp. 1pc : 5 ps 216.000 m2 6.03 100.00 6.03
4 Pas. tembok bata trasram camp. 1pc : 3 ps 24.600 m2 0.74 100.00 0.74
5 Plesteran dinding bata camp. 1pc : 5 ps 481.200 m2 4.83 100.00 4.83
6 Plesteran Beton Kolom ,Listplank 1pc : 3 ps 51.020 m2 0.58 100.00 0.58
7 Finishing Plesteran ( Acian ) 481.200 m2 3.10 100.00 3.10
-
IV. PEKERJAAN BETON MUTU K. 225 -
1 Beton lantai kerja bawah Pondasi 1.600 m3 0.34 100.00 0.34
2 Beton pondasi plat setempat 2,5 x 2,5 2.210 m3 1.87 100.00 1.87
3 Beton pondasi plat setempat 1,25x1,25 1.920 m3 1.62 100.00 1.62
4 Beton sloof 20/35 cm 2.501 m3 3.08 100.00 3.08
5 Beton sloof 15/20 cm 0.813 m3 1.00 100.00 1.00
6 Beton kolom 40/40 cm (L1) 1.012 m3 1.99 100.00 1.99
7 Beton kolom 25/25 cm (L1) 1.550 m3 3.42 100.00 3.42
8 Beton Tangga 1.041 m3 1.28 100.00 1.28
9 Beton kolom praktis 10/10 cm Lantai 1 (Kp1) 0.645 m3 1.66 100.00 1.66
10 Beton Balok Lantai 30/70 0.252 m3 0.39 100.00 0.39
11 Beton Balok Lantai 25/60 0.468 m3 0.73 100.00 0.73
12 Beton Balok Lantai 25/35 0.297 m3 0.40 100.00 0.40
13 Beton Plat Lantai T = 12 cm 9.720 m3 12.44 100.00 12.44
14 Beton kolom 25/25cm ( L.2) 0.864 m3 1.70 100.00 1.70
15 Beton kolom praktis 10/10 cm Lantai 2 (Kp 2 ) 0.360 m3 0.93 100.00 0.93
16 Beton Balok Ring 15/20 0.619 m3 1.25 100.00 1.25
-
V. PEKERJAAN KUSEN DAN DAUN -
1 Kusen pintu / jendela 0.960 M3 2.40 100.00 2.40
2 Daun jendela kaca 3 mm 20.000 BH 0.92 0.00 -
3 Daun pintu panil 4.000 BH 0.42 0.00 -
4 Kaca 5 mm (bening) 8.000 m2 0.30 0.00 -
-
VI PEKERJAAN KUDA KUDA BAJA DAN ATAP -
1 Kuda kuda Baja Ringan 172.90 m2 9.55 100.00 9.55
2 Listplank Kalsi 44.00 m' 0.92 100.00 0.92
3 Atap Genteng Multi roof 172.90 m2 3.96 100.00 3.96
4 Bubungan Genteng Multi roof 24.00 m' 0.25 100.00 0.25
-
VII. PEKERJAAN LANTAI,PELAPIS DINDING DAN PLAFOND -
1 Pas. lantai keramik 40 x 40 cm 182.000 m2 8.71 35.00 3.05
2 Plafond Kalsibort (Rangka Kayu) 121.000 m2 3.02 100.00 3.02
3 List pinggir plafond 72.000 m 0.10 100.00 0.10
-
VIII. PEKERJAAN BESI / PENGUNCI -
1 Kunci tanam 2.00 bh 0.10 0.00 -
2 Grendel Tanam 2.00 bh 0.01 0.00 -
3 Engsel jendela 40.00 bh 0.17 0.00 -
4 Hak angin 40.00 bh 0.17 0.00 -
5 Grendel jendela 20.00 bh 0.08 0.00 -
6 Engsel pintu 4.00 bh 0.03 0.00 -
-
IX. PEKERJAAN INSTALASI LISTRIK -
1 Instalasi Penerangan(titik Lampu ) 9.000 Titik 0.13 50.00 0.07
2 Lampu Pilip XL 18 Wat 8.000 bh 0.09 0.00 -
3 Instalasi Stop Kontak 2.000 bh 0.02 50.00 0.01
4 Saklar tunggal 2.000 bh 0.02 0.00 -
5 Saklar double 2.000 bh 0.02 0.00 -
-
X. PEKERJAAN PENGECATAN -
1 Cat tembok 481.200 m2 2.78 0.00 -
2 Cat Plafond 121.000 m2 0.70 0.00 -
3 Cat kayu 41.700 m2 0.29 0.00 -
-
XI. PENGADAAN MEUBELAIR -
1 Pengadaan Meubelair Ruang Kelas Lengkap 2.000 kls 12.50 100.00 12.50
CATATAN
1 Kemajuan Pekerjaan sampai dengan tanggal …. Mei 2013
adalah sebesar 87.968 %