Anda di halaman 1dari 26

RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN RUANG KELAS BARU (BERTINGKAT) SMK DARUL FALAH


LOKASI : JL. BHANDA SRAYA PAGUTAN
TAHUN ANGGARAN :2012

Kode Harga satuan Jumlah


No Uraian Pekerjaan Volume
Analisa (Rp) (Rp)
1 2 3 4 5 6

I PEKERJAAN PENDAHULUAN
1 Pengukuran /Uitzet & Bouplank 36.00 m LS 5,000.00 180,000.00
2 Bongkar Bangunan Lama 1.00 unit Ls 500,000.00 500,000.00
680,000.00
II. TANAH DAN PASIR
1 Galian tanah pondasi 22.500 m3 SNI DT-91-006-2007(6.2) 35,100.00 789,750.00
2 Mengurug kembali 1/3 X Galian 263,250.00
3 Urugan Tanah Peninggian Lantai 32.400 m3 SNI DT-91-006-2007(6.10) 69,000.00 2,235,600.00
4 Urugan Pasir Pondasi 3.375 m3 SNI DT-91-006-2007(6.11) 59,400.00 200,475.00
5 Urugan Pasir Lantai 8.100 m3 SNI DT-91-006-2007(6.11) 59,400.00 481,140.00
3,970,215.00
III. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pas. Batu Kosong 2.100 m3 SNI DT-91-007-2007(6.9) 153,345.00 322,024.50
2 Pas. Pondasi batu kali 5.160 m3 SNI DT-91-007-2007(6.1) 409,120.00 2,111,059.20
3 Pas. tembok bata camp. 1pc : 5 ps 216.000 m2 SNI DT-91-0009-2007(6.10) 66,953.20 14,461,891.20
4 Pas. tembok bata trasram camp. 1pc : 3 ps 24.600 m2 SNI DT-91-0009-2007(6.8) 72,468.80 1,782,732.48
5 Plesteran dinding bata camp. 1pc : 5 ps 481.200 m2 SNI DT-91-0010-2007(6.5) 24,113.16 11,603,252.59
6 Plesteran Beton Kolom ,Listplank 1pc : 3 ps 51.020 m2 SNI DT-91-0010-2007(6.3) 27,147.24 1,385,052.18
7 Finishing Plesteran ( Acian ) 481.200 m2 SNI DT-91-0010-2007(6.27) 15,460.00 7,439,352.00
39,105,364.16
IV. PEKERJAAN BETON MUTU K. 225
1 Beton lantai kerja bawah Pondasi 1.600 m3 SNI DT-91-0008-2007(6.4) 515,346.55 824,554.48
2 Beton pondasi plat setempat 2,5 x 2,5 2.210 m3 SNI DT-91-0008-2007(6.7a1) 2,025,415.12 4,476,167.41
3 Beton pondasi plat setempat 1,25x1,25 1.920 m3 SNI DT-91-0008-2007(6.7a1) 2,025,415.12 3,888,797.02
4 Beton sloof 20/35 cm 2.501 m3 SNI DT-91-0008-2007(6.7b) 2,953,903.52 7,387,712.71
5 Beton sloof 15/20 cm 0.813 m3 SNI DT-91-0008-2007(6.7b) 2,953,903.52 2,401,523.57
6 Beton kolom 40/40 cm (L1) 1.012 m3 SNI DT-91-0008-2007(6.7h) 4,716,949.05 4,773,552.44
7 Beton kolom 25/25 cm (L1) 1.550 m3 SNI DT-91-0008-2007(6.7h1) 5,299,686.11 8,214,513.47
8 Beton Tangga 1.041 m3 SNI DT-91-0008-2007(6.7b) 2,953,903.52 3,075,013.57
9 Beton kolom praktis 10/10 cm Lantai 1 (Kp1) 0.645 m3 SNI DT-91-0008-2007(6.7i) 6,176,201.57 3,983,650.01
10 Beton Balok Lantai 30/70 0.252 m3 SNI DT-91-0008-2007(6.7n1) 3,759,481.90 947,389.44
11 Beton Balok Lantai 25/60 0.468 m3 SNI DT-91-0008-2007(6.7n1) 3,759,481.90 1,757,557.79
12 Beton Balok Lantai 25/35 0.297 m3 SNI DT-91-0008-2007(6.7n2) 3,273,551.78 971,835.68
13 Beton Plat Lantai T = 12 cm 9.720 m3 SNI DT-91-0008-2007(6.7L) 3,072,423.33 29,863,954.80
14 Beton kolom 25/25cm ( L.2) 0.864 m3 SNI DT-91-0008-2007(6.7h) 4,716,949.05 4,074,264.74
15 Beton kolom praktis 10/10 cm Lantai 2 (Kp 2 ) 0.360 m3 SNI DT-91-0008-2007(6.7j) 6,182,539.00 2,225,714.04
16 Beton Balok Ring 15/20 0.619 m3 SNI DT-91-0008-2007(6.7n) 4,835,402.39 2,990,696.38
81,856,897.55
V. PEKERJAAN KUSEN DAN DAUN
1 Kusen pintu / jendela 0.960 M3 LS 6,000,000.00 5,760,000.00
2 Daun jendela kaca 3 mm 20.000 BH LS 110,000.00 2,200,000.00
3 Daun pintu panil 4.000 BH LS 250,000.00 1,000,000.00
4 Kaca 5 mm (bening) 8.000 m2 LS 90,000.00 720,000.00
9,680,000.00
VI PEKERJAAN KUDA KUDA BAJA DAN ATAP
1 Kuda kuda Baja Ringan 172.90 m2 ls 132,500.00 22,909,250.00
2 Listplank Kalsi 44.00 m' LS 50,000.00 2,200,000.00
3 Atap Genteng Multi roof 172.90 m2 LS 55,000.00 9,509,500.00
4 Bubungan Genteng Multi roof 24.00 m' LS 25,000.00 600,000.00
35,218,750.00
VII. PEKERJAAN LANTAI,PELAPIS DINDING DAN PLAFOND
1 Pas. lantai keramik 40 x 40 cm 182.000 m2 SNI DT-91-0012-2007(6.35) 114,895.00 20,910,890.00
2 Plafond Kalsibort (Rangka Kayu) 121.000 m2 ls 60,000.00 7,260,000.00
3 List pinggir plafond 72.000 m LS 3,500.00 252,000.00
28,422,890.00
VIII. PEKERJAAN BESI / PENGUNCI
1 Kunci tanam 2.00 bh LS 125,000.00 250,000.00
2 Grendel Tanam 2.00 bh LS 15,000.00 30,000.00
3 Engsel jendela 40.00 bh LS 10,000.00 400,000.00
4 Hak angin 40.00 bh LS 10,000.00 400,000.00
5 Grendel jendela 20.00 bh LS 10,000.00 200,000.00
6 Engsel pintu 4.00 bh LS 20,000.00 80,000.00
1,360,000.00
IX. PEKERJAAN INSTALASI LISTRIK
1 Instalasi Penerangan(titik Lampu ) 9.000 Titik LS 35,000.00 315,000.00
2 Lampu Pilip XL 18 Wat 8.000 bh Ls 27,500.00 220,000.00
3 Instalasi Stop Kontak 2.000 bh LS 25,000.00 50,000.00
4 Saklar tunggal 2.000 bh Ls 20,000.00 40,000.00
5 Saklar double 2.000 bh Ls 25,000.00 50,000.00
675,000.00

X. PEKERJAAN PENGECATAN
1 Cat tembok 481.200 m2 M6.11b 13,841.50 6,660,529.80
2 Cat Plafond 121.000 m2 M6.11b 13,841.50 1,674,821.50
3 Cat kayu 41.700 m2 M6.8 16,710.00 696,807.00
9,032,158.30
XI. PENGADAAN MEUBELAIR
1 Pengadaan Meubelair Ruang Kelas Lengkap 2.000 kls ls 15,000,000.00 30,000,000.00
30,000,000.00
REKAPITULASI TOTAL

PEKERJAAN : PEMBANGUNAN RUANG KELAS BARU (BERTINGKAT) SMK DARUL FALAH


LOKASI : JL. BHANDA SRAYA PAGUTAN
TAHUN ANGGARAN :2012

NO URAIAN PEKERJAAN JUMLAH

I PEKERJAAN PENDAHULUAN 680,000.00


II PEKERJAAN TANAH DAN PASIR 3,970,215.00
III PEKERJAAN PASANGAN DAN PLESTERAN 39,105,364.16
IV PEKERJAAN BETON MUTU K. 225 81,856,897.55
V PEKERJAAN KUSEN DAN DAUN 9,680,000.00
VI PEKERJAAN KUDA KUDA BAJA DAN ATAP 35,218,750.00
VII PEKERJAAN LANTAI,PELAPIS DINDING DAN PLAFOND 28,422,890.00
VIII PEKERJAAN BESI / PENGUNCI 1,360,000.00
IX PEKERJAAN INSTALASI LISTRIK 675,000.00
XI PEKERJAAN PENGECATAN 9,032,158.30
XI. PENGADAAN MEUBELAIR 30,000,000.00

JUMLAH Rp 240,001,275.01
DIBULATKAN Rp 240,000,000.00

Terbilang : Dua Ratus empat puluh ribu Rupiah

Mataram, Desember 2012


KEPALA
SMK DARUL FALAH

BAIDAWI, SE
DAFTAR ANALISA HARGA SATUAN TH 2012

Kode Harga Satuan Jumlah Harga


Koefisien Sat Uraian
Analisa (Rp.) (Rp.)

1. PEKERJAAN TANAH
SNI 6.4 1 M PENGUKURAN DAN PEMASANGAN BOUPLANK UNTUK GEDUNG
0.0120 M3 Kayu kls II 3,500,000.00 42,000.00
0.0200 kg Paku 15,000.00 300.00
0.0070 m3 Papan kayu kls II 3,500,000.00 24,500.00
0.1000 hari Tukang kayu 50,000.00 5,000.00
0.0100 hari Kepala tukang kayu 55,000.00 550.00
0.1000 Hari Pekerja 36,000.00 3,600.00
0.0050 Hari Mandor 60,000.00 300.00
76,250.00
SNI-DT-91-0011-2007( 6.20a) 4.8 M2 PAGAR PEMGAMAN DG SENG GELOMBANG
0.0560 m³ Kayu kls II 3,500,000.00 196,000.00
0.1000 kg Paku 15,000.00 1,500.00
0.0500 kg Paku Seng 15,000.00 750.00
6.0000 lbr Seng Gelombang 35,000.00 210,000.00
0.1000 Hari Tukang kayu 50,000.00 5,000.00
0.0100 Hari Kepala tukang kayu 55,000.00 550.00
0.1605 Hari Pekerja 36,000.00 5,778.00
0.0161 Hari Mandor 60,000.00 963.00
420,541.00
Untuk 1 m2 Pagar Pengaman Proyek 87,612.71

SNI DT-91-006-2007(6.1) 1 M3 GALIAN TANAH SEDALAM 1 M


0.7500 Hari Pekerja 36,000.00 27,000.00
0.0250 Hari Mandor 60,000.00 1,500.00
28,500.00
SNI DT-91-006-2007(6.2) 1 M3 GALIAN TANAH SEDALAM 2M
0.9000 Hari Pekerja 36,000.00 32,400.00
0.0450 Hari Mandor 60,000.00 2,700.00
35,100.00

SNI DT-91-006-2007(6.10) 1 M3 URUGAN TANAH TERMASUK DAN PEMADATAN PER 20 CM


1.2000 m3 Tanah urug 40,000.00 48,000.00
0.5000 Hari Pekerja 36,000.00 18,000.00
0.0500 Hari Mandor 60,000.00 3,000.00
69,000.00

SNI DT-91-006-2007(6.11) 1 M3 URUGAN PASIR TERMASUK PENYIRAMAN DAN PEMADATAN


1.2000 m³ Pasir urug 40,000.00 48,000.00
0.3000 Hari Pekerja 36,000.00 10,800.00
0.0100 Hari Mandor 60,000.00 600.00
59,400.00
SNI DT-91-006-2007(6.15) 1 M3 URUGAN SIRTU TERMASUK PENYIRAMAN DAN PEMADATAN
1.2000 m³ Pasir urug 40,000.00 48,000.00
0.2500 Hari Pekerja 36,000.00 9,000.00
0.0250 Hari Mandor 60,000.00 1,500.00
58,500.00
2. PEKERJAAN PASANGAN
SNI DT-91-007-2007(6.9) 1 M3 PAS. BATU KOSONG
1.2000 m³ Batu kali 70,000.00 84,000.00
0.4320 m³ Pasir urug 40,000.00 17,280.00
0.7800 Hari Pekerja 36,000.00 28,080.00
0.3900 Hari Tukang batu 50,000.00 19,500.00
0.0390 Hari Kepala tukang batu 55,000.00 2,145.00
0.0390 Hari Mandor 60,000.00 2,340.00
153,345.00
SNI DT-91-007-2007(6.1) 1 M3 PAS. BATU BELAH 1PC : 4Ps
1.2000 m³ Batu kali 70,000.00 84,000.00
163.0000 kg Semen/kg 1,240.00 202,120.00
0.5200 m³ Pasir pasang 60,000.00 31,200.00
0.6000 Hari Tukang batu 50,000.00 30,000.00
0.0600 Hari Kepala tukang batu 55,000.00 3,300.00
1.5000 Hari Pekerja 36,000.00 54,000.00
0.0750 Hari Mandor 60,000.00 4,500.00
409,120.00
SNI DT-91-0009-2007(6.8) 1 M2 PAS. BATA 1PC : 3Ps
70.0000 bh Bata merah 500.00 35,000.00
14.3700 kg Semen/kg 1,240.00 17,818.80
0.0400 m³ Pasir pasang 60,000.00 2,400.00
0.1000 Hari Tukang batu 50,000.00 5,000.00
0.0100 Hari Kepala tukang batu 55,000.00 550.00
0.3000 Hari Pekerja 36,000.00 10,800.00
0.0150 Hari Mandor 60,000.00 900.00
72,468.80
SNI DT-91-0009-2007(6.10) 1 M2 PAS. BATA 1PC : 5Ps ( 1/2 BATU )
70.0000 bh Bata merah 500.00 35,000.00
9.6800 kg Semen/kg 1,240.00 12,003.20
0.0450 m³ Pasir pasang 60,000.00 2,700.00
0.1000 Hari Tukang batu 50,000.00 5,000.00
0.0100 Hari Kepala tukang batu 55,000.00 550.00
0.3000 Hari Pekerja 36,000.00 10,800.00
0.0150 Hari Mandor 60,000.00 900.00
66,953.20

3. PEKERJAAN PLESTERAN & SIARAN

SNI DT-91-0010-2007(6.3) 1 M2 PLESTERAN TASRAM 1PC : 3Ps


7.7760 kg Semen/kg 1,240.00 9,642.24
0.0230 m³ Pasir pasang 60,000.00 1,380.00
0.1500 Hari Tukang batu 50,000.00 7,500.00
0.0150 Hari Kepala tukang batu 55,000.00 825.00
0.2000 Hari Pekerja 36,000.00 7,200.00
0.0100 Hari Mandor 60,000.00 600.00
27,147.24
SNI DT-91-0010-2007(6.5) 1 M2 PLESTERAN 1PC : 5Ps
5.1840 kg Semen/kg 1,240.00 6,428.16
0.0260 m³ Pasir pasang 60,000.00 1,560.00
0.1500 Hari Tukang batu 50,000.00 7,500.00
0.0150 Hari Kepala tukang batu 55,000.00 825.00
0.2000 Hari Pekerja 36,000.00 7,200.00
0.0100 Hari Mandor 60,000.00 600.00
24,113.16
SNI DT-91-0010-2007(6.25) 1M2 FINISHING SIAR PAS. BATU KALI 1 PC : 2 PS
6.3400 kg Semen/kg 1,240.00 7,861.60
0.0120 m³ Pasir pasang 60,000.00 720.00
0.1400 Hari Tukang batu 50,000.00 7,000.00
0.0140 Hari Kepala tukang batu 55,000.00 770.00
0.3000 Hari Pekerja 36,000.00 10,800.00
0.0150 Hari Mandor 60,000.00 900.00
28,051.60
SNI DT-91-0010-2007(6.27) 1M2 ACIAN
3.2500 kg Semen/kg 1,240.00 4,030.00
0.1000 Hari Tukang batu 50,000.00 5,000.00
0.0100 Hari Kepala tukang batu 55,000.00 550.00
0.1500 Hari Pekerja 36,000.00 5,400.00
0.0080 Hari Mandor 60,000.00 480.00
15,460.00
SNI DT-91-0010-2007(6.3a) 1 M2 PARIASI PLESTERAN DAN NAT (1PC : 3Ps)
7.7760 kg Semen/kg 1,240.00 9,642.24
0.0230 m³ Pasir pasang 60,000.00 1,380.00
0.3000 Hari Tukang batu 50,000.00 15,000.00
0.0300 Hari Kepala tukang batu 55,000.00 1,650.00
0.5000 Hari Pekerja 36,000.00 18,000.00
0.0500 Hari Mandor 60,000.00 3,000.00
48,672.24
PEKERJAAN FINISHING LANTAI
SNI DT-91-0012-2007(6.35) 1 M2 PAS. LANTAI DARI KERAMIK 30/30 cm
1.0000 m² Keramik 30 X 30 45,000.00 45,000.00
10.0000 kg Semen/kg 1,240.00 12,400.00
1.5000 kg Semen warna 7,500.00 11,250.00
0.0450 m³ Pasir pasang 60,000.00 2,700.00
0.0350 Hari Kepala tukang batu 55,000.00 1,925.00
0.3500 Hari Tukang batu 50,000.00 17,500.00
0.6200 Hari Pekerja 36,000.00 22,320.00
0.0300 Hari Mandor 60,000.00 1,800.00
114,895.00
SNI DT-91-0012-2007(6.36) 1 M2 PAS. LANTAI DARI KERAMIK 20/20 cm
1.0000 m² Keramik 20 X 20 50,000.00 50,000.00
0.2938 zak Semen/zak 62,000.00 18,215.60
0.0400 kg Semen warna 7,500.00 300.00
0.0238 m³ Pasir pasang 60,000.00 1,428.00
0.0250 Hari Kepala tukang batu 55,000.00 1,375.00
0.2500 Hari Tukang batu 50,000.00 12,500.00
0.5000 Hari Pekerja 36,000.00 18,000.00
0.0250 Hari Mandor 60,000.00 1,500.00
103,318.60
SNI DT-91-0012-2007(6.50) 1 M2 PAS. DINDING DARI KERAMIK 20/20 cm 1PC : 2Ps
1.0000 m² Keramik 20 X 20 50,000.00 50,000.00
9.3000 kg Semen/kg 1,240.00 11,532.00
1.9400 kg Semen warna 7,500.00 14,550.00
0.0180 m³ Pasir pasang 60,000.00 1,080.00
0.0450 Hari Kepala tukang batu 55,000.00 2,475.00
0.4500 Hari Tukang batu 50,000.00 22,500.00
0.6000 Hari Pekerja 36,000.00 21,600.00
0.0300 Hari Mandor 60,000.00 1,800.00
125,537.00
SNI DT-91-0012-2007(6.35a) 1 M2 PAS. LANTAI DARI KERAMIK 60/60 cm 1PC : 2Ps
1.0000 m² Keramik 60 X 60 (Motif) 50,000.00 50,000.00
10.0000 kg Semen/kg 1,240.00 12,400.00
1.5000 kg Semen warna 7,500.00 11,250.00
0.0450 m³ Pasir pasang 60,000.00 2,700.00
0.0350 Hari Kepala tukang batu 55,000.00 1,925.00
0.3500 Hari Tukang batu 50,000.00 17,500.00
0.6200 Hari Pekerja 36,000.00 22,320.00
0.0300 Hari Mandor 60,000.00 1,800.00
119,895.00

SNI DT-91-0012-2007(6.9) 1 M2 PAS. LANTAI DARI GRANIT 40/40 cm 1PC : 2Ps


6.6300 bh Granit Warna Gelap 45,000.00 298,350.00
10.0000 kg Semen/kg 1,240.00 12,400.00
1.3000 kg Semen warna 7,500.00 9,750.00
0.0450 m³ Pasir pasang 60,000.00 2,700.00
0.0120 Hari Kepala tukang batu 55,000.00 660.00
0.1200 Hari Tukang batu 50,000.00 6,000.00
0.2500 Hari Pekerja 36,000.00 9,000.00
0.0130 Hari Mandor 60,000.00 780.00
339,640.00
SNI DT-91-0012-2007(6.55) 1 M2 PAS. DINDING BATU SISIR 40/40 cm 1PC : 2Ps
1.0000 m2 Batu Sikat 150,000.00 150,000.00
10.0000 kg Semen/kg 1,240.00 12,400.00
0.0450 m³ Pasir pasang 60,000.00 2,700.00
0.0120 Hari Kepala tukang batu 55,000.00 660.00
0.1200 Hari Tukang batu 50,000.00 6,000.00
0.2500 Hari Pekerja 36,000.00 9,000.00
0.0130 Hari Mandor 60,000.00 780.00
181,540.00
SNI DT-91-0012-2007(6.59) 1 M2 PAS. LANTAI DARI NINYL 30/30 cm
1.0000 m² Vinyl 30/30 250,000.00 250,000.00
0.3500 kg Lem Vinyl 15,000.00 5,250.00
0.0150 Hari Kepala tukang batu 55,000.00 825.00
0.1500 Hari Tukang batu 50,000.00 7,500.00
0.1500 Hari Pekerja 36,000.00 5,400.00
0.0080 Hari Mandor 60,000.00 480.00
269,455.00
SNI DT-91-0012-2007(6.39) 1 M' PAS. PLINT KERAMIK 10/30 cm 1PC : 2Ps
3.5298 bh Plint keramik 10 X 30 cm 5,000.00 17,649.00
0.5700 kg Semen/kg 1,240.00 706.80
0.0250 kg Semen warna 7,500.00 187.50
0.0030 m³ Pasir pasang 60,000.00 180.00
0.0090 Hari Kepala tukang batu 55,000.00 495.00
0.0900 Hari Tukang batu 50,000.00 4,500.00
0.0900 Hari Pekerja 36,000.00 3,240.00
0.0050 Hari Mandor 60,000.00 300.00
27,258.30
5. PEKERJAAN KAYU
F.16 1 M2 PEK. USUK 5/7 & RENG 3/4 UNTUK GENTENG METAL
0.0058 m³ Kayu kls II 3,500,000.00 20,300.00
0.0014 m³ Kayu kls I 7,500,000.00 10,500.00
0.2500 kg Paku 15,000.00 3,750.00
0.2000 Hari Tukang kayu 50,000.00 10,000.00
0.0200 Hari Kepala tukang kayu 55,000.00 1,100.00
0.2000 Hari Pekerja 36,000.00 7,200.00
0.0100 Hari Mandor 60,000.00 600.00
53,450.00
F.16a 1 M2 PEK. USUK 4/6 & RENG 2/3 EXPOSE
0.0111 m³ Kayu kls II 3,500,000.00 38,850.00
0.0042 m³ Kayu kls I 7,500,000.00 31,500.00
0.2500 kg Paku 15,000.00 3,750.00
1.0000 Hari Tukang kayu 50,000.00 50,000.00
0.1000 Hari Kepala tukang kayu 55,000.00 5,500.00
0.5000 Hari Pekerja 36,000.00 18,000.00
0.0250 Hari Mandor 60,000.00 1,500.00
149,100.00
SNI DT -9-0011-2007(6.16) 1 M2 PEK. USUK 5/7 & RENG 3/4 UNTUK GENTENG METAL
0.0140 m³ Kayu kls II 3,500,000.00 49,000.00
0.0360 m³ Kayu kls II 3,500,000.00 126,000.00
0.2500 kg Paku 15,000.00 3,750.00
0.1000 Hari Tukang kayu 50,000.00 5,000.00
0.0100 Hari Kepala tukang kayu 55,000.00 550.00
0.1000 Hari Pekerja 36,000.00 3,600.00
0.0050 Hari Mandor 60,000.00 300.00
188,200.00
SNI DT -9-0011-2007(6.21a) 1 M' PAS.LIST PLANK KALSI
0.3000 lbr Kalsi Plank 55,000.00 16,500.00
0.1200 kg Paku 15,000.00 1,800.00
0.2000 Hari Tukang kayu 50,000.00 10,000.00
0.0250 Hari Kepala tukang kayu 55,000.00 1,375.00
0.1000 Hari Pekerja 36,000.00 3,600.00
0.0050 Hari Mandor 60,000.00 300.00
33,575.00
F.21a 1 M2 PAS.PAPAN ROUTER (NOK)
0.0300 m³ Papan kayu kls II 3,500,000.00 105,000.00
0.2500 kg Paku 15,000.00 3,750.00
0.6000 Hari Tukang kayu 50,000.00 30,000.00
0.0600 Hari Kepala tukang kayu 55,000.00 3,300.00
0.2100 Hari Pekerja 36,000.00 7,560.00
0.0105 Hari Mandor 60,000.00 630.00
150,240.00

F6.13 1 M3 PEK.KUDA KUDA KAYU KLAS II


1.1000 m³ Kayu kls II 3,500,000.00 3,850,000.00
5.6000 kg Paku 15,000.00 84,000.00
15.0000 m' Karet talang 60 Cm 20,000.00 300,000.00
12.0000 Hari Tukang kayu 50,000.00 600,000.00
1.2000 Hari Kepala tukang kayu 55,000.00 66,000.00
4.0000 Hari Pekerja 36,000.00 144,000.00
0.4000 Hari Mandor 60,000.00 24,000.00
5,068,000.00
F6.1 1 M3 PEK.KAYU KUSEN KLS I
1.1000 m³ Kayu kls I 7,500,000.00 8,250,000.00
1.2500 kg Paku 15,000.00 18,750.00
1.0000 kg Lem Aica aibon 20,000.00 20,000.00
20.0000 Hari Tukang kayu 50,000.00 1,000,000.00
2.0000 Hari Kepala tukang kayu 55,000.00 110,000.00
6.0000 Hari Pekerja 36,000.00 216,000.00
0.3000 Hari Mandor 60,000.00 18,000.00
9,632,750.00
SNI DT-91-0014-2007(6.11) 1 M PEK.KUSEN PINTU ALMUNIUM
1.1000 M Profil Almunium 60,000.00 66,000.00
2.0000 bh Skrup fixer 200.00 400.00
1.0000 tube Sealant 20,000.00 20,000.00
0.0430 Hari Tukang besi 50,000.00 2,150.00
0.0043 Hari Kepala tukang besi 55,000.00 236.50
0.0430 Hari Pekerja 36,000.00 1,548.00
0.0021 Hari Mandor 60,000.00 126.00
90,460.50
F6.2 1 M3 PEK.KAYU KUSEN KLS II
1.1000 m³ Kayu kls II 3,500,000.00 3,850,000.00
1.2500 kg Paku 15,000.00 18,750.00
1.0000 kg Lem Aica aibon 20,000.00 20,000.00
18.0000 Hari Tukang kayu 50,000.00 900,000.00
2.0000 Hari Kepala tukang kayu 55,000.00 110,000.00
6.0000 Hari Pekerja 36,000.00 216,000.00
0.3000 Hari Mandor 60,000.00 18,000.00
5,132,750.00

F6.6a 1 M2 DAUN JENDELA KACA 3 mm


0.0240 m³ Papan kayu kls I 7,500,000.00 180,000.00
0.3000 kg Lem Aica aibon 20,000.00 6,000.00
2.0000 Hari Tukang kayu 50,000.00 100,000.00
0.2000 Hari Kepala tukang kayu 55,000.00 11,000.00
0.8000 Hari Pekerja 36,000.00 28,800.00
0.0400 Hari Mandor 60,000.00 2,400.00
0.8200 m² Kaca 3 mm (bening) 65,000.00 53,300.00
381,500.00

F6.6 1 M2 DAUN PINTU KACA 5 mm


0.0240 m³ Papan kayu kls I 7,500,000.00 180,000.00
0.3000 kg Lem Aica aibon 20,000.00 6,000.00
2.0000 Hari Tukang kayu 50,000.00 100,000.00
0.2000 Hari Kepala tukang kayu 55,000.00 11,000.00
0.8000 Hari Pekerja 36,000.00 28,800.00
0.0400 Hari Mandor 60,000.00 2,400.00
0.8000 m² Kaca 5 mm (bening) 95,000.00 76,000.00
404,200.00
F.1a 1 M' RAM PINTU/JENDELA ALUMINIUM
1.2000 m' Ram kusen aluminium 50,000.00 60,000.00
0.0500 m' Baut piles 20,000.00 1,000.00
1.2000 m' Karet list 1,000.00 1,200.00
2.0000 Hari Tukang besi 50,000.00 100,000.00
0.2000 Hari Kepala tukang besi 55,000.00 11,000.00
1.0000 Hari Pekerja 36,000.00 36,000.00
Hari Mandor 60,000.00 #VALUE!
209,200.00
F.2 1 M2 DAUN PINTU PINTU/JENDELA ALUMINIUM & KACA SUSU
4.3230 m' Ram kusen aluminium 50,000.00 216,150.00
0.0500 m' Baut piles 20,000.00 1,000.00
1.2000 m' Karet list 1,000.00 1,200.00
1.2000 m2 Kaca Susu 5 mm 120,000.00 144,000.00
1.0000 Hari Tukang besi 50,000.00 50,000.00
0.1000 Hari Kepala tukang besi 55,000.00 5,500.00
1.0000 Hari Pekerja 36,000.00 36,000.00
0.0500 Hari Mandor 60,000.00 3,000.00
456,850.00
F.2a 1 M2 DAUN JENDELA ALUMINIUM & KACA 3 mm
4.3230 m' Ram kusen aluminium 50,000.00 216,150.00
0.0500 kg Baut piles 20,000.00 1,000.00
1.2000 m' Karet list 1,000.00 1,200.00
1.2000 m2 Kaca 3 mm (bening) 65,000.00 78,000.00
1.0000 Hari Tukang besi 50,000.00 50,000.00
0.1000 Hari Kepala tukang besi 55,000.00 5,500.00
1.0000 Hari Pekerja 36,000.00 36,000.00
0.0500 Hari Mandor 60,000.00 3,000.00
390,850.00
F.2b 1 M2 DAUN PINTU ALUMINIUM & PLAT ALMUNIUM 4 mm
4.3230 m' Ram kusen aluminium 50,000.00 216,150.00
0.0500 m' Baut piles 20,000.00 1,000.00
1.2000 m' Karet list 1,000.00 1,200.00
1.2000 m2 Plat Almunium 4 mm 150,000.00 180,000.00
1.0000 Hari Tukang besi 50,000.00 50,000.00
0.1000 Hari Kepala tukang besi 55,000.00 5,500.00
1.0000 Hari Pekerja 36,000.00 36,000.00
0.0500 Hari Mandor 60,000.00 3,000.00
492,850.00
F6.5 1 M2 MENGERJAKAN DAUN PINTU PANIL MEMAKAI BINGKAI LAPIS HPL
0.0400 m³ Papan kayu kls II 3,500,000.00 140,000.00
0.5000 kg Lem Aica aibon 20,000.00 10,000.00
1.2000 m2 Lapisan HPL 250,000.00 300,000.00
0.6000 kg Lem 15,000.00 9,000.00
2.5000 Hari Tukang kayu 50,000.00 125,000.00
0.2500 Hari Kepala tukang kayu 55,000.00 13,750.00
1.0000 Hari Pekerja 36,000.00 36,000.00
0.0500 Hari Mandor 60,000.00 3,000.00
636,750.00

SNI DT-91-0014-2007 (6.4) 3 M2 MENGERJAKAN PINTU BESI HOLLOW


12.6000 m Besi Hollow 4/4 12,500.00 157,500.00
14.7000 m Besi Hollow 2/4 10,000.00 147,000.00
0.0500 kg Kawat las 75,000.00 3,750.00
1.0500 Hari Tukang besi 50,000.00 52,500.00
0.1050 Hari Kepala tukang besi 55,000.00 5,775.00
1.0500 Hari Pekerja 36,000.00 37,800.00
0.0500 Hari Mandor 60,000.00 3,000.00
407,325.00
Untuk 1 m2 Pintu Besi Hollow 135,775.00
SNI DT-91-0014-2007 (6.13a) 10m2 DINDING PARTISI RANGKA ALMUNIUM ( 1 BH)
21.0540 m' Ram kusen aluminium 50,000.00 1,052,700.00
10.5280 lbr ACP 200,000.00 2,105,600.00
0.8000 kg Baut piles 20,000.00 16,000.00
16.0000 m' Karet list 1,000.00 16,000.00
1.1844 m2 Kaca Bening 5 mm 100,000.00 118,440.00
2.5000 Hari Tukang besi 50,000.00 125,000.00
0.2500 Hari Kepala tukang besi 55,000.00 13,750.00
2.0500 Hari Pekerja 36,000.00 73,800.00
0.5000 Hari Mandor 60,000.00 30,000.00
3,551,290.00
Untuk 1 m2 355,129.00
SNI DT-91-0014-2007 (6.13b) 3.27m2 DINDING ACP RANGKA BESI ( 1 BH)
7.0000 m Calsipuring ( CR) 15,000.00 105,000.00
6.5400 m2 ACP 200,000.00 1,308,000.00
1.0000 kg Baut piles 20,000.00 20,000.00
9.3600 kg Besi Pengantung 12,500.00 117,000.00
2.5000 Hari Tukang besi 50,000.00 125,000.00
0.2500 Hari Kepala tukang besi 55,000.00 13,750.00
2.0500 Hari Pekerja 36,000.00 73,800.00
0.5000 Hari Mandor 60,000.00 30,000.00
1,792,550.00
Untuk 1 m2 548,180.43

F6.8 1 M2 MENGERJAKAN DAUN PINTU PANIL LAPIS ALUMINIUM `


0.0250 m³ Papan kayu kls II 3,500,000.00 87,500.00
1.0000 lbr Triplek lapis aluminium 90,000.00 90,000.00
0.0300 kg Paku 15,000.00 450.00
0.5000 kg Lem Aica aibon 20,000.00 10,000.00
2.0000 Hari Tukang kayu 50,000.00 100,000.00
0.2000 Hari Kepala tukang kayu 55,000.00 11,000.00
0.6000 Hari Pekerja 36,000.00 21,600.00
0.0300 Hari Mandor 60,000.00 1,800.00
322,350.00

6. PEKERJAAN ATAP & PLAFOND


PEKERJAAN RANGKA BAJA
SNI- DT-91-0014-2007(6.1) 1 KG BESI PROFIL (KUDA KUDA BAJA)
1.1500 kg Besi profil 15,000.00 17,250.00
0.0060 Hari Kepala tukang las 55,000.00 330.00
0.0600 Hari Tukang las 50,000.00 3,000.00
0.0600 Hari Pekerja terlatih 47,000.00 2,820.00
0.0030 Hari Mandor 60,000.00 180.00
1.0000 Pekerjaan Perakitan 195.50 195.50
23,775.50

SNI- DT-91-0014-2007(6.1a) 1 KG BESI PLAT


1.1500 kg Besi plat 15,000.00 17,250.00
0.0060 Hari Kepala tukang las 55,000.00 330.00
0.0600 Hari Tukang las 50,000.00 3,000.00
0.0600 Hari Pekerja terlatih 47,000.00 2,820.00
0.0030 Hari Mandor 60,000.00 180.00
1.0000 Pekerjaan Perakitan 195.50 195.50
23,775.50

SNI- DT-91-0014-2007(6.3) 100 Kg PEKERJAAN PERAKITAN


1.0000 ltr Solar 7,500.00 7,500.00
0.1000 ltr Pelumas 22,000.00 2,200.00
0.1000 Hari Pekerja 36,000.00 3,600.00
0.1000 Hari Tukang besi 50,000.00 5,000.00
0.0100 Hari Kepala tukang besi 55,000.00 550.00
0.0050 Hari Mandor 60,000.00 300.00
0.0080 Jam Sewa Alat 50,000.00 400.00
19,550.00
Untuk 1 kg 195.50

I.2a 100 Kg PABRIKASI BESI PROFIL


110.0000 kg Besi profil 15,000.00 1,650,000.00
0.0028 unit Mesin gergaji 2,000,000.00 5,600.00
0.1667 unit Mata gergaji 20,000.00 3,334.00
0.0023 unit Mesin bor 5,200,000.00 11,960.00
0.0800 unit Mata bor 50,000.00 4,000.00
15.0000 Kwh Listrik 1,000.00 15,000.00
1.5000 Hari Kepala tukang las 55,000.00 82,500.00
6.0000 Hari Tukang las 50,000.00 300,000.00
5.0000 Hari Pekerja terlatih 47,000.00 235,000.00
2,307,394.00
Untuk 1 kg besi profil = 1/100 x I.2a 23,073.94

I.2b 100 Kg PABRIKASI BESI PLAT


110.0000 kg Besi plat 15,000.00 1,650,000.00
0.0008 unit Mesin potong 1,000,000.00 800.00
0.2000 btl Acytilyin 250,000.00 50,000.00
0.4000 btl Oksigen 200,000.00 80,000.00
0.0007 unit Mesin bor 5,200,000.00 3,640.00
0.1000 unit Mata bor 50,000.00 5,000.00
13.0000 Kwh Listrik 1,000.00 13,000.00
1.5000 Hari Kepala tukang las 55,000.00 82,500.00
5.0000 Hari Tukang las 50,000.00 250,000.00
1.5000 Hari Pekerja terlatih 47,000.00 70,500.00
2,205,440.00
Untuk 1 kg besi plat = 1/100 x I.2b 22,054.40
I.2c 100 cm MENGERJAKAN LAS LISTRIK
0.3000 dos Kawat las 75,000.00 22,500.00
0.0000 unit Mesin las 7,500,000.00 0.00
3.0000 ltr Solar 7,500.00 22,500.00
0.0100 ltr Oli mesin 22,500.00 225.00
0.0100 Hari Kepala tukang las 55,000.00 550.00
0.3000 Hari Tukang las 50,000.00 15,000.00
0.3000 Hari Pekerja terlatih 47,000.00 14,100.00
74,875.00
Untuk 1 cm las listrik = 1/100xI.2c 748.75
RSNI T- 04-2006C(6.5) 1 CM MENGERJAKAN LAS LISTRIK
0.0400 kg Kawat las 75,000.00 3,000.00
0.0300 ltr Solar 7,500.00 225.00
0.0040 ltr Oli mesin 22,500.00 90.00
0.0002 Hari Kepala tukang las 55,000.00 11.00
0.0020 Hari Tukang las 50,000.00 100.00
0.0040 Hari Pekerja terlatih 47,000.00 188.00
0.0170 Jam Sewa Alat 50,000.00 850.00
4,464.00
I.2d 100 Kg PENYETELAN DAN EREKSEN
0.1000 Hari Kepala tukang las 55,000.00 5,500.00
1.0000 Hari Tukang las 50,000.00 50,000.00
2.5000 Hari Pekerja terlatih 47,000.00 117,500.00
1.0000 Hari Alat bantu 25,000.00 25,000.00
198,000.00
Untuk 1 kg ereksen = 1/100 x I.2d 1,980.00
I.2e 10 M2 MENY BESI
1.5000 kg Anti karat 50,000.00 75,000.00
0.8000 kg Minyak Cat 10,000.00 8,000.00
0.7500 Hari Tukang cat 50,000.00 37,500.00
0.5000 Hari Kepala tukang cat 55,000.00 27,500.00
0.2500 Hari Mandor 60,000.00 15,000.00
163,000.00
Untuk 1 m2 anti karat = 1/10 x I.2e 16,300.00

H.15 10 M2 MENGERJAKAN TALANG 0,6 M


3.5000 lbr Seng plat BJLS 30 65,000.00 227,500.00
0.1000 m³ Papan kayu kls II 3,500,000.00 350,000.00
1.0000 kg Paku 15,000.00 15,000.00
6.0000 Hari Tukang besi 50,000.00 300,000.00
0.6000 Hari Kepala tukang besi 55,000.00 33,000.00
3.5000 Hari Pekerja 36,000.00 126,000.00
0.1750 Hari Mandor 60,000.00 10,500.00
1,062,000.00
106,200.00
H.5 1 M2 MENGERJAKAN KAP BAJA RINGAN
1.0500 M2 Bahan Baja Ringan 125,000.00 131,250.00
0.0750 % Mobilisasi Baja Ringan 125,000.00 9,375.00
0.0250 % Pajak Penghasilan 125,000.00 3,125.00
0.0250 % Jaminan Pemasangan 125,000.00 3,125.00
0.2500 % Ongkos Kerja ( Pemasangan ) 125,000.00 31,250.00
178,125.00
SNI-DT-91-0011-2007( 6.20) 1 M2 RANGKA LANGIT LANGIT (60X60),KAYU KLAS II
0.0163 m³ Kayu kls II 3,500,000.00 57,050.00
0.2500 kg Paku 15,000.00 3,750.00
0.3000 Hari Tukang kayu 50,000.00 15,000.00
0.0300 Hari Kepala tukang kayu 55,000.00 1,650.00
0.2000 Hari Pekerja 36,000.00 7,200.00
0.0100 Hari Mandor 60,000.00 600.00
85,250.00
SNI-DT-91-0011-2007( 6.7) 1 M2 MENGERJAKAN PLAFON GYPSUM BORD 1 CM
0.1000 kg Paku 15,000.00 1,500.00
0.3640 lbr Gypsum 9 mm 32,500.00 11,830.00
0.7500 Hari Tukang kayu 50,000.00 37,500.00
0.0750 Hari Kepala tukang kayu 55,000.00 4,125.00
0.2500 Hari Pekerja 36,000.00 9,000.00
0.0125 Hari Mandor 60,000.00 750.00
64,705.00
SNI-DT-91-0011-2007( 6.7a) 1 M2 MENGERJAKAN PLAFON GYPSUM BORD 12 CM
0.1000 kg Paku 15,000.00 1,500.00
0.3640 lbr Gypsum 12 mm 40,000.00 14,560.00
0.7500 Hari Tukang kayu 50,000.00 37,500.00
0.0750 Hari Kepala tukang kayu 55,000.00 4,125.00
0.2500 Hari Pekerja 36,000.00 9,000.00
0.0125 Hari Mandor 60,000.00 750.00
67,435.00
I.6.9 1M¹ PASANG LIST PROFIL PLAFOND GYPSUM
1.0500 m List plafond gypsum C7 12,500.00 13,125.00
0.2000 kg Paku 15,000.00 3,000.00
0.0500 Hari Tukang kayu 50,000.00 2,500.00
0.0050 Hari Kepala tukang kayu 55,000.00 275.00
0.0500 Hari Pekerja 36,000.00 1,800.00
0.0030 Hari Mandor 60,000.00 180.00
20,880.00
I.6.9a 1M¹ PASANG LIST PROFIL PLAFOND GRC
1.0500 m List plafond GRC 15,000.00 15,750.00
0.2000 kg Paku 15,000.00 3,000.00
0.0500 Hari Tukang kayu 50,000.00 2,500.00
0.0050 Hari Kepala tukang kayu 55,000.00 275.00
0.0500 Hari Pekerja 36,000.00 1,800.00
0.0030 Hari Mandor 60,000.00 180.00
23,505.00
I.6.10 1 m² Pasang plafond kalsiboard rangka metal furing
Bahan
2.500 m¹ Metal furing 0.4 x 4 m ASTM - C 645 10,000.00 25,000.00
0.830 m¹ C Channel 0.8 x 4 m ASTM - C 645 60,000.00 49,800.00
0.690 bh Theaded rod 4 mm x 1000 mm 4,000.00 2,760.00
0.690 bh Suspension bracket 2,500.00 1,725.00
0.690 bh Soffit clear 2,500.00 1,725.00
2.080 bh Saddle clip 2,000.00 4,160.00
0.810 bh Paku peluru 2,000.00 1,620.00
0.070 kg Paku 15,000.00 1,050.00
0.400 bh Angle section 3M 5,000.00 2,000.00
1.000 m2 Kalsiboard 35,000.00 35,000.00
16.670 bh Screws 100.00 1,667.00
0.600 bh Joint compound ASTM - E 136 5,000.00 3,000.00
0.830 bh Joint Tape 75 m 15,000.00 12,450.00
0.061 bh Sand paper 2,000.00 122.00
1.000 set Alat bantu (perancah) 5,000.00 5,000.00
Jumlah (I) 147,079.00
Tenaga
1.000 Ongkos kerja dan peralatan 15% dari 147,079.00 22,061.85
Jumlah Total Jumlah Total 169,140.85

I.6.11 1 m² Pasang plafond Gypsum 9 mm rangka metal furing


Bahan
2.500 m¹ Metal furing 0.4 x 4 m ASTM - C 645 10,000.00 25,000.00
0.830 m¹ C Channel 0.8 x 4 m ASTM - C 645 60,000.00 49,800.00
0.690 bh Theaded rod 4 mm x 1000 mm 4,000.00 2,760.00
0.690 bh Suspension bracket 2,500.00 1,725.00
0.690 bh Soffit clear 2,500.00 1,725.00
2.080 bh Saddle clip 2,000.00 4,160.00
0.810 bh Paku peluru 2,000.00 1,620.00
0.070 kg Paku 15,000.00 1,050.00
0.400 bh Angle section 3M 5,000.00 2,000.00
1.000 m2 Gypsum 9 mm 32,500.00 32,500.00
16.670 bh Screws 100.00 1,667.00
0.600 bh Joint compound ASTM - E 136 5,000.00 3,000.00
0.830 bh Joint Tape 75 m 15,000.00 12,450.00
0.061 bh Sand paper 2,000.00 122.00
1.000 set Alat bantu (perancah) 5,000.00 5,000.00
Jumlah (I) 144,579.00
Tenaga
1.000 Ongkos kerja dan peralatan 15% dari 144,579.00 21,686.85
Jumlah Total Jumlah Total 166,265.85
I.6.12 1 m² Pasang plafond Gypsum 12 mm rangka metal furing
Bahan
2.500 m¹ Metal furing 0.4 x 4 m ASTM - C 645 10,000.00 25,000.00
0.830 m¹ C Channel 0.8 x 4 m ASTM - C 645 60,000.00 49,800.00
0.690 bh Theaded rod 4 mm x 1000 mm 4,000.00 2,760.00
0.690 bh Suspension bracket 2,500.00 1,725.00
0.690 bh Soffit clear 2,500.00 1,725.00
2.080 bh Saddle clip 2,000.00 4,160.00
0.810 bh Paku peluru 2,000.00 1,620.00
0.070 kg Paku 15,000.00 1,050.00
0.400 bh Angle section 3M 5,000.00 2,000.00
1.000 m2 Gypsum 12 mm 40,000.00 40,000.00
16.670 bh Screws 100.00 1,667.00
0.600 bh Joint compound ASTM - E 136 5,000.00 3,000.00
0.830 bh Joint Tape 75 m 15,000.00 12,450.00
0.061 bh Sand paper 2,000.00 122.00
1.000 set Alat bantu (perancah) 5,000.00 5,000.00
Jumlah (I) 152,079.00
Tenaga
1.000 Ongkos kerja dan peralatan 15% dari 152,079.00 #VALUE!
Jumlah Total Jumlah Total 152,079.00

H.2e 1 M2 PEKERJAAN ATAP GENTENG METAL


3.2400 lbr Genteng Metal 35,000.00 113,400.00
7.0000 bh Paku ulir 100.00 700.00
0.1500 Hari Tukang kayu 50,000.00 7,500.00
0.0150 Hari Kepala tukang kayu 55,000.00 825.00
0.2000 Hari Pekerja 36,000.00 7,200.00
0.0100 Hari Mandor 60,000.00 600.00
130,225.00
H.4e 1 M2 PEKERJAAN BUBUNGAN GENTENG METAL
1.1000 lbr Bubungan Metal 25,000.00 27,500.00
0.1020 zak Semen/zak 62,000.00 6,324.00
0.0400 m³ Pasir pasang 60,000.00 2,400.00
0.2000 Hari Tukang batu 50,000.00 10,000.00
0.0200 Hari Kepala tukang batu 55,000.00 1,100.00
0.4000 Hari Pekerja 36,000.00 14,400.00
0.0200 Hari Mandor 60,000.00 1,200.00
62,924.00
H.2b 1 M2 PEKERJAAN ATAP GENTENG KERAMIK
13.8000 bh Genteng Keramik 9,500.00 131,100.00
7.0000 bh Paku ulir 100.00 700.00
0.1500 Hari Tukang kayu 50,000.00 7,500.00
0.0150 Hari Kepala tukang kayu 55,000.00 825.00
0.2000 Hari Pekerja 36,000.00 7,200.00
0.0100 Hari Mandor 60,000.00 600.00
147,925.00
H.4b 1 M2 PEKERJAAN BUBUNGAN GENTENG KERAMIK
3.9000 bh Bubungan Genteng Keramik 20,000.00 78,000.00
0.1020 zak Semen/zak 62,000.00 6,324.00
0.0400 m³ Pasir pasang 60,000.00 2,400.00
0.2000 Hari Tukang batu 50,000.00 10,000.00
0.0200 Hari Kepala tukang batu 55,000.00 1,100.00
0.4000 Hari Pekerja 36,000.00 14,400.00
0.0200 Hari Mandor 60,000.00 1,200.00
113,424.00
7. MENGERJAKAN PENGECATAN
M6.11 1 M2 PEK. CAT TEMBOK BARU(MUTU MENENGAH )
0.1000 kg Cat tembok 10,000.00 1,000.00
0.2600 kg Cat tembok 10,000.00 2,600.00
0.1000 kg Plamir tembok 6,000.00 600.00
0.0050 bh Roll cat 15,000.00 75.00
0.2000 lbr Amplas 2,000.00 400.00
0.0630 Hari Tukang cat 50,000.00 3,150.00
0.0063 Hari Kepala tukang cat 55,000.00 346.50
0.0200 Hari Pekerja 36,000.00 720.00
0.0025 Hari Mandor 60,000.00 150.00
9,041.50
M6.11a 1 M2 PEK. CAT TEMBOK BARU(MUTU TINGGI )
0.1000 kg Cat tembok Mutu Tinggi 25,000.00 2,500.00
0.2600 kg Cat tembok Mutu Tinggi 25,000.00 6,500.00
0.1000 kg Plamir tembok 6,000.00 600.00
0.0050 bh Roll cat 15,000.00 75.00
0.2000 lbr Amplas 2,000.00 400.00
0.0630 Hari Tukang cat 50,000.00 3,150.00
0.0063 Hari Kepala tukang cat 55,000.00 346.50
0.0200 Hari Pekerja 36,000.00 720.00
0.0025 Hari Mandor 60,000.00 150.00
14,441.50
M6.11b 1 M2 PEK. CAT TEMBOK EPOXY
0.1000 kg Cat tembok Epoxy 25,000.00 2,500.00
0.2600 kg Cat tembok Epoxy 25,000.00 6,500.00
0.0050 bh Roll cat 15,000.00 75.00
0.2000 lbr Amplas 2,000.00 400.00
0.0630 Hari Tukang cat 50,000.00 3,150.00
0.0063 Hari Kepala tukang cat 55,000.00 346.50
0.0200 Hari Pekerja 36,000.00 720.00
0.0025 Hari Mandor 60,000.00 150.00
13,841.50
M6.8 1 M2 CAT KAYU
0.0800 kg Meny kayu 10,000.00 800.00
0.2000 kg Plamir kayu 10,000.00 2,000.00
0.1700 kg Cat kayu 35,000.00 5,950.00
0.1500 kg Minyak Cat 10,000.00 1,500.00
0.2600 kg Minyak Cat 10,000.00 2,600.00
0.0050 kg Kuas cat 2,000.00 10.00
0.2000 lbr Amplas 2,000.00 400.00
0.0090 Hari Tukang cat 50,000.00 450.00
0.0060 Hari Kepala tukang cat 55,000.00 330.00
0.0700 Hari Pekerja 36,000.00 2,520.00
0.0025 Hari Mandor 60,000.00 150.00
16,710.00

M6.9 1 M² PEKERJAAN POLITUR


0.1500 kg Politur 25,000.00 3,750.00
0.3720 kg Politur 25,000.00 9,300.00
2.0000 lbr Amplas 2,000.00 4,000.00
0.0600 Hari Tukang cat 50,000.00 3,000.00
0.0160 Hari Kepala tukang cat 55,000.00 880.00
Hari Pekerja 36,000.00 0.00
0.0025 Hari Mandor 60,000.00 150.00
21,080.00
M6.14 1 M2 PEK. CAT GENTENG
0.3000 kg Cat genteng 30,000.00 9,000.00
0.0100 kg Kuas cat 2,000.00 20.00
0.0630 Hari Tukang cat 50,000.00 3,150.00
0.0063 Hari Kepala tukang cat 55,000.00 346.50
0.0200 Hari Pekerja 36,000.00 720.00
0.0025 Hari Mandor 60,000.00 150.00
13,386.50

M6.12 1M2 PEKERJAAN MENGETEER DENGAN TEER ARANG


0.3500 kg Teer arang 2,000.00 700.00
0.1000 Hari Pekerja 36,000.00 3,600.00
0.0060 Hari Mandor 60,000.00 360.00
4,660.00
8. PEKERJAAN BETON
A 1 M3 MENYIRAM BETON & MEMBONGKAR BEGESTING
4.0000 Hari Pekerja 36,000.00 144,000.00
144,000.00
SNI DT-91-0008-2007(6.17) 10 KG BESI ULIR
10.5000 kg Besi beton Ulir 8,000.00 84,000.00
0.1500 kg Kawat beton 9,000.00 1,350.00
0.0700 Hari Tukang besi 50,000.00 3,500.00
0.0070 Hari Kepala tukang besi 55,000.00 385.00
0.0700 Hari Pekerja 36,000.00 2,520.00
0.0040 Hari Mandor 60,000.00 240.00
91,995.00
harga per KG. = 1/10 9,199.50
SNI DT-91-0008-2007(6.17a) 10 KG BESI POLOS
10.5000 kg Besi beton Polos 8,000.00 84,000.00
0.1500 kg Kawat beton 9,000.00 1,350.00
0.0700 Hari Tukang besi 50,000.00 3,500.00
0.0070 Hari Kepala tukang besi 55,000.00 385.00
0.0700 Hari Pekerja 36,000.00 2,520.00
0.0040 Hari Mandor 60,000.00 240.00
91,995.00
harga per KG. = 1/10 9,199.50

SNI DT-91-0008-2007(6.20) 1m2 BEGISTING UNTUK PONDASI


0.0400 m³ Kayu kls III 2,000,000.00 80,000.00
0.1000 ltr Minyak begisting 2,000.00 200.00
0.3000 kg Paku 15,000.00 4,500.00
0.2600 Hari Tukang kayu 50,000.00 13,000.00
0.0260 Hari Kepala tukang kayu 55,000.00 1,430.00
0.5200 Hari Pekerja 36,000.00 18,720.00
0.0260 Hari Mandor 60,000.00 1,560.00
Jumlah ( Harga Sekali pakai ) 119,410.00
Harga ( Untuk dua kali pakai ) 1/2 x harga 59,705.00
SNI DT-91-0008-2007(6.21) 1 m2 BEGISTING UNTUK SLOOF
0.0450 m³ Kayu kls III 2,000,000.00 90,000.00
0.1000 ltr Minyak begisting 2,000.00 200.00
0.3000 kg Paku 15,000.00 4,500.00
0.2600 Hari Tukang kayu 50,000.00 13,000.00
0.0260 Hari Kepala tukang kayu 55,000.00 1,430.00
0.5200 Hari Pekerja 36,000.00 18,720.00
0.0260 Hari Mandor 60,000.00 1,560.00
Jumlah ( Harga Sekali pakai ) 129,410.00
Harga ( Untuk dua kali pakai ) 1/2 x harga 64,705.00

SNI DT-91-0008-2007(6.22) 1 m2 BEGISTING UNTUK KOLOM


0.0400 m³ Kayu kls III 2,000,000.00 80,000.00
0.2000 ltr Minyak begisting 2,000.00 400.00
0.4000 kg Paku 15,000.00 6,000.00
0.0150 m³ Kayu kls II 3,500,000.00 52,500.00
0.3500 lbr Triplek 9 mm 90,000.00 31,500.00
2.0000 btg Dolken(bambu) 5,000.00 10,000.00
0.3300 Hari Tukang kayu 50,000.00 16,500.00
0.0330 Hari Kepala tukang kayu 55,000.00 1,815.00
0.6600 Hari Pekerja 36,000.00 23,760.00
0.0330 Hari Mandor 60,000.00 1,980.00
Jumlah ( Harga Sekali pakai ) 224,455.00
Harga ( Untuk dua kali pakai ) 1/2 x harga 112,227.50

SNI DT-91-0008-2007(6.23) 1 m2 BEGISTING UNTUK BALOK


0.0400 m³ Kayu kls III 2,000,000.00 80,000.00
0.2000 ltr Minyak begisting 2,000.00 400.00
0.4000 kg Paku 15,000.00 6,000.00
0.0180 m³ Kayu kls II 3,500,000.00 63,000.00
0.3500 lbr Triplek 9 mm 90,000.00 31,500.00
2.0000 btg Dolken(bambu) 5,000.00 10,000.00
0.3300 Hari Tukang kayu 50,000.00 16,500.00
0.0330 Hari Kepala tukang kayu 55,000.00 1,815.00
0.6600 Hari Pekerja 36,000.00 23,760.00
0.0330 Hari Mandor 60,000.00 1,980.00
Jumlah ( Harga Sekali pakai ) 234,955.00
Harga ( Untuk dua kali pakai ) 1/2 x harga 117,477.50

SNI DT-91-0008-2007(6.4) 1 M3 BETON mutu f' = 7.4 MPa(K100) ,slump (12+2) cm,w/c 0.87
247.0000 kg Semen/kg 1,240.00 306,280.00
0.6952 m3 Krikil pecah 2/3 125,000.00 86,896.55
0.5400 m3 Pasir Beton 75,000.00 40,500.00
200.0000 ltr Air 10.00 2,000.00
0.2750 Hari Tukang batu 50,000.00 13,750.00
0.0280 Hari Kepala tukang batu 55,000.00 1,540.00
1.6500 Hari Pekerja 36,000.00 59,400.00
0.0830 Hari Mandor 60,000.00 4,980.00
515,346.55

SNI DT-91-0008-2007(6.7) 1 M3 BETON mutu f' = 19.3 Mpa (K225) ,slump (12+2) cm,w/c 0.58
371.000 kg Semen/kg 1,240.00 460,040.00
0.720 m3 Krikil pecah 2/3 125,000.00 90,000.00
0.440 m3 Pasir Beton 75,000.00 33,000.00
215.000 ltr Air 10.00 2,150.00
0.275 Hari Tukang batu 50,000.00 13,750.00
0.028 Hari Kepala tukang batu 55,000.00 1,512.50
1.650 Hari Pekerja 36,000.00 59,400.00
0.083 Hari Mandor 60,000.00 4,980.00
664,832.50
SNI DT-91-0008-2007(6.7a) 1 m3 PONDASI FOOT PLAT BETON BERTULANG (2.50 x 2.50 m)
1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
1.2759 m2 BEGISTING PONDASI /SNI DT-91-0008-2007(6.20) 59,705.00 76,178.63
134.5531 kg Besi Beton Ulir (SNI DT- 91-0008- 2007(6.17) 9,199.50 1,237,821.34
61.7033 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 567,639.96
, 2,546,472.43

SNI DT-91-0008-2007(6.7a1) 1 m3 PONDASI FOOT PLAT BETON BERTULANG (2,00 x 2,00 m)


1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
1.5911 m2 BEGISTING PONDASI /SNI DT-91-0008-2007(6.20) 59,705.00 94,993.66
93.3867 kg Besi Beton Ulir (SNI DT- 91-0008- 2007(6.17) 9,199.50 859,110.94
44.1848 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 406,478.01
, 2,025,415.12
SNI DT-91-0008-2007(6.7a2) 1 m3 PONDASI FOOT PLAT BETON BERTULANG (1,50 x 1,50 m)
1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
1.6408 m2 BEGISTING PONDASI /SNI DT-91-0008-2007(6.20) 59,705.00 97,963.08
85.6865 kg Besi Beton Ulir (SNI DT- 91-0008- 2007(6.17) 9,199.50 788,272.89
41.4181 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 381,025.88
, 1,932,094.35

SNI DT-91-0008-2007(6.7b) 1 m3 SLOOF BETON BERTULANG (20/30 CM)


1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
10.0000 m2 BEGISTING PONDASI /SNI DT-91-0008-2007(6.20) 59,705.00 597,050.00
141.8182 kg Besi Beton Ulir (SNI DT- 91-0008- 2007(6.17) 9,199.50 1,304,656.36
42.1071 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 387,364.66
, 2,953,903.52
SNI DT-91-0008-2007(6.7g) 1 m3 BETON KOLOM 25/45 CM
1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
14.0000 m2 BEGISTING KOLOM (SNI DT-91-0008-2007/6.22) 112,227.50 1,571,185.00
308.6504 kg Besi Beton Ulir (SNI DT- 91-0008- 2007(6.17) 9,199.50 2,839,429.30
65.7493 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 604,860.61
, 5,680,307.40

SNI DT-91-0008-2007(6.7h) 1 m3 BETON KOLOM 40/40 CM


1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
10.0000 m2 BEGISTING KOLOM (SNI DT-91-0008-2007/6.22) 112,227.50 1,122,275.00
271.0630 kg Besi Beton Ulir (SNI DT- 91-0008- 2007(6.17) 9,199.50 2,493,644.00
47.4154 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 436,197.55
, 4,716,949.05
SNI DT-91-0008-2007(6.7h1) 1 m3 BETON KOLOM 25/25 CM
1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
16.0000 m2 BEGISTING KOLOM (SNI DT-91-0008-2007/6.22) 112,227.50 1,795,640.00
224.8365 kg Besi Beton Ulir (SNI DT- 91-0008- 2007(6.17) 9,199.50 2,068,383.71
83.7904 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 770,829.90
, 5,299,686.11

SNI DT-91-0008-2007(6.7i) 1 m3 BETON KOLOM PRAKTIS 10/10 CM (T =4.5 m)


1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
24.0000 m2 BEGISTING KOLOM (SNI DT-91-0008-2007/6.22) 112,227.50 2,693,460.00
306.3111 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 2,817,909.07
, 6,176,201.57
SNI DT-91-0008-2007(6.7j) 1 m3 BETON KOLOM PRAKTIS 10/10 CM (T = 3.57 m)
1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
24.0000 m2 BEGISTING KOLOM (SNI DT-91-0008-2007/6.22) 112,227.50 2,693,460.00
307.0000 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 2,824,246.50
, 6,182,539.00

SNI DT-91-0008-2007(6.7L) 1 m3 BETON PLAT LANTAI t= 12 CM


1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
8.3333 m2 BEGISTING UNTUK BALOK (SNI DT-91-0008-2007/6.23) 117,477.50 978,979.17
110.0000 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 1,011,945.00
8.3333 m2 Perancah 50,000.00 416,666.67
, 3,072,423.33
SNI DT-91-0008-2007(6.7La) 1 m3 BETON PLAT DAK ATAP t= 10 CM
1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
10.0000 m2 BEGISTING UNTUK BALOK (SNI DT-91-0008-2007/6.23) 117,477.50 1,174,775.00
98.0000 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 901,551.00
10.0000 m2 Perancah 50,000.00 500,000.00
, 3,241,158.50

SNI DT-91-0008-2007(6.7n) 1 m3 BETON RING BALOK 15/20 CM


1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
13.3333 m2 BEGISTING UNTUK BALOK (SNI DT-91-0008-2007/6.23) 117,477.50 1,566,366.67
213.2143 kg Besi Beton Ulir (SNI DT- 91-0008- 2007(6.17) 9,199.50 1,961,464.82
69.8667 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 642,738.40
, 4,835,402.39
SNI DT-91-0008-2007(6.7o) 1 m3 BETON RING BALOK 13/20 CM
1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
20.0000 m2 BEGISTING UNTUK BALOK (SNI DT-91-0008-2007/6.23) 117,477.50 2,349,550.00
280.5333 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 2,580,766.40
, 5,595,148.90
SNI DT-91-0008-2007(6.7n1) 1 m3 BETON BALOK LANTAI 25/65 CM
1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
8.0667 m2 BEGISTING UNTUK BALOK (SNI DT-91-0008-2007/6.23) 117,477.50 947,651.83
179.4656 kg Besi Beton Ulir (SNI DT- 91-0008- 2007(6.17) 9,199.50 1,650,994.24
53.9163 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 496,003.33
, 3,759,481.90

SNI DT-91-0008-2007(6.7n2) 1 m3 BETON BALOK LANTAI 25/50 CM


1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
8.1143 m2 BEGISTING UNTUK BALOK (SNI DT-91-0008-2007/6.23) 117,477.50 953,246.00
115.2000 kg Besi Beton Ulir (SNI DT- 91-0008- 2007(6.17) 9,199.50 1,059,782.40
64.7525 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 595,690.88
, 3,273,551.78
SNI DT-91-0008-2007(6.7n3) 1 m3 BETON BALOK LANTAI 25/40 CM
1.0000 m³ BETON f'=19.3 Mpa ( K225) SNI DT-91-0008-2007(6.7) 664,832.50 664,832.50
8.1333 m2 BEGISTING UNTUK BALOK (SNI DT-91-0008-2007/6.23) 117,477.50 955,483.67
149.0149 kg Besi Beton Ulir (SNI DT- 91-0008- 2007(6.17) 9,199.50 1,370,862.81
41.9200 kg Besi Beton Polos (SNI DT- 91-0008- 2007(6.17a) 9,199.50 385,643.04
, 3,376,822.01
Sp.GA 1 UNIT SEPTICTANK
7.1280 m3 Galian tanah 28,500.00 203,148.00
0.4260 m3 Pasir urug 40,000.00 17,040.00
6.9600 m2 Pasangan trasram 1pc : 3ps 72,468.80 504,382.85
19.2010 m2 Plesteran trasram plat beton penutup septictank 27,147.24 521,254.16
0.4260 m3 Plat beton penutup septictank 3,241,158.50 1,380,733.52
1.0000 bh Pipa pembuang hawa dia. 1,5" 10,000.00 10,000.00
2.0000 bh Lubang kontrol 50,000.00 100,000.00
2,736,558.52
Sp.A 1 UNIT PEKERJAAN PERESAPAN
4.991 m3 Galian tanah 28,500.00 142,243.50
10.676 m2 Lapisan ijuk 25,000.00 266,900.00
1.340 m3 Sirtu 60,000.00 80,400.00
1.000 m2 Pasangan bata kosong 75,000.00 75,000.00
6.236 m3 Pasangan batu kosong 153,345.00 956,259.42
0.678 m3 Pasangan trasram 1pc : 3ps 72,468.80 49,133.85
0.159 m3 Plat beton penutup peresapan 3,241,158.50 515,344.20
2,085,280.97
Analisa LST1 Panel Utama

3.000 unit Pilot Lamp + Fuse 10,000.00 30,000.00


3.000 bh CT 300/5A 50,000.00 150,000.00
3.000 bh Ampermeter 50,000.00 150,000.00
1.000 bh Volt meter 75,000.00 75,000.00
1.000 bh Slector Switch 50,000.00 50,000.00
1.000 bh MCCB 3 ph 140 - 200 A 45KA 3,000,000.00 3,000,000.00
1.000 bh MCCB 3 ph 100 A 18KA 2,500,000.00 2,500,000.00
1.000 bh MCCB 3 ph 80 A 18KA 2,000,000.00 2,000,000.00
1.000 bh MCCB 3 ph 50 A 18KA 1,500,000.00 1,500,000.00
1.000 set Busbar RSTN - GND 250,000.00 250,000.00
1.000 unit Grounding Panel BC 50 mm 2 1,500,000.00 1,500,000.00
1.000 unit Box Panel 120x 80 x 40 1,000,000.00 1,000,000.00
1.000 lot Kabel + Skun kabel + Asesoris 1,000,000.00 1,000,000.00
1.000 lot Jasa 750,000.00 750,000.00
13,955,000.00

Analisa LST2 Panel Penerangan & Daya

3.000 unit Pilot Lamp + Fuse 10,000.00 30,000.00


1.000 bh MCCB 3 ph 40A 18KA 1,000,000.00 1,000,000.00
1.000 bh MCCB 1 ph 16 A 4.5KA 75,000.00 75,000.00
1.000 bh MCCB 1 ph 10 A 4.5KA 75,000.00 75,000.00
1.000 set Busbar RSTN - GND 250,000.00 250,000.00
1.000 unit Grounding Panel BC 16 mm 2 750,000.00 750,000.00
1.000 unit Box Panel 60x 40 x 20 1,200,000.00 1,200,000.00
1.000 lot Kabel + Skun kabel + Asesoris 200,000.00 200,000.00
1.000 lot Jasa 500,000.00 500,000.00
4,080,000.00

Analisa LST3 Panel AC

3.000 unit Pilot Lamp + Fuse 10,000.00 30,000.00


1.000 bh MCCB 3 ph 80 -100 A 45KA 1,500,000.00 1,500,000.00
2.000 bh MCCB 1 ph 60 A18 KA 750,000.00 1,500,000.00
6.000 bh MCCB 1 ph 16 A 4.5KA 75,000.00 450,000.00
1.000 set Busbar RSTN - GND 150,000.00 150,000.00
1.000 unit Grounding Panel BC 16 mm 2 800,000.00 800,000.00
1.000 unit Box Panel 60x 40 x 20 1,000,000.00 1,000,000.00
1.000 lot Kabel + Skun kabel + Asesoris 250,000.00 250,000.00
1.000 lot Jasa 500,000.00 500,000.00
6,180,000.00

Analisa LST4 Panel UPS

3.000 unit Pilot Lamp + Fuse 10,000.00 30,000.00


1.000 bh MCCB 3 ph 63A 18KA 750,000.00 750,000.00
5.000 bh MCCB 1 ph 20 A 4.5KA 95,000.00 475,000.00
1.000 set Busbar RSTN - GND 150,000.00 150,000.00
1.000 unit Grounding Panel BC 16 mm 2 800,000.00 800,000.00
1.000 unit Box Panel 60x 40 x 20 750,000.00 750,000.00
1.000 lot Kabel + Skun kabel + Asesoris 250,000.00 250,000.00
1.000 lot Jasa 250,000.00 250,000.00
3,455,000.00
Analisa LST.5 INSTALASI PENERANGAN RUANG DAN INSTALASI STOP KONTAK
22.0000 m¹ NYY, 2,5 mm² 3,500.00 77,000.00
2.5000 m¹ Pipa PVC 20 mm 17,500.00 43,750.00
1.0000 lot Klem PVC, Tdoos, lasdop, sock PVC, isolasi 15,000.00 15,000.00
0.5000 Hari Tukang Listrik 50,000.00 25,000.00
0.3000 Hari Pekerja 36,000.00 10,800.00
171,550.00
K.6.1 1 Bh PEKERJAAN MEMASANG KUNCI TANAM
1.0000 bh Kunci tanam 200,000.00 200,000.00
0.5000 hari Tukang kayu 50,000.00 25,000.00
0.0500 hari Kepala tukang kayu 55,000.00 2,750.00
0.1000 hari Pekerja 36,000.00 3,600.00
0.0050 hari Mandor 60,000.00 300.00
231,650.00
K.6.8 1 Bh PEKERJAAN MEMASANG EXPAGNOLET
1.0000 bh Grendel Tanam 25,000.00 25,000.00
0.1500 Hari Tukang kayu 50,000.00 7,500.00
0.0150 Hari Kepala tukang kayu 55,000.00 825.00
0.0150 Hari Pekerja 36,000.00 540.00
0.0010 Hari Mandor 60,000.00 60.00
33,925.00

K.6.4 1 Bh PEKERJAAN MEMASANG ENGSEL JENDELA


1.0000 bh Engsel jendela 7,000.00 7,000.00
0.1000 Hari Tukang kayu 50,000.00 5,000.00
0.0100 Hari Kepala tukang kayu 55,000.00 550.00
0.0100 Hari Pekerja 36,000.00 360.00
0.0010 Hari Mandor 60,000.00 60.00
12,970.00
K.6.5 1 Bh PEKERJAAN MEMASANG HAK ANGIN
1.0000 bh Hak angin 7,500.00 7,500.00
0.1500 Hari Tukang kayu 50,000.00 7,500.00
0.0150 Hari Kepala tukang kayu 55,000.00 825.00
0.0150 Hari Pekerja 36,000.00 540.00
0.0010 Hari Mandor 60,000.00 60.00
16,425.00
K.6.6 1 Bh PEKERJAAN MEMASANG GRENDEL JENDELA
1.0000 bh Grendel jendela 5,000.00 5,000.00
0.1000 Hari Tukang kayu 50,000.00 5,000.00
0.0100 Hari Kepala tukang kayu 55,000.00 550.00
0.0100 Hari Pekerja 36,000.00 360.00
0.0010 Hari Mandor 60,000.00 60.00
10,970.00
K.6.3 1 Bh PEKERJAAN MEMASANG GRENDEL PINTU
1.0000 bh Grendel pintu 10,000.00 10,000.00
0.1500 Hari Tukang kayu 50,000.00 7,500.00
0.0150 Hari Kepala tukang kayu 55,000.00 825.00
0.0150 Hari Pekerja 36,000.00 540.00
0.0010 Hari Mandor 60,000.00 60.00
18,925.00
K.6.2 1 M PEKERJAAN MEMASANG REL PINTU
1.0000 m Rel Pintu 40,000.00 40,000.00
0.1500 Hari Tukang kayu 50,000.00 7,500.00
0.0150 Hari Kepala tukang kayu 55,000.00 825.00
0.0150 Hari Pekerja 36,000.00 540.00
0.0010 Hari Mandor 60,000.00 60.00
48,925.00

K.6.1a 1 Bh PEKERJAAN MEMASANG KUNCI/GEMBOK


1.0000 bh Gembok 20,000.00 20,000.00
0.2500 hari Tukang kayu 50,000.00 12,500.00
0.0250 hari Kepala tukang kayu 55,000.00 1,375.00
0.0200 hari Pekerja 36,000.00 720.00
0.0010 hari Mandor 60,000.00 60.00
34,655.00
J.6.1 1 M¹ PEKERJAAN MEMASANG PIPA PVC Ø 1/2''
1.2000 m' Pipa PVC ø 1/2" (Medium B) 10,000.00 12,000.00
35% Hk Perlengkapan 10,000.00 3,500.00
0.0600 Hari Tukang Pipa 50,000.00 3,000.00
0.0060 Hari Kepala tukang Pipa 55,000.00 330.00
0.0360 Hari Pekerja 36,000.00 1,296.00
0.0020 Hari Mandor 60,000.00 120.00
20,246.00
J.6.2 1 M¹ PEKERJAAN MEMASANG PIPA PVC Ø 2.5''
1.2000 m' Pipa PVC ø 2,5" (Medium A) 35,000.00 42,000.00
35% Hk Perlengkapan 35,000.00 12,250.00
0.0600 Hari Tukang Pipa 50,000.00 3,000.00
0.0060 Hari Kepala tukang Pipa 55,000.00 330.00
0.0360 Hari Pekerja 36,000.00 1,296.00
0.0020 Hari Mandor 60,000.00 120.00
58,996.00
J.6.3 1 M¹ PEKERJAAN MEMASANG PIPA PVC Ø 4''
1.2000 m' Pipa PVC ø 4" (Medium A) 45,000.00 54,000.00
35% Hk Perlengkapan 45,000.00 15,750.00
0.0600 Hari Tukang Pipa 50,000.00 3,000.00
0.0060 Hari Kepala tukang Pipa 55,000.00 330.00
0.0360 Hari Pekerja 36,000.00 1,296.00
0.0020 Hari Mandor 60,000.00 120.00
74,496.00
J.6.11 1 unit PEKERJAAN MEMASANG KLOSET DUDUK
1.0000 bh Kloset Duduk 1,250,000.00 1,250,000.00
35% Hk Perlengkapan 1,250,000.00 437,500.00
1.1000 Hari Tukang Pipa 50,000.00 55,000.00
0.1100 Hari Kepala tukang Pipa 55,000.00 6,050.00
3.3000 Hari Pekerja 36,000.00 118,800.00
0.1600 Hari Mandor 60,000.00 9,600.00
1,876,950.00
J.6.12 1 unit PEKERJAAN MEMASANG WASTAFEL
1.0000 bh Wastafel 1,250,000.00 1,250,000.00
12% Hk Perlengkapan 1,250,000.00 150,000.00
6.0000 kg Semen/kg 1,240.00 7,440.00
0.0100 M3 Pasir pasang 60,000.00 600.00
1.4500 Hari Tukang batu 50,000.00 72,500.00
0.1500 Hari Kepala tukang batu 55,000.00 8,250.00
1.2000 Hari Pekerja 36,000.00 43,200.00
0.1000 Hari Mandor 60,000.00 6,000.00
1,537,990.00
J.6.13 1 bh PEKERJAAN MEMASANG KRAN AIR 1/2"
1.0000 bh Kran air ø 1/2" 25,000.00 25,000.00
12% Hk Perlengkapan 25,000.00 3,000.00
0.1800 Hari Tukang Pipa 50,000.00 9,000.00
0.0180 Hari Kepala tukang Pipa 55,000.00 990.00
0.5000 Hari Pekerja 36,000.00 18,000.00
0.0500 Hari Mandor 60,000.00 3,000.00
58,990.00
J.6.14 1 bh PEKERJAAN MEMASANG FLOUR DRAINASE
1.0000 bh Fluor drain (avour) 25,000.00 25,000.00
12% Hk Perlengkapan 25,000.00 3,000.00
0.1800 Hari Tukang Pipa 50,000.00 9,000.00
0.0180 Hari Kepala tukang Pipa 55,000.00 990.00
0.5000 Hari Pekerja 36,000.00 18,000.00
0.0500 Hari Mandor 60,000.00 3,000.00
58,990.00
J.6.15 1 bh PEKERJAAN MEMASANG BAK AIR PLASTIK VIBRE
1.0000 bh Bak Air Plastik Vibre 400,000.00 400,000.00
12% Hk Perlengkapan 400,000.00 48,000.00
0.1500 Hari Tukang Pipa 50,000.00 7,500.00
0.0150 Hari Kepala tukang Pipa 55,000.00 825.00
0.5000 Hari Pekerja 36,000.00 18,000.00
0.0500 Hari Mandor 60,000.00 3,000.00
477,325.00
K.6.10 1 M² PEKERJAAN MEMASANG KACA BENING 5MM
1.1000 M² Kaca 5 mm (bening) 95,000.00 104,500.00
0.1500 Hari Tukang kayu 50,000.00 7,500.00
0.0150 Hari Kepala tukang kayu 55,000.00 825.00
0.0150 Hari Pekerja 36,000.00 540.00
0.0010 Hari Mandor 60,000.00 60.00
113,425.00
K.6.10a 1 M² PEKERJAAN MEMASANG KACA BENING 5MM(KACA SUSU )
1.1000 M² Kaca 5 mm ( Susu ) 125,000.00 137,500.00
0.1500 Hari Tukang kayu 50,000.00 7,500.00
0.0150 Hari Kepala tukang kayu 55,000.00 825.00
0.0150 Hari Pekerja 36,000.00 540.00
0.0010 Hari Mandor 60,000.00 60.00
146,425.00
DAFTAR HARGA SATUAN UPAH DAN BAHAN
TAHUN 2013

No. JENIS UPAH/BAHAN Harga Satuan


1 2 3 4
A HARGA SATUAN UPAH
1 Pekerja Rp. 36,000.00 Hari
2 Mandor Rp. 60,000.00 Hari
3 Tukang batu Rp. 50,000.00 Hari
4 Kepala tukang batu Rp. 55,000.00 Hari
5 Tukang kayu Rp. 50,000.00 Hari
6 Kepala tukang kayu Rp. 55,000.00 Hari
7 Tukang besi Rp. 50,000.00 Hari
8 Kepala tukang besi Rp. 55,000.00 Hari
9 Tukang cat Rp. 50,000.00 Hari
10 Kepala tukang cat Rp. 55,000.00 Hari
11 Tukang las Rp. 50,000.00 Hari
12 Kepala tukang las Rp. 55,000.00 Hari
13 Tukang Pipa Rp. 50,000.00 Hari
14 Kepala tukang Pipa Rp. 55,000.00 Hari
15 Tukang Listrik Rp. 50,000.00 Hari
16 Kepala tukang Listrik Rp. 55,000.00 Hari
17 Pekerja terlatih Rp. 47,000.00 Hari
18 Pemasak aspal Rp. 36,000.00 Hari
19 Operator Rp. 65,000.00 Hari
20 Pembentu operator Rp. 50,000.00 Hari
21 Penjaga malam Rp. 36,000.00 Hari
22 Sopir Rp. 60,000.00 Hari

B. HARGA SATUAN BAHAN.


B.1. Bahan Pasangan
1 Batu kali Rp. 70,000.00 m³
2 Tanah urug Rp. 40,000.00 m³
3 Pasir pasang Rp. 60,000.00 m³
4 Pasir Beton Rp. 75,000.00 m³
5 Pasir Pasang/kg Rp. 44.44 kg
6 Pasir urug Rp. 40,000.00 m³
7 Pasir ayak untuk beton Rp. 90,000.00 m³
8 Sirtu Rp. 60,000.00 m³
9 Kapur pasang Rp. 300,000.00 m³
10 Semen/zak Rp. 62,000.00 zak
11 Semen/kg Rp. 1,240.00 kg
12 Semen warna Rp. 7,500.00 kg
13 Bata merah Rp. 500.00 bh
14 Krikil pecah 2/3 Rp. 125,000.00 m³
15 Krikil pecah 2/3/kg Rp. 69.44 kg
16 Krikil sungai tak disaring Rp. 90,000.00 m³
17 Tanah pilihan Rp. 45,000.00 m³
18 Air Rp. 10.00 ltr

B.2 Bahan Atap


1 Genteng Metal Rp. 35,000.00 lbr
2 Bubungan Metal Rp. 25,000.00 lbr
3 Seng plat BJLS 30 Rp. 65,000.00 lbr
4 Paku ulir Rp. 100.00 bh
5 Genteng Keramik Rp. 9,500.00 bh
6 Bubungan Genteng Keramik Rp. 20,000.00 bh
B.3 Bahan Kayu
1 Kayu kls I Rp. 7,500,000.00 m³
2 Kayu kls II Rp. 3,500,000.00 m³
3 Papan kayu kls I Rp. 7,500,000.00 m³
4 Papan kayu kls II Rp. 3,500,000.00 m³
5 Kayu kls III Rp. 2,000,000.00 m³
6 Papa kayu kls III Rp. 2,000,000.00 m³
7 Dolken(bambu) Rp. 5,000.00 bt
8 Kayu bakar Rp. 900,000.00 m³

B.4 Bahan Lantai


1 Keramik 10 X 20 Rp. 50,000.00 m²
1 Keramik 20 X 20 Rp. 50,000.00 m²
2 Keramik 30 X 30 Rp. 45,000.00 m²
3 Keramik 60 X 60 (Motif) Rp. 50,000.00 m²
4 Plint keramik 10 X 30 cm Rp. 5,000.00 bh
5 Vinyl 30/30 Rp. 250,000.00 m²

B.5 Bahan Besi + Paku


1 Besi beton Ulir Rp. 8,000.00 kg
2 Besi beton Polos Rp. 8,000.00 kg
3 Kawat beton Rp. 9,000.00 kg
4 Profil Almunium Rp. 60,000.00 m'
5 Ram kusen aluminium Rp. 50,000.00 m'
6 Baut piles Rp. 20,000.00 dus
7 Skrup fixer Rp. 200.00 bh
8 Sealant Rp. 20,000.00 tube
9 Karet list Rp. 1,000.00 m'
10 Karet talang 60 Cm Rp. 20,000.00 m'
11 Paku Rp. 15,000.00 kg
12 Paku Aluminium Rp. 20,000.00 kg
13 Plat Almunium 4 mm Rp. 150,000.00 m2
14 Besi setrip 5.mm Rp. 15,000.00 kg
15 Besi plat Rp. 15,000.00 kg
16 Besi profil Rp. 15,000.00 kg
17 Kontra mur Rp. 25,000.00 bh
18 Angker ø 16 mm p = 40 cm Rp. 5,000.00 bh
19 Baut ø 16 mm Rp. 5,000.00 bh
20 Baut ø 12 mm Rp. 2,500.00 bh

B.6 Bahan Langit-Langit


#VALUE! Teackwood 3 mm Rp. 65,000.00 lbr
#VALUE! Triplek 3 mm Rp. 45,000.00 lbr
#VALUE! Triplek 9 mm Rp. 90,000.00 lbr
#VALUE! Triplek lapis aluminium Rp. 90,000.00 lbr
#VALUE! List plafond gypsum C7 Rp. 12,500.00 m
#VALUE! Kalsiboard 6 mm Rp. 35,000.00 m2
#VALUE! Paku Gypsum Rp. 25,000.00 kg
#VALUE! Gypsum 9 mm Rp. 32,500.00 m2
#VALUE! Gypsum 12 mm Rp. 40,000.00 m2
#VALUE! Kasa Gypsum Rp. 15,000.00 rol
#VALUE! Tepung Gypsum Rp. 5,000.00 kg
#VALUE! Alkasit Rp. 12,500.00 kg
B.7 Bahan Kaca
#VALUE! Kaca 3 mm (bening) Rp. 65,000.00 m²
#VALUE! Kaca 5 mm (bening) Rp. 95,000.00 m²
#VALUE! Kaca Susu 5 mm Rp. 120,000.00 m²
#VALUE! Kaca rayban 3 mm Rp. 65,000.00 m²
#VALUE! Kaca rayban 5 mm Rp. 110,000.00 m²
#VALUE! Glass block Rp. 20,000.00 m²
#VALUE! Kaca 5 mm ( Susu ) Rp. 125,000.00 m²
B.8 Bahan Lain - lain
1 Cat tembok Rp. 10,000.00 kg
2 Cat tembok Mutu Tinggi Rp. 25,000.00 kg
3 Cat tembok Epoxy Rp. 25,000.00 kg
4 Cat genteng Rp. 30,000.00 kg
5 Cat besi Rp. 35,000.00 kg
6 Teer arang Rp. 2,000.00 kg
7 Lem Vinyl Rp. 15,000.00 kg
8 Cat kayu Rp. 35,000.00 kg
9 Anti karat Rp. 50,000.00 kg
10 Lem Aica aibon Rp. 20,000.00 kg
11 Plamir kayu Rp. 10,000.00 kg
12 Politur Rp. 25,000.00 kg
13 Amplas Rp. 2,000.00 lbr
14 Minyak Cat Rp. 10,000.00 kg
15 Minyak tanah Rp. 7,500.00 ltr
16 Kuas cat Rp. 2,000.00 kg
17 Dempul kayu Rp. 12,000.00 kg
18 Meny kayu Rp. 10,000.00 kg
19 Meny besi anti karat Rp. 25,000.00 kg
20 Roll cat Rp. 15,000.00 bh
21 Plamir tembok Rp. 6,000.00 kg
21 Kunci tanam 3 levers Rp. 200,000.00 bh
22 Kunci tanam Rp. 200,000.00 bh
23 Engsel pintu Rp. 7,500.00 psg
24 Engsel jendela Rp. 7,000.00 psg
25 Grendel jendela Rp. 5,000.00 bh
26 Grendel pintu Rp. 10,000.00 bh
27 Hak angin Rp. 7,500.00 bh
28 Rel Pintu Rp. 40,000.00 m'
29 Angker kusen/dok Rp. 1,000.00 bh
30 Pipa PVC ø 2,5" (Medium A) Rp. 35,000.00 m'
31 Pipa PVC ø 4" (Medium A) Rp. 45,000.00 m'
32 Pipa PVC ø 3" (Medium B) Rp. 65,000.00 m'
33 Pipa PVC ø 2" (Medium B) Rp. 35,000.00 m'
34 Pipa PVC ø 1" (Medium B) Rp. 12,500.00 m'
35 Pipa PVC ø 1/2" (Medium B) Rp. 10,000.00 m'
36 Accessories PVC ø 1 (Medium B) Rp. 5,000.00 bh
37 Accessories PVC ø 1/2 (Medium B) Rp. 2,500.00 bh
38 Hand shower sekualitas Ex. San'ei Rp. 200,000.00 bh
39 Kran shower ø 1/2" sekualitas Ex. San'ei Rp. 200,000.00 bh
40 Grendel Tanam Rp. 25,000.00 bh
41 Kran air ø 1/2" Rp. 25,000.00 bh
42 Fluor drain (avour) Rp. 25,000.00 bh
43 Kloset jongkok Rp. 125,000.00 bh
44 Kloset Duduk Rp. 1,250,000.00 bh
45 Sekring box 5 fase ( MCB ) Rp. 400,000.00 bh
46 Titik lampu Rp. 135,000.00 bh
47 Stop kontak broco 10 A Rp. 35,000.00 bh
48 Saklar tunggal Rp. 25,000.00 bh
49 Saklar ganda Rp. 30,000.00 bh
50 Lampu pijar 25 watt Rp. 5,000.00 bh
51 Lampu pijar 15 watt Rp. 4,000.00 bh
52 Lampu TL 1 x 20 watt Rp. 75,000.00 bh
53 Lampu TL bundar 20 watt Rp. 100,000.00 bh
54 Penangkal petir Rp. 5,000,000.00 unit
55 List pinggir 5/5 profil Rp. 7,500.00 m'
56 Solar Rp. 7,500.00 ltr
57 Oli mesin Rp. 22,500.00 ltr
58 Acytilyin Rp. 250,000.00 btl
59 Oksigen Rp. 200,000.00 btl
60 Pelumas Rp. 22,000.00 lrt
61 Mesin las Rp. 7,500,000.00 unit
62 Mesin potong Rp. 1,000,000.00 unit
63 Mesin gergaji Rp. 2,000,000.00 unit
64 Mesin bor Rp. 5,200,000.00 unit
65 Kompresor Rp. 2,000,000.00 unit
66 Kawat las Rp. 75,000.00 dos
67 Gerinda Rp. 1,000,000.00 unit
68 Mata bor Rp. 50,000.00 unit
69 Mata gergaji Rp. 20,000.00 unit
70 Listrik Rp. 1,000.00 Kwh
71 Pompa air (sewa) Rp. 50,000.00 Hari
72 Minyak begisting Rp. 2,000.00 ltr
BOBOT KEMAJUAN PEKERJAAN
PEKERJAAN : PEMBANGUNAN RUANG KELAS BARU (BERTINGKAT) SMK DARUL FALAH
LOKASI : JL. BHANDA SRAYA PAGUTAN
TAHUN ANGGARAN :2012

Prosentase Kemajuan Bobot Kemajuan


Bobot Sat. Pek.
No Uraian Pekerjaan Volume Masing - Masing Item Masing - Masing
(%)
Pekerjaan (%) Item Pekerjaan (%)

1 2 3 4 5 6

I PEKERJAAN PENDAHULUAN
1 Pengukuran /Uitzet & Bouplank 36.00 m 0.07 100.00 0.07
2 Bongkar Bangunan Lama 1.00 unit 0.21 100.00 0.21
-
II. TANAH DAN PASIR -
1 Galian tanah pondasi 22.500 m3 0.33 100.00 0.33
2 Mengurug kembali 1/3 X Galian 0.11 100.00 0.11
3 Urugan Tanah Peninggian Lantai 32.400 m3 0.93 100.00 0.93
4 Urugan Pasir Pondasi 3.375 m3 0.08 100.00 0.08
5 Urugan Pasir Lantai 8.100 m3 0.20 0.00 -
-
III. PEKERJAAN PASANGAN DAN PLESTERAN -
1 Pas. Batu Kosong 2.100 m3 0.13 100.00 0.13
2 Pas. Pondasi batu kali 5.160 m3 0.88 100.00 0.88
3 Pas. tembok bata camp. 1pc : 5 ps 216.000 m2 6.03 100.00 6.03
4 Pas. tembok bata trasram camp. 1pc : 3 ps 24.600 m2 0.74 100.00 0.74
5 Plesteran dinding bata camp. 1pc : 5 ps 481.200 m2 4.83 100.00 4.83
6 Plesteran Beton Kolom ,Listplank 1pc : 3 ps 51.020 m2 0.58 100.00 0.58
7 Finishing Plesteran ( Acian ) 481.200 m2 3.10 100.00 3.10
-
IV. PEKERJAAN BETON MUTU K. 225 -
1 Beton lantai kerja bawah Pondasi 1.600 m3 0.34 100.00 0.34
2 Beton pondasi plat setempat 2,5 x 2,5 2.210 m3 1.87 100.00 1.87
3 Beton pondasi plat setempat 1,25x1,25 1.920 m3 1.62 100.00 1.62
4 Beton sloof 20/35 cm 2.501 m3 3.08 100.00 3.08
5 Beton sloof 15/20 cm 0.813 m3 1.00 100.00 1.00
6 Beton kolom 40/40 cm (L1) 1.012 m3 1.99 100.00 1.99
7 Beton kolom 25/25 cm (L1) 1.550 m3 3.42 100.00 3.42
8 Beton Tangga 1.041 m3 1.28 100.00 1.28
9 Beton kolom praktis 10/10 cm Lantai 1 (Kp1) 0.645 m3 1.66 100.00 1.66
10 Beton Balok Lantai 30/70 0.252 m3 0.39 100.00 0.39
11 Beton Balok Lantai 25/60 0.468 m3 0.73 100.00 0.73
12 Beton Balok Lantai 25/35 0.297 m3 0.40 100.00 0.40
13 Beton Plat Lantai T = 12 cm 9.720 m3 12.44 100.00 12.44
14 Beton kolom 25/25cm ( L.2) 0.864 m3 1.70 100.00 1.70
15 Beton kolom praktis 10/10 cm Lantai 2 (Kp 2 ) 0.360 m3 0.93 100.00 0.93
16 Beton Balok Ring 15/20 0.619 m3 1.25 100.00 1.25
-
V. PEKERJAAN KUSEN DAN DAUN -
1 Kusen pintu / jendela 0.960 M3 2.40 100.00 2.40
2 Daun jendela kaca 3 mm 20.000 BH 0.92 0.00 -
3 Daun pintu panil 4.000 BH 0.42 0.00 -
4 Kaca 5 mm (bening) 8.000 m2 0.30 0.00 -
-
VI PEKERJAAN KUDA KUDA BAJA DAN ATAP -
1 Kuda kuda Baja Ringan 172.90 m2 9.55 100.00 9.55
2 Listplank Kalsi 44.00 m' 0.92 100.00 0.92
3 Atap Genteng Multi roof 172.90 m2 3.96 100.00 3.96
4 Bubungan Genteng Multi roof 24.00 m' 0.25 100.00 0.25
-
VII. PEKERJAAN LANTAI,PELAPIS DINDING DAN PLAFOND -
1 Pas. lantai keramik 40 x 40 cm 182.000 m2 8.71 35.00 3.05
2 Plafond Kalsibort (Rangka Kayu) 121.000 m2 3.02 100.00 3.02
3 List pinggir plafond 72.000 m 0.10 100.00 0.10
-
VIII. PEKERJAAN BESI / PENGUNCI -
1 Kunci tanam 2.00 bh 0.10 0.00 -
2 Grendel Tanam 2.00 bh 0.01 0.00 -
3 Engsel jendela 40.00 bh 0.17 0.00 -
4 Hak angin 40.00 bh 0.17 0.00 -
5 Grendel jendela 20.00 bh 0.08 0.00 -
6 Engsel pintu 4.00 bh 0.03 0.00 -
-
IX. PEKERJAAN INSTALASI LISTRIK -
1 Instalasi Penerangan(titik Lampu ) 9.000 Titik 0.13 50.00 0.07
2 Lampu Pilip XL 18 Wat 8.000 bh 0.09 0.00 -
3 Instalasi Stop Kontak 2.000 bh 0.02 50.00 0.01
4 Saklar tunggal 2.000 bh 0.02 0.00 -
5 Saklar double 2.000 bh 0.02 0.00 -
-
X. PEKERJAAN PENGECATAN -
1 Cat tembok 481.200 m2 2.78 0.00 -
2 Cat Plafond 121.000 m2 0.70 0.00 -
3 Cat kayu 41.700 m2 0.29 0.00 -
-
XI. PENGADAAN MEUBELAIR -
1 Pengadaan Meubelair Ruang Kelas Lengkap 2.000 kls 12.50 100.00 12.50

JUMLAH 100.00 87.97

CATATAN
1 Kemajuan Pekerjaan sampai dengan tanggal …. Mei 2013
adalah sebesar 87.968 %

2 Deviasi kurang sebeasr 12.032 %

Mataram, 15 Mei 2013


KEPALA
SMK DARUL FALAH

BAIDAWI, SE

Anda mungkin juga menyukai