BACKUP DATA PERHITUNGAN VOLUME BOX CULVERT

PEMELIHARAAN RUTIN DS. SENDANGGAYAM KEC. BANJAREJO

VOLUME
NO SKET GAMBAR PERHITUNGAN VOLUME Galian Tanah (m3)
Beton (m3)
JUMLAH SEBELUMNYA

1. GALIAN TANAH = (2,4+1,4)/2 x 1,47 x 6 16.758

2. BETON = ((1,4 x 1,4 x 6) - (0,6+1)/2 x 0,02 x2)) x 6 6.24

3. BEGESTING = (1,4 x 6 x 2) + (1 x 6 x 3 )

4. PEMBESIAN
a. Tul. Pokok = ((6,06 x 50) x 0,62

b. Begel = 3,14 x 31 x 4 x 0,888

c. Begel = 0,5 x 31 x 4 x 0,888

•S' -a *» s • f—i-------i—i 4PIR y1 ’» • MO ■ > i a » 16, 1!


JUMLAH KUMULATIF 16.758 6.24

PPTK TIM TEKNIS PENYEDIA JASA

CV. DAMAI SEJAHTERA

1 YUDI KRISTIAWAN 1................................................

2 SUTION, SE 2................................................

SUTONO, ST, MM ____________________

NIP. 19661219 199102 1 001 3 JORDI MUHAMMAD A. 3................................................ PELAKSANA


E KEBUTUHAN BAHAN
Begesting (m2)Pembesian (kg)
Pasir (m3) Semen Batu PecahBesi
2/3 Begesting

3.62 43.68 4.5

34.8 34.8

187.86 210.41

345.752 387.25

55.056 61.67

34.8 588.668 3.62 43.68 4.5 659.33 34.8