DAFTAR KUANTITAS DAN HARGA

PEKERJAAN TAMBAH / KURANG (CCO) AMANDEMEN KONTRAK

PENINGKATAN JALAN BAAD - SINEGI DISTRIK ANIMHA KABUPATEN MERAUKE

SEMULA PEKERJAAN TAMBAH/KURANG (CCO)

NO URAIAN PEKERJAAN SAT. PEKERJAAN TAMBAH PEKERJAAN KURANG


PERKIRAAN HARGA SATUAN JUMLAH HARGA BOBOT
VOLUME (Rupiah) (Rupiah) (%)
VOLUME JLH. HARGA VOLUME

I DEVISI 1 UMUM
1 Mobilisasi Ls 1.00 125,750,000.00 125,750,000.00 1.07
2 Pengukuran Dan Pematokan Jalan M1 1,480.00 1,257.00 1,860,360.00 0.02 -

II DEVISI 2 PEKERJAAN TIMBUNAN TANAH DAN PASIR PADA BADAN DAN BAHU JALAN
1 Timbunan Pilihan Bahu Jalan M3 284.66 275,673.00 78,473,076.18 0.67 315.56 86,991,738.07
2 Penyiapan Badan Jalan M2 13,320.00 1,009.00 13,439,880.00 0.11 -
3 Urugan Pasir M3 37.00 408,681.00 15,121,197.00 0.13 37.00

III DEVISI 3 PEKERJAAN PERKERASAN BADAN JALAN


1 Pondasi Jalan Beton Bertulang 25/28 Cm
1.a Cor Beton Mutu Sedang fc' = 25 Mpa (K - 300) M3 121.36 3,898,287.00 473,096,110.32 4.03 85.84 334,628,956.08
1.b besi Tulangan Diameter 10 Kg 9,715.47 18,297.00 177,763,954.59 1.51 342.50
1.c besi Tulangan Diameter 8 Kg 6,074.67 18,055.00 109,678,166.85 0.93 2,734.30 49,367,858.72
1.d Bekisting Badan Jalan M2 43.69 283,743.00 12,396,731.67 0.11 252.31 71,591,196.33
2 LPA - Cor Badan Jalan Beton Bertulang Tebal 18 Cm
2.a Cor Beton Mutu Sedang fc' = 25 Mpa (K - 300) M3 1,465.49 3,898,287.00 5,712,900,615.63 48.62 0.29
2.b besi Tulangan Diameter 10 Kg 102,657.57 18,297.00 1,878,325,558.29 15.99 28,799.61
3 Dowel Tulangan Besi Diameter 16 Kg 67.26 18,478.00 1,242,830.28 0.01 372.61 6,885,124.54

IV DEVISI 4 PEKERJAAN LAPIS PERMUKAAN


1 Prime Coat (Lapis Pengikat) M2 8,880.00 20,804.00 184,739,520.00 1.57
2 HRS LATASTON (Tebal 4 Cm) M2 8,880.00 333,952.00 2,965,493,760.00 25.24

(A) JUMLAH 11,750,281,760.81 100.00 549,464,873.73


(B) PAJAK PERTAMBAHAN NILAI (PPN) = 10 % x (A) 1,175,028,176.08
(C) TOTAL HARGA (A) + (B) 12,925,309,936.89
(D) TOTAL HARGA DIBULATKAN 12,925,309,000.00

MENGETAHUI : MENYETUJUI : DIPERIKSA :


KEPALA DINAS PEKERJAAN UMUM PENATAAN PEJABAT PELAKSANA TEKNIS KEGIATN (PPTK) PENGAWAS LAPANGAN
RUANG DAN PERTANAHAN KABUPATEN MERAUKE PENINGKATAN JALAN BAAD - SINEGI PENINGKATAN JALAN BAAD - SINEGI

Ir. H.B.L.TOBING,MEng LEO PATRIA MOGOT,ST U S M A N ,A . Md


NIP. 19601216 199103 1 008 NIP. 19730628 200605 1 002 NIP. 19610110 200012 1 002
AFTAR KUANTITAS DAN HARGA
N TAMBAH / KURANG (CCO) AMANDEMEN KONTRAK

PEKERJAAN TAMBAH/KURANG (CCO) MENJADI

PEKERJAAN KURANG KET


PERKIRAAN HARGA SATUAN JUMLAH HARGA BOBOT (%)
VOLUME (Rupiah) (Rupiah)
JLH. HARGA

1.00 125,750,000.00 125,750,000.00 1.07 TETAP


- 1,480.0 1,257.00 1,860,360.00 0.02 TETAP

600.22 275,673.00 165,464,814.25 1.41 BERTAMBAH


- 13,320.00 1,009.00 13,439,880.00 0.11 TETAP
15,121,197.00 - 408,681.00 - - DIHILANGKAN

207.20 3,898,287.00 807,725,066.40 6.87 BERTAMBAH


6,266,715.18 9,372.97 18,297.00 171,497,239.41 1.46 BERKURANG
8,808.97 18,055.00 159,046,025.57 1.35 BERTAMBAH
296.00 283,743.00 83,987,928.00 0.71 BERTAMBAH

1,130,503.23 1,465.20 3,898,287.00 5,711,770,112.40 48.61 BERKURANG


526,946,458.31 73,857.96 18,297.00 1,351,379,099.98 11.50 BERTAMBAH
439.87 18,478.00 8,127,954.82 0.07 BERTAMBAH

8,880.00 20,804.00 184,739,520.00 1.57 TETAP


8,880.00 333,952.00 2,965,493,760.00 25.24 TETAP

549,464,873.73 11,750,281,760.82 100.00


1,175,028,176.08
12,925,309,936.90
12,925,309,000.00

DIPERIKSA : DIBUAT :
KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
PT.MAKROTHUMIA EIRENE CONSULTANT PT. TUNAS JAYA IRJA

WAYAN DARYASA, ST HENRY KURNIAWAN


Team Leader Direktur
PEMERINTAH KABUPATEN MERAUKE
DINAS PEKERJAAN UMUM PENATAAN RUANG DAN PERTANAHAN
BIDANG BINA MARGA

KONTRAKTOR :PT. PEMBANGUNAN JAYA PAPUA RAYA


NO. KONTRAK : 03/KONTRAK/DAK - K1/DPUPRP - BM/V/2018
TGL MULAI KERJA : 23 MEI 2018
KONSULTAN : PT. MAKROTHUMIA EIRENE CONSULTANT

Kegiatan : -
Pekerjaan : PEMBANGUNAN SIRKUIT BALAP MOTOR
Lokasi : DISTRIK TANAH MIRING
Kabupaten : MERAUKE - PAPUA
T. Anggaran : 2019

DAFTAR KUANTITAS DAN HARGA


BOBOT
Jumlah
NILAI
No. Uraian Pekerjaan Satuan Volume
PEKERJAAN
Harga Satuan Harga Satuan %

I PEKERJAAN PERSIAPAN
A. PEKERJAAN PERSIAPAN UMUM 478,400,000.00 0.674
B. PEKERJAAN MOBILISASI DAN DEMOBILISASI 77,000,000.00 0.108

II PEKERJAAN PEMBENTUKAN LAHAN (CUT & FILL) 6,433,061,917.88 9.061

III PEKERJAAN STRUKTURAL


A. GEDUNG TRIBUN 2,657,426,718.86 3.743
B. GEDUNG SEKRETARIAT (TIDAK TERMASUK LINGKUP) 910,496,470.68 1.282
C. RUMAH JAGA 177,169,596.40 0.250
D. TOILET 209,937,048.46 0.296
E. BENGKEL (TIDAK TERMASUK LINGKUP) 231,436,877.32 0.326
F. POS JAGA (3 UNIT) 39,597,012.19 0.056
G. BANGUNAN GERBANG MASUK 86,246,855.83 0.121

IV PEKERJAAN ARSITEKTURAL
A. GEDUNG TRIBUN 2,967,712,846.00 4.180
B. GEDUNG SEKRETARIAT (TIDAK TERMASUK LINGKUP) 1,019,217,984.12 1.436
C. RUMAH JAGA 526,906,824.01 0.742
D. TOILET 357,025,666.62 0.503
E. BENGKEL (TIDAK TERMASUK LINGKUP) 423,373,185.13 0.596
F. POS JAGA (3 UNIT) 87,709,150.99 0.124
G. BANGUNAN GERBANG MASUK 52,037,207.65 0.073
H. LANDSCAPE 10,844,334,975.64 15.274

V PEKERJAAN LANSEKAP
A. PEKERJAAN HARDSCAPE 788,347,303.00 1.110

VI PEKERJAAN INFRASTRUKTUR
A. PEKERJAAN DRAINASE 1,937,944,871.80 2.730
B. PEKERJAAN JALAN 33,205,620,463.00 46.770
C. MARKA JALAN 5,656,194,000.00 7.967

VII PEKERJAAN ELEKTRIKAL


A. PENYAMBUNGAN, DISTRIBUSI DAN PEMBANGKITAN DAYA 778,615,000.00 1.097
B. PEKERJAAN INSTALASI PENERANGAN 378,980,000.00 0.534
C. PEKERJAAN PENANGKAL PETIR 61,560,000.00 0.087
D. PEKERJAAN SISTEM TELEPON 79,892,000.00 0.113
E. SISTEM TATA SUARA 98,493,000.00 0.139
F. SISTEM FIRE ALARM 59,820,000.00 0.084

VIII PEKERJAAN MEKANIKAL


A. PEKERJAAN PLUMBING AIR BERSIH 74,169,000.00 0.104
B. PEMIPAAN AIR BERSIH TOILET 8,697,000.00 0.012
C. PEMIPAAN AIR KOTOR DAN BUANGAN TOILET 102,746,000.00 0.145
D. PEMIPAAN AIR BERSIH KE AREA MOTOR CROSS 57,850,000.00 0.081
E. PEKERJAAN SISTEM TATA UDARA 60,320,000.00 0.085
F. BANGUNAN SEKERTARIAT 69,920,000.00 0.098

(A) JUMLAH 70,998,258,975.58 100.000


(B) PAJAK PERTAMBAHAN NILAI (PPN) = 10 % x (A) 7,099,825,897.56
(C) TOTAL HARGA (A) + (B) 78,098,084,873.14
(D) TOTAL HARGA DIBULATKAN 78,098,084,000.00
PEMERINTAH KABUPATEN MERAUKE
DINAS PEKERJAAN UMUM PENATAAN RUANG DAN PERTANAHAN
BIDANG BINA MARGA

KONTRAKTOR : : PT. PT. PEMBANGUNAN JAYA PAPUA RAYA


NO. KONTRAK : : 03/KONTRAK/DAK - K1/DPUPRP - BM/V/2018
TGL MULAI KERJA : : 23 MEI 2018
KONSULTAN : : PT. MAKROTHUMIA EIRENE CONSULTANT
:
Kegiatan : PEMBANGUNAN SIRKUIT BALAP MOTOR
Pekerjaan : BENGKEL
Lokasi : DISTRIK TANAH MIRING
Kabupaten : MERAUKE - PAPUA
T. Anggaran : 2019

DAFTAR KUANTITAS DAN HARGA BENGKEL


BOBOT
Jumlah NILAI
No. Uraian Pekerjaan Satuan Volume
PEKERJAAN
Harga Satuan Harga Satuan
%

III PEKERJAAN STRUKTURAL


E. BENGKEL (TIDAK TERMASUK LINGKUP)
E.1 PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bouwplank M 48.00 93,857.00 4,505,136.00 0.688

E.2 PEKERJAAN TANAH DAN PASIR


1 Galian Tanah Pondasi M3 16.11 152,233.00 2,452,473.63 0.375
2 Urugan Tanah Kembali Galian Pondasi M3 5.37 50,744.00 272,495.28 0.042
3 Urugan Pasir Bawah Pondasi tebal 10 cm M3 1.79 878,744.00 1,572,951.76 0.240

E.3 PEKERJAAN STRUKTUR LANTAI 1


1 Pek. Cor lantai kerja 1pc 6psr
˗ Beton campuran 1pc 6psr M3 1.79 2,908,534.00 5,206,275.86 0.795
˗ Begesting Kayu Kls III M2 8.10 247,699.00 2,006,361.90 0.306
2 Pekerjaan Pondasi Telapak 100x100x30 cm (F1) 1.00
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 3.00 3,492,364.00 10,477,092.00 1.600
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 344.24 20,357.00 7,007,693.68 1.070
˗ Bekisting untuk Pondasi M2 2.40 247,699.00 594,477.60 0.091
3 Pekerjaan Pondasi Telapak 60x60x30 cm (F2)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 0.97 3,492,364.00 3,387,593.08 0.517
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 146.28 20,357.00 2,977,821.96 0.455
˗ Bekisting untuk Pondasi M2 1.30 247,699.00 322,008.70 0.049
4 Pekerjaan Pondasi Telapak 102.5x60x30 cm (F3)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 0.55 3,492,364.00 1,920,800.20 0.293
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 71.80 20,357.00 1,461,632.60 0.223
˗ Bekisting untuk Pondasi M2 0.59 247,699.00 146,142.41 0.022
5 Pekerjaan Pondasi Telapak 140x100x30 cm (F4)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 0.28 3,492,364.00 977,861.92 0.149
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 95.42 20,357.00 1,942,464.94 0.297
˗ Bekisting untuk Pondasi M2 0.58 247,699.00 143,665.42 0.022
6 Pek. Kolom Pedestal K-1, uk. 20 x 30 cm
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 0.80 3,492,364.00 2,793,891.20 0.427
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 792.23 20,357.00 16,127,426.11 2.463
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 145.31 20,357.00 2,958,075.67 0.452
˗ Bekisting untuk kolom M2 2.65 419,917.00 1,112,780.05 0.170
7 Pek. Kolom Pedestal K-2, uk. 11 x 11 cm
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 0.20 3,492,364.00 698,472.80 0.107
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 487.53 20,357.00 9,924,648.21 1.516
˗ Pembesian Besi polos/ulir . 8 mm SNI Kg 25.52 20,357.00 519,510.64 0.079
˗ Bekisting untuk kolom M2 1.44 419,917.00 604,680.48 0.092
8 Pekerjaan Sloof uk. 15x30 cm (TB1a)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 2.61 3,492,364.00 9,115,070.04 1.392
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 122.56 20,357.00 2,494,953.92 0.381
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 238.28 20,357.00 4,850,665.96 0.741
˗ Bekisting untuk sloof M2 10.87 247,699.00 2,692,488.13 0.411
9 Pekerjaan Sloof uk. 11x30 cm (TB2a)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 1.37 3,492,364.00 4,784,538.68 0.731
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 131.01 20,357.00 2,666,970.57 0.407
˗ Pembesian Besi polos/ulir . 8 mm SNI Kg 109.56 20,357.00 2,230,312.92 0.341
˗ Bekisting untuk sloof M2 7.39 247,699.00 1,830,495.61 0.280
10 Pek. Kolom K1 , uk. 20 x 30 cm
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 2.93 3,492,364.00 10,232,626.52 1.563
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 1,778.55 20,357.00 36,205,942.35 5.529
˗ Bekisting untuk kolom M2 9.75 419,917.00 4,094,190.75 0.625
11 Pek. Kolom , uk. 11 x 11 cm
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 0.59 3,492,364.00 2,060,494.76 0.315
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 786.87 20,357.00 16,018,312.59 2.446
˗ Pembesian Besi polos/ulir . 8 mm SNI Kg 29.23 20,357.00 595,035.11 0.091
˗ Bekisting untuk kolom M2 4.29 419,917.00 1,801,443.93 0.275
12 Pekerjaan Ringbalk uk. 15x30 cm (RB1a)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 2.61 3,492,364.00 9,115,070.04 1.392
˗ Pembesian Besi polos/ulir . 12 mm SNI Kg 104.43 20,357.00 2,125,881.51 0.325
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 238.28 20,357.00 4,850,665.96 0.741
˗ Bekisting untuk ringbalk M2 4.29 425,609.00 1,825,862.61 0.279
13 Pekerjaan Ringbalk uk. 11x30 cm (RB2)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 1.95 3,492,364.00 6,810,109.80 1.040
˗ Pembesian Besi polos/ulir . 12 mm SNI Kg 121.31 20,357.00 2,469,507.67 0.377
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 242.80 20,357.00 4,942,679.60 0.755
˗ Bekisting untuk ringbalk M2 10.49 425,609.00 4,464,638.41 0.682
14 Pek. Plat talang beton, tebal. 11 cm
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 1.29 3,492,364.00 4,505,149.56 0.688
˗ Pembesian Besi polos/ulir . 8 mm SNI Kg 178.14 20,357.00 3,626,395.98 0.554
˗ Bekisting Kayu Kelas III M2 11.76 247,699.00 2,912,940.24 0.445
No. Uraian Pekerjaan Satuan Volume
PEKERJAAN
Harga Satuan Harga Satuan
%

IV PEKERJAAN ARSITEKTURAL
E BENGKEL (TIDAK TERMASUK LINGKUP)
E.1 PEKERJAAN TANAH DAN PASIR
1 Urugan Pasir Bawah Lantai tebal 10 cm M3 13.96 878,744.00 12,267,266.24 1.873
2 Urugan Tanah Peninggian Lantai M3 55.85 282,037.00 15,751,766.45 2.406

E.2 PEKERJAAN PASANGAN DINDING


1 Pasangan Dinding Bata merah Tebal 1/2 Bata, 1PC 4PS - Pasir Import M2 206.92 329,687.00 68,218,834.04 10.418
2 Plesteran 1PC 3PS, Tebal 20 mm - Pasir Import M2 413.84 174,916.00 72,387,237.44 11.055
3 Pekerjaan Acian M2 413.84 62,001.00 25,658,493.84 3.918
4 Cor lantai ruangan tebal 5 cm, 1 pc 3psr M3 5.02 4,084,554.00 20,504,461.08 3.131
5 Cor lantai rabat tebal 5 cm, 1 pc 3psr + aci kasar M3 1.07 4,084,554.00 4,370,472.78 0.667

E.3 PEKERJAAN KUSEN,PINTU/JENDELA TERMASUK FINISHING & ACCESSORIES


1 Tipe Pintu Polding get.1 uk. 280 x 220 Cm Unit 2.00 15,020,000.00 30,040,000.00 4.588
2 Tipe P1 Pintu kusen Alumunium uk. 80 x 220 Cm Unit 1.00 4,220,000.00 4,220,000.00 0.644
3 Tipe P2 Pintu kusen Alumunium uk. 80 x 220 Cm Unit 2.00 4,220,000.00 8,440,000.00 1.289
4 Tipe P3 Pintu kusen Alumunium uk. 70 x 220 Cm Unit 1.00 3,830,000.00 3,830,000.00 0.585
5 Tipe J1 Jendela Kaca Rangka Alumunium uk. 100 x 130 Cm Unit 1.00 4,220,000.00 4,220,000.00 0.644
6 Tipe GR.1 Bouwvenlight Rangka Alumunium uk. 280 x 115 Cm Unit 3.00 2,510,000.00 7,530,000.00 1.150
7 Tipe GR.2 Bouwvenlight Rangka Alumunium uk. 180 x 50 Cm Unit 2.00 1,410,000.00 2,820,000.00 0.431
8 Tipe GR.3 Bouwvenlight Rangka Alumunium uk. 280 x 50 Cm Unit 2.00 1,985,000.00 3,970,000.00 0.606
9 Tipe GR.4 Bouwvenlight Rangka Alumunium uk. 200 x 65 Cm Unit 1.00 1,691,000.00 1,691,000.00 0.258
10 Tipe GR.5 Bouwvenlight Rangka Alumunium uk. 80 x 65 Cm Unit 1.00 937,000.00 937,000.00 0.143

E.4 PEKERJAAN LANGIT- LANGIT


1 Gypsum Board t=9mm, Rangka Hollow 40x40mm t=0.35mm Galvanized + Gantungan M2 75.75 208,560.00 15,798,420.00 2.413
2 Plafond Gypsum Waterproof, t=12mm berikut Rangka Hollow Galvanised t=0.4mm M2 11.39 236,928.00 2,698,609.92 0.412
3 Acian Beton Expose M 1.00 62,001.00 62,001.00 0.009
4 Shadow Line Aluminium M 83.45 28,000.00 2,336,600.00 0.357

E.5 PEKERJAAN FINISHING LANTAI & DINDING


1 Lantai Keramik 40 x 40 cm Unpolished M2 5.09 365,143.00 1,858,577.87 0.284
2 Lantai Keramik area basah 25 x 25 cm Unpolished M2 14.30 349,917.00 5,003,813.10 0.764
3 Dinding Keramik Area Basah 25 x 40cm Tipe Polished M2 0.54 340,023.00 183,612.42 0.028

E.6 PEKERJAAN SANITAIR


TOILET TYPE 1
1 Closet duduk setara TOTO Type CW 421 J / SW420JP Unit 1.00 3,900,000.00 3,900,000.00 0.596
2 Wastafel setara TOTO tipe LW 236 CJ Unit 1.00 4,600,000.00 4,600,000.00 0.702
3 Floor drain setara TOTO Type TX 1 BN Unit 1.00 400,000.00 400,000.00 0.061
4 Paper holder setara. Toto tipe TX720ACRB Unit 1.00 400,000.00 400,000.00 0.061
5 Shower Spray THX 20 MCRB + TX277S Unit 1.00 400,000.00 400,000.00 0.061
6 Kitchen zink Unit 1.00 700,000.00 700,000.00 0.107
7 Kran zink Unit 1.00 400,000.00 400,000.00 0.061
8 Urnal setara TOTO tipe U 370 M Unit 1.00 4,500,000.00 4,500,000.00 0.687
9 Double Robe Hook TOTO Type TS 118 WS Unit 1.00 200,000.00 200,000.00 0.031
10 Kaca Cermin Unit 0.60 340,000.00 204,000.00 0.031
11 Cove lampu diatas Wastafel dari kayu kelas II finish cat M2 0.60 50,000.00 30,000.00 0.005
12 Meja Beton finishing keramik M 0.59 1,460,000.00 861,400.00 0.132

TOILET TYPE 2
1 Kran dinding setara TOTO tipe T23BQ13N Unit 1.00 575,000.00 575,000.00 0.088
2 Floor drain setara TOTO Type TX 1 BN Unit 1.00 400,000.00 400,000.00 0.061

E.7 PEKERJAAN PENGECATAN


1 Pengecatan Dinding Interior Jenis Cat Acrylic Emulsion M2 206.92 26,873.00 5,560,561.16 0.849
2 Pengecatan Dinding Exterior Jenis Cat Weathershield M2 206.92 49,953.00 10,336,274.76 1.579
3 Pengecatan Plafond & Balok Beton Exposed Jenis Cat AEP M2 87.15 26,873.00 2,341,981.95 0.358

E.8 PEKERJAAN PENUTUP ATAP


1 Pekerjaan Rangka Atap Baja Ringan M2 96.39 302,002.00 29,109,972.78 4.446
2 Penutup Atap Metal Zincalume M2 97.58 447,385.00 43,655,828.30 6.667

JUMLAH 654,810,062.45 100.0


JADWAL PELAKSANAAN PEKERJAAN KURVA "S"
Paket Pekerjaan : PEMBANGUNAN SIRKUIT BALAP MOTOR
Lokasi : DISTRIK TANAH MIRING, KABUPATEN MERAUKE
Tahun : 2019
WAKTU PELAKSANAAN 210 HARI KALENDER
Bobot %
BULAN DESEMBER JANUARI FEBRUARI MARET APRIL MEI JUNI BULAN VIII
MINGGU KE : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
No. URAIAN KET
2 9 16 23
Renc Real
TANGGAL S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D
8 15 22 29 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr 7 hr

I PEKERJAAN PERSIAPAN 100


A PEKERJAAN PERSIAPAN UMUM 0.67 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
B PEKERJAAN MOBILISASI DAN DEMOBILISASI 0.11 0.04 0.04 0.04

II PEKERJAAN PEMBENTUKAN LAHAN (CUT & FILL) 9.06 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65
90
III PEKERJAAN STRUKTURAL
A GEDUNG TRIBUN 3.74 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22
B GEDUNG SEKRETARIAT (TIDAK TERMASUK LINGKUP) 1.28 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
C RUMAH JAGA 0.25 0.04 0.04 0.04 0.04 0.04 0.04
80
D TOILET 0.30 0.07 0.07 0.07 0.07
E BENGKEL (TIDAK TERMASUK LINGKUP) 0.33 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
F POS JAGA (3 UNIT) 0.06 0.02 0.02 0.02
G BANGUNAN GERBANG MASUK 0.12 0.03 0.03 0.03 0.03 0.03
70
IV PEKERJAAN ARSITEKTURAL
A GEDUNG TRIBUN 4.18 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42 0.42
B GEDUNG SEKRETARIAT (TIDAK TERMASUK LINGKUP) 1.44 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18
C RUMAH JAGA 0.74 0.25 0.25 0.25
D TOILET 0.50 0.25 0.25 60
E BENGKEL (TIDAK TERMASUK LINGKUP) 0.60 0.15 0.15 0.15 0.15
F POS JAGA (3 UNIT) 0.12 0.06 0.06
G BANGUNAN GERBANG MASUK 0.07 0.07
H LANDSCAPE 15.27 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09
50
V PEKERJAAN LANSEKAP
A PEKERJAAN HARDSCAPE 1.11 0.28 0.28 0.28 0.28

VI PEKERJAAN INFRASTRUKTUR
40
A PEKERJAAN DRAINASE 2.73 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19
B. PEKERJAAN JALAN 46.77 1.23 1.23 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46 2.46
C MARKA JALAN 7.97 1.99 1.99 1.99 1.19 0.80

VII PEKERJAAN ELEKTRIKAL 30


A PENYAMBUNGAN, DISTRIBUSI DAN PEMBANGKITAN DAYA 1.10 0.27 0.27 0.27 0.27
B PEKERJAAN INSTALASI PENERANGAN 0.53 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
C PEKERJAAN PENANGKAL PETIR 0.09 0.09
D PEKERJAAN SISTEM TELEPON 0.11 0.03 0.03 0.03 0.03
SISTEM TATA SUARA 20
E. 0.14 0.03 0.03 0.03 0.03
F SISTEM FIRE ALARM 0.08 0.02 0.02 0.02 0.02 0.02

VIII PEKERJAAN MEKANIKAL


A PEKERJAAN PLUMBING AIR BERSIH 0.10 0.02 0.02 0.02 0.02 0.02 0.02 10
B PEMIPAAN AIR BERSIH TOILET 0.01 0.01 0.01
C PEMIPAAN AIR KOTOR DAN BUANGAN TOILET 0.14 0.04 0.04 0.04 0.04
D PEMIPAAN AIR BERSIH KE AREA MOTOR CROSS 0.08 0.02 0.02 0.02 0.02 0.02
E PEKERJAAN SISTEM TATA UDARA 0.08 0.04 0.04
F BANGUNAN SEKERTARIAT 0.10 0.02 0.02 0.02 0.02 0

Bobot (%) 100 0.06 0.06 0.67 0.89 1.08 2.32 2.32 3.55 3.45 3.49 3.49 3.49 3.49 3.49 3.49 4.58 4.28 4.66 4.66 4.70 4.59 4.53 4.53 4.61 4.96 4.99 4.88 4.69 3.06 0.98
Rencana
Kumulatif (%) - 0.06 0.12 0.79 1.68 2.76 5.08 7.39 10.94 14.39 17.88 21.37 24.86 28.35 31.84 35.33 39.92 44.19 48.85 53.51 58.21 62.80 67.33 71.86 76.47 81.43 86.41 91.30 95.99 99.05 100
KEMAJUAN
PEKERJAAN Bobot (%) - #REF!
Realisasi
Kumulatif (%) - - #REF!
Deviasi Bobot (%) - 0.059 #REF!

KONTRAKTOR PELAKSANA
PT. BANGUN PERSADA PAPUA RAYA

JONI PASULE
Direktur
PEMERINTAH KABUPATEN MERAUKE
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BIDANG CIPTA KARYA

PEKERJAAN : PEMBANGUNAN SIRKUIT BALAP MOTOR PEKERJAAN : PENGAWASAN PEMBANGUNAN SIRKUIT BALAP MOTOR
KONTRAKTOR : PT. PEMBANGUNAN JAYA PAPUA RAYA KONSULTAN : PT. MAKROTHUMIA EIRENE CONSULTANT
NO. KONTRAK : 03/KONTRAK/DAK - K1/DPUPRP - BM/V/2018 NO. KONTRAK : 10/KONTRAK/DAU-PENG.DAK.1/DPUPRP - BM/V/2018
TGL MULAI KERJA : 02 DESEMBER 2019 TANGGAL KONTRAK : 2 DESEMBER 2019
LOKASI : DISTRIK TANAH MIRING SUMBER DANA : APBD
KABUPATEN : MERAUKE - PAPUA TAHUN ANGGARAN : 2019 - 2020

LAPORAN MINGGU KE - 1
PERIODE 2 DESEMBER S/D 8 DESEMBER
TAHUN 2019
PEKERJAAN : BENGKEL

BOBOT REALISASI KEMAJUAN FISIK


NILAI MINGGU LALU MINGGU INI S/D MINGGU INI PRESTASI
No. Uraian Pekerjaan Satuan Volume PROGRES
PEKERJAAN BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME
% % % % %

III PEKERJAAN STRUKTURAL


E. BENGKEL (TIDAK TERMASUK LINGKUP)
E.1 PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bouwplank M 48.00 0.6880 - - - - - - -

E.2 PEKERJAAN TANAH DAN PASIR


1 Galian Tanah Pondasi M3 16.11 0.3745 - - - - - - -
2 Urugan Tanah Kembali Galian Pondasi M3 5.37 0.0416 - - - - - - -
3 Urugan Pasir Bawah Pondasi tebal 10 cm M3 1.79 0.2402 - - - - - - -

E.3 PEKERJAAN STRUKTUR LANTAI 1


1 Pek. Cor lantai kerja 1pc 6psr
˗ Beton campuran 1pc 6psr M3 1.79 0.7951 - - - - - - -
˗ Begesting Kayu Kls III M2 8.10 0.3064 - - - - - - -
2 Pekerjaan Pondasi Telapak 100x100x30 cm (F1)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 3.00 1.6000 - - - - - - -
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 344.24 1.0702 - - - - - - -
˗ Bekisting untuk Pondasi M2 2.40 0.0908 - - - - - - -
3 Pekerjaan Pondasi Telapak 60x60x30 cm (F2)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 0.97 0.5173 - - - - - - -
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 146.28 0.4548 - - - - - - -
˗ Bekisting untuk Pondasi M2 1.30 0.0492 - - - - - - -
4 Pekerjaan Pondasi Telapak 102.5x60x30 cm (F3)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 0.55 0.2933 - - - - - - -
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 71.80 0.2232 - - - - - - -
˗ Bekisting untuk Pondasi M2 0.59 0.0223 - - - - - - -
5 Pekerjaan Pondasi Telapak 140x100x30 cm (F4)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 0.28 0.1493 - - - - - - -
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 95.42 0.2966 - - - - - - -
˗ Bekisting untuk Pondasi M2 0.58 0.0219 - - - - - - -
6 Pek. Kolom Pedestal K-1, uk. 20 x 30 cm
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 0.80 0.4267 - - - - - - -
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 792.23 2.4629 - - - - - - -
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 145.31 0.4517 - - - - - - -
˗ Bekisting untuk kolom M2 2.65 0.1699 - - - - - - -
7 Pek. Kolom Pedestal K-2, uk. 11 x 11 cm
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 0.20 0.1067 - - - - - - -
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 487.53 1.5157 - - - - - - -
˗ Pembesian Besi polos/ulir . 8 mm SNI Kg 25.52 0.0793 - - - - - - -
˗ Bekisting untuk kolom M2 1.44 0.0923 - - - - - - -
8 Pekerjaan Sloof uk. 15x30 cm (TB1a)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 2.61 1.3920 - - - - - - -
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 122.56 0.3810 - - - - - - -
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 238.28 0.7408 - - - - - - -
˗ Bekisting untuk sloof M2 10.87 0.4112 - - - - - - -
9 Pekerjaan Sloof uk. 11x30 cm (TB2a)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 1.37 0.7307 - - - - - - -
˗ Pembesian Besi polos/ulir . 13 mm SNI Kg 131.01 0.4073 - - - - - - -
˗ Pembesian Besi polos/ulir . 8 mm SNI Kg 109.56 0.3406 - - - - - - -
˗ Bekisting untuk sloof M2 7.39 0.2795 - - - - - - -
10 Pek. Kolom K1 , uk. 20 x 30 cm
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 2.93 1.5627 - - - - - - -
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 1,778.55 5.5292 - - - - - - -
˗ Bekisting untuk kolom M2 9.75 0.6252 - - - - - - -
11 Pek. Kolom , uk. 11 x 11 cm
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 0.59 0.3147 - - - - - - -
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 786.87 2.4463 - - - - - - -
˗ Pembesian Besi polos/ulir . 8 mm SNI Kg 29.23 0.0909 - - - - - - -
˗ Bekisting untuk kolom M2 4.29 0.2751 - - - - - - -
12 Pekerjaan Ringbalk uk. 15x30 cm (RB1a)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 2.61 1.3920 - - - - - - -
˗ Pembesian Besi polos/ulir . 12 mm SNI Kg 104.43 0.3247 - - - - - - -
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 238.28 0.7408 - - - - - - -
˗ Bekisting untuk ringbalk M2 4.29 0.2788 - - - - - - -
13 Pekerjaan Ringbalk uk. 11x30 cm (RB2)
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 1.95 1.0400 - - - - - - -
˗ Pembesian Besi polos/ulir . 12 mm SNI Kg 121.31 0.3771 - - - - - - -
˗ Pembesian Besi polos/ulir . 10 mm SNI Kg 242.80 0.7548 - - - - - - -
˗ Bekisting untuk ringbalk M2 10.49 0.6818 - - - - - - -
14 Pek. Plat talang beton, tebal. 11 cm
˗ Campuran beton 1PC 2PS 3KR, Import (mekanis) M3 1.29 0.6880 - - - - - - -
˗ Pembesian Besi polos/ulir . 8 mm SNI Kg 178.14 0.5538 - - - - - - -
˗ Bekisting Kayu Kelas III M2 11.76 0.4449 - - - - - - -
IV PEKERJAAN ARSITEKTURAL
E BENGKEL (TIDAK TERMASUK LINGKUP)
E.1 PEKERJAAN TANAH DAN PASIR
1 Urugan Pasir Bawah Lantai tebal 10 cm M3 13.96 1.8734 - - - - - - -
2 Urugan Tanah Peninggian Lantai M3 55.85 2.4055 - - - - - - -

E.2 PEKERJAAN PASANGAN DINDING


1 Pasangan Dinding Bata merah Tebal 1/2 Bata, 1PC 4PS - Pasir Import M2 206.92 10.4181 - - - - - - -
2 Plesteran 1PC 3PS, Tebal 20 mm - Pasir Import M2 413.84 11.0547 - - - - - - -
3 Pekerjaan Acian M2 413.84 3.9185 - - - - - - -
4 Cor lantai ruangan tebal 5 cm, 1 pc 3psr M3 5.02 3.1314 - - - - - - -
5 Cor lantai rabat tebal 5 cm, 1 pc 3psr + aci kasar M3 1.07 0.6674 - - - - - - -

E.3 PEKERJAAN KUSEN,PINTU/JENDELA TERMASUK FINISHING & ACCESSORIES


1 Tipe Pintu Polding get.1 uk. 280 x 220 Cm Unit 2.00 4.5876 - - - - - - -
2 Tipe P1 Pintu kusen Alumunium uk. 80 x 220 Cm Unit 1.00 0.6445 - - - - - - -
3 Tipe P2 Pintu kusen Alumunium uk. 80 x 220 Cm Unit 2.00 1.2889 - - - - - - -
4 Tipe P3 Pintu kusen Alumunium uk. 70 x 220 Cm Unit 1.00 0.5849 - - - - - - -
5 Tipe J1 Jendela Kaca Rangka Alumunium uk. 100 x 130 Cm Unit 1.00 0.6445 - - - - - - -
6 Tipe GR.1 Bouwvenlight Rangka Alumunium uk. 280 x 115 Cm Unit 3.00 1.1500 - - - - - - -
7 Tipe GR.2 Bouwvenlight Rangka Alumunium uk. 180 x 50 Cm Unit 2.00 0.4307 - - - - - - -
8 Tipe GR.3 Bouwvenlight Rangka Alumunium uk. 280 x 50 Cm Unit 2.00 0.6063 - - - - - - -
9 Tipe GR.4 Bouwvenlight Rangka Alumunium uk. 200 x 65 Cm Unit 1.00 0.2582 - - - - - - -
10 Tipe GR.5 Bouwvenlight Rangka Alumunium uk. 80 x 65 Cm Unit 1.00 0.1431 - - - - - - -

E.4 PEKERJAAN LANGIT- LANGIT


1 Gypsum Board t=9mm, Rangka Hollow 40x40mm t=0.35mm Galvanized + Gantungan M2 75.75 2.4127 - - - - - - -
2 Plafond Gypsum Waterproof, t=12mm berikut Rangka Hollow Galvanised t=0.4mm M2 11.39 0.4121 - - - - - - -
3 Acian Beton Expose M 1.00 0.0095 - - - - - - -
4 Shadow Line Aluminium M 83.45 0.3568 - - - - - - -

E.5 PEKERJAAN FINISHING LANTAI & DINDING


1 Lantai Keramik 40 x 40 cm Unpolished M2 5.09 0.2838 - - - - - - -
2 Lantai Keramik area basah 25 x 25 cm Unpolished M2 14.30 0.7642 - - - - - - -
3 Dinding Keramik Area Basah 25 x 40cm Tipe Polished M2 0.54 0.0280 - - - - - - -

E.6 PEKERJAAN SANITAIR


TOILET TYPE 1
1 Closet duduk setara TOTO Type CW 421 J / SW420JP Unit 1.00 0.5956 - - - - - - -
2 Wastafel setara TOTO tipe LW 236 CJ Unit 1.00 0.7025 - - - - - - -
3 Floor drain setara TOTO Type TX 1 BN Unit 1.00 0.0611 - - - - - - -
4 Paper holder setara. Toto tipe TX720ACRB Unit 1.00 0.0611 - - - - - - -
5 Shower Spray THX 20 MCRB + TX277S Unit 1.00 0.0611 - - - - - - -
6 Kitchen zink Unit 1.00 0.1069 - - - - - - -
7 Kran zink Unit 1.00 0.0611 - - - - - - -
8 Urnal setara TOTO tipe U 370 M Unit 1.00 0.6872 - - - - - - -
9 Double Robe Hook TOTO Type TS 118 WS Unit 1.00 0.0305 - - - - - - -
10 Kaca Cermin Unit 0.60 0.0312 - - - - - - -
11 Cove lampu diatas Wastafel dari kayu kelas II finish cat M2 0.60 0.0046 - - - - - - -
12 Meja Beton finishing keramik M 0.59 0.1315 - - - - - - -

TOILET TYPE 2
1 Kran dinding setara TOTO tipe T23BQ13N Unit 1.00 0.0878 - - - - - - -
2 Floor drain setara TOTO Type TX 1 BN Unit 1.00 0.0611 - - - - - - -

E.7 PEKERJAAN PENGECATAN


1 Pengecatan Dinding Interior Jenis Cat Acrylic Emulsion M2 206.92 0.8492 - - - - - - -
2 Pengecatan Dinding Exterior Jenis Cat Weathershield M2 206.92 1.5785 - - - - - - -
3 Pengecatan Plafond & Balok Beton Exposed Jenis Cat AEP M2 87.15 0.3577 - - - - - - -

E.8 PEKERJAAN PENUTUP ATAP


1 Pekerjaan Rangka Atap Baja Ringan M2 96.39 4.4456 - - - - - - -
2 Penutup Atap Metal Zincalume M2 97.58 6.6669 - - - - - - -

JUMLAH 100.0 0.000 0.000 0.000

RENCANA = 0.059 %
REALISASI = 0.000 %
DEVIASI = -0.059 %

MENGETAHUI: DISETUJUI OLEH : DIPERIKSA OLEH DIBUAT OLEH


PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK) DIREKSI TEKNIS LAPANGAN KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA
PEMBANGUNAN SIRKUIT BALAP MOTOR PEMBANGUNAN SIRKUIT BALAP MOTOR PT. MAKROTHUMIA EIRENE CONSULTANT PT. BANGUN PERSADA PAPUA RAYA

LEO PATRIA MOGOT,ST U S M A N ,A . Md WAYAN DARYASA, ST. YANI SALEA BATU, ST.
NIP. 19730628 200605 1 002 NIP. 19610110 200012 1 002 Team Leader Sita Manager