JADWAL PELAKSANAAN

TOLLROAD MAINTENANCE

Pekerjaan : Jasa Pemborongan Pekerjaan Dinding Penahan Tanah KM 431+200 - 431+550 B


Nomor Kontrak : 43/KONTRAK-SMG/GM/VII/2022
Tanggal Kontrak : 18-Jul-22
Nomor SPMK : 199/GM.OPS2/EXT/JMTM/VII/2022 Minggu ke : 13 (Tiga Belas)
Tanggal SPMK : 18 Juli 2022 Periode : 10 Oktober s.d 15 Oktober 2022
KONTRAK AWAL ADDENDUM-01 WAKTU PELAKSANAAN PEKERJAAN 90 HARI KALENDER

JULI AGUSTUS SEPTEMBER OKTOBER


NO. MATA SATUAN KUANTITAS JUMLAH HARGA BOBOT DURASI SISA 1 2 3 4 5 6 7 8 9 10 11 12 13
URAIAN PEKERJAAN HARGA SATUAN JUMLAH HARGA (ADD-1) KUANTITAS (ADD- BOBOT (ADD-1) DURASI KETERANGAN
PEMBAYARAN (KONTRAK (KONTRAK) (KONTRAK AWAL) (MINGGU KE-8)
6.a 6.b
(Rp) (Rp) 1) (%)
AWAL) (Rp) (%) 18-Jul 25-Jul 01-Aug 08-Aug 15-Aug 22-Aug 26-Aug 29-Aug 05-Sep 12-Sep 19-Sep 26-Sep 03-Oct 10-Oct
s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d
24-Jul 31-Jul 07-Aug 14-Aug 21-Aug 25-Aug 28-Aug 04-Sep 11-Sep 18-Sep 25-Sep 02-Oct 09-Oct 15-Oct

100,000
SPESIFIKASI KHUSUS 68,977,800.00 2.481 68,977,800.00 2.481

SK. 1.02(2) Pengamanan dan Pengaturan Lalu Lintas, Tipe B Hr 90.00 766,420.00 68,977,800.00 2.481 68,977,800.00 90.00 2.481 3 13 0.191 0.191 0.191 0.191 0.191 0.191 0.191 0.191 0.191 0.191 0.184 0.184 0.184
LEGENDA
0.193 0.193 0.193 0.193 0.193 0.193 0.193 0.193 0.193 0.193

BAB I UMUM 19,800,000.00 0.712 19,800,000.00 0.712


Rencana
1.35 As Built Drawing ls 1.00 4,400,000.000 4,400,000.00 0.158 4,400,000.00 1.00 0.158 1 1 0.158

Realisasi
1.20 (2) Mobilisasi dan Demobilsasi ls 1.00 15,400,000.000 15,400,000.00 0.554 15,400,000.00 1.00 0.554 1 3 0.258 0.258 0.277

0.006 0.011 0.122 0.055 0.028 0.028 0.028


Rencana Item Baru
BAB 2 PEKERJAAN PEMBERSIHAN TEMPAT KERJA 26,408,250.00 0.950 29,721,720.22 1.069

2. 01 Pembersihan Tempat Kerja m2 3,025.00 8,730.000 26,408,250.00 0.950 29,721,720.22 3,404.55 1.069 0 2 0.285 0.665

0.003 0.387 0.026 0.203 0.243 0.086

BAB 3 PEMBONGKARAN 33,045,384.00 1.189

2. 01 Bongkaran Batu Kali (Stone Masonry) m3 916,400.000 33,045,384.00 36.06 1.189 2 2 0.357 0.832

BAB 4 PEKERJAAN TANAH 143,220,000.00 5.151 166,292,295.71 5.981

.4. 01 Galian Biasa Untuk Di Buang m3 2,557.50 56,000.000 143,220,000.00 5.151 127,490,477.38 2,276.62 4.585 0 5 1.803 0.773 0.773 1.545 0.258

0.129 0.037 0.619 0.814 0.350 2.397

4.03 (3) Galian Tanah Keras untuk Dibuang m3 563,930.000 38,801,818.33 68.81 1.396 3 3 0.465 0.465 0.465
50,000
Grafik Rencana Kontrak
BAB 6 DRAINASE 81,200,286.00 2.920 151,775,057.11 5.459
Grafik Realisasi Kontrak
6.05 (1) Buis U Beton Ø 30 cm M 383.40 211,790.000 81,200,286.00 2.920 151,775,057.11 716.63 5.459 2 4 0.730 0.876 2.618 2.618

0.224 Grafik Rencana ADD-01

BAB 7 SUBGRADE 24,714,250.00 0.889 10,870,726.52 0.391 Grafik Realisasi ADD-01


7.05 (1) Pemadatan Tanah Dengan Stamper M2 3,025.00 8,170.000 24,714,250.00 0.889 10,870,726.52 1,330.57 0.391 0 6 0.207 0.030 0.030 0.207 0.207
0.207
0.010 0.017 0.068 0.066 0.046 0.086 0.060

BAB 10 BETON 35,466,915.00 1.276 84,489,812.52 3.039

10.01 (13) Beton Kelas E M3 30.25 1,172,460.000 35,466,915.00 1.276 84,489,812.52 72.06 3.039 1 3 0.765 0.425 3.039

BAB 12 PEKERJAAN LAIN-LAIN 2,380,623,300.00 85.621 2,215,424,471.44 79.680

12.02 (3) Pasangan Batu Kali (Stone Masonry) M3 2,557.50 930,840.000 2,380,623,300.00 85.621 1,781,890,121.44 1,914.28 64.088 3 9 3.211 5.886 11.773 12.843 12.843 21.405 0.410 0.410 0.717

1.265 3.187 8.243 9.893 9.795 10.895 19.669

12.01 (5.a) Penebangan dan Pembuangan Pohon Diameter 15-30 cm bh 567,810.000 5,678,100.00 10.00 0.204 3 3 0.068 0.068 0.068

13.01 Pekerjaan Dinding Bata Ringan , Include Lee Kwan Yew m' 1,140,950.000 427,856,250.00 375.00 15.388 3 3 5.129 5.129 5.129
0,000
Jumlah 2,780,410,801.00 100.000 2,780,397,267.52 100.000

Jumlah Dibulatkan 2,780,410,800.00 2,780,397,200.00

Bobot Rencana Mingguan Kontrak (%) 0.191 0.449 0.734 3.631 4.629 3.931 2.948 13.716 14.229 14.118 21.596 11.770 4.910 3.147

Bobot Kumulatif Kontrak (%) - 0.191 0.640 1.374 5.006 9.635 13.566 16.514 30.231 44.460 58.578 80.174 91.943 96.853 100.000

Bobot Realisasi Mingguan Kontrak (%) 0.198 0.193 0.207 2.106 3.490 8.812 0.365 11.197 10.628 13.657 20.173
KONTRAK AWAL
Bobot Kumulatif Kontrak (%) - 0.198 0.391 0.599 2.705 6.194 15.006 15.372 26.568 37.196 50.853 71.026

Bobot Deviasi Mingguan Kontrak (% ) 0.008 - 0.256 - 0.527 - 1.525 - 1.140 4.880 - 2.583 - 2.520 - 3.601 - 0.460 - 1.423

Bobot Kumulatif Kontrak (%) 0.008 - 0.249 - 0.776 - 2.301 - 3.440 1.440 - 1.143 - 3.663 - 7.264 - 7.724 - 9.147

Bobot Rencana Mingguan ADD-1 (%) 71.026 9.231 9.706 10.038

Bobot Kumulatif ADD-1 (%) 71.026 80.257 89.963 100.000

Bobot Realisasi Mingguan ADD-1 (%) 71.026 5.287 1.639 3.184


ADDENDUM-01
Bobot Kumulatif ADD-1 (%) 71.026 76.313 77.952 81.136

Bobot Deviasi Mingguan ADD-1 (% ) - - 3.943 - 8.067 - 6.853

Bobot Kumulatif ADD-1 (%) - - 3.943 - 12.011 - 18.864

1/4 WAKTU 1/2 WAKTU 3/4 WAKTU


Pemberi Tugas Diperiksa Oleh Dibuat Oleh
PT JASA MARGA TOLLROAD MAINTENANCE Konsultan Pengawas Kontraktor
Area Palikanci-Semarang PT ADHY DUTA PRIMA PT AMBER HASYA

NINIK SURYAWATI AJI PRIO CAROKO, ST RANTO SANDIWIADJI


SUPERVISOR CI/QUANTITY ENGINEER GENERAL SUPERINDENT