ACTION PLAN SISA WAKTU PELAKSANAAN PENGGANTIAN JEMBATAN RUAS JALAN NANGA ELLA - MENUKUNG

PERIODE TGL. 13 NOPEMBER S/D 15 DESEMBER 2019

HARI MINGGU
JANGKA WAKTU RENCANA 33.00 4.00

ACTION PLAN
BOBOT BOBOT PROGRES VOLUME PROGRES VOLUME SISA PROGRES
DESEMBER
SATUAN

VOLUME KONTRAK JUMLAH HARGA (RP)


(%) (%) HARGA SATUAN RENCANA MC. REALISASI RENCANA NILAI
NO. URAIAN PEKERJAAN KETERANGAN
(Rp) (%) MINGGU -2 MINGGU -3 MINGGU -4 MINGGU -1 MINGGU 2
KEBUTUHAN ALAT / KAPASITAS PRODUKSI
WAKTU / HARI
K. AWAL AMD.01 KONTRAK AMANDEMEN BOBOT BOBOT PEKERJA
KONTRAK AWAL AMANDEMEN-01 VOLUME VOLUME BOBOT (%) VOLUME 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
AWAL -01 (%) (%) (disesuaikan)

URAIAN PEKERJAAN 100.00 100.00 3,122,167,798.00 3,334,090,290.06 100.00 - 100.00

3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 2.138 4.034 578.00 1,164.66 115,493.00 66,754,954.00 134,510,077.38 1,164.66 4.03 - - 1,164.66 4.03 5.00 1.00 Motor Grader 39.60 M3/Jam 0.81 0.81 0.81 0.81 0.81

7.1.(10) Beton, fc" 10 Mpa M3 4.571 4.281 105.00 105.00 1,359,248.00 142,721,040.00 142,721,040.00 105.00 4.28 - - 105.00 4.28 5.00 4.00 Cocrete Mixer 0.90 M3/Jam 0.86 0.86 0.86 0.86 0.86

a). Rangka Panel (Bailley) Bantang 21 m Kg 34.469 32.278 33,113.00 33,113.00 32,500.00 1,076,172,500.00 1,076,172,500.00 33,113.00 32.28 - - 33,113.00 32.28 15.00 1.00 Tronton 456.88 Kg/Jam 2.15 2.15 2.15 2.15 2.15 2.15 2.15 2.15 2.15 2.15 2.15 2.15 2.15 2.15 2.15
Penyediaan Struktur Jembatan
7.4.(3)
Rangka Baja Standar
b). Rangka Panel (Bailley) Bantang 30 m Kg 48.295 45.225 46,395.00 46,395.00 32,500.00 1,507,837,500.00 1,507,837,500.00 46,395.00 45.22 46,395.00 45.22 19.00 1.00 Tronton 456.88 Kg/Jam 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38

7.6.(1) Pemasangan Struktur Jembatan Rangka Panel (Bailley) Kg 7.640 7.154 79,508.00 79,508.00 3,000.00 238,524,000.00 238,524,000.00 79,508.00 7.15 - - 79,508.00 7.15 10.00 20.00 Orang 435.00 Kg/Hr/Org 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72

7.6.(1) Pondasi Cerucuk , Penyediaan dan Pemancangan M' 0.205 0.192 692.00 692.00 9,245.00 6,397,540.00 6,397,540.00 692.00 0.19 - - 692.00 0.19 6.00 8.00 Orang 15.00 M'/Hr/Org 0.03 0.03 0.03 0.03 0.03 0.03

7.9.(1) Pasangan Batu M3 2.683 6.836 84.00 228.58 997,146.00 83,760,264.00 227,927,632.68 228.58 6.84 - - 228.58 6.84 19.00 15.00 Orang 0.82 M3/Hr/Org 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36

JUMLAH HARGA KONTRAK/AMD. 01 100.00 100.00 3,122,167,798.00 3,334,090,290.06 100.00 - 100.00 Pekerja 43.00 Orang / Hari 4.56 4.56 4.56 4.56 4.92 4.92 4.89 4.89 4.89 4.89 4.89 4.89 4.89 4.89 4.89 2.74 2.74 3.55 3.55 1.88 1.88 1.88 1.93 1.57 1.57 1.57 1.57 0.72 0.72 - - -

1.00 Unit / hari 4.56 9.13 13.69 18.26 23.18 28.10 33.00 37.89 42.78 47.67 52.56 57.46 62.35 67.24 72.13 74.87 77.61 81.16 84.71 86.59 88.47 90.35 92.28 93.85 95.43 97.00 98.57 99.28 100.00 100.00 100.00 100.00
Motor Grader
Tronton 2.00 Unit / hari

Concrete Mixer 4.00 Unit / hari

ACTION (Rp) REALISASI (Rp) SISA (Rp)

NILAI (Rp) 3,334,090,290.06 - 3,334,090,290.06

RENCANA PENYERAPAN ANGGARAN PERHARI 101,033,039.00 Seratus Satu Juta Tiga Puluh Tiga Ribu Tiga Puluh Sembilan Rupiah

Nanga Ella, 12 Nopember 2019


Dibuat Oleh :
Penyedia Jasa

CV. TIPSANI

RAHMAN ARIF, ST
Kepala Pelaksana