RENCANA ANGGARAN BIAYA

PEMBANGUNAN RUMAH TINGGAL 1 LANTAI


POTORONO, BANTUL, D.I. YOGYAKARTA

No. ITEM PEKERJAAN HARGA TOTAL


A. PEKERJAAN PERSIAPAN Rp 2,682,646.00
B. PEKERJAAN FONDASI BATU KALI Rp 11,839,464.36
C. PEKERJAAN STRUKTUR BETON BERTULANG Rp 24,833,072.95
D. PEKERJAAN TANAH Rp 4,337,877.31
E. PEKERJAAN PASANGAN & PLESTERAN Rp 26,855,818.88
F. PEKERJAAN LANTAI Rp 12,812,177.35
G. PEKERJAAN PLAFOND Rp 5,454,704.40
H. PEKERJAAN KUSEN, DAUN PINTU, DAN JENDELA BESERTA AKSESORIS Rp 22,418,327.34
I. PEKERJAAN SANITASI Rp 3,422,500.00
J. PEKERJAAN PLUMBING Rp 21,028,667.06
K. PEKERJAAN MEKANIKAL ELEKTRIKAL Rp 11,072,143.17
L. PEKERJAAN ATAP Rp 11,415,828.14
M. PEKERJAAN PENGECATAN Rp 15,574,514.55
N. PEKERJAAN LAIN-LAIN Rp 2,405,697.22
TOTAL = Rp 176,153,438.74
DIBLUATKAN = Rp 176,153,500.00
#NAME?
RENCANA ANGGARAN BIAYA
PEMBANGUNAN RUMAH TINGGAL 1 LANTAI
POTORONO, BANTUL, D.I. YOGYAKARTA

HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME
SATUAN TOTAL
A. PEKERJAAN PERSIAPAN 2,682,646.00
1 Pengukuran Dan Pemasangan Bouwplank m¹ 34.00 73,019.00 2,482,646.00
2 Pembuatan Gudang Semen dan Alat-alat LS -
3 Pembuatan Bedeng Buruh sederhana LS -
4 Listrik kerja bln 1.00 200,000.00 200,000.00

B. PEKERJAAN FONDASI BATU KALI 11,839,464.36


1 FONDASI UTUH
Pasangan Batu Kali 1Pc : 5 Ps m³ 7.71 766,060.00 5,905,173.51
Besi Angkur P10 kg 7.71 13,554.00 104,481.01
2 FONDASI TEPI
Pasangan Batu Kali 1Pc : 5 Ps m³ 7.29 766,060.00 5,584,577.40
Besi Angkur P10 kg 12.09 13,554.00 163,822.68
3 FONDASI ROLLAG
Pasangan batu bata m² 0.57 143,770.00 81,409.76

C. PEKERJAAN STRUKTUR BETON BERTULANG 24,833,072.95


1 SLOOF S1 m³ 1.86 3,292,488.00 6,114,150.22
2 KOLOM KP m³ 1.42 3,254,770.00 4,613,636.48
3 BALOK LATEI BL m³ 0.46 3,265,140.00 1,515,229.03
4 RINGBALOK RB1 m³ 2.79 3,075,772.00 8,590,631.20
5 DAK DEPAN m³ 0.59 2,445,121.00 1,430,395.79
6 DAK DEPAN 1 m³ 0.06 2,983,311.00 190,186.08
7 DAK BELAKANG m³ 0.11 1,813,265.00 205,352.26
8 TALANG SAMPING m³ 0.25 2,089,040.00 511,814.80
9 TALANG SAMPING 1 m³ 0.30 2,089,040.00 618,878.10
10 TALANG BELAKANG m³ 0.51 1,813,265.00 927,213.06
11 TOPI - TOPI DEPAN m³ 0.04 3,265,140.00 115,585.96

D. PEKERJAAN TANAH 4,337,877.31


1 Galian m³ 24.28 68,123.00 1,654,252.95
2 Urugan Kembali m³ 8.40 23,232.00 195,148.80
3 Pemadatan Tanah m³ 24.28 60,500.00 1,469,141.16
4 Pasir Urug m³ 3.90 261,100.00 1,019,334.40

E. PEKERJAAN PASANGAN & PLESTERAN 26,855,818.88


1 Pasangan Bata Bata Merah 1Pc:5Ps m² 131.54 143,770.00 18,911,937.11
2 Plesteran 1Pc:4Ps 15 mm m² 144.70 54,900.00 7,943,881.77

F. PEKERJAAN LANTAI 12,812,177.35


1 Keramik 40x40 ex. Lokal m² 35.00 255,667.00 8,948,345.00
2 Keramik Teras dan Trap 40x40 ex. Lokal m² 0.00 253,060.00 -
3 Keramik WC dan R.Jemur 20x20 ex. Lokal m² 1.72 255,096.00 438,765.12
4 Keramik dinding WC 20x40 ex. Roman/Setara m² 6.00 252,096.00 1,512,576.00
5 Meja dapur 20x20 ex. Lokal m² 0.93 273,994.00 253,444.45
6 Dinding Meja dapur 20x40 ex. Roman/Setara m² 1.88 117,994.00 221,828.72
7 Listello WC dan R.Jemur 10x20 ex. Lokal m² 4.53 193,751.00 877,692.03
8 Listello meja dapur 10x20 ex. Lokal m² 2.35 193,751.00 455,314.85
9 Spesi 1Pc:3Ps m³ 1.90 54,900.00 104,211.18
10
11
12
G. PEKERJAAN PLAFOND 5,454,704.40
1 Pekerjaan Rangka Plafond Hollow + Gypsum Board 9 mm m² 31.24 108,478.00 3,388,852.72
2 Pekerjaan List Plafond Gypsum m¹ 39.10 29,089.00 1,137,379.90
3 Pekerjaan Rangka Plafond Hollow + GRC m² 4.92 102,984.00 506,681.28
4 Pekerjaan List Plafond GRC m¹ 14.50 29,089.00 421,790.50

H. PEKERJAAN KUSEN, DAUN PINTU, DAN JENDELA BESERTA AKSESORIS 22,418,327.34


1 Pintu Utama 1 , Bikin+Pasang bh 3.00 4,101,983.83 12,305,951.49
Kusen Alumunium m¹ 11.90 97,714.00 1,162,796.60
Daun pintu plywood rangkap m² 2.70 705,356.00 1,904,461.20
Daun jendela m² 0.65 509,476.00 333,095.41
Kaca 5 mm m² 1.25 161,240.00 201,630.62
Aksesoris ls 1.00 500,000.00 500,000.00

2 Pintu Utama 2 , Bikin+Pasang bh 0.00 - -


Kusen Alumunium m¹ 0.00 97,714.00 -
Daun pintu plywood rangkap m² 0.00 705,356.00 -
Aksesoris ls 0.00 500,000.00 -

3 Pintu 1 , Bikin+Pasang bh 3.00 2,185,999.12 6,557,997.35


Kusen Alumunium m¹ 5.12 97,714.00 500,295.68
Daun pintu plywood rangkap m² 1.68 705,356.00 1,185,703.44
Aksesoris ls 1.00 500,000.00 500,000.00

4 Pintu 2 , Bikin+Pasang ( PVC ) bh 1.00 210,000.00 210,000.00

5 Jendela 1 , Bikin+Pasang bh 2.00 690,620.57 1,381,241.13


Kusen Alumunium m¹ 5.00 97,714.00 488,570.00
Daun jendela m² 0.30 509,476.00 154,065.54
Kaca 5 mm m² 0.30 161,240.00 47,985.02
Aksesoris ls 1.00 400,000.00 400,000.00

6 Jendela 2 , Bikin+Pasang bh 1.00 1,193,106.47 1,193,106.47


Kusen Alumunium m¹ 7.76 97,714.00 758,260.64
Daun jendela m² 0.53 509,476.00 268,188.17
Kaca 5 mm m² 1.03 161,240.00 166,657.66
Aksesoris ls 1.00 400,000.00 400,000.00

7 Bovenlight BV, Bikin+Pasang bh 1.00 210,223.28 210,223.28


Kusen Alumunium m¹ 1.96 97,714.00 191,519.44
Kaca 5 mm m² 0.12 161,240.00 18,703.84

8 Bovenlight BV1, Bikin+Pasang bh 1.00 559,807.62 559,807.62


Kusen Alumunium m² 5.70 97,714.00 556,969.80
Kaca 5 mm m² 0.02 161,240.00 2,837.82

I. PEKERJAAN SANITASI 3,422,500.00


Kloset Duduk ex. std/setara unit 1.00 1,960,000.00 1,960,000.00
Kitchen Zink Std unit 1.00 1,080,000.00 1,080,000.00
Shower Spray ex. std/setara unit 1.00 205,000.00 205,000.00
Tempat Sabun Keramik Putih 10x20 unit 1.00 60,000.00 60,000.00
Floor Drain plastik ex. Std/setara unit 1.00 5,000.00 5,000.00
Kran dinding 1/2" ex. Onda/setara unit 1.00 80,000.00 80,000.00
Kran Leher Angsa 1/2" Std unit 1.00 32,500.00 32,500.00

J. PEKERJAAN PLUMBING 21,028,667.06


a Pompa Air Sumur Dangkal ex. Sanyo/setara unit 1.00 2,709,164.00 2,709,164.00
b Pipa Air Bersih ɸ 3/4 " AW ex. Wavin/setara m¹ 30.00 25,506.00 765,180.00
c Valva-valve & fitting pipa air bersih ls 1.00 500,000.00 500,000.00
d Pipa Air Hujan ɸ 3 " D ex. Wavin/setara m¹ 0.00 111,414.00 -
e Pipa Air Tinja ɸ 4 " D ex. Wavin/setara m¹ 10.50 120,231.00 1,262,425.50
f Pipa Air Kotor ɸ 3 " D ex. Wavin/setara m¹ 10.50 111,414.00 1,169,847.00
g Valva-valve & fitting pipa air bekas & kotor ls 1.00 500,000.00 500,000.00
h Tangki air stainless 1000 ltr ex. Penguin/setara unit 2.00 2,894,490.00 5,788,980.00
i Radar tangki unit 1.00 85,000.00 85,000.00

j Sumur Resapan Air Kotor bh 1.00


Galian m³ 2.59 68,123.00 176,562.14
Menurunkan Buis m¹ 3.50 62,420.00 218,470.00
Pasir Urug m³ 0.10 261,100.00 26,248.63
Ijug (tebal 10 cm) m² 1.01 43,548.00 43,779.22
Batu Koral m³ 0.10 280,250.00 28,173.80
Batu Kali m³ 0.25 766,060.00 192,531.88

k Sumur Resapan Air Tinja bh 1.00 -


Galian m³ 2.59 68,123.00 176,562.14
Menurunkan Buis m¹ 3.50 62,420.00 218,470.00
Pasir Urug m³ 0.10 261,100.00 26,248.63
Ijug (tebal 10 cm) m² 1.01 43,548.00 43,779.22
Batu Koral m³ 0.10 280,250.00 28,173.80
Batu Kali m³ 0.25 766,060.00 192,531.88

l Septictank bh 1.00 -
Pasangan Bata 1Pc:2Ps m² 25.61 143,770.00 3,682,467.27
Plesteran Trasraam 1Pc:2Pc m² 25.61 54,900.00 1,406,186.64
Acian dinding m² 25.61 39,550.00 1,013,017.88
Beton Cover Septictank 1Pc:2Ps:3Kr m³ 1.07 488,475.00 520,470.11
Penulangan P8 kg 16.51 13,554.00 223,790.09
Pipa hawa ɸ 1" m¹ 1.20 25,506.00 30,607.20

K. PEKERJAAN MEKANIKAL ELEKTRIKAL 11,072,143.17


1 Instalasi Penerangan dan Kotak Kontak
Kabel NYA 2x1x2.5 mm² dalam High Impact conduit dia. 20 mm
a Instalasi Listrik Lampu Ruangan titik 22.00 275,063.00 6,051,386.00
Lampu TL 40 W bh 7.00 62,779.00 439,453.00

b Instalasi Listrik Lampu Pilar titik 0.00 275,063.00 -


Lampu pilar bh 0.00 180,750.00 -

c Saklar Tunggal 1 gang ex. Panasonic/setara bh 2.00 47,000.00 94,000.00


d Saklar Ganda 1 gang ex. Panasonic/setara bh 4.00 49,750.00 199,000.00

e Instalasi Stop Kontak biasa titik 4.00 304,986.00 1,219,944.00


Stop Kontak with CP ex. Panasonic/setara bh 4.00 47,889.00 191,556.00

f Panel Switch Lantai1 Box MCB Inbow c/w : unit 1.00


- Box switch MCB isi 4 MCB bh 1.00 350,000.00 350,000.00
- MCB 6A/4.5 KA/ 1P bh 1.00 216,000.00 216,000.00
- Perlengkapan penunjang ls 1.00 100,000.00 100,000.00
- Pekerja ls 1.00 200,000.00 200,000.00

g Instalasi Listrik Pompa Air titik 1.00 251,874.00 251,874.00


Sparring kabel NYM 3x2.5 m¹ 1.00 15,488.55 15,488.55

h Instalasi Listrik dari PLN (Kabel NYY 3x6 mm) m¹ 3.00 17,813.88 53,441.63

2 Distribusi Listrik
Pengadaan Sambungan Daya PLN
a Pengadaan/Pasang baru Daya PLN TR 3 phase
- Biaya penyambungan kVa 1.30 800,000.00 1,040,000.00
- Uang jaminan langganan kVa 1.30 250,000.00 325,000.00
- Biaya administrasi kVa 1.30 250,000.00 325,000.00

L. PEKERJAAN ATAP 11,415,828.14


a Rangka Atap baja Ringan m² 39.04 150,000.00 5,855,625.00
b Alumunium Foil Single side m² 42.94 52,400.00 2,250,121.50
c Genteng beton ex. Lokal m² 40.99 11,640.00 477,116.33
d Nok Genteng Keramik ex. KIA setara m¹ 23.70 11,640.00 275,868.00
e Papan Listplank GRC m¹ 25.76 68,860.00 1,773,833.60
f Papan Tritisan GRC m² 7.73 101,354.00 783,263.71

M. PEKERJAAN PENGECATAN 15,574,514.55


1 Pengecatan Dinding Interior ex. Catylac m² 137.74 35,828.00 4,935,038.29
2 Pengecatan Dinding exterior + pagar ex. Catylac m² 120.00 40,828.00 4,899,360.00
3 Pengecatan Dinding exterior warna gelap ex. Catylac m² 0.00 -
4 Pengecatan Plafond ex. Catylac m² 39.78 93,369.00 3,713,845.34
5 Pengecatan Lis Profil Plafond m¹ 53.60 15,770.00 845,272.00
6 Coating batu alam m² 2.46 68,902.00 169,498.92
7 Cat Pintu & Jendela
a Pintu Utama 1 , Bikin+Pasang bh 1.00 1,011,500.00 1,011,500.00
b Pintu Utama 2 , Bikin+Pasang bh 0.00 - -
N. PEKERJAAN LAIN-LAIN 2,405,697.22
1 Waterproofing Cement based ex. Aquagard/setara
a Dak+Talang m² 14.66 59,284.00 869,392.45

2 Pasangan Batu Alam m² 2.46 312,672.00 769,173.12

3 Pekerjaan Carport
a Pasir m³ 2.62 190,000.00 498,180.00
b Beton m² 1.31 205,150.00 268,951.65