KONSEP PERHITUNGAN BATU SPLIT DAN PASIR

HARGA BATU DARI KUARI / KRASER :


BATU SPLIT :
1. UKURAN 0,5 – 1 = Rp. 60.000 / TON
2. UKURAN 1 - 2 = Rp. 80.000 / TON
3. UKURAN 2 - 3 = Rp. 70.000 / TON

JASA ANGKUT :
1. PENGAMBILAN DARI KRASER KE PROYEK : Rp. 40.000 / M3

PASIR :
HARGA PEMBELIAN DAN JASA ANGKUT :
1. Rp. 90. 000 / M3

PERHITUNGAN DARI TONASE KE M3 :


BATU SPLIT :
1. HARGA 0,5 - 1 = Rp. 60. 000 = Rp. 72. 000 / M3
2. HARGA 1 – 2 = Rp. 80. 000 = Rp 104. 000 / M3
3. HARGA 2 - 3 = Rp. 70. 000 = Rp. 91. 000 / M3

HARGA PENAWARAN BATU SPLIT DAN PASIR YANG DISETUJUI :


BATU SPLIT :
1. BATU SPLIT UKURAN 0,5 – 1 = Rp. 132.000 / M3
2. BATU SPLIT UKURAN 1 - 2 = Rp. 153.000 / M3
3. BATU SPLIT UKURAN 2 - 3 = Rp. 150.000 / M3
PASIR :
4. PASIR = Rp. 115. 000 / M3

KAPASITAS STANDART PENGIRIMAN / HARI = 370 TON (300 M3) / HARI


PERHITUNGAN MODAL / HARGA + JASA ANGKAUT :
BATU SPLIT :
1. Rp. 72. 000 + Rp. 40. 000 = Rp. 112. 000
2. Rp. 104. 000 + Rp. 40. 000 = Rp, 144. 000
3. Rp. 91.000 + Rp. 40. 000 = Rp. 131. 000
PASIR :
4. Rp. 90. 000

ANGGARAN DANA YANG HARUS DIKELUARKAN / HARI :


BATU SPLIT :
1. Rp. 112. 000 x 100 M3 = Rp. 11. 200. 000
2. Rp. 144. 000 x 100 M3 = Rp 14. 400. 000
3. Rp. 131. 000 x 100 M3 = Rp. 13. 100. 000
PASIR :
4. Rp. 90. 000 x 100 M3 = Rp. 9. 000. 000

TOTAL DANA PER HARI = Rp. 47. 700. 000


TOTAL DANA PER 2 BULAN = Rp. 2. 862. 000. 000

ESTIMASI LABA / KEUNTUNGAN :


1. BATU SPLIT 0,5 – 1 = Rp. 20. 000 x 100 x 60 = Rp. 120. 000. 000
2. BATU SPLIT 1 – 2 = Rp. 9. 000 x 100 x 60 = Rp. 54. 000. 000
3. BATU SPLIT 2 - 3 = Rp. 22. 000 x 100 x 60 = Rp. 132. 000. 000
4. PASIR = Rp. 25. 000 x 100 x 60 = Rp. 150. 000. 000 +

TOTAL = Rp. 456. 000. 000