A. Latar Belakang................................................................................1
C.
D. Dasar Kegiatan................................................................................2
E. Sasaran Program.............................................................................2
F. Rancangan Bangun.........................................................................2
H. Susunan Panitia..............................................................................2
I. Penutup...........................................................................................3
DOKUMENTASI KEGIATAN..................................................................4
i
ii
PANITIA PEMBANGUNAN
MASJID JAMI AR ROHMAAN
DESA PASURUAN KEC. PABEDILAN KAB. CIREBON
Sekretariat : Jl. Raya Jendral Gatot Subroto No. 156 Blok Manis
Rt. 003 Rw. 001 Desa Pasuruan Kecamatan Pabedilan Kabupaten
Cirebon
Nomor : 001/PP-Masjid/DKM/XII/2022
Lampiran : 1 Bendel Proposal
Perihal : Permohonan Bantuan Dana
Di Tempat
Assalamualaikum. Wr. Wb.
Salam ta'dzim kami haturkan semoga Bapak / Ibu / Sdr tetap dalam sehat
walafiyat serta sukses dalam menjalankan aktifitas sehari-hari. Berkaitan dengan
rencana pembangunan Masjid Jami Ar Rohman Desa Pasuruan Kec. Pabedilan
Kab.Cirebon, bersama ini kami selaku Panitia memohon dengan penuh hormat
kepada Bapak/Ibu/Sdr para donatur dan dermawan untuk berkenan berpatisipasi
dalam donasi/sumbangan dana. Adapun anggaran biaya pembangunan tersebut
sebesar : Rp. 2.067.656.000 ( Dua Milyar Enam Puluh tujuh Juta Enam Ratus Lima
Puluh Enam Ribu Rupiah ) bagi Masjid Desa Pasuruan Kecamatan Pabedilan
Kabupaten Cirebon :
Nama masjid : Masjid Jami Ar Roman
Alamat : Sekretariat : Jl. Raya Jendral Gatot Subroto No. 156 Blok Manis
Rt. 003 Rw. 001 Desa Pasuruan Kecamatan Pabedilan
Kabupaten Cirebon
Penyelenggara
: DKM Masjid Jami Ar Rohman
KetuaPanitia Sekretaris
Mengetahui,
Ketua MUI Desa Pasuruan Kuwu Desa Pasuruan Ketua DKM Masjid Ar Rohman
1
NANANG KHOIRUL ANAM MUJA YUSUP
PANITIA PEMBANGUNAN
MASJID JAMI AR ROHMAAN
DESA PASURUAN KEC. PABEDILAN KAB. CIREBON
Sekretariat : Jl. Raya Jendral Gatot Subroto No. 156 Blok Manis Rt. 003 Rw.
001 Desa Pasuruan Kecamatan Pabedilan Kabupaten Cirebon
A. LATAR BELAKANG
B. DASAR PEMIKIRAN
Sebagai tempat yang agung dan sangat mulia, maka masjid/ rumah
Allah SWT seharusnya memang tidak hanya berupa bangunan, namun lebih
dari itu masjid seyogyanya bisa menjadi pelindung dan menjadi ciri khas
( religius ) tempat beribadah umat islam khususnya bagi masyarakat islam
sekitarnya dan bisa menjadi kebanggaan tempat suci yang di idam idamkan
oleh seluruh umat islam, bahkan bisa menjadi tempat ternyaman dalam
melakukan aktifitas beribadah supaya lebih khusyuk, serta menunjang semua
kegiatan syiar islam di dalamnya, Hingga tujuan akhirnya semoga segala
kegiatan didalamnya akan menjadi ladang ibadah yang berkah dan penuh
ridho dariNya bagi kita semua umat islam aamiin.
2
C. TUJUAN
D. DASAR KEGIATAN
E. SASARAN PROGRAM
Yang menjadi sasaran pembangunan ini adalah Masjd Jami’ Ar- Rohman Blok
Manis RT 03 RW 01 Desa Pasuruan Kecamatan Pabedilan Kabupaten Cirebon
Jawa Barat Indonesia.
Kayu penyangga plavon yang melapuk di makan usia sehingga di dalam area
utama masjid akan banjir akibat bocor efek dari rusaknya plavon tersebut.
Kondisi genteng yang sudah rusak dan sudah tidak beraturan efek kayu usuk
yang rapuh
Kubah masjid yang terbuat dari material alumunium sudah terlihat kusam
dan bentuknya yang sudah tidak lagi sempurna.
Halaman masjid yang sudah jauh lebih rendah dari jalan utama provinsi di
depannya sehingga halaman akan tergenang air ketika hujan lebat turun.
F. Rancang Bangun
Terlampir
H. Susunan Kepanitiaan
Terlampir
3
I. Penutup
KetuaPanitia Sekretaris
Mengetahui,
Ketua MUI Desa Pasuruan Kuwu Desa Pasuruan Ketua DKM Masjid Ar Rohman
4
SURAT PENYATAAN TANGGUNGJAWAB
Nama : YUSUP
45193
No Handphone 085352024669
Jawa Barat dari segi fisik, administrasi dan keuangan yang terkait
Pabedilan, 18 Desember
2022 Pembuat
Pernyataan
MATERAI
10.000
YUSUP
5
RANCANGAN BANGUNAN MASJID JAMI AR ROHMAN
DESA PASURUAN KEC.PABEDILAN KAB.CIREBON
6
PANITIA PEMBANGUNAN
MASJID JAMI AR ROHMAAN
DESA PASURUAN KEC. PABEDILAN KAB. CIREBON
Sekretariat : Jl. Raya Jendral Gatot Subroto No. 156 Blok Manis Rt. 003 Rw. 001
Desa Pasuruan Kecamatan Pabedilan Kabupaten Cirebon
REKAPITULASI
7
DETAIL RENCANA ANGGARAN BIAYA
: PEMBANGUNAN MESJID AR
PROYEK
ROHMAN
LOKASI : Desa Pasuruan Kecamatan Pabedilan Kabupaten Cirebon
OWNER : Panitia Pembangunan Mesjid AR Rohman
8
1
0 Rabat Beton 1,93 m3 700.000 1.347.500
III PEKERJAAN KONSTRUKSI BETON 697.309.300
Beton Lantai 1
1 Kolom Praktis 13/13 15,80 m1 185.000 2.923.000
2 Kolom Struktur
K1 25/50 Beton 23,05 m3 1.350.000 31.117.500
Besi 2.457,13 kg 25.000 61.428.250
Bekisting 276,60 m2 225.000 62.235.000
K2 15/35 Beton 6,39 m3 1.350.000 8.632.575
Besi 952,96 kg 25.000 23.824.080
Bekisting 121,80 m2 225.000 27.405.000
K3 15/30 Beton 2,84 m3 1.350.000 3.839.400
Besi 482,15 kg 25.000 12.053.820
Bekisting 56,88 m2 225.000 12.798.000
K4 15/25 Beton 1,78 m3 1.350.000 2.399.625
Besi 352,37 kg 25.000 8.809.290
Bekisting 37,92 m2 225.000 8.532.000
3 Balok Beton
balok 25/80 Beton 18,40 m3 1.350.000 24.840.000
Besi 1.826,29 kg 25.000 45.657.300
Bekisting 147,20 m2 225.000 33.120.000
balok 15/80 Beton 0,84 m3 1.350.000 1.134.000
Besi 189,60 kg 25.000 4.740.060
Bekisting 8,40 m2 225.000 1.890.000
balok 20/45 Beton 23,76 m3 1.350.000 32.076.000
Besi 3.079,44 kg 25.000 76.986.000
Bekisting 216,00 m2 225.000 48.600.000
balok 15/50 Beton 2,10 m3 1.350.000 2.835.000
Besi 430,44 kg 25.000 10.761.000
Bekisting 28,00 m2 225.000 6.300.000
balok 15/30 Beton 0,81 m3 1.350.000 1.093.500
Besi 102,08 kg 25.000 2.551.950
Bekisting 10,80 m2 225.000 2.430.000
Beton Atap
1 Plat Beton Atap/talang tebal 12 cm Beton 18,84 m3 1.350.000 25.434.000
Besi 1.469,52 kg 25.000 36.738.000
Bekisting 157,00 m2 300.000 47.100.000
2 Ring Balk 15/20 Beton 0,81 m3 1.350.000 1.093.500
Besi 102,08 kg 25.000 2.551.950
Bekisting 10,80 m2 150.000 1.620.000
3 Plat Beton Kubah tebal 15 cm Beton 1,41 m3 1.350.000 1.903.500
Besi 89,20 kg 25.000 2.230.000
Bekisting 9,42 m2 300.000 2.826.000
Beton Lainnya
1 Balok praktis lintel 34,00 m1 185.000 6.290.000
2 Profil beton 46,00 m1 185.000 8.510.000
IV PEKERJAAN DINDING DAN PELAPIS DINDING 250.471.000
1 Pasangan bata ringan 590,60 m2 175.000 103.355.000
2 Plesteran (tebal 2 cm) + aci 1.109,80 m2 120.000 133.176.000
3 Plesteran (tebal 2 cm) + tanpa aci 35,70 m2 80.000 2.856.000
4 Tali air di atas plint 110,00 m1 22.000 2.420.000
5 Pekerjaan Facade 228,00 m2 38.000 8.664.000
9
V PEKERJAAN LANTAI 153.186.250
Pelapis Lantai
1 Ruang Sholat - mimbar - Khotib 60,35 m2 420.000 25.347.000
2 Ruang Sound 10,95 m2 420.000 4.599.000
3 Teras 249,00 m2 420.000 104.580.000
Pelapis Dinding
1 Ruang Sholat 26,50 m2 420.000 11.130.000
Waterprofing
1 Dak Atap 115,85 m2 65.000 7.530.250
VI PEKERJAAN PINTU DAN JENDELA 59.900.000
1 Type P1 3,00 unit 6.000.000 18.000.000
Kusen alumunium
Daun Pintu Kayu Solid
Finish melamic + Acessories
2 Type P2 2,00 unit 4.000.000 8.000.000
Kusen alumunium
Daun Pintu Kayu Solid
Finish melamic + Acessories
3 Type J1 6,00 unit 2.500.000 15.000.000
Kusen alumunium 3"
Daun jendela alumunium
Acessories
4 Type J2 6,00 unit 1.500.000 9.000.000
Kusen alumunium 3"
Daun jendela alumunium
Acessories
5 Type BV 3,00 unit 500.000 1.500.000
6 Roster 4,00 unit 2.100.000 8.400.000
VII PEKERJAAN ATAP 78.929.000
Rangka Atap
1 Konstruksi kuda-kuda baja ringan 278,00 m2 175.000 48.650.000
2 Listplank double Fibre Cement 20 cm +10cm 73,60 m1 90.000 6.624.000
Penutup atap
hanya
upah
1 Atap genteng eksisting pasang 278,00 m2 60.000 16.680.000
2 Nok standrt 31,00 m1 225.000 6.975.000
VIII PEKERJAAN PLAFOND 71.034.500
1 Plafond gypsum Board 9 mm + rangka hollow
Area Sholat 103,90 m2 175.000 18.182.500
Area Mimbar - Khotib 22,34 m2 175.000 3.909.500
Area sound 10,94 m2 175.000 1.914.500
Area Teras 241,16 m2 175.000 42.203.000
2 List plafond gypsum
Area Sholat 46,20 m1 25.000 1.155.000
Area Mimbar - Khotib 21,50 m1 25.000 537.500
Area sound 13,50 m1 25.000 337.500
Area Teras 111,80 m1 25.000 2.795.000
IX PEKERJAAN PENGECATAN 39.916.500
1 Cat Dinding Luar Dulux
Tampak Depan 86,68 m2 35.000 3.033.800
Tampak Samping kanan 71,65 m2 35.000 2.507.750
Tampak Samping Kiri 71,65 m2 35.000 2.507.750
10
Tampak Belakang 101,70 m2 35.000 3.559.500
2 Cat Dinding Dalam Catylac/Vinilex 554,90 m2 28.000 15.537.200
3 Cat Plafond / List profil
Area Sholat 103,90 m2 25.000 2.597.500
Area Mimbar - Khotib 22,34 m 2
25.000 558.500
Area sound 10,94 m 2
25.000 273.500
Area Teras 241,16 m 2
25.000 6.029.000
4 Cat Listplank 73,60 m1 45.000 3.312.000
X PEKERJAAN INSTALASI LISTRIK 24.435.000
1 Instalasi titik lampu 25,00 ttk 265.000 6.625.000
2 Instalasi Stop Kontak 16,00 ttk 265.000 4.240.000
3 Instalasi Stop Kontak AC 4,00 ttk 265.000 1.060.000
4 Saklar Tunggal 8,00 ttk 75.000 600.000
5 Saklar Ganda/seri 5,00 ttk 75.000 375.000
6 Stop Kontak 16,00 ttk 75.000 1.200.000
7 Stop Kontak AC 4,00 ttk 75.000 300.000
8 KWH Meter 1,00 bh 1.500.000 1.500.000
9 box Panel Pembagi 1,00 bh 400.000 400.000
1
0 Lampu LED strip ttk 0
1
1 Lampu down light/baret 24,00 ttk 140.000 3.360.000
1
2 Lamputempel pilar 6,00 ttk 300.000 1.800.000
1
3 Lampu tsorot taman 4,00 ttk 200.000 800.000
1
4 Lampu Hias (hanya upah pasang- material lampu by owner) 1,00 ttk 75.000 75.000
1
5 MCB 6,00 pcs 150.000 900.000
1
6 Arde Pentanahan + Instalasi 1,00 unit 1.200.000 1.200.000
XI PEKERJAAN LAIN-LAIN 1.500.000
1 Pembersihan Akhir 1,00 ls 1.500.000 1.500.000
TOTAL 1.711.734.787
DIBULATKAN 1.711.735.000
== Satu Milyar Tujuh Ratus Sebelas Juta Tujuh Ratus Tiga Puluh Lima Ribu Rupiah ==
11
REKAPITULASI
: PEMBANGUNAN AREA WUDHU MASJID AR
PROYEK
ROHMAN
: Desa Pasuruan Kecamatan Pabedilan Kabupaten
LOKASI
Cirebon
OWNER : Panitia Pembangunan Mesjid AR Rohman
12
DETAIL RENCANA ANGGARAN BIAYA
: PEMBANGUNAN AREA WUDHU MESJID AR
PROYEK
ROHMAN
LOKASI : Desa Pasuruan Kecamatan Pabedilan Kabupaten Cirebon
OWNE
: Panitia Pembangunan Mesjid AR Rohman
R
13
311,0
2 Plesteran (tebal 2 cm) + aci m2 120.000 37.322.400
2
3Plesteran (tebal 2 cm) + tanpa aci 28,30 m2 80.000 2.264.000
4Tali air di atas plint 54,30 m1 32.000 1.737.600
5Pekerjaan Facade 14,00 m2 38.000 532.000
V PEKERJAAN LANTAI 44.817.000
Pelapis Lantai
1 Area Wudhu 45,60 m2 350.000 15.960.000
2 Area KM/WC 7,80 m2 350.000 2.730.000
Pelapis Dinding
1 Area Wudhu 34,50 m2 350.000 12.075.000
2 Area KM/WC 38,96 m2 350.000 13.636.000
Waterprofing
Kolam Wudhu 6,40 m2 65.000 416.000
VI PEKERJAAN PINTU DAN JENDELA 7.000.000
uni
P1 KM/WC 4,00 1.500.000 6.000.000
t
B uni
KM/WC 4,00 250.000 1.000.000
V t
uni
Roster 1 2,00 1.400.000 2.800.000
t
uni
Roster 2 4,00 800.000 3.200.000
t
VII PEKERJAAN ATAP 36.793.250
Rangka Atap
1 Konstruksi kuda-kuda baja ringan 92,75 m2 175.000 16.231.250
2 Listplank double Fibre Cement 20 cm +10cm 39,80 m1 90.000 3.582.000
Penutup atap
1 Atap genteng 92,75 m2 120.000 11.130.000
2 Nok standrt 26,00 m1 225.000 5.850.000
VIII PEKERJAAN PLAFOND 12.474.000
Plafond gypsum Board 9 mm + rangka hollow
1 Area Wudhu 52,80 m2 175.000 9.240.000
2 KM/WC 7,28 m2 175.000 1.274.000
List plafond gypsum
1 Area Wudhu 56,80 m1 25.000 1.420.000
2 KM/WC 21,60 m1 25.000 540.000
IX PEKERJAAN PENGECATAN 12.600.340
1 Cat Dinding Luar Dulux
Tampak Depan 18,20 m2 35.000 637.000
Tampak Samping kanan 18,37 m2 35.000 642.950
Tampak Samping Kiri 18,37 m2 35.000 642.950
Tampak Belakang 30,60 m2 35.000 1.071.000
225,4
2 Cat Dinding Dalam Catylac/Vinilex m2 28.000 6.313.440
8
3 Cat Plafond / List profil
Area Wudhu 52,80 m2 25.000 1.320.000
KM/WC 7,28 m2 25.000 182.000
4 Cat Listplank 39,80 m1 45.000 1.791.000
14
X PEKERJAAN INSTALASI LISTRIK 9.760.000
1 Instalasi titik lampu 12,00 ttk 265.000 3.180.000
2 Saklar Tunggal 6,00 ttk 75.000 450.000
3 Saklar Ganda/seri 2,00 ttk 75.000 150.000
4 KWH Meter 1,00 bh 1.500.000 1.500.000
5 box Panel Pembagi 1,00 bh 400.000 400.000
6 Lampu down light/baret 12,00 ttk 140.000 1.680.000
7 Lamputempel pilar 2,00 ttk 300.000 600.000
8 MCB 4,00 bh 150.000 600.000
uni
9 Arde Pentanahan + Instalasi 1,00 1.200.000 1.200.000
t
XI PEKERJAAN INSTALASI AIR 20.909.000
1 Instalasi Air Bersih Pipa dia. 1" 6,00 m1 50.000 300.000
2 Instalasi Air Bersih Pipa dia. 3/4" 43,00 m1 38.000 1.634.000
3 Instalasi Air Bersih Pipa dia. 1/2" 22,50 m1 30.000 675.000
4 Saluran Air Bekas Pipa dia. 4" AW 40,00 m1 205.000 8.200.000
5 Saluran Air Bekas Pipa dia. 3" D 6,00 m1 100.000 600.000
6 Saluran Air Kotor Pipa dia. 4" ( fecalin/sawage ) AW 20,00 m1 205.000 4.100.000
7 Saluran Air Kotor Pipa dia. 3" ( fecalin/sawage ) AW 2,00 m1 100.000 200.000
8 Saluran Pipa Vent dia. 1.5" D 20,00 m1 60.000 1.200.000
9 Septictank 1,00 bh 4.000.000 4.000.000
XII PEKERJAAN ACCESSORIES SANITARI 3.385.000
Area Wudhu
acessorie
1 kran s by 26,00 bh 25.000 650.000
owner
acessorie
2 Floor Drain s by 6,00 bh 75.000 450.000
owner
acessorie
3 Whastafle s by 1,00 bh 125.000 125.000
owner
KM/WC
acessorie
1 kran s by 4,00 bh 25.000 100.000
owner
acessorie
2 Closet duduk s by 4,00 bh 275.000 1.100.000
owner
acessorie
3 Shower spray with stop valve s by 4,00 bh 65.000 260.000
owner
acessorie
4 Shower s by 4,00 bh 75.000 300.000
owner
acessorie
5 Gantungan Handuk s by 4,00 bh 25.000 100.000
owner
acessorie
6 Floor Drain s by 4,00 bh 75.000 300.000
owner
XIII PEKERJAAN LAIN-LAIN 1.500.000
1 Pembersihan Akhir 1,00 ls 1.500.000 1.500.000
TOTAL 355.920.783
DIBULATKAN 355.921.000
== Tiga Ratus Lima Puluh Lima Juta Sembilan Ratus Dua Puluh Satu Ribu Rupiah ==
15
DEWAN KEMAKMURAN MASJID (DKM)
MASJID JAMI AR ROHMAN
DESA PASURUAN KEC. PABEDILAN KAB. CIREBON
Sekretariat : Jl. Raya Jendral Gatot Subroto No. 156 Blok Manis Rt. 003 Rw. 001
Desa Pasuruan Kecamatan Pabedilan Kabupaten Cirebon Kode Pos 45193
Telp. / HP : 082311125978
TENTANG
16
6. Peraturan Daerah Kabupaten Cirebon Nomor 3 Tahun 2018
tentang Perubahan atas Peraturan daerah Kabupaten Cirebon
Nomor 1 Tahun 2013 tentang Pedoman Pembentukan Lembaga
Kemasyarakatan di Desa dan Kelurahan.
MEMUTUSKAN
Menetapkan :
Ditetapkan di : Pasuruan
YUSUP
Mengetahui,
17
2. Yth. Panitia Pembanguna Masjid Jami Ar Rohman;
3. Arsip
SUSUNAN PANITIA
PEMBANGUNAN MASJID JAMI AR ROHMAN
DESA PASURUAN KECAMATAN PABEDILAN
KABUPATEN CIREBON
: Kyai Sholehudin
: Kyai Wasmunudin
3 Ketua : H. Faoji
6 Bendahara : Yunus
7 : Marto
Seksi Bidang : Kadori
Rancang Bangun
dan Pengawasan
8 Seksi Bidang
Intern
18
9 Ekstern : Bapa Kuwu MUJA
H. Bachrudin
H. Ibnu Hajar
H. Jahuri Kail
H. Mujahidin
Ust. Nanang KA
Ust. Agus Salim
Ust. Iskandar Mubarok
Bapak Sutarso
Bapak Mung Aziz
Ahmad Khaerudin
Seksi Kemanan : Dulyani
10
: Abdul Hadi
Ditetapkan di : Pasuruan
Tanggal : 11 November 2022 M
12 Robiul Akhir 1444 H
YUSUP
Mengetahui,
Ketua MUI Desa Pasuruan Kuwu Desa Pasuruan
19
PANITIA PEMBANGUNAN
MASJID JAMI AR ROHMAN
DESA PASURUAN KEC. PABEDILAN KAB. CIREBON
Sekretariat : Jl. Raya Jendral Gatot Subroto No. 156 Blok Manis Rt.
003 Rw. 001
Desa Pasuruan Kecamatan Pabedilan Kabupaten Cirebon Kode Pos
45193
0131048823100
REKENING BANK BNI DKM AR ROHMAN
1585773737
PANITIA PEMBANGUNAN
MASJID JAMI AR ROHMAN
DESA PASURUAN KEC. PABEDILAN KAB. CIREBON
Sekretariat : Jl. Raya Jendral Gatot Subroto No. 156 Blok Manis Rt. 003 Rw. 001
Desa Pasuruan Kecamatan Pabedilan Kabupaten Cirebon Kode Pos 45193
KTP PANITIA
PEMBANGUNAN MASJID JAMI AR ROHMAN DESA PASURUAN
KEC.PABEDILAN KAB.CIREBON
Ketua
Sekretaris
Bendahara