Kebutuhan Besi

FOOTPLAT 6 BH P 1 JML 0 BH/FT


X 6 6.00 m'
6.30 - batang D13 mm
6 BH P 1
Y 6 6.00 m'
6.30 - batang D13 mm

KOLOM UTAMA 0 BH T 4
pokok 0 - m'
- - batang D13 mm
begel 0 1.00 bh 15/30
1.05 @ 0.95 0.08 batang Ø8 mm

SLOOF 1 BH P 0
pokok 0 - m'
- - batang Ø10 mm
begel 0 1.00 bh 12/20
1.05 @ 0.74 0.06 batang Ø8 mm

KOLOM PRAKTIS 4 BH T 4.5


pokok 18 72.00 m'
75.60 6.30 batang Ø10 mm
begel 18 91.00 bh 12/15
95.55 @ 43.95 3.66 batang Ø6 mm

BALOK UTAMA 1 BH P 0
pokok 0 - m'
- - batang D13 mm
begel 0 1.00 bh 15/30
1.05 @ 0.84 0.07 batang Ø8 mm

BALOK LATEU 1 BH P 24
pokok 24 96.00 m'
100.80 8.40 batang Ø10 mm
begel 24 121.00 bh 12/15
127.05 @ 60.98 5.08 batang dia 6 mm

PLAT LANTAI BESI


BONDEKS TB.
WIERMESH
0,8MM
M10,5
TERAS - CAD AREA
PLAT TALANG LT1 - CAD AREA
PLAT LANTAI - CAD AREA
PLAT TALANG LT2 11.25 11.25 CAD AREA

JUMLAH 11.25 M2 11.25 M2

Jumlah Total Besi Tulangan 8.74 ≈ 9.00 batang Ø6 mm

Jumlah Total Besi Tulangan 0.21 ≈ 1.00 batang Ø8 mm


Jumlah Total Besi Tulangan 14.70 ≈ 15.00 batang Ø10 mm

Jumlah Total Besi Tulangan ≈ 1.00 batang Ø12 mm

Jumlah Total Besi Tulangan ≈ 1.00 batang D13 mm


RENCANA ANGGARAN PELAKSANAAN

Pekerjaan : Pembangunan Pos Satpam


Lokasi : Komplek Masjid Al Iklas, Kabupaten Gunungkidul
Th.Anggaran : 2022

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT.
(Rp) (Rp)
A PEKERJAAN PERSIAPAN
1 Uitzet dan bouwplank 1.00 ls 100,000.00 100,000.00
2 Pembersihan lokasi 1.00 ls 150,000.00 150,000.00
3 Pengadaan air kerja 1.00 ls 100,000.00 100,000.00
JUMLAH 350,000.00
B PEKERJAAN STRUKTUR
1 Besi Ø6 mm 9.00 batang 39,600.00 356,400.00
Besi Ø10 mm 16.00 batang 111,600.00 1,785,600.00
2 Pasir beton 1.00 m3 250,000.00 250,000.00
3 Split 1.50 m3 300,000.00 450,000.00
4 PC/Semen 19.00 Zak 55,000.00 1,045,000.00
5 Bambu, Papan Begeesting, Perlengkapan Struktur 1.00 Ls 550,000.00 550,000.00
6 Batu Fondasi - m3 175,000.00 -
JUMLAH 4,437,000.00
C PEKERJAAN ARSITEKTUR
1 Bataco 360.00 biji 3,500.00 1,260,000.00
2 Kosen P1 Alumunium Coklat 1.00 unit - -
J1 Alumunium Coklat 1.00 unit - -
J2 Alumunium Coklat 2.00 unit - -
3 Keramik 60/60 9.00 m2 135,000.00 1,215,000.00
4 Pasir Pasang 7.20 m3 250,000.00 1,800,000.00
5 PC/Semen 25.00 Zak 55,000.00 1,375,000.00
6 Rangka Atap Baja Ringan 26.00 m2 165,000.00 4,290,000.00
7 Penutup Atap Metal Roof Pasir 26.00 m2 115,000.00 2,990,000.00
8 Kerpusan Metal Roof Pasir 15.00 m' 35,500.00 532,500.00
9 Gypsum Rangka STUD (langit-langit) 9.00 m2 110,000.00 990,000.00
10 Cat Tembok 25.00 kg 35,000.00 875,000.00
JUMLAH 15,327,500.00
D PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
1 Penyambungan Listrik 1.00 Ls 200,000.00 200,000.00
2 Jaringan listrik 3.00 ttik 125,000.00 375,000.00
3 Lampu LED 2.00 ttik 85,000.00 170,000.00
4 Stop Kontak 1.00 ttik 75,000.00 75,000.00
5 Saklar Ganda 1.00 ttik 75,000.00 75,000.00
JUMLAH 895,000.00
E UPAH TENAGA
1 Tenaga 30.00 OH 90,000.00 2,700,000.00
2 Tukang Batu 30.00 OH 95,000.00 2,850,000.00
3 Kepala Tukang 15.00 OH 105,000.00 1,575,000.00
JUMLAH 7,125,000.00
JUMLAH 28,134,500.00