Setiap proyek memiliki batasan atau limitasi yang dikenal sebagai project
constraint. Hal berikut termasuk ke dalam triple constraints yang utama, kecuali:
A. Communication
B. Scope
C. Cost
D. Time
ANSWER: A
Pada umumnya kegagalan dalam proyek disebabkan hal berikut ini, kecuali:
A. Kurang dana untuk penyelenggaraan proyek.
B. Kurang dukungan dari petinggi organisasi.
C. Tujuan proyek yang kurang jelas.
D. Perencanaan proyek kurang jelas.
ANSWER: A
3.1.4 Pihak-pihak yang terlibat dalam suatu proyek, baik langsung maupun tidak
langsung, disebut:
A. Project Shareholder
B. Project Sponsor
C. Project Stakeholder
D. Project Owner
ANSWER: C
Hal-hal berikut merupakan alasan yang benar bagi organisasi mengadakan suatu
proyek, kecuali:
A. Penerapan teknologi baru dalam produk.
B. Persaingan dengan kompetitor.
C. Menghabiskan anggaran.
D. Keselamatan customer.
ANSWER: C
Seorang manajer proyek harus memiliki hard-skill dan soft-skill. Yang merupakan
contoh soft-skill adalah:
A. Mempunyai kemampuan teknis yang relevan dengan jenis proyek
B. Mempunyai kemampuan memimpin yang baik
C. Mempunyai kemampuan manajemen strategi dan manajemen bisnis
D. Jawaban A dan C benar
ANSWER: B
Hal berikut merupakan elemen utama dalam Quadruple Constraint Tier System, yaitu:
A. Project Integration
B. Client Acceptance
C. Good Communication
D. Semua benar
ANSWER: B
8. 3.1.6 Hal berikut ini merupakan contoh pelaksanaan proyek di lingkungan TEL-U,
kecuali:
A. Memasang unit CCTV di setiap kelas
B. Menambah fitur pembayaran secara digital pada aplikasi i-gracias
C. Merekap absensi mahasiswa, dosen dan karyawan
D. Memperluas area parkir motor mahasiswa
ANSWER: C
ANSWER: A
Which of the following is NOT true about interpersonal and team skills?A. Coaching
means helping your team to get more exercise.B. Motivation means helping team
members get what they want out of the project.C. Influencing means sharing power
with people to get something done.D. Conflict management means finding positive
solutions to conflicts during the project.ANSWER: A
Which of the following is NOT true about portfolio management?A. The portfolio
manager judges the success of the portfolio by combining data from all of its
programs and projects.B. A portfolio can contain projects and programs.C. A
portfolio is organized around a business goal.D. A portfolio is always a group of
programs.ANSWER: D
You�re managing a project to remodel a kitchen. You use earned value calculations
to figure out that you�re going to run $500 over budget if your project continues
at the current rate. Which of the following core characteristics of a project
manager are you using to find the problem?A. KnowledgeB. PerformanceC. Personal
skillsD. None of the aboveANSWER: A
At the beginning of a project, a software team project manager is given a schedule
with everyone�svacations on it. She realizes that because the software will be
delivered to the QA team exactly when they have overlapping vacations, there is a
serious risk of quality problems, because there won�t be anyone to test the
software before it goes into production. What BEST describes the constraint this
places on the project?A. Quality constraintB. Time constraintC. Resource constraint
D. Risk constraintANSWER: C
A project manager is having trouble with his project because one of his team
members is not performing, which is causing him to miss an important date he
promised to a stakeholder. He discovers that the team member knew about the project
problem, but didn�t tell him because the team members are all afraid of his bad
temper. Which BEST describes how the project manager can avoid this situation in
the future?A. Increasing his knowledge of the PMBOK� GuideB. Measuring personal
performanceC. Improving his personal skillsD. Managing stakeholder expectations
ANSWER: C
The project was running late, so the project manager decided to release it on time
even though it was missing some of its features.
Constraint affected:
A. Scope
B. Resources
C. Quality
D. Time
E. Risk
F. Cost
ANSWER: A
The company didn�t have enough money to invest in the project, so they had to draft
people from other departments to work part-time to get the job done.
Constraint affected:
A. Scope
B. Resources
C. Quality
D. Time
E. Risk
F. Cost
ANSWER: B
The team wanted to add more testers to find defects, but the project manager
overruled them.
Constraint affected:
A. Scope
B. Resources
C. Quality
D. Time
E. Risk
F. Cost
ANSWER: C
About halfway through the project, the PM realized that the money was running out
faster than expected. She went through the schedule to try to find ways to move up
the deadline.
Constraint affected:
A. Scope
B. Resources
C. Quality
D. Time
E. Risk
F. Cost
ANSWER: D
A construction project manager assumed that the weather would cooperate with the
plans to complete the job, but thunderstorms have derailed the project.
Constraint affected:
A. Scope
B. Resources
C. Quality
D. Time
E. Risk
F. Cost
ANSWER: E
The project manager didn�t take software license fees into account, which caused
the budget to balloon out of control.
Constraint affected:
A. Scope
B. Resources
C. Quality
D. Time
E. Risk
F. Cost
ANSWER: F
Which of the following is NOT a project constraint?A. QualityB. ScaleC. TimeD. Cost
ANSWER: B
A project manager is running a data center installation project. He finds that his
stakeholder is angry that he�s run over his budget because the staff turned out to
be more expensive than planned. The stakeholder�s unhappy that when the project is
over, the servers won�t have as much drive space as he needs. Which of the
following constraints was not affected by this problem?A. QualityB. ResourcesC.
TimeD. CostANSWER: C
Your manager asks you where to find a list of projects that should be managed
together. What is the BEST place to find this information?A. Project planB. Project
charterC. Portfolio charterD. Program charterANSWER: D
You want to know specifically which business goal a group of projects and programs
is going to accomplish. Which is the BEST place to look for this information?A.
Project planB. Project charterC. Portfolio charterD. Program charterANSWER: C
A project coordinator is having trouble securing programmers for her project. Every
time she asks her boss to give a resource to the project he says that they are too
busy to help out with her project. Which type of organization is she working in?A.
FunctionalB. Weak matrixC. Strong matrixD. ProjectizedANSWER: A
A project manager is having trouble getting customer feedback on her project. Even
though she knows the product won�t be complete for several months, the company
guidelines say she should release an early version and get feedback from end users.
Which type of organization is she working for?A. FunctionalB. VirtualC. HybridD.
ProjectizedANSWER: C
The project manager for a construction project discovers that a new water line is
being created in the neighborhood where he�s managing a project. Government
regulations require that a series of forms for city environmental changes need to
be filled out before his team can continue work on the project. This is an example
of:A. A portfolioB. A programC. An enterprise environmental factorD. A project
ANSWER: C