Anda di halaman 1dari 5

NO NAMA ALAT DAFTAR HARGA (RUPIAH)

1 BACKHOE LOADER 426F2 Rp 1,081,500,000.00


2 BULDOZER
3 WHEEL LOADER
4 WHEEL TRACTOR- SCRAPER
5 COLD PLANER PM620 Rp 4,595,971,755.00
6 EXCAVATOR
7 MOTOR GRADER
8 PAVER ASPAL
9 ROAD RECLAIMER
10 TANDEM ROLLER CB34B Rp 892,237,500.00
11 COMPACT TRACK LOADER Rp 1,431,120,000.00
12 SKID STEER LOADER Rp 1,228,800,000.00
13 TRACK LOADER Rp 1,173,154,560.00
14 TRUK ARTIKULASI Rp 1,732,700,000.00
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Compact Track Loader 239D3 E01
2. Tenaga Pw 67.2 HP
3. Kapasitas Cp 3.4 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,431,120,000 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 143,112,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23578 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 151,845.93 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,431.12 Rupiah


W

Biaya Pasti per Jam = (E+F) G 153,277.05 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (10%-12%) x Pw x Ms H 125,059.20 Rupiah

2. Pelumas = (0,25%-0,35%) x Pw x Mp I 10,080.00 Rupiah

Biaya bengkel (2,2% - 2,8%) x B J 15,742.32


W

3. Perawatan dan (6,4 % - 9 %) x B K 45,795.84 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 30,066.21 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 25,803.30 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 252,546.87 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 405,823.92 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5.75 % / Tahun
2. Upah Operator / Sopir U1 30,066.21 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,803.30 Rp./Jam
4. Bahan Bakar Bensin Mb 10,000.00 Liter
5. Bahan Bakar Solar Ms 18,610.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT


No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Skid Steer Loader 232D3 E02
2. Tenaga Pw 60.2 HP
3. Kapasitas Cp 3.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,228,800,000 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 122,880,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23578 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 130,379.20 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,228.80 Rupiah


W

Biaya Pasti per Jam = (E+F) G 131,608.00 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (10%-12%) x Pw x Ms H 112,050.81 Rupiah

2. Pelumas = (0,25%-0,35%) x Pw x Mp I 9,031.50 Rupiah

Biaya bengkel (2,2% - 2,8%) x B J 13,516.80


W

3. Perawatan dan (6,4 % - 9 %) x B K 39,321.60 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 30,066.21 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 25,803.30 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 229,790.22 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 361,398.22 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5.75 % / Tahun
2. Upah Operator / Sopir U1 30,066.21 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,803.30 Rp./Jam
4. Bahan Bakar Bensin Mb 10,000.00 Liter
5. Bahan Bakar Solar Ms 18,610.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT


No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Track Loader E03
2. Tenaga Pw 274.9 HP
3. Kapasitas Cp 29.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,173,154,560 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 117,315,456 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23578 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 124,475.06 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,173.15 Rupiah


W

Biaya Pasti per Jam = (E+F) G 125,648.21 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (10%-12%) x Pw x Ms H 511,607.51 Rupiah

2. Pelumas = (0,25%-0,35%) x Pw x Mp I 41,236.50 Rupiah

Biaya bengkel (2,2% - 2,8%) x B J 12,904.70


W

3. Perawatan dan (6,4 % - 9 %) x B K 37,540.95 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 30,066.21 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 25,803.30 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 659,159.17 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 784,807.38 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5.75 % / Tahun
2. Upah Operator / Sopir U1 30,066.21 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,803.30 Rp./Jam
4. Bahan Bakar Bensin Mb 10,000.00 Liter
5. Bahan Bakar Solar Ms 18,610.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.


A. URAIAN PERALATAN
1. Jenis Peralatan Truk Artikulasi E03
2. Tenaga Pw 375.5 HP
3. Kapasitas Cp 28.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,732,700,000 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 173,270,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23578 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 183,844.43 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,732.70 Rupiah


W

Biaya Pasti per Jam = (E+F) G 185,577.13 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (10%-12%) x Pw x Ms H 698,805.50 Rupiah

2. Pelumas = (0,25%-0,35%) x Pw x Mp I 56,325.00 Rupiah

Biaya bengkel (2,2% - 2,8%) x B J 19,059.70


W

3. Perawatan dan (6,4 % - 9 %) x B K 55,446.40 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 30,066.21 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 25,803.30 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 885,506.11 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 1,071,083.24 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5.75 % / Tahun
2. Upah Operator / Sopir U1 30,066.21 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,803.30 Rp./Jam
4. Bahan Bakar Bensin Mb 10,000.00 Liter
5. Bahan Bakar Solar Ms 18,610.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

Anda mungkin juga menyukai