PROYEK PRASARANA PENDIDIKAN

KELAPA GADING JAKARTA


Rp 4.519.343.394

1. PEKERJAAN PERSIAPAN 2. PEKERJAAN STRUKTUR


Rp 101.193.190 Rp 4.321.696.046
1.1. ADMIN & DOKUMENTASI 2.1. STRUKTUR BAWAH 2.2. PEKERJAAN STRUKTUR LT 1 2.3. PEKERJAAN STRUKTUR LT 2 2.4. PEKERJAAN STRUKTUR LT 3
A
Rp 30.569.890 Rp 1.207.073.996 Rp 337.054.369 Rp 482.350.399 Rp 482.350.399

1.2. K3 2.1.1. PEKERJAAN PONDASI BORED PILE 2.2.1. PEKERJAAN KOLOM LT 1 2.3.1. PEKERJAAN KOLOM LT 2 2.4.1. PEKERJAAN KOLOM LT 3
Rp 4.948.363 Rp 928.037.653 Rp 107.484.440 Rp 107.484.440 Rp 107.484.440

1.3. MOB & DEMOB 2.1.1.1. PEKERJAAN GALIAN BORED PILE 2.2.1.1. PEKERJAAN PEMBESIAN KOLOM 2.3.1.1. PEKERJAAN PEMBESIAN KOLOM 2.4.1.1. PEKERJAAN PEMBESIAN KOLOM
Rp 10.996.363 Rp 30.723.963 LT 1 LT 2 LT 3
Rp 50.608.818 Rp 50.608.818 Rp 50.608.818
1.4. PAPAN NAMA KEGIATAN 2.1.1.2. PEKERJAAN PEMBESIAN BORED 2.2.1.2. PEKERJAAN BEKISTING KOLOM LT 2.3.1.2. PEKERJAAN BEKISTING KOLOM LT 2.4.1.2. PEKERJAAN BEKISTING KOLOM LT
Rp 494.836 PILE 1 2 3
Rp 725.423.859 Rp 34.711.292 Rp 34.711.292 Rp 34.711.292
1.5. PAGAR PENGAMAN
2.3.1.3. PEKERJAAN PENGECORAN 2.4.1.3. PEKERJAAN PENGECORAN
Rp 28.376.398 2.1.1.3. PEMASANGAN TEMPORARY 2.2.1.3. PEKERJAAN PENGECORAN
KOLOM LT 2 KOLOM LT 3
CASTING KOLOM LT 1
Rp 22.164.330 Rp 22.164.330
1.6. DIREKSI KEET Include Galian Bored Pile Rp 22.164.330
Rp 2.375.214 2.3.2. PEKERJAAN BALOK LT 2 2.4.2. PEKERJAAN BALOK LT 3
2.1.1.4. PEKERJAAN PENGECORAN BORED 2.2.2. PEKERJAAN PLAT LT 1
Rp 153.740.601 Rp 153.740.601
1.7. AIR & LISTRIK KERJA
PILE Rp 213.713.493
Rp 171.889.830 2.3.2.1. PEKERJAAN PEMBESIAN BALOK LT 2.4.2.1. PEKERJAAN PEMBESIAN BALOK LT
Rp 8.877.890 2.2.2.1. PEKERJAAN PEMBESIAN PLAT LT 1 2 3
2.1.2. PEKERJAAN PILE CAP Rp 40.400.272 Rp 78.181.803 Rp 78.181.803
1.8. PENGUKURAN & BOWPLANK
Rp 9.268.952 Rp 173.287.349 2.3.2.2. PEKERJAAN BEKISTING BALOK LT 2.4.2.2. PEKERJAAN BEKISTING BALOK LT
2.2.2.2. PEKERJAAN BEKISTING PLAT LT 1 3
2
2.1.2.1. PEKERJAAN GALIAN PILE CAP Rp 105.148.405 Rp 22.164.330 Rp 22.164.330
1.9. LAND CLEARING & PEMBONGKARAN
Rp 4.098.148 2.2.2.3. PEKERJAAN PENGECORAN PLAT 2.4.2.3. PEKERJAAN PENGECORAN BALOK
Rp 5.285.280 2.3.2.3. PEKERJAAN PENGECORAN BALOK
LT 1 LT 2 LT 3
2.1.2.2. PEKERJAAN PEMBESIAN PILE CAP
Rp 68.164.814 Rp 43.895.216 Rp 43.895.216
Rp 90.576.683
2.2.3. PEKERJAAN TANGGA LT 1 2.3.3. PEKERJAAN PLAT LT 2 2.4.3. PEKERJAAN PLAT LT 3
2.1.2.3. PEKERJAAN BEKISTING PILE CAP Rp 15.856.436
Rp 16.705.624
2.2.3.1. PEKERJAAN PEMBESIAN TANGGA 2.3.3.1. PEKERJAAN PEMBESIAN PLAT LT 2 2.4.3.1. PEKERJAAN PEMBESIAN PLAT LT 3
2.1.2.4. PEKERJAAN PENGECORAN PILE LT 1 Rp 40.400.272 Rp 40.400.272
CAP Rp 8.849.201
Rp 61.906.893 2.3.3.2. PEKERJAAN BEKISTING PLAT LT 2 2.4.3.2. PEKERJAAN BEKISTING PLAT LT 3
2.2.3.2. PEKERJAAN BEKISTING TANGGA
Rp 96.703.833 Rp 96.703.833
2.1.3. PEKERJAAN TIE BEAM LT 1
Rp 105.748.992 Rp 2.194.409 2.3.3.3. PEKERJAAN PENGECORAN PLAT 2.4.3.3. PEKERJAAN PENGECORAN PLAT
2.2.2.3. PEKERJAAN PENGECORAN LT 2 LT 3
2.1.3.1. PEKERJAAN GALIAN TIE BEAM
TANGGA LT 1 Rp 68.164.814 Rp 68.164.814
Rp 4.210.513
Rp 4.812.825 2.3.4. PEKERJAAN TANGGA LT 2 2.4.4. PEKERJAAN TANGGA LT 3
2.1.3.2. PEKERJAAN PEMBESIAN TIE BEAM Rp 15.856.436 Rp 15.856.436
Rp 61.671.347 2.3.3.1. PEKERJAAN PEMBESIAN TANGGA 2.4.3.1. PEKERJAAN PEMBESIAN TANGGA
LT 2 LT 3
2.1.3.3. PEKERJAAN BEKISTING TIE BEAM Rp 8.849.201
Rp 8.849.201
Rp 12.127.877 2.4.3.2. PEKERJAAN BEKISTING TANGGA
2.3.3.2. PEKERJAAN BEKISTING TANGGA
LT 2 LT 3
2.1.3.4. PEKERJAAN PENGECORAN TIE
BEAM Rp 2.194.409 Rp 2.194.409
Rp 27.739.254 2.3.3.3. PEKERJAAN PENGECORAN 2.4.3.3. PEKERJAAN PENGECORAN
TANGGA LT 2 TANGGA LT 3
Rp 4.812.825 Rp 4.812.825
2.5. PEKERJAAN STRUKTUR LT 4 2.6. PEKERJAAN STRUKTUR LT 5 2.7. PEKERJAAN STRUKTUR LT 6 2.8. PEKERJAAN STRUKTUR LT ATAP
A
Rp 482.350.399 Rp 482.350.399 Rp 482.350.399 Rp 365.815.685
2.5.1. PEKERJAAN KOLOM LT 4 2.6.1. PEKERJAAN KOLOM LT 5 2.7.1. PEKERJAAN KOLOM LT 6 2.8.1. PEKERJAAN BALOK LT ATAP
Rp 107.484.440 Rp 107.484.440 Rp 107.484.440 Rp 153.740.601
2.5.1.1. PEKERJAAN PEMBESIAN KOLOM 2.6.1.1. PEKERJAAN PEMBESIAN KOLOM 2.7.1.1. PEKERJAAN PEMBESIAN KOLOM 2.8.1.1. PEKERJAAN PEMBESIAN BALOK LT
LT 4 LT 5 LT 6 ATAP
Rp 50.608.818 Rp 50.608.818 Rp 50.608.818 Rp 78.181.803
2.5.1.2. PEKERJAAN BEKISTING KOLOM LT 2.6.1.2. PEKERJAAN BEKISTING KOLOM LT 2.7.1.2. PEKERJAAN BEKISTING KOLOM LT 2.8.1.2. PEKERJAAN BEKISTING BALOK LT
4 5 6 ATAP
Rp 34.711.292 Rp 34.711.292 Rp 34.711.292 Rp 43.895.216
2.5.1.3. PEKERJAAN PENGECORAN 2.6.1.3. PEKERJAAN PENGECORAN 2.7.1.3. PEKERJAAN PENGECORAN 2.8.1.3. PEKERJAAN PENGECORAN BALOK
KOLOM LT 4 KOLOM LT 5 KOLOM LT 6 LT ATAP
Rp 22.164.330 Rp 22.164.330 Rp 22.164.330 Rp 31.663.582
2.8.2. PEKERJAAN PLAT LT TYPICAL
2.5.2. PEKERJAAN BALOK LT 4 2.6.2. PEKERJAAN BALOK LT 5 2.7.2. PEKERJAAN BALOK LT 6
Rp 153.740.601 Rp 153.740.601 Rp 153.740.601 Rp 212.075.083

2.5.2.1. PEKERJAAN PEMBESIAN BALOK LT 2.6.2.1. PEKERJAAN PEMBESIAN BALOK LT 2.7.2.1. PEKERJAAN PEMBESIAN BALOK LT 2.8.2.1. PEKERJAAN PEMBESIAN PLAT LT
4 5 6 ATAP
Rp 78.181.803 Rp 78.181.803 Rp 78.181.803 Rp 40.400.272
2.5.2.2. PEKERJAAN BEKISTING BALOK LT 2.6.2.2. PEKERJAAN BEKISTING BALOK LT 2.7.2.2. PEKERJAAN BEKISTING BALOK LT 2.8.2.2. PEKERJAAN BEKISTING PLAT LT
4 5 6 ATAP
Rp 22.164.330 Rp 22.164.330 Rp 22.164.330 Rp 103.509.996
2.5.2.3. PEKERJAAN PENGECORAN BALOK 2.6.2.3. PEKERJAAN PENGECORAN BALOK 2.7.2.3. PEKERJAAN PENGECORAN BALOK 2.8.2.3. PEKERJAAN PENGECORAN PLAT
LT 4 LT 5 LT 6 LT ATAP
Rp 43.895.216 Rp 43.895.216 Rp 43.895.216 Rp 68.164.814

2.5.3. PEKERJAAN PLAT LT 4 2.6.3. PEKERJAAN PLAT LT 5 2.7.3. PEKERJAAN PLAT LT 6

2.5.3.1. PEKERJAAN PEMBESIAN PLAT LT 4 2.6.3.1. PEKERJAAN PEMBESIAN PLAT LT 5 2.7.3.1. PEKERJAAN PEMBESIAN PLAT LT 6
Rp 40.400.272 Rp 40.400.272 Rp 40.400.272
2.5.3.2. PEKERJAAN BEKISTING PLAT LT 4 2.6.3.2. PEKERJAAN BEKISTING PLAT LT 5 2.7.3.2. PEKERJAAN BEKISTING PLAT LT 6
Rp 96.703.833 Rp 96.703.833 Rp 96.703.833
2.5.3.3. PEKERJAAN PENGECORAN PLAT 2.6.3.3. PEKERJAAN PENGECORAN PLAT 2.7.3.3. PEKERJAAN PENGECORAN PLAT
LT 4 LT 5 LT 6
Rp 68.164.814 Rp 68.164.814 Rp 68.164.814
2.5.4. PEKERJAAN TANGGA LT 4 2.6.4. PEKERJAAN TANGGA LT 5 2.7.4. PEKERJAAN TANGGA LT 6
Rp 15.856.436 Rp 15.856.436 Rp 15.856.436
2.5.3.1. PEKERJAAN PEMBESIAN TANGGA 2.6.3.1. PEKERJAAN PEMBESIAN TANGGA 2.7.3.1. PEKERJAAN PEMBESIAN TANGGA
LT 4 LT 5 LT 6
Rp 8.849.201 Rp 8.849.201 Rp 8.849.201
2.5.3.2. PEKERJAAN BEKISTING TANGGA 2.6.3.2. PEKERJAAN BEKISTING TANGGA 2.7.3.2. PEKERJAAN BEKISTING TANGGA
LT 4 LT 5 LT 6
Rp 2.194.409 Rp 2.194.409 Rp 2.194.409
2.5.3.3. PEKERJAAN PENGECORAN 2.6.3.3. PEKERJAAN PENGECORAN 2.7.3.3. PEKERJAAN PENGECORAN
TANGGA LT 4 TANGGA LT 5 TANGGA LT 6
Rp 4.812.825 Rp 4.812.825 Rp 4.812.825