RENCANA ANGGARAN BIAYA

PEMBANGUNAN JEMABATAN WISATA DAN PENGHUBUNG

TAHUN 2022

KABUPATEN BANTUL
DAERAH ISTIMEWA YOGYAKARTA
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBANGUNAN JEMBATAN WISATA DAN PENGHUBUNG


LOKASI : KABUPATEN BANTUL DIY
TAHUN ANGGARAN : 2022

TOTAL
NO. URAIAN PEKERJAAN
Sub Total Jumlah Total

REKAPITULASI TOTAL

1 Divisi 1 UMUM (MOBILISASI DAN K3)


mobilisasi 21,954,000.00 21,954,000.00
SMK 28,797,000.00 28,797,000.00
2 Pekerjaan Struktur Jembatan
- Jembatan 2,344,008,857.30 2,344,008,857.30
- Pekerjaan Lain-lain 82,718,513.71 82,718,513.71

Sub Total 2,477,478,371.01


PPN 11% 272,522,620.81
Total 2,750,000,991.82
Dibulatkan 2,750,000,000.00

Terbilang : Dua Milliar Tujuh Ratus Lima Puluh Juta Rupiah


RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBANGUNAN JEMBATAN WISATA DAN PENGHUBUNG


LOKASI : KABUPATEN BANTUL DIY
TAHUN ANGGARAN : 2022

PEKERJAAN STRUKTUR JEMBATAN


Harga Satuan Jumlah
No. Uraian Pekerjaan SAT Volume
( Rp. ) ( Rp. )
1 2 3 4 5 6=4X5

1 PEKERJAAN STRUKTUR JEMBATAN


1 Pek. Pondasi Pondasi Bore Pile
- Pengeboran Tanah Sedalam 2 m m1 24.00 150,000.00 3,600,000.00
- Beton struktur, fc’30 MPa m3 5.18 1,854,319.79 9,607,230.86
- Baja Tulangan Sirip BjTS 280 kg 645.25 19,484.64 12,572,504.68
- Pembuangan Tanah Sisa Galian m3 5.18 51,064.82 264,566.81
2 Pek. Urugan sirtu m3 2.10 201,293.59 422,716.54
3 Pek. Lantai kerja beton B0, t. 50 mm m3 0.61 1,102,824.66 673,936.15
4 Pek. Pilar ( 2 titik)
- Beton struktur, fc’30 MPa m3 34.47 1,854,319.79 63,918,403.33
- Baja Tulangan Sirip BjTS 280 kg 14,049.98 19,484.64 273,758,903.43
- Bekisting multipleks 12 mm m2 62.42 180,946.65 11,294,689.58
- Bekisting pas. Bata area floot m2 29.60 251,982.94 7,458,695.02
5 Pek. Balok Girder Uk.80/180
- Beton struktur, fc’30 MPa m3 51.97 1,854,319.79 96,365,291.10
- Baja Tulangan Sirip BjTS 280 kg 41,444.32 19,484.64 807,527,667.06
- Bekisting multipleks 12 mm m2 138.04 180,946.65 24,977,874.88
6 Pek. Balok Diafragma 20/70
- Beton struktur, fc’30 MPa m3 1.36 1,854,319.79 2,521,874.92
- Baja Tulangan Sirip BjTS 280 kg 1,123.36 19,484.64 21,888,265.51
- Bekisting multipleks 12 mm m2 13.60 180,946.65 2,460,874.37
Pek. Abutmen (2 titik)
- Beton struktur, fc’30 MPa m3 56.77 1,854,319.79 105,273,443.39
- Baja Tulangan Sirip BjTS 280 kg 8,354.61 19,484.64 162,786,609.54
- Bekisting multipleks 12 mm m2 29.60 180,946.65 5,356,020.69
- Bekisting pas. Bata area floot m2 39.40 251,982.94 9,928,127.84
Pek. Balok Beton Uk.40/75
- Beton struktur, fc’30 MPa m3 7.68 1,854,319.79 14,241,176.02
- Baja Tulangan Sirip BjTS 280 kg 13,969.41 19,484.64 272,188,889.87
- Bekisting multipleks 12 mm m2 24.32 180,946.65 4,400,622.41
Pek. Balok Diafragma 20/55
- Beton struktur, fc’30 MPa m3 0.95 1,854,319.79 1,765,312.44
- Baja Tulangan Sirip BjTS 280 kg 756.16 19,484.64 14,733,505.60
- Bekisting multipleks 12 mm m2 9.52 180,946.65 1,722,612.06
7 Pek. Pelat Lantai Jembatan
- Beton struktur, fc’30 MPa m3 23.85 1,854,319.79 44,221,818.47
- Baja Tulangan Sirip BjTS 280 kg 3,982.08 19,484.64 77,589,396.39
- Bekisting multipleks 12 mm m2 124.44 180,946.65 22,517,000.50
Pek. Struktur beton Pelengkung
- Beton struktur, fc’30 MPa m3 1.47 1,854,319.79 2,725,850.10
- Baja Tulangan Sirip BjTS 280 kg 1,400.56 19,484.64 27,289,407.80
- Bekisting multipleks 12 mm m2 18.20 180,946.65 3,293,228.94
8 Pek. Struktur Hand Railing
- Beton struktur K-125 m3 0.69 1,102,824.66 759,294.78
- Baja Tulangan Sirip BjTS 280 kg 1,534.76 19,484.64 29,904,246.52
- Bekisting multipleks 12 mm m2 20.40 180,946.65 3,691,311.56
- Pipa Besi galvanis 2,5 inch m 198.00 199,324.58 39,466,267.04
Pek. Tiang beton di oprit
Harga Satuan Jumlah
No. Uraian Pekerjaan SAT Volume
( Rp. ) ( Rp. )
1 2 3 4 5 6=4X5
- Beton struktur, K-125 m3 0.45 1,102,824.66 496,271.10
- Baja Tulangan Sirip BjTS 280 kg 902.80 19,484.64 17,590,733.25
- Bekisting multipleks 12 mm m2 12.00 180,946.65 2,171,359.74
Pek. Pasang baja siku variasi jembatan
- Baja siku 150.150.10 kg 1,680.00 70,185.37 117,911,421.80
Pek. Pasang railing variasi jembatan
- Pipa galvanis 2 ich m 74.16 181,174.58 13,435,906.93
Pek. Struktur dudukan tiang
- Beton struktur m3 0.40 1,102,824.66 436,718.57
- Angkur m12 bh 88.00 24,398.34 2,147,053.97
- Bekisting multipleks 12 mm m2 22.00 180,946.65 3,980,826.19
- Baseplat t = 5 mm kg 58.41 45,727.27 2,670,929.55
JUMLAH I 2,344,008,857.30
2 PEKERJAAN LAIN-LAIN
1 Pas. Batu pondasi 1SP: 5PP M3 6.00 1,129,428.82 6,776,572.90
2 Plesteran 1PC:5PP Tebal 15mm m2 19.12 103,757.19 1,983,837.47
3 Acian m2 19.12 58,834.73 1,124,920.08
4 Pekerjaan pengecatan handrill/Galvanis m2 39.56 249,270.56 9,861,143.35
5 Pekerjaan pengecatan tiang handrill M2 32.40 62,122.18 2,012,758.54
6 Pekerjaan pengecatan besi siku 150.150.15 m 81.00 45,741.21 3,705,038.36
7 Pekerjaan pengecatan tiang besi/galvanis m2 30.00 249,270.56 7,478,116.80
8 Pekerjaan LPA kelas A M3 29.70 524,248.92 15,570,192.80
9 Pekerjaan LPA kelas B M3 34.65 377,848.36 13,092,445.52
10 pasang karet lastomer bh 16.00 500,000.00 8,000,000.00
11 Pekerjaan aspal AC WC (oprit dan lantai jembatan) Ton 14.7 892,074.01 13,113,487.88
JUMLAH II 82,718,513.71
JUMLAH TOTAL 2,426,727,371.01
HARGA SATUAN PEKERJAAN

JUMLAH JASA 10% HARGA SATUAN


NO. URAIAN PEKERJAAN
(Rp) (Rp) (Rp)
1 2 3 4=(10%X3) 5=(3+4)

A. 2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 M3 PEMBUANGAN TANAH SEJAUH 30 METER 46,422.56 4,642.26 51,064.82
1 M3 PENGURUGAN DENGAN PASIR URUG 260,215.07 26,021.51 286,236.58
1 M3 PENGURUGAN SIRTU PADAT 182,994.18 18,299.42 201,293.59
A. 4.1.1 HARGA SATUAN PEKERJAAN BETON
1 M3 BETON UNTUK LANTAI KERJA (Membuat Beton Campuran 1 PC : 2 PSR : 5 SPLT) 1,002,567.87 100,256.79 1,102,824.66
1 M3 BETON Fc 30 Mpa 1,685,745.27 168,574.53 1,854,319.79
1 M2 PASANG BEGISTING MULTIPLEKS 12 mm 164,496.95 16,449.70 180,946.65
1 KG PEMASANGAN BESI BETON 17,713.31 1,771.33 19,484.64
A. 4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
1 M2 PENGECATAN BAJA ZINCROMATE DUA LAPIS 41,582.92 4,158.29 45,741.21
1 M2 PENGECATAN PIPA GALVANIS MANUAL 3 LAPIS 226,609.60 22,660.96 249,270.56
1 M2 PENGECATAN TEMBOK BARU 56,474.71 5,647.47 62,122.18
1 KG PEMASANGAN BAJA PLAT 41,570.24 4,157.02 45,727.27
1 M1 CERUCUK DOLKEN 29,008.47 2,900.85 31,909.32
HARGA SATUAN PEKERJAAN PLESTERAN
1 M2 PEKERJAAN ACIAN 53,486.12 5,348.61 58,834.73
1 M2 PEKERJAAN PLESTERAN 94,324.72 9,432.47 103,757.19
1 M2 PEMSANGAN DINDING BATA MERAH 229,075.40 22,907.54 251,982.94
1 M3 PEMASANGAN PONDASI BATU BELAH CAMPURAN 1:5 PP 1,026,753.47 102,675.35 1,129,428.82
ANALISA SATUAN PEKERJAAN
HARGA SATUAN UPAH BAHAN ALAT JUMLAH
NO URAIN PEKERJAAN KODE SAT. KOEFISIEN
Rp Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9 10

A. 2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 M3 PEMBUANGAN TANAH SEJAUH 30 METER
Pekerja OH 0.330 133,583.00 44,082.39
Mandor OH 0.010 234,017.00 2,340.17
Jumlah 46,422.56 - - 46,422.56
1 M3 PENGURUGAN DENGAN PASIR URUG
Pekerja OH 0.300 133,583.00 40,074.90
Mandor OH 0.010 234,017.00 2,340.17
3 1.200
Pasir urug M 181,500.00 217,800.00
Jumlah 42,415.07 217,800.00 - 260,215.07
1 M3 PENGURUGAN SIRTU PADAT
Pekerja OH 0.250 133,583.00 33,395.75
Mandor OH 0.025 234,017.00 5,850.43
3 1.200
Sirtu M 119,790.00 143,748.00
Jumlah 39,246.18 143,748.00 - 182,994.18
A. 4.1.1 HARGA SATUAN PEKERJAAN BETON
1 M3 BETON UNTUK LANTAI KERJA (Membuat Beton Campuran 1 PC : 2 PSR : 5 SPLT)
Pekerja OH 1.650 133,583.00 220,411.95
Tukang Batu OH 0.275 166,985.00 45,920.88
Kepala Tukang Batu OH 0.028 200,435.00 5,612.18
Mandor OH 0.083 234,017.00 19,423.41
Semen portland kg 247.000 1,762.00 435,214.00
3 0.575
Pasir Beton M 242,000.00 139,228.57
Kerikil Beton M3 0.689 183,517.00 126,436.88
Air L 215.000 48.00 10,320.00
Jumlah 291,368.42 711,199.46 - 1,002,567.87
1 M3 BETON MUTU TINGGI Fc 30 Mpa
Pekerja OH 1.650 133,583.00 220,411.95
Tukang Batu OH 0.275 166,985.00 45,920.88
Kepala Tukang Batu OH 0.028 200,435.00 5,612.18
Mandor OH 0.083 234,017.00 19,423.41
Semen portland kg 413.000 1,762.00 727,706.00
Pasir Beton m3 0.486 242,000.00 117,612.00
Kerikil Beton m3 0.756 183,517.00 138,738.85
Air L 215.000 48.00 10,320.00
alat bantu (pompa beton,vibrator,genset) ls 1.000 400,000.00 400,000.00
291,368.42 994,376.85 400,000.00 1,685,745.27
A. 4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
1 M2 PENGECATAN BAJA ZINCROMATE DUA LAPIS
Pekerja OH 0.020 133,583.00 2,671.66
Tukang Cat OH 0.200 166,985.00 33,397.00
Kepala Tukang Cat OH 0.020 200,435.00 4,008.70
Mandor OH 0.003 234,017.00 585.04
Zincromate kg 0.010 47,575.00 475.75
Thinner ltr 0.003 51,326.00 138.58
Amplas lbr 0.007 29,282.00 196.19
Kuas bh 0.010 11,000.00 110.00
Jumlah 40,662.40 920.52 - 41,582.92
1 M2 PASANG BEGISTING MULTIPLEKS 12 mm
Pekerja OH 0.1200 133,583.00 16,029.96
Tukang Kayu OH 0.1500 166,985.00 25,047.75
Kepala Tukang OH 0.1500 200,435.00 30,065.25
Tukang kayu 1/2 terampil (bongkar cetakan) OH 0.1200 234,017.00 28,082.04
Mandor OH 0.0500 47,575.00 2,378.75
Kaso 5/7 Albasia (2 x pakai) 50% M3 0.0170 900,000.00 15,300.00
Multipleks 12 mm (2 x pakai) 75% Lbr 0.3470 120,000.00 41,640.00
Paku Biasa 2" - 5" Kg 0.4000 14,883.00 5,953.20
Jumlah 101,603.75 - 62,893.20 164,496.95
1 KG PEMASANGAN BAJA PLAT
Pekerja OH 0.060 133,583.00 8,014.98
Tukang Besi OH 0.060 166,985.00 10,019.10
Keapala Tukang Besi OH 0.006 200,435.00 1,202.61
Mandor OH 0.003 234,017.00 702.05
Besi plat 2-5 mm, rata - rata kg 1.150 18,810.00 21,631.50
Jumlah 19,938.74 21,631.50 - 41,570.24
1 M1 CERUCUK DOLKEN
Pekerja OH 0.100 133,583.00 13,358.30
Mandor OH 0.010 234,017.00 2,340.17
Kayu dolken Ø 8-10/400 cm btg 0.250 53,240.00 13,310.00
Jumlah 15,698.47 - 13,310.00 29,008.47
1 M3 PENGURUGAN SIRTU PADAT
Pekerja OH 0.250 133,583.00 33,395.75
Mandor OH 0.025 234,017.00 5,850.43
3 1.200
Sirtu M 119,790.00 143,748.00
Jumlah 39,246.18 143,748.00 - 182,994.18
1 M3 PEMASANGAN PONDASI BATU BELAH CAMPURAN 1:5 PP
Pekerja OH 1.500 133,583.00 200,374.50
Tukang Batu OH 0.750 166,985.00 125,238.75
Kepala Tukang Batu OH 0.075 200,435.00 15,032.63
Mandor OH 0.075 234,017.00 17,551.28
Batu Belah M3 1.200 251,570.00 301,884.00
Semen portland Kg 136.000 1,762.00 239,632.00
Pasir pasang M3 0.544 233,530.00 127,040.32
Jumlah 358,197.15 668,556.32 - 1,026,753.47
1 KG PEMASANGAN PEMBESIAN BETON
Pekerja OH 0.001 133,583.00 126.90
Tukang Batu OH 0.010 166,985.00 1,586.36
Kepala Tukang Batu OH 0.008 200,435.00 1,603.48
Mandor OH 0.004 234,017.00 936.07
Besi beton kg 1.050 8,000.00 8,400.00
kawat beton Kg 0.003 24,200.00 60.50
alat bantu ls 1.000 5,000.00 5,000.00
Jumlah 4,252.81 13,460.50 - 17,713.31
1 M2 PEKERJAAN PLESTERAN
Pekerja OH 0.300 133,583.00 40,074.90
Tukang Batu OH 0.150 166,985.00 25,047.75
Kepala Tukang Batu OH 0.015 200,435.00 3,006.53
Mandor OH 0.015 234,017.00 3,510.26
Semen portland Kg 10.224 1,762.00 18,014.69
Paisr pasang m3 0.020 233,530.00 4,670.60
Jumlah 71,639.43 22,685.29 94,324.72
1 M2 PEKERJAAN ACIAN
Pekerja OH 0.200 133,583.00 26,716.60
Tukang Batu OH 0.100 166,985.00 16,698.50
Kepala Tukang Batu OH 0.010 200,435.00 2,004.35
Mandor OH 0.010 234,017.00 2,340.17
Semen portland Kg 3.250 1,762.00 5,726.50
Jumlah 47,759.62 5,726.50 53,486.12
1 M2 PENGECATAN PIPA GALVANIS MANUAL 3 LAPIS
Pekerja OH 0.400 133,583.00 53,433.20
Tukang Cat OH 0.800 166,985.00 133,588.00
Kepala Tukang Cat OH 0.080 200,435.00 16,034.80
Mandor OH 0.020 234,017.00 4,680.34
Cat dasar kg 0.110 46,000.00 5,060.00
Cat antara kg 0.170 55,000.00 9,350.00
Cat penutup kg 0.080 48,000.00 3,840.00
Kuas bh 0.010 11,000.00 110.00
Pengencer lt 0.010 51,326.00 513.26
Jumlah 207,736.34 18,873.26 - 226,609.60
1 M2 PENGECATAN TEMBOK BARU
Pekerja OH 0.200 133,583.00 26,716.60
Tukang Cat OH 0.063 166,985.00 10,520.06
Kepala Tukang Cat OH 0.006 200,435.00 1,262.74
Mandor OH 0.003 234,017.00 702.05
Cat dasar kg 0.260 46,000.00 11,960.00
Cat penutup kg 0.100 48,000.00 4,800.00
Pengencer lt 0.010 51,326.00 513.26
Jumlah 39,201.45 17,273.26 - 56,474.71
1 M2 PASANG BATA MERAH
Pekerja OH 0.600 133,583.00 80,149.80
Tukang Batu OH 0.200 166,985.00 33,397.00
Kepala Tukang OH 0.020 200,435.00 4,008.70
Mandor OH 0.030 234,017.00 7,020.51
Bata merah bh 60.000 600.00 36,000.00
semen kg 26.550 1,762.00 46,781.10
pasir pasang m3 0.093 233,530.00 21,718.29
Jumlah 124,576.01 104,499.39 - 229,075.40
HARGA DASAR SATUAN UPAH & ALAT
HARGA HARGA
No. URAIAN KODE SATUAN YG DIGUNAKAN SATUAN
( Rp.) ( Rp.)

1. Pekerja Jam 19,083.29 133,583.00


2. Tukang Jam 23,855.00 166,985.00
3. Mandor Jam 33,431.00 234,017.00
4. Operator Jam 23,855.00 166,985.00
5. Pembantu Operator Jam 19,083.29 133,583.00
6. Sopir / Driver Jam 23,855.00 166,985.00
7. Pembantu Sopir / Driver Jam 19,083.29 133,583.00
8. Mekanik Jam 23,855.00 166,985.00
9. Pembantu Mekanik Jam 19,083.29 133,583.00
10. Kepala Tukang Jam 28,633.57 200,435.00
11. Wheel Loader Jam 390,576.88
12 Dump Truck Jam 243,029.43
13 Motor Grader Jam 325,476.80
14 Vibratory Roller Jam 206,022.72
15 Pengeboran Tanah Sedalam 2 m m 150,000.00
16 alat bantu (pompa beton,vibrator,genset) ls 400,000.00
17 alat bantu (cangku,balincong,skop) ls 5,000.00
18 alat bantu (alat las,genset,driill machine,hacksw,gerinda)) Jam 25,000.00
19 AMP Jam 4,932,070.63
20 Genset Jam 200,865.37
21 Dump Truck Jam 243,029.43
22 Asp. Finisher Jam 240,126.68
23 Tandem Roller Jam 368,467.78
24 P. Tyre Roller Jam 371,792.43
DAFTAR
HARGA DASAR SATUAN BAHAN
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)

1 Pasir Pasang (Sedang) M3 233,530.00


2 Pasir Beton (Kasar) M3 242,000.00
3 Batu Kali M3 228,700.00
4 Agregat Pecah Kasar M3 183,517.00
5 Bahan Tanah Timbunan M3 35,796.00
6 Aspal Kg 7,812.00
7 Semen / PC (kg) Kg 1,762.00
8 Kawat Beton Kg 24,200.00
9 Paku Kg 19,010.00
10 Kayu Perancah M3 1,613,333.00
11 Agr. Kelas A (analisis) M3 359,266.86
12 Agr. Kelas B (analisis) M3 259,689.19
13 Baja Tulangan Kg 10,300.00
14 Agregat Pecah Mesin 0-5 mm M3 205,000.00
15 Agregat Pecah Mesin 5-10 & 10-20 mm M3 205,000.00
16 Aspal Emulsi CSS-1 atau SS-1 Liter 15,125.00
18 Air Liter 48.00
19 Plastizier' Kg 40,000.00
20 Perancah/ formwoks m2 45,000.00
21 Sirtu m3 119,790.00
22 Zincromate kg 47,575.00
23 Thinner ltr 51,326.00
24 Amplas lbr 29,282.00
25 Kuas bh 11,000.00
26 Kaso 5/7 Albasia (2 x pakai) 50% M3 900,000.00
27 Multipleks 12 mm (2 x pakai) 75% Lbr 120,000.00
28 Paku Biasa 2" - 5" Kg 14,883.00
29 Besi plat 2-5 mm, rata - rata kg 18,810.00
30 Kayu dolken Ø 8-10/400 cm m 53,240.00
31 Batu Belah m3 251,570.00
32 Cat dasar kg 46,000.00
33 Cat antara kg 55,000.00
34 Cat penutup kg 48,000.00
35 Bata merah bh 600.00
36 Besi beton kg 8,000.00
37 kawat beton kg 24,200.00
38 Aggregat B m3 259,689.19
39 Lastomer bh 500,000.00
40 Aspal kg 7,812.00
41 Pipa Galvanis 2,5 inch m 140,000.00
42 Pipa Galvanis 2 inch m 125,000.00
43 Angkur m12 bh 15,000.00
44 Baja siku 150 kg 25,000.00
45 baut bh 10,000.00
RENCANA ANGGARAN BIAYA (RAB) SMK

PEKERJAAN PEMBANGUNAN JEMBATAN WISATA DAN PENGHUBUNG


LOKASI KABUPATEN BANTUL DIY
TAHUN ANGGARAN 2022
1 PEKERJAAN PERSIAPAN
Harga Satuan Jumlah
No. Uraian Pekerjaan SAT Volume
( Rp. ) ( Rp. )
1 2 3 4 5 6=4X5

PEKERJAAN PERSIAPAN
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja Dan bh 1.00 200,000.00 200,000.00
Pembuatan Kartu Identitas Pekerja (KIP);
Sosialisasi dan Promosi K3 terdiri
1 atas:
Pengarahan K3 (safety briefing) : Pertemuan
Keselamatan (Safety Talk dan/atau Tool Box org 3.00 50,000.00 150,000.00
Meeting) ;
Spanduk (banner) ; bh 1.00 100,000.00 100,000.00
Poster; bh 1.00 75,000.00 75,000.00
Papan Informasi K3. bh 1.00 142,000.00 142,000.00
Alat Pelindung Diri terdiri atas:
2 -

Topi Pelindung (Safety Helmet) ;


bh 18.00 100,000.00 1,800,000.00
Pelindung Mata (Goggles, Spectacles);
bh 5.00 55,000.00 275,000.00
Tameng Muka (Face Shield);
psg 15.00 75,000.00 1,125,000.00
Masker (Breathing Apparatus);
psg 15.00 10,000.00 150,000.00
Pelindung Pernafasan Dan Mulut (Masker);
psg 15.00 30,000.00 450,000.00
Sarung Tangan (Safety Gloves); psg 15.00 25,000.00 375,000.00
Sepatu Keselamatan (Safety Shoes);
psg 15.00 250,000.00 3,750,000.00
Penunjang Seluruh Tubuh (Full Body
Harness);
psg 5.00 1,000,000.00 5,000,000.00
Rompi Keselamatan (Safety Vest);
psg 15.00 15,000.00 225,000.00
Asuransi Dan Perijinan terdiri atas
3 -
:
BPJS Ketenagakerjaan Dan Kesehatan
Kerja; ls 1.00 3,000,000.00 3,000,000.00

4 Personil K3 terdiri atas :


Ahli K3
Petugas Tanggap Darurat; -
Petugas P3K; org 1.00 1,500,000.00 1,500,000.00
Petugas Pengatur Lalu Lintas
(Flagman ); 1.00 2,000,000.00 2,000,000.00
org
Petugas Medis. -
5 Fasilitas sarana kesehatan; -
Peralatan P3K dan prokes covid 19
(Kotak P3K, Tandu, Tabung Oksigen,
Obat Luka, Perban, bak
1.00 3,000,000.00 3,000,000.00
cuci,sabun,masker,handystaizer) ls
6 Rambu- Rambu terdiri atas : -
Rambu Petunjuk; bh 1.00 100,000.00 100,000.00
Rambu Larangan; bh 3.00 10,000.00 30,000.00
Rambu Peringatan; bh 1.00 100,000.00 100,000.00
Rambu Kewajiban; bh 1.00 100,000.00 100,000.00
Rambu Informasi; bh 1.00 50,000.00 50,000.00
Rambu Pekerjaan Sementara; bh 1.00 600,000.00 600,000.00
Tongkat Pengatur Lalu Lintas (Warning
1.00 2,500,000.00 2,500,000.00
Lights Stick) ;
bh
Kerucut Lalu Lintas (Traffic Cone) ; bh 2.00 500,000.00 1,000,000.00
Lampu Putar (Rotary Lamp ); bh 1.00 1,000,000.00 1,000,000.00

JUMLAH 1. 28,797,000.00
ITEM PEMBAYARAN NO. : 1.2
JENIS PEKERJAAN : MOBILISASI

% TERHADAP TOTAL BIAYA PROYEK =


Lembar 1.2-1
HARGA JUMLAH
No. URAIAN SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)

A. Sewa Tanah M2 35 150,000 5,250,000

B. PERALATAN
Periksa lembar 1.2-2

C. Kantor Lapangan dan Fasilitas 1 6,704,000 6,704,000


1 Base Camp
2 Kantor
3 Barak
4 Bengkel
5 Gudang, dan lain-lain
6 ...................... ....

D. MOBILISASI FASILITAS LABORATORIUM


4 Concrete Testing
Slump Cone
Cylinder/Cube Mould for Compressive Strength
Beam Mould for Flexural Strength (RIGID)
Crushing Machine

G. MOBILISASI & DEMOBILISASI LS 1 10,000,000 10,000,000

Total Biaya Mobilisasi 21,954,000


Analisa EI-635a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. PERKIRAAN VOL. PEK. :


JENIS PEKERJAAN : Laston Lapis Aus (AC-WC) TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : Ton % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.2008 19,083.29 3,831.99


2. Mandor (L03) Jam 0.0201 33,431.00 671.31

JUMLAH HARGA TENAGA 4,503.29

B. BAHAN

1. Agr Pch Mesin 5-10 & 10-15


(M92) M3 0.3206 205,000.00 65,716.48
2. Agr Pch Mesin 0 - 5 (M91) M3 0.4193 205,000.00 85,953.24
3 Semen (M12) Kg 9.6820 1,762.00 17,059.68
4 Aspal (M10) Kg 62.3150 7,812.00 486,804.78

JUMLAH HARGA BAHAN 655,534.18

C. PERALATAN
1. Wheel Loader E15 Jam 0.0054 390,576.88 2,097.03
2. AMP E01 Jam 0.0201 4,932,070.63 99,037.56
3. Genset E12 Jam 0.0201 200,865.37 4,033.44
4. Dump Truck E09 Jam 0.0362 243,029.43 8,790.59
5. Asp. Finisher E02 Jam 0.0125 240,126.68 3,008.00
6. Tandem Roller E17a Jam 0.0128 368,467.78 4,700.24
7 P. Tyre Roller E18 Jam 0.0084 371,792.43 3,126.16
8 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 124,793.03

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 784,830.50


E. OVERHEAD & PROFIT 10.0 % x D 78,483.05
F. HARGA SATUAN PEKERJAAN ( D + E ) 863,313.55
Analisa EI-611

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. PERKIRAAN VOL. PEK. :


JENIS PEKERJAAN : Lapis Resap Pengikat - Aspal Cair/Emulsi TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : Liter % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0015 19,083.29 27.95


2. Mandor (L03) Jam 0.0007 33,431.00 24.49

JUMLAH HARGA TENAGA 52.44

B. BAHAN

1. Aspal Emulsi CSS-1 (M31a) Liter 1.7167 15,125.00 25,964.58


atau SS-1

JUMLAH HARGA BAHAN 25,964.58

C. PERALATAN

1. Asp. Distributor E41 Jam 0.00020 285,198.37 57.27


2. Compressor E05 Jam 0.00073 97,729.88 71.58

JUMLAH HARGA PERALATAN 128.85

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 26,145.87


E. OVERHEAD & PROFIT 10.0 % x D 2,614.59
F. HARGA SATUAN PEKERJAAN ( D + E ) 28,760.46
Analisa EI-611

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. PERKIRAAN VOL. PEK. :


JENIS PEKERJAAN : Lapis Resap Pengikat - Aspal Cair/Emulsi TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : Liter % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0015 19,083.29 27.95


2. Mandor (L03) Jam 0.0007 33,431.00 24.49

JUMLAH HARGA TENAGA 52.44

B. BAHAN

1. Aspal Emulsi CSS-1 (M31a) Liter 1.7167 15,125.00 25,964.58


atau SS-1

JUMLAH HARGA BAHAN 25,964.58

C. PERALATAN

1. Asp. Distributor E41 Jam 0.00020 285,198.37 57.27


2. Compressor E05 Jam 0.00073 97,729.88 71.58

JUMLAH HARGA PERALATAN 128.85

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 26,145.87


E. OVERHEAD & PROFIT 10.0 % x D 2,614.59
F. HARGA SATUAN PEKERJAAN ( D + E ) 28,760.46
Note: 1 Satuan dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-511

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 5.1.(1) PERKIRAAN VOL. PEK. : #REF!


JENIS PEKERJAAN : Lapis Fondasi Agregat Kelas A TOTAL HARGA : #REF!
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : #REF!

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.0779 19,083.29 1,486.55


2. Mandor (L03) jam 0.0097 33,431.00 325.53

JUMLAH HARGA TENAGA 1,812.07

B. BAHAN

1. Agregat A M26 M3 1.2890 359,266.86 463,082.60

JUMLAH HARGA BAHAN 463,082.60

C. PERALATAN
1. Wheel Loader (E15) jam 0.0087 390,576.88 3,398.06
2. Dump Truck (E09) jam 0.0246 243,029.43 5,979.55
3. Motor Grader (E13) jam 0.0010 325,476.80 311.55
4. Vibratory Roller (E19a) jam 0.0097 206,022.72 2,006.09
5 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 11,695.25

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 476,589.92


E. OVERHEAD & PROFIT 10.0 % x D 47,658.99
F. HARGA SATUAN PEKERJAAN ( D + E ) 524,248.92
Analisa EI-512

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. PERKIRAAN VOL. PEK. :


JENIS PEKERJAAN : Lapis Fondasi Agregat Kelas B TOTAL HARGA :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.0779 19,083.29 1,486.55


2. Mandor (L03) jam 0.0097 33,431.00 325.53

JUMLAH HARGA TENAGA 1,812.07

B. BAHAN

1. Aggregat B M27 M3 1.2714 259,689.19 330,176.26

JUMLAH HARGA BAHAN 330,176.26

C. PERALATAN
1. Wheel Loader (E15) jam 0.0086 390,576.88 3,351.83
2. Dump Truck (E09) jam 0.0240 243,029.43 5,840.70
3. Motor Grader (E13) jam 0.0010 325,476.80 311.55
4. Vibratory Roller (E19a) jam 0.0097 206,022.72 2,006.09
5 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 11,510.17

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 343,498.51


E. OVERHEAD & PROFIT 10.0 % x D 34,349.85
F. HARGA SATUAN PEKERJAAN ( D + E ) 377,848.36
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK
No. PAKET KONTRAK
NAMA PAKET
PROP / KAB / KODYA
ITEM PEMBAYARAN NO. PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN Angkur m12 TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa jam 0.1000 19,083.29 1,908.33


2. Tukang jam 0.0100 23,855.00 238.55
3. Mandor jam 0.0010 33,431.00 33.43

JUMLAH HARGA TENAGA 2,180.31

B. BAHAN

1.
2. Angkur m12 bh 1.0000 15,000.00 15,000.00

JUMLAH HARGA BAHAN 15,000.00


C. PERALATAN

1. Alat Bantu Jam 1.0000 5,000.00 5,000.00


2.
3.

JUMLAH HARGA PERALATAN 5,000.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 22,180.31


E. OVERHEAD & PROFIT 10.0 % x D 2,218.03
F. HARGA SATUAN PEKERJAAN ( D + E ) 24,398.34
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK
NAMA PAKET
PROP / KAB / KODYA DIY/BANTUL
ITEM PEMBAYARAN NO. PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN Pipa Galvanis 2 inch TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa jam 0.1000 19,083.29 1,908.33


2. Tukang jam 0.0110 23,855.00 262.41
3. Mandor jam 0.0010 33,431.00 33.43

JUMLAH HARGA TENAGA 2,204.16

B. BAHAN

1. Pipa Galvanis 2 inch m 1.1000 125,000.00 137,500.00


2.

JUMLAH HARGA BAHAN 137,500.00


C. PERALATAN

1. Alat Bantu Jam 1.0000 25,000.00 25,000.00


2.
3.

JUMLAH HARGA PERALATAN 25,000.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 164,704.16


E. OVERHEAD & PROFIT 10.0 % x D 16,470.42
F. HARGA SATUAN PEKERJAAN ( D + E ) 181,174.58
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK
NAMA PAKET
PROP / KAB / KODYA DIY/BANTUL
ITEM PEMBAYARAN NO. PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN PIPA GALVANIS 2,5 Inch TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa jam 0.1000 19,083.29 1,908.33


2. Tukang jam 0.0110 23,855.00 262.41
3. Mandor jam 0.0010 33,431.00 33.43

JUMLAH HARGA TENAGA 2,204.16

B. BAHAN

1. Pipa Galvanis 2,5 inc m 1.1000 140,000.00 154,000.00


2.

JUMLAH HARGA BAHAN 154,000.00


C. PERALATAN

1. Alat Bantu Jam 1.0000 25,000.00 25,000.00


2.
3.

JUMLAH HARGA PERALATAN 25,000.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 181,204.16


E. OVERHEAD & PROFIT 10.0 % x D 18,120.42
F. HARGA SATUAN PEKERJAAN ( D + E ) 199,324.58
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK
NAMA PAKET
PROP / KAB / KODYA
ITEM PEMBAYARAN NO. PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN Baja siku 150.150.15 TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa jam 0.0050 19,083.29 95.42


2. Tukang jam 0.0500 23,855.00 1,192.75
3. Mandor jam 0.0005 33,431.00 16.72

JUMLAH HARGA TENAGA 1,304.88

B. BAHAN

1. Baja siku 150.150.15 kg 1.1000 25,000.00 27,500.00


2. baut bh 1.0000 10,000.00 10,000.00

JUMLAH HARGA BAHAN 37,500.00


C. PERALATAN

1. Alat Bantu Jam 1.0000 25,000.00 25,000.00


2.
3.

JUMLAH HARGA PERALATAN 25,000.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 63,804.88


E. OVERHEAD & PROFIT 10.0 % x D 6,380.49
F. HARGA SATUAN PEKERJAAN ( D + E ) 70,185.37