Anda di halaman 1dari 7

BQ

PEKERJAAN JEMBATAN PERUMAHAN GEDEG


NO PEKERJAAN VOLUME SATUAN HARGA JUMLAH
1 Persiapan
a. Site survey 1 ls 5000000 5000000
b. Sosialisasi 1 ls 5000000 5000000
c. Fasilitas dan alat bantu 1 ls 4500000 4500000
d. Management project 8 mg 5000000 40000000
Sub totsl 54500000
2 Pekerjaan Tanah
a. Setting Out 1 ls 5000000 5000000
b. mob demob 1 ls 10000000 10000000
c. Excavation 228 m3 125000 28500000
d. perapaian 1 ls 1500000 1500000
Sub totsl 45000000
3 Pekerjaan Stros
a. mobdemob 1 ls 1500000 1500000
b. Besi D13 1153 kg 11000 12683000
c. besi 12 723 kg 11000 7953000
d. Fabrikasi besi 1876 kg 2000 3752000
e. Brton K 200 11.869 m3 2500000 29672500
f. Uparh bor dan cor 168 m1 140000 23520000
Sub totsl 14183000
4 Pekerjaan beton
1.Lean Concrete
a.Pasir 10 m3 250000 2592000
b. Semen 42 sak 60000 2520000
c. Pasangan batu parapet 3.15 m3 1900000 5985000
d. Begesting dan upah 9.84 m2 250000 2460000
f. Uparh cor 10.368 m3 250000 2592000
2. abutment
a.besi 16 7752 kg 11000 85272000
b.beton k300 80.286 m3 2700000 216772200
c. bekesting dan upah 147.16 m2 250000 36790000
d. fabrikasi besi 7752 kg 1500 11628000
e. upah cor 80.286 m3 200000 16057200
3. Balok Garder
a. Besi D 13 730.33 kg 11000 8033630
b. Besi 10 360.914 kg 11000 3970054
c.beton k300 10.388 m3 2700000 28047600
d.bekesting dan upah 68.635 m2 250000 17158750
f. fabrikasi besi 1091.244 kg 1500 1636866
g.upah cor 10.388 m3 200000 2077600
h. elstomer bearing pad 14 pcs 750000 10500000
4. Diafragma
a. Besi D 13 169.884 kg 11000 1868724
b. besi 10 104.755 kg 11000 1152305
c. beton k300 2.28 m3 2700000 6156000
d. Begesting dan upah 31.35 m2 250000 7837500
e. fabrikasi besi 274.639 kg 1500 411958.5
f. upah cor 2.28 m3 200000 456000
471975387.5
5 Plat Jembatan
a.besi D13 1061.178 kg 11000 11672958
b. beton k300 10.07 m3 2700000 27189000
c. bekesting dan upah 56.27 m2 250000 14067500
d.fabrikasi 1061.178 kg 1500 1591767
e.upah cor 10.07 m3 200000 2014000
Sub totsl 56535225
6 Plat Injak
a.Besi D 13 1009 kg 11000 11099000
b.Beton k 200 5.7 m3 2500000 14250000
c. bekesting dan upah 8.8 m2 250000 2200000
d.Fabrikasi besi 1009 kg 2000 2018000
e.Upah cor 5.7 m3 200000 1140000
Sub totsl 30707000
7 Wingwall 0
a. besi 12 351.461 kg 11000 3866071
b.beton k 200 3.744 m3 2500000 9360000
c.begesting dan upah 39.936 m2 250000 9984000
d.Fabrikasi besi 351.461 kg 2000 702922
e.Upah cor 3.744 m3 200000 748800
Sub total 24661793
8 Trotoar
a. besi 12 415.096 kg 11000 4566056
b.beton k 200 3.176 m3 2500000 7940000
c.begesting dan upah 27.515 m2 250000 6878750
d.Fabrikasi besi 415.096 kg 2000 830192
e.Upah cor 3.176 m3 200000 635200
Sub total 20850198
9 Tiang sandaran
a. besi 12 34.011 kg 11000 374121
b. besi 10 17.76 kg 11000 195360
b.beton k 200 0.157 m3 2500000 392500
c.begesting dan upah 0.578 m2 250000 144500
d.Fabrikasi besi 54.771 kg 2000 109542
e.Upah cor 0.157 m3 200000 31400
f. pipapa galvanis 3 inch 5 btg 1200000 6000000
7247423
10 Parapet
a. bata 10000 bj 600 6000000
b.pasir 3 m3 250000 750000
c.semen 30 zak 60000 1800000
d. upah pasang bata 1 ls 3000000 3000000
Sub total 11550000

Total Rp 850,280,477
Margin 15% Rp 21,257,011.91
Rp 871,537,488

Total 117653054
Analisa Harga Material
PEKERJAAN JEMBATAN PERUMAHAN GEDEG
NO PEKERJAAN VOLUME SATUAN HARGA JUMLAH
3 Pekerjaan Stros
b. Besi D13 1153 kg 11000 12683000
c. besi 12 723 kg 11000 7953000
e. Brton K 200 11.869 m3 2500000 29672500
f. Uparh bor dan cor 168 m1 140000 23520000
Sub totsl 12683000
Pekerjaan beton
1.Lean Concrete
4 a.Pasir 10 m3 250000 2592000
b. Semen 42 sak 60000 2520000
2. abutment
a.besi 16 7752 kg 11000 85272000
b.beton k300 80.286 m3 2700000 216772200
3. Balok Garder
a. Besi D 13 730.33 kg 11000 8033630
b. Besi 10 360.914 kg 11000 3970054
c.beton k300 10.388 m3 2700000 28047600
h. elstomer bearing pad 14 pcs 750000 10500000
4. Diafragma
a. Besi D 13 169.884 kg 11000 1868724
b. besi 10 104.755 kg 11000 1152305
c. beton k300 2.28 m3 2700000 6156000
366884513
5 Plat Jembatan
a.besi D13 1061.178 kg 11000 11672958
b. beton k300 10.07 m3 2700000 27189000
Sub totsl 38861958
Plat Injak
a.Besi D 13 1009 kg 11000 11099000
b.Beton k 200 5.7 m3 2500000 14250000
Sub totsl 25349000
6 Wingwall 0
a. besi 12 351.461 kg 11000 3866071
b.beton k 200 3.744 m3 2500000 9360000
Sub total 13226071
7 Trotoar
a. besi 12 415.096 kg 11000 4566056
b.beton k 200 3.176 m3 2500000 7940000
Sub total 12506056
8 Tiang sandaran
a. besi 12 34.011 kg 11000 374121
b. besi 10 17.76 kg 11000 195360
b.beton k 200 0.157 m3 2500000 392500
f. pipapa galvanis 3 inch 5 btg 1200000 6000000
Sub total 6961981
9 Parapet
a. bata 10000 bj 600 6000000
b.pasir 3 m3 250000 750000
c.semen 30 zak 60000 1800000

Sub total 8550000

Total Rp 485,022,579
Rp 12,125,564.48
Rp 497,148,143

10
Analisa Harga Upah
PEKERJAAN JEMBATAN PERUMAHAN GEDEG
NO PEKERJAAN VOLUME SATUAN HARGA JUMLAH
1 Persiapan
a. Site survey 1 ls 5000000 5000000
b. Sosialisasi 1 ls 5000000 5000000
c. Fasilitas dan alat bantu 1 ls 4500000 4500000
d. Management project 8 mg 5000000 40000000
Sub totsl 54500000
2 Pekerjaan Tanah
a. Setting Out 1 ls 5000000 5000000
b. mob demob 1 ls 10000000 10000000
c. Excavation 228 m3 125000 28500000
d. perapaian 1 ls 1500000 1500000
Sub totsl 45000000
3 Pekerjaan Stros
a. mobdemob 1 ls 1500000 1500000
d. Fabrikasi besi 1876 kg 2000 3752000
f. Uparh bor dan cor 168 m1 140000 23520000
4 Pekerjaan Beton
1. Lean Concret
c. Pasangan batu parapet 3.15 m3 1900000 5985000
d. Begesting dan upah 9.84 m2 250000 2460000
f. Uparh cor 10.368 m3 250000 2592000
2. Abutment
c. bekesting dan upah 147.16 m2 250000 36790000
d. fabrikasi besi 7752 kg 1500 11628000
e. upah cor 80.286 m3 200000 16057200
3. Balok Garder
d.bekesting dan upah 68.635 m2 250000 17158750
f. fabrikasi besi 1091.244 kg 1500 1636866
g.upah cor 10.388 m3 200000 2077600
4. Diafragma
d. Begesting dan upah 31.35 m2 250000 7837500
e. fabrikasi besi 274.639 kg 1500 411958.5
f. upah cor 2.28 m3 200000 456000
5 Plat Jembatan
c. bekesting dan upah 56.27 m2 250000 14067500
d.fabrikasi 1061.178 kg 1500 1591767
e.upah cor 10.07 m3 200000 2014000
6 Plat Injak
c. bekesting dan upah 8.8 m2 250000 2200000
d.Fabrikasi besi 1009 kg 2000 2018000
e.Upah cor 5.7 m3 200000 1140000
7 Wingwall
c.begesting dan upah 39.936 m2 250000 9984000
d.Fabrikasi besi 351.461 kg 2000 702922
e.Upah cor 3.744 m3 200000 748800
8 Trotoar
c.begesting dan upah 27.515 m2 250000 6878750
d.Fabrikasi besi 415.096 kg 2000 830192
e.Upah cor 3.176 m3 200000 635200
9 Tiang sandaran
c.begesting dan upah 0.578 m2 250000 144500
d.Fabrikasi besi 54.771 kg 2000 109542
e.Upah cor 0.157 m3 200000 31400
10 Parapet
d. upah pasang bata 1 ls 3000000 3000000
Sub total 179959447.5
Total 279459447.5
Profit 41918917.125
321378364.625