NO URAIAN PEKERJAAN VOLUME SATUAN UPAH BAHAN UPAH (Rp) BAHAN (Rp) TOTAL HARGA (RP)
1 2 3 4 3 6 7 8 9
I PEKERJAAN PENDAHULUAN/PERSIAPAN
1 Pekerjaan Perataan dan Pembersihan Lahan 1,125.00 m2 1,500 1,687,500 - 1,687,500
2 Air Kerja 1.00 ls 1,000,000 1,000,000 1,000,000 1,000,000 2,000,000
3 Listrik Kerja 1.00 ls 1,000,000 3,500,000 1,000,000 3,500,000 4,500,000
4 Kordinasi/ Keamanan dan Jaga Malam 1.00 ls 20,000,000 - 20,000,000 20,000,000
5 Pengukuran dan Bowplank 140.00 m' 10,000 15,000 1,400,000 2,100,000 3,500,000
6 Pembuatan Gudang Material dan Peralatan 1.00 ls 1,000,000 3,000,000 1,000,000 3,000,000 4,000,000
7 Mobilisasi dan Demobilisasi 1.00 ls 5,000,000 - 5,000,000 5,000,000
Sub Total 6,087,500 34,600,000 40,687,500
B Span / Kuda2
1 Kolom WF 250x125 8,165.00 kg 5,000 23,000 40,825,000 187,795,000 228,620,000
2 Plat Tapak Span t=10mm 1,671.78 kg 5,000 24,000 8,358,900 40,122,720 48,481,620
3 Plat Perkuatan Span t=8mm 448.00 kg 5,000 24,000 2,240,000 10,752,000 12,992,000
4 Baut Mur Span dia 16mm - 2,5" 162.00 bh 5,000 8,500 810,000 1,377,000 2,187,000
5 Cat 191.31 m² 10,170 19,224 1,945,623 3,677,743 5,623,366
Sub Total 54,179,523 243,724,463 297,903,986
C Atap
1 Gording CNP 125x50x20x3,2 5,602.24 kg 5,000 23,000 28,011,200 128,851,520 156,862,720
2 Plat tupai2 t=3mm 33.63 kg 5,000 24,000 168,150 807,120 975,270
3 Baut 3/8Sag Rod RB dia 10mm 840.00 bh 5,000 3,000 4,200,000 2,520,000 6,720,000
4 Zag Rod RB dia 10mm 265.83 kg 5,000 13,500 1,329,150 3,588,705 4,917,855
5 Ikatan Angin dia 12mm 218.39 kg 5,000 13,500 1,091,950 2,948,265 4,040,215
6 Trekstang 40.00 bh 10,000 50,000 400,000 2,000,000 2,400,000
7 Cat 737.43 m² 10,170 19,224 7,499,663 14,176,354 21,676,017
8 Seng Galvalum 0,45 + Aluminium Foil 1,729.08 m² 35,000 100,000 60,517,800 172,908,000 233,425,800
9 Atap Transparan 52.92 m² 35,000 80,000 1,852,200 4,233,600 6,085,800
10 Baut SDS 12-50 1,848.00 bh 1,500 2,000 2,772,000 3,696,000 6,468,000
Sub Total 107,842,113 335,729,564 443,571,677
D Monitor
1 Kolom Monitor
- Double CNP 150x50x20x3,2 338.80 kg 5,000 23,000 1,694,000 7,792,400 9,486,400
- Plat t=10mm 49.46 kg 5,000 24,000 247,300 1,187,040 1,434,340
- Baut Mur Span dia 16mm-2,5" 112.00 bh 5,000 8,500 560,000 952,000 1,512,000
- Cat 34.46 m² 10,170 19,224 350,458 662,459 1,012,917
2 Span Monitor
- Double CNP 150x50x20x3,2 848.54 kg 5,000 23,000 4,242,700 19,516,420 23,759,120
- Plat t=10mm 109.90 kg 5,000 24,000 549,500 2,637,600 3,187,100
- Baut Mur Span dia 16mm-2,5" 196.00 bh 5,000 8,500 980,000 1,666,000 2,646,000
- Cat 120.38 m² 10,170 19,224 1,224,265 2,314,185 3,538,450
3 Atap Monitor
- CNP 125x50x20x3,2 1,251.20 kg 5,000 23,000 6,256,000 28,777,600 35,033,600
- Plat tupai2 t=3mm 98.91 kg 5,000 24,000 494,550 2,373,840 2,868,390
- Baut & Mur 1/2" 448.00 bh 5,000 3,000 2,240,000 1,344,000 3,584,000
- Zag Rod RB dia 13mm-1,5" 110.86 kg 5,000 13,500 554,300 1,496,610 2,050,910
- Cat 363.42 m² 10,170 19,224 3,695,981 6,986,386 10,682,367
- Seng Galvalum 0,45 142.20 m² 35,000 100,000 4,977,000 14,220,000 19,197,000
- Atap Transparan 20.16 m² 35,000 80,000 705,600 1,612,800 2,318,400
- Baut SDS 12-50 924.00 bh 1,500 2,000 1,386,000 1,848,000 3,234,000
- Rabung 33.00 m' 35,000 100,000 1,155,000 3,300,000 4,455,000
- Jerjak Besi Siku + 8mm 40.80 m² 75,000 100,000 3,060,000 4,080,000 7,140,000
Sub Total 34,372,654 102,767,340 137,139,994
V PEKERJAAN DINDING
1 Pasangan Batu Bata 1,245.01 m² 26,194 71,555 32,611,481 89,086,691 121,698,171
2 Plesteran Dinding 2,490.02 m² 26,331 28,282 65,565,339 70,422,746 135,988,085
3 Cor Balok dan Kolom Praktis 2.76 m³ 554,400 3,269,640 1,530,144 9,024,206 10,554,350
4 Pasangan Kaca Block/Roster 78.00 m² 35,000 135,000 2,730,000 10,530,000 13,260,000
5 Cat Dinding 2,490.02 m² 10,170 19,224 25,323,503 47,868,144 73,191,648
Sub Total 127,760,467 226,931,787 354,692,254
X PEMBERSIHAN AKHIR
1 Pembersihan Akhir 1.00 ls 25,000,000 25,000,000 - 25,000,000
Sub Total 25,000,000 - 25,000,000